Res. 21942-2024 Sala Constitucional · Sala Constitucional · 01/08/2024

Order to Build Sewers and Treatment PlantsOrden de construir alcantarillado y plantas de tratamiento

View document ↓ Ver documento ↓ View original source ↗ Ver fuente original ↗

Loading…Cargando…

OutcomeResultado

Partially grantedParcialmente con lugar

The Chamber ordered AyA and the municipalities of Quepos, Golfito, and Garabito to arrange, fund, and coordinate sewers and treatment plants within the prescribed deadlines, but denied the claim against the Ministry of Finance and referred the Palmares issues to the earlier case.La Sala ordenó al AyA y a las municipalidades de Quepos, Golfito y Garabito gestionar, presupuestar y coordinar alcantarillados y plantas de tratamiento dentro de los plazos fijados, pero rechazó el amparo contra el Ministerio de Hacienda y remitió lo relativo a Palmares al expediente anterior.

SummaryResumen

The Constitutional Chamber partially granted the amparo because effective measures had not been taken to address wastewater sanitation in Quepos, Golfito, and Garabito. It found that AyA failed to implement the loan approved for the Priority Areas Sanitation Program, did not timely answer the Ministry of Finance’s requests, and presented no alternative strategy when the credit operation was closed. The municipalities likewise failed to undertake concrete, coordinated efforts to secure compliance with the applicable sanitation duties. This institutional inaction violated the applicant’s right to a healthy and ecologically balanced environment. The Chamber ordered AyA and the local governments to arrange and coordinate, within eighteen months, construction of sewer systems and wastewater treatment plants, allocate the necessary budget, and provide a schedule that the applicant could monitor. Completion must occur within a reasonable period not exceeding two years. The claim against the Ministry of Finance was denied because responsibility for the challenged omissions was not attributable to that ministry.La Sala Constitucional declaró parcialmente con lugar el amparo por la falta de acciones efectivas para solucionar el saneamiento de aguas residuales en Quepos, Golfito y Garabito. Determinó que el AyA no ejecutó el préstamo aprobado para el Programa de Saneamiento en Zonas Prioritarias, no respondió oportunamente a los requerimientos del Ministerio de Hacienda ni presentó una estrategia alternativa ante el cierre de la operación crediticia. También reprochó a las municipalidades la ausencia de gestiones concretas y coordinadas para impulsar el cumplimiento de las obligaciones legales de saneamiento. Esa inactividad vulneró el derecho del recurrente a un ambiente sano y ecológicamente equilibrado. La Sala ordenó al AyA y a los gobiernos locales gestionar y coordinar, dentro de dieciocho meses, la construcción de alcantarillado y plantas de tratamiento, presupuestar los recursos y entregar un cronograma fiscalizable; las obras deberán concluir en un plazo razonable no mayor de dos años. El amparo fue rechazado respecto del Ministerio de Hacienda.

Key excerptExtracto clave

Accordingly, the alleged violation of fundamental rights attributable to the Ministry of Finance is ruled out; the claim against AyA is granted because this Chamber observes that the respondent authority has not only failed to provide a definitive solution to the reported problems, but the record also does not show that it devised a different strategy following the closure of the loan entered into with Germany’s KfW. In sum, there is no indication that significant efforts were made to implement the loan agreement financing the Priority Areas Sanitation Program or that the necessary actions were taken in coordination with the relevant municipal and health authorities to provide solutions for the lack of water sanitation. Consequently, the claim against the Costa Rican Institute of Aqueducts and Sewers and the municipalities of Jacó, Golfito, and Quepos must be granted because the applicant’s right to a healthy and ecologically balanced environment was violated. The amparo is partially granted for violation of the right to a healthy and ecologically balanced environment. Insofar as the claim is directed in part against the Municipality of Palmares and the Costa Rican Institute of Aqueducts and Sewers regarding that municipality, this matter shall be severed for processing in case 02-7556-0007-CO. Insofar as the claim is directed against the municipalities of Garabito, Golfito, and Nombre02 and the Costa Rican Institute of Aqueducts and Sewers regarding those municipalities, the claim is granted.Así las cosas, se descarta la vulneración a los derechos fundamentales que se atribuyen al Ministerio de Hacienda; y se acoge el recurso en cuanto se dirige contra el AyA, pues observa esta Sala que la autoridad recurrida no sólo no ha brindado una solución definitiva a los problemas denunciados, sino que tampoco se desprende que haya diseñado una estrategia distinta, ante el cierre del préstamo suscrito con el KFW, de Alemania. En suma, no se observa que se hayan hecho esfuerzos importantes para hacer efectivo el contrato de préstamo para financiar el programa de saneamiento de zonas prioritarias o que se tomaran acciones necesarias en coordinación con las instancias municipales y sanitarias que corresponden, a fin de brindar las soluciones a la falta de saneamiento de las aguas. Como consecuencia procede acoger el recurso en cuanto se dirige contra el Instituto de Acueductos y Alcantarillados y las municipalidades de Jacó, Golfito y Quepos, al haberse quebrantado el derecho a un ambiente sano y ecológicamente equilibrado del recurrente. Se declara parcialmente con lugar el recurso por violación del derecho a un ambiente sano y ecológicamente equilibrado. En cuanto el recurso se dirige en parte contra la Municipalidad de Palmares y el Instituto de Acueductos y Alcantarillados en lo referente a esa Municipalidad, desglósese este asunto para que sea tramitado en el expediente 02-7556-0007-CO. En cuanto el recurso se dirige contra las municipalidades de Garabito, Golfito y Nombre02 y el Instituto de Acueductos y Alcantarillados, en lo referente a esas municipalidades, se declara con lugar el recurso.

Pull quotesCitas destacadas

  • "Sin embargo, en el informe rendido por el representante del AyA recurrido, no se indica a esta Sala ni se desprende de la prueba aportada al expediente, qué desarrollo tiene el proyecto, si existiere, o qué acciones se han tomado, dirigidas a dar una solución a la falta de planta de tratamiento en los distintos cantones de Palmares, Jacó, Nombre02 y Golfito."

    "However, the report submitted by the respondent AyA representative neither informs this Chamber, nor does the evidence in the record show, what progress the project has made, if it exists, or what actions have been taken to solve the lack of treatment plants in the various cantons of Palmares, Jacó, Nombre02, and Golfito."

    Considerando V

  • "Sin embargo, en el informe rendido por el representante del AyA recurrido, no se indica a esta Sala ni se desprende de la prueba aportada al expediente, qué desarrollo tiene el proyecto, si existiere, o qué acciones se han tomado, dirigidas a dar una solución a la falta de planta de tratamiento en los distintos cantones de Palmares, Jacó, Nombre02 y Golfito."

    Considerando V

  • "Como en otras ocasiones se ha expuesto, comprende este Tribunal, que algunos problemas ambientales requieren coordinación entre diversas instancias estatales; sin embargo, ello no justifica que el AyA dentro del ámbito de sus competencias y en atención a las necesidades de los administrados, decida en este caso, simplemente no responder a las notas enviadas por el Ministerio de Hacienda que le instan desde el 2022; y no presentara el plan de acción que se le pidió para establecer una planificación clara y precisa para lograr la pronta aceleración del contrato de préstamo para financiar el programa de saneamiento de zonas prioritarias."

    "As this Court has stated on other occasions, it understands that some environmental problems require coordination among several state institutions; however, this does not justify AyA, within its sphere of authority and in view of residents’ needs, simply deciding not to answer the notices sent by the Ministry of Finance since 2022 or failing to submit the requested action plan establishing clear and precise planning to promptly accelerate the loan agreement financing the Priority Areas Sanitation Program."

    Considerando V

  • "Como en otras ocasiones se ha expuesto, comprende este Tribunal, que algunos problemas ambientales requieren coordinación entre diversas instancias estatales; sin embargo, ello no justifica que el AyA dentro del ámbito de sus competencias y en atención a las necesidades de los administrados, decida en este caso, simplemente no responder a las notas enviadas por el Ministerio de Hacienda que le instan desde el 2022; y no presentara el plan de acción que se le pidió para establecer una planificación clara y precisa para lograr la pronta aceleración del contrato de préstamo para financiar el programa de saneamiento de zonas prioritarias."

    Considerando V

  • "Se les ordena a esas autoridades que prevean, dentro de sus presupuestos, las partidas necesarias para la construcción de la referida planta de tratamiento y alcantarillado, y que suministren al recurrente el detalle del presupuesto que se destinará a ese fin, así como un cronograma de las actividades, con el objeto de que pueda fiscalizar el cumplimiento de las etapas de la construcción; todo esto, en el entendido de que deberán finalizar la tarea indicada, en un término razonable, que no podrá exceder los dos años."

    "Those authorities are ordered to include in their budgets the appropriations necessary to construct the referenced treatment plant and sewer system and to provide the applicant with details of the budget allocated for that purpose, together with a schedule of activities so that compliance with each construction stage may be monitored; the specified task must be completed within a reasonable period not exceeding two years."

    Por tanto

  • "Se les ordena a esas autoridades que prevean, dentro de sus presupuestos, las partidas necesarias para la construcción de la referida planta de tratamiento y alcantarillado, y que suministren al recurrente el detalle del presupuesto que se destinará a ese fin, así como un cronograma de las actividades, con el objeto de que pueda fiscalizar el cumplimiento de las etapas de la construcción; todo esto, en el entendido de que deberán finalizar la tarea indicada, en un término razonable, que no podrá exceder los dos años."

    Por tanto

  • "Se notifica al Ministro de Salud para que coordine esfuerzos con los recurridos y fiscalice que las mencionadas plantas de tratamiento e infraestructura, se construyan en cada localidad, de conformidad con la normativa de salud."

    "The Minister of Health shall be notified to coordinate efforts with the respondents and oversee the construction of the referenced treatment plants and infrastructure in each locality in accordance with health regulations."

    Por tanto

  • "Se notifica al Ministro de Salud para que coordine esfuerzos con los recurridos y fiscalice que las mencionadas plantas de tratamiento e infraestructura, se construyan en cada localidad, de conformidad con la normativa de salud."

    Por tanto

Full documentDocumento completo

Sections

Procedural marks

Document Review *230215890007CO* SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, at nine thirty a.m. on uno de agosto de dos mil veinticuatro.

Constitutional rights action (recurso de amparo) processed under expediente nro. 23-021589-0007-CO, filed by [Nombre01 001], identity card [Valor CED02], against INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS, MINISTERIO DE HACIENDA, MUNICIPALIDADES DE GOLFITO, Nombre02 Y GARABITO, subsequently extended to include MUNICIPALIDAD DE PALMARES.

Considering the Facts:

  1. 1In a written submission received by the Secretariat of the Court at 4:48 on 5 de setiembre de 2023, the petitioner filed a constitutional rights action. He states that there is no treatment plant (planta de tratamiento) or sanitary sewer system (alcantarillado sanitario) in the central district of Palmares (a situation addressed in expediente nro. 02- 007756-0007-CO). He indicates that in Garabito, specifically Jacó, the situation is similar to that of Palmares, because residents are affected by severe anthropogenic pollution (contaminación antrópica) in their streams and rivers, causing the death of aquatic life and health problems for residents and for river and marine ecosystems. He comments that water sanitation apparently has never been a priority for the respondents. In light of this problem, the communities of Golfito, Quepos, Jacó and Palmares had been included in the Programa de Saneamiento en Zonas Prioritarias, thereby authorizing the construction of treatment plants and their respective sanitary sewer systems.Nevertheless, he complains that, through official letter MH-DM-OF-1303-2023 dated 16 de agosto de 2023, the minister of MINISTERIO DE HACIENDA informed the executive president of Instituto de Acueductos y Alcantarillados (ICAA) that the program was being canceled. This also entailed eliminating the budget and financing for the projects in the 4 communities, on the crude argument that there had been no prompt progress in carrying out the works or obtaining the necessary enabling acts (actos habilitadores). The reasoning even included the fact that the president of ICAA had asked the minister of MINISTERIO DE HACIENDA to remove the Nombre02 and Golfito projects from the schedule of activities and financing, intending to retain only the Palmares and Jacó projects. He states that none of the 4 projects will be carried out by order of the minister of MINISTERIO DE HACIENDA, who directed that the Programa de Saneamiento en Zonas Prioritarias be left without budgetary funding, a decision that irrationally prevents all the works in the 4 cities from being carried out.He alleges that the actions of the respondent authorities violate Articles 21, 50 and 89 of the Constitution because they will usher in a period of uncontrolled and irreversible environmental damage, harming the rights even of people who have not yet been born. He requests that the action be granted and that the respondents be ordered to take the appropriate measures to activate the source of financing for the treatment plant and sanitary sewer projects in Palmares, Jacó, Nombre02 and Golfito. He asks that the action be granted.
  2. 2By ruling issued at 18:08 on 12 de setiembre de 2023, the proceeding was admitted and reports were requested from the minister of MINISTERIO DE HACIENDA and the executive president of Instituto Costarricense de Acueductos y Alcantarillados (ICAA).
  3. 3Luis Alejandro Guillén Guardia, in his capacity as executive president of Instituto Costarricense de Acueductos y Alcantarillados, reports: “II. REQUEST FOR CONSOLIDATION OF ACTIONS (ACUMULACIÓN DE RECURSOS) I respectfully request that this constitutional rights action be consolidated with the action contained in Expediente of this SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA N° 02-007756-000-CO, to which a proper response was submitted on 13/09/2023 and for which we provided abundant evidence and reports that also support the present case. Reference: Through ruling N° 2000-02760 of this Honorable SALA CONSTITUCIONAL, Expediente N° 00-002499-0007-CO, issued at eleven hours and six minutes on veinticuatro de marzo del dos mil, the Court stated in its Sole Whereas clause (Único Considerando) that, because of the evident connection between the facts alleged and in order to avoid contradictory decisions, two constitutional rights actions were ordered to be processed jointly (CONSOLIDATION).III. POSITION OF AYA We fully invoke the response submitted by the institution I represent regarding the CONSTITUTIONAL RIGHTS ACTION EXPEDIENTE N° 02-007756-0007-CO. We are resubmitting all the technical documentation issued by the various institutional departments involved in the matter. WE ALSO SUBMIT NEW EVIDENCE RELATING TO OFFICIAL LETTER N° UEN-PC-2023-02218 DATED 18/09/2023, SIGNED BY SUELLEN RAMÍREZ MEJÍAS, AN OFFICIAL OF UEN PROGRAMACIÓN Y CONTROL OF INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS; IT CONSTITUTES AN EXPANSION OF THE REPORT SUBMITTED FOR EXPEDIENTE N° 02-007756-0007-CO AND COVERS THE SANITARY SEWER PROJECTS IN JACÓ, GOLFITO AND QUEPOS. The petitioner alleges that ‘( …. ) water sanitation apparently has never been a priority for the respondents. In light of this problem, the communities of Golfito, Quepos, Jacó and Palmares had been included in the Programa de Saneamiento en Zonas Prioritarias, thereby authorizing the construction of treatment plants and their respective sanitary sewer systems.’ The foregoing is wholly INADMISSIBLE; the Palmares case has been explained in the response given to the constitutional rights action Expediente 02-007756-0007-CO.As to the other projects, we attach Board of Directors Resolution N° AN-2017-358 of 11/08/358 of Instituto Costarricense de Acueductos y Alcantarillados, which provides as follows: THEREFORE, IT IS RESOLVED: A) To authorize the Institutional Head to conduct the appropriate negotiations with the government authorities so that MINISTERIO DE HACIENDA may formalize the cooperation through which the following projects are financed: • 000412 Construction of the Palmares Sanitary Sewer System • 000467 Project for Construction of the Sanitary Sewer System of the City of Nombre02 • 000471 Project for Construction of the Sanitary Sewer System of the City of Golfito • 000413 Sanitary Sewer System for the City of Jacó. B) To delegate to the Administration the verification of compliance with the legal and technical provisions arising from national legislation that apply to the Institute in the negotiations concerning this cooperation and transfer. IV. REPORT OF THE EXECUTIVE PRESIDENCY OF AYA Through Official Letter N° PRE-2023-01201 dated 13/09/2023, this Executive Presidency submits a REPORT at the request of Dirección Jurídica.

In light of this problem, the communities of Golfito, Quepos, Jacó and Palmares had been included in the Programa de Saneamiento en Zonas Prioritarias, thereby authorizing the construction of treatment plants and their respective sanitary sewer systems.

Its contents are set out below: “Based on the available financing, different scenarios for making use of the investment were proposed. The changes in the projects to be considered were due to the opposition of Municipalidad and Marina Bahía Golfito to the location of the future Wastewater Treatment Plant (Planta de Tratamiento de Aguas Residuales), as described in document PRE-2023-00493 (attached). The need to adapt to current social conditions in the Golfito Sanitary Sewer Project resulted in the proposal to carry out the Jacó and Palmares projects with a scope consistent with the available resources. During the June del 2023 mission with Banco KfW, in which MINISTERIO DE HACIENDA participated, it was determined that the borrower needed to assess the Program’s appropriateness and urgency. On this basis, through note MH-DM-OF-1303-2023 of 16 de agosto, MINISTERIO DE HACIENDA asked AyA to coordinate the appropriate actions to carry out the orderly closing of the credit operation and the other activities associated with it.

With respect to the actions that the Executive Presidency will take in response to the decision of MINISTERIO DE HACIENDA, in its capacity as borrower under Loan Agreement 28568, the Senior Administration is preparing an analysis of risks, implications and actions to be undertaken from legal, financial, technical and environmental perspectives, in order to facilitate the proposal of other alternatives and the establishment of a feasible financing strategy that will enable the program to be completed.” He asks that the action be denied.

  1. 4Erik Herrera Bonilla, in his capacity as Deputy Legal Director of the Ministerio de Hacienda, reports pursuant to Agreement number MH-DM-ACDO-0039-2023 of 17 de mayo 2023, whereby authority was delegated to him by the Minister of Finance. He states: “II. On the merits (Sobre el fondo) First, it must be noted that the Ministerio de Hacienda is the institution responsible for tax collection, oversight of the Financial Administration, allocation of financial resources to public entities, and administration of the public debt, through a sustainable fiscal policy, in order to contribute to the economic and social stability and growth of the country’s inhabitants; its creation dates back to the promulgation of Decreto Ejecutivo LV dated 14 de octubre de 1825. Pursuant to Ley N° 8131 of 18 de setiembre de 2001, published in La Gaceta N° 198 dated 16 de octubre de 2001, the Ministerio de Hacienda is the only agent legally empowered to borrow and to manage and oversee the public debt of the Central Administration; accordingly, official letter number MH-DM-OF-1303-2023 was issued under the legal authority vested in it.Furthermore, in accordance with Ley 2726 of 14 de abril de 1961, Ley Constitutiva Instituto Costarricense Acueductos y Alcantarillados, as amended, the Instituto Costarricense Acueductos y Alcantarillados is an autonomous State institution created to direct, set policies, establish and enforce regulations, carry out and promote planning, financing, and development, and resolve all matters relating to the supply of drinking water; the collection and disposal of sewage and liquid industrial waste; and the regulation of storm-sewer systems in urban areas throughout the national territory. Thus, pursuant to its powers, that institution bears not only primary authority over the subject matter but also responsibility for determining priorities for the construction of treatment plants and sanitary sewer systems, as well as the continuation of Programs it considers important for safeguarding the right to health.In this regard, the Chamber itself stated in resolution 2003-01431: VI.- Regarding the powers of the Instituto de Acueductos y Alcantarillados and the Ministerio de Salud concerning sanitary sewer systems. Without prejudice to the matters set forth in the preceding recital (considerando), the Ley General de Salud and the Ley Constitutiva del Instituto Costarricense de Acueductos y Alcantarillados establish that technical oversight of water-supply and sewer systems is jointly vested in the Instituto Nacional de Acueductos y Alcantarillados and the Ministerio de Salud. To begin with, the Ley Constitutiva del AyA expressly provides as follows: “ARTICLE 2º.- The Instituto Costarricense de Acueductos y Alcantarillados shall: a) Direct and oversee all matters pertaining to the provision to the inhabitants of the Republic of drinking-water services and the collection and disposal of sewage, liquid industrial waste, and stormwater in urban areas; (…) d) Advise other State agencies and coordinate public and private activities in all matters relating to the establishment of water-supply and sewer systems and the control of water-resource pollution; consultation with the Institute shall be mandatory in every case, and compliance with its recommendations shall be compulsory (…) g) Directly administer and operate water-supply and sewer systems throughout the country, which it shall gradually assume, taking into account expediency and the availability of resources.Systems currently administered and operated by municipal corporations may remain under their control for as long as they provide efficient service. (…) The institution is hereby authorized to enter into agreements with local bodies for the administration of such services or to administer them through mixed-membership administrative boards composed of the Institute and the respective communities, whenever advisable for improved service provision and in accordance with the applicable regulations. For the same reasons and with the same characteristics, regional administrative boards involving several municipalities may also be created;" The Ministerio de Salud, within the scope of its powers, is also directly required to act in this area. In this regard, Article 289 of the Ley General de Salud, specifically concerning sewerage, provides as follows: "Every sewer system shall remain under the technical oversight of the Ministry and the Servicio Nacional de Acueductos y Alcantarillado, and the private- or public-law persons that construct, administer, and operate such systems shall comply with the regulations issued by the Executive Branch, in consultation with the Servicio Nacional de Acueductos y Alcantarillado, governing their construction and operation and the discharge and final treatment of effluents." Under this law, the Minister responsible for the sector is tasked with issuing technical health standards with which private- or public-law natural or legal persons must comply in the matters for which the law itself so requires, including, without any doubt, matters relating to sanitary sewerage (…)” In light of the foregoing, and with respect to the condition of the treatment plant and sanitary sewer system in the central district of Palmares, human-caused pollution (contaminación antrópica) in streams and rivers in Jacó, and water sanitation, these matters fall outside the powers of this Ministry; consequently, the Instituto Costarricense de Acueductos y Alcantarillados and the respective Municipalidades are responsible for addressing those allegations.Now, through Ley número 9723 dated 14 de agosto de 2019, Loan Agreement number 28568 to Finance the Programa de Saneamiento en Zonas Prioritarias, entered into between the República de Costa Rica and Banco KFW Frankfurt am Main (hereinafter KFW), was approved for an amount of up to exactly seventy-nine million two hundred seventy-eight thousand five hundred ninety-one euros (EUR 79.278.591,00); paragraph 1.2 thereof provides: “(…) AyA and KfW shall establish, by separate agreement ("Separate Agreement"), the details of the Program and eligible projects, as well as the works, goods, and services to be financed from the Loan.” Accordingly, the Instituto Costarricense de Acueductos y Alcantarillados and KfW established, by a Separate Agreement between the two parties, the details of the Program and eligible projects, as well as the works, goods, and services to be financed from the Loan, in order to establish sanitation measures in priority areas.Therefore, contrary to the erroneous assertion made, Loan Agreement N° 28568 contains no such authorization for the construction of treatment plants and their respective sanitary sewer systems; both the works and the progress of disbursements for carrying them out are activities incumbent upon the Instituto Costarricense de Acueductos y Alcantarillados and Banco KFW, which approves them. With respect to official letter number MH-DM-OF-1303-2023, it is important to clarify that its scope does not encompass the cancellation of a Program, but rather the coordination of the appropriate actions to achieve the orderly closeout of the credit operation and other activities associated solely with financing. This request arose from statements by the Instituto Costarricense Acueductos y Alcantarillados regarding its inability to complete, in terms of number and scope, the projects initially agreed upon with KFW using the amount of the loan agreement.In addition, the Ministerio de Hacienda, representing the Government and acting as Borrower under KfW Loan Agreement 28568, informed the executive president of the Instituto Costarricense Acueductos y Alcantarillados that, pursuant to clause 3.5 of the Loan Agreement, it would provide notice of the waiver of disbursement of the loan funds not yet requested. As recorded in the cited official letter, the Instituto Costarricense Acueductos y Alcantarillados stated that it could undertake only two of the original projects, and even those not in their entirety but with a reduced scope, because investment costs had nearly tripled, increasing from EUR 65.3 millones (sin IVA) to EUR 168.5 millones (sin IVA). To do so, however, it would require a significant extension of the loan disbursement period, from 2024 to 2027, even though on 27 de setiembre it will already reach its fourth year of implementation and, as of julio 2023, the Instituto Costarricense Acueductos y Alcantarillados has disbursed only 0.04% of the loan funds and has made no progress to date on the planned works, thereby generating considerable costs for the public treasury.Accordingly, it may be concluded that the protected party’s (amparado) contention that the Ministerio de Hacienda ordered the closure of the Program is incorrect, because the Program forms part of the core functions of the Instituto Costarricense Acueductos y Alcantarillados, over which the Ministry has no authority. Likewise, it is imperative to clarify that funding is not being eliminated for the projects in the communities identified by that party, because, pursuant to its legal authority as an autonomous institution and its technical judgment, it is the Instituto Costarricense Acueductos y Alcantarillados that is responsible for determining which projects must be included in its budget. Furthermore, the waiver of disbursement of the loan amounts not yet requested is not based on scant reasoning, because there are multiple, solid, and measurable technical facts demonstrating that the financing of the Program through the credit operation has been characterized by critically poor performance during most of its implementation, as follows: • As it approached completion of its fourth year of implementation, as of julio 2023 the Program had disbursed only 0,04% of the loan funds and, even today, has made no progress on the planned works; indeed, no tender relating to the actual execution of the works has even been published or awarded. • Due to multiple problems encountered during implementation (weaknesses in pre-investment (preinversión), the need to conduct and expand various studies, identification of flood-prone areas, delays in designing the Treatment Plants, delays in drafting the terms of reference for tenders, an outdated cost base and substantial cost overruns for the planned works, limited installed capacity, among others), the Instituto Costarricense de Acueductos y Alcantarillados significantly reduced the scope of this Program, stating that it would decrease from the 4 original projects agreed upon in the aforementioned Separate Agreement to only 2, both with a reduced scope compared with that originally proposed. • Construction of those two reduced-scope works would not begin until marzo de 2025, even though implementation of this Program began on 27 de setiembre de 2019, once Ley 9723 approving the cited Loan Agreement with KfW was promulgated in La Gaceta.

• In the interests of transparency and accountability, the Ministerio de Hacienda has made available to the public, through the Ministry’s website, information related to the implementation of the external loans (créditos externos) financing various public investment programs/projects. This information shows that, for several years, the Program has faced a series of delays, problems, and periods of stagnation due to the limited implementation capacity of the Instituto Costarricense de Acueductos y Alcantarillados, which have contributed to its critical performance situation, with very little progress to date. • In this regard, since the I Semester of 2021, the Program has exhibited critical performance from which it has been unable to recover; instead, this condition has worsened over the years, despite the efforts made by this Ministry to urge the Instituto Costarricense de Acueductos y Alcantarillados to implement the Program and the loan financing it efficiently and effectively.

Evidence of the foregoing can be found in the official letters (oficios) sent to various senior officials of that Institute to warn them of these situations and request prompt solutions regarding implementation. In that regard, official letter number DM-1219-2021 dated 11 de noviembre de 2021, addressed to Mr. Tomás Martínez, Executive President of the Instituto Costarricense de Acueductos y Alcantarillados, conveyed this Ministry’s concern regarding the Program’s performance and the clear and significant delays already evident at that time, including those relating to one of the principal procurements (contrataciones) required for implementation of the Program, namely the engagement of the Implementation Consultant (Consultor de Implementación, CI), and the extensions of the deadlines for receipt of bids, which led to constant replanning in both financial matters (payments to be made) and the activity schedule.

The Instituto Costarricense de Acueductos y Alcantarillados was also informed that the types of situations observed in the specific case involving KFW were considered significant because they had also arisen in other similar programs of the Institution, creating uncertainty regarding the effectiveness and efficiency with which the lessons learned from ongoing and completed programs/projects in the Institute’s portfolio were being applied. Subsequently, the declaration that the company prequalification process (concurso de Precalificación) had yielded no successful bidder led the Instituto Costarricense de Acueductos y Alcantarillados to decide to restart the procurement processes individually, by project. The Institute was therefore advised of the concern regarding the additional period that, even at that time, it estimated it would require to complete the Program, namely 24 additional months.

With respect to the works for the PTAR Golfito, Palmares and Jacó, the Institute was also urged to continue coordinating the necessary channels of communication with stakeholders and key personnel so that it could optimize and improve stakeholder management and establish the strategic partnerships and agreements required to ensure that the works began in a timely manner, while minimizing any setbacks in their development. In its capacity as Borrower under Loan Agreement (Contrato de Préstamo) KfW 28568, this Ministerio de Hacienda stated that it was urgent and necessary for the Instituto Costarricense de Acueductos y Alcantarillados, as the Implementing Entity (Entidad Ejecutora), to coordinate the measures required to remedy its difficulties so as to make appropriate progress in implementing the Program and minimize future impacts on the implementation schedule, thereby allowing it to be completed within the contractually established period without generating cost overruns.

Accordingly, the Ministerio de Hacienda awaited notification of the measures that the Instituto Costarricense de Acueductos y Alcantarillados would implement to improve and strengthen management of the Program, so that those measures would produce and be reflected in improved implementation indicators in the short term; however, they never materialized. Consistent with the foregoing, through official letter number MH-DM-OF-2702-2022 dated 09 de noviembre del 2022, addressed to Mr. Roberto Guzmán Gutiérrez, who was then Executive President of the Instituto Costarricense de Acueductos y Alcantarillados, concern was expressed regarding the Program’s critical performance. As of that date, none of the financing had been disbursed, and the Program’s physical progress stood at 18.22%, representing less than 1% progress during the preceding year. At that time, he was advised of other matters that remained critical:

  • 1)The notice to proceed (orden de inicio) for the activities assigned to the Implementation Consultant had only been issued in agosto 2022;
  • 2)The interinstitutional agreement (convenio interinstitucional) with INCOFER, which was essential to the development of the Golfito treatment plant, had not been finalized;
  • 3)There was no clarity regarding pre-investment (preinversión) for other Program works; and
  • 4)Although the procurement of works had not yet begun, cost overruns had already been identified in their implementation. The urgency of taking advantage of the KFW mission, which was to be held during the same month of noviembre 2022, was likewise emphasized so that AyA-KfW could jointly design a plan to accelerate activities and works that would mitigate the impact of the 24 months of delays suffered by the Program, and so that the Institute would, in turn, prioritize its projects and resources to ensure adequate financing for the Program’s scope and undertake proper planning to mitigate future risks and new sources of delay. The Institute was also requested, once the KFW mission had concluded, to submit to this Ministry the action plan agreed upon by the Bank and the Instituto Costarricense de Acueductos y Alcantarillados to resume implementation of the Program, reduce the existing delay, and manage the risks that could affect it. Nevertheless, through official letter number MH-DM-OF-0143-2023 dated 2 de febrero de 2023, addressed to Mr. Alejandro Guillén Guardia, Executive President of the Instituto Costarricense de Acueductos y Alcantarillados, this Ministry was compelled to remind the Institute to submit the Action Plan requested in noviembre del 2022 through official letter MH-DM-OF-2702-2022, a request prompted by the Program’s critical status. It was also stated that the Dirección de Crédito Público of this Ministry had requested that Plan from the Program’s Implementing Unit (Unidad Ejecutora) on various occasions and that the Unit had indicated that the senior management of the Instituto Costarricense de Acueductos y Alcantarillados needed to define the courses of action to reassess the Program’s scope and its cost increases. The Institute was therefore advised that submission of the plan was of great importance in view of the critical performance results exhibited by the Program. At that time, according to the Schedule of the Separate Loan Agreement (Cronograma del Acuerdo Separado del Préstamo), the works for the four sanitation projects were clearly delayed, since they should have begun in julio de 2021, whereas the calls for tenders would not be published until the second quarter of 2023. The Instituto Costarricense de Acueductos y Alcantarillados was further informed that the complete lack of implementation of loan funds as of 31 de diciembre 2022 had a substantial impact on the Program’s monitoring indicators, considering that the loan had been in force since setiembre 2019. For the Ministerio de Hacienda, it was particularly important that the decisions required by the Program’s Implementing Unit be made and that the aforementioned Action Plan be submitted, setting forth clear and precise planning to achieve the Program’s prompt acceleration and specifying the activities, responsible parties, and compliance deadlines that would definitively resolve, among other matters, the exponential increase in the Program’s total cost. Nevertheless, the repeated requests were disregarded. Everything described above has imposed high costs on the country in the form of commitment fees (comisiones de compromiso) paid to Banco KfW. Due to the slow and almost nonexistent disbursement of the loan funds, as of 31 de julio 2023, a total of US$860.462,94 had been paid in commitment fees, while only US$33.926,09 of the loan funds had been disbursed. This reflects a highly significant disparity between the two indicators, given that more than 25 times the amount disbursed by the Bank had been paid to it in such fees. In other words, Costa Rica incurred an extremely high financial cost because the funds were not used, as compared with the actual utilization of the full amount made available by KfW for implementation by the Instituto Costarricense de Acueductos y Alcantarillados within the framework of the Program. Accordingly, acting pursuant to its powers and legal authority, seeking the greatest benefit for the República de Costa Rica, and safeguarding the public treasury (erario público), the Ministerio de Hacienda requested coordination of the appropriate actions to bring about the orderly closing of the loan operation and other associated activities solely in relation to the financing, which, nearly four years after its approval, had shown no progress and had generated only expenses disproportionate to the amounts disbursed by the Instituto Costarricense de Acueductos y Alcantarillados. At no time, however, did it order the cancellation of a program of the Instituto Costarricense de Acueductos y Alcantarillados, since the Program’s continuation does not even fall within the Ministry’s powers but rather within those of that autonomous institution. In light of the foregoing, the petitioner (recurrente) is incorrect in asserting that the Ministerio de Hacienda ordered that the Quepos, Golfito, Palmares and Jacó projects not be carried out or that it decided to leave the Programa de Saneamiento en Zonas Prioritarias without budgetary funding, which would cause irreversible environmental damage and impair the rights of people who have not yet even been born. It falls within the powers of the Instituto Costarricense Acueductos y Alcantarillados to continue the projects if it considers them necessary and to make the corresponding budget allocations required to complete them. Likewise, it cannot reasonably be alleged that the Ministerio de Hacienda violated constitutional provisions 21, 50 and 89 when its legal powers include managing the public debt through a sustainable fiscal policy intended to contribute to economic stability and growth. Accordingly, coordinating the appropriate actions to close a loan operation concerns technical and financial matters relating to the sustainability of the operation in light of its costs and expected progress.

In this regard, the Minutes of the Meeting dated 22 de junio de 2023, held in connection with the KFW supervision mission, stated the following: Extension of the disbursement period: Mention is made of the uncertainty regarding the costs to the Borrower should it terminate the Loan Agreement or in the event of a possible extension, and the need to have projected information in this regard in order to make decisions. It is emphasized that a specific amount for each matter could not be guaranteed at the time of the meeting. Despite this, the Ministry of Finance does need the aforementioned information in order to analyze realistic scenarios that support timely decision-making, and therefore requests that KfW provide an estimate in this regard. (Boldface does not appear in the original) Once reviewed from a technical standpoint and its implications assessed, this information led the Ministry of Finance to decide to request the closing of the credit transaction, as this was deemed beneficial to the interests of the State, which this Ministry protects in accordance with its powers.

It is reiterated that the decision to reduce the scope of the projects from 4 to 2, with a reduced scope under the Program, originated within the Instituto Costarricense de Acueductos y Alcantarillados itself, and the Ministry of Finance had no involvement whatsoever in it. It is also emphasized that this Ministry did not in any way instruct that the Program be left without budgetary funding, since the Instituto Costarricense de Acueductos y Alcantarillados is technically and legally capable of carrying out the Program’s works with the resources it budgets for that purpose. III. Relief Requested. On the basis of the factual and legal grounds set forth above, I request that the constitutional rights petition (recurso de amparo) filed by Mr. [Nombre01 001] be dismissed, since this Ministry, within the scope of its powers, has complied with the applicable regulations and has not violated the fundamental rights to Health, to a Healthy and Ecologically Balanced Environment, or to the Protection of Natural Beauty.”

  1. 5By order of the reporting justice issued at 7:01 a.m. on 20 de setiembre de 2023, the parties to the petition were expanded and the Minister of Health was ordered to submit a report.
  2. 6Mario Urcuyo Solórzano, in his capacity as Acting Minister of Health, reports. He states: “STATUTORY REPORT. This report is based on official letter N° MS-DPRSA-USA-1996-2023 dated 02 de octubre de 2023, issued by Eng. Eugenio Androvetto Villalobos, Director of the Dirección de Protección Radiológica y Salud Ambiental, and Eng. Ricardo Morales Vargas, Acting Head of the Unidad de Salud Ambiental, which states as follows: “In response to your inquiry, we wish to indicate that this Directorate lacks the administrative and legal authority to resolve the matter, since the specific question concerns the property boundaries (linderos) applicable to the proposed activity, an issue governed by municipal regulations and the Reglamento de Construcciones, and there is no specific Ministry of Health regulation governing the location of industries. Having reviewed official letter MS-DRRSHN-DARSCQ-0301-2023 and Technical Report MS-DRRSHN-DARSCQ-IT-606-2023, it is the opinion of this Directorate that the nuisances can be confined to the property, which is a site interpreted by the Governing Health Area (Área Rectora de Salud, ARS) as industrial, classifying the activity as harmless or a nuisance upon conducting its legal analysis; we agree with this classification of the activity.It should be noted that the Municipalidad de San Carlos, through Opinion DIC 59210, Municipal Location Decision, approved the location; therefore, in 2 accordance with Ley 8220, specifically the provisions of Article 3, that approval must remain in effect, since it was granted for the activity described as manufacturing various metal and plastic materials. Likewise, the cited company was granted the Free Trade Zone Regime (Régimen de Zona Franca) for the activities described through Agreement 268-2022, signed by the Presidencia de la República, without prejudice to its obligation to comply with all other health, environmental, labor, commercial, and tax legislation. A more fundamental issue, noted in official letter MS-DPRSA-USA-521-2023 concerning a similar case, is the reason why the Ministry provides applicants with the ‘Application for Location Permit’ form, since there is no specific legal framework requiring such a permit for the type of activity in question; Decreto 43432-S provides only the following in Article 8: ‘b.Location permit granted by the Ministry, solely for activities regulated by the following specific regulations: Decreto Ejecutivo No. 32833-S del 3 de agosto de 2005 “Reglamento general de cementerios”; Decreto Ejecutivo No. 38928-S del 14 de noviembre del 2014 “Reglamento sobre rellenos sanitarios”; Decreto Ejecutivo No. 39136-S-MINAE del 15 de junio del 2015 “Reglamento sobre condiciones de operación y control de emisiones de instalaciones para coincineración de residuos sólidos ordinarios”; Decreto Ejecutivo No. 39887-S-MINAE del 18 de abril del 2016 “Reglamento de aprobación de sistemas de tratamiento de aguas residuales” and Decreto Ejecutivo No. 33724-COMEX-MEIC-S del 8 de enero del 2007, whereby Resolución No. 176-2006 (COMIECO-XXXVIII) is published.’ The interpretation and procedure that this Directorate has generally followed, or recommended that the Governing Areas (or their Regional support units) follow, is that the Ministry should only classify the activity (harmless, a nuisance, unhealthy, or hazardous) pursuant to the Reglamento sobre Higiene Industrial, Decreto Ejecutivo N°11492-SPP, and that the respective Municipality should determine matters related to land use (uso del suelo).Considering that the legal analysis conducted by the Región Huetar Norte and the Governing Area is also sound in its comprehensive interpretation of health, industrial safety and hygiene, and construction legislation, this Directorate recommends that those regional and local levels alert or consult the Municipality regarding the inconsistencies detected between the construction and location permits granted by the local government, and that they abide by whatever the latter subsequently decides.” CONCLUSIONS. The contents of the aforementioned official letter N° MS-DPRSA-USA-1996-2023 dated 02 de octubre de 2023 demonstrate that the Ministry of Health authorities have carried out all due 3 measures to address the request made by this Constitutional Chamber. EVIDENCE. A duly certified copy of the referenced documents is submitted. RELIEF REQUESTED. In view of the foregoing, we respectfully request that this Constitutional Chamber deem the request made by order issued at seven hours and one minute on veintinueve de setiembre de dos mil veintitrés to have been addressed, as the requested response was provided in a timely and proper manner.”
  3. 7By order of the reporting justice issued at 15:05 on 19 de octubre de 2023, the parties to the petition were expanded and the mayors of Golfito, Nombre02, and Garabito were ordered to submit reports.
  4. 8Jong Kwan Kim Jin, in his capacity as Mayor of Quepos, reports. He states: “FIRST: In my capacity as legal representative of the Municipalidad de Quepos, the local government of this canton, on behalf of all residents of this honorable community, I express my full and absolute support. I likewise join in the statements made by the petitioner, Mr. [Nombre01 001], identity card CED01. SECOND: This city indeed lacks a treatment plant where sewage can receive proper treatment, and this unquestionably represents a public health problem that must be addressed urgently. This canton has waited years for a response, but no positive action has been taken by the competent authorities. THIRD: Nombre02 was indeed included in the Programa de Saneamiento en Zonas Prioritarias, with the objective of finally carrying out the construction of a treatment plant and sanitary sewer system (alcantarillado sanitario).Nevertheless, in an arbitrary manner that violated constitutional rights, it was proposed that Nombre02 be removed from the list of the 4 communities benefiting from the project, only for the ultimate decision to be made to cancel the entire program and withdraw the budget and financing already allocated for this crucial purpose benefiting 4 communities. FOURTH: As shown in the record, in Ministry of Finance Official Letter MH-DM-OF-1303-2023 dated 16 de agosto de 2023, following prior meetings between the Instituto Costarricense de Acueductos y Alcantarillados and the Ministry of Finance, this government entity, acting on behalf of the government, decided to close the Programa de Saneamiento en Zonas Prioritarias without any technical criteria supporting that decision and while showing no interest whatsoever in the needs faced daily by the residents of this canton, particularly in this area, which has serious flooding problems and no treatment plant.FIFTH: It is absolutely reprehensible for such an important project to be eliminated by an arbitrary decision of senior officials, since our community urgently needs the construction of a treatment plant and sanitary sewer system. Continuing to postpone this project represents a ticking time bomb, because the public health problem will inevitably become unsustainable in the future, and treating this wastewater now would entail less expense than later addressing a host of diseases that will result in the deaths of many living beings, including humans, animals, and marine flora and fauna.” He requests that the petition be dismissed.
  5. 9By a written submission added to the digital case file on October 27, 2023, Juan Pablo Morera, in his capacity as representative of the Asociación Cámara de Comercio, Industria, Turismo y afine de Palmares, filed a request for active intervention (coadyuvancia activa). He states: “FIRST: I request that we be recognized as active intervenors (coadyuvantes activos) in this amparo proceeding (amparo). We base our request on diffuse interests (intereses difusos) and the right to a healthy environment (derecho a un ambiente sano) established in constitutional provision 50. SECOND: As a matter of environmental social responsibility, we believe it is our duty to request that this amparo proceeding be granted and that the respondents be ordered to build the respective treatment plants and sanitary sewer systems (alcantarillados sanitarios). We place particular emphasis on the plant in Palmares de Alajuela, because we are residents of this canton and there is a constitutional ruling dating back 20 years that orders the construction of the infrastructure necessary to protect future generations.THIRD: It is perfectly clear that a situation in which a program that helps finance treatment plants and sanitary sewer systems is dismantled or broken up should not be permitted by this Chamber, because doing so harms river ecosystems and even the sea itself. Although our constitutional provision 50 does not refer to sanitation (saneamiento) as a fundamental human right, this Chamber has recognized it as such, and we request that it so rule. The protection to which we refer unquestionably arises from constitutional provisions 21 and 50, and it is essential that the standard under which the environment, life, quality of life, and ecosystems take precedence prevail; otherwise, we would be doing a disservice to our children and their children. FOURTH: We consider it essential that this Chamber take into account that, among the SUSTAINABLE DEVELOPMENT GOALS, Goal 6 states: ‘Goal 6. Ensure availability and sustainable management of water and sanitation for all.’ This, incidentally, is closely aligned with the in dubio pro aqua principle, and under those parameters we request that the amparo proceeding be granted in all respects.Every day that passes without treatment plants places the planet at greater risk, because polluted waters continue to flow from the upper watersheds (cuencas altas) of Palmares to the sea, and this must be analyzed and addressed in your ruling on this amparo proceeding. In truth, the statement that ‘efforts are being made’ to move the projects forward is simply an empty argument that should not be accepted by you, because environmental human rights are at stake, and we request that you so rule. To assert, as the respondents do, that the treatment-plant projects will not be completed because they have withdrawn from the Banco KFW Frankfurt am Main loan is a highly dangerous argument that creates uncertainty, and the fact that the respondents from the INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS were not responsible and diligent does not justify limiting the financing of the Programa de Saneamiento en Zonas Prioritarias project.Quite the contrary, we consider it essential to rule that the State, through all of its institutions, must urgently work more vigorously to complete the treatment plants and sanitary sewer systems, particularly the one in Palmares, where for 20 years we have lacked prompt and effective environmental justice (justicia ambiental pronta y cumplida). We request a ruling that the standards established by the Ministerio de Hacienda ordering the termination of the Banco KFW Frankfurt am Main operation are constitutionally defective (viciados de inconstitucionalidad). We request a ruling that issuing a determination that deprives the treatment-plant and sanitary-sewer projects in the 4 localities of financing is irrational and violates the principle of progressivity (principio de progresividad). Finally, we must point out that we are at a global environmental crossroads, where we must not halt or restrict the financing of 4 vital projects; we therefore request that the amparo proceeding be granted.”
  6. 10Freiner Lara Blanco, in his capacity as mayor of Golfito, reports. He states: “FIRST: I, the undersigned, in my capacity as municipal mayor and as the person responsible for the health and well-being of the population of this canton of Golfito, express my absolute support for the statements made by the petitioner. SECOND: The canton of Golfito lacks a treatment plant in which sewage (agua negra) can be properly treated, which constitutes a complete violation of the right to a healthy and ecologically balanced environment (derecho a un ambiente sano y equilibrado), as well as an infringement of the universal right to public health. THIRD: The arbitrary actions of officials in eliminating this project of such great importance are completely misguided and outrageous toward our community, which urgently needs the construction of a treatment plant and sanitary sewer system. The lack of a plant puts the health of many communities at risk; in light of the foregoing, this representative of the Cantón de Golfito requests that this proceeding be granted and that the respondents be ordered to construct a treatment plant and sanitary sewer system.”
  7. 11Tobías Murillo Rodríguez, in his capacity as mayor of Garabito, reports. He states: “SOLE: Having been served with notice of the amparo proceeding under expediente N° 23-021589-0007-co, the following response is submitted in order to address the petitioner’s request: • A report is submitted regarding the matter in question, concerning the construction of treatment plants and their respective sanitary sewer systems in the Cantón de Garabito. This report will demonstrate that, through AME-530-2023-TM, dated September 26, 2023, this Mayor, seeking to resolve this problem for our community, submitted a request to the Presidente de la República. This resulted in two responses from AyA pursuant to instructions from the Presidente de la República Rodrigo Chaves Robles.” He requests that the proceeding be denied.
  8. 12By order issued at 15:58 on July 9, 2024, the proceeding was expanded and notice was served on the Alcalde de la Municipalidad de Palmares.
  9. 13Andrés Vargas Rodríguez, in his capacity as Alcalde Municipal de Palmares, reports under oath. He explains: “With respect to the water-treatment plant in the canton of Palmares, the Municipalidad is holding ongoing meetings with personnel from AYA, oficina regional de Palmares, for the purpose of coordinating the project’s development, because it falls within that institute’s authority to secure the public funds for its construction. Accordingly, the Municipalidad de Palmares is awaiting AyA’s submission of the construction project for approval, as provided in article 118 of the Ley de Construcciones: ‘ARTICLE 118. Wastewater treatment (tratamiento de aguas residuales). Wastewater must be treated and disposed of through a sanitary sewer system, septic tank (tanque séptico), or a treatment system that complies with the Reglamento de Aprobación de Sistemas de Tratamientos de Aguas Residuales, Decreto Ejecutivo N°39887-SMINAE and its amendments, or any regulations replacing it.The discharge of wastewater into the stormwater sewer system (sistema de alcantarillado pluvial) is prohibited. Furthermore, the responsible professional must comply with the provisions established by the CFIA in the CIHSE.’” He cites judgment N° 2021002888 issued at 9:30 on February 26, 2021. He adds that, pursuant to: “(…) the Ley Constitutiva del Instituto Costarricense de Acueductos y Alcantarillados, article 1°, that institute is responsible for ‘establishing policies, establishing and applying standards, carrying out and promoting the planning, financing, and development of, and resolving all matters related to, the supply of drinking water and the collection and disposal of sewage and liquid industrial waste, as well as the regulation of stormwater sewer systems in urban areas. For these purposes, the lnstituto Costarricense de Acueductos y Alcantarillados is hereby created as an autonomous State institution for the entire national territory.’

In the same vein, section 2° establishes the legal functions granted to AyA by the founding legislation, namely:

‘a) To direct and oversee all matters concerning the provision to the inhabitants of the Republic of drinking-water services and the collection and disposal of sewage, liquid industrial waste, and stormwater in urban areas; b) To determine the priority, advisability, and feasibility of the various proposed projects for constructing, renovating, expanding, or modifying aqueduct and sewerage works, which may not be carried out without its approval; c) To promote watershed conservation (conservación de las cuencas hidrográficas) and ecological protection, as well as the control of water pollution (…); g) To directly administer and operate aqueduct and sewerage systems throughout the country, assuming responsibility for them progressively in light of the advisability and availability of resources. Systems currently administered and operated by municipal corporations may remain under their authority as long as they provide efficient service.

Under no circumstances may it delegate the administration of the aqueduct and sanitary sewer systems of the Área Metropolitana.

Nor may it delegate the administration of systems for which financial responsibility exists while that responsibility rests directly with the Instituto.

The institution is authorized to enter into agreements with local bodies for the administration of such services, or to administer them through administrative boards composed jointly of the Instituto and the respective communities, whenever doing so is advisable for the improved provision of services and in accordance with the applicable regulations. For the same reasons and with the same characteristics, regional administrative boards involving several municipalities may also be created, (...)

  • i)To construct, expand, and renovate aqueduct and sewerage systems whenever necessary and advisable for the better satisfaction of national needs; and j) To oversee the proper investment of all resources allocated by the State for aqueduct and sanitary sewerage works.’ As may be seen, AyA has the statutory authority (competencia legal) to construct sanitary sewer systems for the treatment of sewage or wastewater (aguas servidas) in the canton.

THIRD: To comply with the order issued in expediente 02-007756-0007-CO, by resolution rendered at catorce horas treinta minutos del tres de febrero del dos mil quince, insofar as the Municipalidad de Palmares is concerned, it ordered “(...) that all necessary measures be taken so that, within the non-extendable period of one year counted from notification of this resolution, the Regulatory Plan (Plan Regulador) for the Cantón de Palmares is provided to this Institute, so that the wastewater and sewage treatment system (sistema de tratamiento de aguas negras y residuales) for the Cantón de Palmares may be completed within the following three and a half years.” On 27 de marzo del 2023, at diez horas 00n catorce minutos, Arq. Silvia Carazo Angulo, Acting Head of the Departamento de Ingeniería Municipal, sent official letter MP-DU-108-2023 by email to the representatives of the Instituto de Acueductos y Alcantarillados for the Cantón de Palmares, Pedro Barrantes Ramírez, Head of the Oficina Cantonal de Palmares; Melvin Castro González, Director of Operations and Maintenance for the Región Central Oeste; and Tatiana Vindas Valerio, Operations and Maintenance Engineer for the Región Central Oeste, thereby delivering to them the hydrogeological variable (variable hidrogeológica) forming part of the Plan Regulador del Cantón de Palmares process and thus providing the required input so that said Institute may complete the wastewater and sewage treatment system for the Cantón de Palmares, in accordance with the Plan de Inversión de Saneamiento 20212026 de AYA.

As stated in section 1.1, Rationale, the hydrogeological study (estudio hidrogeológico) that was conducted constitutes that input and arose from the need to generate technical knowledge concerning the availability, quality, and vulnerability of groundwater resources (recurso hídrico subterráneo), so that decision-making institutions may have access to more technical and scientific information.

Accordingly, the Municipalidad de Palmares has no outstanding document requested by AyA that would prevent this Institute from completing the wastewater and sewage treatment system for the Cantón de Palmares, since the remaining applicable legal regulations concern construction-permit procedures (trámites de construcción), governed by the Ley de Construcciones and its respective regulations, which apply nationwide and to which both public institutions are subject.” (…) REQUESTS: Therefore, since the Municipalidad de Palmares delivered the hydrogeological variable from the Plan Regulador process, which AyA required to complete the wastewater and sewage treatment system for the Cantón de Palmares, I request that the order issued to the entity I represent by the Sala Constitucional de la Corte Suprema de Justicia be deemed fulfilled.” She requests that the petition be dismissed.

  1. 14The statutory requirements have been observed in the proceedings conducted.

Magistrada Alvarado Paniagua writes the opinion; and,

Whereas:

I. SUBJECT MATTER OF THE PETITION

The petitioner states that there is neither a treatment plant (planta de tratamiento) nor a sanitary sewer system (alcantarillado sanitario) in the central district of Palmares (a situation addressed in expediente nro. 02- 007756-0007-CO). He states that the situation in Garabito, specifically Jacó, is similar to that in Palmares, because residents are affected by extensive anthropogenic pollution (contaminación antrópica) in their streams and rivers, causing the death of aquatic life and health problems for residents and for river and marine ecosystems. He comments that water sanitation (saneamiento de las aguas) apparently has never been a priority for the respondents. In light of this problem, the communities of Golfito, Quepos, Jacó and Palmares had been included in the Programa de Saneamiento en Zonas Prioritarias, thereby authorizing the construction of treatment plants and their respective sanitary sewer systems.

Nevertheless, he complains that, through official letter MH-DM-OF-1303-2023 dated 16 de agosto de 2023, the Ministro de Hacienda informed the Executive President of the Instituto de Acueductos y Alcantarillados (ICAA) that the program had been canceled. He adds that the budget and financing for the projects in the 4 communities were eliminated on the crude pretext that there had been no prompt progress in carrying out the works or obtaining the necessary enabling acts (actos habilitadores). Part of the rationale was even that the President of ICAA had asked the Ministro de Hacienda to remove the Nombre02 and Golfito projects from the schedule of activities and financing, intending to retain only the Palmares and Jacó projects. He complains that none of the 4 projects will be carried out because the Ministro de Hacienda ordered that the Programa de Saneamiento en Zonas Prioritarias be left without budgetary funding, a matter that irrationally brings all works in the 4 cities to a halt.

He alleges that the actions of the respondent authorities violate constitutional provisions 21, 50 and 89, because they will usher in a period of uncontrolled and irreversible environmental damage, impairing the rights even of people who have not yet been born. He requests that the petition be granted and that the respondents be ordered to take the appropriate steps to activate the source of financing for the treatment-plant and sanitary-sewer projects in Palmares, Jacó, Nombre02 and Golfito.

II. PROVEN FACTS

The following facts are deemed duly established and material to the adjudication of this matter, either because they have been substantiated or because the respondent authority failed to address them, as directed in the initial order:

Regarding the treatment plant and sewer systems of the Municipalidad de Palmares:

  • a)A constitutional protection action (recurso de amparo) filed by [Nombre01 001] against the Municipalidad de Palmares and the Ministerio de Salud, processed under expediente número 02-007756-0007-CO, addressed the same allegations concerning the lack of water treatment in the community of Palmares. Judgment No. 2003- 001431, issued at 00:00 horas del 21 de febrero de 2003, ordered: “THEREFORE: THE PETITION IS GRANTED. JORGE ISAAC VASQUEZ PÉREZ, IN HIS CAPACITY AS ALCALDE MUNICIPAL DE PALMARES; HEIDI RAMIREZ SANCHEZ, LUIS CARLOS ARAYA BADILLA, CORALIA PACHECO MOREIRA, OLDEMAR SEGURA RODRIGUEZ, AND MIGUEL ÁNGEL VASQUEZ, IN THEIR CAPACITY AS REGIDORES DE LA MUNICIPALIDAD DE PALMARES; AND EVERARDO RODRIGUEZ BASTOS, IN HIS CAPACITY AS PRESIDENTE EJECUTIVO DEL INSTITUTO COSTARR ICENSE DE ACUEDUCTOS Y ALCANTARILLADOS, OR WHOMEVER HOLDS THEIR RESPECTIVE OFFICES, ARE HEREBY ORDERED, UNDER PENALTY OF DISOBEDIENCE, WITHIN THE NON-EXTENDABLE PERIOD OF DOCE MESES COUNTED FROM NOTIFICATION OF THIS JUDGMENT, TO TAKE THE NECESSARY STEPS FOR THE CONSTRUCTION OF A SEWAGE TREATMENT PLANT FOR THE ENTIRE COMMUNITY OF PALMARES, WHICH SHALL INCLUDE SUBMISSION OF AN ENVIRONMENTAL IMPACT ASSESSMENT (ESTUDIO DE IMPACTO AMBIENTAL) TO SETENA.

THOSE AUTHORITIES ARE LIKEWISE ORDERED TO PROVIDE IN THEIR BUDGETS THE APPROPRIATIONS NECESSARY FOR CONSTRUCTION OF THE AFOREMENTIONED TREATMENT PLANT AND TO PROVIDE THE PETITIONER WITH A LETTER DETAILING THE BUDGET TO BE ALLOCATED FOR THAT PURPOSE AND A SCHEDULE OF ACTIVITIES, SO THAT COMPLIANCE WITH THE CONSTRUCTION PHASES MAY BE MONITORED; ALL OF THIS WITH THE UNDERSTANDING THAT THEY MUST COMPLETE THE INDICATED TASK WITHIN A REASONABLE PERIOD, WHICH MAY NOT EXCEED DOS AÑOS. IN ADDITION, EDUARDO LOPEZ C ARDENAS, IN HIS CAPACITY AS MINISTRO DE SALUD A.I., OR WHOMEVER HOLDS THAT OFFICE, IS ORDERED, UNDER PENALTY OF DISOBEDIENCE, TO COORDINATE EFFORTS WITH THE OTHER RESPONDENTS AND MONITOR THAT THE AFOREMENTIONED TREATMENT PLANT IS CONSTRUCTED IN ACCORDANCE WITH HEALTH REGULATIONS. THE ALCALDE AND THE REGIDORES DE LA MUNICIPALIDAD DE PALMARES, OR WHOMEVER HOLDS THEIR RESPECTIVE OFFICES, ARE ORDERED, UNDER PENALTY OF DISOBEDIENCE, TO PROVIDE A PERMANENT SOLUTION TO THE PUBLIC-HEALTH PROBLEM CAUSED BY THE MER CADO MUNICIPAL DE PALMARES WITHIN THE NON-EXTENDABLE PERIOD OF DOS AÑOS; AND EDUARDO LOPEZ CARDENAS, IN HIS CAPACITY AS MINISTRO DE SALUD A.I., OR WHOMEVER HOLDS THAT OFFICE, IS ORDERED, UNDER PENALTY OF DISOBEDIENCE, TO ORDER THE CLOSURE OF THE MERCADO MUNICIPAL DE PALMARES IF THE PROBLEM AT ISSUE IS NOT CORRECTED WITHIN THE INDICATED PERIOD” (see expediente número 02-007756-0007-CO, incorporated ad effectum videndi et probandi).

  • b)By interlocutory resolution (resolución interlocutoria) 2023006228 issued at 9:15 horas del 17 de marzo de 2023 in expediente 02-007756-0007-CO, this Chamber ordered: “The application alleging noncompliance (gestión de desobediencia) is partially granted solely with respect to the order concerning the construction of a sewage treatment plant for the Cantón de Palmares. Katerine Ramírez González and Filadelfo Sancho, respectively Alcaldesa and Presidente del Concejo Municipal, both of the Municipalidad de Palmares; Alexei Carrillo Villegas, in his capacity as Ministro de Salud; and Alejandro Guillén Guardia, in his capacity as Presidente Ejecutivo del Instituto Costarricense de Acueductos y Alcantarillados, or whomever holds those offices, are again directed to comply with the order issued by this Chamber in judgment No. 2003-001431 at 00:00 horas del 21 de febrero de 2003. The foregoing is subject to the warning that, should they fail to comply, the initiation of disciplinary administrative proceedings (procedimiento administrativo disciplinario) shall be ordered pursuant to artículo 53 de la Ley de la Jurisdicción Constitucional and, in addition, certified copies of the relevant records shall be forwarded to the Ministerio Público pursuant to artículo 71 de la Ley de la Jurisdicción Constitucional. As to the order concerning the Mercado Municipal de Palmares, the application is denied. Let notice be given.” (see expediente número 02-007756-0007-CO, incorporated ad effectum videndi et probandi).
  • c)On 27 de marzo del 2023, Arq. Silvia Carazo Angulo, Head of the Departamento de Ingeniería Municipal de Palmares, sent official letter MP-DU-108-2023 by email to the representatives of the Instituto de Acueductos y Alcantarillados for the Cantón de Palmares, Pedro Barrantes Ramírez, Head of the Oficina Cantonal de Palmares; Melvin Castro González, Director of Operations and Maintenance for the Región Central Oeste; and Tatiana Vindas Valerio, Operations and Maintenance Engineer for the Región Central Oeste, thereby delivering to them the hydrogeological variable forming part of the Plan Regulador del Cantón de Palmares process, an input required so that said Institute may complete the wastewater and sewage treatment system for the Cantón de Palmares in accordance with the Plan de Inversión de Saneamiento 20212026 de AYA (report of the Alcalde de Palmares).

Regarding the treatment plants and sewer systems of Jacó, Nombre02 and Golfito d) By Ley número 9723 dated 14 de agosto de 2019, Contrato de préstamo N° 28568 para financiar el programa de saneamiento de zonas prioritarias, executed with Banco KFW Frankfurt am Main (hereinafter KFW), was approved and published in Alcance 210 a la Gaceta 183 del 27 de setiembre del 2019. Said Program consists of four components for constructing infrastructure works in four cities in Costa Rica that were selected as priorities according to several technical selection criteria, including the impact on the beneficiary population and the project’s environmental and economic impact: Palmares, Jacó, Nombre02 and Golfito. It provides that wastewater-sanitation infrastructure works (obras de infraestructura para el saneamiento de aguas residuales) will be constructed in each city, including a sewer system, a water-collection network (red de recolección de aguas), and a treatment plant and, in the case of the city of Palmares, a Centro de Investigación y Formación en Tecnologías de Saneamiento. (See the report of the Ministerio de Hacienda and the Asamblea Legislativa portal: Archivo_Leyes - Contrato de préstamo N° 28568 para financiar... (asamblea.go.cr)).

  • e)On various occasions during the period from 2021 to 2023, the Ministerio de Hacienda asked AyA to coordinate the appropriate actions to carry out the orderly closure of the credit operation with the KFW bank and the other activities associated with the Project, because it had determined that the Instituto Costarricense de Acueductos y Alcantarillados had performed critically in implementing the program. The Ministerio de Hacienda expressed concern regarding the Program’s performance and the evident and significant delays experienced up to that time, including those related to one of the principal procurements required for implementation of the Program, namely, the engagement of the Implementation Consultant (Consultor de Implementación, CI), and the extensions of the deadlines for receiving bids, which led to constant replanning, both in financial matters (payments to be made) and in the schedule of activities.

The Instituto Costarricense de Acueductos y Alcantarillados was also advised that situations of the type encountered in this particular case involving KFW were considered relevant because they had also arisen in other similar Programs of the Institution, creating uncertainty as to the effectiveness and efficiency with which lessons learned from ongoing and completed Programs/projects in the Instituto’s Portfolio were being applied. Subsequently, the declaration that the corporate prequalification tender was unsuccessful (Declaración desierta del concurso de Precalificación de las empresas) led the Instituto Costarricense de Acueductos y Alcantarillados to decide to restart the procurement procedures, but individually (by project); it was therefore advised of the concern regarding the additional period that the Instituto already estimated it would require from that point to complete the Program, corresponding to an additional 24 months (see report).

  • f)With respect to the works to be carried out in Golfito, Palmares and Jacó, the Ministerio de Hacienda urged AyA to continue coordinating the necessary channels of communication with stakeholders and key personnel so that it could optimize and improve stakeholder management, thereby establishing strategic partnerships and reaching the agreements required to ensure the timely commencement of the works while minimizing any setbacks in their development (see report).
  • g)Through official letter number MH-DM-OF-2702-2022 dated 09 de noviembre del 2022, addressed to Mr. Roberto Guzmán Gutiérrez, then Executive President of the Instituto Costarricense de Acueductos y Alcantarillados, concern was expressed regarding the Program’s critical performance, as no disbursement of the financing had been made by that date and the Program’s physical progress stood at 18.22%, representing progress of less than 1% during the preceding year. At that time, other matters that remained critical were identified:
  • 1)The notice to proceed (orden de inicio) for the activities assigned to the Implementation Consultant had only been issued in agosto 2022;
  • 2)The interinstitutional agreement with INCOFER, which was essential for development of the Golfito treatment plant, had not been finalized;
  • 3)There was no clarity regarding preinvestment (preinversión) for other Program works; and
  • 4)Although procurement of the works had not yet begun, cost overruns in their implementation had already been identified. Likewise, the urgency of taking advantage of the KFW mission, which was to be held during the same month of noviembre 2022, was emphasized so that AyA-KfW could jointly design a plan to accelerate activities and works, thereby mitigating the impact of the 24 months of delays experienced by the Program, and so that the Instituto would, in turn, prioritize its projects and resources to guarantee adequate financing for the scope of the Program while undertaking proper planning to mitigate future risks and new sources of delay. The Instituto was also requested, once the KFW mission had concluded, to submit to this Ministerio the action plan agreed upon by the Bank and the Instituto Costarricense de Acueductos y Alcantarillados to restore implementation of the Program, reduce the existing delay and manage the risks that could affect it.
  • h)Through official letter number MH-DM-OF-0143-2023 dated 2 de febrero de 2023, addressed to Mr. Alejandro Guillén Guardia, Executive President of the Instituto Costarricense de Acueductos y Alcantarillados, the Ministerio de Hacienda had to remind the Instituto to submit the Action Plan requested in noviembre del 2022 through official letter MH-DM-OF-2702-2022, a request prompted by the Program’s critical status. It was also stated that the Dirección de Crédito Público of this Ministerio had requested that Plan from the Program Implementation Unit (Unidad Ejecutora del Programa) on several occasions; that Unit had indicated that the Senior Administration of the Instituto Costarricense de Acueductos y Alcantarillados needed to define the courses of action in order to reassess the scope of the Program and the increase in its costs. The Instituto was therefore advised that submission of the plan was of great importance in view of the Program’s critical performance results, since, according to the Schedule of the Separate Loan Agreement, the works for the four sanitation projects were already clearly delayed: they should have begun in julio de 2021, whereas the invitations to tender would not be published until the second quarter of 2023.
  • i)Additionally, the Instituto Costarricense de Acueductos y Alcantarillados was advised that the absence of any use of loan proceeds as of 31 de diciembre 2022 had a major impact on the Program’s monitoring indicators, considering that the loan had been in effect since setiembre 2019. For the Ministerio de Hacienda, the decisions required by the Program Implementation Unit and submission of the indicated Action Plan—which was to establish clear and precise planning for the Program’s prompt acceleration and set out the activities, responsible parties and compliance deadlines that would definitively resolve, among other matters, the exponential increase in the Program’s total cost—were of particular importance; nevertheless, the repeated requests were disregarded. (report of the Ministro de Hacienda) j) Through official letter number MH-DM-OF-1303-2023 of 16 de agosto de 2023, the Ministerio de Hacienda asked AyA to coordinate the appropriate actions to carry out the orderly closure of the credit operation and the other activities associated solely with the financing; this request arose from statements by the Instituto Costarricense Acueductos y Alcantarillados concerning its inability to complete, in terms of quantity and scope, the projects initially agreed upon with KFW using the amount of the loan agreement (see report of the Ministro de Hacienda).
  • k)In light of the changes to the treatment-plant construction projects, Ay A prepared a proposal for implementation of the Jacó and Palmares projects with a scope consistent with the available resources. However, following the Ministerio de Hacienda’s instruction to AyA, through memorandum MH-DM-OF-1303-2023 of 16 de agosto, to coordinate the appropriate actions to carry out the orderly closure of the credit operation and the other activities associated with it, the Executive Presidency of AyA is preparing an analysis of risks, implications and actions to be undertaken from legal, financial, technical and environmental perspectives, in order to facilitate the proposal of other alternatives and the definition of a feasible financing strategy that would enable completion of the program (AyA report).

III.ON THE COLLECTION, TREATMENT AND FINAL DISPOSAL OF SEWAGE (RECOLECCIÓN, TRATAMIENTO Y DISPOSICIÓN FINAL DE LAS AGUAS NEGRAS). To effectively ensure the protection of a healthy and ecologically balanced environment, the State, understood in the broad sense, has a duty to adopt the measures necessary to provide timely and effective treatment of sewage in the country’s communities. In this regard, this Constitutional Court has held that the Instituto Costarricense de Acueductos y Alcantarillados, the Municipalities and the Ministerio de Salud are responsible—within their respective areas of authority—for ensuring the proper collection, treatment and final disposal of such wastewater. Thus, in the specific case of the Instituto Costarricense de Acueductos y Alcantarillados, its own Enabling Law (Ley Constitutiva)—Ley No. 2726 de 14 de abril de 1961 y sus reformas—provides as follows:

“Article 1.- For the purpose of directing, setting policies, establishing and applying standards, undertaking and promoting the planning, financing and development of, and resolving all matters related to, the supply of drinking water and the collection and disposal of sewage and liquid industrial waste, as well as the regulatory aspects of storm-sewer systems in urban areas throughout the national territory, the Instituto Costarricense de Acueductos y Alcantarillados is hereby created as an autonomous institution of the State.” Accordingly, pursuant to Article 2 of that same body of law, that institution is responsible for (…) Directing and overseeing all matters pertaining to providing the inhabitants of the republic with drinking-water services and services for the collection and disposal of sewage, liquid industrial waste and stormwater in urban areas (…)”. Similarly, the Ley General de Salud—Ley No. 5395 de 30 de octubre de 1973—provides in Article 2 that the Executive Branch, through the Ministerio de Salud, is responsible for defining national health policy and for planning and coordinating all public and private health-related activities, as well as carrying out those activities assigned to it by law.

Likewise, Article 341 of that law establishes, among the powers of the Ministerio de Salud, the authority to order and adopt the special measures authorized by that legislation to prevent risks or harm to human health, or to prevent such risks or harm from spreading or worsening, and to prevent private parties from continuing or repeating violations. Regarding the specific matter at issue, the Ley General de Salud, in Book 1, Title 3, Chapter 3, “Obligations and Restrictions Governing the Sanitary Disposal of Excreta and Wastewater,” provides, insofar as relevant, as follows:

“Article 285.- Excreta, sewage, wastewater and stormwater shall be disposed of properly and hygienically in order to prevent contamination of the soil and natural water sources intended for human use and consumption, the creation of breeding grounds for disease vectors, and air pollution caused by conditions that compromise its purity or quality.” (Emphasis not in the original).

“Article 287.- Every natural or legal person who owns dwellings, establishments or buildings in which persons conduct their activities shall be responsible for ensuring that such property has a system for the disposal of excreta, sewage and wastewater approved by the Ministerio, and the users of dwellings, establishments or buildings shall be required to maintain that system in proper working condition.” “Article 288.- Every owner is required to connect the system for disposal of excreta, sewage, and wastewater from their property to the sanitary sewer system (alcantarillado sanitario) in places where it is operational, except in those cases recognized as proper exceptions under the relevant regulations.” Likewise, it follows from those provisions that the authorities of the Ministerio de Salud are obligated to ensure the application of and compliance with the provisions of that law and its regulations, without prejudice to the powers and obligations conferred and imposed by special laws upon other public bodies or entities within their respective fields of action (Article 337).

This thus confirms the various functions and obligations that the legal system imposes upon the Instituto Costarricense de Acueductos y Alcantarillados and the Ministerio de Salud regarding the collection, treatment, and final disposal of sewage (aguas negras). Moreover—as stated previously in the preceding recital (considerando)—those functions and obligations must be exercised in a coordinated manner to ensure administrative effectiveness and efficiency.

IV.The lack of a waste and sewage treatment plant in Palmares. The petitioner claims that, as of the date this proceeding was filed, several cantons still lacked a waste and sewage treatment plant (planta de tratamiento de desechos y aguas negras). Insofar as the proceeding concerns the lack of infrastructure in the Cantón de Palmares specifically, the AyA representative, in the report submitted in this matter, asks the Chamber to consider the provisions of ruling 03-01431, issued at 10:53 a.m. on February 21, 2003, which granted the proceeding filed on September 18, 2002, by the same petitioner, [Nombre01 002]. He recalls that, on that occasion, this Chamber ordered the respondent Instituto Costarricense de Acueductos y Alcantarillados, the Municipalidad de Palmares, and the Ministerio de Salud to begin the necessary steps to build a treatment plant within 12 months.

Indeed, in 2003, this Court ruled as follows: “The proceeding is hereby GRANTED. Jorge Isaac Vásquez Pérez, in his capacity as Alcalde Municipal de Palmares, and Heidi Ramírez Sánchez, Luis Carlos Araya Badilla, Coralia Pacheco Moreira, Oldemar Segura Rodríguez, and Miguel Ángel Vásquez, in their capacity as Regidores de la Municipalidad de Palmares, and Everardo Rodríguez Bastos, in his capacity as Presidente Ejecutivo del Instituto Costarricense de Acueductos y Alcantarillados, or whoever may hold their respective offices, are hereby ORDERED, UNDER PENALTY OF DISOBEDIENCE, within the non-extendable period of TWELVE MONTHS from service of this judgment, to take the necessary steps to construct a sewage treatment plant for the entire locality of Palmares, for which purpose an environmental impact study (estudio de impacto ambiental) must be submitted to SETENA. Those authorities are likewise ordered to provide in their budgets the appropriations necessary to construct the aforementioned treatment plant and to furnish the petitioner with a memorandum detailing the budget allocated for that purpose and a schedule of activities, so that compliance with the stages of construction may be monitored; all of this on the understanding that they must complete the specified task within a reasonable period, which may not exceed TWO YEARS.

In addition, Eduardo López Cárdenas, in his capacity as Ministro de Salud a.i., or whoever holds that office, is hereby ordered, UNDER PENALTY OF DISOBEDIENCE, to coordinate efforts with the other respondents and oversee the construction of the aforementioned treatment plant in accordance with health regulations. The Alcalde and the Regidores de la Municipalidad de Palmares, or whoever holds their respective offices, are hereby ordered, UNDER PENALTY OF DISOBEDIENCE, to provide a definitive solution to the public-health problem caused by the Mercado Municipal de Palmares within the NON-EXTENDABLE PERIOD OF TWO YEARS; and Eduardo López Cárdenas, in his capacity as Ministro de Salud a.i., or whoever holds that office, is hereby ordered, UNDER PENALTY OF DISOBEDIENCE, to order the closure of the Mercado Municipal de Palmares if the problem at issue is not corrected within the specified period.

The State, the Instituto Costarricense de Acueductos y Alcantarillados, and the Municipalidad de Palmares are ordered to pay the damages and losses caused by the facts underlying this declaration, which shall be assessed in proceedings to enforce the judgment before the contentious-administrative jurisdiction. The respondents are advised that, pursuant to Article 71 of the Ley de esta jurisdicción, any person who receives an order issued in an amparo proceeding (recurso de amparo) that they must comply with or enforce, and who fails to comply with or enforce it, shall be subject to imprisonment for three months to two years, or a fine of twenty to sixty days, provided that the offense is not punishable by a more severe penalty. This decision shall be personally served on ALL OFFICIALS MENTIONED IN THE OPERATIVE PART OF THIS JUDGMENT, or on whoever holds those same offices in their stead.

Regarding this matter, the Alcalde de la Municipalidad de Palmares informs this Chamber that, at present, with respect to that canton’s water-treatment project, on March 27, 2023, Arq. Silvia Carazo Angulo, Encargada del Departamento de Ingeniería Municipal de Palmares, sent official letter MP-DU-108-2023 by email to the Jefe de Oficina Cantonal de Palmares, the Director Operación y Mantenimiento Región Central Oeste, and the Ingeniera Operación y Mantenimiento de la Región Central Oeste, all of the Instituto de Acueductos y Alcantarillados del cantón de Palmares, thereby delivering to them the hydrogeological variable (variable hidrogeológica) forming part of the Plan Regulador del Cantón de Palmares process. This input was required so that the Institute could complete the sewage and wastewater treatment system (sistema de tratamiento de aguas negras y residuales) for the canton of Palmares, in accordance with AYA’s Plan de Inversión de Saneamiento 20212026.

He adds that the Municipalidad “is in (sic) constant meetings with AYA officials from the regional office in Palmares for the purpose of coordinating the project’s development, since that institute is responsible for obtaining the public funds for its construction. The Municipalidad de Palmares is therefore awaiting AyA’s submission of the construction project for approval, in accordance with the regulations governing wastewater treatment.” From the factual circumstances described, insofar as they concern the failure to construct the water-treatment plant in the Municipalidad de Palmares, which is alleged against that Municipalidad and the Instituto de Acueductos y Alcantarillados, this matter shall be severed for processing under expediente 02-7556-0007-CO.

V. The lack of a waste and sewage treatment plant and sewer system in Jacó, Nombre02, and Golfito

Insofar as the proceeding concerns the lack of waste and sewage treatment infrastructure and sewer systems in the municipalities of Jacó, Nombre02, and Golfito, a review of the reports submitted under oath and the evidence provided shows that, despite the need for a waste and sewage treatment plant and sewer system in those areas—in the same sense indicated in the preceding Considerando IV concerning the Municipalidad de Palmares—the respondent authorities reveal that the cantons of Jacó, Nombre02, and Golfito likewise lack the infrastructure necessary to carry out wastewater treatment processes in accordance with applicable national legislation and technical regulations.

Regarding that omission, the representative of the Ministerio de Hacienda explains to this Chamber in his report that, although a loan agreement to finance the Programa de Saneamiento de Zonas Prioritarias was approved in 2019 through ley 9723 and entered into with Banco KFW Frankfurt am Main (hereinafter KFW, published in Alcance 210 to Gaceta 183 of September 27, 2019), the fact remains that, for that program—which was intended to construct wastewater sanitation infrastructure, including a sewer system, a water collection network, a treatment plant, and, in the case of the city of Palmares, a Centro de Investigación y Formación en Tecnologías de Saneamiento—the Ministerio de Hacienda deemed it necessary for AyA to prepare an action plan, which it had already requested in November 2022 through official letter MH-DM-OF-2702-2022.

In the report, the representative of the Ministerio de Hacienda emphasizes that the Dirección de Crédito Público of that Ministry had requested on several occasions that the Unidad Ejecutora del Programa prepare a plan defining the courses of action to be taken by the Administración Superior del Instituto Costarricense de Acueductos y Alcantarillados to reassess the scope of the Program and its increased costs. This was due to the Program’s critically poor performance results, since at that time, according to the Cronograma del Acuerdo Separado del Préstamo, the works for the four sanitation projects were clearly delayed: they should have begun in July 2021, whereas the calls for tenders would not be published until the second quarter of 2023.

He further reports that the Ministerio de Hacienda warned the Instituto Costarricense de Acueductos y Alcantarillados of the severe impact on the Program’s monitoring indicators caused by the complete lack of disbursement of loan funds as of December 31, 2022, considering that the loan had entered into force in September 2019. He explains that, for the Ministerio de Hacienda, it was particularly important for the Unidad Ejecutora del Programa to make the required decisions and submit the specified action plan, establishing clear and precise planning to achieve the Program’s prompt acceleration and setting out the activities, responsible parties, and compliance deadlines that would definitively resolve, among other matters, the exponential increase in the Program’s total cost. Nevertheless, the repeated requests were disregarded.

Based on the foregoing situation, through official letter number MH-DM-OF-1303-2023 of August 2023, the Ministerio de Hacienda asked AyA to coordinate the appropriate actions for an orderly termination of the credit operation and the other activities associated with the financing. He explains that this request arose from statements by the Instituto Costarricense Acueductos y Alcantarillados concerning the impossibility of completing, in their intended number and scope, the projects initially agreed upon with KFW using the amount provided under the loan agreement.

For his part, the representative of respondent AyA adds in his report that, in view of the changes to the treatment-plant construction projects for the four cantons (Jacó, Palmares, Nombre02, and Golfito) and the directive from the Ministerio de Hacienda ordering the termination of the credit operation intended to fund that infrastructure, the Presidencia Ejecutiva del AyA is preparing an analysis of risks, implications, and actions to be undertaken from legal, financial, technical, and environmental perspectives. This analysis is intended to facilitate the proposal of other alternatives and the definition of a feasible financing strategy that will enable the Program to be carried out (AyA report).

However, the report submitted by the representative of respondent AyA neither informs this Chamber, nor does the evidence added to the expediente show, the project’s stage of development, if any, or what actions have been taken to remedy the lack of treatment plants in the various cantons of Palmares, Jacó, Nombre02, and Golfito.

In accordance with the considerations set forth, the Chamber finds it established that, five years after the loan to finance the sanitation program for the priority areas of Golfito, Nombre02 Palmares and Jacó, entered into with KFW, was approved by law and published in Supplement 210 to La Gaceta 183 of 27 de setiembre del 2019, it has been in the closing phase since agosto de 2023 due to the lack of implementation. This Chamber notes with concern that, since 2022, the Ministry of Finance had asked AyA to prepare an action plan so that the loan could be secured; however, to date AyA has not responded to the Ministry of Finance. Nor has it proposed any strategy, much less begun construction of the infrastructure works for wastewater sanitation (saneamiento de aguas residuales) and the related facilities for the cantons of Palmares, Jacó, Golfito and Quepos.

Accordingly, the alleged violation of fundamental rights (derechos fundamentales) by the Ministry of Finance is dismissed, and the amparo action (recurso) is granted insofar as it is directed against AyA, because this Chamber observes that the respondent authority (autoridad recurrida) has not only failed to provide a definitive solution to the reported problems, but there is also no indication that it has devised an alternative strategy in response to the closing of the loan entered into with KFW, of Germany.

It is also observed that the municipalities in question have not taken definite and concrete action to press AyA to fulfill its legal duty to provide the residents of their jurisdictions with a sewage disposal service (servicio de evacuación de aguas negras), as required by the Ley Constitutiva Instituto Costarricense Acueductos y Alcantarillados), or to coordinate a solution to the water-related problem described.

As this Court has stated on other occasions, it understands that some environmental problems require coordination among various government entities; however, this does not justify AyA, within the scope of its powers and in view of the needs of the governed population (administrados), simply deciding in this case not to respond to the notices sent by the Ministry of Finance urging it to act since 2022, or failing to submit the action plan requested of it to establish clear and precise planning aimed at promptly accelerating the loan agreement to finance the sanitation program for priority areas.

In short, there is no indication that significant efforts were made to implement the loan agreement to finance the sanitation program for priority areas, or that the necessary actions were taken in coordination with the corresponding municipal and health authorities to provide solutions to the lack of water sanitation. Consequently, the action must be granted insofar as it is directed against the Instituto de Acueductos y Alcantarillados and the municipalities of Jacó, Golfito and Quepos, because the petitioner’s right to a healthy and ecologically balanced environment (derecho a un ambiente sano y ecológicamente equilibrado) was violated.

VI.Conclusion. Accordingly, insofar as the action is directed against the Municipalidad de Palmares, the petitioner must abide by the ruling in judgment number 03-01431 at 10:53 hours on 21 de febrero de 2003, which granted the action filed on 18 de setiembre de 2002. Insofar as it is directed against the Ministry of Finance, the action must be dismissed, and it is partially granted insofar as it is directed against AyA and the municipalities of Garabito, Golfito and Quepos, for violation of the petitioner’s right to a healthy and ecologically balanced environment, under the terms set forth in the operative part (parte dispositiva) of this judgment.

VII. DOCUMENTATION SUBMITTED TO THE CASE FILE (EXPEDIENTE)

The parties are hereby advised that, if they have submitted any paper document, as well as objects or evidence contained on any additional electronic, computer, magnetic, optical or telematic device or produced using new technologies, these must be retrieved from the Court within a maximum period of 30 business days following service of this judgment. Otherwise, any such material not retrieved within that period shall be destroyed, pursuant to the "Reglamento sobre Expediente Electrónico ante el Poder Judicial", approved by the Corte Plena at session N° 27-11 of 22 de agosto del 2011, article XXVI, and published in Boletín Judicial number 19 of 26 de enero del 2012, as well as the resolution approved by the Consejo Superior del Poder Judicial at session N° 43-12 held on 3 de mayo del 2012, article LXXXI.

Por tanto:

The action is partially granted for violation of the right to a healthy and ecologically balanced environment. Insofar as the action is directed in part against the Municipalidad de Palmares and the Instituto de Acueductos y Alcantarillados with respect to that Municipality, this matter shall be severed for processing under case file 02-7556-0007-CO. Insofar as the action is directed against the municipalities of Garabito, Golfito and Nombre02 and the Instituto de Acueductos y Alcantarillados with respect to those municipalities, the action is granted. Luis Alejandro Guillén Guardia, in his capacity as executive president of the Instituto Costarricense de Acueductos y Alcantarillados; Jong Kwan Kim Jin, in his capacity as mayor of Nombre02; Freiner Lara Blanco, in his capacity as mayor of Golfito; and Tobías Murillo Rodríguez, in his capacity as mayor of Garabito, or whoever may hold those offices, are ordered, within the scope of their powers and within eighteen months following service of this judgment, to take the appropriate measures and arrange and coordinate the construction of a sewage treatment plant (planta de tratamientos de aguas negras) and sewerage system (alcantarillado) for the respective localities of Quepos, Golfito and Garabito.

Those authorities are ordered to include in their budgets the appropriations necessary to construct the aforementioned treatment plant and sewerage system, and to provide the petitioner with details of the budget allocated for that purpose, as well as a schedule of activities so that the petitioner may monitor compliance with the stages of construction; all with the understanding that they must complete the specified task within a reasonable period, which may not exceed two years. The respondent authorities are warned that, pursuant to article 71 of the Ley de la Jurisdicción Constitucional, any person who receives an order issued in an amparo proceeding (recurso de amparo) that the person must comply with or enforce, and who fails to comply with or enforce it, shall be subject to imprisonment for three months to two years or a fine of twenty to sixty days, provided that the offense is not punishable by a more severe penalty.

The Instituto Costarricense de Acueductos y Alcantarillados and the Municipalidades de Quepos, Golfito and Garabito are ordered to pay the legal costs, damages and losses arising from the events underlying this declaration, which shall be assessed during enforcement of the judgment before the administrative litigation jurisdiction (jurisdicción de lo contencioso administrativo). Insofar as the action is directed against the Ministry of Finance, it is denied. The Ministro de Salud shall be notified so that he may coordinate efforts with the respondents and oversee the construction of the aforementioned treatment plants and infrastructure in each locality in accordance with health regulations.

Fernando Castillo V.

President Paul Rueda L.

Jorge Araya G.

Anamari Garro V.

Ingrid Hess H.

Aracelly Pacheco S.

Alexandra Alvarado P.

*747DRXUH80T461* CASE FILE N° 23-021589-0007-CO Telephone numbers: Telf01/ ALA-4TA (800-7252-482). Fax: Telf02 / Telf03. Website: www.poder-judicial.go.cr/salaconstitucional. Address: (Dirección01, Dirección02, 100 meters south of the Perpetuo Socorro church). Filing office for matters involving vulnerable groups: Dirección03, San José, Distrito Catedral, Dirección04, between 19th and 21st Streets, Dirección05

Secciones

Marcadores

Revisión del Documento *230215890007CO* SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas treinta minutos del uno de agosto de dos mil veinticuatro .

Recurso de amparo que se tramita en expediente nro. 23-021589-0007-CO, interpuesto por, [Nombre01 001], cédula de identidad [Valor CED02], contra INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS, MINISTERIO DE HACIENDA, MUNICIPALIDADES DE GOLFITO, Nombre02 Y GARABITO, AMPLIADO A LA MUNICIPALIDAD DE PALMARES.

Resultando:

  1. 1Por escrito recibido en la Secretaría de la Sala a las 4:48 horas del 5 de setiembre de 2023, el recurrente interpone recurso de amparo. Señala que no existe planta de tratamiento, ni alcantarillado sanitario en el distrito central de Palmares (situación conocida en el expediente nro. 02- 007756-0007-CO). Indica que, en Garabito, propiamente Jacó, la situación es similar a la de Palmares, pues los ciudadanos se ven afectados por gran contaminación antrópica en sus quebradas y ríos, trayendo muerte a la vida fluvial y problemas de salud a los pobladores, a los ecosistemas fluviales y marinos. Comenta que, al parecer, el saneamiento de las aguas nunca ha sido prioridad de los recurridos. Ante dicha problemática las comunidades de Golfito, Quepos, Jacó y Palmares habían sido incluidas en el Programa de Saneamiento en Zonas Prioritarias, autorizándose así la construcción de plantas de tratamiento y sus respectivos alcantarillados sanitarios.No obstante, reclama que el ministro de Hacienda mediante el oficio MH-DM-OF-1303-2023 de fecha 16 de agosto de 2023, le comunicó al presidente ejecutivo del Instituto de Acueductos y Alcantarillados (ICAA) la cancelación del programa. Además, la eliminación del presupuesto y financiamiento de los proyectos de las 4 comunidades, bajo el burdo argumento que no existe prontitud en materializar las obras ni la obtención de actos habilitadores necesarios. Incluso, parte de la argumentación es que el presidente del ICAA solicitó al ministro de Hacienda eliminar del cronograma de actividades y financiamiento a los proyectos de Nombre02 y de Golfito, queriendo dejar solo los Palmares y Jacó. Señala que ninguno los 4 proyectos se llevarán a cabo por orden del ministro de Hacienda, que dispuso dejar el Programa de Saneamiento en Zonas Prioritarias sin contenido presupuestario, asunto que conlleva al cierre irracional de la materialización de todas las obras en las 4 ciudades.Acusa que la actuación de las autoridades recurridas, violenta los numerales 21, 50 y 89 constitucionales, pues se entrará en un periodo desenfrenado, así como irreversible de daños ambientales perjudicando derechos de gente que incluso no ha nacido. Solicita declarar con lugar el recurso y ordenar a las recurridas tomar las acciones pertinentes para activar la fuente de financiamiento de los proyectos de plantas de tratamiento y alcantarillados sanitarios de Palmares, Jacó, Nombre02 y Golfito. Pide se declare con lugar el recurso.
  2. 2Mediante resolución de las 18:08 horas del 12 de setiembre de 2023 se dio curso al proceso y se solicitó informe al ministro de Hacienda y el presidente ejecutivo del Instituto Costarricense de Acueductos y Alcantarillados (ICAA),
  3. 3Informa Luis Alejandro Guillén Guardia, en su condición de presidente ejecutivo del Instituto Costarricense de Acueductos y Alcantarillados, informa: “II. SOLICITUD DE ACUMULACION DE RECURSOS Solicito respetuosamente la acumulación del presente recurso de amparo con el que consta en Expediente de esa Sala Constitucional de la Corte Suprema de Justicia N° 02-007756-000-CO sobre el cual se dio debida respuesta el pasado 13/09/2023 y sobre el que aportamos abundante prueba e informes que a su vez sirven de respaldo al presente caso. Referencia Mediante resolución N° 2000-02760 de esa Honorable Sala Constitucional, Expediente N° 00-002499-0007-CO de las once horas con seis minutos del veinticuatro de marzo del dos mil, en su Único Considerando indicó, que por evidente conexidad de los hechos planteados y a efectos de evitar pronunciamientos contradictorios, se ordena darles tramitación conjunta a dos recursos de amparo (ACUMULACIÓN).III. POSICIÓN DE AYA Invocamos en un todo la respuesta emitida por mi representada en relación con el RECURSO DE AMPARO EXPEDIENTE N° 02-007756-0007-CO. Nos permitimos enviar nuevamente toda la documentación técnica emitida por las distintas áreas institucionales involucradas con el tema. ASIMISMO, APORTAMOS UNA NUEVA PRUEBA QUE SE REFIERE AL OFICIO N° UEN-PC-2023-02218 DE FECHA 18/09/2023 SUSCRITO POR SUELLEN RAMÍREZ MEJÍAS, FUNCIONARIA DE LA UEN PROGRAMACIÓN Y CONTROL DEL INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS; Y QUE CONSTITUYE A UNA AMPLIACION DEL INFORME RENDIDO PARA EXPEDIENTE N° 02-007756-0007-CO ABARCANDO LOS PROYECTOS DE ALCANTARILLADO SANITARIO DE JACÓ, GOLFITO Y QUEPOS. Alega el recurrente que, “( …. ) al parecer el saneamiento de las aguas nunca ha sido prioridad de los recurridos. Ante dicha problemática las comunidades de Golfito, Quepos, Jacó y Palmares habían sido incluidas en el Programa de Saneamiento en Zonas Prioritarias, autorizándose así la construcción de plantas de tratamiento y sus respectivos alcantarillados sanitarios”.Lo anterior es absolutamente IMPROCEDENTE, el caso de Palmares se ha explicado a través de la respuesta dada al recurso de amparo Expediente 02-007756-0007-CO. Y sobre los demás proyectos adjuntamos Acuerdo de Junta Directiva N° AN-2017-358 del 11/08/358 del Instituto Costarricense de Acueductos y Alcantarillados mediante el cual se establece lo siguiente: POR TANTO, SE ACUERDA: A ) Autorizar al Jerarca Institucional, para que lleve a cabo las negociaciones pertinentes ante las autoridades de Gobierno, con el propósito de que el Ministerio de Hacienda formalice la cooperación, mediante la cual se financian los siguientes proyectos • 000412 Construcción Alcantarillado Sanitario de Palmares • 000467 Proyecto Construcción Alcantarillado Sanitario de la Ciudad de Nombre02 • 000471 Proyecto Construcción Alcantarillado Sanitario de la Ciudad de Golfito • 000413 Alcantarillado Sanitario para la Ciudad de Jacó.B) Delegar en la Administración la verificación del cumplimiento de las disposiciones legales y técnicas que emana de la legislación nacional, que son aplicables al Instituto, en las negociaciones de esta cooperación y transferencia. IV. INFORME PRESIDENCIA EJECUTIVA DE AYA Mediante Oficio N° PRE-2023-01201 de fecha 13/09/2023 esta Presidencia Ejecutiva rinde INFORME a solicitud de la Dirección Jurídica.

Ante dicha problemática las comunidades de Golfito, Quepos, Jacó y Palmares habían sido incluidas en el Programa de Saneamiento en Zonas Prioritarias, autorizándose así la construcción de plantas de tratamiento y sus respectivos alcantarillados sanitarios A continuación se detalla el contenido del mismo: “En función del financiamiento disponible, se plantearon diferentes escenarios de aprovechamiento de la inversión. Los cambios en los proyectos a considerar se debieron a la oposición de la Municipalidad y la Marina Bahía Golfito sobre la ubicación de la futura Planta de Tratamiento de Aguas Residuales, conforme con lo descrito en el documento PRE-2023-00493 (adjunto). La necesidad de ajustarse a las condiciones sociales actuales en el Proyecto del Alcantarillado Sanitario de Golfito dio como resultado la propuesta para la ejecución de los proyectos de Jacó y Palmares, con un alcance acorde con los recursos disponibles.

Durante la misión de junio del 2023 con el Banco KfW, la cual contó con la participación del Ministerio de Hacienda, se determinó la necesidad de valorar la pertinencia y urgencia del Programa por parte del prestatario. Bajo esta premisa, el Ministerio de Hacienda mediante nota MH-DM-OF-1303-2023 del 16 de agosto, solicitó al AyA proceder a coordinar las acciones que correspondan para realizar el cierre ordenado de la operación del crédito y demás actividades asociadas al mismo. Con respecto a las acciones que tomará la Presidencia Ejecutiva ante la decisión del Ministerio de Hacienda, en calidad de prestatario del Contrato de Préstamo 28568, la Administración Superior se encuentra construyendo un análisis de riegos, implicaciones y acciones a desarrollar, desde el punto de vista legal, financiero, técnico y ambiental, que faciliten la propuesta de otras alternativas y la definición de una estrategia factible de financiamiento que permita la consecución del programa” Pide se declare sin lugar el recurso.

  1. 4Informa Erik Herrera Bonilla, en su condición de Subdirector Jurídico del Ministerio de Hacienda, en aplicación del Acuerdo número MH-DM-ACDO-0039-2023 de 17 de mayo 2023, por el que se le delega por parte del señor Ministro de Hacienda. Expone: “II. Sobre el fondo En primera instancia, es menester indicar que el Ministerio de Hacienda es la institución responsable de la recaudación de impuestos, la rectoría de la Administración Financiera, de la asignación de los recursos financieros a las entidades públicas y la administración de la deuda pública, por medio de una política fiscal sostenible, para contribuir a la estabilidad y crecimiento económico y social de los habitantes del país y su creación se remonta a la promulgación del Decreto Ejecutivo LV de fecha 14 de octubre de 1825. Y que según la Ley N° 8131 de 18 de setiembre de 2001, publicada en La Gaceta N° 198 de fecha 16 de octubre de 2001, el Ministerio de Hacienda es el único agente con capacidad legal de endeudamiento, gestión y control de la deuda pública de la Administración Central, por lo que atendiendo a las habilitaciones legales con las que cuenta es que se planteó el oficio número MH-DM-OF-1303-2023.Asimismo, el Instituto Costarricense Acueductos y Alcantarillados, de conformidad con la Ley 2726 de 14 de abril de 1961, Ley Constitutiva Instituto Costarricense Acueductos y Alcantarillados y sus reformas, corresponde a una institución autónoma del Estado, creada con el propósito de dirigir, fijar políticas, establecer y aplicar normas, realizar y promover el planeamiento, financiamiento y desarrollo y resolver todo lo relacionado con el suministro de agua potable; recolección y evacuación de aguas negras y residuos industriales líquidos, lo mismo que el aspecto normativo de los sistemas de alcantarillado pluvial en áreas urbanas, para todo el territorio nacional. Por lo que en dicha institución, conforme a sus competencias, es en la que recae no solo la rectoría en la materia, sino la responsabilidad de determinar la prioridad en la construcción de plantas de tratamiento y alcantarillados sanitarios, y la continuidad de los Programas que consideren de importancia para el resguardo del derecho a la salud de las personas.En este sentido la propia Sala indicó en su resolución 2003-01431: VI.- Sobre las competencias del Instituto de Acueductos y Alcantarillados y del Ministerio de Salud en materia de alcantarillados sanitarios. Sin perjuicio de lo expuesto en el considerando anterior, la Ley General de Salud y la Ley Constitutiva del Instituto Costarricense de Acueductos y Alcantarillados establecen que el control técnico de los acueductos y alcantarillados le corresponde, conjuntamente, al Instituto Nacional de Acueductos y Alcantarillados y al Ministerio de Salud. Para empezar, Ley Constitutiva del AyA, expresamente contempla lo siguiente: “ARTICULO 2º.- Corresponde al Instituto Costarricense de Acueductos y Alcantarillados: a) Dirigir y vigilar todo lo concerniente para proveer a los habitantes de la república de un servicio de agua potable, recolección y evacuación de aguas negras y residuos industriales líquidos y de aguas pluviales en las áreas urbanas; (…) d) Asesorar a los demás organismos del Estado y coordinar las actividades públicas y privadas en todos los asuntos relativos al establecimiento de acueductos y alcantarillados y control de la contaminación de los recursos de agua, siendo obligatoria, en todo caso, su consulta, e inexcusable el cumplimiento de sus recomendaciones (…) g) Administrar y operar directamente los sistemas de acueductos y alcantarillados en todo el país, los cuales se irán asumiendo tomando en cuenta la conveniencia y disponibilidad de recursos.Los sistemas que actualmente están administrados y operados por las corporaciones municipales podrán seguir a cargo de éstas, mientras suministren un servicio eficiente. (…) Queda facultada la institución para convenir con organismos locales, la administración de tales servicios o administrarlos a través de juntas administradoras de integración mixta entre el Instituto y las respectivas comunidades, siempre que así conviniere para la mejor prestación de los servicios y de acuerdo con los reglamentos respectivos. Por las mismas razones y con las mismas características, también podrán crearse juntas administradoras regionales que involucren a varias municipalidades;" Por su parte, el Ministerio de Salud, dentro del ámbito de sus competencias, también se encuentra directamente obligado a actuar en esta materia. En ese sentido, el artículo 289 de la Ley General de Salud, en cuanto a la materia del alcantarillado, propiamente, dispone lo siguiente: "Todo sistema de alcantarillado, quedará bajo el control técnico del Ministerio y del Servicio Nacional de Acueductos y Alcantarillado y las personas de derecho privado o público que los construyan, administren y operen se sujetarán a las normas que el Poder Ejecutivo, en consulta con el Servicio Nacional de Acueductos y Alcantarillado, dicte para condicionar su construcción, funcionamiento y la evacuación y tratamiento final de los fluentes." De conformidad con esta ley, le corresponde al Ministro del ramo dictar las normas técnicas de salud, a las cuales deben ceñirse las personas físicas o jurídicas de derecho privado o público, en las materias en que la propia ley lo requiera, entre las cuales, sin duda alguna, se encuentra lo relativo al alcantarillado sanitario (…)” Conteste con lo anterior y respecto a la condición de la planta de tratamiento y el alcantarillado sanitario en el distrito central de Palmares, la contaminación antrópica en quebradas y ríos en Jacó y lo que respecta al saneamiento de las aguas, son temas que exceden las competencias de esta Cartera ministerial, por lo que corresponde al Instituto Costarricense de Acueductos y Alcantarillados, así como a las Municipalidades respectivas, referirse a dichos alegatos.Ahora bien, mediante la Ley número 9723 de fecha 14 de agosto de 2019, se aprobó el Contrato de Préstamo número 28568 para Financiar el Programa de Saneamiento en Zonas Prioritarias, suscrito entre la República de Costa Rica y el Banco KFW Frankfurt am Main (en adelante KFW), por un monto hasta de setenta y nueve millones doscientos setenta y ocho mil quinientos noventa y un euros exactos (EUR 79.278.591,00), el cual en el punto 1.2 establece: “(…) El AyA y el KfW fijarán por acuerdo separado ("Acuerdo separado") los detalles del Programa y de los proyectos elegibles, así como las obras, bienes y servicios a financiar con cargo al Préstamo.” En razón de lo anterior, el Instituto Costarricense de Acueductos y Alcantarillados y el KfW fijaron por Acuerdo Separado, entre ambas partes, los detalles del Programa y de los proyectos elegibles, así como las obras, bienes y servicios a financiar con cargo al Préstamo, para establecer medidas de saneamiento en zonas prioritarias, por lo que no existe en el Contrato de préstamo N° 28568 tal autorización para la construcción de plantas de tratamiento y sus respectivos alcantarillados sanitarios como erróneamente se indica, tanto las obras como el avance en los desembolsos para llevar a cabo las obras son actividades propias del Instituto Costarricense de Acueductos y Alcantarillados y el Banco KFW quien aprueba los mismos.En lo que respecta al oficio número MH-DM-OF-1303-2023, es importante aclarar que el alcance del mismo no corresponde a la cancelación de un Programa, sino a la coordinación de las acciones que correspondan para realizar el cierre ordenado de la operación del crédito y demás actividades asociadas únicamente al financiamiento; solicitud que obedece, a las manifestaciones del Instituto Costarricense Acueductos y Alcantarillados, respecto a la imposibilidad de llevar a término, en cantidad y alcance, los proyectos inicialmente consensuados con el KFW con el monto del contrato de préstamo. Además, el Ministerio de Hacienda en representación del Gobierno, y en calidad de Prestatario del Contrato de Préstamo KfW 28568, le indica al presidente ejecutivo del Instituto Costarricense Acueductos y Alcantarillados que se procederá de conformidad con la cláusula 3.5 del Contrato de Préstamo, a notificar la renuncia al desembolso de los recursos aún no solicitados del crédito.Tal y como consta en el oficio señalado, el Instituto Costarricense Acueductos y Alcantarillados afirmó que únicamente podrían asumir, pero no en su totalidad sino con alcance reducido, dos de los proyectos iniciales, debido a que los costos de inversión se incrementaron casi tres veces pasando de EUR 65.3 millones (sin IVA) a EUR 168.5 millones (sin IVA); sin embargo, para ello requerirían de una extensión del plazo de desembolsos del crédito significativa, pasando de 2024 al año 2027 a pesar de que el 27 de setiembre alcanzará ya su cuarto año de ejecución y el Instituto Costarricense Acueductos y Alcantarillados ha desembolsado a julio 2023 solamente el 0.04% de los fondos del crédito y cuenta con nulos avances a la fecha en términos de las obras planificadas, lo que genera costos considerables para el erario público. Así las cosas, es dable concluir que no es correcta la apreciación del amparado en el sentido que el Ministerio de Hacienda instruyó el cierre del Programa, dado que el mismo forma parte de las funciones sustantivas del Instituto Costarricense Acueductos y Alcantarillados, sobre lo cual el Ministerio no tiene injerencia.De igual forma, resulta imperioso aclarar que no se está eliminando el presupuesto a los proyectos de las comunidades que indica pues es al Instituto Costarricense Acueductos y Alcantarillados al que le corresponde conforme sus habilitaciones legales como institución autónoma, y criterio técnico, determinar qué proyectos deberá presupuestar. Además, la renuncia al desembolso de las cantidades aún no solicitados del crédito, no se fundamenta en escasos argumentos, pues se tienen múltiples y sólidos hechos técnicos medibles que demuestran que el financiamiento del Programa mediante la operación de crédito se ha caracterizado por un crítico desempeño durante la mayor parte de su ejecución, veamos: • Cercano al cumplimiento de su cuarto año de ejecución, el Programa había desembolsado a julio 2023 solamente el 0,04% de los fondos del crédito, y cuenta aún a hoy, con nulos avances a la fecha en términos de las obras planificadas, no se cuenta inclusive con ninguna licitación publicada ni adjudicada en lo referido al desarrollo de obras propiamente). • Debido a múltiples problemas presentados durante su ejecución (debilidades de preinversión, necesidad de desarrollar y ampliar distintos estudios, identificación de zonas inundables, atrasos en el diseño de las Plantas de Tratamiento, atrasos en el diseño de los términos de referencia de las licitaciones, base de costos desactualizada y altos sobrecostos en las obras conforme lo planificado, escasa capacidad instalada, entre otros), este Programa sufrió una reducción significativa de su alcance por parte del Instituto Costarricense de Acueductos y Alcantarillados, indicando que pasaría de los 4 proyectos iniciales acordados en el Acuerdo Separado antes citado, a tan solo 2 y estos, con un alcance reducido con respecto al originalmente planteado. • Que esas dos obras con alcance reducido, comenzarían su construcción hasta marzo de 2025, a pesar de que este Programa inició su ejecución desde el 27 de setiembre de 2019, una vez que fue promulgada en La Gaceta la Ley 9723 que aprobó el Contrato de Préstamo citado con el KfW. • El Ministerio de Hacienda, en aras de transparentar y rendir cuentas, ha puesto a disposición de la ciudadanía a través de la página Web ministerial, la información relacionada con la ejecución de los créditos externos que financian distintos Programas/proyectos de inversión pública, en la cual se evidencia que el Programa ha venido enfrentando por varios años una serie de retrasos, problemas y estancamientos, dada la limitada capacidad de ejecución del Instituto Costarricense de Acueductos y Alcantarillados que han propiciado su crítica situación de desempeño, con muy pobres avances a la fecha. • Sobre este particular, desde el I Semestre del año 2021, el Programa ha venido presentando un desempeño crítico, del cual no ha podido recuperarse y más bien, se ha acentuado a través de los años dicha condición, pese a los esfuerzos que desde este Ministerio se han realizado para instar al Instituto Costarricense de Acueductos y Alcantarillados a que ejecute dicho Programa y el crédito que lo financia con eficiencia y eficacia.Como prueba de lo anterior, se encuentran los oficios que se han dirigido a distintos jerarcas del citado Instituto para advertir de estas situaciones y solicitar prontas soluciones a la ejecución. En ese sentido, se encuentra el oficio número DM-1219-2021 de fecha 11 de noviembre de 2021, dirigido al señor Tomás Martínez, Presidente Ejecutivo del Instituto Costarricense de Acueductos y Alcantarillados, con el cual este Ministerio le manifestó la preocupación en cuanto al desempeño del Programa, los evidentes y significativos retrasos ya mostrados a ese momento, incluyendo lo relativo a una de las principales contrataciones requeridas para la ejecución del Programa, como lo era la contratación del Consultor de Implementación (CI) y el aumento en los plazos para la recepción de ofertas, lo cual generó replanificaciones constantes, tanto en aspectos financieros (pagos a realizar) como en el cronograma de actividades.También se le externó al Instituto Costarricense de Acueductos y Alcantarillados que el tipo de situaciones mostradas para el caso particular con el KFW se consideraban relevantes debido a que en otros Programas similares de la Institución ya se habían también evidenciado, generando incertidumbre en cuanto a la eficacia y eficiencia con que se estaban aplicando las lecciones aprendidas generadas en los Programas/proyectos de la Cartera del Instituto en ejecución y finalizados. Posterior a ello, la Declaración desierta del concurso de Precalificación de las empresas, implicó que luego el Instituto Costarricense de Acueductos y Alcantarillados tomara la decisión de iniciar nuevamente los procesos de contratación, pero de forma individual (por proyecto), por lo que se le hizo ver la preocupación sobre el plazo que desde ese momento el citado Instituto ya estimaba iba a requerir de más, para concluir el Programa y que correspondía a 24 meses adicionales.Incluso con respecto a las obras de la PTAR Golfito, Palmares y Jacó, se instó al Instituto a seguir coordinando los espacios de comunicación necesarios con los interesados y con personal clave, que le permitieran optimizar y mejorar la gestión de los involucrados, de tal forma que se realizaran las alianzas estratégicas, así como los acuerdos requeridos para garantizar un inicio oportuno de las obras, minimizando cualquier contratiempo con el desarrollo de estas. Este Ministerio, en calidad de Prestatario del Contrato de Préstamo KfW 28568, señaló que era urgente y necesario que el Instituto Costarricense de Acueductos y Alcantarillados como Entidad Ejecutora, coordinara las gestiones necesarias para subsanar su problemática en aras de avanzar adecuadamente en la ejecución del Programa y minimizar futuros impactos en el cronograma de ejecución, de tal forma que permitiera concluirlo en el plazo contractualmente establecido y sin generar sobrecostos.Siendo así el Ministerio de Hacienda quedó atento a la comunicación de las acciones que estaría implementando el Instituto Costarricense de Acueductos y Alcantarillados, para mejorar y fortalecer la gestión del Programa, de tal forma que las mismas propiciaran y reflejaran en el corto plazo mejores indicadores en su ejecución, mismas que nunca se materializaron. En línea con lo anterior, mediante oficio número MH-DM-OF-2702-2022 de fecha 09 de noviembre del 2022, dirigido al señor Roberto Guzmán Gutiérrez, Presidente Ejecutivo del Instituto Costarricense de Acueductos y Alcantarillados en ese momento, se externó la preocupación por el crítico desempeño que mostraba el Programa, en donde a esa fecha no se había realizado ningún desembolso del financiamiento, y el avance físico del Programa era de un 18.22%, avance que representaba menos del 1% en el último año. Para ese entonces, le fueron indicados otros elementos que continuaban siendo críticos:1) La orden de inicio para las actividades asignadas al Consultor de Implementación se había dado apenas en agosto 2022;2) No se había finiquitado el convenio interinstitucional con INCOFER que resultaba fundamental para el desarrollo de la planta de tratamiento de Golfito;3) No se tenía claridad de la preinversión para otras obras del Programa y4) A pesar de que no se había iniciado con la contratación de obras ya se identifican sobrecostos en la ejecución de las mismas. De igual manera, se manifestó la urgencia de aprovechar la misión del KFW, que se celebraría en el mismo mes de noviembre 2022, para que en conjunto AyA-KfW diseñaran un plan de aceleración de actividades y obras que le permitan mitigar el impacto de los 24 meses de retrasos sufridos en el Programa y que a su vez el Instituto priorizara sus proyectos y recursos para garantizar el adecuado financiamiento de los alcances del Programa y a la vez realizara una adecuada planificación que permita la mitigación de riesgos futuros y nuevas fuentes de retrasos. También, se le solicitó al Instituto que una vez que se diera por finalizada la misión del KFW se presentara a este Ministerio el plan de acción que hubieran acordado entre el Banco y el Instituto Costarricense de Acueductos y Alcantarillados, para retomar la senda de ejecución del Programa, reducir el retraso existente y administrar los riesgos que podrían afectarlo. No obstante, mediante oficio número MH-DM-OF-0143-2023 de fecha 2 de febrero de 2023, dirigido al Señor Alejandro Guillén Guardia, Presidente Ejecutivo del Instituto Costarricense de Acueductos y Alcantarillados, este Ministerio debió realizar un recordatorio al Instituto para la presentación del Plan de Acción que se le había solicitado en noviembre del 2022 en el oficio MH-DM-OF-2702-2022 y cuya solicitud estaba motivada en su crítico estado de situación. Asimismo, se externó que la Dirección de Crédito Público de este Ministerio había solicitado dicho Plan a la Unidad Ejecutora del Programa en distintas oportunidades; siendo que dicha Unidad había indicado que se requería de la definición de las líneas de acción por parte de la Administración Superior del Instituto Costarricense de Acueductos y Alcantarillados para revalorar el alcance del Programa y el aumento en los costos del mismo. Por lo que se le señala al Instituto que la presentación de dicho plan reviste gran importancia, dados los críticos resultados de desempeño mostrados por el Programa, en donde a ese momento, según el Cronograma del Acuerdo Separado del Préstamo, las obras de los cuatro proyectos de saneamiento mostraban un evidente retraso pues debieron haber iniciado en julio de 2021, cuando las licitaciones serían publicadas hasta el segundo trimestre del 2023. Adicionalmente, se le indicó al Instituto Costarricense de Acueductos y Alcantarillados, que era de alto impacto en los indicadores de seguimiento del Programa, el hecho de la nula ejecución de recursos del préstamo al 31 de diciembre 2022, considerando que su entrada en vigencia data desde setiembre 2019. Para el Ministerio de Hacienda la toma de decisiones que la Unidad Ejecutora del Programa requería y la presentación del Plan de acción indicado, en donde estableciera una planificación clara y precisa para lograr la pronta aceleración del mismo y plasmara las actividades, responsables y plazos de cumplimiento, que llevarían a resolver de forma definitiva, entre otros, el tema del incremento exponencial del costo total del Programa, resultaba de especial importancia, no obstante se hizo caso omiso a las reiteradas solicitudes. Todo lo descrito con anterioridad, ha generado al país altos costos por concepto de las comisiones de compromiso pagadas al Banco KfW. En virtud de la lentitud y casi nulo desembolso de los recursos del crédito, se tiene que al 31 de julio 2023 se habían pagado un total de US$860.462,94 en comisiones de compromiso y tan solo se habían desembolsado US$33.926,09 de los recursos del crédito, lo cual refleja una disparidad muy significativa en ambos indicadores, dado que se han pagado al Banco en dichas comisiones más de 25 veces lo que este ha desembolsado, es decir, se ha materializado un altísimo costo financiero para Costa Rica debido al no uso de los recursos versus el aprovechamiento real de la totalidad de los mismos que ha puesto a disposición el KfW para que pudiera ejecutarlos Instituto Costarricense de Acueductos y Alcantarillados en el marco del Programa. Siendo así el Ministerio de Hacienda, conforme sus competencias y habilitaciones legales y buscando el mayor beneficio para la República de Costa Rica y en resguardo del erario público, solicitó la coordinación de las acciones que correspondan para realizar el cierre ordenado de la operación del crédito y demás actividades asociadas, únicamente al financiamiento que muy cercano a sus cuatro años después de su aprobación no mostró avances sino únicamente gastos desproporcionados en relación a los montos desembolsados por parte de Instituto Costarricense de Acueductos y Alcantarillados, más en ningún momento ordenó la cancelación de un Programa del Instituto Costarricense de Acueductos y Alcantarillados, pues su continuidad ni siquiera corresponde a sus competencias, sino a las propias de dicha institución autónoma. Acotado lo anterior, no lleva razón el recurrente al afirmar que el Ministerio de Hacienda ordenó que los proyectos de Quepos, Golfito, Palmares y Jacó no se llevaran a cabo, ni que haya dispuesto dejar sin contenido presupuestario al Programa de Saneamiento en Zonas Prioritarias, lo cual generará daños ambientales irreversibles perjudicando derechos de gente que incluso no ha nacido. Pues resulta propio de las competencias del Instituto Costarricense Acueductos y Alcantarillados dar continuidad a los proyectos de considerarlos necesarios y realizar las presupuestaciones respectivas para llevarlos a su consecución; asimismo, no podría considerarse factible alegar la violación de los numerales 21, 50 y 89 constitucionales por parte del Ministerio de Hacienda cuando sus competencias legales incluyen la administración de la deuda pública, por medio de una política fiscal sostenible para contribuir a la estabilidad y crecimiento económico, siendo así la coordinación de las acciones que correspondan para realizar el cierre de una operación de crédito corresponde a aspectos técnicos-financieros que versan sobre la sostenibilidad de la operación conforme a los costos que representa y los avances esperados de la misma.

Al respecto, en la Minuta de la Reunión de fecha 22 de junio de 2023 realizada con motivo de la misión de supervisión de KFW se manifestó lo siguiente: Ampliación de plazo de desembolso: Se menciona la incertidumbre sobre los costos para el Prestatario en caso de que éste rescinda el Contrato de Préstamo o ante una posible prórroga y la necesidad de tener información proyectada al respecto, para tomar decisiones. Se destaca que no puede garantizarse un monto concreto para cada tema al momento de la reunión. A pesar de esto, para el Ministerio de Hacienda sí es necesario el contar con la información citada para analizar escenarios realistas que apoyen la toma de decisiones oportunas, por lo que le solicita al KfW brindar una estimación al respecto. (La negrita no pertenece al original) Información que una vez revisada desde el ámbito técnico y valoradas sus implicaciones, llevó al Ministerio de Hacienda a tomar la decisión de solicitar el cierre de la operación de crédito, por considerarse beneficioso a los intereses del Estado que la presente Cartera protege conforme sus competencias.

Se reitera que la decisión de acortar el alcance de los proyectos de 4 a 2 con un alcance reducido en el marco del Programa, fue una decisión gestada desde el seno del propio Instituto Costarricense de Acueductos y Alcantarillados, en la cual el Ministerio de Hacienda no tuvo ninguna injerencia. Asimismo, se hace énfasis en que este Ministerio no instruyó de ninguna manera a dejar sin contenido presupuestario el Programa, siendo que el Instituto Costarricense de Acueductos y Alcantarillados técnica y legalmente está en capacidad de llevar a cabo las obras del Programa con los recursos que presupueste para ello. III. Petitoria Al amparo de las razones de hecho y de derecho expuestas, solicito declarar sin lugar el recurso de amparo interpuesto por el señor [Nombre01 001], ya que este Ministerio dentro de sus competencias se ha ajustado a lo dispuesto por la normativa y no ha violentado los derechos fundamentales a la Salud, al Ambiente Sano y Ecológicamente Equilibrado, y la Protección de las Bellezas Naturales”.

  1. 5Mediante resolución de magistrado instructor de las 7:01 horas del 20 de setiembre de 2023, se ampliaron las partes del recurso y se requirió informe al ministro de Salud.
  2. 6Informa Mario Urcuyo Solórzano, en su condición de ministro de Salud a. i.. Expone: “INFORME DE LEY. El presente informe se sustenta en el oficio N° MS-DPRSA-USA-1996-2023 del 02 de octubre de 2023, emitido por el Ing. Eugenio Androvetto Villalobos, Director de la Dirección de Protección Radiológica y Salud Ambiental, e Ing. Ricardo Morales Vargas, Jefe a. i. de la Unidad de Salud Ambiental; en el que se indica lo que sigue: “En atención a su consulta, nos permitimos indicar que esta Dirección no tiene la competencia administrativa ni jurídica para resolver, pues lo expresamente consultado, es sobre los linderos para la actividad propuesta, aspecto que está contemplado en la reglamentación municipal y el Reglamento de Construcciones, y no existe reglamento específico del Ministerio de Salud para normar la ubicación de industrias. Analizado el oficio MS-DRRSHN-DARSCQ-0301-2023 y el Informe Técnico MS-DRRSHN-DARSCQ-IT-606-2023 es el criterio de esta Dirección, que las molestias son confinables al inmueble, siendo este un sitio que el ARS interpreta como industrial, clasificándolo como inofensivo o incómodo, al realizar el análisis jurídico, criterio éste de clasificación de la actividad con el que concordamos.Cabe mencionar que la Municipalidad de San Carlos mediante Dictamen DIC 59210 Resolución Municipal de Ubicación da por aprobada la ubicación, por lo que de 2 conformidad con la Ley 8220, específicamente lo indicado en el artículo 3º, la misma debe mantenerse, pues fue otorgado para la actividad descrita como de fabricación de distintos materiales de metal y plástico. Asimismo, a la empresa citada y para las actividades descritas, le fue otorgado el Régimen de Zona Franca mediante Acuerdo 268-2022, firmado por la Presidencia de la República, sin menoscabo de sujetarse al resto de la legislación sanitaria, ambiental, laboral, de comercio y tributaria. Un asunto más de fondo, y que anotado en el oficio MS-DPRSA-USA-521-2023 sobre un caso similar, es la razón por la que el Ministerio proporciona al administrado el formulario de “Solicitud de Permiso de Ubicación”, pues no existe ordenamiento jurídico específico sobre que éste sea requerido para el tipo de actividad en mención, siendo que el Decreto 43432-S, solamente indica en su artículo 8º lo siguiente: “b.Permiso de ubicación otorgado por el Ministerio, únicamente para aquellas actividades reguladas mediante los reglamentos específicos: Decreto Ejecutivo No. 32833-S del 3 de agosto de 2005 "Reglamento general de cementerios"; Decreto Ejecutivo No. 38928-S del 14 de noviembre del 2014 "Reglamento sobre rellenos sanitarios"; Decreto Ejecutivo No. 39136-S-MINAE del 15 de junio del 2015 "Reglamento sobre condiciones de operación y control de emisiones de instalaciones para coincineración de residuos sólidos ordinarios"; Decreto Ejecutivo No. 39887-S-MINAE del 18 de abril del 2016 "Reglamento de aprobación de sistemas de tratamiento de aguas residuales" y Decreto Ejecutivo No. 33724-COMEX-MEIC-S del 8 de enero del 2007 mediante el cual se publica la Resolución No. 176-2006 (COMIECO-XXXVIII).” La interpretación y trámite que usualmente esta Dirección ha seguido o recomendado sigan las Áreas Rectoras (o su apoyo Regional) es que el Ministerio solamente clasifique la actividad (inofensiva, incómoda, insalubre, o peligrosa) según el Reglamento sobre Higiene Industrial, Decreto Ejecutivo N°11492-SPP, y sea la Municipalidad respectiva la que establezca lo relacionado al uso del suelo.Considerando que el análisis jurídico realizado por la Región Huetar Norte y Área Rectora, también es sólido al interpretar de manera integral la legislación sanitaria, de seguridad e higiene industrial y de construcciones, esta Dirección recomienda que sean dichos niveles regionales y locales, los que alerten o consulten a la Municipalidad sobre las incongruencias detectadas entre los permisos constructivos y de ubicación otorgados por el gobierno local; y se sujeten a lo que se resuelva por éste posteriormente.” CONCLUSIONES. Se tiene por demostrado, mediante el contenido del oficio N° MS-DPRSA-USA-1996-2023 del 02 de octubre de 2023, antes citado, que se han realizado todas las diligencias debidas 3 por parte de las autoridades del Ministerio de Salud, para atender lo solicitado por esta Sala Constitucional. PRUEBA. Se remite copia de los documentos indicados debidamente certificada. PETITORIA.En virtud de lo expuesto, respetuosamente solicitamos a esta Sala Constitucional, dar por atendida la solicitud planteada mediante resolución de las siete horas y un minuto del veintinueve de setiembre de dos mil veintitrés, al haberse dado respuesta en tiempo y forma a lo requerido”.
  3. 7Mediante resolución de magistrado instructor de las 15:05 horas del 19 de octubre de 2023, se ampliaron las partes del recurso y se requirió informe a los alcaldes de Golfito, Nombre02 y Garabito.
  4. 8Informa Jong Kwan Kim Jin, en su condición de alcalde de Quepos. Expone: “PRIMERO: Que en mi condición de representante legal de la Municipalidad de Quepos, gobierno local de este cantón, en Nombre01 de todos los pobladores de esta honorable comunidad, manifiesto total y absoluto apoyo. Asimismo, me adhiero a las manifestaciones del señor recurrente [Nombre01 001], cédula de identidad CED01. SEGUNDO: Que efectivamente esta ciudad carece de una planta de tratamiento en la cual se le dé el tratamiento adecuado a las aguas negras y ciertamente esto representa un problema de salud pública que debe atenderse de manera urgente y que este cantón ha esperado durante años por una respuesta, sin embargo, no se ha obtenido alguna gestión positiva de parte de las autoridades competentes. TERCERO: Que efectivamente Nombre02 fue incluido en el Programa de Saneamiento en Zonas Prioritarias, con el objetivo de ejecutar al fin la construcción de planta de tratamiento y alcantarillado sanitario.Sin embargo, de manera arbitraria violentando derechos constitucionales, sugirieron sacar a Nombre02 de la lista de las 4 comunidades beneficiadas con el proyecto para al final decidir cancelar todo el programa y quitar el presupuesto y financiamiento que ya había sido destinado para este fin tan importante de 4 comunidades beneficiadas. CUARTO: Que tal y como consta en autos, en el Oficio del Ministerio de Hacienda MH-DM-OF-1303-2023 con fecha del 16 de agosto de 2023, luego de reuniones previas sostenidas entre el Instituto Costarricense de Acueductos y Alcantarillados y el Ministerio de Hacienda, esta entidad gubernamental en representación del gobierno decidió sin criterios técnicos que respalden tal decisión y mostrando cero interés en las necesidades que enfrentan los pobladores de este cantón diariamente, especialmente esta zona que tiene serios problemas de inundaciones, sin una planta de tratamiento, decidieron cerrar el Programa de Saneamiento en Zonas Prioritarias.QUINTO: Que resulta absolutamente reprochable que por una decisión arbitraria de jerarcas se elimine un proyecto tan importante, ya que nuestra comunidad necesita con urgencia la construcción de una planta de tratamiento y alcantarillado sanitario y seguir postergando este proyecto representa una bomba de tiempo, porque a futuro inevitablemente la problemática de salud pública se volverá insostenible y resulta un gasto menor atender ahora el tratamiento de estas aguas que a futuro atender una serie de enfermedades que resultarán en muertes de muchos seres vivos, tanto seres humanos como animales y flora y fauna marina”. Pide se declare sin lugar el recurso.
  5. 9Por escrito incorporado al expediente digital el 27 de octubre de 2023, Juan Pablo Morera en su condición de representante de la Asociación Cámara de Comercio, Industria, Turismo y afine de Palmares, plantea solicitud de coadyuvancia activa. Expone: “PRIMERO: Solicito se nos tenga como coadyuvantes activos de este amparo. Nos fundamentamos en los intereses difusos y el derecho a un ambiente sano contemplado en la norma 50 constitucional. SEGUNDO: Consideramos, por un criterio de responsabilidad social ambiental, que es nuestro deber pedir que este amparo sea declarado con lugar y que se obligue a los recurridos a tener que construir las plantas de tratamiento y los alcantarillados sanitarios respectivos. Hacemos especial énfasis respecto a la planta de Palmares de Alajuela, pues somos vecinos de este cantón y existe un voto constitucional que data desde hace 20 años que ordena a tener que hacerse la infraestructura necesaria en protección de las generaciones futuras.TERCERO: Es perfectamente claro, que la situación donde se desmantela, o se desarticula un programa, que colabora en financiar plantas de tratamiento y alcantarillados sanitarios, no debe ser permitido por esta Sala, pues ello daña ecosistemas fluviales y hasta el propio mar. Si bien nuestra norma constitucional 50 no habla del saneamiento como derecho humano fundamental, esta Sala sí lo ha reconocido a este como tal y pedimos que se disponga ello. La protección que señalamos emana de las normas 21 y 50 constitucionales definitivamente y es fundamental que prevalezca el criterio donde el ambiente, la vida, la calidad de vida y los ecosistemas estén por delante, pues sino le haríamos un flaco favor a nuestros hijos y a los hijos de ellos. CUARTO: Nosotros consideramos que es fundamental que esta Sala pondere, que dentro de los OBJETIVOS DEL DESARROLLO SOSTENIBLE, se destaca el principio 6 que dice: “Objetivo 6.Garantizar la disponibilidad de agua y su gestión sostenible y el saneamiento para todos” Que por cierto ello va muy de la mano del principio in dubio pro aqua y bajo esos parámetros pedimos encontrar con lugar el amparo en todos sus términos. Cada día que pasa sin plantas de tratamiento comprometemos más al planeta, pues hay aguas contaminadas que siguen fluyendo desde las cuencas altas de Palmares, hasta el mar y esto debe ser analizado y contemplado en el voto de ustedes para este amparo. La verdad, el que se diga que “se hacen esfuerzos” para lograr que los proyectos caminen, es simplemente un argumento hueco que no debe ser escuchado por ustedes, pues existen derechos humanos ambiental en juego y así pedimos que se disponga. Exponer, como hacen los recurridos, que los proyectos de plantas de tratamiento no van a finalizar por salirse del préstamo del Banco KFW Frankfurt am Main es un argumento muy peligroso y generador de incertidumbre y el hecho de que los recurridos del INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS no hubiesen sido responsables y diligentes, no es algo que justifique limitar el financiamiento del proyecto Programa de Saneamiento en Zonas Prioritarias, todo lo contrario, consideramos que es fundamental que se disponga que es urgente que el Estado, con todas sus instituciones trabajen más fuertemente para materializar las plantas de tratamiento y los alcantarillados sanitarios, especialmente el de Palmares, donde tenemos 20 años sin que exista justicia ambiental pronta y cumplida.Pedimos que se disponga, como criterios viciados de inconstitucionalidad, los establecidos por el Ministerio de Hacienda que ordenaron finalizar la operación del Banco KFW Frankfurt am Main. Pedimos que se diga que es irracional y violatorio al principio de progresividad, el haber emitido un criterio que deja sin un financiamiento los proyectos de plantas de tratamiento y los alcantarillados sanitarios de las 4 localidades. Y no podíamos terminar sin señalar que estamos en una encrucijada ambiental planetaria, donde no debemos detenernos a restringir el financiamiento de 4 proyectos vitales, por lo que se pide que se encuentre con lugar el amparo”.
  6. 10Informa Freiner Lara Blanco, en su condición de alcalde de Golfito. Expone: “PRIMERO: Quien suscribe en calidad de alcalde municipal y como responsable del bienestar de la salud de la población de este cantón de Golfito manifiesto mi absoluto apoyo a las manifestaciones realizadas por el recurrente. SEGUNDO: El cantón de Golfito carece de una planta de tratamiento en la cual se le de (sic) el tratamiento adecuado a el agua negra, siendo lo anterior una completa violación al derecho a un ambiente sano y equilibrado, además representando de igual manera una transgresión al derecho universal de la salud pública. TERCERO: Que el accionar de forma arbitraria de jerarcas en cuanto a eliminar este proyecto de tan gran importancia, resulta completamente desubicado, y grotesco contra la comunidad que tenemos la gran urgencia de la construcción de una planta de tratamiento y alcantarillado sanitario La falta de una planta pone en riesgo la salud de muchas poblaciones; por lo expuesto anteriormente solicita este representante del Cantón de Golfito que, el presente recurso sea declarado con lugar y se obligue a los recurridos a la construcción de una planta de tratamiento y alcantarillado sanitario”.
  7. 11Informa Tobías Murillo Rodríguez, en su condición de alcalde de Garabito. Expone: “ÚNICO: Notificado del Amparo bajo el expediente N° 23-021589-0007-co, se procede a contestar de la siguiente manera, con el fin de atender lo solicitado por el recurrente: • Se remite informe sobre el caso en mención, referente a la construcción de plantas de tratamiento y sus respectivos alcantarillados sanitarios en el Cantón de Garabito. El cual permitirá evidenciar que mediante AME-530-2023-TM, de fecha 26 de setiembre de 2023, este Alcalde buscando solventar esta problemática a nuestra comunidad remitió solicitud al Presidente de la República. De lo cual derivan dos respuestas del AyA por instrucción del Presidente de la República Rodrigo Chaves Robles”. Pide se declare sin lugar el recurso.
  8. 12Por resolución de las 15:58 horas del 9 de julio de 2024, se amplió el proceso y se dio traslado al Alcalde de la Municipalidad de Palmares.
  9. 13Informa bajo juramento Andrés Vargas Rodríguez, en su carácter de Alcalde Municipal de Palmares. Explica: “En lo que respecta a la planta de tratamiento de aguas del cantón de Palmares, la Municipalidad está en constantes reuniones con los personeros de AYA, oficina regional de Palmares, con la finalidad de coordinar que le proyecto se desarrolle, ello en razón de que es competencia de dicho instituto buscar los fondos públicos para la construcción del mismo, por lo que, la Municipalidad de Palmares está a la espera de que AyA presente el proyecto constructivo para aprobación, conforme lo dicta el artículo 118 de la Ley de Construcciones "ARTÍCULO 118. Tratamiento de aguas residuales Las aguas residuales deben de ser tratadas y dispuestas en un alcantarillado sanitario, tanque séptico o un sistema de tratamiento que cumpla con lo dispuesto en el Reglamento de Aprobación de Sistemas de Tratamientos de Aguas Residuales, Decreto Ejecutivo N°39887-SMINAE y sus reformas o normativa que lo sustituya.Se prohíbe descargar las aguas residuales al sistema de alcantarillado pluvial. Además, el profesional responsable debe de acatar las disposiciones establecidas por el CFIA en el CIHSE." Cita la sentencia N° 2021002888 de las 9:30 del 26 de febrero del 2021. Añade que conforme: “(…) lo dicta la Ley Constitutiva del Instituto Costarricense de Acueductos y Alcantarillados en su artículo 1°, le corresponde a dicho instituto “fijar políticas establecer y aplicar normas, realizar y promover el planeamiento, financiamiento y desarrollo y de resolver todo lo relacionado con el suministro de agua potable y recolección y evacuación de aguas negras y residuos industriales líquidos, lo mismo que el aspecto normativo de los sistemas de alcantarillado pluvial en áreas urbanas, para todo el territorio nacional se crea el lnstituto Costarricense de Acueductos y Alcantarillados, como institución autónoma del Estado”.

En ese mismo sentido, el numeral 2° establece las funciones legales que el constituyente a AyA, a saber:

"a) Dirigir y vigilar todo lo concerniente para proveer a los habitantes de la república de un servicio de agua potable, recolección y evacuación de aguas negras y residuos industriales líquidos y de aguas pluviales en las áreas urbanas; b) Determinar la prioridad, conveniencia y viabilidad de los diferentes proyectos que se propongan para construir, reformar, ampliar, modificar obras de acueductos y alcantarillados, las cuales no se podrán ejecutar sin su aprobación; c) Promover la conservación de las cuencas hidrográficas y la protección ecológica, así como el control de la contaminación de las aguas (…); g) Administrar y operar directamente los sistemas de acueductos y alcantarillados en todo el país, los cuales se irán asumiendo tomando en cuenta la conveniencia y disponibilidad de recursos. Los sistemas que actualmente están administrados y operados por las corporaciones municipales podrán seguir a cargo de éstas, mientras suministren un servicio eficiente.

Bajo ningún concepto podrá delegar la administración de los sistemas de acueductos y alcantarillado sanitario del Área Metropolitana.

Tampoco podrá delegar la administración de los sistemas sobre los cuales exista responsabilidad financiera y mientras ésta corresponda directamente al Instituto.

Queda facultada la institución para convenir con organismos locales, la administración de fales servicios o administrarlos a través de juntas administradoras de integración mixta entre el instituto y las respectivas comunidades, siempre que así conviniere para la mejor prestación de los servicios y de acuerdo con los reglamentos respectivos. Por las mismas razones y con las mismas características, también podrán crearse juntas administradoras regionales que involucren a varias municipalidades, (...)

  • i)Construir ampliar y reformar los sistemas de acueductos y alcantarillados en aquellos casos en que sea necesario y así lo aconseje la mejor satisfacción de las necesidades nacionales; y j) Controlar la adecuada inversión de todos los recursos que el Estado asigne para obras de acueductos y alcantarillado sanitario." Como puede observarse, la competencia legal para construir sistemas de alcantarillado sanitario para el tratamiento de las aguas negras o servidas del cantón es AyA.

TERCERO: Para cumplir con lo ordenado en el expediente 02-007756-0007-CO, mediante resolución de las catorce horas treinta minutos del tres de febrero del dos mil quince, en lo que respecta a la Municipalidad de Palmares, dispuso"(...) disponer lo necesario a efecto que en el término improrrogable de un año contado a partir de la notificación de esta resolución, se le suministre el Plan Regulador del Cantón de Palmares a este Instituto, a fin de que dentro de los tres años y medio siguientes se concluya con el sistema de tratamiento de aguas negras y residuales del cantón de Palmares," en fecha 27 de marzo del 2023, al ser las diez horas 00n catorce minutos, la Arq. Silvia Carazo Angulo, Encargada del Departamento de Ingeniería Municipal a.i., remitió a través de correo electrónico a los representantes del Instituto de Acueductos y Alcantarillados del cantón de Palmares, señores Pedro Barrantes Ramírez, Jefe de Oficina Cantonal de Palmares, Melvin Castro González, Director Operación y Mantenimiento Región Central Oeste, y Tatiana Vindas Valerio, Ingeniera Operación y Mantenimiento de la Región Central Oeste, el oficio MP-DU-108-2023, haciéndoles entrega de la variable hidrogeológica que conforma el proceso del Plan Regulador del Cantón de Palmares, cumpliendo de esta forma en la entrega del insumo requerido para que dicho Instituto pueda concluir el sistema de tratamiento de aguas negras y residuales del cantón de Palmares, ello conforme al Plan de Inversión de Saneamiento 20212026 de AYA.

El estudio hidrogeológico realizado, tal y como consta en el apartado 1.1 Justificación, constituye el insumo y nace como una necesidad de generar conocimiento técnico en temas relacionados con disponibilidad, calidad y vulnerabilidad del recurso hídrico subterráneo, para que las instituciones tomadoras de decisiones cuenten con mayor información técnico científica.

Siendo así, de parte de la Municipalidad de Palmares no existe documento requerido por AyA pendiente para que éste Instituto pueda concluir el sistema de tratamiento de aguas negras y residuales del cantón de Palmares, ya que la restante normativa legal aplicable es la respectiva a trámites de construcción, regulados por la Ley de Construcciones y su respectivo reglamento, el cual es de alcance nacional, mismo al que se encuentran sujetos ambas instituciones públicas" (…)PETICIONES: Por Io tanto, al haber entregado la Municipalidad de Palmares la variable hidrogeológica del proceso del Plan Regulador, misma que era requerida por AyA para concluir el sistema de tratamiento de aguas negras y residuales del cantón de Palmares, solicito que se tenga por cumplido por parte de mi representada lo ordenado por la Sala Constitucional de la Corte Suprema de Justicia.” Pide se declare sin lugar el recurso.

  1. 14En los procedimientos seguidos se han observado las prescripciones legales.

Redacta la Magistrada Alvarado Paniagua; y,

Considerando:

I. OBJETO DEL RECURSO

El accionante expone que no existe planta de tratamiento, ni alcantarillado sanitario en el distrito central de Palmares (situación conocida en el expediente nro. 02- 007756-0007-CO). Indica que, en Garabito, propiamente Jacó, la situación es similar a la de Palmares, pues los ciudadanos se ven afectados por gran contaminación antrópica en sus quebradas y ríos, trayendo muerte a la vida fluvial y problemas de salud a los pobladores, a los ecosistemas fluviales y marinos. Comenta que, al parecer, el saneamiento de las aguas nunca ha sido prioridad de los recurridos. Ante dicha problemática las comunidades de Golfito, Quepos, Jacó y Palmares habían sido incluidas en el Programa de Saneamiento en Zonas Prioritarias, autorizándose así la construcción de plantas de tratamiento y sus respectivos alcantarillados sanitarios. No obstante, reclama que el ministro de Hacienda mediante el oficio MH-DM-OF-1303-2023 de fecha 16 de agosto de 2023, le comunicó al presidente ejecutivo del Instituto de Acueductos y Alcantarillados (ICAA) la cancelación del programa.

Añade que la eliminación del presupuesto y financiamiento de los proyectos de las 4 comunidades, se da bajo el burdo argumento que no existe prontitud en materializar las obras ni la obtención de actos habilitadores necesarios. Incluso, parte de la argumentación es que el presidente del ICAA solicitó al ministro de Hacienda eliminar del cronograma de actividades y financiamiento a los proyectos de Nombre02 y de Golfito, queriendo dejar solo los Palmares y Jacó. Reclama que ninguno de los 4 proyectos se llevarán a cabo por orden del Ministro de Hacienda, que dispuso dejar el Programa de Saneamiento en Zonas Prioritarias sin contenido presupuestario, asunto que conlleva al cierre irracional de la materialización de todas las obras en las 4 ciudades. Acusa que la actuación de las autoridades recurridas, violenta los numerales 21, 50 y 89 constitucionales, pues se entrará en un periodo desenfrenado, así como irreversible de daños ambientales perjudicando derechos de gente que incluso no ha nacido.

Solicita declarar con lugar el recurso y ordenar a las recurridas tomar las acciones pertinentes para activar la fuente de financiamiento de los proyectos de plantas de tratamiento y alcantarillados sanitarios de Palmares, Jacó, Nombre02 y Golfito.

II. HECHOS PROBADOS

De importancia para la decisión de este asunto, se estiman como debidamente demostrados los siguientes hechos, sea porque así han sido acreditados o bien porque la autoridad recurrida haya omitido referirse a ellos, según lo prevenido en el auto inicial:

En cuanto a la planta de tratamiento y alcantarillados de la Municipalidad de Palmares:

  • a)En recurso de amparo promovido por [Nombre01 001] contra la Municipalidad de Palmares y el Ministerio de Salud, tramitado bajo el expediente número 02-007756-0007-CO, se conocieron los mismos hechos denunciados por la falta de tratamiento de las aguas en la comunidad de Palmares. Se dispuso mediante la sentencia No. 2003- 001431 de las 00:00 horas del 21 de febrero de 2003: “POR TANTO: SE DECLARA CON LUGAR EL RECURSO. SE LE ORDENA JORGE ISAAC VASQUEZ PÉREZ, EN SU CONDICION DE ALCALDE MUNICIPAL DE PALMARES, Y A HEIDI RAMIREZ SANCHEZ, LUIS CARLOS ARAYA BADILLA, CORALIA PACHECO MOREIRA, OLDEMAR SEGURA RODRIGUEZ, Y MIGUEL ÁNGEL VASQUEZ, EN SU CONDICION DE REGIDORES DE LA MUNICIPALIDAD DE PALMARES, Y A EVERARDO RODRIGUEZ BASTOS, EN SU CALIDAD DE PRESIDENTE EJECUTIVO DEL INSTITUTO COSTARR ICENSE DE ACUEDUCTOS Y ALCANTARILLADOS, O A QUIEN EN SU LUGAR EJERZA SUS CARGOS, BAJO PENA DE DESOBEDIENCIA, QUE EN EL TÉRMINO IMPRORROGABLE DE DOCE MESES CONTADO A PARTIR DE LA NOTIFICACION DE ESTA SENTENCIA, GESTIONEN LA CONSTRUCCION DE UNA PLANTA DE TRATAMIENTOS DE AGUAS NEGRAS PARA TODA LA LOCALIDAD DE PALMARES, PARA LO CUAL SE DEBERA INCLUIR LA PRESENTACION DE UN ESTUDIO DE IMPACTO AMBIENTAL A LA SETENA.

EN LOS MISMOS TÉRMINOS, SE LES ORDENA A ESAS AUTORIDADES QUE PREVEAN, DENTRO DE SUS PRESUPUESTOS, LAS PARTIDAS NECESARIAS PARA LA CONSTRUCCION DE LA REFERIDA PLANTA DE TRATAMIENTO, Y QUE LE SUMINISTREN AL RECURRENTE UNA NOTA DONDE SE DETALLE EL PRESUPUESTO QUE SE DESTINARA A ESE FIN, Y UN CRONOGRAMA DE ACTIVIDADES, CON EL OBJETO DE QUE SE PUEDA FISCALIZAR EL CUMPLIMIENTO DE LAS ETAPAS DE LA CONSTRUCCION; TODO ESTO, EN EL ENTENDIDO QUE DEBERAN FINALIZAR LA TAREA INDICADA, EN UN TÉRMINO RAZONABLE, QUE NO PODRA EXCEDER DE DOS AÑOS. ADEMAS, SE LE ORDENA A EDUARDO LOPEZ C ARDENAS, EN SU CALIDAD DE MINISTRO DE SALUD A.I., O A QUIEN OCUPE SU PUESTO, BAJO PENA DE DESOBEDIENCIA, QUE COORDINE ESFUERZOS CON LOS OTROS RECURRIDOS Y FISCALICE QUE LA ME NCIONADA PLANTA DE TRATAMIENTO SE CONSTRUYA DE CONFORMIDAD CON LA NORMATIVA DE SALUD. SE LE ORDENA AL ALCALDE Y A LOS REGIDORES DE LA MUNICIPALIDAD DE PALMARES, O A QUIENES OCUPEN SUS CARGOS, BAJO PENA DE DESOBEDIENCIA, QUE DEN SOLUCION DEFINITIVA AL PROBLEMA SANITARIO PROVOCADO POR EL MER CADO MUNICIPAL DE PALMARES, EN EL PLAZO IMPRORROGABLE DE DOS AÑOS, Y A EDUARDO LOPEZ CARDENAS, EN SU CALIDAD DE MINISTRO DE SALUD A.I., O A QUIEN OCUPE SU PUESTO, BAJO PENA DE DESOBEDIENCIA, QUE ORDENE EL CIERRE DEL MERCADO MUNICIPAL DE PALMARES, SI EL PROBLEMA DE MARRAS NO ES CORREGIDO EN EL PLAZO INDICADO” (ver expediente número 02-007756-0007-CO, traído ad efectum videndi et probandi).

  • b)Por resolución interlocutoria 2023006228 de las 9:15 horas del 17 de marzo de 2023, dictada en expediente 02-007756-0007-CO, esta Sala dispuso: “Se acoge parcialmente la gestión de desobediencia, únicamente, respecto a la orden girada relacionada con la construcción de una planta de tratamiento de aguas negras para el Cantón de Palmares. Se reitera a Katerine Ramírez González y a Filadelfo Sancho, por su orden Alcaldesa y Presidente del Concejo Municipal, ambos de la Municipalidad de Palmares, a Alexei Carrillo Villegas, en su condición de Ministro de Salud, y a Alejandro Guillén Guardia, en su condición de Presidente Ejecutivo del Instituto Costarricense de Acueductos y Alcantarillados, o a quienes en sus lugares ocupen dichos cargos, el cumplimiento de lo dispuesto por esta Sala en la sentencia No. 2003-001431 de las 00:00 horas del 21 de febrero de 2003. Lo anterior, bajo la advertencia de ordenar la apertura de un procedimiento administrativo disciplinario, con base en lo dispuesto el artículo 53 de la Ley de la Jurisdicción Constitucional, en caso de no hacerlo y, además, testimoniar piezas al Ministerio Público conforme lo dispuesto en el artículo 71 de la Ley de la Jurisdicción Constitucional. En cuanto a lo ordenado respecto al Mercado Municipal de Palmares, no ha lugar a la gestión formulada. Notifíquese.” (ver expediente número 02-007756-0007-CO, traído ad efectum videndi et probandi).
  • c)El 27 de marzo del 2023, la Arq. Silvia Carazo Angulo, Encargada del Departamento de Ingeniería Municipal de Palmares, remitió a través de correo electrónico a los representantes del Instituto de Acueductos y Alcantarillados del cantón de Palmares, señores Pedro Barrantes Ramírez, Jefe de Oficina Cantonal de Palmares, Melvin Castro González, Director Operación y Mantenimiento Región Central Oeste, y Tatiana Vindas Valerio, Ingeniera Operación y Mantenimiento de la Región Central Oeste, el oficio MP-DU-108-2023, haciéndoles entrega de la variable hidrogeológica que conforma el proceso del Plan Regulador del Cantón de Palmares, insumo requerido para que dicho Instituto pueda concluir el sistema de tratamiento de aguas negras y residuales del cantón de Palmares, conforme al Plan de Inversión de Saneamiento 20212026 de AYA (informe de Alcalde de Palmares).

En cuanto a la planta de tratamiento y alcantarillados de Jacó, Nombre02 y Golfito d) Mediante la Ley número 9723 de fecha 14 de agosto de 2019, se aprobó Contrato de préstamo N° 28568 para financiar el programa de saneamiento de zonas prioritarias, suscrito con el Banco KFW Frankfurt am Main (en adelante KFW), publicada en el Alcance 210 a la Gaceta 183 del 27 de setiembre del 2019. Dicho Programa consta de cuatro componentes, para construir las obras de infraestructura en cuatro ciudades de Costa Rica, las cuales han sido escogidas como prioritarias según varios criterios técnicos de selección que implican entre otros el impacto sobre la población beneficiaria, el impacto ambiental y económico del proyecto, que son: Palmares, Jacó, Nombre02 y Golfito. Se dispone que en cada una de ellas se construirán obras de infraestructura para el saneamiento de aguas residuales que incluyen la construcción del alcantarillado, la red de recolección de aguas, una planta de tratamiento y en el caso de la ciudad de Palmares un Centro de Investigación y Formación en Tecnologías de Saneamiento. (ver informe de Ministerio de Hacienda y portal de la Asamblea Legislativa: Archivo_Leyes - Contrato de préstamo N° 28568 para financiar... (asamblea.go.cr)).

  • e)En distintas ocasiones entre el periodo del año 2021 al 2023, el Ministerio de Hacienda ha pedido al AyA proceder a coordinar las acciones que correspondan para realizar el cierre ordenado de la operación del crédito con el banco KFW y demás actividades asociadas al Proyecto, debido a que ha determinado hay un desempeño crítico, del Instituto Costarricense de Acueductos y Alcantarillados en la ejecución del programa. El Ministerio de Hacienda manifestó la preocupación en cuanto al desempeño del Programa, los evidentes y significativos retrasos mostrados a ese momento, incluyendo lo relativo a una de las principales contrataciones requeridas para la ejecución del Programa, como lo era la contratación del Consultor de Implementación (CI) y el aumento en los plazos para la recepción de ofertas, lo cual generó replanificaciones constantes, tanto en aspectos financieros (pagos a realizar) como en el cronograma de actividades.

También se le externó al Instituto Costarricense de Acueductos y Alcantarillados que el tipo de situaciones mostradas para el caso particular con el KFW se consideraban relevantes debido a que en otros Programas similares de la Institución ya se habían también evidenciado, generando incertidumbre en cuanto a la eficacia y eficiencia con que se estaban aplicando las lecciones aprendidas generadas en los Programas/proyectos de la Cartera del Instituto en ejecución y finalizados. Posterior a ello, la Declaración desierta del concurso de Precalificación de las empresas, implicó que luego el Instituto Costarricense de Acueductos y Alcantarillados tomara la decisión de iniciar nuevamente los procesos de contratación, pero de forma individual (por proyecto), por lo que se le hizo ver la preocupación sobre el plazo que desde ese momento el citado Instituto ya estimaba iba a requerir de más, para concluir el Programa y que correspondía a 24 meses adicionales (ver informe).

  • f)Respecto a las obras a desarrollarse en Golfito, Palmares y Jacó, el Ministerio de Hacienda instó al AyA seguir coordinando los espacios de comunicación necesarios con los interesados y con personal clave, que le permitieran optimizar y mejorar la gestión de los involucrados, de tal forma que se realizaran las alianzas estratégicas, así como los acuerdos requeridos para garantizar un inicio oportuno de las obras, minimizando cualquier contratiempo con el desarrollo de estas (ver informe).
  • g)Por el oficio número MH-DM-OF-2702-2022 de fecha 09 de noviembre del 2022, dirigido al señor Roberto Guzmán Gutiérrez, Presidente Ejecutivo del Instituto Costarricense de Acueductos y Alcantarillados en ese momento, se externó la preocupación por el crítico desempeño que mostraba el Programa, en donde a esa fecha no se había realizado ningún desembolso del financiamiento, y el avance físico del Programa era de un 18.22%, avance que representaba menos del 1% en el último año. Para ese entonces, le fueron indicados otros elementos que continuaban siendo críticos:
  • 1)La orden de inicio para las actividades asignadas al Consultor de Implementación se había dado apenas en agosto 2022;
  • 2)No se había finiquitado el convenio interinstitucional con INCOFER que resultaba fundamental para el desarrollo de la planta de tratamiento de Golfito;
  • 3)No se tenía claridad de la preinversión para otras obras del Programa y
  • 4)A pesar de que no se había iniciado con la contratación de obras ya se identifican sobrecostos en la ejecución de las mismas. De igual manera, se manifestó la urgencia de aprovechar la misión del KFW, que se celebraría en el mismo mes de noviembre 2022, para que en conjunto AyA-KfW diseñaran un plan de aceleración de actividades y obras que le permitan mitigar el impacto de los 24 meses de retrasos sufridos en el Programa y que a su vez el Instituto priorizara sus proyectos y recursos para garantizar el adecuado financiamiento de los alcances del Programa y a la vez realizara una adecuada planificación que permita la mitigación de riesgos futuros y nuevas fuentes de retrasos. También, se le solicitó al Instituto que una vez que se diera por finalizada la misión del KFW se presentara a este Ministerio el plan de acción que hubieran acordado entre el Banco y el Instituto Costarricense de Acueductos y Alcantarillados, para retomar la senda de ejecución del Programa, reducir el retraso existente y administrar los riesgos que podrían afectarlo.
  • h)Mediante oficio número MH-DM-OF-0143-2023 de fecha 2 de febrero de 2023, dirigido al Señor Alejandro Guillén Guardia, Presidente Ejecutivo del Instituto Costarricense de Acueductos y Alcantarillados, el Ministerio de Hacienda debió realizar un recordatorio al Instituto para la presentación del Plan de Acción que se le había solicitado en noviembre del 2022 en el oficio MH-DM-OF-2702-2022 y cuya solicitud estaba motivada en su crítico estado de situación. Asimismo, se externó que la Dirección de Crédito Público de este Ministerio había solicitado dicho Plan a la Unidad Ejecutora del Programa en distintas oportunidades; siendo que dicha Unidad había indicado que se requería de la definición de las líneas de acción por parte de la Administración Superior del Instituto Costarricense de Acueductos y Alcantarillados para revalorar el alcance del Programa y el aumento en los costos del mismo. Por lo que se le señala al Instituto que la presentación de dicho plan reviste gran importancia, dados los críticos resultados de desempeño mostrados por el Programa, en donde a ese momento, según el Cronograma del Acuerdo Separado del Préstamo, las obras de los cuatro proyectos de saneamiento mostraban un evidente retraso pues debieron haber iniciado en julio de 2021, cuando las licitaciones serían publicadas hasta el segundo trimestre del 2023.
  • i)Adicionalmente, se le indicó al Instituto Costarricense de Acueductos y Alcantarillados, que era de alto impacto en los indicadores de seguimiento del Programa, el hecho de la nula ejecución de recursos del préstamo al 31 de diciembre 2022, considerando que su entrada en vigencia data desde setiembre 2019. Para el Ministerio de Hacienda la toma de decisiones que la Unidad Ejecutora del Programa requería y la presentación del Plan de acción indicado, en donde estableciera una planificación clara y precisa para lograr la pronta aceleración del mismo y plasmara las actividades, responsables y plazos de cumplimiento, que llevarían a resolver de forma definitiva, entre otros, el tema del incremento exponencial del costo total del Programa, resultaba de especial importancia, no obstante se hizo caso omiso a las reiteradas solicitudes.(informe Ministro de Hacienda) j) Por el oficio número MH-DM-OF-1303-2023 de 16 de agosto de 2023, el Ministerio de Hacienda pide al AyA, que coordine las acciones que correspondan para realizar el cierre ordenado de la operación del crédito y demás actividades asociadas únicamente al financiamiento; solicitud que obedece, a las manifestaciones del Instituto Costarricense Acueductos y Alcantarillados, respecto a la imposibilidad de llevar a término, en cantidad y alcance, los proyectos inicialmente consensuados con el KFW con el monto del contrato de préstamo (ver informe Ministro de Hacienda) k) Ante los cambios en los proyectos de construcción de planta de tratamiento el Ay A determinó la propuesta para la ejecución de los proyectos de Jacó y Palmares, con un alcance acorde con los recursos disponibles.

Sin embargo, al Ministerio de Hacienda mediante nota MH-DM-OF-1303-2023 del 16 de agosto, al AyA proceder a coordinar las acciones que correspondan para realizar el cierre ordenado de la operación del crédito y demás actividades asociadas al mismo, la Presidencia Ejecutiva del AyA, se encuentra construyendo un análisis de riegos, implicaciones y acciones a desarrollar, desde el punto de vista legal, financiero, técnico y ambiental, que faciliten la propuesta de otras alternativas y la definición de una estrategia factible de financiamiento que permita la consecución del programa (informe del AyA).

III. SOBRE LA RECOLECCIÓN, TRATAMIENTO Y DISPOSICIÓN FINAL DE LAS AGUAS NEGRAS

Para cumplir, efectivamente, con la protección a un ambiente sano y ecológicamente equilibrado, el Estado, entendido en sentido amplio, está en el deber de disponer de las medidas necesarias para que en las comunidades del país se brinde tratamiento oportuno y efectivo a las aguas negras. En ese sentido, este Tribunal Constitucional ha sido del criterio que, tanto al Instituto Costarricense de Acueductos y Alcantarillados, como a las Municipalidades y al Ministerio de Salud, les corresponde -dentro de sus respectivos ámbitos de competencia-, velar por la debida recolección, tratamiento y disposición final de tales aguas. Así, en el caso específico del Instituto Costarricense de Acueductos y Alcantarillados, su propia Ley Constitutiva -Ley No. 2726 de 14 de abril de 1961 y sus reformas-, dispone lo siguiente:

“Artículo 1.- Con el objeto de dirigir, fijar políticas, establecer y aplicar normas, realizar y promover el planeamiento, financiamiento y desarrollo y de resolver todo lo relacionado con el suministro de agua potable y recolección y evacuación de aguas negras y residuos industriales líquidos, lo mismo que el aspecto normativo de los sistemas de alcantarillado pluvial en áreas urbanas, para todo el territorio nacional se crea el Instituto Costarricense de Acueductos y Alcantarillados, como institución autónoma del Estado.” Por lo que a dicha institución le corresponde, conforme a lo dispuesto en el artículo 2° de ese mismo cuerpo normativo (…) Dirigir y vigilar todo lo concerniente para proveer a los habitantes de la república de un servicio de agua potable, recolección y evacuación de aguas negras y residuos industriales líquidos y de aguas pluviales en las áreas urbanas (…)”. De igual forma, la Ley General de Salud -Ley No. 5395 de 30 de octubre de 1973-, dispone, en su artículo 2°, que le corresponde al Poder Ejecutivo, a través del Ministerio de Salud, la definición de la política nacional de salud, planificación y coordinación de todas las actividades públicas y privadas relativas a salud, así como la ejecución de aquellas actividades que le competen conforme a la ley.

De igual forma, el artículo 341 de la referida ley establece, dentro de las atribuciones del Ministerio de Salud, la de ordenar y tomar las medidas especiales que habilita esa normativa para evitar el riesgo o daño a la salud de las personas o que éstos se difundan o se agraven y para inhibir la continuación o reincidencia en la infracción de los particulares. En cuanto al tema específico, la Ley General de Salud, en su Libro 1, Título 3, Capítulo 3, “De las obligaciones y restricciones para la evacuación sanitaria de excretas y aguas servidas”, dispone -en lo conducente-, lo siguiente:

“Artículo 285.- Las excretas, las aguas negras, las servidas y las pluviales, deberán ser eliminadas adecuada y sanitariamente a fin de evitar la contaminación del suelo y de las fuentes naturales de agua para el uso y consumo humano, la formación de criaderos de vectores y enfermedades y la contaminación del aire mediante condiciones que atenten contra su pureza o calidad.” (El destacado no forma parte del original).

“Artículo 287.- Toda persona, natural o jurídica, propietaria de viviendas o de establecimientos o edificios en que las personas desarrollen sus actividades, responderá de que tales bienes dispongan de un sistema de disposición de excretas y de aguas negras y servidas aprobado por el Ministerio y los usuarios de viviendas, establecimientos o edificios estarán obligados a mantener dicho sistema en buenas condiciones de funcionamiento.” “Artículo 288.- Todo propietario queda obligado a conectar el sistema de eliminación de excretas de aguas negras y servidas de su propiedad al alcantarillado sanitario en los lugares en que éste estuviera en funcionamiento, salvo en los casos de excepción que los reglamentos pertinentes reconozcan como procedentes.” Asimismo, de dicha normativa se colige la obligación de las autoridades del Ministerio de Salud de velar por la aplicación y el control del cumplimiento de las disposiciones de esa ley y de su reglamentación, sin perjuicio de las facultades y obligaciones que leyes especiales otorguen e impongan a otros órganos o entes públicos dentro de sus respectivos campos de acción (artículo 337).

Se corrobora, así, las distintas funciones y obligaciones que el ordenamiento jurídico le impone al Instituto Costarricense de Acueductos y Alcantarillados, y al Ministerio de Salud, en materia de recolección, tratamiento y disposición final de las aguas negras. Funciones y obligaciones que, además -y como ya se adelantó en el considerando anterior-, se deben ejercer de forma coordinada, para asegurar así la eficacia y eficiencia administrativas.

IV.De la falta de una planta de tratamiento de desechos y aguas negras en Palmares. El recurrente reclama que a la fecha de interposición de este recurso, aun no se cuenta con una planta de tratamiento de desechos y aguas negras en diversos cantones. En cuanto el recurso se refiere a la falta de infraestructura del Cantón de Palmares en particular, en el informe dado en este asunto por el representante del AyA, este pide a la Sala tomar en cuenta lo dispuesto por el voto 03-01431 de las 10:53 horas del 21 de febrero de 2003, que dispuso acoger el recurso planteado el 18 de setiembre de 2002, por el mismo recurrente [Nombre01 002]. Recuerda que en esa oportunidad, esta Sala ordenó a los recurridos Instituto Costarricense de Acueductos y Alcantarillados y la Municipalidad de Palmares así como al Ministerio de Salud que iniciaran las gestiones para construir una planta de tratamiento en el término de 12 meses.

Efectivamente, en el año 2003, dispuso al efecto este Tribunal: “Se declara CON LUGAR el recurso. Se le ORDENA Jorge Isaac Vásquez Pérez, en su condición de Alcalde Municipal de Palmares, y a Heidi Ramírez Sánchez, Luis Carlos Araya Badilla, Coralia Pacheco Moreira, Oldemar Segura Rodríguez, y Miguel Ángel Vásquez, en su condición de Regidores de la Municipalidad de Palmares, y a Everardo Rodríguez Bastos, en su calidad de Presidente Ejecutivo del Instituto Costarricense de Acueductos y Alcantarillados, o a quien en su lugar ejerza sus cargos, BAJO PENA DE DESOBEDIENCIA, que en el término improrrogable de DOCE MESES contado a partir de la notificación de esta sentencia, gestionen la construcción de una planta de tratamientos de aguas negras para toda la localidad de Palmares, para lo cual se deberá incluir la presentación de un estudio de impacto ambiental a la SETENA. En los mismos términos, se les ordena a esas Autoridades que prevean, dentro de sus presupuestos, las partidas necesarias para la construcción de la referida planta de tratamiento, y que le suministren al recurrente una nota donde se detalle el presupuesto que se destinará a ese fin, y un cronograma de actividades, con el objeto de que se pueda fiscalizar el cumplimiento de las etapas de la construcción; todo esto, en el entendido que deberán finalizar la tarea indicada, en un término razonable, que no podrá exceder de DOS AÑOS.

Además, se le ordena a Eduardo López Cárdenas, en su calidad de Ministro de Salud a.i., o a quien ocupe su puesto, BAJO PENA DE DESOBEDIENCIA, que coordine esfuerzos con los otros recurridos y fiscalice que la mencionada planta de tratamiento se construya de conformidad con la normativa de Salud. Se le ordena al Alcalde y a los Regidores de la Municipalidad de Palmares, o a quienes ocupen sus cargos, BAJO PENA DE DESOBEDIENCIA, que den solución definitiva al problema sanitario provocado por el Mercado Municipal de Palmares, en el plazo IMPRORROGABLE DE DOS AÑOS, y a Eduardo López Cárdenas, en su calidad de Ministro de Salud a.i., o a quien ocupe su puesto, BAJO PENA DE DESOBEDIENCIA, que ordene el cierre del Mercado Municipal de Palmares, si el problema de marras no es corregido en el plazo indicado. Se condena al Estado, al Instituto Costarricense de Acueductos y Alcantarillados y a la Municipalidad de Palmares, al pago de los daños y perjuicios causados con los hechos que sirven de base a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso administrativo.

Se le advierte los recurridos que, de conformidad con el artículo 71 de la Ley de esta jurisdicción, se impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo y no la cumpliere o no la hiciere cumplir, siempre que el delito no esté más gravemente penado. Notifíquese la presente resolución TODOS LOS FUNCIONARIOS MENCIONADOS EN LA PARTE DISPOSITIVA DE ESTA SENTENCIA, o a quienes ocupen esos mismos puestos en su lugar, EN FORMA PERSONAL Sobre este extremo, el Alcalde de la Municipalidad de Palmares informa a esta Sala que, en la actualidad, en lo que se refiere al proyecto de tratamiento de aguas de ese Cantón, desde el 27 de marzo del 2023, la Arq. Silvia Carazo Angulo, Encargada del Departamento de Ingeniería Municipal de Palmares, remitió a través de correo electrónico al Jefe de Oficina Cantonal de Palmares, al Director Operación y Mantenimiento Región Central Oeste, y a la Ingeniera Operación y Mantenimiento de la Región Central Oeste todos del Instituto de Acueductos y Alcantarillados del cantón de Palmares, el oficio MP-DU-108-2023, haciéndoles entrega de la variable hidrogeológica que conforma el proceso del Plan Regulador del Cantón de Palmares, insumo requerido para que dicho Instituto pueda concluir el sistema de tratamiento de aguas negras y residuales del cantón de Palmares, conforme al Plan de Inversión de Saneamiento 20212026 de AYA.

Añade que la Municipalidad “está en (sic) constantes reuniones con los personeros de AYA, oficina regional de Palmares, con la finalidad de coordinar que el proyecto se desarrolle, ello en razón de que es competencia de dicho instituto buscar los fondos públicos para la construcción del mismo, por lo que, la Municipalidad de Palmares está a la espera de que AyA presente el proyecto constructivo para aprobación, conforme la normativa que regula el tratamiento de aguas residuales”.

Del cuadro fáctico descrito, en cuanto a la falta de construcción de la planta de tratamiento de aguas en la Municipalidad de Palmares, que se reclama a esa Municipalidad y al Instituto de Acueductos y Alcantarillados; desglósese este asunto para que sea tramitado en el expediente 02-7556-0007-CO.

V. De la falta de una planta de tratamiento de desechos y aguas negras y alcantarillado en Jacó, Nombre02 y Golfito

En cuanto el recurso se refiere a la falta de infraestructura de tratameinto de desechos y aguas negras y alcantarillados en las municipalidades de Jacó Nombre02 y Golfito; luego de revisados los informes rendidos bajo la solemnidad de juramento, así como la prueba aportada, se desprende que pese a la necesidad de contar en esas zonas con la planta de tratamiento de desechos y aguas negras y alcantarillado, – en el mismo sentido indicado en el Considerando IV anterior, referido a la Municipalidad de Palmares- en los cantones de Jacó, Nombre02 y Golfito, las autoridades recurridas revelan que, tampoco cuentan con esa infraestructura, necesaria para para ejecutar los procesos de tratamiento de las aguas residuales, según la legislación nacional y normativa técnica aplicable.

Sobre la omisión apuntada, el representante del Ministerio de Hacienda explica a esta Sala en su informe que, si bien desde el año 2019 por la ley 9723 se aprobó un contrato de préstamo para financiar el programa de saneamiento de zonas prioritarias, suscrito con el Banco KFW Frankfurt am Main (en adelante KFW, publicado en el Alcance 210 a la Gaceta 183 del 27 de setiembre del 2019). Lo cierto es que tal programa, -para construir las obras de infraestructura para el saneamiento de aguas residuales que incluyen la construcción del alcantarillado, la red de recolección de aguas, una planta de tratamiento y en el caso de la ciudad de Palmares un Centro de Investigación y Formación en Tecnologías de Saneamiento-, el Ministerio de Hacienda estimó necesario que el AyA hiciera un plan de acción, que ya había solicitado en noviembre del 2022, mediante el oficio MH-DM-OF-2702-2022.

En el informe, el representante del Ministerio de Hacienda hace énfasis en que la Dirección de Crédito Público de esa Cartera había solicitado un Plan a la Unidad Ejecutora del Programa en distintas oportunidades; que definiera las líneas de acción por parte de la Administración Superior del Instituto Costarricense de Acueductos y Alcantarillados para revalorar el alcance del Programa y el aumento en los costos del mismo. Lo anterior dado los críticos resultados de desempeño mostrados por el Programa, donde a ese momento, según el Cronograma del Acuerdo Separado del Préstamo, las obras de los cuatro proyectos de saneamiento mostraban un evidente retraso pues debieron haber iniciado en julio de 2021, cuando las licitaciones serían publicadas hasta el segundo trimestre del 2023.

Informa además, que el Ministerio de Hacienda advirtió al Instituto Costarricense de Acueductos y Alcantarillados, el alto impacto en los indicadores de seguimiento del Programa, debido a la nula ejecución de recursos del préstamo al 31 de diciembre 2022, considerando que su entrada en vigencia data desde setiembre 2019. Explica que para el Ministerio de Hacienda, la toma de decisiones que la Unidad Ejecutora del Programa requería y la presentación del Plan de acción indicado, en donde estableciera una planificación clara y precisa para lograr la pronta aceleración del mismo y plasmara las actividades, responsables y plazos de cumplimiento, que llevarían a resolver de forma definitiva, entre otros, el tema del incremento exponencial del costo total del Programa, resultaba de especial importancia, no obstante se hizo caso omiso a las reiteradas solicitudes.

Con base en la situación anterior, por el oficio número MH-DM-OF-1303-2023 de agosto de 2023, el Ministerio de Hacienda pidió al AyA, coordinar las acciones que correspondan para realizar el cierre ordenado de la operación del crédito y demás actividades asociadas al financiamiento; solicitud que explica obedece, a las manifestaciones del Instituto Costarricense Acueductos y Alcantarillados, respecto a la imposibilidad de llevar a término, en cantidad y alcance, los proyectos inicialmente consensuados con el KFW con el monto del contrato de préstamo.

Por su parte, el representante del AyA recurrido, añade en su informe que, en atención a los cambios en los proyectos de construcción de planta de tratamiento de los cuatro cantones (Jacó, Palmares, Nombre02 y Golfito) y ante la disposición del Ministerio de Hacienda que ordena el cierre de la operación de crédito para hacer dicha infraestructura, la Presidencia Ejecutiva del AyA se encuentra construyendo un análisis de riegos, implicaciones y acciones a desarrollar, desde el punto de vista legal, financiero, técnico y ambiental, que faciliten la propuesta de otras alternativas y la definición de una estrategia factible de financiamiento que permita la consecución del programa (informe del AyA).

Sin embargo, en el informe rendido por el representante del AyA recurrido, no se indica a esta Sala ni se desprende de la prueba aportada al expediente, qué desarrollo tiene el proyecto, si existiere, o qué acciones se han tomado, dirigidas a dar una solución a la falta de planta de tratamiento en los distintos cantones de Palmares, Jacó, Nombre02 y Golfito.

De conformidad con las consideraciones expuestas, la Sala tiene por acreditado que luego de cinco años que por ley se aprobó el préstamo para financiar el programa de saneamiento de zonas prioritarias de Golfito, Nombre02 Palmares y Jacó, suscrito con el KFW, publicado en el Alcance 210 a la Gaceta 183 del 27 de setiembre del 2019, el mismo se encuentra e en fase de cierre desde agosto de 2023, por la falta de ejecución. Llama la atención de esta Sala que el Ministerio de Hacienda pidió desde el año 2022 al AyA levantara un plan de acción para poder contar con el préstamos; sin embargo, a la fecha el AyA no ha respondido al Ministerio de Hacienda. Tampoco ha planteado alguna estrategia y mucho menos empezado a construir las obras de infraestructura para el saneamiento de aguas residuales y las construcciones que ello incluye, para los cantones de Palmares, Jacó, Golfito y Quepos.

Así las cosas, se descarta la vulneración a los derechos fundamentales que se atribuyen al Ministerio de Hacienda; y se acoge el recurso en cuanto se dirige contra el AyA, pues observa esta Sala que la autoridad recurrida no sólo no ha brindado una solución definitiva a los problemas denunciados, sino que tampoco se desprende que haya diseñado una estrategia distinta, ante el cierre del préstamo suscrito con el KFW, de Alemania.

Por otro lado se observa que tampoco las municipalidades en cuestión han tomado acciones definidas y concretas para impulsar a que el AyA asuma su deber legal de para proveer a los habitantes de sus circunscripciones de un servicio de evacuación de aguas negras, conforme lo dispone la Ley Constitutiva Instituto Costarricense Acueductos y Alcantarillados) y se dé de manera coordinada una solución al problema de aguas descrito.

Como en otras ocasiones se ha expuesto, comprende este Tribunal, que algunos problemas ambientales requieren coordinación entre diversas instancias estatales; sin embargo, ello no justifica que el AyA dentro del ámbito de sus competencias y en atención a las necesidades de los administrados, decida en este caso, simplemente no responder a las notas enviadas por el Ministerio de Hacienda que le instan desde el 2022; y no presentara el plan de acción que se le pidió para establecer una planificación clara y precisa para lograr la pronta aceleración del contrato de préstamo para financiar el programa de saneamiento de zonas prioritarias.

En suma, no se observa que se hayan hecho esfuerzos importantes para hacer efectivo el contrato de préstamo para financiar el programa de saneamiento de zonas prioritarias o que se tomaran acciones necesarias en coordinación con las instancias municipales y sanitarias que corresponden, a fin de brindar las soluciones a la falta de saneamiento de las aguas. Como consecuencia procede acoger el recurso en cuanto se dirige contra el Instituto de Acueductos y Alcantarillados y las municipalidades de Jacó, Golfito y Quepos, al haberse quebrantado el derecho a un ambiente sano y ecológicamente equilibrado del recurrente.

VI.Conclusión. Así las cosas, en cuanto el recurso se dirige contra la Municipalidad de Palmares, debe estarse el recurrente a lo indicado en la sentencia número 03-01431 de las 10:53 horas del 21 de febrero de 2003, que dispuso acoger el recurso planteado el 18 de setiembre de 2002. En cuanto se dirige contra el Ministerio de Hacienda, procede desestimar el recurso y se acoge parcialmente, en cuanto se dirige contra el AyA y las municipalidades de Garabito, Golfito y Quepos, por violación del derecho a un ambiente sano y ecológicamente equilibrado del recurrente, en los términos que se indican en la parte dispositiva de esta sentencia.

VII. DOCUMENTACIÓN APORTADA AL EXPEDIENTE

Se previene a las partes que de haber aportado algún documento en papel, así como objetos o pruebas contenidas en algún dispositivo adicional de carácter electrónico, informático, magnético, óptico, telemático o producido por nuevas tecnologías, éstos deberán ser retirados del despacho en un plazo máximo de 30 días hábiles contados a partir de la notificación de esta sentencia. De lo contrario, será destruido todo aquel material que no sea retirado dentro de este plazo, según lo dispuesto en el "Reglamento sobre Expediente Electrónico ante el Poder Judicial", aprobado por la Corte Plena en sesión N° 27-11 del 22 de agosto del 2011, artículo XXVI y publicado en el Boletín Judicial número 19 del 26 de enero del 2012, así como en el acuerdo aprobado por el Consejo Superior del Poder Judicial, en la sesión N° 43-12 celebrada el 3 de mayo del 2012, artículo LXXXI.

Por tanto:

Se declara parcialmente con lugar el recurso por violación del derecho a un ambiente sano y ecológicamente equilibrado. En cuanto el recurso se dirige en parte contra la Municipalidad de Palmares y el Instituto de Acueductos y Alcantarillados en lo referente a esa Municipalidad, desglósese este asunto para que sea tramitado en el expediente 02-7556-0007-CO. En cuanto el recurso se dirige contra las municipalidades de Garabito, Golfito y Nombre02 y el Instituto de Acueductos y Alcantarillados, en lo referente a esas municipalidades, se declara con lugar el recurso. Se ordena a Luis Alejandro Guillén Guardia, en su condición de presidente ejecutivo del Instituto Costarricense de Acueductos y Alcantarillados, Jong Kwan Kim Jin, en su condición de alcalde de Nombre02 Freiner Lara Blanco, en su condición de alcalde de Golfito y Tobías Murillo Rodríguez, en su condición de alcalde de Garabito o a quienes ocupen tales cargos, que dentro del ámbito de sus competencias, en el término de dieciocho meses contado a partir de la notificación de esta sentencia, tomen las medidas que corresponden, gestionen y coordinen la construcción de una planta de tratamientos de aguas negras y alcantarillado para las distintas localidades de Quepos, Golfito y Garabito, respectivamente.

Se les ordena a esas autoridades que prevean, dentro de sus presupuestos, las partidas necesarias para la construcción de la referida planta de tratamiento y alcantarillado, y que suministren al recurrente el detalle del presupuesto que se destinará a ese fin, así como un cronograma de las actividades, con el objeto de que pueda fiscalizar el cumplimiento de las etapas de la construcción; todo esto, en el entendido de que deberán finalizar la tarea indicada, en un término razonable, que no podrá exceder los dos años. Se advierte a las autoridades recurridas que, de conformidad con lo establecido por el artículo 71, de la Ley de la Jurisdicción Constitucional, se impondrá prisión de tres meses a dos años o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada dentro de un recurso de amparo y no la cumpliere o no la hiciere cumplir, siempre que el delito no esté más gravemente penado.

Se condena a la Instituto Costarricense de Acueductos y Alcantarillados, a las Municipalidades de Quepos, Golfito y Garabito al pago de las costas, daños y perjuicios ocasionados con los hechos que sirven de base a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso administrativo. En cuanto al Ministerio de Hacienda, se declara sin lugar el recurso. Se notifica al Ministro de Salud para que coordine esfuerzos con los recurridos y fiscalice que las mencionadas plantas de tratamiento e infraestructura, se construyan en cada localidad, de conformidad con la normativa de salud.

Fernando Castillo V.

Paul Rueda L.

Jorge Araya G.

Anamari Garro V.

Ingrid Hess H.

Aracelly Pacheco S.

Alexandra Alvarado P.

*747DRXUH80T461*

Document not found. Documento no encontrado.

Implementing decreesDecretos que afectan

    TopicsTemas

      Concept anchorsAnclajes conceptuales

        Spanish key termsTérminos clave en español

        This document cites

        • Ley 2726 Organic Law of the Costa Rican Institute of Aqueducts and Sewers
        • Ley 5395 General Health Law

        Este documento cita

        • Ley 2726 Ley Constitutiva del Instituto Costarricense de Acueductos y Alcantarillados
        • Ley 5395 Ley General de Salud

        News & Updates Noticias y Actualizaciones

        All articles → Todos los artículos →

        Weekly Dispatch Boletín Semanal

        Field reporting and policy analysis from Costa Rica's forests. Reportajes y análisis de política desde los bosques de Costa Rica.

        ✓ Subscribed. ✓ Suscrito.

        One email per week. No spam. Unsubscribe in one click. Un correo por semana. Sin spam. Cancela en un clic.

        Or WhatsApp channelO canal de WhatsApp →
        Coalición Floresta © 2026 · All rights reserved © 2026 · Todos los derechos reservados

        Stay Informed Mantente Informado

        Conservation news and action alerts, straight from the field Noticias de conservación y alertas de acción, directo desde el campo

        Email Updates Actualizaciones por Correo

        Weekly updates, no spam Actualizaciones semanales, sin spam

        Successfully subscribed! ¡Suscripción exitosa!

        WhatsApp Channel Canal de WhatsApp

        Join to get instant updates on your phone Únete para recibir actualizaciones instantáneas en tu teléfono

        Join Channel Unirse al Canal
        Coalición Floresta Coalición Floresta © 2026 Coalición Floresta. All rights reserved. © 2026 Coalición Floresta. Todos los derechos reservados.
        🙏