a. Note with the approval request and project description (property, owner, developer, number of housing units, type of urban regime to which it will be subject, area table, discharge point (stormwater and/or wastewater), detail of materials to be used in pavements and sidewalks, etc.)
b. Copy of cadastral plan, only for plans generated in the six months prior to the date of submission of the preliminary project, for the issuance date of this directive, first half of 2015.
c. Site design showing the location of the project components (building footprints, treatment plant, detention pond, etc.), it must be provided in printed physical form (11x17" maximum) and in digital PDF format, on a compact disc.
d. If the property owner is not the one conducting the process, a notarized document must be submitted legitimizing the person conducting the process for that purpose.
e. Stormwater (pluvial), wastewater (sanitario), and potable water calculation report (memoria de cálculo) as indicated in this policy.
f. If required: approximate location of the Wastewater Treatment Plant (Planta de Tratamiento de Aguas Residuales).
g. Constructions that intend to channel water towards a stormwater sewer system (alcantarillado pluvial) located on national routes, in addition to obtaining the approval of the stormwater mitigation system from the municipality, must have the discharge approval from the Ministry of Public Works and Transport (Ministerio de Obras Públicas y Transportes, MOPT).
h. Construction projects bordering rivers, streams (quebradas), or creeks shall not carry out any type of work within the protection zone established in the Forest Law (Ley Forestal).
i. Stormwater discharges via stormwater easement (servidumbre pluvial) shall be permissible only when the latter is formally constituted.
j. Discharge pipe outlets into water bodies. All stormwater culvert outlets from residential subdivisions and projects in general must be protected against erosive processes that may be caused by the water entering the river, and undermining (socavación) must be prevented by means of a connection of the culvert to the river at a 45º angle with respect to the bank.
k. The culvert outlet must not be below the mean river level, as this would prevent water from exiting the culverts during a storm. Also, regarding the water entering the river, the water fall must be protected with energy dissipation structures to prevent undermining (socavación).
l. The analysis of mean levels shall be performed for flows with a return period of 50 years.