La Gaceta N° 192, 02/10/2015
OutcomeResultado
The manual establishes the administrative procedure and requirements for obtaining stormwater drainage approval in the Municipality of Carrillo, with an estimated total period of 22 calendar days.El manual establece el procedimiento administrativo y los requisitos para obtener la aprobación del desfogue pluvial en la Municipalidad de Carrillo, con un plazo total estimado de 22 días naturales.
SummaryResumen
This manual, approved by the Municipality of Carrillo in 2015, establishes the administrative procedure for obtaining stormwater drainage approval—a prerequisite for construction permits for infrastructure, earthwork, and civil projects. The application is processed by the Municipal Engineering and Services Department and the Territorial Development Department. It details an exhaustive list of requirements, including a copy of the cadastral map, a recent property certification, owner authorization, a professional responsibility letter from a CFIA-registered engineer, topographic plans, complete hydrological studies, and storm sewer design, with additional requirements if discharge is to a natural watercourse or existing drain. A site inspection is conducted within 8 calendar days, and a final decision is issued within 15 calendar days, for an estimated total of 22 calendar days. The manual relies on Law 8220 (Protection of Citizens from Excessive Bureaucracy), the Urban Planning Law, the Construction Law and regulations, the Water Law, and AyA and INVU regulations, with mandatory updates every three months.Este manual, aprobado por la Municipalidad de Carrillo en 2015, establece el procedimiento administrativo para que los administrados obtengan la aprobación del desfogue pluvial, un requisito previo al permiso de construcción para obras de infraestructura, movimiento de tierras y obras civiles. El trámite se presenta ante la Dirección de Ingeniería y Servicios Municipales y el Departamento de Desarrollo Territorial. Detalla la lista exhaustiva de requisitos, que incluyen copia del plano catastrado, certificación literal de la propiedad, autorización del propietario, nota de responsabilidad profesional de un ingeniero inscrito en el CFIA, planos topográficos, estudios hidrológicos completos y diseño de alcantarillado pluvial, con requisitos adicionales si el desfogue descarga a un cauce natural o a un colector existente. Se prevé una inspección de campo en un plazo máximo de 8 días y una resolución final en no más de 15 días naturales, para un proceso total estimado en 22 días naturales. El manual se fundamenta en la Ley 8220 de Protección al Ciudadano del Exceso de Trámites, la Ley de Planificación Urbana, la Ley de Construcciones y su reglamento, la Ley de Aguas, y reglamentos del AyA y el INVU, con actualización periódica cada tres meses.
Key excerptExtracto clave
The Municipal Council of Carrillo, by agreement 2, clause 19, issued in Ordinary Session No. 17-2015, held on April 28, 2015, approved the text of the Administrative Procedure Manual for Obtaining Stormwater Drainage Approval submitted by the Municipal Engineering and Services Department... 1. PROCESS: Obtaining Stormwater Drainage Approval 1.1 Objective To establish the procedure and requirements for the applicant to obtain stormwater drainage approval, a necessary document to continue with procedures in different institutions and to obtain the Construction Permit for infrastructure works, earth moving, and civil works. 1.2 Participating Units Engineering and Services Department Territorial Development Department 1.2.1 Norm and Policy 1. Law 8220 "Protection of Citizens from Excessive Administrative Requirements and Procedures" 2. Compliance with the Municipal Code, Urban Planning Law, Construction Law and its regulations, Water Law.El Concejo Municipal de Carrillo, mediante acuerdo 2, inciso 19, emitido en la Sesión Ordinaria Nº 17-2015, celebrada el día 28 de abril del 2015, aprobó el texto del Manual de procedimiento para la obtención de Desfogue Pluvial presentado por la Dirección de Ingeniería y Servicios Municipales... 1. PROCESO: Obtención del Desfogue Pluvial 1.1 Objetivo Establecer el procedimiento y los requisitos para que el administrado pueda obtener el desfogue pluvial, documento necesario para continuar con los trámites en diferentes instituciones y obtención del Permiso de Construcción en obras de infraestructura, movimiento de tierras, obras civiles. 1.2 Unidades que Participan Dirección de Ingeniería y Servicios Departamento de Desarrollo Territorial 1.2.1 Norma y Política 1. Ley 8220 "Protección al Ciudadano del Exceso de Requisitos y Trámites Administrativos 2. Cumplir con el Código Municipal, Ley de Planificación Urbana, Ley de Construcciones y su reglamento, Ley de Aguas.
Pull quotesCitas destacadas
"Se estima como máximo, 22 días naturales a partir de su presentación en plataforma de servicios para la resolución de cada caso."
"A maximum of 22 calendar days is estimated from its submission on the services platform for the resolution of each case."
Sección 1.2.3 - Tiempo Estimado del Proceso
"Se estima como máximo, 22 días naturales a partir de su presentación en plataforma de servicios para la resolución de cada caso."
Sección 1.2.3 - Tiempo Estimado del Proceso
"Cuando se establezca una servidumbre pluvial hasta un cauce de dominio público se requerirá el visto bueno del o los colindantes, cuyas firmas deberán estar debidamente autenticadas por un notario público."
"When a stormwater easement is established to a public-domain watercourse, the approval of the adjoining neighbors will be required, whose signatures must be duly authenticated by a public notary."
Requisito 6.4
"Cuando se establezca una servidumbre pluvial hasta un cauce de dominio público se requerirá el visto bueno del o los colindantes, cuyas firmas deberán estar debidamente autenticadas por un notario público."
Requisito 6.4
"El periodo de retorno mínimo a usar es de 10 años."
"The minimum return period to be used is 10 years."
Requisito 6.1 - Desfogue a cauce permanente o intermitente
"El periodo de retorno mínimo a usar es de 10 años."
Requisito 6.1 - Desfogue a cauce permanente o intermitente
Full documentDocumento completo
throughout the entire text - Complete Text of Regulation 2 Administrative Procedure Manual for Obtaining Stormwater Discharge Approval Complete Text record: 106EA7 MUNICIPALIDAD DE CARRILLO ADMINISTRATIVE PROCEDURE MANUAL FOR OBTAINING STORMWATER DISCHARGE APPROVAL (DESFOGUE PLUVIAL) The Municipal Council of Carrillo, by means of agreement 2, clause 19, issued in Ordinary Session No. 17-2015, held on April 28, 2015, approved the text of the Procedure Manual for obtaining Stormwater Discharge Approval (Desfogue Pluvial) submitted by the Directorate of Engineering and Municipal Services. Therefore, in compliance with Article 4, Publicity of procedures, of Law No. 8220, Protection of the Citizen from Excess Procedures and Requirements, its respective publication proceeds:
1. PROCESS: Obtaining Stormwater Discharge Approval (Desfogue Pluvial) 1.1 Objective To establish the procedure and requirements so that the citizen (administrado) may obtain the stormwater discharge approval (desfogue pluvial), a document necessary to continue with procedures before different institutions and to obtain the Construction Permit for infrastructure works, earthworks (movimiento de tierras), and civil works.
1.2 Participating Units Directorate of Engineering and Services Department of Territorial Development 1.2.1 Regulations and Policy 1. Law 8220 "Protection of the Citizen from Excess Requirements and Administrative Procedures" 2. Comply with the Municipal Code, Urban Planning Law, Construction Law and its regulations, Water Law.
3. Abide by the provisions issued by the Municipal Services Area of the Comptroller General of the Republic and the Municipal Internal Audit.
4. Update the procedures that make up the manuals every three months, or at a time that is convenient according to institutional needs.
1.2.2 Persons responsible for the process Director of Engineering and Services Head of the Department of Territorial Development.
Documents and Forms . Procedure Manuals 1.2.3 Estimated Process Time A maximum of 22 calendar days is estimated from its submission at the service platform for the resolution of each case.
1.3 Procedures Complete the application form Submit the following requirements at the Service Platform area:
| No. | REQUIREMENT | LEGAL BASIS |
|---|
| 1 | Copy of the Cadastral Plan of the Property | Articles 3 and 4, Municipal Code | | 2 | Literal certification of the property, issued no more than one month prior | Articles 3 and 4, Municipal Code | | 3 | Letter from the owner authorizing the procedure | Articles 3 and 4, Municipal Code | | 4 | Note from the responsible professional registered with the CFIA indicating their responsibility for the calculations and the project | Articles 2, 3, 6, and 7 of the Regulations for the contracting of consulting services in Engineering and Architecture. | | 5 | Plan of the topographic profile and contour lines of the property at every meter. On flat terrains, obtaining contours at every 20 cm must be considered. | Urban Planning Law, Chapters II and IV; Construction Law and its Regulations for the plan approval procedure for construction. | | 6 | Complete hydrological study signed by a professional in Civil Engineering or Construction. It must contain the project description, methodology to be used, image of the basin to be analyzed, estimation of rainfall intensity based on the equations prepared by Varhson and Alfaro for the CFIA or another improved form, calculation of flow generated by the project including the flow generated by the tributary area of the zone, before and after the project. Green areas, roofs, streets, among others, must be included. | Urban Planning Law, Chapters II and IV; Construction Law and its Regulations for the plan approval procedure for construction. | | 6.1 | In case the discharge is to a permanent or intermittent watercourse: A hydrological study of the watercourse's basin must be submitted, which must include cross-sections of the watercourse every ten meters covering 50 meters upstream and 100 meters downstream from the discharge point. The discharge outlet points must be determined using Lambert coordinates. The outlet elevation must be indicated, considering it the lowest point of the discharge structure. A hydraulic design of the discharge structure must be submitted. If necessary, it must be indicated whether protection works for the watercourse must be built. The minimum return period to be used is 10 years. A certification from the Water Department of MINAE indicating the type of watercourse must be provided. | A y A Technical Standards Regulations, Chapters 1.3, 2.3, and 3.3; Executive Decree 32688-MP-MIVAH-SMEIC, published in the Official Gazette La Gaceta No. 199 of October 17, 2005; Organic Law of the CFIA, standard plan regulations, subsection b). INVU Construction Regulations, No. 3391 and its amendments, chapter III.3.10 | | 6.2 | In case of discharging to an existing collector, a Hydrological study must be submitted; line, direction, diameter, and capacity of the existing pipe, as well as its slope, material, conditions, and other characteristics. | A y A Technical Standards Regulations, Chapters 1.3, 2.3, and 3.3; INVU Construction Regulations, No. 3391 and its amendments, chapter III.3.10 | | 6.3 | Storm sewer design must be designed up to the interconnection points with existing systems or to the natural receiving body in the case of stormwater. Compliance with the A y A Technical Standards Regulations is required. | A y A Technical Standards Regulations, Chapters 1.3, 2.3, and 3.3; INVU Construction Regulations, No. 3391 and its amendments, chapter III.3.10 | | 6.4 | When a stormwater easement (servidumbre pluvial) is established to a public-domain watercourse, the approval (visto bueno) of the adjacent property owner(s) will be required, whose signatures must be duly authenticated by a notary public. The approval must include the authorized width of that easement. Registration of said easement must be carried out before the registry. However, the procedure may be initiated in parallel. | Urban Planning Law, Chapters II and IV; Construction Law and its Regulations for the plan approval procedure for construction. | | 6.5 | Site plan of complexes and roofs of the Project (indicating all impervious surfaces). | | 7 Construction design sheet for the proposed stormwater system, Indicate on the plan the discharge point of the stormwater to the river or stream or an existing system. (It must be part of the set of construction sheets of the project to be submitted to the Department of Territorial Development for its respective construction license).
Construction Law and its Regulations for the plan approval procedure for construction.
Within a period not exceeding 8 calendar days, the site inspection will be carried out, corroborating the data established by the applicant or the professional. Within a period not exceeding 15 calendar days, a response will be given with the approval or the request for corrections (subsanes), as the case may be.
It is effective from its publication.
en la totalidad del texto - Texto Completo Norma 2 Manual de procedimiento para la obtención de Desfogue Pluvial Texto Completo acta: 106EA7 MUNICIPALIDAD DE CARRILLO MANUAL DE PROCEDIMIENTO ADMINISTRATIVO PARA LA OBTENCIÓN DE DESFOGUE PLUVIAL El Concejo Municipal de Carrillo, mediante acuerdo 2, inciso 19, emitido en la Sesión Ordinaria Nº 17-2015, celebrada el día 28 de abril del 2015, aprobó el texto del Manual de procedimiento para la obtención de Desfogue Pluvial presentado por la Dirección de Ingeniería y Servicios Municipales, por lo que en cumplimiento con el artículo 4, Publicidad de los trámites de la Ley Nº 8220, Protección al Ciudadano de Exceso de Trámites y Requisitos, procede a su respectiva publicación:
1. PROCESO: Obtención del Desfogue Pluvial 1.1 Objetivo Establecer el procedimiento y los requisitos para que el administrado pueda obtener el desfogue pluvial, documento necesario para continuar con los trámites en diferentes instituciones y obtención del Permiso de Construcción en obras de infraestructura, movimiento de tierras, obras civiles.
1.2 Unidades que Participan Dirección de Ingeniería y Servicios Departamento de Desarrollo Territorial 1.2.1 Norma y Política 1. Ley 8220 "Protección al Ciudadano del Exceso de Requisitos y Trámites Administrativos 2. Cumplir con el Código Municipal, Ley de Planificación Urbana, Ley de Construcciones y su reglamento, Ley de Aguas.
3. Acatar las disposiciones emitidas por el Área de Servicios Municipales de la Contraloría General de la República y la Auditoría Interna Municipal.
4. Actualizar los procedimientos que forman los manuales cada tres meses, o en el momento que sea conveniente según las necesidades institucionales.
1.2.2 Personas responsables del proceso Director de Ingeniería y Servicios Jefe de Departamento de Desarrollo Territorial.
Documentos y Formularios . Manuales de Procedimientos 1.2.3 Tiempo Estimado del Proceso Se estima como máximo, 22 días naturales a partir de su presentación en plataforma de servicios para la resolución de cada caso.
1.3 Procedimientos Llenar hoja de solicitud Entregar los siguientes requisitos en el área de Plataforma de Servicios:
| Nº | REQUISITO | FUNDAMENTO LEGAL | | --- | --- | --- | | 1 | Copia del Plano Catastrado de la Propiedad | Artículos 3 y 4 Código Municipal | | 2 | Certificación literal de la propiedad, con un plazo no mayor a un mes de haber sido emitida | Artículos 3 y 4 Código Municipal | | 3 | Carta del propietario autorizando realizar el trámite | Artículos 3 y 4 Código Municipal | | 4 | Nota del profesional responsable inscrito ante el CFIA la cual indica su responsabilidad en los cálculos y del proyecto | Artículos 2,3,6 y 7 del Reglamento para la contratación de servicios de consultoría en Ingeniería y Arquitectura. | | 5 | Plano del perfil topográfico y de curvas de nivel de la propiedad a cada metro. En terrenos planos se deberá de considerar obtener curvas a cada 20 cm | Ley de Planificación Urbana, capítulos II y IV Ley de Construcciones y su Reglamento para el trámite de visado de planos para la construcción. | | 6 | Estudio hidrológico completo firmado por un profesional en Ingeniería Civil o Construcción. Debe de contener la descripción del proyecto, metodología a usar, imagen de la cuenca a analizar, estimación de la intensidad de lluvia con base en las ecuaciones confeccionadas por Varhson y Alfaro para el CFIA u otra forma mejorada, cálculo caudal generado por el proyecto incluyendo el caudal generado por el área tributaria de la zona, antes y después del proyecto, se deben incluir zonas verdes, techos, calles, entre otros. | Ley de Planificación Urbana, capítulos II y IV Ley de Construcciones y su Reglamento para el trámite de visado de planos para la construcción. | | 6.1 Caso que el desfogue se de a un cauce permanente o intermitente: Se debe presentar el estudio hidrológico de la cuenca del cauce el cual debe de incluir secciones transversales del cauce cada diez metros las cuales abarcarán 50 metros aguas arriba y 100 metros aguas abajo del punto de desfogue. Se deberá de determinar por medio de coordenadas Lambert los puntos de salida del desfogue. Se debe de indicar la elevación de salida, considerándola el punto más bajo de la estructura de desfogue. Se deberá de presentar diseño hidráulico de la estructura de desfogue. Si es necesario se deberá de indicar si se deben de construir obras de protección al cauce. El periodo de retorno mínimo a usar es de 10 años Se debe aportar una certificación del Departamento de aguas del MINAE donde se indique el tipo de cauce. | Reglamento de Normas Técnicas del AyA, Capítulos 1.3, 2.3 y 3.3 Decreto Ejecutivo- 32688-MP-MIVAH- SMEIC, publicada en el Diario Oficial La Gaceta Nº 199 del 17 de octubre de 2005 Ley orgánica del CFIA, reglamento de planos tipo, inciso b). Reglamento de construcciones del INVU, Nº 3391 y sus reformas, capítulo III.3.10 | | | 6.2. En caso de desfogar a un colector existente debe de presentar en estudio Hidrológico; línea, dirección, diámetro y capacidad de tubería existente, así como la pendiente, material, condiciones y demás características de la misma. | Reglamento de Normas Técnicas del AyA, Capítulos 1.3, 2.3 y 3.3 Reglamento de construcciones del INVU, Nº 3391 y sus reformas, capítulo III.3.10 | | | 6.3. Diseño de alcantarillado pluvial se deberá diseñar hasta los puntos de interconexión con los sistemas existentes o al cuerpo receptor natural en el caso de pluvial. Se deberá de cumplir con el Reglamento de Normas Técnicas del AyA. | Reglamento de Normas Técnicas del AyA, Capítulos 1.3, 2.3 y 3.3 Reglamento de construcciones del INVU, Nº 3391 y sus reformas, capítulo III.3.10 | | | 6.4. Cuando se establezca una servidumbre pluvial hasta un cauce de dominio público se requerirá el visto bueno del o los colindantes, cuyas firmas deberán estar debidamente autenticadas por un notario público. En el visto bueno se debe incluir el ancho que se autoriza de esa servidumbre. Se deberá de realizar la inscripción de dicha servidumbre ante el registro. Sin embargo se podrá iniciar el trámite en forma paralela | Ley de Planificación Urbana, capítulos II y IV Ley de Construcciones y su Reglamento para el trámite de visado de planos para la construcción. | | | 6.5. Planta de conjuntos y de techos del Proyecto (señalando todas las superficies impermeabilizadas), | | | 7 Lamina de diseño constructivo de sistema pluvial propuesto, Indicar en el plano el punto de descarga de los pluviales al río o quebrada o un sistema existente. (Debe ser parte del conjunto de láminas constructivas del proyecto a presentar ante Departamento de Desarrollo Territorial para su respectiva licencia constructiva).
Ley de Construcciones y su Reglamento para el trámite de visado de planos para la construcción.
En un plazo no mayor a 8 días naturales se realizará la inspección al sitio corroborando los datos establecidos por el solicitante o el profesional En un plazo no mayor de 15 días naturales se dará respuesta con la aprobación o la solicitud de subsanes según sea el caso.
Rige a partir de su publicación.