02/10/2015
OutcomeResultado
Approves the administrative procedure manual for obtaining a stormwater discharge permit from the Municipality of Carrillo, establishing the technical and legal requirements and processing timelines.Aprueba el manual de procedimiento para la obtención del desfogue pluvial ante la Municipalidad de Carrillo, estableciendo los requisitos técnicos, legales y plazos del trámite.
SummaryResumen
This document establishes the administrative procedure and requirements for the public to obtain a stormwater discharge permit from the Municipality of Carrillo. This permit is a prerequisite for continuing with various applications and obtaining construction licenses for infrastructure projects, earthworks, and civil works. The manual details the participating units (the Engineering and Services Directorate and the Territorial Development Department), the applicable legal framework (Law 8220, the Municipal Code, the Urban Planning Law, the Construction Law and its regulations, the Water Law), the estimated processing time (a maximum of 22 calendar days), and the list of requirements, which include: a copy of the cadastral plan, a recent property title certification, the owner's authorization, a letter from the responsible CFIA-registered professional, topographic and contour maps, a complete hydrological study, and the stormwater system design. Specific conditions are outlined depending on the discharge point (permanent or intermittent watercourse, existing collector, or stormwater easement). The manual also states that a site inspection will be conducted within 8 calendar days and a final decision (approval or request for corrections) will be issued within 15 calendar days.Este documento establece el procedimiento y los requisitos administrativos para que los administrados obtengan el desfogue pluvial ante la Municipalidad de Carrillo, un trámite necesario para continuar con distintos permisos y obtener la licencia de construcción en obras de infraestructura, movimiento de tierras y obras civiles. El manual detalla las unidades participantes (Dirección de Ingeniería y Servicios y el Departamento de Desarrollo Territorial), el marco normativo aplicable (Ley 8220, Código Municipal, Ley de Planificación Urbana, Ley de Construcciones y su reglamento, Ley de Aguas), el tiempo estimado del proceso (22 días naturales como máximo) y la lista de requisitos, entre los que se incluyen: copia del plano catastrado, certificación literal de la propiedad, autorización del propietario, nota del profesional responsable, planos topográficos, estudio hidrológico completo y diseño del sistema pluvial. Se especifican condiciones particulares según el punto de descarga (cauce permanente o intermitente, colector existente, servidumbre pluvial). Asimismo, se indica que la inspección de campo se realizará en un plazo máximo de 8 días naturales y la respuesta final (aprobación o solicitud de subsanación) en no más de 15 días naturales.
Key excerptExtracto clave
1. PROCESS: Obtaining the Stormwater Discharge 1.1 Objective To establish the procedure and requirements for citizens to obtain the stormwater discharge permit, a document necessary to continue with procedures in different institutions and to obtain the Construction Permit for infrastructure works, earthworks, and civil works. 1.3 Procedures Fill out the application form Submit the following requirements at the Service Platform area: [list of requirements with legal basis] A site inspection to verify the information provided by the applicant or the professional will be conducted within a maximum of 8 calendar days. A response with the approval or a request for corrections, as the case may be, will be issued within a maximum of 15 calendar days.1. PROCESO: Obtención del Desfogue Pluvial 1.1 Objetivo Establecer el procedimiento y los requisitos para que el administrado pueda obtener el desfogue pluvial, documento necesario para continuar con los trámites en diferentes instituciones y obtención del Permiso de Construcción en obras de infraestructura, movimiento de tierras, obras civiles. 1.3 Procedimientos Llenar hoja de solicitud Entregar los siguientes requisitos en el área de Plataforma de Servicios: [lista de requisitos con fundamento legal] En un plazo no mayor a 8 días naturales se realizará la inspección al sitio corroborando los datos establecidos por el solicitante o el profesional En un plazo no mayor de 15 días naturales se dará respuesta con la aprobación o la solicitud de subsanes según sea el caso.
Pull quotesCitas destacadas
"Establecer el procedimiento y los requisitos para que el administrado pueda obtener el desfogue pluvial, documento necesario para continuar con los trámites en diferentes instituciones y obtención del Permiso de Construcción en obras de infraestructura, movimiento de tierras, obras civiles."
"To establish the procedure and requirements for citizens to obtain the stormwater discharge permit, a document necessary to continue with procedures in different institutions and to obtain the Construction Permit for infrastructure works, earthworks, and civil works."
1.1 Objetivo
"Establecer el procedimiento y los requisitos para que el administrado pueda obtener el desfogue pluvial, documento necesario para continuar con los trámites en diferentes instituciones y obtención del Permiso de Construcción en obras de infraestructura, movimiento de tierras, obras civiles."
1.1 Objetivo
"Se estima como máximo, 22 días naturales a partir de su presentación en plataforma de servicios para la resolución de cada caso."
"A maximum of 22 calendar days is estimated, from the date of submission at the service platform, for the resolution of each case."
1.2.3 Tiempo Estimado del Proceso
"Se estima como máximo, 22 días naturales a partir de su presentación en plataforma de servicios para la resolución de cada caso."
1.2.3 Tiempo Estimado del Proceso
"En un plazo no mayor a 8 días naturales se realizará la inspección al sitio corroborando los datos establecidos por el solicitante o el profesional En un plazo no mayor de 15 días naturales se dará respuesta con la aprobación o la solicitud de subsanes según sea el caso."
"A site inspection to verify the information provided by the applicant or the professional will be conducted within a maximum of 8 calendar days. A response with the approval or a request for corrections, as the case may be, will be issued within a maximum of 15 calendar days."
1.3 Procedimientos
"En un plazo no mayor a 8 días naturales se realizará la inspección al sitio corroborando los datos establecidos por el solicitante o el profesional En un plazo no mayor de 15 días naturales se dará respuesta con la aprobación o la solicitud de subsanes según sea el caso."
1.3 Procedimientos
Full documentDocumento completo
in the entirety of the text - Complete Text of Rule 2 Administrative Procedure Manual for Obtaining a Storm Drainage Permit (Desfogue Pluvial) Complete Text of Act: 106EA7 MUNICIPALITY OF CARRILLO ADMINISTRATIVE PROCEDURE MANUAL FOR OBTAINING A STORM DRAINAGE PERMIT (DESFOGUE PLUVIAL) The Municipal Council of Carrillo, by agreement 2, item 19, issued in Regular Session No. 17-2015, held on April 28, 2015, approved the text of the Procedure Manual for obtaining a Storm Drainage Permit (Desfogue Pluvial) presented by the Directorate of Engineering and Municipal Services, and therefore, in compliance with Article 4, Publicity of procedures, of Law No. 8220, Protection of the Citizen from Excessive Procedures and Requirements, proceeds with its respective publication:
1. PROCESS: Obtaining a Storm Drainage Permit (Desfogue Pluvial) 1.1 Objective To establish the procedure and requirements so that the administered party can obtain the storm drainage permit (desfogue pluvial), a document necessary to continue with procedures in different institutions and to obtain the Construction Permit (Permiso de Construcción) for infrastructure works, earthworks (movimiento de tierras), and civil works.
1.2 Participating Units Directorate of Engineering and Services Department of Territorial Development 1.2.1 Rule and Policy 1. Law 8220 "Protection of the Citizen from Excessive Requirements and Administrative Procedures" 2. Comply with the Municipal Code, Urban Planning Law, Construction Law and its regulations, Water Law.
3. Abide by the provisions issued by the Municipal Services Area of the Comptroller General of the Republic and the Municipal Internal Audit.
4. Update the procedures that form the manuals every three months, or at any time it is convenient according to institutional needs.
1.2.2 Persons responsible for the process Director of Engineering and Services Head of the Department of Territorial Development.
Documents and Forms . Procedure Manuals 1.2.3 Estimated Process Time A maximum of 22 calendar days is estimated from its submission at the services platform for the resolution of each case.
1.3 Procedures Fill out the application form Submit the following requirements at the Services Platform area:
| No. | REQUIREMENT | LEGAL BASIS |
|---|---|---|
| 1 | Copy of the Cadastral Plan of the Property | Articles 3 and 4 of the Municipal Code |
| 2 | Literal certification of the property, issued no more than one month prior | Articles 3 and 4 of the Municipal Code |
| 3 | Letter from the owner authorizing the procedure | Articles 3 and 4 of the Municipal Code |
| 4 | Note from the responsible professional registered with the CFIA indicating their responsibility for the calculations and the project | Articles 2, 3, 6, and 7 of the Regulation for the contracting of consulting services in Engineering and Architecture. |
| 5 | Plan of the topographic profile and contour lines of the property at every meter. On flat terrain, obtaining contours every 20 cm must be considered. | Urban Planning Law, Chapters II and IV; Construction Law and its Regulations for the plan approval procedure for construction. |
| 6 | Complete hydrological study signed by a professional in Civil Engineering or Construction. It must contain the project description, methodology to be used, image of the basin to be analyzed, estimation of rainfall intensity based on the equations developed by Varhson and Alfaro for the CFIA or another improved form, calculation of flow generated by the project including the flow generated by the tributary area of the zone, before and after the project; green areas, roofs, streets, among others, must be included. | Urban Planning Law, Chapters II and IV; Construction Law and its Regulations for the plan approval procedure for construction. |
| 6.1 | If the drainage outlet (desfogue) is to a permanent or intermittent watercourse: A hydrological study of the watercourse basin must be presented, which must include cross-sections of the watercourse every ten meters, covering 50 meters upstream and 100 meters downstream from the drainage outlet point. The outlet points of the drainage must be determined using Lambert coordinates. The outlet elevation must be indicated, considering the lowest point of the drainage structure. A hydraulic design of the drainage structure must be presented. If necessary, it must be indicated whether protection works for the watercourse must be built. The minimum return period to use is 10 years. A certification from the Water Department of MINAE must be provided indicating the type of watercourse. | Technical Standards Regulation of AyA, Chapters 1.3, 2.3, and 3.3; Executive Decree 32688-MP-MIVAH-SMEIC, published in the Official Gazette La Gaceta No. 199 of October 17, 2005; Organic Law of the CFIA, standard plan regulation, subsection b). Construction Regulations of INVU, No. 3391 and its amendments, Chapter III.3.10 |
| 6.2. | In the case of draining into an existing storm sewer (colector): The hydrological study must present the line, direction, diameter, and capacity of the existing pipe, as well as its slope, material, conditions, and other characteristics. | Technical Standards Regulation of AyA, Chapters 1.3, 2.3, and 3.3; Construction Regulations of INVU, No. 3391 and its amendments, Chapter III.3.10 |
| 6.3. | The storm sewer system (alcantarillado pluvial) design must be carried out up to the interconnection points with existing systems or to the natural receiving body in the case of stormwater. The Technical Standards Regulation of AyA must be complied with. | Technical Standards Regulation of AyA, Chapters 1.3, 2.3, and 3.3; Construction Regulations of INVU, No. 3391 and its amendments, Chapter III.3.10 |
| 6.4. | When a storm drainage easement (servidumbre pluvial) is established to a public domain watercourse, the approval of the adjacent landowner(s) will be required, whose signatures must be duly authenticated by a notary public. The approved width of said easement must be included in the approval. The registration of said easement (servidumbre) must be carried out before the registry. However, the procedure may be initiated in parallel. | Urban Planning Law, Chapters II and IV; Construction Law and its Regulations for the plan approval procedure for construction. |
| 6.5. | Overall site plan and roof plan of the Project (indicating all impervious surfaces), |
7 Construction design sheet of the proposed storm drainage system, indicating on the plan the stormwater discharge point to the river or stream or an existing system. (This must be part of the set of construction sheets for the project to be submitted to the Department of Territorial Development for its respective construction license.)
Construction Law and its Regulations for the plan approval procedure for construction.
Within a period not exceeding 8 calendar days, an on-site inspection will be carried out, verifying the data established by the applicant or the professional. Within a period not exceeding 15 calendar days, a response will be given with the approval or the request for corrections (subsanes), as the case may be.
Effective from its publication.
en la totalidad del texto - Texto Completo Norma 2 Manual de procedimiento para la obtención de Desfogue Pluvial Texto Completo acta: 106EA7 MUNICIPALIDAD DE CARRILLO MANUAL DE PROCEDIMIENTO ADMINISTRATIVO PARA LA OBTENCIÓN DE DESFOGUE PLUVIAL El Concejo Municipal de Carrillo, mediante acuerdo 2, inciso 19, emitido en la Sesión Ordinaria Nº 17-2015, celebrada el día 28 de abril del 2015, aprobó el texto del Manual de procedimiento para la obtención de Desfogue Pluvial presentado por la Dirección de Ingeniería y Servicios Municipales, por lo que en cumplimiento con el artículo 4, Publicidad de los trámites de la Ley Nº 8220, Protección al Ciudadano de Exceso de Trámites y Requisitos, procede a su respectiva publicación:
1. PROCESO: Obtención del Desfogue Pluvial 1.1 Objetivo Establecer el procedimiento y los requisitos para que el administrado pueda obtener el desfogue pluvial, documento necesario para continuar con los trámites en diferentes instituciones y obtención del Permiso de Construcción en obras de infraestructura, movimiento de tierras, obras civiles.
1.2 Unidades que Participan Dirección de Ingeniería y Servicios Departamento de Desarrollo Territorial 1.2.1 Norma y Política 1. Ley 8220 "Protección al Ciudadano del Exceso de Requisitos y Trámites Administrativos 2. Cumplir con el Código Municipal, Ley de Planificación Urbana, Ley de Construcciones y su reglamento, Ley de Aguas.
3. Acatar las disposiciones emitidas por el Área de Servicios Municipales de la Contraloría General de la República y la Auditoría Interna Municipal.
4. Actualizar los procedimientos que forman los manuales cada tres meses, o en el momento que sea conveniente según las necesidades institucionales.
1.2.2 Personas responsables del proceso Director de Ingeniería y Servicios Jefe de Departamento de Desarrollo Territorial.
Documentos y Formularios . Manuales de Procedimientos 1.2.3 Tiempo Estimado del Proceso Se estima como máximo, 22 días naturales a partir de su presentación en plataforma de servicios para la resolución de cada caso.
1.3 Procedimientos Llenar hoja de solicitud Entregar los siguientes requisitos en el área de Plataforma de Servicios:
| Nº | REQUISITO | FUNDAMENTO LEGAL | | --- | --- | --- | | 1 | Copia del Plano Catastrado de la Propiedad | Artículos 3 y 4 Código Municipal | | 2 | Certificación literal de la propiedad, con un plazo no mayor a un mes de haber sido emitida | Artículos 3 y 4 Código Municipal | | 3 | Carta del propietario autorizando realizar el trámite | Artículos 3 y 4 Código Municipal | | 4 | Nota del profesional responsable inscrito ante el CFIA la cual indica su responsabilidad en los cálculos y del proyecto | Artículos 2,3,6 y 7 del Reglamento para la contratación de servicios de consultoría en Ingeniería y Arquitectura. | | 5 | Plano del perfil topográfico y de curvas de nivel de la propiedad a cada metro. En terrenos planos se deberá de considerar obtener curvas a cada 20 cm | Ley de Planificación Urbana, capítulos II y IV Ley de Construcciones y su Reglamento para el trámite de visado de planos para la construcción. | | 6 | Estudio hidrológico completo firmado por un profesional en Ingeniería Civil o Construcción.
Debe de contener la descripción del proyecto, metodología a usar, imagen de la cuenca a analizar, estimación de la intensidad de lluvia con base en las ecuaciones confeccionadas por Varhson y Alfaro para el CFIA u otra forma mejorada, cálculo caudal generado por el proyecto incluyendo el caudal generado por el área tributaria de la zona, antes y después del proyecto, se deben incluir zonas verdes, techos, calles, entre otros. | Ley de Planificación Urbana, capítulos II y IV Ley de Construcciones y su Reglamento para el trámite de visado de planos para la construcción. | | 6.1 Caso que el desfogue se de a un cauce permanente o intermitente: Se debe presentar el estudio hidrológico de la cuenca del cauce el cual debe de incluir secciones transversales del cauce cada diez metros las cuales abarcarán 50 metros aguas arriba y 100 metros aguas abajo del punto de desfogue. Se deberá de determinar por medio de coordenadas Lambert los puntos de salida del desfogue.
Se debe de indicar la elevación de salida, considerándola el punto más bajo de la estructura de desfogue. Se deberá de presentar diseño hidráulico de la estructura de desfogue. Si es necesario se deberá de indicar si se deben de construir obras de protección al cauce. El periodo de retorno mínimo a usar es de 10 años Se debe aportar una certificación del Departamento de aguas del MINAE donde se indique el tipo de cauce. | Reglamento de Normas Técnicas del AyA, Capítulos 1.3, 2.3 y 3.3 Decreto Ejecutivo- 32688-MP-MIVAH- SMEIC, publicada en el Diario Oficial La Gaceta Nº 199 del 17 de octubre de 2005 Ley orgánica del CFIA, reglamento de planos tipo, inciso b). Reglamento de construcciones del INVU, Nº 3391 y sus reformas, capítulo III.3.10 | | | 6.2. En caso de desfogar a un colector existente debe de presentar en estudio Hidrológico; línea, dirección, diámetro y capacidad de tubería existente, así como la pendiente, material, condiciones y demás características de la misma. | Reglamento de Normas Técnicas del AyA, Capítulos 1.3, 2.3 y 3.3 Reglamento de construcciones del INVU, Nº 3391 y sus reformas, capítulo III.3.10 | | | 6.3.
Diseño de alcantarillado pluvial se deberá diseñar hasta los puntos de interconexión con los sistemas existentes o al cuerpo receptor natural en el caso de pluvial. Se deberá de cumplir con el Reglamento de Normas Técnicas del AyA. | Reglamento de Normas Técnicas del AyA, Capítulos 1.3, 2.3 y 3.3 Reglamento de construcciones del INVU, Nº 3391 y sus reformas, capítulo III.3.10 | | | 6.4. Cuando se establezca una servidumbre pluvial hasta un cauce de dominio público se requerirá el visto bueno del o los colindantes, cuyas firmas deberán estar debidamente autenticadas por un notario público. En el visto bueno se debe incluir el ancho que se autoriza de esa servidumbre. Se deberá de realizar la inscripción de dicha servidumbre ante el registro. Sin embargo se podrá iniciar el trámite en forma paralela | Ley de Planificación Urbana, capítulos II y IV Ley de Construcciones y su Reglamento para el trámite de visado de planos para la construcción. | | | 6.5.
Planta de conjuntos y de techos del Proyecto (señalando todas las superficies impermeabilizadas), | | | 7 Lamina de diseño constructivo de sistema pluvial propuesto, Indicar en el plano el punto de descarga de los pluviales al río o quebrada o un sistema existente. (Debe ser parte del conjunto de láminas constructivas del proyecto a presentar ante Departamento de Desarrollo Territorial para su respectiva licencia constructiva).
Ley de Construcciones y su Reglamento para el trámite de visado de planos para la construcción.
En un plazo no mayor a 8 días naturales se realizará la inspección al sitio corroborando los datos establecidos por el solicitante o el profesional En un plazo no mayor de 15 días naturales se dará respuesta con la aprobación o la solicitud de subsanes según sea el caso.
Rige a partir de su publicación.