← Environmental Law Center← Centro de Derecho Ambiental
Res. 00139-2013 Tribunal Contencioso Administrativo Sección III · Tribunal Contencioso Administrativo Sección III · 04/04/2013
OutcomeResultado
The Court denied the appeal, affirmed the municipal order to vacate and demolish the project built without a permit, and declared the administrative process exhausted.El Tribunal rechazó la apelación y confirmó la orden municipal de desalojo y demolición del proyecto construido sin licencia, dando por agotada la vía administrativa.
SummaryResumen
The Administrative Litigation Court denied the appeal against an order to vacate and demolish a project comprising sixteen buildings and thirty-eight homes constructed in Carrillo without a municipal permit. It held that municipalities have both the authority and the duty to verify that every project has prior authorization, halt and close illegal construction, and order demolition after completing the procedure established in Articles 93 et seq. of the Construction Law. The permit application remained pending because essential requirements were missing, including current environmental viability, adequate water availability, and municipal approval of a cadastral plan. The companies continued building despite a closure and four notices directing them to comply. The Court rejected the fiduciary owner’s due-process claim, found that certification of a twelve-millimeter water meter did not establish sufficient water availability, and ruled that the possible environmental effects of demolition—or the alleged absence of springs, mangroves, biological reserves, or other sensitive features—did not justify preserving a project erected unlawfully.El Tribunal Contencioso Administrativo rechazó la apelación contra la orden de desalojar y demoler un proyecto de dieciséis edificios y treinta y ocho viviendas construido en Carrillo sin licencia municipal. Confirmó que las municipalidades tienen el poder-deber de verificar que toda obra cuente previamente con permiso, paralizar y clausurar construcciones ilegales y, después del procedimiento de los artículos 93 y siguientes de la Ley de Construcciones, ordenar su demolición. La solicitud de licencia seguía pendiente porque faltaban requisitos esenciales, entre ellos viabilidad ambiental vigente, disponibilidad hídrica suficiente y visado municipal de un plano catastrado. Las sociedades continuaron construyendo pese a la clausura y a cuatro prevenciones para ponerse a derecho. El Tribunal descartó la indefensión de la propietaria fiduciaria, consideró insuficiente la certificación de un medidor de agua de doce milímetros y rechazó que el posible impacto ambiental de demoler o la ausencia alegada de elementos naturales sensibles justificaran conservar una obra levantada ilegalmente.
Key excerptExtracto clave
For all the foregoing reasons, this Court considers that the respondent Municipal Administration observed the procedure established in Articles 93 et seq. of the Construction Law, culminating in the act ordering the vacation and demolition of the structures after noncompliance with Article 89(a) of the Construction Law was established. In that regard, the alleged damage that demolition may cause must, in principle, be borne by the owners of the properties on which the works were constructed, since their unlawful conduct caused the Municipality of Carrillo to have to apply the stated sanction. The challenged act is affirmed, and the administrative process is declared exhausted.Por todo lo expuesto, estima este Tribunal que la Administración Municipal recurrida ha observado el procedimiento previsto en los artículos 93 y siguientes de la Ley de Construcciones, que ha culminado con el acto en que se ordena el desalojo y la demolición de lo edificado, al acreditarse el incumplimiento a lo dispuesto en el artículo 89 inciso a) de la Ley de Construcciones. En ese sentido, los presuntos daños que pueda causar la demolición, deberán ser asumidos -en principio- por los propietarios de los inmuebles en que se construyeron las obras, quienes provocaron con sus conductas ilegítimas que la Municipalidad de Carrillo tenga que aplicar la sanción indicada. Se confirma el acto impugnado y se da por agotada la vía administrativa.-
Pull quotesCitas destacadas
"Esta facultad, que es por su propia naturaleza obligatoria, se trata de un poder-deber de las autoridades municipales que no pueden dejar de aplicar ante el acaecimiento de transgresiones al ordenamiento urbanístico."
"This authority, which is mandatory by its very nature, constitutes both a power and a duty of municipal authorities that they cannot decline to exercise when land-use regulations are violated."
Considerando III.1
"Esta facultad, que es por su propia naturaleza obligatoria, se trata de un poder-deber de las autoridades municipales que no pueden dejar de aplicar ante el acaecimiento de transgresiones al ordenamiento urbanístico."
Considerando III.1
"La Municipalidad recurrida en uso de los poderes de policía, debe proceder a verificar que toda edificación temporal o permanente dentro de su jurisdicción, se encuentre amparada a la respectiva licencia constructiva, misma que debe ser extendida previo al levantamiento de las obras."
"In exercising its police powers, the respondent Municipality must verify that every temporary or permanent structure within its jurisdiction is covered by the corresponding building permit, which must be issued before construction begins."
Considerando III.1
"La Municipalidad recurrida en uso de los poderes de policía, debe proceder a verificar que toda edificación temporal o permanente dentro de su jurisdicción, se encuentre amparada a la respectiva licencia constructiva, misma que debe ser extendida previo al levantamiento de las obras."
Considerando III.1
"Aunado a que en dicha certificación de medidor extendida por el Instituto Costarricense de Acueductos y Alcantarillados, se consigna que el diámetro del servicio es de 12 mm, lo cual, se estima insuficiente para un proyecto habitacional que consta de dieciséis edificios, para un total de 38 viviendas en condominio."
"Moreover, the meter certification issued by the Costa Rican Institute of Aqueducts and Sewers states that the service diameter is 12 mm, which is considered insufficient for a residential project consisting of sixteen buildings and a total of 38 condominium units."
Considerando III.3
"Aunado a que en dicha certificación de medidor extendida por el Instituto Costarricense de Acueductos y Alcantarillados, se consigna que el diámetro del servicio es de 12 mm, lo cual, se estima insuficiente para un proyecto habitacional que consta de dieciséis edificios, para un total de 38 viviendas en condominio."
Considerando III.3
"Cabe recordar a las empresas recurrentes, que la sanción prevista en el artículo 96 de la Ley de Construcciones, para quienes hayan edificado obras, sin que de previo la Municipalidad competente les hubiera otorgado la licencia constructiva, y sin que, realizadas las dos prevenciones para que se pusieran a derecho, lo hicieran en los plazos concedidos al efecto (artículos 93 y 94 de la Ley de Construcciones) , consiste en la demolición de lo construido, lo cual, se hará por cuenta del propietario (artículo 96 de la Ley de Construcciones)."
"The appellant companies must be reminded that the sanction prescribed by Article 96 of the Construction Law for those who build without first obtaining a permit from the competent municipality and who fail to comply within the allotted periods after two notices under Articles 93 and 94 is demolition of the construction at the owner’s expense."
Considerando III.4
"Cabe recordar a las empresas recurrentes, que la sanción prevista en el artículo 96 de la Ley de Construcciones, para quienes hayan edificado obras, sin que de previo la Municipalidad competente les hubiera otorgado la licencia constructiva, y sin que, realizadas las dos prevenciones para que se pusieran a derecho, lo hicieran en los plazos concedidos al efecto (artículos 93 y 94 de la Ley de Construcciones) , consiste en la demolición de lo construido, lo cual, se hará por cuenta del propietario (artículo 96 de la Ley de Construcciones)."
Considerando III.4
Full documentDocumento completo
Administrative Litigation Court, Main Line 2545-00-03 Fax 2545-00-33 Email ...01 _______________________________________________________________________ CASE FILE: 11-006398-1027-CA MATTER: MUNICIPAL APPEAL APPELLANTS: CONDOMINIOS PURA VIDA EN EL MAR S.A. AND ANOTHER RESPONDENT: MUNICIPALIDAD DE CARRILLO No. 139-2013 ADMINISTRATIVE LITIGATION COURT. THIRD SECTION, ANNEX A OF THE II JUDICIAL CIRCUIT OF SAN JOSÉ. Goicoechea, at sixteen hours and twenty-five minutes on cuatro de abril del dos mil trece.- Appeal filed by Nombre103330, identity card number CED79342, in his capacity as Treasurer with powers of an unlimited general attorney-in-fact (Apoderado Generalísimo sin límite de suma) of the company CONDOMINIOS PURA VIDA EN EL MAR. S.A., corporate identification number CED79343, and Nombre71470, identity card number CED79344, in his capacity as President with powers of an unlimited general attorney-in-fact of the company S.A. LAZAR ABOGADOS Y NOTARIOS, corporate identification number CED12250; against the decision issued at eight hours and forty-five minutes on dos de setiembre del dos mil once by the ALCALDÍA MUNICIPAL DE CARRILLO.- Opinion drafted by Judge Álvarez Molina, with the concurring votes of Judge Solano Ulloa and Judge Muñoz Chacón; and,
WHEREAS:
The following facts relevant to these proceedings are deemed duly established:
The representative of Condominios Pura Vida en el Mar, S.A. alleges that the decision issued at eight forty-five a.m. on September second, two thousand nine, by the Mayor of the Municipality of Carrillo is contrary to law for the following reasons: i) He maintains that construction of the project did in fact begin; that the construction permit has been pending since 2006; and that the final stage was practically complete when the respondent Municipality conducted the inspection in 2009; ii) That they did pay the construction tax, contrary to the Municipality’s assertion; iii) That the demolition order issued by the Municipal Mayor’s Office would cause environmental harm to the area, given the scale of the project; iv) He alleges that the completed construction has caused no environmental harm because the project is not located within a biological reserve and the site has no springs (nacientes), mangroves, or other environmentally significant features; v) That, during the processing of the construction permit, circumstances beyond his control prevented him from meeting the requirements imposed by the respondent Municipality, such as obtaining renewed confirmation of water availability, because although the Instituto Costarricense de Acueductos y Alcantarillados had already granted it, the municipal authority does not recognize it.
For his part, the representative of S.A. Lazar Abogados y Notarios states that “…I hereby adopt each and every one of the arguments advanced…” in the subsidiary appeal (recurso de apelación en subsidio) filed by Condominios Pura en el Mar, S.A. He further alleges that “…in its capacity as trustee (fiduciaria) of the aforementioned properties, it has never been notified by the Municipalidad de Carrillo of any type of issue, whether a WARNING OR REQUIREMENT (PREVENCIÓN O REQUERIMIENTO), that must be addressed with respect to those properties or the structures located thereon, even though the information concerning the title held by my client is public information recorded in the Registro Nacional and accessible to any person…” (folios 160, 161, 165 and 165 of the case file (expediente)).
Based on a comprehensive analysis of the arguments and the case file, this Chamber concludes that the decision issued at ocho horas cuarenta y cinco minutos del dos de setiembre del dos mil once by the Office of the Mayor of Carrillo must be affirmed for the reasons set forth below:
Consequently, this Tribunal finds that it is not a legally valid argument to allege that, because the residential complex has been substantially completed and because there are allegedly no springs (nacientes), mangroves, biological reserves, or other elements of environmental importance in that area, the demolition order issued by the respondent entity is unjustified. This is because it is an established fact, demonstrated not only by the evidence contained in the case file but also by the appellants’ own statements, that they constructed a project consisting of 16 buildings, comprising a total of 38 condominium dwellings, without first obtaining a building permit (licencia de construcción). Furthermore, they continued construction even though the then-owner of the properties was served with four notices to bring the project into legal compliance, which she failed to do, since the application for a building permit remains pending approval (folios 64 a 66, 68, 84, 85, 101 a 103, 118 a 121 del expediente).
Such conduct is substantially contrary to Articles 74 and 89(a) of the Construction Law (Ley de Construcciones). Accordingly, the arguments presented are without merit. 5) Conclusion (Corolario). In view of the foregoing, this Tribunal does not find that the challenged administrative act (acto impugnado) lacks the elements necessary for its validity, because it states its grounds in accordance with Article 136 of the General Law of Public Administration (Ley General de la Administración Pública); it identifies the basis giving rise to it and was issued in compliance with the formal requirements of the administrative procedure (procedimiento administrativo) established in Sections 93 et seq. of the Ley de Construcciones. The challenged action (conducta impugnada) must therefore be affirmed, as it hereby is, and the administrative remedies are consequently deemed exhausted. In light of the foregoing, the appeal (recurso de apelación) is denied, and the decision issued at eight forty-five a.m. on September second, two thousand eleven, by the Office of the Mayor of Carrillo is therefore affirmed. The administrative remedies are deemed exhausted.-
THEREFORE.
The challenged act is affirmed, and administrative remedies are deemed exhausted.- Evelyn Solano Ulloa Marianella Álvarez Molina Francisco J. Muñoz Chacón CASE FILE: 11-006398-1027-CA MATTER: MUNICIPAL APPEAL APPELLANT: CONDOMINIOS PURA VIDA EN EL MAR S.A. AND ANOTHER PARTY RESPONDENT: MUNICIPALIDAD DE CARRILLO 3
Tribunal Contencioso Administrativo, Central 2545-00-03 Fax 2545-00-33 Correo Electrónico ...01 _______________________________________________________________________ ASUNTO: APELACIÓN MUNICIPAL RECURRENTE: CONDOMINIOS PURA VIDA EN EL MAR S.A. Y OTRO RECURRIDA: MUNICIPALIDAD DE CARRILLO No. 139-2013 TRIBUNAL CONTENCIOSO ADMINISTRATIVO. SECCIÓN TERCERA, ANEXO A DEL II CIRCUITO JUDICIAL DE SAN JOSÉ. Goicoechea, a las dieciséis horas veinticinco minutos del cuatro de abril del dos mil trece.- Recurso de apelación interpuesto por Nombre103330 , cédula de identidad número CED79342, en su condición de Tesorero con facultades de Apoderado Generalísimo sin límite de suma de la empresa CONDOMINIOS PURA VIDA EN EL MAR. S.A., cédula jurídica número CED79343 y Nombre71470 , cédula de identidad número CED79344, en su carácter de Presidente con facultades de Apoderado Generalísimo sin límite de suma de la sociedad S.A. LAZAR ABOGADOS Y NOTARIOS, cédula jurídica número CED12250; contra la resolución de las ocho horas cuarenta y cinco minutos del dos de setiembre del dos mil once, dictada por la ALCALDÍA MUNICIPAL DE CARRILLO.- Redacta la jueza Álvarez Molina, con el voto afirmativo de la jueza Solano Ulloa y del juez Muñoz Chacón; y,
CONSIDERANDO:
Io.- HECHOS PROBADOS. Se tienen como debidamente acreditados los siguientes hechos que resultan relevantes para este proceso:
IIo.- OBJETO DEL RECURSO. El representante de la empresa Condominios Pura Vida en el Mar, S.A., alega que la resolución de las ocho horas cuarenta y cinco minutos del dos de setiembre del dos mil nueve, dictada por el Alcalde Municipal de Carrillo, resulta contraria a derecho por las siguientes razones: i) Sostiene que sí se inició la construcción del proyecto; que el permiso de construcción se encuentra en trámite desde el 2006 y que la última etapa estaba prácticamente terminada, al momento en que la Municipalidad recurrida realizó la inspección del año 2009; ii) Que sí realizaron el pago del impuesto sobre la construcción, contrario a lo indicado por la Municipalidad; iii) Que la orden de demolición dispuesta por la Alcaldía Municipal, causaría un daño ambiental a la zona, dada la envergadura de la obra; iv) Alega que con la construcción realizada no se ha producido daño al ambiente, porque la obra no se encuentra en una reserva biológica, no cuenta con nacientes, manglares u otro elemento ambiental de importancia; v) Que en la tramitación del permiso de construcción, situaciones ajenas a su voluntad le han impedido cumplir los requisitos solicitados por la Municipalidad recurrida, como por ejemplo: obtener una nueva disponibilidad de agua, pues aunque el Instituto Costarricense de Acueductos y Alcantarillados ya se la había otorgado, el ente municipal no la reconoce.
Por su parte, el representante de la sociedad S.A. Lazar Abogados y Notarios, indica que “…hago propios todos y cada uno de los argumentos esgrimidos…” en el recurso de apelación en subsidio interpuesto por la empresa Condominios Pura en el Mar, S.A. Asimismo alega, que “…en su condición de fiduciaria de los inmuebles antes indicados, nunca ha siso apercibida por la Municipalidad de Carrillo de ningún tipo de problema; ya sea (PREVENCIÓN O REQUERIMIENTO) que deba atenderse con respecto a dichos inmuebles o las construcciones que sobre los mismos se ubican, a pesar de que la información sobre el título que ostenta mi representada es información pública que consta en el Registro Nacional y de acceso para cualquier persona…” (folios 160, 161, 165 y 165 del expediente).
IIIo.- SOBRE EL CASO CONCRETO. A partir de un análisis integral de las argumentaciones así como del expediente, concluye esta Cámara que la resolución de las ocho horas cuarenta y cinco minutos del dos de setiembre del dos mil once, dictada por la Alcaldía Municipal de Carrillo, debe confirmarse por las razones que de seguido se exponen:
POR TANTO.
Se confirma el acto impugnado y se da por agotada la vía administrativa.- Evelyn Solano Ulloa Marianella Álvarez Molina Francisco J. Muñoz Chacón ASUNTO: APELACIÓN MUNICIPAL RECURRENTE: CONDOMINIOS PURA VIDA EN EL MAR S.A. Y OTRO RECURRIDA: MUNICIPALIDAD DE CARRILLO 3
Document not found. Documento no encontrado.