Res. 05811-2011 Sala Constitucional · Sala Constitucional · 10/05/2011
OutcomeResultado
The Chamber granted relief only because the resident’s request went unanswered and ordered a response within five days, but declined to require the municipality to build a retaining wall or decide responsibility for stabilizing the slope in amparo proceedings.La Sala acogió el amparo únicamente por falta de respuesta a la gestión del recurrente y ordenó contestarla en cinco días, pero rechazó atribuir al municipio la construcción del muro de contención o decidir en amparo la responsabilidad por estabilizar el talud.
SummaryResumen
The Constitutional Chamber decided an amparo filed by a resident who attributed the instability of a slope adjoining several homes to work performed by the Municipality of Heredia and sought a retaining wall, drainage works, and an answer to a pending request. The Chamber found that the risk had been addressed through technical studies by municipal officials and the National Emergency Commission. Those studies identified vulnerability associated with the steep incline, the homes’ proximity to the slope, heavy rainfall, and stormwater discharges, but did not establish that municipal works caused the instability. It held that responsibility for constructing stabilization works was a civil-law matter that could not be decided in summary amparo proceedings, while warning that the municipality must use its powers to order and supervise whatever measures are required to prevent the slope from collapsing. The Chamber nevertheless granted the claim concerning the right of petition because the mayor had not answered the resident’s February 18, 2011 letter.La Sala Constitucional resolvió un recurso de amparo promovido por un vecino que atribuía a trabajos de la Municipalidad de Heredia la inestabilidad de un talud contiguo a varias viviendas y solicitaba la construcción de un muro de contención, obras de alcantarillado y respuesta a una gestión pendiente. La Sala consideró acreditado que la situación de riesgo había sido atendida mediante estudios técnicos municipales y de la Comisión Nacional de Emergencias. Esos estudios identificaron vulnerabilidad asociada con la pendiente, la proximidad de las viviendas, las lluvias y los desfogues de aguas pluviales, sin demostrar que las obras municipales hubieran causado la inestabilidad. Determinó que la responsabilidad por las obras de estabilización corresponde discutirse en la jurisdicción civil, no mediante amparo, aunque advirtió que el municipio debe ordenar y fiscalizar las medidas necesarias para impedir el desplome. Sin embargo, acogió el recurso por violación del derecho de petición, pues el alcalde no respondió la nota presentada el 18 de febrero de 2011.
Key excerptExtracto clave
Responsibility for the works that must be constructed to maintain the slope’s stability is a matter of civil law and is not to be decided through summary amparo proceedings. Therefore, insofar as the claimant seeks a declaration that the Municipality of Heredia violated the local residents’ right to safety by carrying out works that destabilized the slope, and that this injury must be remedied by requiring it to construct a retaining wall, the amparo must be denied. This is subject to the warning that, within the scope of its powers, the Municipality must order and supervise the execution of the works required to prevent the slope from collapsing. In this matter, it has neither been demonstrated nor alleged that the Municipal Mayor of Heredia answered the claimant’s letter of February 18, 2011; this part of the claim must therefore be granted, and the respondent must be ordered to answer that letter and serve the response within five days following notice of this judgment. The amparo is granted solely for violation of the right of petition. José Manuel Ulate Avendaño, Municipal Mayor of the Central Canton of Heredia, or whoever holds that office, is ordered to answer the claimant’s letter of February 18, 2011 and serve the response upon him within five days following notice of this judgment. The amparo is denied in all other respects.La responsabilidad de las obras que deben levantarse para mantener la estabilidad del talud es una cuestión de derecho civil y no a dirimir en la vía sumaria del amparo. Por ello, en cuanto el actor solicita declarar que la Municipalidad de Heredia violó el derecho a la seguridad de los vecinos del lugar, con la ejecución de obras que falsearon el talud y que esa lesión debe remediarse endilgándole la construcción de un muro de retención, el amparo debe declararse sin lugar. Lo anterior, bajo la advertencia que la Municipalidad deberá ordenar y fiscalizar, en el marco de sus competencias, que se ejecuten las obras que se requiera para evitar que el talud se desplome. En este asunto, no se demuestra ni alega que el Alcalde Municipal de Heredia haya contestado la nota del recurrente del 18 de febrero de 2011, por lo que este extremo del recurso debe acogerse, ordenando al recurrido contestar la nota señalada y notificar la respuesta en los cinco días siguientes a la notificación de la presente sentencia. Se declara con lugar el recurso únicamente por violación del derecho de petición. Se ordena a José Manuel Ulate Avendaño, Alcalde Municipal del Cantón Central de Heredia, o a quien ocupe su cargo, contestar la nota del recurrente del 18 de febrero de 2011 y notificarle la respuesta, en los cinco días siguientes a la notificación de esta sentencia. En lo demás, se declara sin lugar el amparo.
Pull quotesCitas destacadas
"El vínculo con los primeros derechos enunciados nace de la denuncia de encontrarse varias personas en una situación de riesgo que se considera no ha sido atendida con celeridad."
"The connection with the first rights mentioned arises from the allegation that several people are in a risk situation that is considered not to have been addressed promptly."
Considerando IV
"El vínculo con los primeros derechos enunciados nace de la denuncia de encontrarse varias personas en una situación de riesgo que se considera no ha sido atendida con celeridad."
Considerando IV
"El deber de resolver no implica la obtención de una respuesta favorable o no, pero sí la necesaria congruencia entre el objeto de lo pedido y el de lo contestado."
"The duty to decide does not entail receiving a favorable response, but it does require consistency between what was requested and what is answered."
Considerando V
"El deber de resolver no implica la obtención de una respuesta favorable o no, pero sí la necesaria congruencia entre el objeto de lo pedido y el de lo contestado."
Considerando V
"Se condena a la Municipalidad de Heredia al pago de las costas, daños y perjuicios ocasionados, los cuales se liquidarán en ejecución de sentencia de lo contencioso administrativo."
"The Municipality of Heredia is ordered to pay the resulting costs, damages, and losses, which shall be assessed in enforcement proceedings before the administrative-litigation jurisdiction."
Por tanto
"Se condena a la Municipalidad de Heredia al pago de las costas, daños y perjuicios ocasionados, los cuales se liquidarán en ejecución de sentencia de lo contencioso administrativo."
Por tanto
Full documentDocumento completo
*110043700007CO* CONSTITUTIONAL CHAMBER OF THE SUPREME COURT OF JUSTICE. San José, at sixteen hours and eighteen minutes on the tenth of May of two thousand eleven.
Amparo appeal (recurso de amparo) filed by Alexander García Sandí, identity card 0104580610, against the Municipalidad de Heredia.
Background:
Justice Guerrero Portilla writes the opinion; and, Whereas (Considerando):
I.Subject matter of the appeal. The petitioner requests that the Municipalidad del Cantón Central de Heredia be ordered to undertake work to stabilize an embankment adjoining his home and to respond to the letter that he addressed to the entity’s Mayor on 18 February 2011.
II.Proven facts. The following facts are considered duly established and relevant to the disposition of this matter, either because they have been proven or because the respondent failed to address them as ordered in the initial ruling:
IV.Merits. The application for constitutional relief (amparo) filed by the plaintiff concerns the right to safety and physical integrity, as well as the right of petition. The connection with the first rights listed arises from the allegation that several persons are in a situation of risk that is considered not to have been addressed promptly (see, e.g., judgment #2006-16035 issued at 9:38 a.m. on 3 November 2006). However, the report submitted under oath by the municipal officials involved, together with the documents they provided, shows that the matter has in fact been addressed. The technical report requested in September 2010 was prepared in February 2011, and its conclusions identify a situation of vulnerability, although one caused not by the Municipalidad but by the distance between the petitioner’s home and those of other residents and by the gradient of the slope (talud). Likewise, neither the evidence submitted by the parties nor, in particular, the report of the Comisión Nacional de Prevención de Riesgos y Atención de Emergencias indicates that the risk was caused by municipal works.
Responsibility for the works that must be constructed to maintain the stability of the slope is a matter of civil law and is not to be decided in summary amparo proceedings (vía sumaria del amparo). Therefore, insofar as the plaintiff requests a declaration that the Municipalidad de Heredia violated the right to safety of the local residents by carrying out works that destabilized the slope and that this violation must be remedied by requiring it to construct a retaining wall, the application must be denied. The foregoing is subject to the caveat that the Municipalidad must, within the scope of its authority, order and oversee the performance of the works required to prevent the slope from collapsing.
V.With regard to the right of petition and prompt response, governed by Article 27 of the Political Constitution and Article 32 of the Law on Constitutional Jurisdiction, that right requires public officials to decide requests submitted by persons subject to the Administration within ten business days from the date on which such requests are filed, unless another response period has been specified; provided that the Chamber shall assess any reasons offered for deeming that period insufficient, in light of the circumstances and nature of the matter, in which case the Administration remains obligated to inform the petitioner of the reasons for the delay in issuing its decision. In any event, the duty to decide does not entail receiving either a favorable or unfavorable response, but it does require consistency between the subject matter of the request and that of the response.
VI.In this matter, it has neither been shown nor alleged that the Mayor of the Municipalidad de Heredia responded to the petitioner’s letter of 18 February 2011. This portion of the application must therefore be granted, and the respondent must be ordered to answer that letter and serve notice of the response within five days following service of this judgment.
Por tanto:
The application is granted solely as to the violation of the right of petition. José Manuel Ulate Avendaño, Mayor of the Cantón Central de Heredia, or whoever holds that office, is ordered to answer the petitioner’s letter of 18 February 2011 and serve notice of the response upon him within five days following service of this judgment. In all other respects, the application for amparo is denied. The Municipalidad de Heredia is ordered to pay the legal costs, damages, and losses caused, which shall be assessed during enforcement of the judgment in the administrative litigation proceedings. The aforementioned official is advised that, pursuant to Article 71 of the Law on Constitutional Jurisdiction, any person who receives an order issued in an amparo proceeding that he or she must comply with or cause to be complied with, and who fails to comply with it or cause it to be complied with, shall be subject to imprisonment for three months to two years, or a fine of twenty to sixty day-fines, provided that the offense is not subject to a more severe penalty. This decision shall be served personally upon the respondent.
Ana Virginia Calzada M.
President Ernesto Jinesta L.
Fernando Cruz C.
Fernando Castillo V.
Ricardo Guerrero P.
Jorge Araya G.
Enrique Ulate C.
*110043700007CO* SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las dieciséis horas y dieciocho minutos del diez de mayo del dos mil once.
Recurso de amparo interpuesto por Alexander García Sandí, cédula de identidad 0104580610, contra la Municipalidad de Heredia.
Resultando:
Redacta el Magistrado Guerrero Portilla; y,
Considerando:
I.Objeto del recurso. Solicita el recurrente se ordene a la Municipalidad del Cantón Central de Heredia adoptar las obras de estabilización de un talud colindante con su vivienda y sea contestada la nota que dirigió al Alcalde del ente el 18 de febrero de 2011.
II.Hechos probados. De importancia para la decisión de este asunto, se estiman como debidamente demostrados los siguientes hechos, sea porque así han sido acreditados o bien porque el recurrido haya omitido referirse a ellos según lo prevenido en el auto inicial:
IV.Sobre el fondo. El amparo planteado por el actor se relaciona con el derecho a la seguridad e integridad física, así como con el derecho de petición. El vínculo con los primeros derechos enunciados nace de la denuncia de encontrarse varias personas en una situación de riesgo que se considera no ha sido atendida con celeridad (v., p.ej., la sentencia #2006-16035 de las 9:38 horas del 3 de noviembre del 2006). Sin embargo, del informe rendido bajo juramento por los funcionarios municipales involucrados y los documentos que aportan se evidencia que el caso sí se ha atendido. Que el informe técnico que se requirió en setiembre de 2010 fue elaborado en febrero de 2011 y las conclusiones que contiene señalan una situación de vulnerabilidad, pero no causada por la Municipalidad, sino por la distancia que media entre la vivienda del recurrente y otros vecinos y la pendiente del talud. Asimismo ni la prueba aportada por las partes ni, en especial, el informe de la Comisión Nacional de Prevención de Riesgos y Atención de Emergencias, señalan que el riesgo fuera provocado por obras municipales.
La responsabilidad de las obras que deben levantarse para mantener la estabilidad del talud es una cuestión de derecho civil y no a dirimir en la vía sumaria del amparo. Por ello, en cuanto el actor solicita declarar que la Municipalidad de Heredia violó el derecho a la seguridad de los vecinos del lugar, con la ejecución de obras que falsearon el talud y que esa lesión debe remediarse endilgándole la construcción de un muro de retención, el amparo debe declararse sin lugar. Lo anterior, bajo la advertencia que la Municipalidad deberá ordenar y fiscalizar, en el marco de sus competencias, que se ejecuten las obras que se requiera para evitar que el talud se desplome.
V.En lo que se refiere al derecho de petición y pronta respuesta, regulado en los artículos 27 de la Constitución Política y 32 de la Ley de la Jurisdicción Constitucional, él obliga a los funcionarios públicos a resolver las solicitudes de los administrados en el plazo de diez días hábiles a partir de la fecha de presentación de tales gestiones, a falta de que no se hubiere señalado otro plazo para contestar, con la salvedad que la Sala apreciará las razones que se aduzcan para considerar insuficiente ese plazo, atendidas las circunstancias y la índole del asunto, en cuyo caso la Administración siempre está obligada a comunicarle al petente las causas de la demora en pronunciarse. En todo caso, el deber de resolver no implica la obtención de una respuesta favorable o no, pero sí la necesaria congruencia entre el objeto de lo pedido y el de lo contestado.
VI.En este asunto, no se demuestra ni alega que el Alcalde Municipal de Heredia haya contestado la nota del recurrente del 18 de febrero de 2011, por lo que este extremo del recurso debe acogerse, ordenando al recurrido contestar la nota señalada y notificar la respuesta en los cinco días siguientes a la notificación de la presente sentencia.
Por tanto:
Se declara con lugar el recurso únicamente por violación del derecho de petición. Se ordena a José Manuel Ulate Avendaño, Alcalde Municipal del Cantón Central de Heredia, o a quien ocupe su cargo, contestar la nota del recurrente del 18 de febrero de 2011 y notificarle la respuesta, en los cinco días siguientes a la notificación de esta sentencia. En lo demás, se declara sin lugar el amparo. Se condena a la Municipalidad de Heredia al pago de las costas, daños y perjuicios ocasionados, los cuales se liquidarán en ejecución de sentencia de lo contencioso administrativo. Se advierte al funcionario dicho que, de conformidad con el artículo 71 de la Ley de la Jurisdicción Constitucional, se impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo y no la cumpliere o no la hiciere cumplir, siempre que el delito no esté más gravemente penado. Notifíquese al recurrido la presente resolución en forma personal.
Ana Virginia Calzada M.
Presidenta Ernesto Jinesta L.
Fernando Cruz C.
Fernando Castillo V.
Ricardo Guerrero P.
Jorge Araya G.
Enrique Ulate C.
Document not found. Documento no encontrado.