← Environmental Law Center← Centro de Derecho Ambiental
Res. 19776-2014 Sala Constitucional · Sala Constitucional · 03/12/2014
OutcomeResultado
By majority vote, the Chamber denied the action and left the Puerto Jiménez Partial Regulatory Plan in place, over dissents that would have declared it unconstitutional.La Sala, por mayoría, declaró sin lugar la acción y mantuvo el Plan Regulador Parcial de Puerto Jiménez, con votos salvados que habrían declarado su inconstitucionalidad.
SummaryResumen
The Constitutional Chamber denied the constitutional challenge against the Puerto Jiménez Partial Regulatory Plan and its Zoning Regulation, which were contested for lacking prior environmental assessment, potentially affecting mangroves and other ecosystems, providing insufficient informed public participation, and involving an interested private company in their preparation and financing. The majority did not invalidate the land-use instrument. In a separate concurrence, Justice Castillo Víquez explained that private financing and preparation did not transfer the urban-planning power because approval remained with the Municipality of Golfito, INVU, and ICT; he nevertheless warned that such arrangements require particularly rigorous public oversight. He also reaffirmed that mangroves belong to the public zone and the State’s natural heritage and therefore cannot be granted under concession. Justices Armijo and Cruz dissented and would have granted the action; Cruz additionally objected to allowing private parties with a direct interest to control preparation of the plan.La Sala Constitucional declaró sin lugar la acción promovida contra el Plan Regulador Parcial de Puerto Jiménez y su Reglamento de Zonificación, cuestionados por la falta de valoración ambiental previa, la posible afectación de manglares y otros ecosistemas, la insuficiente participación ciudadana y la intervención de una empresa privada interesada en su elaboración y financiamiento. La mayoría no anuló el instrumento territorial. En nota separada, el magistrado Castillo Víquez explicó que el financiamiento y la preparación privada del proyecto no trasladaron la potestad de planificación urbana, porque la aprobación correspondió a la Municipalidad de Golfito, el INVU y el ICT; advirtió, sin embargo, que estas situaciones exigen una fiscalización pública especialmente rigurosa. También reafirmó que los manglares pertenecen a la zona pública y al patrimonio natural del Estado y no pueden concesionarse. Los magistrados Armijo y Cruz salvaron el voto y habrían acogido la acción; Cruz además cuestionó que particulares con interés directo controlaran la preparación del plan.
Key excerptExtracto clave
Having established the foregoing, the grievance raised by the petitioners lacks constitutional grounds, although it might have a legal or even ethical basis. Therefore, in cases where private parties prepared and financed the proposed Coastal Regulatory Plan that was ultimately approved by public authorities—there are 42 such cases, according to information on the ICT website—those authorities, particularly oversight bodies, must exercise more intensive, continuous, and even ex officio supervision to determine that approval of those plans did not and does not impair the general interest for the benefit of private interests; this practice was fortunately prohibited on the basis of opinions issued by the Office of the Attorney General and the Office of the Comptroller General of the Republic. On a different matter, I consider it essential to reaffirm that mangroves may not be granted under concession, not only because the regulation so provides, but also because, as is well known, they belong to the public zone and the State’s natural heritage under constitutional law—its values, principles, and rules—the international instruments that guarantee and protect humanity’s right to a healthy and ecologically balanced environment, and the legislation in force.Establecido lo anterior, el agravio que plantean los accionantes no tiene sustento constitucional, aunque sí podría tener asidero legal e incluso ético. De ahí que en estos casos, donde son los sujetos privados los que han elaborado y financiado el proyecto del Plan Regulador Costero que finalmente es aprobado por las Administraciones Públicas -hay 42 casos según se informa en la página del ICT-, se requiere que estas, y en especial los órganos de fiscalización, ejerzan un control más intenso y permanente e, incluso, de oficio, con el objeto de establecer que con la aprobación de esos planes no se afectaron (ni se afectan) los intereses generales en aras de beneficiar los intereses privados; práctica que afortunadamente se prohibió, con base en los pronunciamientos de la Procuraduría y Contraloría General de la República. En otro orden de ideas, considero fundamental reafirmar el hecho que los manglares no son susceptibles de ser concesionados, no solo porque el reglamento así lo establece sino porque, como es bien sabido, pertenecen a la ZP y al PNE, conforme al Derecho de la Constitución (valores, principios y normas), los instrumentos internacionales que garantizan y protegen a favor de la humanidad el derecho a un ambiente saludable y ecológicamente equilibrado y la legislación vigente.
Pull quotesCitas destacadas
"La legitimación de los accionantes proviene de la existencia de intereses difusos dada la tutela invocada del derecho a un ambiente sano y ecológicamente equilibrado."
"The petitioners have standing because diffuse interests are involved, given their invocation of the right to a healthy and ecologically balanced environment."
Resultando 2
"La legitimación de los accionantes proviene de la existencia de intereses difusos dada la tutela invocada del derecho a un ambiente sano y ecológicamente equilibrado."
Resultando 2
"Por lo expuesto, salvamos el voto y declaramos con lugar la acción."
"For the reasons stated, we dissent and would grant the action."
Voto salvado de los magistrados Armijo y Cruz
"Por lo expuesto, salvamos el voto y declaramos con lugar la acción."
Voto salvado de los magistrados Armijo y Cruz
"La huida al Derecho privado de estas Administraciones que ejercen funciones públicas soberanas o su ejercicio por parte de particulares es inconstitucional, pues, en este último caso lesiona, una garantía constitucional, así como el principio de la indelegabilidad de las potestades públicas, máxime que, en este caso, se trata de funciones públicas de soberanía."
"The resort to private law by administrations exercising sovereign public functions, or the exercise of those functions by private parties, is unconstitutional because, in the latter case, it violates a constitutional guarantee and the principle that public powers may not be delegated, especially where sovereign public functions are involved."
Nota separada del magistrado Castillo Víquez
"La huida al Derecho privado de estas Administraciones que ejercen funciones públicas soberanas o su ejercicio por parte de particulares es inconstitucional, pues, en este último caso lesiona, una garantía constitucional, así como el principio de la indelegabilidad de las potestades públicas, máxime que, en este caso, se trata de funciones públicas de soberanía."
Nota separada del magistrado Castillo Víquez
"Es realmente muy grave que la definición de un asunto de interés público sea controlado por un particular, situación que compromete el fin público."
"It is extremely serious for the determination of a matter of public interest to be controlled by a private party, as that situation jeopardizes the public purpose."
Nota del magistrado Cruz Castro
"Es realmente muy grave que la definición de un asunto de interés público sea controlado por un particular, situación que compromete el fin público."
Nota del magistrado Cruz Castro
Full documentDocumento completo
Document Review Decision No. 2014-19776 CONSTITUTIONAL CHAMBER OF THE SUPREME COURT OF JUSTICE. San José, at ten thirty a.m. on December 3, 2014.
Action of unconstitutionality filed by Manuel Ramón Ramírez Umaña, identity card 2-335-746, in his capacity as representative of Friends of the Osa S. A.; Bernardo José Aguilar González, identity card 1-566-270, in his capacity as representative of Fundación Geotrópica; Laura Robleto Villalobos, identity card 6-343-627; Héctor González Pacheco, identity card 1-599-966; and Jorge Lobo Segura, identity card 1-526-636; seeking a declaration that the PUERTO JIMÉNEZ LAND-USE PLAN, GOLFITO-PUNTARENAS, is unconstitutional on the grounds that it contravenes Articles 7, 50, 89, and 169 of the Political Constitution, as well as Article 5 of the Convention on Nature Protection and Wildlife Preservation in the Western Hemisphere (Law No. 3763), Article 4 of the Convention Concerning the Protection of the World Cultural and Natural Heritage (Law No. 5980), and Article 4 of the Convention on Wetlands of International Importance (Law No. 7224). The Office of the Attorney General of the Republic also participated in the proceedings.
Findings of Fact:
They request that the action be granted, that the Regulatory Plan (Plan Regulador) in question be declared unconstitutional, and that the Municipalidad de Golfito and the Procuraduría General de la República be ordered, in order to remedy the consequences of the constitutional violations, to initiate judicial review proceedings (procesos contenciosos) to resolve all relevant matters concerning every concession granted, especially the concession granted to Bahía Cocodrilo S. A. for a docking facility (atracadero) and, subsequently, for a marina. They ask for a declaration that there are no vested rights acquired in good faith (derechos adquiridos de buena fe), because such rights are based on clear constitutional violations affecting State property (patrimonio del Estado). In addition, they request a declaration that the Instituto Costarricense de Turismo (ICT), the Instituto Nacional de Vivienda y Urbanismo (INVU), and the Municipalidad de Golfito have committed serious violations of constitutional rules and principles by approving the PRPPJ and the Zoning Regulations (Reglamento de Zonificación) without verifying the environmental variable (variable ambiental).
They also ask that it be declared unconstitutional to use regulations to remove protections for biodiversity and authorize land-use change (cambio de uso del suelo) on land that is State-owned because it consists of forests and wetlands. Finally, they request that the declaration of unconstitutionality (declaratoria de inconstitucionalidad) be made retroactive to the date on which the challenged Decreto was published in La Gaceta. They request that the effects of the plan and the concessions be suspended.
2.- By resolution issued at 10: 18 hours on March 25, 2013, this Court admitted the action for consideration and granted a hearing to the Procuraduría General de la República and the President of the Concejo Municipal de Golfito. The applicants have standing based on the existence of diffuse interests (intereses difusos), given the protection sought for the right to a healthy and ecologically balanced environment (ambiente sano y ecológicamente equilibrado).
Although this was not a conflict of jurisdiction (conflicto de competencias), in judgment number 2008-016975 of 12 de noviembre de 2008, the Sala Constitucional struck down as unconstitutional a decree that empowered municipalities to grant concessions within the State Natural Heritage (patrimonio natural del Estado, PNE) in the maritime-terrestrial zone (zona marítimo-terrestre). Consistent with the preceding cases, the Sala Constitucional held that, because the fundamental right to a healthy and ecologically balanced environment was implicated, the matter was constitutional in nature. This was so even though, in principle, the relationship between the decree and the statutory provisions defining the powers to administer the PNE and its status as public-domain property (bien de dominio público) designated for conservation raised an issue of legality. The present case involves the same conflict of jurisdiction between a municipality and MINAE, although it concerns not a protected wilderness area (área silvestre protegida), but rather that portion of the maritime-terrestrial zone which, because it forms part of the PNE, is administered by MINAE.
Accordingly, this conflict transcends the merely legal sphere and implicates the constitutional principle of proper State protection of the environment established in artículo 50 of the Constitución Política. Therefore, as in the cited precedents, the Puerto Jiménez Partial Regulatory Plan (Plan Regulador Parcial de Puerto Jiménez) must be struck down as unconstitutional in this case. Regarding public participation (participación ciudadana), the Sala Constitucional has repeatedly held that such participation in matters affecting the environment derives from artículo 50 of the Constitución Política itself, read in conjunction with artículo 9, also of the Constitución Política (Sentencia de la Sala Constitucional número 2002-10693 de 7 de noviembre de 2002). Approval of the plan complied with the requirements established for that purpose in artículo 17 of the Ley de Planificación Urbana (LPU) número 4240 de 15 de noviembre de 1968.
Obviously, if no environmental assessment (evaluación ambiental) of the regulatory plan existed when the hearing required by that provision was held, it is almost certain that the environmental variable (variable ambiental) had not been incorporated, at least not under the terms required by the “Manual de Instrumentos Técnicos para el Proceso de Evaluación de Impacto Ambiental”. Similarly, if the plan is not struck down because its regulations incorporated mangroves or for the reason discussed below, this omission may be remedied by issuing a new call for a public hearing to consider the proposal to incorporate the environmental variable. In connection with this issue and in its capacity as the highest technical-legal advisory body of the public administration, this Procuraduría General stated in legal opinion number OJ-95-2005 that, because land-use planning (ordenamiento territorial), whose basic instrument is territorial planning (planificación territorial), constitutes the exercise of a public function, municipalities—and, in this case, the Instituto Costarricense de Turismo and the Instituto Nacional de Vivienda y Urbanismo—could not approve regulatory plans whose preparation had been arranged and financed by private-law entities (sujetos de derecho privado), since doing so would constitute relinquishment of the exercise of a public power conferred by law (artículo 28 de la Ley Orgánica del Ambiente y 15 de la Ley de Planificación Urbana).
Obviously, the foregoing does not prevent municipalities from agreeing with other public entities, such as the Universidad de Costa Rica, to prepare regulatory plans. This remains true even if that entity receives a donation from a private-law entity for such purposes, provided that the donation does not compromise the preparation of the respective regulatory plan. This is what was stated in opinion C-70-2009. It adds that arranging and financing the preparation of a regulatory plan, in addition to being unlawful, is unconstitutional. Besides guaranteeing the right to a healthy and ecologically balanced environment as a fundamental right, artículo 50 of the Constitución Política establishes the State’s duty to safeguard it. This means that the article enshrines the State’s duty to protect and safeguard the environment as a constitutional principle. Municipal entities, as territorially decentralized public administrations, are bound by that principle.
In other words, they are required to protect and safeguard the environment when exercising their powers and jurisdiction. One of these powers is to plan the territory and determine land use (uso del suelo). Because of its implications, this power has significant effects on the environment. Precisely for that reason, an environmental impact assessment (evaluación de impacto ambiental, EIA) is required for one of its principal instruments: regulatory plans. In light of the foregoing, having private-law entities arrange and finance the preparation of coastal regulatory plans entails partially relinquishing the exercise of a public function that affects the environment, as is the case with land-use planning. This, in turn, entails failure to comply with the duty to safeguard and protect the environment that artículo 50 assigns to the State and, generally, to all public authorities. In its capacity as adviser to the Sala, it recommends: 1.
Granting the action if the preparation of the Plan Regulador Parcial de Puerto Jiménez, Golfito-Puntarenas, published in La Gaceta número 65 del jueves 1 de abril de 2004, was arranged and financed by a private-law entity and, consequently, striking it down as unconstitutional. 2. Striking down the Plan Regulador Parcial de Puerto Jiménez, Golfito-Puntarenas, published in La Gaceta número 65 del jueves 1 de abril de 2004, because its zoning regulations (reglamento de zonificación) incorporate part of the patrimonio natural del Estado by including the mangroves of the maritime-terrestrial zone. Should this Sala find the foregoing inappropriate, this Órgano Asesor recommends granting the action if the Plan Regulador Parcial de Puerto Jiménez, Golfito-Puntarenas, published in La Gaceta número 65 del jueves 1 de abril de 2004, was approved without an environmental impact assessment, but without striking down that plan, and ordering the Municipalidad de Golfito to incorporate the environmental variable under the terms established in the “Manual de Instrumentos Técnicos para el Proceso de Evaluación del Impacto Ambiental (Manual de EIA)- Parte III” and artículo 67 of the “Reglamento General sobre los Procedimientos de Evaluación Ambiental (EIA)” and submit it for consideration by SETENA, allowing a reasonable period for that purpose.
Additionally, insofar as the environmental variable was not discussed at the hearing at which the regulatory plan challenged in this action was considered, this Procuraduría is of the opinion that the Sala Constitucional may order the Municipalidad de Golfito to issue a new call for a hearing for that purpose.
7.- By a written submission sent to the Chamber on May 14, 2013, Cory Williams, in his capacity as President of Bahía Cocodrilo S. A., appears as a passive intervenor (coadyuvante pasivo) within the period granted and requests that this constitutional challenge (acción de inconstitucionalidad) be dismissed, explaining the background and counterarguments. Regarding the background, he states that the company holds a concession in the restricted zone (zona restringida) of the coastal sector of Puerto Jiménez, in strict compliance with Law No. 6043 and its Regulations, the special law governing the matter. He asserts that the company also holds a concession over an area in the public zone (zona pública) adjacent thereto, obtained in strict compliance with Law No. 7744, the provisions of which are not challenged in this action. He adds that, within this context, as a party directly interested in the resolution of this action, the company enters an appearance because the rights granted to it by the competent institutions would be revoked if the regulatory plan (Plan Regulador) were annulled, particularly the investment schedule for the Marina Bahía Cocodrilo Project being carried out in the coastal area adjacent to the restricted zone of the maritime-terrestrial zone (zona marítimo terrestre).
He notes that this Chamber has already reviewed and approved its project in the consolidated amparo proceedings (recursos de amparo) Nos. 08-012630-0007-CO and 09-001300-0007-CO, which, by Judgment No. 2012-264, were dismissed after an exhaustive technical and legal analysis of the project and the institutional authorizations and permits granted for that purpose, confirming that it complies with the legislation applicable to the matter. He points out that significant financial investments are currently being made in the approved projects and that, for this reason, the company has undertaken contractual commitments with clients, partners, and financial institutions based on the legal certainty afforded by 14 continuous years of procedures, assessments, and interinstitutional approvals, as this Chamber established in Judgment No. 2012-264. He adds that Bahía Cocodrilo S. A. has operated legally and continuously in the area for 14 years, currently has 95 direct employees and up to 125 during the high season, and generates many additional indirect jobs for tourism entrepreneurs, local farm owners with ecotourism projects, guides, and suppliers in the hospitality sector; consequently, Bahía Cocodrilo S. A. is one of the companies generating the greatest employment and related economic activity in the canton of Golfito.
He argues that the specific grounds of unconstitutionality asserted against the Puerto Jiménez Regulatory Plan should not be resolved through these proceedings, but rather through administrative or judicial proceedings, as appropriate, and notes that the Chamber should take into account that it has already considered and ruled on the approval of the Plan and on public participation in Judgment No. 2012-264. Regarding the applicants’ first argument, he states that the Plan was approved before an environmental impact assessment (Evaluación de Impacto Ambiental) was required, since it was published in La Gaceta No. 65 of April 1, 2004, after the Municipalidad de Golfito approved it at Session No. 8 of February 16, 2004, Chapter Three, Article 10, having previously obtained approval from INVU and ICT and while respecting the boundary demarcation (amojonamiento) of the mangroves and the public zone established by IGN.
He clarifies that the procedure prescribed by Article 17 of the Urban Planning Law (Ley de Planificación Urbana) was followed because, as part of that process, a public hearing (audiencia pública) was held on June 26, 2003, at which the community presented its views and concerns regarding the proposed Regulatory Plan; finally, as stated, it was published in La Gaceta, all in accordance with Laws No. 4240 and No. 6043 and the latter’s Regulations. He contends that, as recorded by the Municipalidad de Golfito in its response to this Chamber, in Decision No. 2002-1220 the Chamber held that an environmental impact study (estudio de impacto ambiental) must be approved before regulatory plans are approved and adopted; however, no specific regulations existed until the promulgation of Executive Decree No. 32967-MINAE, “Manual de EIA-Parte III,” of February 20, 2006, published in La Gaceta No. 85 of May 4, 2006.
He concludes that, because regulatory plans were not required to undergo such a prior study on April 1, 2004, the defect alleged by the applicants does not exist. He asserts that, in close connection and conformity with the foregoing, the Chamber, in Decision No. 2006-11562, found it inadvisable to annul regulatory plans approved before the publication date of the aforementioned Executive Decree No. 32967-MINAE because no specific regulations on the matter existed; as the Municipality states in its report to this Chamber, the provisions of that Decree may not be applied retroactively to the Regulatory Plan at issue. He adds that these regulations likewise cannot be applied to the detriment of acquired rights (derechos adquiridos) and consolidated legal situations (situaciones jurídicas consolidadas), as in the case of Bahía Cocodrilo S. A. in the restricted-zone sector of Puerto Jiménez.
For purposes of approving the Marina Project, the Comisión Interinstitucional de Marinas y Atracaderos Turísticos (CIMAT) ordered, at the relevant time, the preparation of a study entitled “Caracterización para el desarrollo de Marinas y Atracaderos Turísticos de la Costa del Pacífico de Costa Rica,” which is an environmental instrument consistent with the environmental fragility indices (índices de fragilidad ambiental) applied to our coasts and the adjacent land area. He notes that, with regard to those indices, the Municipalidad de Golfito began preparing the Plan Regulador Cantonal de Golfito, in which they have been incorporated for the entire canton and are ready for the corresponding assessment and approval by SETENA. He considers it troubling that, despite having complied with all legal and technical requirements, administrative procedures, and interinstitutional permits, the rights of Bahía Cocodrilo S. A. could be adversely affected by regulations decreed and published after the approval of the challenged Regulatory Plan, placing the company he represents in a state of complete defenselessness (indefensión) and manifest legal uncertainty.
They attach the maps from the study “Caracterización para el desarrollo de Marinas y Atracaderos Turísticos de la Costa del Pacífico de Costa Rica” and official letter CIMAT 146-2013. A list of regulatory plans approved by the competent institutions and a list of regulatory plans approved by SETENA are also submitted, showing that at least 55 coastal regulatory plans and 22 cantonal regulatory plans approved before the environmental impact study was required by the decree of February 20, 2006, remain in force. He states that, under those 77 regulatory plans, the municipalities were not required to approve the assessment in question because the rule was adopted subsequently, and that all of them include use concessions (concesiones de uso) over the restricted zone, projects in the design stage, projects under construction, and tourism developments in operation, the great majority without complaints or reports concerning environmental matters and subject to periodic oversight by the various institutions, including SETENA, which conducts ongoing audits of the technical oversight (regencia) of their construction and operation.
Regarding the applicants’ second argument, concerning the violation of Article 89 of the Constitution, he argues that it is not true that the PRPPJ permits the granting of use concessions in the public zone, mangroves, or wetlands, since those areas are expressly excluded from the area available for concession. He contends that it is likewise untrue that concessions may be granted in areas of “high environmental fragility.” He clarifies that, to the contrary, the zoning map (plano de zonificación) and the Plan Regulations expressly establish that all mangroves are protected. He states that the applicants made a reckless assertion without submitting evidence, claiming that concessions would be granted in mangroves because the Plan had not been submitted to SETENA for approval. He explains that Article 5 of the Plan Regulations states the opposite and therefore disputes the claim that the Municipality violated the principle of objective substantiation (principio de objetivación) and the precautionary principle (principio precautorio), because as of April 1, 2004, neither the Regulations nor case law required SETENA to approve an environmental impact study for any regulatory plan, given that Decree No. 32967-MINAE was not published until 2006.
He maintains that, in the case of this Plan, the technical studies demonstrated that all mangroves and other fragile areas had to be protected, and they were, as shown on the zoning map, which prohibits the granting of concessions in those areas. He adds that, for this reason, the resulting environmental protection is equivalent to that which an environmental impact study would provide. He asserts that mangroves fall within the jurisdiction of MINAE and were excluded from the restricted zone, thereby remaining protected areas (áreas protegidas) pursuant to Articles 73 and 73 bis of Law No. 6043. He adds that, pursuant to Article 13 of Ley Forestal No. 7575 of February 13, 1996, mangroves are a type of forest forming part of the State’s natural heritage (patrimonio natural del Estado), administered by MINAE. He argues that, in accordance with these rules and because the administration of mangroves falls within the jurisdiction of MINAE, Article 5 of the Regulatory Plan Regulations establishes an absolute protection zone (zona de protección absoluta) for mangroves, estuaries, streams, and rivers; that “trails must be designed in accordance with the standards and requirements established by MINAE”; and that “no concessions shall be granted in this zone.” He concludes that this clearly established MINAE’s jurisdiction and a strong protection regime for mangroves and other fragile areas.
He notes that the environmental fragility indices are being prepared. He transcribes the Municipality’s statements in this regard from its report to this Chamber concerning the agreement with ProDUS. He reiterates that the Regulatory Plan protects every mangrove area. He states that, in accordance with Opinion C-100-95 of the Procuraduría General de la República dated May 10, 1995, which defines coastal regulatory plans, the Plan constitutes a legal and technical instrument comprising two components: a graphic component and a written component, and that the Municipalidad de Golfito took the existence of environmental variables into account. He adds that, for this reason, annulment of the Regulatory Plan would adversely affect not only the landscape but also the various ecosystems already protected in the absence of regulation, causing legal uncertainty, the loss of jobs associated with projects currently in operation, and a reduction in municipal revenue from fees and taxes, among other consequences.
He contends that the Chamber so stated in Judgment No. 2006-11562. He emphasizes that, in its report to this Chamber, the Municipality stated that the Regulatory Plan Regulations under review were approved by all competent institutions, were duly published and submitted to a public hearing, and followed the procedures for publication of the notice, responses to objections, and consultations. Accordingly, those institutions assessed the Plan in light of environmental protection, including the protection of natural beauty, as established in section 1.1, entitled “Development Criteria,” and section 1.2, entitled “Land Uses.” He adds that, likewise, Article 1, entitled “Objectives of the Regulations,” sets forth the measures necessary to comply with Law No. 6043, protect and conserve the area’s natural resources, control infrastructure development in the maritime-terrestrial zone, and foster a pleasant tourism environment for visitors.
It confirms that the general provisions of the Regulations establish 29,58% as an absolute protection area (área de protección absoluta) for mangroves, estuaries, streams, and rivers. It clarifies that this area does not include the area of the mangrove, estuary, stream, or river being protected and, consequently, considers that the petitioners’ argument lacks merit because all environmentally fragile areas (áreas frágiles) were protected. It notes that the petitioners never filed timely objections to the aforementioned Plan, in accordance with the procedure established for that purpose in the Urban Planning Law (Ley de Planificación Urbana), nor did they do so afterward. They transcribe provisions of the Regulations intended to preserve natural scenic beauty, such as compliance with the boundary monumentation (amojonamiento) representing the special protection zone established by IGN: Article 3, General Provisions; Article 4, Public Zone; Article 5, Protection Zone (Z PRO).
It states that subsection 1.4, entitled Roadway Regulations (Reglamento de Vialidad), sets forth the restrictions limiting the road network. It asserts that, for construction, the interested party must submit a development project for concession areas (áreas en concesión) within no more than 10 months after ICT approves the application. It concludes that the foregoing demonstrates that environmental protection was duly assessed and applied in accordance with the criteria of the institutions (INVU, ICT, MINAET) and the legislation in force when this Regulatory Plan (Plan Regulador) was evaluated and approved. It reiterates that annulment of the Plan would have highly detrimental effects, including damage to the various ecosystems due to the lack of regulation, serious legal uncertainty, loss of employment from projects currently in operation, and reduced revenue from fees and taxes, as stated by Municipalidad de Carrillo in its response to this Chamber.
Regarding the petitioners’ third argument concerning the mangrove protection zone (zona de protección), it adds that, as may be seen in the attached PRPPJ General Plan (Plano de Conjunto), the mangroves near the Plan are excluded and delimited, and the demarcation is consistent with the boundary markers (mojones) currently in place (evidence 8 and 9). It states that the only area of Puerto Jiménez where the mangroves are duly protected is precisely the sector covered by the aforementioned Plan. It adds that, because mangroves are classified as ZP, they are duly demarcated with boundary markers and are therefore protected and administered by MINAE. The mangroves are also excluded from land subject to the private-property regime because the boundary markers establish where private property ends and the mangrove begins. It maintains that the foregoing is confirmed and ratified by the coastal regulatory plans approved by the competent institutions (ICT, INVU, and the Municipality of the respective jurisdiction) that present circumstances similar to the case under review.
These are the respective regulatory plans for Playa Esterillos (Puntarenas, 1993), Playa Coyotera (Guanacaste, 1995), Playa Puerto Soley (Guanacaste, 1993), and Playa Zapotal (Guanacaste, 1999). It notes that the PRPPJ protects this inalienable area not subject to acquisitive prescription (zona inalienable e imprescriptible) and that, in contrast, illegal construction exists in the adjacent coastal sectors where there is no coastal planning whatsoever, due to the absence of land-use planning (ordenamiento territorial) (evidence 9). It states that all activities and development are prohibited within the Plan’s area of application and that there is an absolute protection zone and the corresponding adjacent restricted zone (zona restringida), which is not the case under the remainder of the planning regime. It contends that the protection zone (Z PRO) does not include the mangroves, as the Office of the Attorney General (Procuraduría) erroneously stated in its report, since that zone begins at the boundary of the mangrove demarcated by IGN with boundary markers.
Thus, far from being unprotected, as the petitioners erroneously argue, the mangroves, estuaries, and streams are duly safeguarded by the aforementioned Plan. It asserts that the adjacent protection zone represents 41% of the restricted zone currently under concession to Bahía Cocodrilo S. A., demonstrating that the percentage of protection approved by ICT, INVU, and Municipalidad de Golfito is very high. Regarding the petitioners’ fourth argument, it states that the Municipality, INVU, and ICT—not a private company—approved the Regulatory Plan. It explains that the first version of the PRPPJ was donated by our company, Bahía Cocodrilo S. A., but final approval by Municipalidad de Golfito is a public power that cannot be supplanted. It explains that the Plan was approved by the Municipality, INVU, and ICT, was submitted for public consultation (consulta pública), and was approved by the Council at its session of 19 de enero de 2004.
It emphasizes that the nonbinding legal opinion OJ-96-2005 issued by Procuraduría General de la República came later. With respect to that legal opinion, it notes that it was issued on 14 de julio de 2005, that is, one year and five months after the Plan was published in La Gaceta No. 65 del 1 de abril de 2005. It states that, for this reason, OJ-96-2005 likewise cannot be applied retroactively against the PRPPJ; in any event, that opinion was not binding on Municipalidad de Golfito because it was addressed to a legislator. It contends that, pursuant to Article 3 of its Organic Law (Ley Orgánica), the opinions issued by the Procuraduría are not binding on legislators because legislators are not part of the Public Administration. It states that only public acts are binding for the adoption of a regulatory plan and that the respective authority of INVU and ICT to approve coastal regulatory plans derives from Ley de Zona Marítimo Terrestre No. 6043.
It adds that the concept of jurisdiction (competencia), as the legal authority to act, is defined by Article 59 of the General Law of Public Administration (Ley General de la Administración Pública). It maintains that donating preliminary studies for a regulatory plan to a municipality is entirely legal and ethical. They provide a list of 42 coastal regulatory plans in which the donor of the studies is a private party, as recorded on ICT’s official website. It argues that this demonstrates the regularity and normality with which the institutions have accepted this method of financing. Regarding the fifth argument advanced by the petitioners, it asserts that informed public participation (participación ciudadana informada) did take place before municipal approval. It states that the Chamber has already ruled on this matter, specifically in recital VI (considerando VI) of judgment 264-2012, issued in expediente 08-012630-007-CO, where it held that no violation of any fundamental right existed.
Municipalidad de Golfito published the Regulatory Plan in La Gaceta, giving the public an opportunity to appear in and participate in the approval process: there was a public notice, a hearing, publication, and consideration of objections and comments, as established in Ley No. 6043 and its Regulations, in conjunction with the Urban Planning Law. It adds that the petitioners never filed any objection to the aforementioned Plan, as provided for by that law. It concludes that such participation complied with the regulations in force at that time; accordingly, it was not possible for the environmental variable (variable ambiental) invoked by the petitioners to have been disclosed to citizens in advance, since it was not legally mandatory when the Plan was approved in 2004. It requests that the constitutional challenge (acción de inconstitucionalidad) be dismissed.
Subsequently, the Procuraduría, in opinion C-093-2007, stated that coastal regulatory plans (planes reguladores costeros) are the appropriate planning mechanism for the maritime-terrestrial zone (zona marítimo terrestre) administered by the Municipalities and therefore may not include mangrove areas for the granting of concessions, because those areas belong to the State’s natural heritage (patrimonio natural del Estado), which must be administered by MINAE. It also stated that this instrument must incorporate the environmental variable (variable ambiental) and that adoption of the regulatory plan (plan regulador) falls to the Municipality, since approval by ICT and INVU is equivalent to an endorsement in the plan-drafting process, through which those institutes oversee and verify that the plan conforms to the broader planning they undertake. Constitutional judgment No.1993-6706 of 15:21 hours on 21 de diciembre de 1993 ruled to the same effect.
The Reglamento de la Ley de Zona Marítimo Terrestre, Decreto Ejecutivo No. 7841-P, expressly refers to coastal regulatory plans as local land-use planning instruments (instrumentos de planificación territorial). According to Article 17 of that regulation, regulatory plans covering that zone must conform to the guidelines and recommendations contained in the general land-use plan (plan general de uso de tierra). In addition, ICT and the MIDEPLAN Planning Office must prepare a general land-use plan for that zone. Article 38 makes the granting of concessions contingent upon the preparation and approval of a regulatory plan where the maritime-terrestrial zone has been declared to be of tourism interest. According to the opinion of the Procuraduría OJ-096-2005, although Articles 3 and 35 of the Ley de Zona Marítimo Terrestre assign administration of that zone to the municipalities, Article 26 of that same Law grants ICT the authority to plan land use in that zone and states that it is competent to prepare and approve regulatory plans and issue guidelines for their preparation; however, ICT is not competent to adopt coastal regulatory plans, because that is the responsibility of the municipalities.
It states that this makes clear that local land-use planning within the maritime-terrestrial zone is a public power established by law and a responsibility of the municipalities. Public powers may not be delegated, and municipalities have the jurisdiction and authority to plan and control urban development within the boundaries of their respective jurisdictions through the adoption and implementation of regulatory plans. For the purpose of preparing regulatory plans, local governments may enter into private contracts concerning specific matters, such as technical matters, to support assessment criteria and decision-making, since these are support tools for achieving public and collective purposes. If the plans are prepared by INVU or ICT, they must be submitted to the municipality for adoption. Broadly speaking, the authority to prepare, approve, and adopt those plans belongs to the municipalities, while INVU and ICT possess residual and exceptional authority to prepare and approve plans.
Por tanto, the preparation of regulatory plans is a nondelegable public power vested in the Municipalities. Other public entities assist the municipalities in that work. ICT has the authority to plan land use in the maritime-terrestrial zone and is competent to prepare and approve regulatory plans, issuing guidelines for that task. The municipality is the primary authority with standing (legitimación) to submit regulatory-plan projects to SETENA, together with environmental fragility indices (índices de fragilidad ambientales) and an environmental analysis (análisis ambiental) or another methodology. Exceptionally, ICT or INVU may prepare them. Plans approved in violation of the public powers held by the competent authorities are affected by defects rendering them null and void (vicios de nulidad), and the official who authorizes or orders the implementation of those acts also incurs liability; accordingly, private parties do not have standing to submit or prepare the environmental impact assessment (evaluación de impacto ambiental) of regulatory plans before SETENA, unless they are acting as consultants to the authority preparing a regulatory plan.
18.- By means of a brief submitted to the Chamber at 16:24 hours on 20 de septiembre de 2013, Isidro Santos Palacios, in his capacity as President of the Concejo de Golfito, responded to the hearing granted. He states that the requirement for an environmental assessment (valoración ambiental) in coastal regulatory plans (planes reguladores costeros) originated with the promulgation of Decreto Ejecutivo 32967-MINAE, of febrero de 2006, which was published and entered into force after the studies supporting the preparation, evaluation, and approval of the Plan in question by public institutions (IFAM, ICT, INVU, IGN) and others with jurisdiction over the matter, in accordance with the laws and regulations in force at that time. He reiterates that said Plan was approved by the Municipalidad de Golfito in Session No. 8 of 16 de febrero del 2004 and published in the Diario Oficial La Gaceta No. 65 of 1 de abril de 2004.
This means that said plan was approved on the basis of the demarcation of the public-zone sector (zona pública) of the coastal area in question, carried out by the Instituto Geográfico Nacional, and the declaration of Tourist Suitability (Aptitud Turística) issued by ICT through an agreement adopted at ordinary session of the Junta Directiva No. 4902, article 5, subsection VII, of 8 de marzo de 1999, in strict compliance with the provisions established for that purpose in Ley No. 6043 and its Regulations. Consequently, ICT, INVU, and the Municipalidad de Golfito exercised the regulatory authority (potestad reglamentaria) established by Ley No. 6043 and its Regulations in close relation and conformity with the Ley de Planificación Urbana; they also issued the corresponding notice of public hearing and subsequently published it in the Diario Oficial La Gaceta. Regarding the names of the companies or private parties that conducted and financed those studies, he clarified that the following consulting companies, among others, participated in preparing the studies for the PRPPJ: Ingeniera Civil ICSA S. A., Grupo PLERUS S. A., and ISUMA Ingenieros y Geólogos Consultores, with Bahía Cocodrilo S. A. acting as the developer.
This was fully known and accepted by INVU and ICT, as recorded in official letter No. CZM 333-99 of 24 de agosto de 1999 from the Comisión de Zona Marítimo Terrestre del ICT; official letter No. PU-C-PT-190-2001 of 20 de diciembre de 2001 from INVU; and official letter No. PU-C-D-011-2003 of 8 de enero de 2003 from INVU. He states that the case record contains 42 coastal-zoning maps approved by the competent public entities, each of which clearly specifies that the regulatory plans were promoted and financed by private entities, demonstrating that, before the cited 2006 regulations, there was no legal restriction in this regard. As to the question of whether Bahía Cocodrilo S. A. or associated third parties participated in any way in financing or conducting the studies that resulted in the aforementioned Regulatory Plan, he states that the position expressed by the Procuraduría General de la República in legal opinion 096-2005, which concerns the nonapproval of coastal regulatory plans whose preparation was arranged, contracted, and financed by private-law entities, is not binding and, moreover, was issued after the PRPPJ had been approved by the Municipalidad del Golfito, since that approval occurred on 16 de febrero de 2004 and its publication in La Gaceta took place on 1 de abril de 2004.
He indicates that although some of the studies that ultimately made up the Coastal Regulatory Plan were funded by private parties, its final interinstitutional approval resulted from the exercise of public authority in full compliance with the rigor of the law governing the matter. In other words, the oversight and approval powers granted to the State and its institutions in land-use regulation and territorial planning (ordenamiento y planificación territorial) were exercised, in this specific case, in accordance with the law—that is, in accordance with what was legally in force and effective at that time. He notes that it should be borne in mind that the corresponding studies were brought to the attention of, and subjected to the relevant technical assessments by, the competent public entities, as provided by Ley No. 6043 and the Ley de Planificación Urbana. He clarifies that in 2006 the Municipalidad de Golfito took the initiative to include environmental fragility indices (índices de fragilidad ambientales) in the preparation of the Plan Regulador Cantonal de Golfito for the entire canton, and that these indices are ready for the corresponding evaluation and approval by SETENA.
These indices were prepared for the entire canton of Golfito with the intention of applying them to cantonal and coastal regulatory plans; however, this process was interrupted by a lack of resources. In other words, the studies were completed and are currently pending final approval by SETENA, as stated in the response of 30 de abril de 2013.
Classification Area (Ha) Mangrove 1.76 Wetland 0.91 Lagoon 0.58 Forest 1.64 Lagoon Protection Zone 1.50 Estuary Protection Zone 0.10 Total 6,49 Report SINAC-ACOSA-PNE-AD-079-2013, prepared by Eng. Joel García Medina of the Programa de Patrimonio Nacional del Estado, indicates that “within the PRPPJ of the Canton of Golfito, the area designated for private use conflicts with wetland areas identified in the certification, specifically polygons H3, measuring 0,22 has, and H4, measuring 0,48 has. A proposed gravel road within the regulatory plan crosses two mangrove areas (public zone), polygons H1 and H2. A proposed pedestrian walkway affects wetland polygon H5.” She concludes that, according to the classification of the State’s natural heritage within the PRPPJ of the canton of Golfito, certain uses conflict with certification D-0183 of 20 de junio del 2007; these areas are not subject to municipal concession (concesión municipal) pursuant to article 73 of Ley N° 6043.
She states that this Área has not issued any use permit (permiso de uso) authorizing the activities under article 18 of the Ley Forestal. She requests that the Municipalidad de Golfito be asked whether it has made the amendments to the Regulatory Plan needed to conform it to the certification of the State’s natural heritage and, if it has not made the amendments to the regulatory plan at issue, that it be ordered to make the necessary adjustments to exclude from the planning process those areas classified as part of the State’s natural heritage. The reporting official submits as evidence official letter SINAC-ACOSA-PNE-AD-079-2013, which states, in relevant part [this Chamber will use abbreviations even though they do not appear in the original text]:
“According to the desktop study (estudio de gabinete), it can be determined that, within the area designated for private use in the PRPPJ of the Canton of Golfito (private property), there is a conflict with wetland areas identified in the certification; specifically, wetlands H3, measuring 22 hectares, and H4, measuring 0,48 hectares, are located within the area designated for private uses. Furthermore, it is observed that a gravel road in the regulatory plan crosses two mangrove areas, H1 and H2, and that a pedestrian walkway affects wetland H5, according to the regulatory-plan proposal. In conclusion, the PRPPJ, as shown on the sheet maintained in the digital files, contains land uses (usos de suelo) that conflict with certification D-0183, issued in the Ciudad de Golfito on veinte días del mes de junio del año dos mil siete, in compliance with LF N° 7575 and Dictamen C-297-2004 of the Procuraduría General de la República.” She also submits report No. ACOSA-GMRN-071 with certification of the State’s natural heritage ACOSA-D-0183 of 20 de junio de 2007, which states:
“3. Identification of Natural Forest Areas. Field verification was conducted in the areas proposed as Z PRO, which were identified as natural forest areas undergoing natural regeneration (regeneración natural), covering 1.64 hectares. Based on observations, certain species predominate, such as (…). Intermediate canopies were observed, and some areas are classified as brushlands and secondary-growth thickets (charrales y tacotales), which serve as buffer areas (áreas de amortiguamiento), both for the forest area and to encourage secondary development alongside the natural regeneration prevailing at the site. Much of this vegetation is associated with the mangrove and wetlands, such as the lagoon found at the site; these are therefore intrinsically related plant associations. These ecosystems are associated because they not only form part of a buffer vegetation cover (cobertura vegetativa de amortiguamiento), but are also linked to the site’s water regime (régimen hídrico) and to the soil composition in that sector.
Accordingly, the protection and preservation of this remnant vegetation (remanencia de vegetación) is extremely important for the site’s wetlands and mangroves. Sampling was unnecessary because these areas are clearly defined at the site and properly demarcated under the proposed Regulatory Plan (Plan regulador). 4. Location of Mangrove Areas. This type of ecosystem is fully delineated on the map proposed in the Regulatory Plan, which shows that the predominant species are principally Rhizophora mangle and Avicennia, influenced by tidal salinity. It has been altered and affected by urban growth in the area. A wetland was identified at the site that is not classified as a mangrove, but rather as a coastal lagoon-type wetland (humedal tipo laguna costera) associated with the mangrove. It is a freshwater site, although it is affected by incoming tides, and it represents an important wildlife habitat for species such as great egrets, crocodiles, waterbirds, and populations of crabs and other mollusks from the area.
It is therefore recommended that it be classified as a coastal lagoon, and it contains water throughout the year. Based on the geographic information system analysis, we determined that this lagoon covers an area of 0.58 hectares and that its protection area (área de protección) must likewise be zoned as prescribed by Article 33 of Ley Forestal No. 7575, with a horizontal radius of 50 meters, resulting in a protection area of 1.50 hectares. This area includes the protection areas contained in the proposed zoning, as shown in Figure No. 3 of the report. 5. Location of Wetland Areas. At this location, we found two wetland areas associated with the mangrove that are not zoned at the site. A GPS survey was therefore conducted to locate and delineate them, and an area of 0.91 hectares was recorded. This also includes areas they had classified as Z PRO where a wetland actually exists. These are wetlands that hold water during the rainy season and are covered by a vascular plant of the sedge family.
Waterbirds such as black-bellied whistling ducks and herons were also observed at the site. There are likewise many crab burrows, possibly belonging to the species Uca spp. The site consists of sandy, peaty soil (suelo arenoso y turberoso). 6. Delineation of the Z PRO. Because the site contains two water-related wetlands (humedales hídricos), including the Estero Pueblo Viejo, which is identified in the Regulatory Plan zoning with its corresponding 15-meter Z PRO, while the coastal lagoon, although zoned as a mangrove area, does not have its corresponding protection zone (zona de protección), the latter was calculated using the Geographic Information System with a radius of 50 meters. The two protection zones together cover an area of 1.60 hectares, entirely within the ZR area of the ZMT.
7. Other Field Data. One of the limitations of this Regulatory Plan is its delineation of the ZR, namely the 150-meter strip. Under the submitted proposal, this delineation is incorrect because it is drawn based on the boundary markers (mojones) for the 50-meter ZP, without taking into account the markers for the mangrove areas. Article 11 of law 6043 states as follows: “ZP also includes, regardless of its extent, the area occupied by all mangroves along the mainland or island coastlines and estuaries of the national territory.” The proper delineation must therefore also be made from the markers delimiting the mangrove. Accordingly, the restricted area (área restringida), as delineated using GPS data and the information-system analysis, is larger and can be seen in Figure # 4. It covers an area of 23.55 hectares and encompasses nearly the entire PRPPJ area, a situation that must be corrected.
Several buildings were identified within the public zone (zona pública), three of them at the Parrot Bay hotel between markers 921-922-923. A house was also observed and located at marker 941; it stands within the public zone, is registered to Brisa de la Bahía S A, and is occupied by Mr. Carlos Luis Villegas García. 8. PNE Zoning. Based on the field inspection, GPS survey, and analysis using the geographic information system, we were able to delineate wetlands, forests, and protection zones in accordance with the methodology recommended by Resolution SINAC-013-2006. This established 6 types of wetland categories, 3 areas with forest cover (coberturas boscosas), and 4 areas subject to the protection regime (régimen de protección) for a lagoon and estuary. In total, there are 4.89 hectares classified as PNE within the ZMT in the PRPPJ; their boundaries, classification data, and land-cover data can be seen in Figure No. 3 and Table 1 of this study.
The protection areas of the coastal lagoon and part of the estuary, covering an area of 1.60 hectares, were also zoned (sic). These zones must remain under this regime even though they are not administered by MINAE, and they must be respected as prescribed by Articles 33 and 34 of ley forestal 7575. No class VII or VIII forest-suitability areas (áreas de aptitud forestal) were identified in the PRPPJ. (…). Conclusions. Based on the results obtained, we have reached the following conclusions: 1. The PNE area identified and quantified in the PRPPJ covers 4.89 hectares and consists of forest, wetland, lagoon, and mangrove areas, pursuant to Resolution R-SINAC-013-2006. 2. The protection areas that are not classified as PNE but must be included in the Regulatory Plan’s land-use zoning (zonificación de uso) cover an area of 1.60 hectares. 3. There is a problem with the delineation of the ZR in the PRPPJ; this area, which forms part of the ZMT, must therefore be corrected. 4.
Several buildings were identified within the public zone, three of them at the Panot Bay hotel between markers 921-922-923. A house was also observed and located at marker 941; it stands within the public zone, is registered to Brisa de la Bahía S.A., and is occupied by Mr. Carlos Luís Villegas García. (…) It is hereby certified: That the attached maps, tables, and digital files, duly identified, correspond to the classification of PNE lands within the ZMT in accordance with the PRPPJ-Golfito Proposal. That, pursuant to the report, the following is recommended: First. Issue the corresponding certification to Municipalidad de Osa and ICT stating that within the PRPPJ there are 1.76 hectares of mangrove areas; that there are also 0.91 hectares consisting solely of wetland areas; that 0.58 hectares constitute a coastal lagoon; and that 1.64 hectares of natural and secondary forest (bosque natural y secundario) areas were identified as prescribed by Article 3 of LF No. 7575; that all these areas form part of the PNE; and that they are duly identified, georeferenced (georeferenciadas), and quantified in the following table (…) Second. We likewise certify that no class VII or VIII forest-suitability areas were identified in the Puerto Jiménez Regulatory Plan.”
24.- By written submission forwarded to the Secretariat of this Chamber at 13:16 on 22 November 2013, Cory Braun Williams, in his capacity as President of Bahía Cocodrilo S. A., vested with the powers of a general attorney-in-fact without limitation as to amount (apoderado generalísimo sin límite de suma), addresses the evidence requested by the Court on its own motion (prueba para mejor resolver) from the Municipalidad de Golfito and asserts that the coastal planning at issue was confined and limited to the restricted zone (zona restringida) of the sector under examination. He adds that it did not encompass or include adjacent and/or adjoining private property for assessment, zoning, regulation, and integration into the coastal regulatory plan (plan regulador costero), as shown by the approved zoning map and the corresponding regulations. He explains that the owners of the adjacent and/or adjoining private properties never gave any express consent to include their land in that coastal planning.
He states that the public zone (zona pública) and the restricted zone have been duly demarcated by IGN, the sole competent public entity established by express legal mandate to perform that technical work; furthermore, that official agency also proceeded to delimit and place boundary markers (amojonamiento) for the mangroves and other relevant areas located in the restricted zone of the planned coastal area. He maintains that this assertion has been confirmed and ratified by the respective institutions, as demonstrated by the extensive evidence submitted by the party he represents, including INVU official letter No. PU-C-PT-132-2003 of 6 October 2003, which states: “5. The Partial Regulatory Plan clearly establishes the Public Zone and the Restricted Zone (officially demarcated by the IGN boundary markers) (…) 7. The Public Zone and Restricted Zone are duly demarcated by the boundary markers of the Instituto Geográfico Nacional, as certified by the only Institute competent to do so.” He understands that the foregoing is demonstrated both in the graphic component of the PRPPJ and in the INVU official letters submitted for that purpose, as well as in the survey report concerning the areas of the State’s natural heritage (patrimonio natural del Estado) at issue here.
He asserts that, from that point onward, the Catastro Nacional likewise proceeded to register the corresponding cadastral plans for the area comprising the restricted zone, while the Municipalidad de Golfito granted the respective use concessions (concesiones de uso), in strict compliance with the PRPPJ, as well as Ley No. 6043 and its Regulations. He adds that the areas within the restricted zone that are demarcated as part of the State’s natural heritage are likewise not subject to concession, pursuant to Article 73 of Ley 6043, and therefore considers that the coastal planning under review contains no inconsistency whatsoever concerning this matter. Official letter No. ACOSA D-276-2013 of 17 September 2013 certifies that the areas of the State’s natural heritage within the PRPPJ, described in that official letter, are not subject to municipal concession. He notes that official letter No. ACOSA-GMRM-071 of 18 June 2006 states that the existing mangrove areas are “duly demarcated on the map proposed in the regulatory plan,” and that report also states that the zones within the PRPPJ are duly identified “…in the zoning of the regulatory plan (…) all within the Restricted Zone of the Maritime-Terrestrial Zone (Zona Marítimo Terrestre).” He argues that the demarcation of the Maritime-Terrestrial Zone respects and takes into account the boundary at which the inviolable private-property regime begins, pursuant to Article 45 of the Constitution.
He emphasizes that the Municipalidad correctly responded that within the PRPPJ there are no private-use areas that conflict with mangrove and/or wetland areas. He states that the privately owned area adjoining the restricted-zone sector of the coastal area does not form part of the PRPPJ. He notes that this Chamber has held that there must be an appropriate balance and equilibrium between the two regimes. Regarding polygon H3 of 0.22 hectares and polygon H4 of 0.48 hectares, he attaches a figure and states the following: Polygons H3 and H4 are wetlands (humedales) (as correctly defined by the ACOSA assessing official in the report at issue) located within adjoining private property that, as the Municipalidad indicated in its response to this Chamber dated 8 November 2013, does not form part of the PRPPJ. Polygons H3 and H4 are not mangroves and were not classified as such either in the 2007 PNE report, in the report signed by Eng.
Joel García Medina on 22 October 2013, or in the response of M.Sc. Etilma Morales Mora dated 23 October 2013. Because polygons H3 and H4 are not mangroves, IGN did not place boundary markers around them. He adds that the area of the State’s natural heritage contained within the PRPPJ is correctly demarcated and does not form part of the restricted zone; it is therefore not eligible for concession. He considers that, on page 11, the PNE report defines polygons H3 and H4 as “wetlands in a public-zone area,” which are protected by Articles 41, 42, and 45 of Ley No. 7554, which define wetlands broadly and do not strictly associate them with proximity to the sea. He argues that, accordingly, as shown in the attached figure, “one of these wetlands extends more than one kilometer inland from the point where the ACOSA official identifies it in his report, across other private properties, without that wetland having been assessed in its entirety” (sic).
He understands that it is clear in this case that there is a system of wetlands converging in the mangroves of the Puerto Jiménez area, as occurs along our coastlines. He adds that if these systems are located within the restricted zone of the Maritime-Terrestrial Zone, they must be demarcated by IGN and protected by the competent institutions, as occurs in the case of the PRPPJ. He states that if these wetland systems are located within adjoining privately owned land, they must likewise be respected and protected in accordance with the applicable provisions of Ley No. 7554 cited above. Regarding polygons H1 and H2, which are reportedly crossed by a proposed gravel road and a pedestrian pathway that, according to the Report, affects the wetland located in polygon H5, he maintains that the cited gravel routes provide access to the beach and existed before the assessment and approval of the PRPPJ, as demonstrated by official letter No. PU-C-D 106-2002 of 16 December 2002, which mentions and accepts their existence.
He adds that, insofar as the pedestrian trail might affect Wetland H5, that trail complies with the provisions of the aforementioned Articles of Ley No. 7554, specifically Article 45, read in conjunction with the provisions of Decreto Ejecutivo 35868-MINAET concerning wetland protection, because the wetlands are duly demarcated in the PRPPJ and cannot be granted under concession. He states that, to illustrate the foregoing, he attaches a total of 14 zoning plans obtained from the official ICT website, corresponding to regulatory plans currently in force, in which the relationship among neighboring private properties, restricted areas, mangroves, and existing wetlands is similar to the characteristics of the PRPPJ. He concludes that all these matters concern ordinary legality and do not form part of the constitutional challenge (acción de inconstitucionalidad); accordingly, they should not be heard or considered in constitutional proceedings.
Regarding the principal issue presented in this action, he indicates that it must be borne in mind that the PRPPJ (public zone and restricted zone) was prepared, approved by the competent institutions, and published in La Gaceta on a date (16 February 2004) preceding the nonbinding opinion of the Procuraduría General de la República (OJ-095-2005 of 14 July 2005). Therefore, the principle of non-retroactivity of the law (principio de no retroactividad de la ley) established in Article 34 of the Constitution is applicable by virtue of the vested rights (derechos adquiridos) and settled legal situations (situaciones jurídicas consolidadas) arising from the State’s approval of that coastal planning. He reiterates that this was stated both by ICT in official letter No. AL-1716-2013 and by INVU in official letter No. C-PU-D-716-2013, which he submits as evidence requested by the Court on its own motion.
25.- By order issued at 14:02 on 24 October 2014, the parties were summoned to the hearing scheduled for 6 November 2014.
26.- The notices (edictos) referred to in the second paragraph of Article 81 of the LJC were published in Nos. 075, 076, and 077 of the Boletín Judicial on 19, 22, and 23 April 2013 (available in the Sistema de Gestión de Despachos Judiciales).
28.- By written submission dated 5 November 2014, the representative of Bahía Cocodrilo S.A. requested audiovisual support materials for the hearing of 6 November 2014.
32.- By written submission forwarded to the Chamber on 11 November 2014, the claimant Héctor González Pacheco likewise submits his conclusions from the hearing of 6 November 2014. He reiterates his arguments concerning the unconstitutionality of the challenged Plan Regulador and submits biologist Javier Baltodano’s report on the Plan Regulador.
34.- On 24 November 2014, Cory Braun Williams, in his capacity as President and legal representative of Bahía Cocodrilo S.R.L., a passive intervenor (coadyuvante pasivo) in these proceedings, appears to respond to the claimants’ conclusions.
35.- The statutory requirements have been complied with in these proceedings.
Justice Rueda Leal, drafting; and,
Whereas:
I.On the Formal Admissibility Requirements for the Action. An action of unconstitutionality (acción de inconstitucionalidad) is a proceeding subject to certain formalities that must be satisfied for the Chamber to validly consider the merits of the challenge. In this regard, Article 75 of the Constitutional Jurisdiction Law (Ley de la Jurisdicción Constitucional) establishes the admissibility requirements for an action of unconstitutionality. First, there must be a prior matter pending resolution, either in judicial proceedings or in the procedure for exhausting administrative remedies (agotar la vía administrativa), in which unconstitutionality has been invoked as a reasonable means of protecting the right or interest alleged to have been infringed. In its second and third paragraphs, the law exceptionally establishes circumstances in which no prior matter is required: when, by the nature of the matter, there is no individual and direct injury; when the defense of diffuse or collective interests (intereses difusos o colectivos) is involved; or when the action is filed directly by the Comptroller General of the Republic, the Attorney General of the Republic, the Chief Public Prosecutor of the Republic, or the Ombudsman.
As to the need for a prior matter pending resolution in administrative proceedings, it must involve the procedure that exhausts administrative remedies, which, pursuant to Article 126 of the General Public Administration Law (Ley General de la Administración Pública), commences when ordinary appeals (recursos ordinarios) are filed before the highest-ranking superior of the body that issued the final act; otherwise, the action would be inadmissible. Consistent with this, this Court has held as follows:
“IV.- Furthermore, it is clear from the appeal filed—individually, it bears repeating—by Mr. Barquero Ramírez that he merely requested the ‘review’ and ‘revocation’ of the challenged resolution. He did not concurrently file an appeal (recurso de apelación) before the corresponding superior. Since, pursuant to Article 126 of the General Public Administration Law, administrative remedies within decentralized entities are exhausted by their corresponding highest-ranking authority, and since filing an appeal in addition to a motion for revocation (revocatoria) is optional (Article 347.2 ibidem), it cannot be understood that intervention by the highest administrative authority was requested in this case, such that a decision capable of exhausting administrative remedies might be issued. This, in turn, reinforces the conclusion that the proceeding cited as the basis for this action is unsuitable for that purpose, requiring its dismissal at the threshold, as is hereby done.” (Judgment 2005-16829 at 09:17 on December 2, 2005).
There are also other formalities that must be fulfilled, namely: explicit identification of the challenged provisions, supported by proper legal grounds and specific citation of the constitutional rules and principles deemed infringed; authentication by an attorney of the pleading filing the action; proof of standing (powers of attorney and certifications); and a verbatim certified copy of the pleading in which the unconstitutionality of the provisions was invoked in the underlying matter. If the applicants fail to provide any of these requirements, the Office of the President of the Chamber may order them to cure the omission.
II.Standing and Admissibility of This Action of Unconstitutionality. The applicants challenge the Partial Regulatory Plan for Puerto Jiménez, Golfito-Puntarenas (Plan Regulador Parcial de Puerto Jiménez Golfito-Puntarenas) and the Zoning Regulations (Reglamento de Zonificación), asserting that they do so in defense of a diffuse interest: protection of the environment, as guaranteed by Article 50 of the Political Constitution. Indeed, the second paragraph of Article 75 of the Constitutional Jurisdiction Law provides for this exception to the general rules governing the admissibility of actions, which require the existence of a case pending resolution in judicial or administrative proceedings. Regarding the concept of a diffuse interest, in Judgment No. 1993-3750, issued at 15:00 on July 30, 1993, this Court stated as follows:
“… Although difficult to define and even more difficult to identify, diffuse interests cannot, under our law—as this Chamber has already held—be merely collective interests; nor may they be so diffuse that their ownership becomes indistinguishable from that of the national community as a whole, or so specific that particular persons or identifiable groups, or groups that are readily identifiable, stand out in relation to them, whose standing would derive not from diffuse interests but from the corporate interests pertaining to a community as a whole. They are therefore individual interests, but at the same time are dispersed among more or less extensive and amorphous groups of persons who share an interest and who consequently sustain actual or potential harm that is more or less equal for all. It is therefore rightly said that these are equal interests of groups of persons who find themselves in particular circumstances and, at the same time, of each individual within them.
In other words, diffuse interests have a dual nature, since they are both collective—because they are shared by the public at large—and individual, and may therefore be asserted as such.” According to the case law of this Chamber, diffuse interests exist when the protection of the environment, cultural heritage, the defense of the country’s territorial integrity, and the proper management of public expenditure, among other matters, are at stake. In the case before us, the applicants allege infringement of the fundamental right to a healthy and ecologically balanced environment, because biodiversity and the natural landscape are placed at risk, as well as the violation of several environmental principles. Accordingly, it is appropriate to consider the merits of the action.
Although the applicants have proper standing, this does not exempt them from complying with the requirements for instituting constitutional proceedings. As the Attorney General’s Office of the Republic correctly notes, the applicants allege infringement of Articles 7, 50, 89, and 169 of the Political Constitution; Article 5 and the following related provisions of the Convention on Nature Protection and Wildlife Preservation in the Western Hemisphere (Ley No. 3763); Article 4 and the following related provisions of the Convention Concerning the Protection of the World Cultural and Natural Heritage (Ley No. 5980); and Article 4 and the following related provisions of the Convention on Wetlands of International Importance (Ley No. 7224). However, they did not provide grounds for the alleged infringement of Articles 7 and 169 of the Constitution. Accordingly, it is not for this Court to cure that omission by the applicants, and therefore no ruling will be made concerning those provisions, although the stated grounds of unconstitutionality will nevertheless be addressed based on the remaining constitutional provisions invoked and properly supported.
III.Interventions in Support (coadyuvancias). Article 83 of the LJC establishes that, within 15 days following the first publication of the notice referred to in the second paragraph of Article 81, the parties appearing in matters pending as of the date the action was filed, or those with a legitimate interest, may enter an appearance to support the arguments that may justify granting or denying the action or, where appropriate, to expand the grounds of unconstitutionality concerning the matter in which they are interested. In this case, by a decision issued at 8:39 on May 21, 2013, this Chamber accepted the interventions in support submitted by representatives of the Cámara de Turismo de Corcovado, the Board of Directors of the Asociación de Desarrollo Integral de Puerto Jiménez, and Sociedad Bahía Cocodrilo S.A. In the pleading filed at 14:59 on May 21, 2013, and attached to this case file by this Court’s severance decision (resolución de desglose) No. 2013-7263, issued at 9:05 on May 31, 2013, the Auditors of the Asociación de Desarrollo Integral de Puerto Jiménez state that the letter submitted by the President, Vice President, and a Board Member of that Association was irregular because it lacked the approval of the Board of Directors, and they therefore request that the submission be disregarded.
In view of the foregoing, and because in the sub examine we are faced with a dispute in which standing to challenge arises from the existence of diffuse interests involving the right to the environment, the application submitted by Walter Aguirre Aguirre, Estarlin Marín Hidalgo, and Luz Marina Sibar Sibar should be granted, allowing them to participate as supporting intervenors (coadyuvantes), though not in their capacity as representatives of that organization, but solely in their personal capacities as persons interested in the resolution of this matter by virtue of the diffuse interest in environmental protection. Having resolved the applications for intervention in support, the Court proceeds to decide the merits of this matter.
IV.Subject Matter of the Action. The applicants challenge the PRPPJ and its corresponding Zoning Regulations, published in La Gaceta on Thursday, April 1, 2004, No. 65, on the ground that they are contrary to Articles 50 and 89 of the Political Constitution; Article 5 and the following related provisions of the Convention on Nature Protection and Wildlife Preservation in the Western Hemisphere (Ley No. 3763); Article 4 and the following related provisions of the Convention Concerning the Protection of the World Cultural and Natural Heritage (Ley No. 5980); and Article 4 and the following related provisions of the Convention on Wetlands of International Importance Especially as Waterfowl Habitat (Ley No. 7224). The text of the challenged Regulations for said Plan provides as follows:
“REGULATIONS FOR THE PARTIAL REGULATORY PLAN FOR PUERTO JIMÉNEZ GOLFITO-PUNTARENAS The Partial Regulatory Plan for Puerto Jiménez is the culmination of an entire process of research and social, economic, environmental, geographic, and environmental analysis of the area, intended to establish regulated land-use planning (ordenamiento regulado) for the benefit of the local community.
This document has received final approval from the Instituto Costarricense de Turismo (ICT), the Urban Planning Directorate of the Instituto Nacional de Vivienda y Urbanismo (INVU), and the Municipalidad de Golfito, and has also fulfilled the requirement of a public hearing (Audiencia Pública) in compliance with Article 17 of Urban Planning Law (Ley de Planificación Urbana) number 4240.
1.1 Development Criteria The Regulatory Plan (Plan Regulador) is based on the following development criteria:
1.2 Land Uses (Usos del Suelo) Land uses directly determine the proposed recommended use of the land, in accordance with the development criteria set forth above.
1.3 Zoning Regulations (Reglamento de Zonificación) These Zoning Regulations incorporate the experience and principles of other regulatory plans (planes reguladores) currently in force. New concepts are introduced in order to regulate the utilization of the proposed land uses (usos del suelo), adapting them to the topography and to environmental, biological, cultural, and other considerations.
The Municipalidad del cantón de Golfito, Puntarenas, hereinafter the Municipality, in exercise of the powers granted to it by the Urban Planning Law (Ley de Planificación Urbana) N° 4240 and its amendments, and pursuant to the provisions of the Maritime-Terrestrial Zone Law (Ley sobre la Zona Marítimo Terrestre) N° 6043 and its Regulations, the Organic Environmental Law (Ley Orgánica de Ambiente) N° 7554, the Municipal Code (Código Municipal) N° 7794, and the approval of the Instituto Costarricense de Turismo and the Dirección de Urbanismo del Instituto Nacional de Vivienda y Urbanismo:
HEREBY ENACTS:
The following Regulations for the Partial Regulatory Plan (Plan Regulador Parcial) of Puerto Jiménez, for the tourism territorial jurisdiction located between coordinates Lamber Norte 277.77N-534.42 E, 276.31 N-540.42 E, a sector demarcated by Instituto Geográfico Nacional boundary markers N° 865 through 975 in consecutive order, adjoining a public road and private properties beside the Puerto Jiménez airfield and the public road leading toward Platanares.
THE MUNICIPALIDAD DE GOLFITO HEREBY NOTIFIES THE COMMUNITY OF THE CANTON OF THE ADOPTION OF THE PUERTO JIMÉNEZ ZONING REGULATIONS, CONSISTING OF THE FOLLOWING ARTICLES.
Article 1—Objectives of the Regulations.
These Regulations have the following objectives:
Article 2—Definitions:
Article 3—General Rules a) For purposes of these Regulations, the following zones are proposed for the Puerto Jiménez Partial Coastal Sector, as shown in the following table:
Percentage Proposed zones Area (Ha) (%) Protection Zone 2.9384 29,58 Commercial Zone 0.2648 2,67 Tourist Accommodation Zone 6.1479 61,89 Basic Services Zone 0.0706 0,71 Roadways 0.5114 5,15 Total 9 9331 100 b) All fences on parcels resulting from the zoning must conform to the boundary of the inalienable 50 meters marked by the IGN boundary markers.
Article 4—Public Zone (Zona Pública, ZP) a) Purposes: To fulfill the intent of Ley 6043 and its Regulations regarding the right of public use of the 50 meters measured from the ordinary high-tide line (pleamar ordinaria). Existing tree cover in the beach berm area must be preserved to the greatest extent possible; this is the sector beyond the reach of ordinary tides. The berm sands are susceptible to removal, and the vegetation that holds them in place must therefore be maintained.
Article 5—Protection Zone (Zona de Protección, Z PRO).
Article 6—Commercial Zone (ZC).
. Lot frontage: 10 m minimum, 30 m maximum . Minimum setback (retiro): 3 m side and 5 rear, 7m front . Maximum lot coverage: 70% of the lot . Lot size: 600m² minimum, 1000 m² maximum . Maximum height: 2 stories or 7 m. Mezzanines are not permitted . In addition to commercial use, the owner’s single-family dwelling shall be permitted.
. Parking within the lot or property.
. Engineered buildings must be designed using earthquake-resistant materials and construction systems, as established by the Código Sísmico y de Cimentaciones de Costa Rica.
. The technical foundation specifications indicated in the soil study incorporated into these Regulations must be observed.
Article 7—Low-Density Tourist Accommodation Zone (Zona de Alojamiento Turístico de Baja Densidad, ZAT BD) a) Purpose: Intended for the establishment of low-density tourism facilities, associated with complementary lodging and food-service activities for domestic and foreign tourists, and also allowing recreation and leisure for visitors. Tourism projects must incorporate a forestry component and preserve existing vegetation to the greatest extent possible.
ü Maximum lot area 15 000 m² ü Setbacks: side 3m, front 7, rear 10m - Green area 35 % minimum -Recreational area 10 % -Commercial facilities area 0.5 % -Internal roads 15% -Width of internal roads 7 m -Maximum coverage 30% -Maximum height 2 stories or 7 m. Mezzanines are not permitted -Minimum lot area 2000 m - Maximum density 60 persons per Ha.
Article 8—Basic Services Zone (ZSB) a) Purpose: Intended to provide basic services to visitors who do not stay overnight in the area.
ü Maximum height 1 story ü Maximum coverage 60 % ü Minimum coverage, green areas 20 % ü Setbacks 3 m side and rear, 5 m front ü Maximum roof height 3,5 m ü For buildings with thatched roofs 10 m g) Concessions: In accordance with the provisions of the Maritime-Terrestrial Zone Law N° 6043.
Article 9—General Rules ü Fill works are not permitted.
ü No drainage systems are permitted in fill areas near the beach. ü Stormwater drainage systems must be directed toward green areas. ü The discharge of stormwater (channeled or piped) onto the beach is prohibited. ü Motor vehicle access to the beach is prohibited. ü The extraction of materials from the Maritime-Terrestrial Zone (Zona Marítimo Terrestre) is prohibited. ü The accumulation and storage of construction or excavation materials in the Public Zone (Zona Pública) is prohibited. ü Parcels or lots adjoining the estuary or mangroves must provide the setback line (alineamiento) issued by the Urban Planning Directorate (INVU) before construction begins. ü Individual and collective sewage systems must submit their design and infiltration tests for approval. ü For the construction of wells in designated areas, a supporting study and the corresponding approval must be submitted. For construction projects, the interested party must submit a development project for the concession area within no more than 10 months after its application has been approved by the ICT.
The development project must include the following:
ü Name and address of the concessionaire (natural or legal person). ü Project name (project type specified by the ICT). ü Name, signature, and CFIA registration number. ü Written in Spanish. ü Cadastral plan of the area to be developed. ü Property location plan (boundaries, setback lines, restrictions). ü Contour plan at 0,50-meter intervals, indicating pedestrian and vehicular access. ü Site design plan at a scale of 1:100. ü Longitudinal and cross sections of the project. ü Estimated budget for the works. ü Financing method. ü Drinking-water supply and wastewater and solid-waste disposal systems. ü Project description report indicating: implementation timeframes, potential market, quality of the facilities, administration of the personnel to be employed, rates to be charged, and services subject to charges. ü Environmental Impact Study (Estudio de Impacto Ambiental) (SETENA). ü Certification of drinking-water availability, in accordance with the requirements of the ICT Development Department.
1.4 Roadway Regulations Article 10.-Natural constraints or tree cover and natural drainage result in limited development with respect to roadway connections.
. Existing 7-meter street, which retains the same right-of-way, as indicated on the Roadway Plan.
. Sidewalk, curb, and gutter: 1,65 m . Roadway: 3,70 m . 6-meter pedestrian path:
. Ditch and green area: 1,50 m on both sides . Roadway: 3,00 m . Proposed 14-meter road: the main access road running from the main road to the Basic Services Zone, near marker N° 947, parallel to the estuary.
. Sidewalk and ditch: 3,50 m on both sides . Roadway: 7,00 m Contains a map that may be consulted in La Gaceta No. 65 of 1° de abril de 2004, page 33.” The petitioners contend that the publication of the PRPPJ infringes the fundamental right to a healthy and ecologically balanced environment by placing biodiversity and the natural landscape at risk. They add that several environmental principles are also violated, including the rational use of land, informed public participation, the precautionary principle, the principle of environmental non-regression, the principle of objective substantiation, and the principle of non-reduction of forest area (irreductibilidad del bosque). They state that these principles impose on private parties, municipalities, and the State the obligation, among other things, to conduct prior environmental studies before issuing regulations intended to establish the territorial planning (ordenamiento territorial) of an area, particularly where biodiversity may be affected.
They invoke various judgments of this Chamber (judgments Nos. 233-1993, 5399-1993, 1886-1995, 4587-1997, 6322-2003) to argue that the protection of a healthy and ecologically balanced environment must not yield to economic considerations or to companies pursuing private interests. Specifically, they state that there are five grounds for granting this action. FIRST. The Plan was approved and published without assessing the environmental variable (variable ambiental). SECOND: Because the Plan was approved and published without incorporating the environmental variable, Article 89 was violated in connection with the principles of objective substantiation of environmental protection and precaution, which could result in harm to the landscape and the various ecosystems in the area. THIRD: The Plan contains indeterminate criteria, such as proposing the protection of 28,58%, and these criteria lack reasonableness and scientific justification, thereby leaving the mangrove unprotected.
FOURTH: A private company pursuing commercial purposes prepared the PRPPJ in order to construct its docking facility or marina. FIFTH: There was never any informed public participation prior to municipal approval. It follows from the foregoing that the petitioners challenge the Plan and its corresponding Regulations on substantive and procedural grounds; in this regard, this Chamber will analyze the arguments in the order in which they were presented solely by the petitioners.
This clarification is made because, when responding to the hearing granted by this Court pursuant to Article 81 of the Ley de la Jurisdicción Constitucional, the Procuraduría General de la República introduced an issue relating to the administration of the State’s natural heritage that was neither raised by the petitioners nor included within the scope of this action, according to the publication of the corresponding notices. Accordingly, this Court will not rule on that issue, because it is improper for a body whose function in this matter is to advise this Court, and whose opinion must be limited solely to the matters raised by the petitioners, to introduce new arguments through that procedure.
V.First argument: The PRPPJ was approved without the environmental variable. The petitioners assert that, from the time the challenged regulations were issued, they lacked an environmental impact assessment (evaluación de impacto ambiental), as required by this Court in judgments numbers 2002-1220 and 2003-6322, even though SETENA had not issued the relevant regulations at that time, because they consider that this omission violates the principles of objective substantiation and environmental non-regression. They further state that such an analysis must not be confused with the environmental impact study required for each infrastructure project authorized in the Maritime-Terrestrial Zone.
Without intending to conduct a review of the legality of the challenged matter, this Court nevertheless considers it pertinent to mention the regulatory framework then in force in order to determine whether this particular point was addressed when the Regulatory Plan (Plan Regulador) at issue was adopted.
As the petitioners correctly indicate, this Court held in judgment No. 2002-1220 that municipal autonomy was not infringed by requiring an environmental impact assessment before a regulatory plan could be approved:
“VI.- …The Chamber considers that (…) every urban development regulatory plan must, before being approved and implemented, undergo an environmental impact assessment from the perspective established by constitutional Article 50, so that land-use planning and its various regulatory regimes are compatible with the scope of the higher-ranking provision…”.
On the contrary, it held that such a requirement is consistent with constitutional Article 50 and the State’s duty to protect the constitutional right to a healthy and ecologically balanced environment:
“Constitutional Article 50 is the direct source of the right of ‘every person’ to a healthy and ecologically balanced environment, which binds the Public Authorities, in protecting the environment—understood in the broadest possible sense—to apply the protective rule. This Chamber has repeatedly held that the development of fundamental rights and public freedoms is subject to statutory reservation (reserva de ley); accordingly, in this field, the regulatory authority that the Political Constitution itself reserves to the Executive Branch is inconceivable without the existence of a statute. As already noted, Article 17 of the Ley Orgánica del Ambiente, in furtherance of constitutional Article 50, establishes the obligation to obtain an environmental impact study (estudio de impacto ambiental) before carrying out activities or projects that, by their nature, may alter or pollute the environment.
As the Office of the Attorney General correctly states in its report, the environmental impact study is conceived by the legislature as a technical procedure that makes it possible to control potential environmental alteration and the resulting effects on ecosystems. This is unquestionably a technical matter whose detailed regulation falls outside the logic of the legislative process and may, as a matter of principle and within the existing legal framework, be regulated by the Executive Branch. The Ley Orgánica del Ambiente clearly provides that ‘... Human activities that alter or destroy elements of the environment or generate waste or toxic or hazardous materials shall require an environmental impact assessment (evaluación de impacto ambiental) created under this law ...,’ which, properly construed, supports the conclusion that no human activity capable of altering or polluting the environment may dispense with the aforementioned environmental impact study.
The mechanism devised by the Executive Branch to establish, prima facie, whether a proposed human activity may alter or destroy the environment has been the submission of the form known as the ‘Preliminary Environmental Assessment’ (‘Evaluación Ambiental Preliminar’). It is therefore not the case, as the Administrative Environmental Tribunal asserts in its report, that the Executive Branch has absolute discretion to identify the projects that must undergo an environmental impact study, because, under the Political Constitution itself (art. 50) and the Ley Orgánica del Ambiente, as a general principle, every human activity that modifies the surroundings ‘shall require’ that study. It is therefore the nature of the project or works that will determine, in each case, whether an environmental impact study is required, rather than arbitrary conditions established through regulations. The regulations must establish only the manner in which the project’s characteristics will be ascertained, and those characteristics will determine whether the environmental impact study is warranted.
This means that the defense and preservation of the right to a healthy and ecologically balanced environment, recognized in constitutional Article 50, is every person’s fundamental right and operates as an unavoidable general principle; consequently, generic exceptions cannot be made in this area (in urban-planning matters and the other topics addressed by Articles 19 and 20) to exempt compliance with environmental obligations, since doing so risks stripping the guarantee of a governmental response in defense of the environment of its constitutional character. Accordingly, the mechanism used by the Executive Decree to determine a priori which activities or works are exempt from an environmental impact study—based on the size of the works, the existence of regulatory plans (planes reguladores), the number of persons involved in the operation or activity, the number of rooms, the project’s classification (social interest), or land use—demonstrates an overreach in the exercise of regulatory authority that exceeds the delegation contained in Article 17 of the Ley Orgánica del Ambiente and deprives residents of their right to have the Public Authorities exercise direct environmental oversight—not through delegation to professional supervisors (regencias)—in applying protective legislation.
This does not mean that the Executive Branch may not, by regulation and on the basis of precise technical studies, determine that a particular activity or project does not require environmental impact studies; however, such a determination must be properly reasoned and justified. It must be recalled that when an exception is made to a higher-ranking form of oversight (constitutional oversight), the reasonableness and proportionality of the exceptional circumstance will be subject to judicial review, whether through ordinary legal proceedings or constitutional review. But under the general system conceived by the derivative constituent authority (Constituyente derivado), a generalized exception whose sole reason or basis is the very existence of the provision declaring it is inadmissible.” (Judgment No. 2002-1220, reiterated in Judgment No. 2003-6322) Indeed, in furtherance of those principles, Article 17 of the Ley Orgánica del Ambiente, No. 7554 of October 4, 1996, provides:
“Article 17.—Environmental Impact Assessment. Human activities that alter or destroy elements of the environment or generate waste or toxic or hazardous materials shall require an environmental impact assessment by the Secretaría Técnica Nacional Ambiental created under this law. Prior approval by that agency shall be an indispensable requirement for commencing the activities, works, and projects. Statutes and regulations shall specify which activities, works, or projects will require an environmental impact assessment.” In accordance with this provision’s delegation regarding which activities, works, or projects would require an environmental impact assessment, SETENA was compelled to regulate this subject matter by Executive Decree. One of the Decrees issued for that purpose, which specified which projects had to undergo an environmental impact assessment, was reviewed by this Tribunal in Judgment No. 2012-2002 because those regulations excluded certain projects from such assessment without a technical basis:
“Accordingly, the mechanism used by the Executive Decree to determine a priori which activities or works are exempt from an environmental impact study—based on the size of the works, the existence of regulatory plans, the number of persons involved in the operation or activity, the number of rooms, the project’s classification (social interest), or land use—demonstrates an overreach in the exercise of regulatory authority that exceeds the delegation contained in Article 17 of the Ley Orgánica del Ambiente and deprives residents of their right to have the Public Authorities exercise direct environmental oversight—not through delegation to professional supervisors—in applying protective legislation. This does not mean that the Executive Branch may not, by regulation and on the basis of precise technical studies, determine that a particular activity or project does not require environmental impact studies; however, such a determination must be properly reasoned and justified.
It must be recalled that when an exception is made to a higher-ranking form of oversight (constitutional oversight), the reasonableness and proportionality of the exceptional circumstance will be subject to judicial review, whether through ordinary legal proceedings or constitutional review. But under the general system conceived by the derivative constituent authority, a generalized exception whose sole reason or basis is the very existence of the provision declaring it is inadmissible.” Consequently, on that occasion, Articles 19 and 20 of the Reglamento de Procedimientos de la Secretaría Técnica Nacional Ambiental, SETENA, Executive Decree 26.228-MINAE, were annulled, as was, by connection, Article 20 of Executive Decree 25.705-MINAE. As a result, it was only upon the entry into force of the Reglamento de EIA, Executive Decree No. 31.849 of May 24, 2004, that Article 67—in force at that time—established the obligation to subject regulatory plans and any other land-use planning instrument to a Strategic Environmental Assessment (Evaluación Ambiental Estratégica):
“Article 67.—Integration of the environmental variable into Regulatory Plans. The Regulatory Plans established under the Ley de Planificación Urbana and the Ley de la Zona Marítima Terrestre, or any other official land-use planning plans or programs intended to plan the development of human activities that may potentially affect the environment, shall satisfy the requirement of integrating the environmental-impact variable, which shall be subject to an environmental-viability process (viabilidad ambiental) conducted by SETENA before approval by the respective authorities.
Through its Manual de EIA, SETENA shall establish the terms of reference, instruments, and procedures for integrating that environmental variable into regulatory plans or land-use planning plans or programs. This shall apply both to those currently being prepared or to be prepared in the future and to those already approved that have not yet obtained environmental viability.” Likewise, Article 66 of that Decree provided:
“Article 66.—Procedures and instruments of the Strategic Environmental Assessment (Evaluación Ambiental Estratégica, EAE). Through the Manual de la EIA, SETENA shall establish the basic guidelines and procedures for the gradual development and implementation of a Strategic Environmental Assessment system in the country, as part of its responsibility as the Environmental Impact Assessment authority conferred by the Ley Orgánica del Ambiente.” Nevertheless, this undertaking was not completed until February 20, 2006, when SETENA, through Executive Decree 32.967-MINAE, issued the Manual de Instrumentos Técnicos para el Proceso de Evaluación del Impacto Ambiental-Parte III.
The foregoing is relevant to this review because the claimants maintain that the environmental assessment in question should have been completed before the challenged Regulatory Plan and its Regulations were adopted. However, the challenged regulations were adopted by the Concejo Municipal de Golfito at Session No. 8 of February 16, 2004, and published in the Diario Oficial La Gaceta No. 65 on April 1, 2004. Thus, this Plan was issued during the period in which, although the Chamber had advised SETENA of the duty and need to incorporate environmental assessment into land-use planning instruments, the regulations enabling municipalities to carry out that undertaking had not yet been implemented when the PRPPJ was issued, as explained above. This Tribunal has considered this situation in cases similar to the matter under review (sub examine), as occurred with the Plan Regulador de Escazú:
“IV.- Regarding the violation of Article 50 of the Political Constitution. The record also shows that the Escazú Regulatory Plan (Plan Regulador de Escazú) was approved by the Concejo Municipal de Escazú at extraordinary session number 59, held on diecisiete de diciembre de dos mil cuatro, through Agreement AC-396-04, which was published on tres de febrero de dos mil cinco in the Official Gazette La Gaceta; an erratum was subsequently published and communicated through the same official medium on jueves diecisiete de marzo siguiente, in La Gaceta number 54… In that context, in the opinion of this Constitutional Court, there are no grounds for granting this appeal as it pertains to the Municipalidad de Escazú on this issue, not only because the omission found was due to reasons beyond its control, but also because, as the respondent authority argues, the Regulatory Plan for that canton may be reviewed subsequently by SETENA, as SETENA must do in the case of all regulatory plans in effect prior to the promulgation of the Regulations of veintiocho de junio de dos mil cuatro.
Moreover, the annulment of the approved Regulatory Plan, as sought by the appellant, would in no way provide greater protection for the fundamental right enshrined in Article 50 of the Constitution because, as the respondent Mayor argues, ‘…urban growth in the canton had been proceeding very rapidly, and there was no uniform regulation adapted to its circumstances, meaning that the environmental harm being caused to the canton and to the Escazú community in general was more serious without the Plan than with its promulgation.’ Consideration must also be given to the regulatory content of every regulatory plan with respect to such important matters as construction, road systems, subdivision (fraccionamiento), and zoning (zonificación), whose regulation would be left with a gap that, far from benefiting the residents of the canton of Escazú, could cause them harm if the recently published Regulatory Plan were annulled.
Nevertheless, as ordered in the operative part of this decision, immediately after SETENA publishes the Manual de Instrumentos Técnicos para el Proceso de Evaluación de Impacto Ambiental, the Municipalidad de Escazú must submit the Regulatory Plan challenged in this amparo proceeding (amparo) to the environmental feasibility process (proceso de viabilidad ambiental), so that it may make, without delay, the adjustments determined by SETENA.” (Judgment No. 2005-9765, issued at 15:37 on 27 de julio de 2005.)
This precedent was also applied to the Pérez Zeledón Urban Regulatory Plan (Plan Regulador Urbano de Pérez Zeledón) in Judgment No. 2006-11562, issued at 15:30 on 9 de agosto de 2006, in which this Court reiterated the following:
“V.- Conclusion. In the present action, the decision transcribed above is entirely relevant to the case because, although the Pérez Zeledón Urban Regulatory Plan does not have an environmental impact assessment (evaluación de impacto ambiental), under the terms discussed supra, declaring it unconstitutional would in fact leave the environment unprotected, insofar as it would leave that area without land-use planning (ordenamiento territorial). The failure to have an environmental impact study (estudio de impacto ambiental) does not, in itself, constitute a violation of the right to a healthy and ecologically balanced environment, as the petitioner assumes. Acceptance of that argument would entail a presumption that every Urban Regulatory Plan harms the environment unless an environmental impact study rebuts that presumption; the reasoning just cited is logically inconsistent, and therefore the proposed ground of unconstitutionality is unfounded. Nor do the judicial precedents mentioned support the position advanced by the petitioner; accordingly, the constitutional challenge must be dismissed.” (Emphasis added.)
Thus, this Court has held that no responsibility could be attributed to the municipalities for SETENA’s delay in regulating the respective procedures, much less could they be expected not to fulfill one of their most important duties, namely, to regulate land use in order to protect the health, safety, comfort, and welfare interests of their communities. Likewise, in preparing and planning that Plan, the authorities were and remain required to adhere to other studies and verify compliance with the regulations in force. They are also obligated subsequently to incorporate the environmental variable (variable ambiental) into the Plan in question. According to the representative of the Municipalidad de Golfito, that process began in 2006 in collaboration with the Programa de Investigación en Desarrollo Urbano Sostenible (ProDUS) de la Universidad de Costa Rica. However, it was interrupted by a communication from the Universidad received by the Municipality on 23 de enero de 2013, stating that it lacked the resources to continue preparing the Plan Regulador Cantonal de Golfito and the environmental fragility indices (índices de fragilidad ambiental).
Consequently, by Agreement 22 adopted at ordinary session 03-2013, held at 16:15 on 23 de enero de 2013, the Concejo Municipal resolved to seek resources from JUDESUR so that INVU and ICT could continue that process, although the fact remains that the environmental variable has yet to be incorporated. This situation demonstrates the present need to order the competent authorities to continue the proceedings and complete that process as required by the legal system, but it does not warrant declaring the regulations in question unconstitutional, much less annulling them as requested by the petitioners. As this Court has stated in similar situations, doing so would cause greater harm to the community due to the absence of land-use planning, which, far from being consistent with the right enshrined in Article 50 of the Constitution, could violate it even further. The petitioners should bear in mind that a Regulatory Plan does not automatically authorize the granting of a concession or permit; rather, the impacts of projects must first be assessed by SETENA.
Accordingly, the action must be dismissed as to this issue, without prejudice to warning the respondent authority that it must continue the process of preparing and incorporating the respective environmental fragility indices.
According to the petitioners, because the PRPPJ was approved and published without incorporating the environmental variable, the principles of objective environmental protection (principio de objetivación de tutela ambiental) and precaution (principio precautorio) were violated, which could cause harm to the landscape, the area’s various ecosystems, and the mangroves. They state that, as a result, the different land areas are neither clear nor justified (for example, the percentage established for the protection zone (zona de protección), at 29,58% of the area); furthermore, it is inadmissible for the regulatory provision to state that one of the development criteria is “not to make proposals that entail high costs for the Municipalidad de Golfito and the concession holders (concesionarios).” In this regard, it must be reiterated that the omission of the Plan’s environmental impact assessment in the sub examine case is not attributable to the Municipality, because SETENA had not, at that time, established the procedures through which compliance would be verified. It is further emphasized that a Regulatory Plan does not automatically authorize the granting of a concession or permit for a particular project because, in every case, the characteristics of each project and its environmental impact must first be assessed by SETENA and supported by the relevant studies.
There can be no doubt that mangroves are of such importance that their protection derives not only from Article 50 of the Constitution but also from international rules whose content has been incorporated into our legal system and regarding which this Court has ruled as follows:
“V.- On the protection of wetlands (humedales). This Chamber has addressed the importance of these ecosystems and their protection in Judgments 2001-12817, issued at 10:28 on 14 de diciembre del 2001, and 2007-6246, issued at 19:30 on 8 de mayo del 2007, among others, noting that wetlands are considered the world’s most productive ecosystems. In Costa Rica, Article 40 of the Ley Orgánica del Ambiente defines them as:
‘Ecosystems dependent on natural or artificial, permanent or temporary, lentic (lénticos) or lotic (lóticos), fresh, brackish, or saltwater regimes, including marine areas extending to the outer boundary of seagrasses or reefs or, in their absence, to a depth of seis metros at low tide.’ Regarding the importance of these ecosystems, in Decision No. 2009-014288, issued at 15:19 on 09 de setiembre de 2009, this Court stated:
‘The importance of wetlands lies not only in their biodiversity and the processes occurring at the ecological level, but also in their provision of supporting functions and essential products for human communities in both the developing and industrialized world.
According to legal scholarship and scientific studies, the term wetlands encompasses a wide variety of ecosystems with very different characteristics. They may be classified into seven landscape units: estuaries, open coasts, floodplains, freshwater marshes, lakes, peatlands, and flood forests; or as saltwater wetlands, freshwater wetlands, or artificial wetlands. Each consists of a series of physical, chemical, and biological components, such as soils, water, animal and plant species, and nutrients. The processes among and within these components enable a wetland to perform functions such as flood control and storm protection and to generate products such as wildlife, fisheries, and forest resources; wetlands also purify water and stabilize the coastline. Not all characteristics are present in every wetland, and few perform all these functions in the same manner.
In addition, they possess highly valuable attributes such as biological diversity and the uniqueness of cultural heritage. It is the combination of these ecosystem functions, products, and attributes that makes wetlands (humedales) important to society. By storing precipitation and releasing runoff (escorrentía) evenly, wetlands can lessen the destructive force of floods and rivers, and therefore the conservation of natural storage areas may avoid the need to construct dams and reservoirs. Their vegetation can stabilize the coastline by reducing the energy of waves, currents, or other erosive forces, while plant roots hold bottom sediments in place, which can prevent both the erosion of valuable agricultural or inhabited land and damage to property. Wetlands that remove nutrients improve water quality and help prevent eutrophication (eutrofización), which may avoid the need to construct water-treatment systems.
Moreover, many support dense populations of fish, livestock, or wildlife that feed in their nutrient-rich waters or on their substrate, or graze in their lush grasslands. The hydrological, nutrient, and matter cycles and energy flows of wetlands can stabilize local climatic conditions, particularly precipitation and temperatures, thereby affecting agricultural and natural-resource-based activities, the stability of natural ecosystems, and the wetland itself. They also contribute to recreation, fisheries, agricultural resources, and tourism, as well as to the direct use of the forest resources that yield a significant number of goods, ranging from firewood, construction timber, and bark, among timber products, to resins and medicines, which are “secondary” non-timber forest products. They are even important as a genetic reserve for certain plant species—such as rice.” Several international instruments address their protection, most notably the Convention on Wetlands, or Ramsar Convention, signed by our country pursuant to Ley No. 7224 on 9 de abril de 1991 and published in La Gaceta on 8 de mayo de that same year.
The Ramsar Convention defines a wetland as: “Areas of marshes, swamps, peatlands, or waters, whether natural or artificial, permanent or temporary, static or flowing, fresh, brackish, or salt, including areas of marine water whose depth at low tide does not exceed six meters.” The Convention proclaims the duty of States to protect these ecosystems—not only in their own interests but also in the international interest—and countries are therefore required to develop national policies aimed at conserving these environments within their land-use policies. Among the various obligations undertaken by signatory countries is the designation of at least one wetland of international importance for inclusion in the List of Ramsar Sites, which must be selected on the basis of its international significance from an ecological, botanical, zoological, limnological, or hydrological standpoint; this is therefore a commitment relating to the protection of specific sites (Article 2).
In addition, obligations unrelated to specific sites are undertaken, such as preparing and implementing management plans in a manner that promotes the wise use (uso racional) of wetlands within their territory (Article 3). They are also required to promote the conservation of wetlands and waterfowl by establishing nature reserves in wetlands, whether or not they are included in the List” (Article 4). Finally, the signatory countries must coordinate their policies and regulations concerning the conservation of wetlands and their flora and fauna (Article 5). Thus, the parties establish a system for protecting wetlands, first through a list of wetlands of international importance (Ramsar Sites), and second by seeking the wise use of all wetlands within their territory. Likewise, the “Guidelines for the Implementation of the Wise Use Concept of the Convention,” adopted through Recommendation 4.10, state that “the wise-use provisions apply to all wetlands and the systems supporting them within the territory of a Contracting Party, both those included in the List and all others.” According to the Secretariat of the Ramsar Convention, the National Wetlands Policy must include the following objective: “To prevent further losses of remaining wetlands and encourage the rehabilitation of the country’s wetlands while maintaining their integrity, conserving their genetic diversity, and ensuring that their enjoyment and economic use are sustainable.” It should also “encompass all types of wetlands.” It is therefore clear that, under the Ramsar Convention, every ecosystem possessing the characteristics of a wetland must be used wisely and sustainably under the terms defined by the Convention and the Conference of the Parties.” (See judgment No. 2013-7934, issued at 9:05 on 14 de junio de 2013.)
In our country, these are areas forming part of the State Natural Heritage (Patrimonio Natural del Estado) and belonging to the public zone (zona pública). With respect to mangroves, the Ley sobre Zona Marítimo Terrestre provides:
“Article 11.- The public zone shall also include, regardless of its extent, the area occupied by all mangroves along the mainland and island coastlines and all estuaries within the national territory.” Municipalities administer the maritime-terrestrial zone (zona marítimo terrestre), which includes both the public zone and the restricted zone (zona restringida). Nevertheless, mangroves are excluded from that administration even when located within those areas, because they fall under the authority of MINAE, pursuant to the Ley Forestal:
“Article 13.- Establishment and administration The State Natural Heritage shall consist of the forests and forestlands (terrenos forestales) of national reserves, areas declared inalienable, properties registered in its name, and those belonging to municipalities, autonomous institutions, and other bodies of the Public Administration, except for real property securing credit transactions with the Sistema Bancario Nacional that becomes part of its assets.
The Ministerio del Ambiente y Energía shall administer this heritage. Where appropriate, acting through the Procuraduría General de la República, it shall register the lands with the Registro Público de la Propiedad as individually identified properties owned by the State.
Non-governmental organizations that acquire real property containing forest or suitable for forestry, using funds derived from donations or the public treasury that were obtained on behalf of the State, must transfer such property into the State’s name.” “Article 18.- Authorization of activities Within the State Natural Heritage, the State may conduct or authorize research, training, and ecotourism activities once they have been approved by the Ministro del Ambiente y Energía, who shall determine, when appropriate, whether environmental impact assessments (evaluaciones del impacto ambiental) must be conducted, as provided by the regulations to this law.” This is also set forth in Article 4 of the Reglamento de la Ley sobre la Zona Marítimo Terrestre and Article 2, subsection 23), of the Reglamento a la Ley de Conservación de Vida Silvestre:
“Article 4.- In accordance with Decreto Nº 7210-A of 19 de julio de 1977, the mangroves or saltwater forests located along the mainland or island coastlines and estuaries of the national territory, which form part of the public zone within the maritime-terrestrial zone, constitute a Forest Reserve (Reserva Forestal) and are subject to the Ley Forestal and all provisions of that decree. The restricted zone begins at the vegetation line along the shore of the estuaries and at the boundary of the mangroves or saltwater forests where these extend more than 50 meters beyond ordinary high tide.” “23) MANGROVE: An ecosystem dominated by groups of pantropical plant species, typically comprising trees, shrubs, and associated vegetation, which possess morphological, physiological, and reproductive adaptations enabling them to colonize areas subject to tidal exchange. The general landscape is dominated by forests of different mangrove species, estuaries, and channels.
Salinity concentrations vary according to the climatic season and the inflow of inland waters, with salt-concentration values ranging from very low to very high.” Accordingly, the State Natural Heritage is a legally protected interest (bien jurídico), defined and individually identified in our legal system, and the lands comprising it under environmental legislation do not require a declaration as a protected wildlife area (área silvestre protegida) in order to receive protection from the Administration, because their very nature determines the protection afforded to them. Their limited use is clearly prescribed by law and its regulations, and their uses are essentially restricted to research, training, and ecotourism activities previously approved by the Ministerio del Ambiente y Energía, not by the municipality (see Article 18 of the Ley Forestal cited above).
Article 5 of the challenged PRPPJ provides:
“Article 5.- Protection Zone (Z PRO).
Regarding the percentage of the protection-zone area claimed by the petitioners, according to the Presidente Municipal, that 29.58% area designated for the absolute protection of mangroves, estuaries, streams, and rivers does not include the actual area of the estuary, stream, or river being protected, and therefore the protected area is larger. It is likewise reiterated that the determination of the areas in question resulted from the boundaries established by the Instituto Geográfico Nacional at that time. It must be borne in mind that this Institute publishes the official demarcations on the basis of which Catastro approves all plans. In this regard, Articles 16 and 17 of the Ley Forestal, Article 13 of the Reglamento de la Ley Forestal, and Article 63 of the Reglamento de la Ley sobre Zona Marítimo Terrestre provide:
“Article 63.- The Instituto Geográfico Nacional shall publish a notice in the Diario Oficial for each portion of the maritime-terrestrial zone in which it has demarcated the public zone.
The Dirección General de Catastro shall not register any plan that does not bear the approval of the Instituto Geográfico Nacional with respect to the delineation of the public zone.” Likewise, the INVU and the ICT reviewed the regulations at issue, proposed the changes they deemed appropriate, and approved them, stating that they were consistent with the demarcated areas. As established before this Court, in official letter PU-C-D-011-2003 of January 8, 2003, issued by the INVU, this Plan respected the stream protection area, specified land use (uso de suelo), modified the road network, primarily its main access, and respected the mangrove protection area, among other matters; to that end, a certification from the Instituto Geográfico Nacional was attached, certifying the boundary markers (mojones) and their locations (see official letter attached to the case file). Therefore, it is not valid to assert that, on the date the challenged Plan was issued, the measures adopted by the Municipalidad de Golfito, the INVU, and the ICT lacked technical criteria or the verification required by the legal system then in force, since, as stated in the preceding recital (considerando), the omission of the environmental assessment (evaluación ambiental) claimed by the petitioners cannot be attributed to the municipality because the regulations necessary for its implementation did not exist at that time. Consequently, the petitioners’ allegations in this regard are rejected.
Now, official letter ACOSA-D-183-2007, issued by the Área de Conservación de Osa on July 20, 2007, was introduced into the record as evidence. That letter certified the State natural heritage area (área de patrimonio natural del Estado) identified in the regulatory plan (Plan Regulador) under review and, although it acknowledges that the Municipalidad de Golfito has not granted any concession (concesión) over that area, it sets forth the following conclusions:
“1. The State natural heritage area identified and quantified in the Plan Regulador de Puerto Jiménez covers 4.89 hectares and comprises forest, wetland, lagoon, and mangrove areas, based on resolution R-SINAC-013-2006.
2. The protection areas that are not classified as State natural heritage but must be included in the land-use zoning (zonificación de Uso) of the Plan Regulador cover an area of 1.60 hectares.
3. There is a problem with the demarcation of the restricted zone (zona restringida) in the Plan Regulador de Puerto Jiménez; therefore, that area, which forms part of the maritime-terrestrial zone (zona marítimo terrestre), must be corrected.
4. Several buildings were identified on-site within the public zone (zona pública), three of them at the hotel Parrot Bay between boundary markers 921-922-923; a house was also observed and located at boundary marker 941, which lies within the public zone, is registered to Brisa de la Bahía S.A., and is occupied by Mr. Carlos Luís Villegas García (…)” Consistent with the foregoing, it issued the following recommendations:
“First: Issue the corresponding certification to the Municipalidad de Osa and the Instituto Costarricense de Turismo stating that, within the Plan Regulador de Puerto Jiménez, there are 1.76 has of mangrove areas, 0.91 has of wetland areas, 0.58 has of coastal lagoon, and 1.64 has of forest areas.
Second: Certify that the Plan Regulador de Puerto Jiménez contains no Class VII and VIII lands suitable for forestry (áreas de aptitud forestal), according to the Metodología de Capacidad de Uso del Suelo de Costa Rica.
Third: Notify the Municipalidad de Golfito and the Instituto Geográfico Nacional regarding the demarcation of the restricted zone and make the corresponding correction to the boundary proposed in this regulatory plan.” Likewise, official letter SINAC-ACOSA-PNE-AD-079-2013, prepared by Engineer Joel García Medina of the Programa de Patrimonio Nacional del Estado, states that, according to the desktop study (estudio de gabinete), it can be determined that, within the private-use area (área de uso privado) of the Plan Regulador Parcial de Puerto Jiménez of the canton of Golfito, the area designated for private use conflicts with wetland areas covered by the certification, specifically polygons H3 of 0,22 has and H4 of 0,48 has. Likewise, a proposed gravel road within the regulatory plan crosses two mangrove areas (public zone), polygons H1 and H2; a proposed pedestrian walkway affects the wetland in polygon H5; and the letter concludes that, according to the digital files, the Plan’s land uses conflict with certification ACOSA D-0183 of June 20, 2007.
It should be noted that the first official letter, ACOSA-D-0183 of June 20, 2007, states that the boundary-marker certification issued at that time by the Instituto Geográfico Nacional was erroneous, while official letter SINAC-ACOSA-PNE-AD-079-2013, prepared by the Programa de Patrimonio Nacional del Estado of the same MINAE, now states that official letter ACOSA-D-0183 of June 20, 2007, is also erroneous.
The foregoing allows this Court to reach 2 conclusions:
1-The three technical assessments differ in their results and reach different conclusions; consequently, this Court cannot give greater credence to one over another. Moreover, they were issued in different years, and the geomorphological conditions of the area may have changed, or the techniques used may have influenced the conclusions reached. Furthermore, during the hearing held on November 6, the representative of the Instituto Geográfico Nacional clearly stated that the State natural heritage has not yet been precisely demarcated and that, although work on the matter is underway, funding and years of work will be required to clarify the updated study. Accordingly, this jurisdiction is not the competent forum for resolving the accuracy and technical validity of such reports; that matter belongs in the corresponding ordinary legality proceedings (vía de legalidad). Therefore, from a constitutional perspective, no omission may be attributed to the authorities that approved the regulatory plan at issue, since they acted in accordance with the legal system then in force and the information available to them.
2-However, once the public authorities have identified inconsistencies of this nature, they cannot leave them unaddressed. In accordance with the precautionary principle (principio precautorio) and the principle of coordination among public agencies (principio de coordinación de las instancias públicas), this means that, for the protection of the environment, the MINAE, the Instituto Geográfico Nacional, and the Municipalidad de Golfito were required to verify the information at issue beginning in 2007, when the inconsistencies were identified, and, if necessary, immediately correct the measurements and, consequently, the land-use planning (ordenamiento territorial) under review. It is unacceptable that this situation has remained unresolved from 2007 to the present, to the point that there are now three opinions that “apparently” differ. We say “apparently” because, as noted, the results obtained must be evaluated using standardized scientific methodologies and technological resources, particularly because ACOSA’s own report acknowledges that the study was subject to the following technical limitations:
“a- No updated orthophotographic material was available to provide a more accurate demarcation of the State natural heritage areas.
b- Likewise, it was not possible to obtain the project’s topographic survey, topographic plans, or digital materials for improved data processing, resulting in georeferencing and location and demarcation problems concerning the State natural heritage areas.” Based on the foregoing, this Court finds that, as the Concejo Municipal de Golfito stated, it does not have the authority to unilaterally correct the boundaries of the State natural heritage; rather, under the legal system, that task falls in the first instance to the MINAE and the Instituto Geográfico Nacional, pursuant to the Ley Forestal, the Ley sobre Zona Marítimo Terrestre, and their respective regulations. Thus, once that matter has been resolved, and only if necessary, the Municipalidad must determine whether the challenged regulations should be corrected, as provided in Article 17 of the Ley de Planificación Urbana. As a preventive measure and to safeguard the constitutional right to a healthy and ecologically balanced environment, this Court requested a report from the Municipalidad de Golfito on these matters.
The President of the Concejo Municipal stated that, although the regulatory plan at issue has not been amended, the decision was made not to grant any concession within the areas demarcated by the Área de Conservación and that, moreover, the privately owned area adjoining the restricted-zone sector referred to by the Engineer does not form part of this partial Plan. Likewise, regarding the other matters identified in the report issued in 2013, it was reported that the gravel road within the regulatory plan that crosses polygons H1 and H2 existed before the Plan was prepared, as did the pedestrian walkway in polygon H5, which fulfills the purposes established by the Ley Orgánica del Ambiente and the Ley Forestal and was expressly noted by the ICT and the INVU when the Plan was approved. In summary, the described conflict among expert opinions (dictámenes) did not exist when the PRPPJ was approved, and the determination of which opinion is the most accurate must first be made in proceedings other than constitutional proceedings, given the scientific and technical complexity of the subject.
Nevertheless, it is equally true that this confusing situation warrants attention from the competent administrative and judicial authorities to clarify whether corrections are required and to proceed accordingly.
Regarding the criterion challenged by the petitioners, set forth in Article 1.1, entitled Development Criteria, which provides: “The regulatory plan is based on the following development criteria: (…) b) Refrain from making proposals that entail high costs for the Municipalidad de Golfito and the concession holders (concesionarios)”; this Chamber finds that it is not the provision, per se, that entails a violation of a fundamental right, but potentially its application to a specific case. Nevertheless, whether this clause has been improperly applied could validly be reviewed only in a specific factual situation and resolved through contentious-administrative proceedings (vía de lo contencioso administrativo). Thus, although the criterion, and particularly the wording used, might suggest that it encourages abuse, it is not in itself unconstitutional because its mere enactment does not necessarily violate a constitutional right, nor can it be characterized as necessarily infringing the rights contained in international treaties duly incorporated into the legal system.
It must also be borne in mind that, in any event, legislation such as the Ley de Control Interno and the Ley contra la Corrupción y el Enriquecimiento Ilícito en la Función Pública—among others—is currently in force and requires public officials to establish the corresponding controls and conduct themselves in accordance with the duty of probity (deber de probidad):
“Article 3.- Duty of probity.
Public officials shall be required to direct their administration toward serving the public interest. This duty shall be manifested primarily by identifying and addressing priority collective needs in a planned, regular, efficient, and continuous manner and under conditions of equality for the inhabitants of the Republic; likewise, by demonstrating integrity and good faith in exercising the powers conferred upon them by law; ensuring that the decisions they adopt in fulfillment of their duties conform to impartiality and to the objectives of the institution in which they serve; and, finally, by administering public resources in accordance with the principles of legality, effectiveness, economy, and efficiency, while rendering satisfactory accounts. (Ley No. 8422, del 6 de octubre de 2004) That said, verification of compliance with such oversight falls to the authorities and bodies provided for that purpose by the legal system, not to the constitutional jurisdiction. Accordingly, under the terms stated above, this Court does not find the constitutional defects alleged by the petitioners.
VII.Fourth allegation: The private company prepared the challenged Plan for commercial purposes in order to construct its docking facility or marina. The petitioners state that the minutes of the Concejo de Golfito dated 19 de enero de 2004, chapter 6, article 12, ordinary session 2, expressly established that Bahía Cocodrilo S. A. paid for the preparation of the PRPPJ. During that session, some council members denounced the fact that the plan pursued private interests: first a docking facility and then a marina. They warn that a pier, a docking facility, and especially a marina are forms of infrastructure that may lead to pollution and the destruction of marine life, the mangrove forest, and the natural and rural landscape. They therefore consider it vital that this action be granted, because a regulatory plan (plan regulador) conceived with such projects in mind must incorporate a highly detailed scientific environmental analysis assessing the impact of that infrastructure. They consider the fact that the private company prepared and paid for the regulations in question to constitute grounds for unconstitutionality, since it could benefit from them in developing its tourism projects without first obtaining an environmental impact assessment (evaluación de impacto ambiental) from SETENA, despite this being required by case law.
This Chamber finds that this allegation encompasses arguments of various kinds that the petitioners have presented together. First, it must be noted that the petitioners refer to the impacts caused by the infrastructure of the docking facility and marina granted under concession to the company by the Municipality. Those matters, however, do not fall within the subject matter of this action, because what is challenged here is the Regulatory Plan and, in any event, verification of the allegations made in that regard is not a matter for determination in these proceedings. Second, the assertion that the company is benefiting from a plan prepared and approved without the environmental component required by case law is an issue directly related to the first allegation, which has already been examined in detail. It is therefore appropriate to address what appears to be the core of this fourth allegation: the fact that the private company promoted and financed the project that culminated in the regulations in question and could benefit from them in developing its tourism projects.
In its report, the Procuraduría warns of the alleged unconstitutionality, citing for that purpose legal opinion OJ-96-2005, which provides that land-use planning (ordenamiento territorial)—whose basic instrument is spatial planning (planificación territorial)—constitutes the exercise of a public function; consequently, municipalities—and, in this case, the ICT and the INVU—may not approve regulatory plans whose preparation was arranged and financed by private-law entities, because doing so would amount to relinquishing the exercise of a public power granted by law. It adds that municipalities may enter into agreements with other public entities for the preparation of regulatory plans and that, even where such an entity receives a donation from a private-law entity for that purpose, the donation must not compromise the preparation of the respective regulatory plan, as indicated in opinion C-70-2009.
It states that arranging and financing the preparation of a regulatory plan, besides being unlawful, is unconstitutional because municipalities are required to protect and safeguard the environment in exercising their powers and authority. The exercise of this power with respect to public-domain property (bien demanial), such as the maritime-terrestrial zone (zona marítimo terrestre), also serves conservation purposes and is therefore a means of fulfilling the State’s duty to protect and safeguard the environment.
Based on the submissions made by the petitioners, the Presidente Municipal, and the intervening company (sociedad coadyuvante), this Court finds it sufficiently established that the latter, by hiring other companies, undertook the technical studies that culminated in the preparation of the plan approved by the Municipalidad, the INVU, and the ICT. It was also established that the company was subsequently granted concessions within the planned territory.
That said, it follows from the petitioners’ own allegation that they are not challenging the Municipalidad’s authority to approve a plan prepared, funded, and proposed by private parties benefiting from such planning; nor are they challenging whether private parties are constitutionally authorized to prepare, fund, and propose a regulatory plan. What they argue is that, because those parties paid for its preparation and benefited from the plan, the Plan must be deemed unconstitutional.
Certain clarifications are required in this regard. This Court notes the existence of certain provisions that may at one time have been interpreted as authorizing municipalities to request or receive assistance from other public or private parties with respect to land-use planning. Article 31 of the Ley sobre la Zona Marítimo Terrestre may be cited:
“Article 31.- All urban or tourism development plans affecting the maritime-terrestrial zone must be approved by the Instituto Nacional de Vivienda y Urbanismo and the Instituto Costarricense de Turismo, as well as by any other official agencies having legal authority to intervene for that purpose.
Only Costa Rican natural or legal persons eligible to hold concessions may participate in tourism developments within or providing access to the maritime-terrestrial zone. Foreign entities may likewise participate, provided that they are tourism companies and that more than fifty percent of their development capital belongs to Costa Ricans.” Article 62 of the Regulations to that Law provides:
“Article 62.- Concessions may not be granted for parcels on which the public zone (zona pública) has not been demarcated. For that purpose, each municipality shall demarcate the public zone along the coastline within its jurisdiction, particularly in those areas of the maritime-terrestrial zone where the construction of works or buildings is contemplated, and shall contract with the Instituto Geográfico Nacional for the studies necessary for that purpose. The Instituto shall perform the demarcation in accordance with article 2 of these Regulations, except along coastlines undergoing highly dynamic coastal formation processes, where the public zone shall be demarcated according to the boundaries established by the Instituto Geográfico Nacional based on the studies it conducts in each case.
To cover the cost of the demarcation, municipalities may charge concession holders whose parcels adjoin the public zone a fee per linear meter of frontage, calculated by dividing the cost of the demarcation by the number of linear meters covered by it.
Those interested in contracting for the demarcation of the public zone must request authorization from the respective municipality; once authorization has been obtained, they may contract with the aforementioned Instituto, and the cost shall be borne by the interested parties.” Article 61 of the Ley de Planificación Urbana provides:
“Article 61.- The municipality may contract with the Instituto or specialized private firms for the preparation of specific planning studies or projects.” Without attempting to conduct a review of the legality of those actions, which exceeds this Court’s jurisdiction, it is nevertheless clear that all opinions issued by the Procuraduría General de la República regarding the interpretation of the provisions governing this particular matter, as well as those issued by the Contraloría General de la República, postdated the issuance of this Regulatory Plan. Indeed, in official letter C-PU-D-716-2013, issued by the INVU and submitted to the Chamber, that Directorate stated that, from 7 de junio de 2006 to the present, it had determined not to approve Coastal Regulatory Plans (Planes Reguladores Costeros) prepared or financed by private companies, in compliance with legal opinion OJ-96-2005 of the Procuraduría General de la República, opinions C-234-2007 and NC-091-2010 of that same body, and official letter DFOE-SM-105-2007 of the Contraloría General de la República.
Those documents are unquestionably binding at present; however, as is clearly established, they were issued after the Municipalidad de Golfito adopted this Regulatory Plan on 16 de febrero de 2004. Accordingly, it is not for this Court to determine whether the actions of the Municipalidad de Golfito, the INVU, or the ICT in interpreting those provisions were correct, because that is a review of legality falling within the jurisdiction of the ordinary courts. The fact remains that the express and manifest prohibition concerning contributions that private parties may make, and the manner in which such contributions may be accepted for purposes of preparing land-use planning studies or proposals, was issued after the challenged regulations; consequently, a constitutional defect cannot be retroactively attributed to those regulations on that basis.
The petitioners argue that the unconstitutionality arises from the benefit received by private parties, without making clear what those benefits were or demonstrating any direct harm to “local interests and services in each canton.” Furthermore, it is also untrue that approval of this Regulatory Plan automatically entailed approval of the docking facility and marina projects in question, because there is even a special law governing that matter, the “Ley de Concesión y Operación de Marinas y Atracaderos Turísticos,” published on 6 de febrero de 1998, which regulates the relevant concession and requires a prior environmental assessment (evaluación ambiental) of the projects’ impacts. Those impacts were reviewed by SETENA and verified by the CIMAT, not by this Municipio. Accordingly, the direct relationship alleged by the petitioners cannot be established either.
Consequently, determining whether the approval of a plan prepared, funded, and proposed by private parties benefits them to the detriment of the common good—of “local interests and services in each canton”—is a matter that can only be determined by examining the plan in the particular case, which cannot be adjudicated through a constitutional challenge (acción de inconstitucionalidad) and which, given the evidence that would have to be taken in that regard, could only be adjudicated through ordinary legality proceedings (vía de legalidad ordinaria). Accordingly, this fourth claim by the petitioners, insofar as it merely asserts that the Plan is unconstitutional because it benefited the company that prepared, funded, and proposed the Plan, is insufficient to grant this action.
VIII.Fifth claim: There was never informed citizen participation (participación ciudadana) prior to municipal approval. The petitioners state that although a public hearing (audiencia pública) was held, the members of the public who attended to learn about this plan were never informed about its environmental variable (variable ambiental), because neither the institutions nor the Municipalidad de Golfito submitted the project to SETENA. It bears repeating that the omission identified by the petitioners cannot be attributed to the challenged regulations if the regulations they demand had not yet been issued at that time. At the appropriate time, the Concejo Municipal submitted the regulatory plan (Plan Regulador) project to public consultation, in accordance with Article 17 of the Ley de Planificación Urbana, No. 4240 de 15 de noviembre de 1968. Accordingly, the Municipalidad de Golfito could not have been required to hold a hearing that included the environmental variable if, at that time, SETENA had not implemented the procedures necessary for its inclusion.
However, as indicated above, the Municipality is currently required to incorporate the environmental fragility indices (índices de fragilidad ambiental), and SETENA must assess them and comply with the corresponding procedures. At that time, therefore, the right to citizen participation relating to the regulatory plan and the environmental variable at issue must be given effect; however, in this context, that does not mean that the challenged regulations are unconstitutional.
IX.Conclusion: Regarding the claims submitted by the petitioners, and following the order in which they were presented, this Chamber concludes as follows: FIRST: there are no grounds for granting the action because, when the PRPPJ was approved, neither the Regulations nor the Environmental Impact Assessment Manual (Manual de Evaluación de Impacto Ambiental) regulating Article 17 of the Ley Orgánica del Ambiente existed. SECOND: there are no grounds for finding a violation of Article 89 of the Constitution, since the technical criteria required at the time the regulations at issue were issued were available and the demarcated areas were established on that basis. THIRD: The wording of Article 1.1. subsection b) of the PRPPJ Regulations is not unconstitutional in itself. FOURTH: The petitioners assert that the mere granting of the marina concession (concesión) and other infrastructure to the company that participated in preparing the regulatory plan is harmful, but they submit no body of evidence whatsoever.
It must also be noted that adding to this claim the harm that would result from such infrastructure would entail changing the subject matter of this action, which, as stated, concerns exclusively the PRPPJ and its regulations. FIFTH: In light of what was stated regarding the first claim, the omission identified by the petitioners cannot be attributed to the challenged regulations if the regulations they demand had not yet been issued at that time. This does not preclude holding the corresponding hearing and ensuring citizen participation when the environmental variable is incorporated into the regulatory plan.
Therefore:
By majority vote, the action is denied. Justice Jinesta files a separate note and orders that, within 3 months from notification of this judgment, the State, MINAE, and its competent bodies definitively and precisely delimit the areas of the Patrimonio Natural del Estado. If there is any overlap in those areas, they must use all means permitted by the legal system to recover those lands promptly and effectively. Justice Rueda agrees that the action should be dismissed but dissents as to the scope of the operative portion (parte dispositiva), because: 1) he considers that the Municipalidad de Golfito should be ordered to incorporate the environmental variable into the Plan Parcial Regulador de Puerto Jiménez, pursuant to Article 67 of the “Reglamento General sobre los Procedimientos de Evaluación de Impacto Ambiental,” approved by Decreto Ejecutivo No. 31.849 de 24 de mayo 2004, as amended by Decreto Ejecutivo No. 34.688 de 25 de febrero de 2008, and the “Manual de Instrumentos Técnicos para el Proceso de Evaluación del Impacto Ambiental (Manual de EIA)- Parte III,” approved in Decreto Ejecutivo 32.967-MINAE de 20 de febrero de 2006; and 2) he considers that MINAE and the Instituto Geográfico Nacional should be ordered, within a maximum period of 4 years from notification of this judgment, to carry out the procedures required to demarcate precisely the boundaries of the Patrimonio Natural del Estado and, should any correction result, the Municipalidad de Golfito must amend the regulatory plan accordingly; pending such verification, and in application of the precautionary principle (principio precautorio), the Municipalidad de Golfito must maintain the decision applied to date not to grant concessions in the distinguishable areas identified by the Área de Conservación de Osa.
Justices Armijo Sancho and Cruz Castro dissent, grant the action, and annul the Plan Regulador de Puerto Jiménez, Golfito-Puntarenas, finding it contrary to the rights protected under Articles 7, 50, 89 and 169 of the Constitución Política, as well as Article 5º of the Convención para la Protección de la Flora, Fauna y de las Bellezas Escénicas Naturales de los Países de América (Ley No. 3763), Article 4º of the Convención sobre la Protección del Patrimonio Mundial, Cultural y Natural (Ley No. 5980), and Article 4º of the Convención Relativa a los Humedales de Importancia Internacional (Ley No. 7224). Justices Castillo Víquez and Cruz Castro file separate notes.
Gilbert Armijo S.
President Ernesto Jinesta L. Fernando Cruz C.
Fernando Castillo V. Paul Rueda L.
Nancy Hernández L. Luis Fdo. Salazar A.
prl / azunigag NOTE BY JUSTICE JINESTA LOBO I certainly agree with the reasoning for denying the constitutional challenge. Nevertheless, as ordered in Voto No. 3480-2003, in which I joined, given the uncertainty concerning the precise and effective delimitation of the Patrimonio Natural del Estado (e.g., mangroves, wetlands, rivers, streams, etc.), an order must be issued to the State and its competent bodies to prevent its impairment and unlawful reduction. Accordingly, in every case involving doubt or dispute, I order that, within 3 months from notification of this judgment, the State, MINAE, and its competent bodies definitively and precisely delimit the areas of the Patrimonio Natural del Estado. If there is any overlap in those areas, they must use all means permitted by the legal system to recover those lands promptly and effectively.
Ernesto Jinesta L.
Case 13-03396.
Justice Rueda agrees that the action should be dismissed but dissents as to the scope of the operative portion, because: 1) he considers that the Municipalidad de Golfito should be ordered to incorporate the environmental variable into the Plan Parcial Regulador de Puerto Jiménez, pursuant to Article 67 of the “Reglamento General sobre los Procedimientos de Evaluación de Impacto Ambiental,” approved by Decreto Ejecutivo No. 31.849 de 24 de mayo 2004, as amended by Decreto Ejecutivo No. 34.688 de 25 de febrero de 2008, and the “Manual de Instrumentos Técnicos para el Proceso de Evaluación del Impacto Ambiental (Manual de EIA)- Parte III,” approved in Decreto Ejecutivo 32.967-MINAE de 20 de febrero de 2006; and 2) he considers that MINAE and the Instituto Geográfico Nacional should be ordered, within a maximum period of 4 years from notification of this judgment, to carry out the procedures required to demarcate precisely the boundaries of the Patrimonio Natural del Estado and, should any correction result, the Municipalidad de Golfito must amend the regulatory plan accordingly; pending such verification, and in application of the precautionary principle, the Municipalidad de Golfito must maintain the decision applied to date not to grant concessions in the distinguishable areas identified by the Área de Conservación de Osa.
The undersigned notes that, although the action must be dismissed in accordance with the considerations set forth in the judgment, since the actions taken complied with the law within the regulatory framework in force when the challenged Plan was approved, the fact remains that 2 current circumstances were identified which, in view of the precautionary principle and the principle of environmental protection (principio de protección al ambiente), could not be ignored and warranted this Court issuing two specific directives:
1- The Chamber is called upon to safeguard the principle of legal certainty (principio de seguridad jurídica) and to do so without detriment to the provisions of Article 50 of the Constitution. Thus, although the SETENA Regulations had not been issued when the Plan at issue was approved, there remains a subsequent obligation to incorporate into land-use planning (ordenamiento territorial) the environmental variable required by Article 67 of the Reglamento de Evaluación de Impacto Ambiental and the corresponding Manual. For that reason, I consider that the proper course was to order the Municipalidad de Golfito to incorporate the environmental variable and submit the regulatory plan at issue to SETENA so that the corresponding compliance assessment (evaluación de conformidad) could ultimately be verified.
2- Likewise, at the public hearing held on 6 de noviembre de 2014 and in their reports, the public authorities identified inconsistencies regarding the delimitation of the Patrimonio Natural del Estado that could not be ignored. Accordingly, although certified information from the Instituto Geográfico Nacional concerning the delimitation of the mangroves was available in 2004, and it therefore cannot be alleged that the adopted land-use planning was based on manifestly arbitrary criteria, the record established, through two MINAE technical reports prepared in 2007 and 2013—which even contradict each other—that inconsistencies exist in the georeferenced measurements (medidas georeferenciadas) recorded by IGN. As indicated in the judgment, that situation did not render the challenged regulations unconstitutional, since they were prepared on the basis of the official criteria existing in 2004; however, in my view, it did warrant ordering MINAE and IGN to investigate and verify the inconsistencies subsequently identified and, if a correction were appropriate, ordering the Municipalidad de Golfito to adjust its regulations accordingly, as this Court similarly ordered in Judgment No. 2003-3480 when ruling on the constitutional challenge brought against the Plan Regulador Costero Turístico Playa Platanares:
“It is clear that the precautionary principle (principio precautorio) requires the State to adopt all measures necessary not only to punish harm to environmental assets (bienes ambientales), but also to prevent such harm from occurring. However, when imposing a particular restriction, this Chamber may not rely on uncertain information such as that contained in the case file (expediente), which, through the corresponding inquiries, could easily show that the alleged overlap does not exist in this case. Properly understood, the precautionary principle concerns the adoption of measures not when the facts giving rise to a risk are unknown, but when there is uncertainty as to whether such facts will actually produce harmful effects on the environment. In the present case, it is clear that we are faced with the first of these situations; that is, there is no certainty as to the existence of an overlap between the Plan Regulador and the Refugio de Vida Silvestre.
The situation would be different if the fact were certain but its danger to the environment were in doubt. Accordingly, the Chamber must dismiss this action of unconstitutionality (acción de inconstitucionalidad), given that neither actual harm nor an imminent risk of violation of the provisions contained in Articles 21, 50, and 89 of the Political Constitution (Constitución Política) has been established. Nevertheless, the Ministry of Environment and Energy must be ordered to conduct immediately the field test needed to determine with complete certainty whether the alleged overlap actually exists and, if so, to take immediately all measures permitted by the legal system to recover the strip of land alleged to have been encroached upon.
VIII.Conclusion. Based on the arguments set forth in the preceding paragraphs, this Chamber has concluded that the Plan Regulador Sector Costero Turístico Playa Platanares, adopted by resolution of the Consejo Municipal de Golfito at the ordinary session held on trece de marzo de mil novecientos noventa y nueve, and published in the Diario Oficial La Gaceta número 74, de diecinueve de abril de mil novecientos noventa y nueve, is not unconstitutional for the reasons invoked by the plaintiff; therefore, pursuant to artículo 87 de la Ley de la Jurisdicción Constitucional, the appropriate course is to dismiss this action of unconstitutionality in its entirety. This decision is issued without prejudice to any conclusions that the authorities of the Ministry of Environment and Energy may reach by conducting topographic surveys using a theodolite or any other suitable method, should they determine with certainty or a sufficient degree of probability that an overlap between the Plan Regulador de la Zona Costera de Playa Platanares and the Refugio Nacional de Vida Silvestre Preciosa-Platanares Categoría Mixta actually exists in this case.
To that end, the Minister of Environment and Energy is ordered to conduct, within a maximum period of tres meses from service of this judgment, the topographic surveys required to determine with certainty whether the alleged overlap actually occurs in this case. If an encroachment upon the protected area has occurred, the Minister shall employ all means permitted by the legal system to recover those lands promptly and effectively.”
Likewise, it should have been ordered that, pending such confirmation and pursuant to the precautionary principle, the Municipalidad de Golfito was required to maintain the resolution applied to date not to grant concessions in the distinguishable areas identified by the Área de Conservación de Osa.
Paul Rueda L.
Dissenting Opinion of Justices Armijo Sancho and Cruz Castro.
With the utmost respect for the members of the Constitutional Court, we, the undersigned Justices, conclude that this action should be granted and, consequently, that the Plan Regulador de Puerto Jiménez, Golfito-Puntarenas should be annulled because we consider it contrary to the rights protected under Articles 7, 50, 89, and 169 of the Political Constitution, as well as artículo 5º de la Convención para la Protección de la Flora, Fauna y de las Bellezas Escénicas Naturales de los Países de América (Ley No. 3763), artículo 4º de la Convención sobre la Protección del Patrimonio Mundial, Cultural y Natural (Ley No. 5980), and artículo 4º de la Convención Relativa a los Humedales de Importancia Internacional (Ley No. 7224), for the reasons explained below.
As is apparent from the case file, the action of unconstitutionality challenges the Plan Regulador Parcial de Puerto Jiménez Golfito-Puntarenas and the Reglamento de Zonificación. It essentially raises three arguments alleging procedural unconstitutionality (preparation by a private company, argument FOUR; failure to conduct a public consultation, argument FIVE; and failure to consider the environmental variable, argument ONE) and two arguments alleging substantive unconstitutionality (violation of the precautionary principle, argument TWO; and indeterminate criteria, argument THREE). In our view, the unconstitutionality in this case lies primarily in the preparation of the Plan Regulador by a private company and the failure to consider the environmental variable.
I—Preparation of the Plan by a private company As to this issue, the question is not, as stated in the majority opinion, whether the approved Plan benefits or harms the private company that prepared it, but whether Local Governments may validly delegate to a private party the management and/or financing of the preparation of coastal regulatory plans (planes reguladores costeros). In this regard, because the case file establishes that the Concejo Municipal de Golfito proceeded to “approve the Plan Regulador Parcial del Sector Costero de Puerto Jiménez, Golfito, promoted by Bahía Cocodrilo S.A.” (resolution adopted under artículo duodécimo, capítulo sexto, de la sesión ordinaria número 3, celebrada a las 15:30 horas del día 19 de enero del 2004), we concur with the position outlined by the Procuraduría General de la República in its report. Because land-use planning (ordenamiento territorial) constitutes the exercise of a public function, municipalities may not approve regulatory plans whose preparation has been managed and financed by private-law entities, since doing so would amount to relinquishing the exercise of a public power granted by law (artículo 28, Ley Orgánica del Ambiente –LOA- y 15 de la LPU). Thus, the management and financing of the preparation of a regulatory plan by a private party are unconstitutional.
Furthermore, the municipal authority to plan the territory and determine land use has significant effects on the environment, especially when the planning concerns public-domain property (bien demanial) such as the maritime-terrestrial zone (zona marítimo terrestre). Therefore, as the Procuraduría rightly explains, the management and financing of coastal regulatory plans by private-law entities entails relinquishing the partial exercise of a public function affecting the environment, namely land-use planning. This entails not only an unconstitutional delegation of public functions but also a failure to fulfill the duty to safeguard and protect the environment assigned to the State by Article 50.
Because of the legal nature of a regulatory plan (under artículo 1 de la Ley de Planificación Urbana, a regulatory plan is a set of plans, maps, and regulations defining development policy, land uses, thoroughfares, public utilities, community facilities, and other matters), its preparation and approval clearly fall within the authority vested in the Municipalities, which CANNOT (in the same sense established by the Chamber in votos Nº 9792-98 y Nº7965-99) delegate that authority (powers and duties) to a third party. This is especially true in this case, where, as stated above, the matter involves the duty to protect public-domain property.
The fact that the Municipality ratified the plan prepared by the private company does not cure the process. Municipalities may not approve or adopt regulatory plans whose preparation has been managed, contracted, or financed by private-law entities.
II—Exclusion of the environmental variable The fact that this Plan Regulador was approved without considering the environmental variable constitutes a clear and manifest infringement of the right to a healthy and ecologically balanced environment, as proclaimed in Article 50 of the Constitution, as well as of the principles of rational land use, informed citizen participation, precaution, non-regression in environmental matters, and forest non-reducibility (irreductibilidad del bosque), none of which may under any circumstances be disregarded by this Constitutional Court. It is clear that this regulation contradicts and overlooks the scope of the position adopted by this Constitutional Court in decisions Nos. 233-1993, 5399,1993, 1886,1995, 4587-1997 y 6322-2003, all of which predate the publication of the challenged regulatory instrument. In our judgment, the defect identified here is not amenable to any validation, as contemplated in the operative portion of this judgment by requiring the Municipalidad de Golfito to incorporate the environmental variable into the Plan Regulador.
In this regard, we consider that the appropriate course is to annul this instrument and issue a new one consistent with the principles and guidelines developed by this Constitutional Court in its case law and disregarded on this occasion. In any event, it should be noted that the decisions of this Constitutional Court are binding erga omnes and are fully effective in and of themselves, without any need for subsequent regulations to be issued to give effect to a ruling of the Chamber. Even more evident, however, is the fact that this regulation was prepared by private companies for the purpose, according to the claimants, of operating a marina or mooring facility. This defect, which was also noted by the Procuraduría General de la República in its opinion, in the terms stated supra, renders the aforementioned Plan Regulador unconstitutional. Given the significance of the environmental principles involved, the regulation of land within a canton may be prepared and developed only by Municipal Corporations within the framework of the powers arising from Article 169 of the Constitution; namely, the protection of local interests and services, which also encompasses protection of the right to a healthy and ecologically balanced environment. For the foregoing reasons, we dissent and would grant the action.
Gilbert Armijo S. Fernando Cruz C.
Justice Justice SEPARATE OPINION OF JUSTICE CASTILLO VÍQUEZ I concur in the decision and vote to dismiss this action, but I add the reasons that I shall now explain. The claimants allege as a grievance the fact that a private company financed and prepared the project that culminated in the PRPPJ; however, as has been demonstrated in the record, it was approved by the competent entities (the municipality, INVU, and ICT), and therefore this is not a case in which the urban-planning power was exercised by a private party and, consequently, the institutional guarantee (garantía institucional) was not infringed. As is well known, the concept of institutional guarantee[1] encompasses a set of activities which, given their nature, cannot be managed through organizational forms governed by private law; that is, they cannot be removed from the public sphere. Within the sphere of Public Administration itself, what has been called the constitutional reservation in favor of the Administration (reserva constitucional de la Administración)—understood broadly as reserved to the Executive Branch and the other Public Administrations possessing constitutional powers, as in the case of municipal corporations—comprises political direction, police powers, and promotional activity.
These activities, which are sovereign public functions, must necessarily be performed by an Administration as regulated by the Constitution, that is, with the attributes of its institutional guarantee. The reservation in favor of the Administration is identified with the prohibition against formal privatization—that is, resorting to the private legal system. The substantive subject matter of the reservation is what justifies the constitutional singularity of the Public Administration. There is no freedom to choose the organizational form or legal regime under which to carry out these activities belonging to the reservation in favor of the Public Administration. The flight into private law (huida al Derecho privado) by Administrations exercising sovereign public functions, or the exercise of such functions by private parties, is unconstitutional because, in the latter case, it infringes a constitutional guarantee as well as the principle that public powers may not be delegated (indelegabilidad de las potestades públicas), especially since the functions at issue here are sovereign public functions.
The situation is different for public-service activities and logistical or supply activities, which are not typically administrative—they do not fall within the reservation in favor of the Public Administration—and need not necessarily be performed by Administrations in accordance with their institutional guarantee. The Administration may choose between an administrative-law regime and a private-law regime. By contrast, the Administration’s unrestricted market activity must preferably be carried out under a private-law regime in order to safeguard competition, although this option presents several dilemmas regarding the protection of certain fundamental rights and oversight of public funds, in accordance with the principle that: “wherever public funds go, oversight must follow”; although, truthfully, in our system private law has governed the activities of a number of entities whose principal line of business is industrial, commercial, or financial, while their organization is governed by public law because they have adopted organizational forms under that body of law—autonomous institution, semi-autonomous institution, state public entity, and non-state public entity.
On this point, legal scholarship is correct in stating that: “Constitutional bodies and, in general, the other branches of the State may not resort to private law in carrying out their own exclusive functions, but they may do so in performing certain auxiliary or instrumental functions. As with the reservation in favor of the Administration, it is the exclusive powers that define the sphere in which a constitutional body is required to use public law.” (TRONCOSO REIGADA, Antonio, Privatización, Empresa Pública y Constitución, Marcial Pons, Ediciones Jurídicas y Sociales S.A., Madrid, 1997, pages 458 and 459).
Having established the foregoing, the grievance raised by the claimants has no constitutional basis, although it may have a legal and even an ethical basis. Accordingly, in cases such as these, where private parties prepared and financed the Coastal Regulatory Plan (Plan Regulador Costero) project that was ultimately approved by the Public Administrations—there are 42 cases, according to information on the ICT website—the Administrations, and especially the oversight bodies, must exercise more intensive and ongoing control, including on their own initiative, in order to determine that approval of those plans did not adversely affect (and does not adversely affect) the public interest for the sake of benefiting private interests; fortunately, this practice was prohibited on the basis of the opinions issued by the Procuraduría and the Contraloría General de la República.
In a different vein, I consider it essential to reaffirm that mangroves may not be granted under concession, not only because the regulations so provide, but also because, as is well known, they belong to the ZP and the PNE pursuant to the Law of the Constitution (Derecho de la Constitución) (values, principles, and rules), the international instruments that guarantee and protect, for the benefit of humanity, the right to a healthy and ecologically balanced environment, and the legislation in force.
Fernando Castillo V.
Note by Justice Cruz Castro:
I consider it extremely serious for a regulatory plan to be financed and prepared with private funds, particularly when the private parties have a direct interest in the plan’s contents. The Procuraduría addresses this issue very clearly when it states that preparation of a regulatory plan affecting territorial planning (planificación territorial) constitutes the exercise of a public function, which did not permit ICT and INVU to approve such regulatory plans, because that function may neither be managed nor financed by persons governed by private law, since doing so entails relinquishing the exercise of a public power conferred by law, Article 28 of the LOA and Article 15 of the LPU. Even in the case of a donation by a person governed by private law, such a donation may not condition preparation of the respective regulatory plan. The Contraloría General de la República expressed a similar opinion in its opinion C-70-2009.
It is truly extremely serious for the determination of a matter of public interest to be controlled by a private party, a situation that compromises the public purpose. It may properly be stated that private management and financing of the preparation of a regulatory plan, in addition to being illegal, is unconstitutional because it contravenes constitutional Article 50, a provision that, in addition to guaranteeing the right to a healthy and ecologically balanced environment as a fundamental right, establishes the State’s duty to protect it. Thus, that article enshrines the State’s duty to protect and safeguard the environment as a constitutional principle. Municipal entities, as territorially decentralized public administrations, are bound by that principle and are therefore required to protect and safeguard the environment when exercising their powers and authority. One of those powers is obviously territorial planning and the determination of land use (uso del suelo).
Because of its implications, this power has a significant impact on the environment and on balanced and healthy development. This is why an Environmental Impact Study (Estudio de Impacto Ambiental) is required for the preparation of one of its principal instruments: regulatory plans. The exercise of this power with respect to a public-domain asset (bien demanial) such as the ZMT—which, as this Chamber has held in its case law, also serves conservation purposes—is one way of fulfilling the State’s duty to protect and safeguard the environment (Judgment No. 2408-2007 of February 21, 2007). I consider that the management and financing of coastal regulatory plans by persons governed by private law entails partially relinquishing the exercise of a public function that affects the environment, namely territorial land-use planning (ordenamiento del territorio). This results in a failure to safeguard and protect the environment, a duty that constitutional Article 50 assigns to the State and all public authorities.
In accordance with the arguments set forth above, acting on my own initiative, I hereby bring these facts to the attention of the Fiscal General. They concern the approval of a regulatory plan prepared and financed with private funds, because I believe that the state authorities who approved it under those circumstances may have committed a breach of official duties (incumplimiento de deberes) or the offense of rendering an unlawful decision (prevaricato), since their actions not only contradict the statutory and constitutional provisions cited above, but also conflict with the positions of the Procuraduría General de la República and the Contraloría General de la República. I consider these facts extremely serious in relation to public interests as important as the environment and the exercise of public powers. For this reason, I am forwarding a copy of this judgment and the attached documents to the Ministerio Público so that the prosecuting authority may investigate and determine whether, in this case, an offense against the duties of public office may have occurred.
Fernando Cruz C.
Revisión del Documento Res. Nº 2014-19776 SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las diez horas treinta minutos del tres de diciembre de dos mil catorce.
Acción de inconstitucionalidad promovida por Manuel Ramón Ramírez Umaña, cédula 2-335-746, en su condición de representante de Friends of the Osa S. A.; Bernardo José Aguilar González, cédula 1-566-270, en su condición de representante de la Fundación Geotrópica; Laura Robleto Villalobos, cédula 6-343-627; Héctor González Pacheco, cédula 1-599-966 y Jorge Lobo Segura, cédula 1-526-636; para que se declare inconstitucional el PLAN REGULADOR DE PUERTO JMÉNEZ, GOLFITO-PUNTARENAS, por estimarlo contrario a los artículos 7, 50, 89 y 169 de la Constitución Política, así como del artículo 5 de la Convención para la Protección de la Flora, Fauna y de las Bellezas Escénicas Naturales de los Países de América (Ley No. 3763), el artículo 4 de la Convención sobre la Protección del Patrimonio Mundial, Cultural y Natural (Ley No. 5980) y del artículo 4 de la Convención Relativa a los Humedales de Importancia Internacional (Ley No. 7224). Intervino también en el proceso la Procuraduría General de la República.
Resultando:
artículo 1.1 titulado Criterios de Desarrollo establece: “El Plan Regulador se basa en los siguientes criterios de desarrollo: a) Aplicar las normas de la Ley 6043 y su Reglamento. b) No incurrir en propuestas que impliquen costos altos para la Municipalidad de Golfito y de los concesionarios”. Al respecto indican, que esto refleja que el plan se dispuso a partir de que el ahorro de gastos de los futuros concesionarios era importantísimo y consideran que eso es inmoral y poco cristalino, sobre todo si se advierte que fue elaborado por la empresa privada que se beneficiaría de las concesiones. Estiman que es preocupante que todo un instrumento de planificación territorial que debería contemplar criterios de gestión ambiental y legal establezca ese tipo de parámetros económicos, primando lo monetario sobre el derecho a la salud y a disfrutar de un ambiente ecológicamente equilibrado. Dicen que por eso debe acogerse la presente acción, pues lo anterior viola no solo el principio precautorio, sino el de irreductibilidad del bosque, la razonabilidad científica y la objetividad.
CUARTO: La empresa privada con fines comerciales elaboró el PRPPJ para hacer su atracadero o marina. Sostienen que tal como consta en el acta del Concejo de Golfito del 19 de enero de 2004, capítulo 6, artículo 12, de la sesión ordinaria 2, quedó expresamente dicho, que la empresa Bahía Cocodrilo S. A., pagó la elaboración del PRPPJ. En esa sesión algunos regidores denunciaron que ese plan perseguía intereses privados: primero un atracadero y luego una marina. Agregan que aportan además del acta un documento de concesión a favor de la empresa Bahía Cocodrilo S. A. donde consta que obtuvieron una concesión en el 2008 para hacer una marina en el sitio del atracadero o muelle, justamente en áreas contempladas por el PRPPJ, lo que deja claro que este plan está hecho a gusto de una empresa con fines de una marina y con intereses también hoteleros. Advierten que un muelle, un atracadero y una marina, son infraestructuras que pueden llevar a la contaminación y destrucción de la vida marina y del manglar, así como del paisaje natural y rural.
Por ello, consideran que es vital que se acoja esta acción, pues un plan regulador con tales proyectos en mente, debe incorporar un análisis científico ambiental muy detallado que valore el impacto de dichas infraestructuras. Concluyen que resulta gravoso que una empresa privada haya elaborado y pagado la normativa en cuestión, pudiendo beneficiarse del mismo para desarrollo de sus proyectos turísticos, sin contar de previo con una Evaluación de Impacto Ambiental (EIA) por parte de SETENA, a pesar de que así lo exigía la jurisprudencia. QUINTO: Nunca hubo participación ciudadana informada previa a la aprobación municipal. Al respecto aclara que si bien se dio una audiencia pública, la población que acudió a informarse sobre este plan, nunca fue informada de la variable ambiental del mismo, pues ni las instituciones ni la Municipalidad de Golfito presentaron nunca un proyecto a la SETENA.
Consideran que esa audiencia está viciada de inconstitucionalidad, tal como lo ha resuelto esta Sala de manera reiterada. Aducen que se ha incumplido el principio 10 de la Declaración de Río de 1992, el artículo 2 de la Convención de Aarhus. Transcriben, en lo conducente, las sentencias de esta Sala No. 2120-2003 y No. 18106-2009. Aducen que el artículo 6 de la Ley Orgánica del Ambiente, establece la obligación del Estado y las municipalidades de fomentar la participación en la toma decisiones y acciones tendentes a proteger y mejorar el ambiente y que en el mismo sentido, se pronuncia el artículo 5 del Código Municipal. Afirman que al carecer de tal evaluación preliminar, la comunidad no tuvo realmente la oportunidad de participar debidamente informada. Solicitan que se declare con lugar la acción, declarando inconstitucional el Plan Regulador en cuestión, y que se ordene a la Municipalidad de Golfito y la Procuraduría General de la República, que para eliminar las consecuencias de las violaciones constitucionales, inicie los procesos contenciosos para resolver lo pertinente sobre todas las concesiones otorgadas, en especial la otorgada a la empresa Bahía Cocodrilo S. A. para un atracadero y, posteriormente, para una marina.
Piden que se señale que no existen derechos adquiridos de buena fe, porque los mismos se fundamentan en violaciones constitucionales evidentes al patrimonio del Estado. Además, solicitan que se declare que el Instituto Costarricense de Turismo (ICT), el Instituto Nacional de Vivienda y Urbanismo (INVU) y la Municipalidad de Golfito han incurrido en violaciones serias a normas y principios constitucionales, al aprobar el PRPPJ y el Reglamento de Zonificación sin verificar la variable ambiental. También piden que se declare inconstitucional, que por vía reglamentaria se desproteja la biodiversidad y se autorice cambiar el uso del suelo en terrenos, que son propiedad estatal por ser bosques y humedales. Finalmente, piden que se disponga que la declaratoria de inconstitucionalidad sea retroactiva al momento de la publicación del Decreto impugnado en La Gaceta. Solicitan que se suspendan los efectos del plan y las concesiones.
Clasificación Área (Ha) Manglar 1.76 Humedal 0.91 Laguna 0.58 Bosque 1.64 Zona de Protección de Laguna 1.50 Zona de Protección de Estero 0.10 Total 6,49 Del informe SINAC-ACOSA-PNE-AD-079-2013, elaborado por el Ing. Joel García Medina, del Programa de Patrimonio Nacional del Estado se desprende, que “en el PRPPJ del Cantón de Golfito el área indicada como de uso privado se contrapone con áreas de humedal de la certificación en los polígonos H3 de 0,22 has y H4 de 0,48 has. Una vía de lastre propuesta dentro del plan regulador atraviesa dos áreas de manglar (zona pública) polígonos H1 y H2. Un paso peatonal propuesto afecta humedal polígono H5”. Concluye que de conformidad con la clasificación del patrimonio natural del Estado en el PRPPJ del cantón de Golfito existen usos que se contraponen a la certificación D-0183 del 20 de junio del 2007, áreas no sujetas a concesión municipal de conformidad con lo establecido en el artículo 73 de la Ley N° 6043.
Señala que esta Área no ha emitido ningún permiso de uso autorizando las actividades del artículo 18 de la Ley Forestal. Solicita que se consulte a la Municipalidad de Golfito si ha realizado las modificaciones al Plan Regulador, a fin de ajustarse a la certificación del patrimonio natural del Estado y en caso de que no hubiese realizado las modificaciones al plan regulador de marras, se le ordene realizar los ajustes necesarios para que se excluyan de la planificación las áreas clasificadas como patrimonio natural del Estado. La informante, aporta como prueba el oficio SINAC-ACOSA-PNE-AD-079-2013, que en lo conducente dice [esta Sala utilizará las abreviaturas, aunque en el texto original no aparezcan]:
“De acuerdo con el estudio de gabinete se puede identificar que dentro del área de uso privado del PRPPJ del Cantón de Golfito (propiedad privada), se contrapone con áreas de Humedal de la certificación, se puede indicar que dentro del área de usos privado se encuentra los humedales H3 de 22 hectáreas y el H4 de 0,48 hectáreas. Por otra parte, se observa que una vía de lastre del plan regulador atraviesa dos áreas de manglar el H1 y el H2, además un paso peatonal afecta el humedal H5, esto de acuerdo con la propuesta del plan regulador. En conclusión el PRPPJ en la lámina que se tiene en los archivos digitales se contrapone en sus usos de suelo a la certificación D-0183 dado en la Ciudad de Golfito a los veinte días del mes de junio del año dos mil siete, en acatamiento a lo dispuesto por la LF N° 7575 y al Dictamen C-297-2004 de la Procuraduría General de la República”.
También aporta el informe No. ACOSA-GMRN-071 con la certificación del patrimonio natural del Estado ACOSA-D-0183 del 20 de junio de 2007, que señala:
“3. Identificación de Áreas de Bosque Natural. Se realizó la verificación de campo de las áreas propuestas como Z PRO en las cuáles se identifican como áreas de bosque naturales en procesos de regeneración natural, los cuales tiene un área de 1.64 hectáreas. Según lo observado, predominan algunas especies como (…). Se observan doseles intermedios y en algunas áreas se encuentran en clasificación de charrales y tacotales que son áreas de amortiguamiento, tanto para el área de bosque como para estimular un desarrollo secundario a la regeneración natural predominante en el sitio. Gran parte de esta vegetación está asociada al manglar y a los humedales como la laguna encontrada en el sitio, por lo cual son asociaciones vegetales que están intrínsecamente relacionadas. Estos ecosistemas que se encuentran asociados debido a que no solo forman parte de una cobertura vegetativa de amortiguamiento sino están asociado al régimen hídrico del sitio y del mismo suelo que se compone en ese sector, por lo que la protección y permanencia de esa remanencia de vegetación es muy importante para los humedales y manglares del sitio, no hubo necesidad de realizar muestreo debido a que son áreas que están bien definidas en el sitio y está bien demarcadas según el Plan regulador propuesto. 4.
Ubicación de Áreas de Manglar. Con respecto a este tipo de ecosistema, se encuentra totalmente delimitado en el mapa propuesto en el plan regulador donde se observa que predominan especies de rizophora mangle y avicenia principalmente, influido por la salinidad de la marea, se encuentra alterado y afectado por el crecimiento urbano de la zona. En el sitio se identifica un humedal que no clasifica como manglar sino es un humedal tipo laguna costera que está asociada al manglar, es un sitio de agua dulce pero es afectado por el ingreso de mareas en el lugar y representa un hábitat importante a la vida silvestre como especies de garzas blancas, cocodrilos, aves acuáticas, y poblaciones de cangrejos y otros moluscos de la zona, por lo que se recomienda clasificarlo como laguna costera, permanece todo el año con agua. Con base al análisis del sistema de información geográfico, determinamos que dicha laguna tiene un área de 0.58 hectáreas y igualmente debe zonificarse su área de protección según lo indicado el artículo 33 de la Ley Forestal No. 7575, con 50 metros de radio en forma horizontal y que esto genera un área de protección de 1.50 hectáreas, esta área incluye las áreas de protección que están en la zonificación propuesta según puede observarse en la figura No 3 del informe. 5.
Localización de Áreas de Humedales. En este punto nos encontramos dos áreas de humedales que están asociadas al manglar y que no están zonificadas en el sitio, por lo que correspondió hacer el levantamiento de GPS, donde las cuáles se ubicaron y se delimitaron y se registraron un área de 0.91 hectáreas, esto incluye también las áreas que ellos habían clasificado como Z PRO donde realmente existe un humedal. Dichas áreas son humedales que mantienen agua en el invierno y que están cubiertas de una planta vascular de la familia ciperáceas y que, además, se observó aves acuáticas como piches y garzas en el sitio. Igualmente existen gran cantidad de nidos de cangrejos posiblemente de la especie ucca spp. El sitio se compone de un suelo arenoso y turberoso en el sitio. 6. Delimitación de las Z PRO. Debido a que el sitio tiene dos humedales hídricos como el estero pueblo viejo que está identificado en la zonificación del plan regulador con su debida Z PRO de 15 metros, no obstante la laguna costera, aunque está zonificada como área de mangle no tiene su zona de protección correspondiente de la cuál fue calculada con el Sistema de Información Geográfico con un radio de 50 metros y que ambas zonas de protección suman un área de 1.60 hectáreas, todo dentro del área de la ZR de la ZMT. 7.
Otros Datos de Campo. Uno de los aspectos limitantes de este plan regulador es su delimitación de la ZR o sea la franja de los 150 metros, según en la propuesta presentada está delimitación no es correcta ya que se hace el delineamiento con base a los mojones de la ZP de los 50 metros y no se toman en cuenta, los mojones de las áreas de manglar por lo que según lo indicado en el artículo 11 de la ley 6043 dice lo siguiente: “ZP es también, sea cual fuere su extensión, la ocupada por todos los manglares de los litorales continentales o insulares v esteros del territorio nacional”, por lo que la verdadera delimitación debe realizarse a partir también de los mojones que delimitan el manglar, por lo que el área restringida queda delimitada con la información de GPS y el análisis del Sistema de información, es más amplia y se puede observar en la figura # 4, de la cual corresponde un área 23.55 hectáreas, casi totalmente, abarca toda el área del PRPPJ, situación que debe corregirse al respecto.
En el sitio se identificaron varias edificaciones en zona pública tres de ellas en el hotel Parrot Bay entre los mojones 921-922-923. También fue observada y ubicada una casa en el mojón 941 que se encuentra en zona pública y que está a nombre de Brisa de la Bahía S A y quién es habitada por el Sr. Carlos Luis Villegas García. 8. Zonificación de PNE. Con base a la inspección de campo, el levantamiento de GPS y el análisis con el sistema de información geográfico pudimos delimitar humedales, bosques y zonas de protección siguiendo la metodología recomendada por la Resolución SINAC-013-2006, donde se estableció 6 tipos de categorías de humedales, 3 áreas con coberturas boscosas y 4 áreas bajo el régimen de protección de una laguna y estero. En total tenemos 4.89 hectáreas que son PNE y que se encuentran en la zona marítima terrestre en el PRPPJ y pueden observarse su delimitación y datos de clasificación y de coberturas en la figura No 3 y en la tabla 1 de este estudio.
También se zonificó (sic) las áreas de protección de la laguna costera y parte del estero que abarcan un área de 1.60 hectáreas, estas zonas deben mantener bajo este régimen aunque no son de administración del MINAE, pero deben respetarse según lo indicado en el artículo 33 y 34 de la ley forestal 7575. No se identificaron áreas de aptitud forestal clase VII y VIII en el PRPPJ. (…). Conclusiones. Con base a los resultados obtenidos hemos determinados las siguientes conclusiones: 1. El área de PNE identificado y cuantificado en el PRPPJ, es de una extensión de 4.89 hectáreas y corresponden a áreas de bosque, humedales, lagunas y manglares con base en la resolución R-SINAC-013-2006. 2. Las áreas de protección que no clasifican como PNE, pero deben estar contempladas en la zonificación de uso del Plan Regulador corresponden a un área de 1.60 hectáreas. 3. Existe problema en la delimitación de la ZR en el PRPPJ por lo que debe rectificarse dicha área que forma parte de la ZMT. 4.
En el sitio se identificaron varias edificaciones en zona pública tres de ellas en el hotel Panot Bay entre los mojones 921-922-923, también fue observada y ubicada una casa en el mojón 941 que se encuentra en zona pública y que está a nombre de Brisa de la Bahía S.A. y que es habitada por el Sr. Carlos Luís Villegas García. (…) Certifica: Que los mapas, cuadros y archivos digitales adjuntos, debidamente identificados, corresponden a la clasificación de los terrenos del PNE en la ZMT de acuerdo con la Propuesta del PRPPJ-Golfito. Que de acuerdo con informe se recomienda: Primero. Proceder a la certificación correspondiente a la Municipalidad de Osa y al ICT que en el PRPPJ donde existen 1.76 hectáreas en áreas de manglar, también que hay 0.91 hectáreas que corresponde a solo áreas de humedal, que existen 0.58 hectáreas que representan ser una laguna costera y que se identificaron 1.64 hectáreas de áreas de bosque natural y secundario según lo indicado en el artículo 3 de la LF No. 7575, que todas estas áreas forman parte del PNE y que quedan debidamente identificados, georeferenciadas y cuantificados en el siguiente cuadro (…) Segundo. Igualmente lo certificamos que no se identificaron áreas de aptitud forestal clase VII y VIII en el plan regulador de Puerto Jiménez”.
Redacta el Magistrado Rueda Leal ; y,
Considerando:
I.Sobre los presupuestos formales de admisibilidad de la acción. La acción de inconstitucionalidad es un proceso con determinadas formalidades, que deben ser satisfechas a efectos de que la Sala pueda válidamente conocer el fondo de la impugnación. En ese sentido, el artículo 75 de la Ley de la Jurisdicción Constitucional, establece los presupuestos de admisibilidad de la acción de inconstitucionalidad. En un primer término, se exige la existencia de un asunto previo pendiente de resolver, sea en vía judicial, o bien, en el procedimiento para agotar de la vía administrativa, en que se haya invocado la inconstitucionalidad como medio razonable para amparar el derecho o interés que se considera lesionado. En el párrafo segundo y tercero, la ley establece de manera excepcional, presupuestos en los que no se exige el asunto previo, cuando por la naturaleza del asunto, no exista una lesión individual y directa, o se trate de la defensa de intereses difusos o colectivos, o bien cuando es formulada en forma directa por el Contralor General de la República, el Procurador General de la República, el Fiscal General de la República y el Defensor de los Habitantes.
Ahora bien, en cuanto a la necesidad de un asunto previo pendiente de resolver en sede administrativa, es necesario, que este trate del procedimiento que agota la vía administrativa, el cual, de conformidad con el artículo 126 de la Ley General de la Administración Pública, se da a partir del momento en que se interponen los recursos ordinarios ante el superior jerarca del órgano que dictó el acto final, pues de lo contrario la acción resultaría inadmisible. En igual sentido, este Tribunal ha sostenido lo siguiente:
“IV.- A mayor abundamiento, del recurso que planteara -individualmente, se insiste- el señor Barquero Ramírez, se observa con claridad que éste tan solo solicitó la “revisión” y “revocatoria” del acuerdo impugnado. No interpuso concomitantemente el recurso de apelación para ante el superior respectivo. Puesto que, conforme al artículo 126 de la Ley General de la Administración Pública, la vía administrativa la agota en las entidades descentralizadas su correspondiente jerarca; y siendo potestativo plantear la apelación además de la revocatoria (artículo 347.2 ibidem), no es dable entender que en este caso se haya pedido la intervención del jerarca administrativo, tal que pueda venir a dictarse una resolución que tenga la consecuencia de provocar el agotamiento de la vía. Esto, a su vez, refuerza la convicción de que el procedimiento que se aduce como base de esta acción no es idóneo para tal efecto, lo cual obliga a desestimarla ad portas, como en efecto se hace.” (Sentencia 2005-16829 de las 09:17 horas del 2 de diciembre del 2005).
Asimismo, existen otras formalidades que deben ser cumplidas, a saber, la determinación concreta de las normas y principios constitucionales que se consideren infringidos, la autenticación por abogado del escrito en el que se plantea la acción, la acreditación de las condiciones de legitimación (poderes y certificaciones), así como la certificación literal del escrito en el que se invocó la inconstitucionalidad de las normas en el asunto base, requisitos todos que en caso de no ser aportadas por los accionantes, pueden ser prevenidos para su cumplimiento por la Presidencia de la Sala.
II.La legitimación y admisibilidad de esta acción de inconstitucionalidad. Los accionantes impugnan el Plan Regulador Parcial de Puerto Jiménez Golfito-Puntarenas y el Reglamento de Zonificación, aduciendo que lo hacen en defensa de un interés difuso: la protección del ambiente garantizado en el artículo 50 de la Constitución Política. En efecto, el párrafo segundo del artículo 75 de la Ley de la Jurisdicción Constitucional, contempla esta excepción a las reglas generales de admisibilidad de las acciones, que señalan como requisito la existencia de un caso pendiente de resolver en la vía judicial o administrativa. Respecto de la noción de interés difuso, en la sentencia No. 1993-3750, de las 15:00 del 30 de julio de 1993, este Tribunal indicó lo siguiente:
“… Los intereses difusos, aunque de difícil definición y más difícil identificación, no pueden ser en nuestra ley -como ya lo ha dicho esta Sala- los intereses meramente colectivos; ni tan difusos que su titularidad se confunda con la de la comunidad nacional como un todo, ni tan concretos que frente a ellos resulten identificados o fácilmente identificables personas determinadas, o grupos personalizados, cuya legitimación derivaría, no de los intereses difusos, sino de los corporativos que atañen a una comunidad en su conjunto. Se trata entonces de intereses individuales, pero a la vez, diluidos en conjuntos más o menos extensos y amorfos de personas que comparten un interés y, por ende reciben un perjuicio, actual o potencial, más o menos igual para todos, por lo que con acierto se dice que se trata de intereses iguales de los conjuntos que se encuentran en determinadas circunstancias y, a la vez, de cada una de ellas.
Es decir, los intereses difusos participan de una doble naturaleza, ya que son a la vez colectivos -por ser comunes a una generalidad- e individuales, por lo que pueden ser reclamados en tal carácter” Según la jurisprudencia de esta Sala, existen intereses difusos cuando está de por medio la protección del ambiente, el patrimonio cultural, la defensa de la integridad territorial del país y del buen manejo del gasto público, entre otros. En el caso que nos ocupa, los accionantes aducen la lesión al derecho fundamental a un ambiente sano y ecológicamente equilibrado, al ponerse en riesgo la diversidad y el paisaje natural, y la violación de varios principios de índole ambiental. Por lo anterior, resulta procedente conocer la acción por el fondo.
Ahora bien, aun cuando los accionantes se encuentran debidamente legitimados, ello no los exime del cumplimiento de los requisitos que debe reunir la interposición de un proceso de constitucionalidad. Como bien advierte la Procuraduría General de la República, los gestionantes invocan como lesionados los artículos 7, 50, 89 y 169 de la Constitución Política, artículo 5 y los siguientes y concordantes de la Convención para la Protección de la Flora, Fauna y de las Bellezas Escénicas Naturales de los Países de América (Ley No. 3763), el artículo 4 y los siguientes y concordantes de la Convención sobre la Protección del Patrimonio Mundial, Cultural y Natural (Ley No. 5980) y del artículo 4 y los siguientes y concordantes de la Convención Relativa a los Humedales de Importancia Internacional (Ley No. 7224). Sin embargo, no motivaron la lesión de los artículos 7 y 169 constitucionales. Dado lo anterior, no corresponde a este Tribunal suplir dicha falta de los accionantes y, por ello, respecto de tales normas se omitirá todo pronunciamiento, aunque igualmente se atenderán los motivos de inconstitucionalidad señalados, con fundamento en las demás artículos constitucionales invocados debidamente fundamentados.
III.Las coadyuvancias. El artículo 83 de la LJC establece que en el plazo de 15 días posteriores a la primera publicación del edicto a que se refiere el párrafo segundo del artículo 81, las partes que figuren en los asuntos pendientes a la fecha de la interposición de la acción, o aquellos con interés legítimo, podrán apersonarse a fin de coadyuvar en las alegaciones que pudieren justificar su procedencia o improcedencia, o para ampliar, en su caso, los motivos de inconstitucionalidad en relación con el asunto que les interesa. En la especie, mediante resolución de las 8:39 horas del 21 mayo de 2013, esta Sala aceptó las coadyuvancias planteadas por los representantes de la Cámara de Turismo de Corcovado, de la Junta Directiva de la Asociación de Desarrollo Integral de Puerto Jiménez y de la Sociedad Bahía Cocodrilo S.A. En el escrito presentado a las 14:59 horas del 21 de mayo de 2013, y adjunto a este expediente por resolución de desglose de este Tribunal No. 2013-7263 de las 9:05 horas del 31 de mayo de 2013, los Fiscales de la Asociación de Desarrollo Integral de Puerto Jiménez manifiestan que la carta remitida por el Presidente, el Vicepresidente y un Vocal de dicha Asociación fue irregular por no contar con el acuerdo de la Junta Directiva, por lo que solicitan que tal gestión sea ignorada.
En virtud de lo anterior y dado que en el sub examine, estamos frente a una discusión en que la legitimación para su cuestionamiento deriva de la existencia de intereses difusos por tratarse del derecho al ambiente, procede acoger la gestión planteada por Walter Aguirre Aguirre, Estarlin Marín Hidalgo y Luz Marina Sibar Sibar como coadyuvantes mas no en su condición de representantes de dicha organización, sino únicamente a título personal como interesados en la resolución de este asunto en virtud del interés difuso por la protección al ambiente. Resuelto lo concerniente a las solicitudes de coadyuvancia planteadas, se procede a resolver este asunto por el fondo.
IV.Objeto de la acción. Los accionantes impugnan el PRPPJ y su respectivo Reglamento de zonificación publicado en La Gaceta del jueves 1 de abril de 2004, No. 65, por estimarlo contrario a los artículos 50 y 89 de la Constitución Política, así como del artículo 5 y los siguientes y concordantes de la Convención para la Protección de la Flora, Fauna y de las Bellezas Escénicas Naturales de los Países de América (Ley No. 3763); artículo 4 y los siguientes y concordantes, de la Convención sobre la Protección del Patrimonio Mundial, Cultural y Natural (Ley No. 5980) y del artículo 4 y los siguientes y concordantes, de la Convención Relativa a los Humedales de Importancia Internacional especialmente como Hábitat de Aves Acuáticas (Ley No. 7224). El texto del Reglamento del dicho Plan impugnado dispone lo siguiente:
“REGLAMENTO PLAN REGULADOR PARCIAL DE PUERTO JIMÉNEZ GOLFITO-PUNTARENAS El Plan Regulador Parcial de Puerto Jiménez es una síntesis de todo un proceso de investigación y análisis social, económico, ambiental, geográfico y ambiental del área a fin de plantear un ordenamiento regulado en beneficio de la comunidad local.
Este documento cuenta con la aprobación final del Instituto Costarricense de Turismo (ICT), de la Dirección de Urbanismo del Instituto Nacional de Vivienda y Urbanismo (INVU) y la Municipalidad de Golfito, cumpliendo a su vez con la Audiencia Pública en acatamiento del artículo 17 de la Ley de Planificación Urbana número 4240.
1.1 Criterios de Desarrollo El Plan Regulador se basa en los siguientes criterios de desarrollo:
1.2 Usos del Suelo Los usos del suelo son causa directa de la propuesta de utilidad recomendada del terreno en concordancia con los criterios de desarrollo expuestos.
1.3 Reglamento de Zonificación El presente Reglamento de Zonificación contiene las nuevos conceptos con el fin de regular la explotación de los usos del suelo propuestos adecuándolos a la topografía, aspectos ambientales, biológicos, culturales, entre otros.
La Municipalidad del cantón de Golfito, Puntarenas, en adelante la Municipalidad, en ejercicio de las facultades que le otorga la Ley de Planificación Urbana N° 4240 y sus reformas, y atendiendo las disposiciones de la Ley sobre la Zona Marítimo Terrestre N° 6043 y su Reglamento, la Ley Orgánica de Ambiente N° 7554, el Código Municipal N° 7794, la aprobación del Instituto Costarricense de Turismo y de la Dirección de Urbanismo del Instituto Nacional de Vivienda y Urbanismo:
PROMULGA:
El siguiente Reglamento del Plan Regulador Parcial de Puerto Jiménez, para la jurisdicción territorial turístico localizado entre las coordenadas Lamber Norte 277.77N-534.42 E, 276.31 N-540.42 E, sector delimitado por los mojones del Instituto Geográfico Nacional N° 865 al 975 en orden consecutivo, que colinda con calle pública y propiedades privadas al costado del campo de aterrizaje de Puerto Jiménez y la calle pública que va hacia Platanares.
LA MUNICIPALIDAD DE GOLFITO AVISA POR ESTE MEDIO A LA COMUNIDAD DEL CANTÓN, LA ADOPCIÓN DEL REGLAMENTO DE ZONIFICACIÓN DE PUERTO JIMÉNEZ QUE CONSTA DEL SIGUIENTE ARTICULADO.
Artículo 1º-Objetivos del Reglamento.
El presente Reglamento tiene los siguientes objetivos:
Artículo 2º-Definiciones:
Artículo 3º-Normas generales a) Para los efectos de este Reglamento, el sector Parcial Costero de Puerto Jiménez se propone las siguientes zonas, según la siguiente tabla:
Porcentaje Zonas propuestas Área (Ha) (%) Zona de Protección 2.9384 29,58 Zona Comercial 0.2648 2,67 Zona de Alojamiento Turístico 6.1479 61,89 Zona de Servicios Básicos 0.0706 0,71 Vialidad 0.5114 5,15 Total 9 9331 100 b) Todas las cercas de las parcelas resultantes de la zonificación deben ajustarse a la línea de los 50 metros inalienables marcada por los mojones del IGN.
Artículo 4º-Zona Pública (ZP) a) Propósitos: Cumplir con el espíritu de la Ley 6043 y su Reglamento, en cuanto al derecho de uso público de los 50 metros medidos a partir de la pleamar ordinaria. Se debe mantener al máximo la arborización existente en la zona de la berma de la playa, que es el sector donde no llega la influencia de las mareas ordinarias, las arenas de la berma son propensas a la remoción, por lo que debe de mantenerse la vegetación que la retiene.
Artículo 5º-Zona de Protección (Z PRO).
Artículo 6º- Zona Comercial (ZC).
. Frente del lote 10 m mínimo, 30 m máximo . Retiro mínimo 3 m lateral y 5 posterior, 7m frontal . Cobertura máxima 70% del lote . Tamaño del lote 600m² mínimo, 1000 m² máximo . Altura máxima 2 pisos o 7 m. No se permiten mezanines . Además del uso comercial, se permitirá la vivienda unifamiliar del propietario.
. Parqueo dentro del lote o propiedad.
. Se deberán proyectar edificaciones técnicas con materiales y sistemas constructivos sismorresistentes según lo establece el Código Sísmico y de Cimentaciones de Costa Rica.
. Deberán respetarse las especificaciones técnicas para cimentaciones indicadas en el estudio de suelos incorporado en este Reglamento.
Artículo 7º-Zona de Alojamiento Turístico de Baja Densidad (ZAT BD) a) Propósito: Destinada a la instalación de planta turística de baja densidad, ligada a las actividades complementarias de servicios de hospedaje y alimentación de los turistas nacionales y extranjeros, además permitirá la recreación y esparcimiento de los visitantes. Los proyectos turísticos deben incorporarse al componente forestal, respetar al máximo la vegetación existente.
ü Superficie máxima del lote 15 000 m² ü Retiros lateral 3m, frontal 7, posterior 10m - Área verde 35 % mínimo -Área recreativa 10 % -Área de equipamiento comercial 0.5 % -Vías internas 15% -Ancho de caminos internos 7 m -Cobertura máxima 30% -Altura máxima 2 pisos o 7 m. No se permiten mezanines -Area mínima del lote 2000 m - Densidad máxima 60 personas por Ha.
Artículo 8º-Zona de Servicios Básicos (ZSB) a) Propósito: Destinada a brindar servicios básicos a los visitantes que no pernoctan en el área.
ü Altura máxima 1 piso ü Cobertura máxima 60 % ü Cobertura mínima, zonas verdes 20 % ü Retiros 3 m lateral y posterior, 5 m frontal ü Altura máxima de techo 3,5 m ü En caso de edificaciones con techo de paja 10 m g) Concesiones: De conformidad con lo que establece la Ley sobre la Zona Marítimo Terrestre N° 6043.
Artículo 9º-Normas Generales ü No se permiten obras de relleno.
ü No se permiten drenajes en zonas de relleno en las proximidades de la playa. ü Los drenajes de aguas pluviales deben de dirigirse a las zonas verdes. ü Se prohíbe la descarga de aguas pluviales (canalizadas o entubadas) en la playa. ü Se prohíbe el acceso de vehículos motorizados a la playa. ü No se permite la extracción de materiales de la Zona Marítimo Terrestre. ü No se permite la acumulación y almacenamiento de materiales de construcción o excavación en la Zona Pública. ü Las parcelas o lotes colindantes con el estero o manglares deben presentar el alineamiento otorgado por la Dirección de Urbanismo (INVU) antes de iniciar la construcción. ü Los sistemas individuales y colectivos de aguas negras deben presentar para su visado, el diseño y pruebas de infiltración. ü Para la construcción de pozos en áreas determinadas se debe presentar estudio que lo justifique y su aprobación correspondiente. Para las construcciones el interesado deberá presentar un proyecto de desarrollo del área en concesión, en un plazo no mayor a 10 meses después de aprobada su solicitud por parte del ICT.
El proyecto de desarrollo debe presentar lo siguiente:
ü Nombre y dirección del concesionario (persona física o jurídica). ü Nombre del proyecto (tipología indicada por el ICT). ü Nombre, firma y código incorporado al CFIA. ü Escrito en idioma español. ü Plano de catastro del área a desarrollar. ü Plano de localización de finca (colindancias, alineamientos, restricciones). ü Plano de curvas de nivel a cada 0,50 metros, indicar accesos peatonales y vehiculares. ü Plano de diseño sitio a escala 1:100. ü Secciones longitudinales y transversales del proyecto. ü Presupuesto estimado de las obras. ü Forma de financiamiento. ü Sistema de abastecimiento de agua potable y eliminación de aguas residuales, desechos sólidos. ü Memoria descriptiva del proyecto donde indique: plazos de ejecución, mercado potencial, calidad de las instalaciones, administración de personal a emplear, tarifas a cobrar, servicios por cobrar. ü Estudio de Impacto Ambiental (SETENA). ü Certificación de disponibilidad de agua potable, de acuerdo con los requisitos del Departamento de Fomento del ICT.
1.4 Reglamento de Vialidad Artículo 10.-Las restricciones de tipo natural o arborización, drenajes naturales, dan a un desarrollo limitado en cuanto a las comunicaciones viales.
. Calle existente de 7 metros lo cual se mantiene con el mismo derecho, como se indica en el plano de Vialidad.
. Acera, Cordón y caño: 1,65 m . Calzada: 3,70 m . Sendero peatonal de 6 metros:
. Cuneta y área verde: 1,50 m ambos lados . Calzada: 3,00 m . Vía Propuesta de 14 metros: de acceso principal que entra de la carretera principal hasta la Zona de Servicios Básicos, cerca del mojón N° 947, va paralela al estero.
. Acera y cuneta: 3,50 m ambos lados . Calzada: 7,00 m Contiene mapa que puede ser consultado en La Gaceta No. 65 de 1° de abril de 2004, página 33”.
Los accionantes aducen que con la publicación del PRPPJ se lesiona el derecho fundamental a un ambiente sano y ecológicamente equilibrado, al ponerse en riesgo la diversidad y el paisaje natural. Agregan que también se transgreden varios principios de índole ambiental, como el de explotación racional de la tierra, de participación ciudadana informada, precautorio, de no regresión en materia ambiental, de objetivación y de irreductibilidad del bosque. Señalan que esos principios imponen a los particulares, las municipalidades y el Estado la obligación, entre otras cosas, de hacer los estudios ambientales previos antes de emitir normativa tendiente a ordenar territorialmente un espacio, sobre todo cuando existe biodiversidad que puede ser afectada. Invocan diversas sentencias de esta Sala (sentencias Nos. 233-1993, 5399-1993, 1886-1995, 4587-1997, 6322-2003) para aducir que la tutela a un ambiente sano y ecológicamente equilibrado no debe ceder frente a consideraciones de índole económica o de empresas con intereses particulares.
Concretamente, señalan que hay cinco motivos por los que corresponde declarar con lugar esta acción. PRIMERO. La aprobación y la publicación del Plan se dio sin que se hubiese valorado la variable ambiental. SEGUNDO: Como el Plan se aprobó y publicó sin integrar la variable ambiental, se violó el artículo 89 en relación con los principios de objetivación de la tutela ambiental y el precautorio, lo que podría conllevar daños al paisaje y los diferentes ecosistemas de la zona. TERCERO: El Plan tiene criterios indeterminados como lo es el proponer la protección de un 28,58%, y estos criterios carecen de razonabilidad y justificación científica, por lo que se produce la desprotección del manglar. CUARTO: La empresa privada con fines comerciales elaboró el PRPPJ para hacer su atracadero o marina. QUINTO: Nunca hubo participación ciudadana informada previa a la aprobación municipal. De lo anterior se desprende que los accionantes impugnan el Plan y su respectivo Reglamento por razones de fondo y de procedimiento; al respecto, esta Sala procederá a analizar los alegatos en el orden en que fueron expuestos únicamente por los accionantes.
Esta precisión se hace, en virtud de que la Procuraduría General de la República, al rendir la audiencia concedida por este Tribunal de conformidad con el artículo 81 de la Ley de la Jurisdicción Constitucional, introdujo un aspecto relativo a la administración del patrimonio natural del Estado que no fue alegado por los accionantes, ni fue objeto de esta acción, según la publicación de los edictos respectivos. De manera que este Tribunal no se pronunciará con respecto a este, toda vez que resulta improcedente que por tal vía se incorporen nuevos alegatos por parte de un órgano, cuya función, en lo que a esta materia respecta, es de asesor de este Tribunal y cuyo pronunciamiento debe limitarse únicamente a los extremos alegados por los accionantes.
V.Primer alegato: El PRPPJ se aprobó sin la variable ambiental. Los accionantes afirman que la normativa impugnada careció desde su emisión de la evaluación de impacto ambiental, según lo dispuso este Tribunal en las sentencias números 2002-1220 y 2003-6322, aunque SETENA no hubiese emitido la normativa para entonces, pues consideran que tal omisión lesiona el principio de objetivación y no regresión en materia ambiental. Refieren, además, que no se debe confundir tal análisis con el estudio de impacto ambiental que deberá tener cada proyecto de infraestructura que se autorice en la zona marítimo terrestre.
Sin pretender realizar por parte de este Tribunal un análisis de legalidad del extremo cuestionado, sí resulta atinente hacer mención del marco normativo de aquel entonces, a fin de determinar si para la adopción del Plan Regulador en cuestión se atendió este punto en particular.
Como bien indican los accionantes, este Tribunal en sentencia No. 2002-1220, dispuso que la autonomía de las municipalidades no se lesionaba con el requerimiento de que previo a la aprobación de un plan regulador, se exigiera una evaluación de impacto ambiental:
“VI.- …Estima la Sala que (…) todo plan regulador del desarrollo urbano deba contar, de previo a ser aprobado y desarrollado, con un examen del impacto ambiental desde la perspectiva que da el artículo 50 constitucional, para que el ordenamiento del suelo y sus diversos regímenes, sean compatibles con los alcances de la norma superior…”.
Todo lo contrario, estableció que tal requerimiento es conforme con lo dispuesto en el artículo 50 constitucional y el deber del Estado de tutelar el derecho constitucional a un ambiente sano y ecológicamente equilibrado:
"El artículo 50 constitucional es fuente directa del derecho de «toda persona» a un ambiente sano y ecológicamente equilibrado, lo que vincula en la tutela del medio ambiente, conceptuado en el sentido más amplio posible, a los Poderes Públicos en la aplicación de la norma protectora. Reiteradamente esta Sala ha señalado que el desarrollo de los derechos fundamentales y de las libertades públicas es reserva de ley; es por ello que en este campo, la potestad reglamentaria que la misma Constitución Política reserva al Poder Ejecutivo, es inimaginable sin la existencia de una ley. Ya se adelantó que la Ley Orgánica del Ambiente establece en el artículo 17, como desarrollo de lo que dispone el artículo 50 constitucional, la obligación de contar con un estudio de impacto ambiental para realizar actividades o proyectos que por su naturaleza puedan alterar o contaminar el medio ambiente. Como con acierto lo señala la Procuraduría en su informe, el estudio de impacto ambiental se concibe, por el legislador, como un procedimiento técnico que permite controlar una posible alteración ambiental con la consecuente afectación de los ecosistemas.
Sin duda alguna, se trata de materia técnica cuya regulación en detalle escapa la lógica del procedimiento legislativo y puede, como tesis de principio y dentro del marco legal existente, ser reglamentada por el Poder Ejecutivo. La Ley Orgánica del Ambiente señala con claridad que «... Las actividades humanas que alteren o destruyan elementos del ambiente o generen residuos, materiales tóxicos o peligrosos, requerirán de una evaluación de impacto ambiental creada en esta ley ...», lo que permite afirmar, en correcta lectura, que ninguna actividad humana que pueda alterar o contaminar el ambiente puede prescindir del referido estudio de impacto ambiental. La fórmula que el Poder Ejecutivo ha ideado para que pueda establecerse, «prima facie», si la actividad humana que se emprende puede alterar o destruir el ambiente, ha sido la presentación del formulario llamado «de Evaluación Ambiental Preliminar».
No es entonces, como lo sostiene el Tribunal Ambiental Administrativo en su informe, que el Poder Ejecutivo tenga discrecionalidad absoluta para señalar los proyectos que deben realizar el estudio de impacto ambiental, en tanto por disposición de la propia Constitución Política (art. 50) y la Ley Orgánica del Ambiente, como principio general, toda actividad humana de modificación del entorno «requerirá» el referido estudio. Es entonces la condición del proyecto o la obra la que determinará, en cada caso, si se requiere o no del estudio de impacto ambiental y no el establecimiento de condiciones arbitrarias por la vía reglamentaria. El reglamento solo debe establecer la forma en que se conocerán las condiciones del proyecto, y ello es lo que determinará la procedencia o improcedencia del estudio de impacto ambiental. Esto significa que la defensa y la preservación del derecho a un ambiente sano y ecológicamente equilibrado, conceptuado en el artículo 50 constitucional, es el derecho fundamental de toda persona y funciona como un principio general ineludible, de manera que en esta materia no es posible hacer excepciones genéricas (en materia urbanística y otros tópicos de lo que se ocupan los artículos 19 y 20) para exonerar el cumplimiento de obligaciones ambientales, pues con ello se corre el riesgo de desconstitucionalizar la garantía de respuesta estatal en defensa del ambiente.
Así las cosas, el mecanismo usado por el Decreto Ejecutivo determinando «a priori» actividades u obras que están exentas del estudio de impacto ambiental, en atención al tamaño de la obra, a la existencia de planes reguladores, al número de personas en la operación o actividad, a la cantidad de habitaciones, la calificación del proyecto(interés social) o el uso del suelo, evidencia un exceso en el ejercicio de la potestad reglamentaria que supera la remisión al artículo 17 de la Ley Orgánica del Ambiente y que vacía de contenido el derecho de los habitantes a que los Poderes Públicos ejerzan control ambiental directo –no por delegación en regencias- en la aplicación de la legislación tutelar. No se quiere decir con ello, que no pueda el Poder Ejecutivo, vía reglamentaria, determinar, con fundamento en estudios técnicos precisos que una determinada actividad o proyecto no requiera los estudios de impacto ambiental; pero ello supone que tal definición esté debidamente motivada y justificada.
Recuérdese que en el caso de exceptuar un control de rango superior (constitucional), la razonabilidad y la proporcionalidad de la circunstancia excepcional, serán revisables por el juez, sea en la vía legal ordinaria o del control de constitucionalidad. Pero al régimen general concebido por el Constituyente derivado, es inadmisible una excepción generalizada que no tiene otra motivación o fundamentación, que la existencia misma de la norma que así lo declara." (sentencia No. 2002-1220, reiterada en la sentencia No. 2003-6322) En efecto, en desarrollo de tales principios, la Ley Orgánica del Ambiente, No. 7554 del 4 de octubre de 1996, dispone en el artículo 17:
“Artículo 17.-Evaluación de Impacto Ambiental. Las actividades humanas que alteren o destruyan elementos del ambiente o generen residuos, materiales tóxicos o peligrosos, requerirán de una evaluación de impacto ambiental por parte de la Secretaría Técnica Nacional Ambiental creada en esta ley. Su aprobación previa, de parte de ese organismo, será requisito indispensable para iniciar las actividades, obras y proyectos. Las leyes y los reglamentos indicarán cuáles actividades, obras o proyectos requerirán la evaluación de impacto ambiental”.
De acuerdo con la remisión que hace esta norma respecto de cuáles actividades, obras o proyectos requerirán de la evaluación de impacto ambiental, es que SETENA se vio compelida a regular por Decreto Ejecutivo lo relativo a esta materia. Precisamente uno de los Decretos emitidos en tal sentido y que establecían cuáles proyectos debían estar sometidos a la evaluación de impacto ambiental, fue objeto de pronunciamiento por este Tribunal en la sentencia No. 2012-2002, toda vez que dicha normativa excluía de tal evaluación determinados proyectos, sin un sustento técnico:
“Así las cosas, el mecanismo usado por el Decreto Ejecutivo determinando "a priori" actividades u obras que están exentas del estudio de impacto ambiental, en atención al tamaño de la obra, a la existencia de planes reguladores, al número de personas en la operación o actividad, a la cantidad de habitaciones, la calificación del proyecto(interés social) o el uso del suelo, evidencia un exceso en el ejercicio de la potestad reglamentaria que supera la remisión al artículo 17 de la Ley Orgánica del Ambiente y que vacía de contenido el derecho de los habitantes a que los Poderes Públicos ejerzan control ambiental directo –no por delegación en regencias- en la aplicación de la legislación tutelar. No se quiere decir con ello, que no pueda el Poder Ejecutivo, vía reglamentaria, determinar, con fundamento en estudios técnicos precisos que una determinada actividad o proyecto no requiera los estudios de impacto ambiental; pero ello supone que tal definición esté debidamente motivada y justificada.
Recuérdese que en el caso de exceptuar un control de rango superior (constitucional), la razonabilidad y la proporcionalidad de la circunstancia excepcional, serán revisable por el juez, sea en la vía legal ordinaria o del control de constitucionalidad. Pero al régimen general concebido por el Constituyente derivado, es inadmisible una excepción generalizada que no tiene otra motivación o fundamentación, que la existencia misma de la norma que así lo declara.” Por lo que en esa oportunidad, se anularon los artículos 19 y 20 del Reglamento de Procedimientos de la Secretaría Técnica Nacional Ambiental, SETENA, Decreto Ejecutivo 26.228-MINAE y por conexidad el artículo 20 del Decreto Ejecutivo 25.705-MINAE. Ello trajo como consecuencia, que fuese a partir de la entrada en vigencia del Reglamento de EIA, Decreto Ejecutivo No. 31.849 de 24 de mayo 2004, que se estableciera en el artículo 67 –vigente en aquel momento-, la obligación de someter a una Evaluación Ambiental Estratégica los planes reguladores y cualquier otro instrumento de planificación del uso del suelo:
“Artículo 67.—Integración de la variable ambiental en los Planes Reguladores. Los Planes Reguladores establecidos por la Ley de Planificación Urbana y por la Ley de la Zona Marítima Terrestre, o aquellos otros planes o programas oficiales de ordenamiento del uso del suelo, como forma de planificar el desarrollo de actividades humanas potencialmente impactantes al medio, deberán cumplir el requisito de integrar la variable de impacto ambiental, la cual estará sujeta a un proceso de viabilidad ambiental por parte de la SETENA, de previo a su aprobación por las autoridades respectivas.
La SETENA, por medio de su Manual de EIA, establecerá los términos de referencia, los instrumentos y los procedimientos para que dicha variable ambiental sea integrada a los planes reguladores o planes o programas de ordenamiento del uso del suelo, aplicable, tanto a aquellos que se encuentren en elaboración o se elaborarán en el futuro, como a aquellos ya aprobados, que todavía no cuenten con la viabilidad ambiental.” Asimismo, ese Decreto dispuso en el artículo 66:
“Artículo 66.—Procedimientos e instrumentos de la EAE. La SETENA, vía Manual de la EIA, establecerá los lineamientos y procedimientos básicos para el desarrollo e implementación gradual de un sistema de Evaluación Ambiental Estratégica en el país como parte de su responsabilidad como autoridad de Evaluación de Impacto Ambiental conferido en la Ley Orgánica del Ambiente.” No obstante, tal cometido no se llevó a cabo sino hasta el 20 de febrero de 2006, en que SETENA, por Decreto Ejecutivo 32.967-MINAE, emitió el Manual de Instrumentos Técnicos para el Proceso de Evaluación del Impacto Ambiental-Parte III.
Lo expuesto es de relevancia a efectos de este estudio, toda vez que los accionantes consideran que previo a adoptar el Plan Regulador y su Reglamento impugnado, debía haberse cumplido con la evaluación ambiental en cuestión. Sin embargo, la normativa impugnada fue adoptada por el Concejo Municipal de Golfito, en sesión No. 8 del 16 de febrero de 2004 y publicado en el Diario Oficial La Gaceta No. 65, el 1 de abril de 2004. De manera que la emisión de este Plan se produjo dentro del lapso en el cual, si bien la Sala advirtió a SETENA el deber y la necesidad de incorporar la evaluación ambiental a los planes de ordenamiento territorial, lo cierto es que para el momento de emisión del PRPPJ, la reglamentación para que los municipios ejecutaran tal cometido no había sido implementada, según se sido valorada por este Tribunal en casos similares al sub examine, como acaeció con el Plan Regulador de Escazú:
“IV.- En cuanto a la violación al artículo 50 de la Constitución Política. Se desprende también de los autos que el Plan Regulador de Escazú fue aprobado por el Concejo Municipal de Escazú en la sesión extraordinaria numero 59, efectuada el diecisiete de diciembre de dos mil cuatro, Acuerdo AC-396-04, el cual se publicó el tres de febrero de dos mil cinco en el Diario Oficial La Gaceta y posteriormente se publicó una fe de erratas, que se comunicó por el mismo medio oficial el jueves diecisiete de marzo siguiente, en La Gaceta número 54… En ese contexto, a juicio de este Tribunal Constitucional no se encuentra mérito para acoger este recurso en cuanto a la Municipalidad de Escazú, en lo que atañe a este extremo, no sólo porque la omisión que se constata obedece a razones ajenas a su voluntad sino también porque, como alega la autoridad recurrida, el Plan Regulador de ese cantón puede ser revisado a posteriori por la SETENA, como deberá hacer en el caso de todos los planes reguladores vigentes desde antes de la promulgación del Reglamento del veintiocho de junio de dos mil cuatro.
Además, la anulación del Plan Regulador aprobado, según pretende la recurrente, de forma alguna representaría una mayor tutela al derecho fundamental consagrado en el artículo 50 constitucional, puesto que tal como alega el Alcalde recurrido "…el crecimiento urbano del cantón venía siendo muy apresurado y no existía una regulación uniforme adaptada a la realidad de este, lo que significa que el daño ambiental que se estaba provocando al cantón y a la comunidad escazuceña en general, era más grave sin la existencia del Plan que con su promulgación." Se tiene presente, asimismo, el contenido normativo de todo plan regulador en aspectos tan importantes como la construcción, vialidad, fraccionamiento y zonificación, en cuya regulación quedaría una laguna que, lejos de beneficiar a los pobladores del cantón de Escazú les podría acarrear perjuicios en caso de que se anulara el Plan Regulador recientemente publicado.
No obstante, como se ordena en la parte dispositiva de esta resolución, inmediatamente después de que la SETENA publique el Manual de Instrumentos Técnicos para el Proceso de Evaluación de Impacto Ambiental, debe la Municipalidad de Escazú someter el Plan Regulador objeto de este amparo al proceso de viabilidad ambiental, para que sin dilación alguna efectúe los ajustes que la SETENA determine.”(Sentencia No. 2005-9765 de las 15:37 horas del 27 de julio de 2005.)
Precedente aplicado también al caso del Plan Regulador Urbano de Pérez Zeledón, en sentencia No. 2006-11562, de las 15:30 horas del 9 de agosto de 2006, en el que este Tribunal reiteró lo siguiente:
“V.- Conclusión. En la presente acción, la resolución transcrita es enteramente atinente al caso, pues en efecto aunque el Plan Regulador Urbano de Pérez Zeledón no cuenta con la evaluación de impacto ambiental, en los términos referidos supra, es lo cierto que su declaratoria de inconstitucionalidad provocaría una desprotección del ambiente, en tanto implicaría dejar esa zona sin ordenamiento territorial. La omisión de contar con un estudio de impacto ambiental no configura, por sí mismo, una lesión al derecho a contar con un ambiente sano y ecológicamente equilibrado, tal como lo asume la accionante. La admisión del argumento mencionado, supondría presumir que todo Plan Regulador Urbano lesiona el medio ambiente, salvo que el estudio de impacto ambiental excluya tal presunción; la coherencia del argumento recién citado, resulta lógicamente inconsistente, pues esta razón la inconstitucionalidad que se propone, es infundada. Los antecedentes jurisprudenciales que se han mencionado, tampoco respaldan la tesis que expresa la accionante, por lo que procede declarar sin lugar la acción de inconstitucionalidad planteada.”(El subrayado es nuestro).
De manera que este Tribunal ha considerado, que en el retardo en que incurrió SETENA en regular los procedimientos respectivos, no podía imputarse a los municipios responsabilidad alguna y menos aún, pretender que no cumplieran con uno de sus deberes más relevantes, cual es ordenar el territorio a efectos de procurar la protección de los intereses de la salud, seguridad, comodidad y bienestar de su comunidad. Asimismo, en la elaboración y planificación de dicho Plan, las autoridades debían y deben ajustarse a otros estudios y verificar el cumplimiento de la normativa vigente. Por otro lado, tienen la obligación de integrar posteriormente la variable ambiental al Plan en cuestión. Proceso que según indicó el representante de la Municipalidad de Golfito, fue iniciado desde el 2006, en colaboración con el Programa de Investigación en Desarrollo Urbano Sostenible (ProDUS) de la Universidad de Costa Rica.
No obstante, se vio interrumpido por comunicación de la Universidad recibida en el Municipio el 23 de enero de 2013, en el que manifestó no tener los recursos para continuar con la elaboración del Plan Regulador Cantonal de Golfito y los índices de fragilidad ambiental. En consecuencia, el Concejo Municipal, por acuerdo 22 de la sesión ordinaria 03-2013 de las 16:15 horas del 23 de enero de 2013, dispuso buscar los recursos ante JUDESUR, para que el INVU y el ICT pudieran continuar con dicho trámite, aunque lo cierto es que todavía pende la inclusión de tal variable. Esta situación pone en evidencia la necesidad actual de conminar a las autoridades competentes a continuar el trámite y finalizar dicho proceso según lo dispone el ordenamiento, pero no la declaratoria de inconstitucionalidad de la normativa en cuestión y menos aún, la anulación de la misma solicitada por los accionantes, pues tal como lo ha indicado este Tribunal en situaciones similares, ello implicaría mayores perjuicios para la comunidad ante la ausencia de un ordenamiento territorial, lo que lejos de ser consecuente con el derecho consagrado en el artículo 50 constitucional, podría lesionarlo todavía más.
Tomen en cuenta los accionantes, que un Plan Regulador no autoriza en forma automática el otorgamiento de una concesión o permiso, sino que los impactos de los proyectos deben ser evaluados antes por SETENA. En consecuencia, procede desestimar la acción en cuanto a este extremo se refiere, sin dejar de advertir a la autoridad recurrida que deberá continuar con el proceso de elaboración e integración de los índices de fragilidad ambiental respectivos.
VI.Segundo y Tercer alegato: La violación al artículo 89 constitucional y la protección de los manglares. Según los promoventes, como el PRPPJ se aprobó y publicó sin integrar la variable ambiental, se violaron los principios objetivación de tutela ambiental y el precautorio, lo que podría conllevar daños al paisaje, los diferentes ecosistemas de la zona, y los manglares. Señalan que, por ello, no están claras ni justificadas las diferentes áreas del suelo (por ejemplo, el porcentaje establecido para la zona de protección en 29,58% del área); además, resulta inadmisible que la disposición reglamentaria señale que uno de los criterios de desarrollo es “no incurrir en propuestas que impliquen costos altos para la Municipalidad de Golfito y de los concesionarios”. Sobre el particular, se debe reiterar, que la omisión de la evaluación de impacto ambiental del Plan en el sub examine, no resulta imputable a la Municipalidad, por no haberse establecido por parte de SETENA en aquel momento, los procedimientos a través de los cuales se verificara su cumplimiento. Por otro lado, se enfatiza, que un Plan Regulador no autoriza automáticamente el otorgamiento de una concesión o permiso de un proyecto en particular, pues en todo caso, la condición de cada uno de ellos y su impacto en el ambiente, debe ser valorada previamente por SETENA y contar con los estudios pertinentes.
Sin duda alguna, los manglares revisten de una importancia tal, que su protección no solo deviene del artículo 50 constitucional, sino también de normas internacionales, cuyo contenido ha sido adoptado en nuestro ordenamiento jurídico y respecto del cual se ha pronunciado este Tribunal, en el siguiente sentido:
“V.- Sobre la protección a los humedales. Esta Sala se ha referido a la relevancia de estos ecosistemas y su protección, en las sentencias 2001-12817 de las 10:28 horas del 14 de diciembre del 2001 y 2007-6246 de las 19:30 horas del 8 de mayo del 2007, entre otras, señalando que los humedales son considerados como los ecosistemas más productivos del mundo. En Costa Rica, el artículo 40 de la Ley Orgánica del Ambiente los ha definido como: “Ecosistemas con dependencia de regímenes acuáticos, naturales o artificiales, permanentes o temporales, lénticos o lóticos, dulces, salobres o salados, incluyendo extensiones marinas hasta el límite posterior de fanerógamas o arrecifes, o en su ausencia, hasta seis metros de profundidad en marea baja”. Sobre la importancia de estos ecosistemas, en la resolución No. 2009-014288 de las 15:19 horas del 09 de setiembre de 2009, este Tribunal señaló:
“La importancia de los humedales no lo es sólo en función de la biodiversidad y de las que se desarrollan a escala ecológica, sino porque proveen de funciones de apoyo y productos esenciales para las comunidades humanas en el mundo en desarrollo e industrializado.
Según la doctrina y estudios científicos, el término humedales comprende una gran variedad de ecosistemas, con características muy distintas, se pueden clasificar en siete unidades paisajísticas: estuarios, costas abiertas, llanuras de inundación, pantanos de agua dulce, lagos, turberas y bosques de inundación; o en humedales de agua salada, de agua dulce o humedales artificiales. Cada uno está formado por una serie de componentes físicos, químicos y biológicos, tales como suelos, agua, especies de animales, vegetales y nutrimentos. Los procesos entre estos componentes y dentro de cada uno de ellos, permiten que el humedal desempeñe funciones, como el control de inundaciones y la protección contra tormentas, y que se generen productos, como la vida silvestre, pesquería y recursos forestales, purifican el agua y estabilizan la línea de la costa. No todas las características están presentes en cada humedal, pocos desempeñan todas las funciones de la misma manera.
Además, presentan atributos muy valiosos como la diversidad biológica y la singularidad del patrimonio cultural. Es la combinación de estas funciones, productos y atributos de los ecosistemas la que hace que los humedales sean importantes para la sociedad. Mediante el almacenamiento de las precipitaciones y la liberación uniforme de la escorrentía, los humedales pueden disminuir la embestida destructiva de las crecidas y los ríos, por lo que la conservación de los depósitos naturales puede evitar la construcción de presas y embalses. Su vegetación puede estabilizar la línea costera mediante la reducción de la energía de las olas, corrientes u otras fuerzas de erosión, al mismo tiempo que con las raíces de las plantas, sostiene los sedimentos del fondo en su lugar, lo que puede prevenir tanto la erosión de valiosas tierras agrícolas o habitadas, como el daño a la propiedad. Los humedales que remueven nutrientes, mejoran la calidad del agua y ayudan a prevenir la eutrofización, lo que puede evitar la necesidad de construir sistemas de tratamiento del agua.
Por otro lado, muchos sostienen la vida de densas poblaciones de peces, ganado o vida silvestre, que se alimentan de sus aguas ricas en nutrientes o de su sustrato, o bien comen en sus exuberantes pastizales. Los ciclos hidrológicos, de nutrientes y de materia, y los flujos de energía de los humedales, pueden estabilizar las condiciones climáticas locales, en particular, las precipitaciones y las temperaturas, lo que influye tanto en las actividades agrícolas como en aquellas basadas en los recursos naturales, como en la estabilidad de los ecosistemas naturales y en el mismo humedal. Coadyuvan además en la recreación, pesquerías, recurso agrícola y el turismo, así como en el aprovechamiento directo de los recursos forestales que generan en un importante número de bienes, que van desde leña, madera para la construcción y corteza, entre los productos maderables, hasta resinas y medicinas, que son productos forestales “secundarios´ no maderables.
Son incluso importantes como reserva genética de ciertas especies vegetales -como el arroz-.” Varios instrumentos internacionales, entre los que destaca la Convención sobre los Humedales o Convención de Ramsar, suscrita por nuestro país según Ley No. 7224 el 9 de abril de 1991 y publicada en La Gaceta el 8 de mayo de ese mismo año, se ocupan de su protección. En la Convención de Ramsar, el humedal es definido como: “Extensiones de marismas, pantanos, turberas o aguas de régimen natural o artificial, permanentes o temporales, estancadas o corrientes, dulces, salobres o saladas, incluyendo las extensiones de agua marina cuya profundidad en marea baja no exceda de seis metros”. La Convención proclama el deber de los Estados de proteger -en aras no solamente de sus propios intereses, sino de intereses internacionales- estos ecosistemas, por lo que los países tienen la obligación de desarrollar políticas nacionales tendentes a la conservación de estos ambientes en sus políticas del uso de la tierra.
En cuanto a las obligaciones adquiridas por los países signatarios, que son de diversa índole, se encuentra la designación de al menos un humedal de importancia internacional para ser incluido en la Lista de Sitios Ramsar, cuya selección deberá basarse en su interés internacional desde el punto de vista ecológico, botánico, zoológico, limnológico o hidrológico, por lo que es un compromiso referido a la protección de sitios específicos (artículo 2). Además, se adquieren obligaciones no relacionadas con sitios específicos, como elaborar y aplicar sus planes de gestión de forma que favorezcan el uso racional de los humedales de su territorio (artículo 3). También se obliga a fomentar la conservación de las zonas húmedas y de las aves acuáticas creando reservas naturales en los humedales, estén o no inscritos en la Lista” (artículo 4). Por último, los países firmantes deben coordinar sus políticas y regulaciones relativas a la conservación de los humedales, de su flora y de su fauna (artículo 5).
Así, las partes instauran un sistema de protección de las zonas húmedas, en primer lugar a través de una lista de humedales de importancia internacional (sitios Ramsar), y en segundo lugar, procurando el uso racional de todos los humedales en su territorio. Asimismo, en los “Lineamientos para la Aplicación del Concepto de Uso Racional de la Convención”, adoptados por la Recomendación 4.10, se indica que “las disposiciones sobre el uso racional se aplican a todos los humedales y a los sistemas que los sustentan dentro del territorio de una Parte Contratante, tanto los incluidos en la Lista, como todos los demás.” Según la Secretaría de la Convención de Ramsar, la Política Nacional de Humedales debe contemplar como objetivo: “Evitar nuevas pérdidas de los humedales que aún existan y alentar la rehabilitación de los humedales del país manteniendo su integridad, conservando su diversidad genética y velando por que su disfrute y aprovechamiento económico sean sostenibles.” Y debería “abarcar todos los tipos de humedales”.
Es claro entonces que según la Convención de Ramsar, todo ecosistema que reúna las características de humedal, debe ser utilizado de forma racional y sostenible en los términos que la Convención y la Conferencia de las Partes han definido.” (ver sentencia No. 2013-7934 de las 9:05 horas del 14 de junio de 2013) En nuestro país, son áreas que forman parte de nuestro patrimonio natural del Estado y pertenecen a la zona pública. La ley sobre Zona Marítimo Terrestre, respecto de los manglares dispone:
“Artículo 11.- Zona pública es también, sea cual fuere su extensión, la ocupada por todos los manglares de los litorales continentales e insulares y esteros del territorio nacional”.
Las municipalidades administran la zona marítimo terrestre, que incluye tanto la zona pública como la zona restringida. No obstante, los manglares están excluidos de esa administración aunque se ubiquen en dichas áreas, ya que competen al MINAE, según la Ley Forestal:
“Artículo 13.- Constitución y administración El patrimonio natural del Estado estará constituido por los bosques y terrenos forestales de las reservas nacionales, de las áreas declaradas inalienables, de las fincas inscritas a su nombre y de las pertenecientes a municipalidades, instituciones autónomas y demás organismos de la Administración Pública, excepto inmuebles que garanticen operaciones crediticias con el Sistema Bancario Nacional e ingresen a formar parte de su patrimonio.
El Ministerio del Ambiente y Energía administrará el patrimonio. Cuando proceda, por medio de la Procuraduría General de la República, inscribirá los terrenos en el Registro Público de la Propiedad como fincas individualizadas de propiedad del Estado.
Las organizaciones no gubernamentales que adquieran bienes inmuebles con bosque o de aptitud forestal, con fondos provenientes de donaciones o del erario, que se hayan obtenido a nombre del Estado, deberán traspasarlos a nombre de este.” “Artículo 18.- Autorización de labores En el patrimonio natural, el Estado podrá realizar o autorizar labores de investigación, capacitación y ecoturismo, una vez aprobadas por el Ministro del Ambiente y Energía, quien definirá, cuando corresponda, la realización de evaluaciones del impacto ambiental, según lo establezca el reglamento de esta ley.” Así lo consigna el Reglamento de la Ley sobre la Zona Marítimo Terrestre, en el artículo 4 y el artículo 2 inciso 23) del Reglamento a la Ley de Conservación de Vida Silvestre:
“Artículo 4º.- De acuerdo con el decreto Nº 7210-A de 19 de julio de 1977, los manglares o bosques salados que existen en los litorales continentales o insulares y esteros del territorio nacional, y que forman parte de la zona pública en la zona marítimo terrestre, constituyen Reserva Forestal y están afectos a la Ley Forestal y a todas las disposiciones de ese decreto. Partiendo de la línea de vegetación a la orilla de los esteros y del límite de los manglares o bosques salados cuando éstos se extiendan por más de 50 metros de la pleamar ordinaria, comienza la zona restringida”.
“23) MANGLAR: Ecosistema dominado por grupos de especies vegetales pantropicales y típicamente arbóreas, arbustivas y vegetación asociada, las cuales cuentan con adaptaciones morfológicas, fisiológicas y reproductivas que permiten colonizar áreas sujetas al intercambio de mareas. El paisaje general está dominado por la presencia de bosques de diferentes especies de mangle, esteros y canales. Las concentraciones de salinidad varían según la estación climática y al aporte de aguas continentales encontrándose valores de concentración de sales desde muy bajos hasta muy altos”.
De este modo, el Patrimonio Natural del Estado es un bien jurídico, definido e individualizado en nuestro ordenamiento jurídico, cuyos terrenos que lo conforman según la legislación ambiental, no necesitan de una declaratoria de área silvestre protegida para ser objeto de protección por parte de la Administración, por cuanto su propia naturaleza define su tutela. El uso limitado de los mismos está claramente dispuesto en la ley y sus reglamentos; y sus usos están destinados básicamente a labores de investigación, capacitación y ecoturismo, previamente aprobados por el Ministerio del Ambiente y Energía, no por el municipio (ver artículo 18 de la Ley Forestal citado).
El PRPPJ impugnado en el artículo 5 dispone:
“Artículo 5º—Zona de Protección (Z PRO).
Ahora bien, dicha disposición y su delimitación en el Plan se adoptó con fundamento en los mojones certificados por el Instituto Geográfico Nacional. Asimismo, sobre tal área no procede el otorgamiento de concesión alguna y en los usos, remite a aquellos establecidos por las normas ambientales.
Con relación al porcentaje del área de la zona de protección que reclaman los accionantes, según informó el Presidente Municipal, ese 29.58% de área para protección absoluta de manglares, esteros, quebradas y ríos, no incluye el área misma del estero, quebrada o río que se está protegiendo, por lo que el área protegida es mayor. Asimismo, se reitera, la determinación de las áreas en cuestión fue resultado de los límites establecidos por el Instituto Geográfico Nacional en aquel momento. Debe tomarse en cuenta, que tal Instituto es quien realiza las publicaciones oficiales de la demarcación, con base en las cuales Catastro aprueba todos los planos. Al efecto los numerales 16 y 17 de la Ley Forestal, 13 del Reglamento de la Ley Forestal y 63 del Reglamento de la Ley sobre Zona Marítimo Terrestre que indican:
“Artículo 63.- El Instituto Geográfico Nacional deberá publicar aviso en el Diario Oficial, de cada porción de la zona marítimo terrestre en que haya demarcado la zona pública.
La Dirección General de Catastro no registrará ningún plano que no lleve el visto bueno del Instituto Geográfico Nacional en lo referente a la delimitación de la zona pública.” En igual sentido, el INVU y el ICT revisaron la normativa en cuestión, propusieron los cambios que consideraron oportunos y los aprobaron manifestando que eran acordes con las áreas demarcadas. Según quedó acreditado para este Tribunal, en el oficio PU-C-D-011-2003 del 8 de enero de 2003, emitido por el INVU, este Plan respetó el área de protección de quebradas, presentó uso de suelo, modificó la vialidad, principalmente en su acceso principal, respetó el área de protección del manglar entre otros y para ello se adjuntó la certificación del Instituto Geográfico Nacional mediante la cual se certificaron los mojones y su ubicación (ver oficio adjunto al expediente). De manera que no resulta válido indicar, que para la fecha de emisión del Plan impugnado, lo adoptado por la Municipalidad de Golfito, el INVU y el ICT careciera de criterios técnicos o de la verificación que el ordenamiento jurídico vigente -en aquella oportunidad- implicaba, pues, como se indicó en el considerando previo, la omisión de la evaluación ambiental reclamada por los accionantes, no puede atribuírsele al municipio por no existir para tal momento la normativa necesaria, a efectos de ser implementada. Por consiguiente, los extremos alegados por los accionantes en este sentido son descartados.
Ahora bien, a los autos fue traída como prueba el oficio ACOSA-D-183-2007, emitido por el Área de Conservación de Osa el 20 de julio de 2007, mediante el cual fue certificada el área de patrimonio natural del Estado identificada en el Plan Regulador de estudio, que si bien reconoce que dicha área no ha sido objeto de concesión por parte de la Municipalidad de Golfito, sí advierte las siguientes conclusiones:
“1. El área de patrimonio natural del Estado identificado y cuantificado en el Plan Regulador de Puerto Jiménez, es de una extensión de 4.89 hectáreas y corresponden a áreas de bosque, humedales, lagunas y manglares con base en la resolución R-SINAC-013-2006.
2. Las áreas de protección que no clasifican como patrimonio natural del Estado pero deben estar contempladas en la zonificación de Uso del Plan Regulador corresponden a un área de 1.60 hectáreas.
3. Existe problema en la delimitación de la zona restringida en el plan regulador de Puerto Jiménez por lo que debe rectificarse dicha área que forma parte de la zona marítimo terrestre.
4. En el sitio se identificaron varias edificaciones en zona pública tres de ellas en el hotel Parrot Bay entre los mojones 921-922-923, también fue observada y ubicada una casa en el mojón 941 que se encuentra en zona pública y que está a nombre de Brisa de la Bahía S.A. y que es habitada por el Sr. Carlos Luís Villegas García (…)” En consonancia con ello, emitió las siguientes recomendaciones:
“Primero: Proceder a la certificación correspondiente a la Municipalidad de Osa y al Instituto Costarricense de Turismo que en el Plan Regulador de Puerto Jiménez donde existen 1.76 has en áreas de manglar, 0.91 has en áreas de humedal, 0.58 has en una laguna costera y 1.64 has en áreas de bosque.
Segundo: Proceder a certificar que en el Plan Regulador de Puerto Jiménez no existen áreas de aptitud forestal clase VII y VIII según la Metodología de Capacidad de Uso del Suelo de Costa Rica.
Tercero: Notificar a la Municipalidad de Golfito y al Instituto Geográfico Nacional sobre la demarcación de la zona restringida y efectuar la correspondiente corrección sobre el límite propuesto en este plan regulador.” Asimismo, en el oficio SINAC-ACOSA-PNE-AD-079-2013, elaborado por el Ing. Joel García Medina del Programa de Patrimonio Nacional del Estado, se indica que de acuerdo con el estudio de gabinete se puede identificar dentro del área de uso privado del Plan Regulador Parcial de Puerto Jiménez del cantón de Golfito, que el área indicada como de uso privado se contrapone con áreas de humedal de la certificación en los polígonos H3 de 0,22 has y H4 de 0,48 has. Asimismo, una vía de lastre propuesta dentro del plan regulador atraviesa dos áreas de manglar (zona pública) polígonos H1 y H2, un paso peatonal propuesto afecta humedal polígono H5 y concluye que de acuerdo con los archivos digitales, el Plan se contrapone en sus usos de suelo a la certificación ACOSA D-0183 de 20 de junio de 2007.
Nótese, como el primer oficio ACOSA-D-0183 de 20 de junio de 2007, indica que la certificación de mojones emitida por el Instituto Geográfico Nacional en aquel momento era errónea y ahora, en el oficio SINAC-ACOSA-PNE-AD-079-2013, elaborado por el Programa de Patrimonio Nacional del Estado, del mismo MINAE, señala que el oficio ACOSA-D-0183 de 20 de junio de 2007, también lo es.
Lo anterior permite arribar a este Tribunal a 2 conclusiones:
1-Las tres valoraciones técnicas difieren en su resultado y arriban a conclusiones diferentes, por lo que no podría este Tribunal darle mayor crédito a una u otra, además fueron emitidas en periodos anuales diferentes y pudieron haber variado las condiciones de geomorfología de la zona, o influir, las técnicas utilizadas para llegar a esas conclusiones. Por otro lado durante la vista celebrada el pasado 6 de noviembre, el representante del Instituto Geográfico Nacional fue claro en señalar que actualmente no se ha delimitado certeramente el patrimonio natural del Estado y que a pesar de que trabajan en eso, requieren de presupuesto y años para clarificar el estudio de actualización. Así las cosas, esta jurisdicción no es la instancia competente llamada a dirimir la veracidad y tecnicidad de tales informes, sino que ello atañe a la vía de legalidad respectiva. Por ello, desde la perspectiva constitucional, no puede serle imputada a las autoridades que aprobaron el Plan Regulador en cuestión omisión alguna, al haber actuado conforme con el ordenamiento vigente en aquel momento y con la información que se contaba.
2-Ahora bien, una vez que es evidenciado por las autoridades públicas que existen inconsistencias de esa naturaleza, no se pueden dejar sin atender. Lo que implica, en atención a los principios precautorio y de coordinación de las instancias públicas, que en aras de la protección al ambiente, el MINAE, el Instituto Geográfico Nacional y la Municipalidad de Golfito estaban llamadas a verificar la información en cuestión desde el año 2007, en tanto se advierten inconsistencias, y en caso de ser necesario, proceder a rectificar las medidas inmediatamente y con ello, el ordenamiento territorial en estudio. Resulta inaceptable que desde el año 2007 a la fecha, tal situación no haya sido dilucidada, al punto que actualmente son tres los criterios que en “apariencia” difieren, y señalamos que es en “apariencia”, porque como fue indicado, deben valorarse los resultados obtenidos con metodologías científicas estándares y medios tecnológicos, ya que en el propio informe de ACOSA se advierte haber tenido las siguientes limitaciones técnicas para realizar dicho estudio:
“a- No se contó con material orthofotos actualizado para brindar una mejor delimitación de las áreas del patrimonio natural del Estado.
b- Igualmente no se pudo obtener el levantamiento topográfico del proyecto, ni planos topográficos, ni material digital para un mejor procesamiento de datos, ya que generan problemas de georeferenciación y de ubicación y delimitación de las áreas de patrimonio natural del Estado.” De lo expuesto este Tribunal constata, que en efecto, como indicó el Concejo Municipal de Golfito, no está en sus manos corregir unilateralmente los linderos del patrimonio natural del Estado, sino que es una tarea que compete en primera instancia, según el ordenamiento jurídico, al MINAE y al Instituto Geográfico Nacional, de conformidad con lo dispuesto en la Ley Forestal, la Ley sobre Zona Marítimo Terrestre y sus reglamentos respectivos. De modo que una vez definida tal situación, y solo si fuese necesario, corresponde a la Municipalidad verificar si procede rectificar o no la normativa impugnada, según lo dispone el artículo 17 de la Ley de Planificación Urbana.
Ahora, de manera preventiva y en aras de resguardar el derecho constitucional a un ambiente sano y ecológicamente equilibrado, este Tribunal solicitó informe a la Municipalidad de Golfito sobre tales extremos. El Presidente del Concejo Municipal indicó, que aun cuando no se ha modificado el Plan Regulador en cuestión, la decisión adoptada fue no conceder concesión alguna en las áreas demarcadas por el Área de Conservación y que, además, el área de propiedad privada colindante con el sector de la zona restringida, al que alude el Ingeniero, no forma parte de este Plan parcial. Asimismo, respecto de los otros extremos advertidos en el informe rendido en el año 2013, se informó que la vía de lastre que dentro del plan regulador atraviesa los polígonos H1 y H2, es una vía existente y anterior a la elaboración del Plan, al igual que el paso peatonal en el polígono H5, que cumple con los fines señalados por la Ley Orgánica del Ambiente y la Ley Forestal, y fue advertido expresamente por el ICT y el INVU al momento de su aprobación.
En resumen, la controversia de dictámenes descrita, por un lado, no se dio al momento de aprobación del PRPPJ, y, por el otro, la determinación de cuál sea el criterio más acertado, debe ser precisada previamente en una vía que no sea la constitucional, dado el grado de complejidad técnica científica de la materia. Empero, no menos cierto es que tal situación confusa amerita ser atendida por las autoridades administrativas y judiciales competentes, a fin de clarificar si se deben realizar rectificaciones y proceder de conformidad.
En relación con el criterio cuestionado por los accionantes, dispuesto en el artículo 1.1 titulado Criterios de Desarrollo que estatuye: “El Plan Regulador se basa en los siguientes criterios de desarrollo: (…) b) No incurrir en propuestas que impliquen costos altos para la Municipalidad de Golfito y de los concesionarios”; esta Sala constata que no es la norma, per se, la que implica una lesión a un derecho fundamental, sino eventualmente, su aplicación a un caso concreto. No obstante, la existencia de una indebida aplicación de esta cláusula, solo podría válidamente ser revisada en una situación fáctica concreta y ser dilucidada en la vía de lo contencioso administrativo. De manera que, aunque el criterio y, particularmente la redacción utilizada, podría sugerir la inducción a un abuso, no es en sí misma inconstitucional, porque no produce de modo necesario y por su misma promulgación una lesión a un derecho constitucional, ni puede calificarse como necesariamente vejatorio de los derechos contenidos en los tratados internacionales debidamente incorporados al ordenamiento jurídico.
No debe perderse de vista, que en todo caso existe normativa vigente como la Ley de Control Interno y la Ley contra la Corrupción y el Enriquecimiento Ilícito en la Función Pública -entre otras-, que conminan al funcionario público a establecer los controles respectivos y ajustar su actuación al deber de probidad:
“Artículo 3.- Deber de probidad.
El funcionario público estará obligado a orientar su gestión a la satisfacción del interés público. Este deber se manifestará, fundamentalmente, al identificar y atender las necesidades colectivas prioritarias, de manera planificada, regular, eficiente, continua y en condiciones de igualdad para los habitantes de la República; asimismo, al demostrar rectitud y buena fe en el ejercicio de las potestades que le confiere la ley; asegurarse de que las decisiones que adopte en cumplimiento de sus atribuciones se ajustan a la imparcialidad y a los objetivos propios de la institución en la que se desempeña y, finalmente, al administrar los recursos públicos con apego a los principios de legalidad, eficacia, economía y eficiencia, rindiendo cuentas satisfactoriamente. (Ley No. 8422, del 6 de octubre de 2004) Ahora bien, la verificación del cumplimiento de dicho control es propio de las autoridades e instancias que el ordenamiento jurídico prevé para tal efecto, pero no de la jurisdicción constitucional. Así las cosas, en los términos indicados anteriormente, este Tribunal no advierte los vicios de constitucionalidad señalados por los accionantes.
VII.Cuarto alegato: La empresa privada, con fines comerciales, elaboró el Plan impugnado para hacer su atracadero o marina. Los accionantes señalan que en el acta del Concejo de Golfito del 19 de enero de 2004, capítulo 6, artículo 12, de la sesión ordinaria 2, quedó expresamente claro que la empresa Bahía Cocodrilo S. A. pagó la elaboración del PRPPJ. En esa sesión, algunos regidores denunciaron que ese plan perseguía intereses privados: primero un atracadero y luego una marina. Advierten que un muelle, un atracadero y más todavía una marina son infraestructuras que pueden llevar a la contaminación y destrucción de la vida marina, el manglar, el paisaje natural y el rural. Por ello, consideran vital que se acoja esta acción, pues un plan regulador con tales proyectos en mente, debe incorporar un análisis científico ambiental muy detallado, que valore el impacto de dichas infraestructuras. Consideran motivo de inconstitucionalidad el hecho de que la empresa privada haya elaborado y pagado la normativa en cuestión, pudiendo beneficiarse de la misma para el desarrollo de sus proyectos turísticos, sin contar de previo con una evaluación de impacto ambiental por parte de SETENA, a pesar de que así lo exige la jurisprudencia.
Esta Sala verifica que este alegato entraña argumentos de diversa índole que los accionantes presentan unidos. En primer término, se debe advertir que los gestionantes hacen referencia a los impactos ocasionados por la infraestructura del atracadero y la marina concesionados a la empresa por parte del Municipio. Sin embargo, estos extremos no corresponden al objeto de esta acción, ya que lo aquí impugnado es el Plan Regulador y, en todo caso, la verificación de lo acusado en ese sentido, no es propia de conocimiento en esta vía. En segundo lugar, el que se afirme que dicha empresa se está beneficiando de un plan que se elaboró y aprobó sin la variable ambiental exigida por la jurisprudencia, es un aspecto que tiene directa relación con el primer alegato ya examinado con detalle. Corresponde entonces hacer referencia a lo que parece ser el núcleo de este cuarto alegato, el hecho de que la empresa privada haya promovido y financiado el proyecto que culminó con la normativa en cuestión, pudiendo beneficiarse del mismo para el desarrollo de sus proyectos turísticos.
En su informe, la Procuraduría advierte la inconstitucionalidad señalada, invocando para tal efecto la opinión jurídica OJ-96-2005, que dispone que el ordenamiento territorial –cuyo instrumento básico es la planificación territorial– es el ejercicio de una función pública, por lo que las municipalidades –y para el caso, el ICT y el INVU– no pueden aprobar planes reguladores cuya elaboración haya sido gestionada y financiada por sujetos de derecho privado, pues con ello estarían renunciando al ejercicio de una potestad pública otorgada por ley. Agrega que las municipalidades pueden convenir con otros entes públicos la elaboración de planes reguladores y que incluso en el caso de que tal ente recibiera una donación por parte de un sujeto de derecho privado para tales efectos, esta donación no debe comprometer la elaboración del plan regulador respectivo, según lo indica el dictamen C-70-2009. Manifiesta que la gestión y el financiamiento de la elaboración de un plan regulador, aparte de ser ilegal, es inconstitucional, porque las municipalidades están obligadas a proteger y tutelar el ambiente en el ejercicio de sus potestades y competencias. El ejercicio de esta potestad respecto de un bien demanial como la zona marítimo terrestre, también tiene fines conservacionistas, por lo que es una forma de ejercer el deber estatal de protección y tutela del ambiente.
A tenor de lo aportado por los accionantes, el Presidente Municipal y la sociedad coadyuvante, este Tribunal tiene por suficientemente demostrado que esta se ocupó, mediante la contratación de otras empresas, de los estudios técnicos que concluyeron con la elaboración del plan aprobado por la Municipalidad, el INVU y el ICT. También se tuvo por demostrado, que en efecto, a dicha empresa se le han otorgado posteriormente concesiones en el territorio planificado.
Ahora bien, del propio alegato de los accionantes se desprende, que no están poniendo en entredicho la competencia de la Municipalidad para aprobar el plan elaborado, costeado y propuesto por los sujetos privados que se beneficien de tal planificación; tampoco si los sujetos privados están constitucionalmente habilitados para elaborar, costear, y proponer un plan regulador. Lo que aducen es que en razón de que ellos pagaron esa elaboración y de que tal plan les benefició, se debe entender que el Plan es inconstitucional.
Al respecto, se deben hacer algunas precisiones. Este Tribunal advierte la existencia de algunas normas, que pudieron haber sido interpretadas en algún momento como habilitantes para que los municipios solicitaran o recibieran colaboración por parte de otros sujetos públicos o particulares, respecto del ordenamiento territorial. Podría citarse, el artículo 31 de la Ley sobre la Zona Marítimo Terrestre:
“Artículo 31.- Todos los planos de desarrollos urbanos o turísticos que afecten la zona marítimo terrestre deberán ser aprobados por el Instituto Nacional de Vivienda y Urbanismo y el Instituto Costarricense de Turismo, así como por los demás organismos oficiales que tuvieren competencia para intervenir al efecto, de acuerdo con la ley.
Solamente podrán intervenir en desarrollos turísticos en la zona marítimo terrestre o con acceso a ella, personas físicas o jurídicas costarricenses que puedan tener concesiones. Igualmente podrán intervenir entidades extranjeras siempre que se trate de empresas turísticas, cuyo capital para el desarrollo pertenezca en más de un cincuenta por ciento a costarricenses.” El Reglamento de esa Ley, en el artículo 62 dispone:
“Artículo 62.- No se podrán otorgar concesiones en lotes donde no esté demarcada la zona pública. A tal efecto, cada municipalidad demarcará la zona pública a lo largo del litoral de su jurisdicción y en especial en aquellas áreas de la zona marítimo terrestre en que se contemple la construcción de obras o edificaciones, debiendo contratar los estudios necesarios para este fin con el Instituto Geográfico Nacional, el cual demarcará de acuerdo con lo establecido en el artículo 2 de este reglamento, salvo en los litorales que presenten procesos formadores de costas muy dinámicos, en los que se demarcará la zona pública según las delimitaciones que fija el Instituto Geográfico Nacional de conformidad con los estudios que realice en cada caso.
Para cubrir el costo de la demarcación, las municipalidades podrán cobrar a los concesionarios cuyos lotes colinden con la zona pública una tasa por metro lineal de frente, la cual se calculará dividiendo el costo de la demarcación entre el número de metros lineales que abarque la misma.
Quienes tengan interés para contratar la demarcación de la zona pública, deberán solicitar autorización a la municipalidad respectiva; una vez obtenida podrán contratarla con el citado Instituto y el costo correrá por cuenta de los interesados.” La Ley de Planificación Urbana, en el artículo 61 indica:
“Artículo 61.- La municipalidad podrá contratar la confección de determinados estudios o proyectos de planificación, con el Instituto o firmas particulares especializadas.” Sin pretender realizar un estudio sobre la legalidad de las actuaciones, lo cual excede la competencia de este Tribunal, lo que sí queda patente es que todos los pronunciamientos de la Procuraduría General de la República respecto de la interpretación de las normas sobre este tema en particular y de la Contraloría General de la República, fueron emitidos con posterioridad a la emisión de este Plan Regulador. De hecho, en el oficio C-PU-D-716-2013, emitido por el INVU y aportado a la Sala, esa Dirección señaló que se había dispuesto desde el 7 de junio de 2006 a la fecha, no aprobar Planes Reguladores Costeros que hubieran sido elaborados o financiados por empresas privadas, en acatamiento de la opinión jurídica OJ-96-2005 de la Procuraduría General de la República, el dictamen C-234-2007 y NC-091-2010 de ese mismo órgano, así como el oficio DFOE-SM-105-2007 de la Contraloría General de la República.
Documentos, que sin duda alguna, son vinculantes actualmente; empero, como queda claramente evidenciado, fueron emitidos con posterioridad a la adopción por parte de la Municipalidad de Golfito de este Plan Regulador -16 de febrero de 2004-. Así las cosas, no le corresponde a este Tribunal determinar si la actuación de la Municipalidad de Golfito, el INVU o el ICT, en la interpretación de tales disposiciones fue correcta o no, por tratarse de un examen de legalidad que corresponde a la jurisdicción ordinaria. Lo cierto es que la prohibición expresa y manifiesta respecto del aporte que puedan realizar los particulares y la forma en que podría ser aceptada, para efectos de la elaboración de estudios o propuestas de ordenamiento territorial, fueron emitidos con posterioridad a la normativa impugnada, por lo que no se le puede atribuir retroactivamente un vicio de constitucionalidad en ese sentido.
Los accionantes aducen que la inconstitucionalidad se deriva del beneficio que reciben los particulares, sin que quede claro cuáles han sido estos ni se demuestren los perjuicios directos para “los intereses y servicios locales en cada cantón”. Por otro lado, tampoco es cierto que la aprobación de este Plan Regulador significara automáticamente la aprobación de los proyectos del atracadero y la marina en cuestión, pues para dichos efectos, incluso existe una ley especial, “Ley de Concesión y Operación de Marinas y Atracaderos Turísticos” publicada el 6 de febrero de 1998, que regula la concesión al respecto y exige de previo para tal efecto, la evaluación ambiental de los impactos de los proyectos, que fueron conocidos por SETENA y verificados por el CIMAT, no por este Municipio. De manera que tampoco puede atribuirse la relación directa aludida por los accionantes.
En consecuencia, determinar si la aprobación de un plan elaborado, costeado y propuesto por particulares beneficia a estos en perjuicio del bien común –de “los intereses y servicios locales en cada cantón”– es un asunto que solo puede determinarse examinando el plan en el caso particular, lo que no es objeto de conocimiento vía acción de inconstitucionalidad y que por la prueba necesaria a evacuar al respecto, solo podría ser objeto de conocimiento en la vía de legalidad ordinaria. Por lo anterior, este cuarto alegato de los accionantes, al limitarse a señalar que es inconstitucional el Plan porque benefició a la empresa que elaboró, costeó y propuso el Plan, es insuficiente para declarar con lugar esta acción.
VIII.Quinto alegato: Nunca hubo participación ciudadana informada previa a la aprobación municipal. Los accionantes señalan que si bien se dio una audiencia pública, la población que acudió a informarse sobre este plan, nunca fue informada acerca de la variable ambiental del mismo, pues ni las instituciones ni la Municipalidad de Golfito presentaron el proyecto a SETENA. Nuevamente se reitera, que no puede imputársele la omisión señalada por los accionantes a la normativa impugnada, si para tal momento no había sido emitida la reglamentación que exigen. En su momento oportuno, el Concejo Municipal sometió el proyecto del Plan Regulador a consulta pública, de conformidad con lo dispuesto en el artículo 17 de la Ley de Planificación Urbana, No. 4240 de 15 de noviembre de 1968. Así las cosas, no podía ser exigida a la Municipalidad de Golfito, una audiencia que incluyera la variable ambiental, si para dicho momento, SETENA no había implementado los procedimientos necesarios para su inclusión.
Ahora bien, como se indicó anteriormente, el Municipio está obligado a incorporar actualmente los índices de fragilidad ambiental y para ello SETENA deberá valorarlos y cumplir con los procedimientos respectivos, por lo que en dicho momento deberá hacerse efectivo el derecho de participación ciudadana que atañe al Plan Regulador con la variable ambiental en cuestión, pero ello no implica dado tal contexto, que la normativa impugnada resulte inconstitucional.
IX.Conclusión: Respecto de los alegatos presentados por los accionantes, siguiendo el orden de cada uno de ellos, esta Sala concluye lo siguiente: PRIMERO: no hay mérito para declarar con lugar la acción, porque al momento de la aprobación del PRPPJ no existía ni el Reglamento ni el Manual de Evaluación de Impacto Ambiental, que regulan el artículo 17 de la Ley Orgánica del Ambiente. SEGUNDO: no hay mérito para declarar la violación del artículo 89 constitucional, toda vez que se contaron con los criterios técnicos requeridos para el momento en que fue emitida la normativa en cuestión y con fundamento en ello se establecieron las áreas demarcadas. TERCERO: La redacción del artículo 1.1. inciso b) del Reglamento del PRPPJ no es inconstitucional en sí misma. CUARTO: Los accionantes refieren que la mera concesión de la marina y otras infraestructuras a la empresa que intervino en la elaboración del Plan Regulador son perjudiciales, pero no presentan acervo probatorio alguno.
Asimismo, ha de advertirse que el añadir en este alegato los perjuicios que resultarían de tales infraestructuras, supondría variar el objeto de esta acción, que como se ha dicho, se refiere exclusivamente al PRPPJ y su reglamento. QUINTO: A la luz de lo señalado respecto del primer alegato, no puede imputársele la omisión señalada por los accionantes a la normativa impugnada, si para tal momento no había sido emitida la reglamentación que exigen. Lo que no obsta, para que en el momento en que se lleve a cabo la incorporación de la variable ambiental al Plan Regulador, se realice la audiencia correspondiente y se garantice la participación ciudadana al efecto.
Por tanto:
Por mayoría se declara sin lugar la acción. El Magistrado Jinesta pone nota y ordena que en el plazo de 3 meses, contado a partir de la notificación de esta sentencia, el Estado, el MINAE y sus órganos competentes procedan, a delimitar, de manera definitiva y cierta las áreas del Patrimonio Natural del Estado. De haber traslape en dichas zonas deberán emplear todos los medios que el ordenamiento jurídico permite, para recuperar dichos terrenos en forma pronta y efectiva. El Magistrado Rueda coincide con la desestimatoria de la acción pero salva el voto en cuanto a los alcances de la parte dispositiva, por cuanto: 1) considera que se debe ordenar a la Municipalidad de Golfito incorporar en el Plan Parcial Regulador de Puerto Jiménez la variable ambiental, conforme al artículo 67 del "Reglamento General sobre los Procedimientos de Evaluación de Impacto Ambiental”, aprobado mediante el Decreto Ejecutivo No. 31.849 de 24 de mayo 2004, reformado mediante el Decreto Ejecutivo No. 34.688 de 25 de febrero de 2008, y el "Manual de Instrumentos Técnicos para el Proceso de Evaluación del Impacto Ambiental (Manual de EIA)- Parte III”, aprobado en el Decreto Ejecutivo 32.967-MINAE de 20 de febrero de 2006; y 2) estima que se debe ordenar al MINAE y al Instituto Geográfico Nacional que procedan, en un plazo máximo de 4 años a partir de la notificación de esta sentencia, a realizar los trámites requeridos a efectos de demarcar con exactitud los linderos del patrimonio natural del Estado y, de resultar alguna rectificación, la Municipalidad de Golfito deberá modificar el Plan Regulador en dicho sentido; en el ínterin de tal verificación y en aplicación del principio precautorio, la Municipalidad de Golfito deberá mantener el acuerdo aplicado hasta el momento, de no otorgar concesiones en las áreas diferenciables advertidas por el Área de Conservación de Osa.
Los Magistrados Armijo Sancho y Cruz Castro salvan el voto y declaran con lugar la acción, y anulan el Plan Regulador de Puerto Jiménez, Golfito-Puntarenas, por estimarlo contrario a los derechos protegidos en los artículos 7, 50, 89 y 169 de la Constitución Política, así como el artículo 5º de la Convención para la Protección de la Flora, Fauna y de las Bellezas Escénicas Naturales de los Países de América (Ley No. 3763), el artículo 4º de la Convención sobre la Protección del Patrimonio Mundial, Cultural y Natural (Ley No. 5980) y el artículo 4º de la Convención Relativa a los Humedales de Importancia Internacional (Ley No. 7224). Los Magistrados Castillo Víquez y Cruz Castro ponen nota.
Gilbert Armijo S.
Ernesto Jinesta L. Fernando Cruz C.
Fernando Castillo V. Paul Rueda L.
Nancy Hernández L. Luis Fdo. Salazar A.
prl / azunigag NOTA DEL MAGISTRADO JINESTA LOBO Ciertamente coincido con los argumentos para declarar sin lugar la acción de inconstitucionalidad. Empero, tal y como se dispuso en el Voto No. 3480-2003, en el que concurrí con mi voto, ante la incertidumbre sobre la delimitación cierta y efectiva del Patrimonio Natural del Estado (v. gr. Manglares, humedales, ríos, quebradas, etc) , es menester impartir una orden al Estado y sus órganos competentes, para evitar su menoscabo y disminución irregular. Por lo anterior, en todos los casos de duda u objeto de cuestionamiento, ordeno que en el plazo de 3 meses contados a partir de la notificación de esta sentencia el Estadio, el MINAE y sus órganos competentes procedan, a delimitar, de manera definitiva y cierta las áreas del Patrimonio Natural del Estado. De haber traslape en dichas zonas deberán emplear todos los medios que el ordenamiento jurídico permite, para recuperar dichos terrenos en forma pronta y efectiva.
Ernesto Jinesta L.
13-03396.
El Magistrado Rueda coincide con la desestimatoria de la acción pero salva el voto en cuanto a los alcances de la parte dispositiva, por cuanto: 1) considera que se debe ordenar a la Municipalidad de Golfito incorporar en el Plan Parcial Regulador de Puerto Jiménez la variable ambiental, conforme al artículo 67 del "Reglamento General sobre los Procedimientos de Evaluación de Impacto Ambiental”, aprobado mediante el Decreto Ejecutivo No. 31.849 de 24 de mayo 2004, reformado mediante el Decreto Ejecutivo No. 34.688 de 25 de febrero de 2008, y el "Manual de Instrumentos Técnicos para el Proceso de Evaluación del Impacto Ambiental (Manual de EIA)- Parte III”, aprobado en el Decreto Ejecutivo 32.967-MINAE de 20 de febrero de 2006; y 2) estima que se debe ordenar al MINAE y al Instituto Geográfico Nacional que procedan, en un plazo máximo de 4 años a partir de la notificación de esta sentencia, a realizar los trámites requeridos a efectos de demarcar con exactitud los linderos del patrimonio natural del Estado y, de resultar alguna rectificación, la Municipalidad de Golfito deberá modificar el Plan Regulador en dicho sentido; en el ínterin de tal verificación y en aplicación del principio precautorio, la Municipalidad de Golfito deberá mantener el acuerdo aplicado hasta el momento, de no otorgar concesiones en las áreas diferenciables advertidas por el Área de Conservación de Osa.
El suscrito advierte, que a pesar de que la acción debe ser desestimada de conformidad con las consideraciones expuestas en la sentencia, toda vez que lo actuado se ajustó a derecho dentro del contexto normativo vigente cuando se aprobó el Plan impugnado, lo cierto es que existen 2 situaciones actuales que fueron evidenciadas y que en atención al principio precautorio y de protección al ambiente, no podían ser ignoradas y ameritaban por parte de este Tribunal, emitir dos preceptos en particular:
1- La Sala está llamada a salvaguardar el principio de seguridad jurídica y de hacerlo sin detrimento de lo establecido en el artículo 50 constitucional. De manera que si bien el Reglamento de SETENA no se había emitido para cuando fue aprobado el Plan en cuestión, sí subyace la obligación posterior de incorporarle al ordenamiento territorial la variable ambiental que dispone el artículo 67 del Reglamento de Evaluación de Impacto Ambiental y el Manual respectivo. En razón de ello, considero que lo propio era ordenar a la Municipalidad de Golfito que incorporara la variable ambiental y remitiera el Plan Regulador en cuestión a SETENA para finalmente verificar la respectiva evaluación de conformidad.
2- De igual modo, las autoridades públicas evidenciaron en la audiencia pública celebrada el 6 de noviembre de 2014 y en sus informes, inconsistencias con respecto a la delimitación del patrimonio natural del Estado que no podían ser ignoradas. Así las cosas, aunque para el 2004 se contaba con la información certificada por el Instituto Geográfico Nacional con respecto a la delimitación de los manglares y por ello no puede alegarse que el ordenamiento territorial adoptado lo fuera con base en criterios abiertamente arbitrarios, lo cierto es que se acreditó en autos, mediante dos informes técnicos del MINAE elaborados en el 2007 y 2013, que incluso se contradicen, que existen inconsistencias en las medidas georeferenciadas por el IGN. Tal situación, como se indicó en la sentencia no implicaba la inconstitucionalidad de la normativa impugnada, pues su elaboración se basó en los criterios oficiales existentes en el 2004, pero sí ameritaba, desde mi punto de vista, ordenar al MINAE y al IGN indagar y constatar las inconsistencias advertidas posteriormente, y de proceder una rectificación, ordenar a la Municipalidad de Golfito ajustar su normativa a tales efectos, como en similar sentido ordenó este Tribunal en la sentencia No. 2003-3480, al resolver la acción de inconstitucionalidad interpuesta contra el Plan Regulador Costero Turístico Playa Platanares:
“Es claro que el principio precautorio obliga al Estado a adoptar todas aquellas medidas necesarias para no sólo sancionar la lesión de los bienes ambientales, mas también para evitar que tales daños se produzcan. Sin embargo, al imponer una determinada limitación, no puede esta Sala basarse en datos inciertos como los constantes en el expediente, los cuales a través de la realización de las pesquisas correspondientes, podrían fácilmente demostrar que en la especie no existe el traslape acusado. Bien entendido el principio precautorio, el mismo se refiere a la adopción de medidas no ante el desconocimiento de hechos generadores de riesgo, sino ante la carencia de certeza respecto de que tales hechos efectivamente producirán efectos nocivos en el ambiente. En el presente caso, es claro que nos encontramos ante el primero de los supuestos, es decir, no existe certeza acerca de la existencia de la transposición entre el Plan Regulador y el Refugio de Vida Silvestre.
Contrario sería el caso en que se tuviera certeza del hecho, pero duda acerca de su peligrosidad para el ambiente. Así las cosas, debe la Sala declarar sin lugar la presente acción de inconstitucionalidad, en vista de que no se comprueba que haya lesión efectiva ni riesgo inminente de violación, de las normas contenidas en los artículos 21, 50 y 89 de la Constitución Política. Debe sin embargo, ordenarse al Ministerio de Ambiente y Energía la inmediata realización de la prueba de campo que le permita determinar con toda certeza si el traslape acusado efectivamente se da, para entonces tomar de inmediato todas las medidas que el ordenamiento le permite a efecto de recuperar la franja que se alega invadida.
VIII.Conclusión. A partir de los argumentos contenidos en los párrafos que anteceden, esta Sala ha llegado a la conclusión de que el Plan Regulador Sector Costero Turístico Playa Platanares, adoptado mediante acuerdo del Consejo Municipal de Golfito en sesión ordinaria celebrada el trece de marzo de mil novecientos noventa y nueve, y publicado en el Diario Oficial La Gaceta número 74, de diecinueve de abril de mil novecientos noventa y nueve, no es inconstitucional por las razones invocadas por la actora, por lo que de conformidad con lo establecido en el artículo 87 de la Ley de la Jurisdicción Constitucional, lo que procede es declarar sin lugar la presente acción de inconstitucionalidad en todos sus extremos. Esta resolución es dictada sin perjuicio de las conclusiones a las que puedan llegar las autoridades del Ministerio de Ambiente y Energía, mediante la realización de estudios topográficos empleando teodolito o cualquier otro método idóneo, si determinan con certeza o con suficiente grado de probabilidad, que la transposición entre el Plan Regulador de la Zona Costera de Playa Platanares y el Refugio Nacional de Vida Silvestre Preciosa-Platanares Categoría Mixta, efectivamente se da en el presente caso.
Para ello, se ordena al Ministro de Ambiente y Energía a efectuar, en el plazo máximo de tres meses a partir de la notificación de esta sentencia, los estudios topográficos requeridos para determinar con certeza si el traslape acusado efectivamente ocurre en este caso. De haber ocurrido una invasión del área protegida, deberá emplear todos los medios que el ordenamiento le permite, para recuperar dichos terrenos en forma pronta y efectiva.”
Asimismo, se debió ordenar que en el ínterin de tal confirmación y en aplicación del principio precautorio, la Municipalidad de Golfito tenía que mantener el acuerdo, aplicado hasta el momento, de no otorgar concesiones en las áreas diferenciables advertidas por el Área de Conservación de Osa.
Paul Rueda L.
Voto Salvado de los Magistrados Armijo Sancho y Cruz Castro.
Con el mayor respeto para los miembros del Tribunal Constitucional, los suscritos Magistrados procedemos a considerar que esta acción debe declararse con lugar, y por tanto, procede anular el Plan Regulador de Puerto Jiménez, Golfito-Puntarenas, por estimarlo contrario a los derechos protegidos en los artículos 7, 50, 89 y 169 de la Constitución Política, así como el artículo 5º de la Convención para la Protección de la Flora, Fauna y de las Bellezas Escénicas Naturales de los Países de América (Ley No. 3763), el artículo 4º de la Convención sobre la Protección del Patrimonio Mundial, Cultural y Natural (Ley No. 5980) y el artículo 4º de la Convención Relativa a los Humedales de Importancia Internacional (Ley No. 7224), conforme las razones que se explican a continuación.
Conforme se desprende del expediente, la acción de inconstitucionalidad se presenta en contra del Plan Regulador Parcial de Puerto Jiménez Golfito-Puntarenas y del Reglamento de Zonificación. Se aducen básicamente tres argumentos de inconstitucionalidad por la forma (elaboración por empresa privada argumento CUARTO, no consulta popular argumento QUINTO y no variable ambiental argumento UNO) y dos argumentos de inconstitucionalidad por el fondo (violación a principio precautorio argumento DOS, criterios indeterminados argumento TRES). Nos parece que la inconstitucionalidad en este caso radica principalmente en la elaboración del Plan Regulador por parte de una empresa privada y en la no consideración de la variable ambiental.
I-Sobre la elaboración del Plan por parte de una empresa privada En cuanto a este aspecto, la cuestión no es, como se indica en el voto de mayoría, comprobar si el Plan aprobado beneficia o perjudica a la empresa privada que elaboró el plan, sino, determinar si los Gobiernos Locales pueden válidamente delegar en un sujeto privado la gestión y/o el financiamiento de la elaboración de los planes reguladores costeros. En este sentido, habiéndose comprobado en el expediente que el Concejo Municipal de Golfito procedió a “aprobar el Plan Regulador Parcial del Sector Costero de Puerto Jiménez, Golfito, promovido por Bahía Cocodrilo S.A” (acuerdo tomado en el artículo duodécimo, capítulo sexto, de la sesión ordinaria número 3, celebrada a las 15:30 horas del día 19 de enero del 2004), compartimos el criterio esbozado por la Procuraduría General de la República en su informe. Siendo el ordenamiento territorial el ejercicio de una función pública, las municipalidades no pueden aprobar planes reguladores cuya elaboración haya sido gestionada y financiada por sujetos de derecho privado, pues con ello estaría renunciando al ejercicio de una potestad pública otorgada por ley (artículo 28, Ley Orgánica del Ambiente –LOA- y 15 de la LPU). Así que la gestión y el financiamiento de la elaboración de un plan regulador, por parte de un sujeto privado, resultan inconstitucionales.
Además, la potestad municipal de planificar el territorio y determinar el uso del suelo, tiene efectos importantes en relación con el ambiente, máxime si se trata de la planificación en un bien demanial como lo es la zona marítimo terrestre. Por ello, la gestión y el financiamiento de la elaboración de los planes reguladores costeros por sujetos de derecho privado, como bien lo esboza la Procuraduría, conlleva declinar el ejercicio parcial de una función pública que incide sobre el ambiente, como es el caso del ordenamiento del territorio. Lo cual implica, no sólo una delegación inconstitucional de funciones públicas, sino a su vez, incumplir con el deber de tutela y protección del ambiente que el artículo 50 asigna al Estado.
Por la naturaleza jurídica de un plan regulador (conforme al artículo 1 de la Ley de Planificación Urbana un plan regulador es un conjunto de planes, mapas, reglamentos para definir la política de desarrollo, usos de tierra, vías de circulación, servicios públicos, facilidades comunales y otros) su elaboración y aprobación es evidentemente competencia dada a las Municipalidades, quienes NO pueden (en el mismo sentido en que la Sala lo estableció en los votos Nº 9792-98 y Nº7965-99) delegar dicha competencia (potestades y deberes) en un tercero. Máxime en este caso, donde, según se dijo, se está frente a la obligación de protección de un bien demanial.
No sanea el proceso el hecho de que la Municipalidad haya ratificado el plan hecho por la empresa privada. Las Municipalidades no pueden aprobar o adoptar planes reguladores cuya elaboración haya sido gestionada, contratada o financiada por sujetos de derecho privado.
II- Sobre la exclusión de la variable ambiental El hecho de haberse aprobado este Plan Regulador sin tomar en consideración la variable ambiental constituye una clara y evidente afectación del derecho a un medio ambiente sano y ecológicamente equilibrado, en los términos en que ha sido proclamado en el artículo 50 constitucional, así como de los principios de precautorio, no regresión en materia ambiental y de irreductibilidad del bosque, que desde ningún punto de vista puede ser soslayado por este Tribunal Constitucional. Es claro que dicho reglamento contradice y olvida los alcances del criterio sostenido por este Tribunal Constitucional en las decisiones Nos. 233-1993, 5399,1993, 1886,1995, 4587-1997 y 6322-2003, todas ellas anteriores a la publicación del instrumento normativo cuestionado. A nuestro juicio, el vicio que se aprecia en esta oportunidad no es susceptible de ninguna convalidación, como se pretende en la parte dispositiva de esta sentencia, al exigirse a la Municipalidad de Golfito que incorpore en el Plan Regulador la variable ambiental.
En este sentido, consideramos que lo procedente es anular el presente instrumento y que se emita uno nuevo acorde con los principios y lineamientos que ha desarrollado este Tribunal Constitucional en su Jurisprudencia y que son dejados de lado en esta oportunidad. En todo caso, es preciso mencionar que las decisiones de este Tribunal Constitucional son vinculantes erga omnes y gozan de eficacia plena, por sí mismas, sin necesidad que con posterioridad se dicte la reglamentación necesaria para hacer efectiva una disposición de la Sala. Pero todavía es más evidente el hecho que dicho reglamento haya sido elaborado por empresas privadas en aras de lograr, según los actores, la advertido por la Procuraduría General de la República en su dictamen, en los términos que se indicó supra, hace inconstitucional el Plan Regulador aludido, teniendo en cuenta que por la magnitud de los principios ambientales involucrados, la regulación del territorio de un cantón solo puede ser elaborada y desarrollada por las Corporaciones municipales en el marco de las competencias que se desprenden del artículo 169 constitucional, es decir, la defensa de los intereses y servicios locales, dentro de lo cual también se incluye la protección del derecho a un medio ambiente sano y ecológicamente equilibrado. Por lo expuesto, salvamos el voto y declaramos con lugar la acción.
Gilbert Armijo S. Fernando Cruz C.
Magistrado Magistrado NOTA SEPARADA DEL MAGISTRADO CASTILLO VÍQUEZ Concurro con mi voto y declaro sin lugar la presente acción, pero adiciono las razones que de inmediato paso a explicar. Se plantea como agravio el hecho de que una empresa privada haya financiado y elaborado el proyecto que culminó en el PRPPJ; empero, como ha quedado demostrado en autos, su aprobación fue realizada por los entes competentes (la municipalidad, el INVU y el ICT), por lo que no estamos en presencia del ejercicio de la potestad de planificación urbana en manos de un sujeto privado y, por consiguiente, no se ha lesionado la garantía institucional. Como es bien sabido, bajo el concepto de la garantía institucional[1] se engloban un conjunto de actividades que, dada su naturaleza, no es dable su gestión a través de figuras organizativas de Derecho privado, es decir, no puede salir del ámbito de lo público. En el ámbito propiamente de la Administración Pública, lo que se ha denominado la reserva constitucional de la Administración –en un sentido amplio reservada al Poder Ejecutivo y a las demás Administraciones Públicas con competencias constitucionales, como es el caso de las corporaciones municipales-, esta integrada por la actividad de dirección política, la actividad de policía y de fomento.
Estas actividades, que son funciones públicas de soberanía, tienen que ser desarrollas obligatoriamente por una Administración, tal y como se encuentra regulada por la Constitución, es decir, con los rasgos de su garantía institucional. Hay una identificación entre reserva de Administración y prohibición de privatización formal –recurso al ordenamiento jurídico privado-. Es el objeto material de la reserva lo que justifica la singularidad constitucional de la Administración pública. No existe libertad de elección de forma o régimen jurídico para desarrollar estas actividades que pertenecen a la reserva de Administración Pública. La huida al Derecho privado de estas Administraciones que ejercen funciones públicas soberanas o su ejercicio por parte de particulares es inconstitucional, pues, en este último caso lesiona, una garantía constitucional, así como el principio de la indelegabilidad de las potestades públicas, máxime que, en este caso, se trata de funciones públicas de soberanía.
Distinto es el supuesto de la actividad de servicio público y la actividad logística o de suministro que no son típicamente administrativas –no están dentro de la reserva de Administración Pública- y no tienen obligatoriamente que ser ejercidas por Administraciones de conformidad con su garantía institucional. La Administración puede optar entre el régimen del Derecho administrativo y el régimen de Derecho privado. En cambio, la actividad libre en el mercado de la Administración tiene que ser desarrollada preferente en régimen de Derecho privado con la finalidad de salvaguardar la competencia, aunque esta opción presenta una serie de dilemas de cara a garantizar algunos derechos fundamentales y los controles de los fondos públicos, a tenor del principio que establece que: “ahí donde van los fondos públicos debe ir el control”, aunque, en honor a la verdad, en nuestro medio el Derecho privado ha regulado la actividad de una serie de entes cuya principal giro es industrial, comercial o financiero, pero su organización está regulada por el Derecho público, pues han adoptado las figuras organizativas de este derecho –institución autónoma, semiautónoma, ente público estatal y ente público no estatal-.
En este punto acierta la doctrina cuando expresa que: “Los órganos constitucionales, y en general, el resto de los poderes del Estado, no pueden recurrir al Derecho privado para el cumplimiento de sus funciones propias y exclusivas, pero sí pueden hacerlo para desarrollar algunas funciones auxiliares o instrumentales. Al igual que en la reserva de Administración, son las competencias exclusivas lo que marca el ámbito de utilización obligada del Derecho público por parte del órgano constitucional”. (TRONCOSO REIGADA, Antonio, Privatización, Empresa Pública y Constitución, Marcial Pons, Ediciones Jurídicas y Sociales S.A., Madrid, 1997, páginas 458 y 459).
Establecido lo anterior, el agravio que plantean los accionantes no tiene sustento constitucional, aunque sí podría tener asidero legal e incluso ético. De ahí que en estos casos, donde son los sujetos privados los que han elaborado y financiado el proyecto del Plan Regulador Costero que finalmente es aprobado por las Administraciones Públicas -hay 42 casos según se informa en la página del ICT-, se requiere que estas, y en especial los órganos de fiscalización, ejerzan un control más intenso y permanente e, incluso, de oficio, con el objeto de establecer que con la aprobación de esos planes no se afectaron (ni se afectan) los intereses generales en aras de beneficiar los intereses privados; práctica que afortunadamente se prohibió, con base en los pronunciamientos de la Procuraduría y Contraloría General de la República.
En otro orden de ideas, considero fundamental reafirmar el hecho que los manglares no son susceptibles de ser concesionados, no solo porque el reglamento así lo establece sino porque, como es bien sabido, pertenecen a la ZP y al PNE, conforme al Derecho de la Constitución (valores, principios y normas), los instrumentos internacionales que garantizan y protegen a favor de la humanidad el derecho a un ambiente saludable y ecológicamente equilibrado y la legislación vigente.
Fernando Castillo V.
Nota del Magistrado Cruz Castro:
Estimo que es muy grave que un plan regulador sea financiado y elaborado con fondos de particulares, con el agravante que tienen un interés directo en el contenido de dicho plan. La Procuraduría señala muy bien este tema cuando afirma que la elaboración del plan regulador que incide en la planificación territorial, es el ejercicio de una función pública que no permitía al ICT y el INVU–, aprobar dichos planes reguladores, pues no puede ser getionada ni financiada por sujetos de derecho privado, pues con ello se renuncia al ejercicio de una potestad pública otorgada por ley artículo 28 de la LOA y 15 de la LPU. Ni en el supuesto de una donación de un sujeto de derecho privado, tal donación no puede condicionar la elaboración del plan regulador respectivo. Opinión similar expresa la Contraloría General de la República, en su dictamen C-70-2009. Es realmente muy grave que la definición de un asunto de interés público sea controlado por un particular, situación que compromete el fin público.
Bien puede afirmarse que la gestión y el financiamiento de la elaboración de un plan regulador, aparte de ser ilegal, es inconstitucional, pues contraviene el artículo 50 constitucional, norma que además de garantizar el derecho a un ambiente sano y ecológicamente equilibrado como derecho fundamental, establece el deber estatal de tutelarlo. Así, ese artículo consagra como principio constitucional el deber estatal de proteger y tutelar el ambiente. Los entes municipales, como administración pública territorialmente descentralizada, están vinculados a dicho principio y por eso están obligados a proteger y tutelar el ambiente en el ejercicio de sus potestades y competencias. Obviamente una de esas potestades es la de planificar el territorio y determinar el uso del suelo. Se trata de una potestad que por sus implicaciones tiene una importante incidencia en el ambiente y en un desarrollo equilibrado y saludable.
Es por eso que se requiere de un Estudio de Impacto Ambiental para la elaboración de uno de sus principales instrumentos: los planes reguladores. El ejercicio de esta potestad respecto de un bien demanial como la ZMT que, como lo ha señalado esta Sala en su jurisprudencia, también tiene fines conservacionistas, es una forma de ejercer el deber estatal de protección y tutela del ambiente (sentencia No. 2408-2007 de 21 de febrero de 2007). Considero que la gestión y financiamiento de los planes reguladores costeros por sujetos de derecho privado, conlleva declinar el ejercicio parcial de una función pública que incide sobre el ambiente, como es el caso del ordenamiento del territorio. De esta forma se incumple la tutela y protección del ambiente que el artículo 50 constitucional asigna al Estado y a todos los poderes públicos. Conforme a los argumentos expuestos, como una iniciativa particular, pongo en conocimiento del Fiscal General estos hechos, que se refieren a la aprobación de un plan regulador elaborado y financiado con fondos particulares, porque estimo que la autoridades estatales que así lo aprobaron, pudieron incurrir en un incumplimiento de deberes o en un delito de prevaricato, puesto que no sólo contradicen normas legales y constitucionales, según se citaron, sino que contradicen criterios de la Procuraduría General de la República y de la Contraloría General de la República.
Estimo que son hechos muy graves para bienes públicos tan importantes como el ambiente y el ejercicio de potestades públicas y por este motivo, remito una copia de este fallo y de los documentos anexos al Ministerio Público, para que el órgano de la acusación investigue y determine si en este caso pudo existir un delito en perjuicio de los deberes de la función pública.
Fernando Cruz C.
Document not found. Documento no encontrado.