Coalición Floresta Logo Coalición Floresta Search Buscar
Language: English
About Acerca de Contact Contacto Search Buscar Notes Notas Donate Donar Environmental Law Derecho Ambiental
About Acerca de Contact Contacto Search Buscar Notes Notas Donate Donar Environmental Law Derecho Ambiental
Language: English
Beta Public preview Vista previa

← Environmental Law Center← Centro de Derecho Ambiental

Reglamento 0 (Compañía Nacional de Fuerza y Luz S.A., 10/10/2023) · 10/10/2023

Temporary Regulation for Distributed Energy Resources for Self-Consumption at CNFLReglamento temporal para la atención de los recursos energéticos distribuidos para autoconsumo en la CNFL

View document ↓ Ver documento ↓ View original source ↗ Ver fuente original ↗

Loading…Cargando…

OutcomeResultado

Repealed normNorma derogada

SummaryResumen

This temporary regulation establishes the requirements, procedures, and technical conditions for the interconnection of distributed energy resources (DER) based on renewable sources for self-consumption, both with and without delivery of surplus energy to the grid, within the distribution network of the Compañía Nacional de Fuerza y Luz (CNFL). It is issued in the absence of all regulatory instruments that ARESEP must issue pursuant to Law No. 10086 and its Executive Decree No. 43879-MINAE, in order not to hinder the development of distributed generation. It defines the responsibilities of CNFL and DER owners (PDER), the stages of application, inspection, contract signing, and meter installation, as well as tariff-related aspects and circuit penetration capacity. It includes the obligation to obtain environmental feasibility from SETENA for systems greater than 500 kVA. The provisions will be adjusted as ARESEP publishes definitive regulation.El reglamento establece, de manera temporal, los requisitos, procedimientos y condiciones técnicas para la interconexión de recursos energéticos distribuidos (DER) basados en fuentes renovables para autoconsumo, tanto con entrega de excedentes a la red como sin ella, en la red de distribución de la Compañía Nacional de Fuerza y Luz (CNFL). Se dicta en ausencia de la totalidad de los instrumentos regulatorios que debe emitir la ARESEP conforme a la Ley N° 10086 y su Decreto Ejecutivo N° 43879-MINAE, con el fin de no obstaculizar el desarrollo de la generación distribuida. Define responsabilidades de la CNFL y de los propietarios de los DER (PDER), etapas de solicitud, inspección, firma de contrato e instalación de medidores, así como aspectos tarifarios y de capacidad de penetración por circuito. Incluye la obligación de gestionar viabilidad ambiental ante SETENA para sistemas mayores a 500 kVA. Las disposiciones se ajustarán conforme la ARESEP publique la regulación definitiva.

Key excerptExtracto clave

Article 5 – Environmental Feasibility Distributed generation systems for self-consumption with a capacity greater than 500 kVA must obtain environmental feasibility from the National Environmental Technical Secretariat (SETENA). Article 10 – DER Penetration Capacity per Distribution Circuit As established in the Procedure for DER penetration capacity per distribution circuit that integrates with the SEN distribution networks, established by ARESEP, while penetration studies are being developed, CNFL shall use as a maximum capacity criterion not to exceed fifteen percent (15%) of the maximum demand of the circuit. Maximum demand is considered as that measured at the output of the substation to which the circuit is connected under normal operating conditions of the same; the power associated with backup circuits is not considered. This does not apply for cases without delivery of surplus to the grid.Artículo 5º- Viabilidad ambiental Los sistemas de generación distribuida para autoconsumo con potencia mayor a 500 kVA deberán gestionar la viabilidad ambiental ante la Secretaría Técnica Nacional Ambiental (SETENA). Artículo 10.- Capacidad de penetración de DER por circuito de distribución Según se establece en el Procedimiento de capacidad de penetración de DER por circuito de distribución que se integran con las redes de distribución del SEN, establecido por la ARESEP, mientras se desarrollan los estudios de penetración, la CNFL utilizará como criterio de capacidad máxima, no exceder el quince por ciento (15%) de la demanda máxima del circuito. Se considera demanda máxima, como aquella medida a la salida de la subestación a la cual está conectado el circuito bajo condiciones de operación normal del mismo, no se considera la potencia asociada a los circuitos de respaldo. Esto no aplica para casos sin entrega de excedentes.

Pull quotesCitas destacadas

  • "Los sistemas de generación distribuida para autoconsumo con potencia mayor a 500 kVA deberán gestionar la viabilidad ambiental ante la Secretaría Técnica Nacional Ambiental (SETENA)."

    "Distributed generation systems for self-consumption with a capacity greater than 500 kVA must obtain environmental feasibility from the National Environmental Technical Secretariat (SETENA)."

    Artículo 5º

  • "Los sistemas de generación distribuida para autoconsumo con potencia mayor a 500 kVA deberán gestionar la viabilidad ambiental ante la Secretaría Técnica Nacional Ambiental (SETENA)."

    Artículo 5º

  • "Este reglamento establece los requisitos, procedimientos y demás detalles necesarios para la operatividad e interconexión de los Recursos Energéticos Distribuidos, en adelante DER, para autoconsumo en la Compañía Nacional de Fuerza y Luz S.A., en adelante CNFL, mientras la ARESEP publica lo correspondiente."

    "This regulation establishes the requirements, procedures, and other necessary details for the operation and interconnection of Distributed Energy Resources, hereinafter DER, for self-consumption at the Compañía Nacional de Fuerza y Luz S.A., hereinafter CNFL, while ARESEP publishes the corresponding instruments."

    Por tanto

  • "Este reglamento establece los requisitos, procedimientos y demás detalles necesarios para la operatividad e interconexión de los Recursos Energéticos Distribuidos, en adelante DER, para autoconsumo en la Compañía Nacional de Fuerza y Luz S.A., en adelante CNFL, mientras la ARESEP publica lo correspondiente."

    Por tanto

  • "La CNFL utilizará como criterio de capacidad máxima, no exceder el quince por ciento (15%) de la demanda máxima del circuito."

    "CNFL shall use as a maximum capacity criterion not to exceed fifteen percent (15%) of the maximum demand of the circuit."

    Artículo 10

  • "La CNFL utilizará como criterio de capacidad máxima, no exceder el quince por ciento (15%) de la demanda máxima del circuito."

    Artículo 10

Full documentDocumento completo

Articles

in the entirety of the text - Complete Text of Standard 0 Temporary regulation for the attention of distributed energy resources for self-consumption at CNFL COMPAÑÍA NACIONAL DE FUERZA Y LUZ S. A (This standard was repealed by Article 25 of the Regulation for the attention of distributed energy resources (DER) for self-consumption at CNFL, published in La Gaceta N° 38 of February 26, 2025) GERENCIA GENERAL DIRECCIÓN DISTRIBUCIÓN DE LA ENERGÍA DIRECCIÓN COMERCIALIZACIÓN TEMPORARY REGULATION FOR THE ATTENTION OF DISTRIBUTED ENERGY RESOURCES FOR SELF-CONSUMPTION AT CNFL 10/04/2023

General Provisions

  1. 1That on January 7, 2022, Ley N° 10086 Promotion and regulation of distributed energy resources from renewable sources was published in the Official Gazette La Gaceta.
  2. 2That on February 1, 2023, Decreto Ejecutivo 43879-MINAE Regulation to the Law for the promotion and regulation of distributed energy resources from renewable sources, N° 10086 of January seven, 2022, was published in the official gazette La Gaceta.
  3. 3That Decreto 43879-MINAE in its Article 29 establishes that:

Decreto Ejecutivo N° 39220-MINAE, denominated "Reglamento Generación distribuida para autoconsumo con fuentes renovables modelo de contratación neta sencilla" of September 14, 2015, published in La Gaceta N° 196 of October 08, 2015, is repealed in its entirety.

  1. 4That Ley N° 10086 establishes as its objective:

The present law has as its objective to establish the necessary conditions to promote and regulate, under a special regime of efficient, secure and sustainable integration, the activities related to the access, the installation, the connection, the interaction and the control of distributed energy resources based on renewable energy sources.

  1. 5That Ley N° 10086 establishes in its Article 9 the declaration of public interest:

The research and promotion of distributed energy resources, renewable source energies and energy storage systems that result in benefit for the comprehensiveness of the SEN and the best satisfaction of the public interest are declared of public interest.

  1. 6That Ley N° 10086 establishes in its Article 6 the responsibility of the Autoridad Reguladora de los Servicios Públicos (ARESEP) to establish the tariffs, procedures, methodologies, requirements and regulatory instruments for the implementation and compliance with Law 10086.
  2. 7That as of the date of publication of Decreto 43879-MINAE, the tariffs, procedures, methodologies, requirements and regulatory instruments for the implementation and compliance with Ley N° 10086 are not available.
  3. 8That Ley N° 6227 Ley General de la Administración Pública establishes in its Articles 11, 12, 15 and 16 that:

CHAPTER I

Considering:

11

1. The Public Administration shall act subject to the legal system and may only perform those acts or provide those public services that said system authorizes, according to the hierarchical scale of its sources.

2. The act expressly regulated by written norm shall be considered authorized, at least regarding motive or content, even if it is in an imprecise form.

12

1. A public service shall be considered authorized when the subject and the purpose of the same have been indicated. In this case, the entity in charge may provide it in accordance with its own regulations on the other aspects of the activity, under the rule of Law.

15

1. Discretion may occur even in the absence of law in the specific case, but it shall be subject in all cases to the limits imposed on it by the legal system expressly or implicitly, to ensure that its exercise is efficient and reasonable.

16

1. In no case may acts be dictated contrary to univocal rules of science or technique, or to elementary principles of justice, logic or convenience.

Granting the power that the law gives to the administrator, to regulate itself in order to be able to comply with the acts in pursuit of a public purpose ordered by law.

  1. 9That according to resolution RE-0076-JD-2023 Tariff methodology derived from Law N° 10086 referring to: a) Fixing of interconnection charges to the distribution networks applicable to distributed energy resources, b) Tariff for access to the distribution networks by the distributed generator, c) Purchase-sale of excess energy (excedentes) and economic recognition between distribution companies, as well as by the distributed generators to the distribution company, d) Recognition of the costs, profitability, investments and fee incurred by the distribution companies for the integration of distributed energy resources into the SEN (tariff T-DER), for cases without delivery of excess energy (excedentes) to the network, stages 1, 2 and 4 must be applied (Stage 1: Interconnection application (variable CSInt+1,e)), (Stage 2: Engineering studies and initial inspection (variable CEIt+1,e)) and (Stage 4: Reinspection in case stage 3 is unsuccessful- (variable CRIt+1,e)).

10.-That on September 14, 2023, the resolutions RE-0103- IE-2023, RE-0104-IE-2023, RE-0105-IE-2023 and RE-0106- IE-2023 of the ARESEP, referring to the fixing of tariffs for distributed energy resources, according to Law N° 10086, were published in supplement N° 174 to La Gaceta N° 169.

11.-That on September 14, 2023, resolution RE0095- JD-2023 of the ARESEP, corresponding to the Procedure for DER penetration capacity per distribution circuit that are integrated with the distribution networks of the SEN, was published in supplement N° 174 to La Gaceta N° 169. Therefore; In order to comply with the provisions of Ley N° 10086 and Decreto 43879-MINAE, the Temporary Regulation for the attention of Distributed Energy Resources for self-consumption at CNFL is established.

This regulation establishes the requirements, procedures and other necessary details for the operability and interconnection of Distributed Energy Resources, hereinafter DER, for self-consumption at the Compañía Nacional de Fuerza y Luz S.A., hereinafter CNFL, while the ARESEP publishes the corresponding instruments.

As the ARESEP publishes regulatory instruments, this regulation will be adjusted, in order to adapt without hindering the development of distributed energy resources and guaranteeing compliance with the regulations in force at any given time.

As of the moment of publication of the regulatory instruments applicable to DER by the ARESEP or the Operador del Sistema Eléctrico Nacional (OS), the owners will have a period of 3 months for their compliance, or the period indicated in said regulatory instruments, including the signing of a new interconnection contract or addendum to the existing one, as established by the ARESEP.

1

To complement the provisions of Ley N° 10086, Decreto 43879-MINAE and the regulatory instruments issued by the ARESEP, as well as to regulate the aspects not standardized therein, in order to integrate the DER for self-consumption that interact with the CNFL distribution system until the ARESEP establishes the procedures, methodologies, requirements and regulatory instruments for the implementation and compliance with Law 10086.

2

This regulation applies to customers (personas abonadas), whether individuals or legal entities, who wish to install distributed energy resources for self-consumption connected to the CNFL distribution system in the operating modes with and without delivery of excess energy (excedentes) to the network. Once the ARESEP establishes the requirements for operating systems with and without delivery of excess energy (excedentes) to the network, the PDER must adapt to said regulation.

3

For the purposes of this regulation, the following abbreviations shall apply:

ARESEP Autoridad Reguladora de los Servicios Públicos CNFL Compañía Nacional de Fuerza y Luz S. A.

CFIA Colegio Federado de Ingenieros y Arquitectos DER Distributed Energy Resources GD Distributed Generation (Generación Distribuida) IVA Value Added Tax (Impuesto al Valor Agregado) kVA Unit of measurement of apparent power, kilo volt ampere LASIMEE Laboratorio de Sistemas de Medición de Energía Eléctrica de la CNFL MINAE Ministerio de Ambiente y Energía MW Unit of measurement of real power, mega watt OS Operador del Sistema Eléctrico Nacional PDER Individual or legal entity owning a DER SAE Energy Storage System (Sistema de Almacenamiento de Energía) SCADA Supervisión, Control y Adquisición de Datos SEN Sistema Eléctrico Nacional UL Underwriters Laboratories

4

For the application of this regulation, the terms mentioned shall have the following meaning:

. Self-consumption (Autoconsumo): use of the energy generated by the PDER to supply their own demand at the same site where it is produced.

. Penetration capacity (Capacidad de penetración): maximum capacity of each electrical circuit of the SEN to be able to accept distributed energy resources without these affecting its operation, in accordance with the applicable regulations issued by the ARESEP for this purpose.

. Interconnection contract (Contrato de interconexión): the accessory legal instrument signed between CNFL and the PDER that establishes the general and specific conditions under which a DER will interact with the distribution network and its impact on the SEN at the common interconnection point (punto de interconexión común), the commercial and regulatory conditions of access. The termination of the interconnection contract or its breach does not affect the validity and effectiveness of the electricity supply contract.

. Principal contract or electricity supply contract (Contrato principal o contrato de suministro de energía): the principal contract signed between CNFL and the customer (persona abonada) for the supply of electricity, in which the conditions, technical and commercial requirements under which the electric service will be provided are established, as well as the obligations, rights, duties and sanctions to which the parties commit, in strict adherence to the current regulations and laws.

. Excess energy (Excedentes): electrical energy generated from renewable energy sources and injected into the electrical distribution network, once the distributed generator has satisfied their own demand.

. Distributed generation for self-consumption (Generación distribuida para autoconsumo): set of technologies or equipment necessary for the generation of electrical energy from renewable energy sources used by the distributed generator.

. Distributed generator (Generador distribuido): individual or legal entity that owns and operates a small-scale distributed generation system for self-consumption, from renewable energy sources, in the operating mode with delivery of excess energy (excedentes) to the network and operating mode without delivery of excess energy (excedentes) to the network . Operation with delivery of excess energy (excedentes) to the network (Operación con entrega de excedentes a la red): mode of distributed generation for self-consumption, in which the distributed generation system is interconnected with the SEN, so that it can allow the injection of excess energy (excedentes) into the distribution network.

. Operation without delivery of excess energy (excedentes) to the network (Operación sin entrega de excedentes a la red): mode of distributed generation for self-consumption, in which the distributed generation systems have technological mechanisms to manage the excess energy (excedentes) at the generation point and make the delivery of excess energy (excedentes) impossible while operating in parallel with the SEN.

. Operator of the National Electric System (Operador del Sistema Eléctrico Nacional, OS): technical unit that has the responsibility of planning, directing and coordinating the operation of the national electric system and the national electric market to satisfy the country's electrical demand, as well as the coordination and execution of energy transfer at the regional level, according to what is stipulated in national and regional regulations.

. Customer (Persona abonada): individual or legal entity that has signed one or more contracts for the use of electrical energy.

. Distributed Energy Resources (DER): are generation and storage technologies connected directly to the distribution network, capable of exporting active electrical power. For the purposes of this regulation, DER are understood as: (a) distributed generation systems for self-consumption and (b) energy storage systems . National Electric System (Sistema Eléctrico Nacional, SEN): the power system composed of the following interconnected elements: generation plants, the transmission network, the distribution networks, storage systems and the electrical loads of users.

5

Distributed generation systems for self-consumption with a power greater than 500 kVA must process the environmental viability (viabilidad ambiental) before the Secretaría Técnica Nacional Ambiental (SETENA).

6

It shall be the responsibility of the customer (persona abonada), through a professional duly registered and authorized by the CFIA to assume responsibility according to the type of works, to size the DER according to their historical consumption. For new consumption or properties that do not have a consumption history, the person responsible for the design must develop the detailed calculation report (memoria de cálculo) to determine the capacity of the self-consumption systems to be installed.

7

The maximum capacity of a distributed generation system for self-consumption allowed is 5000 kilowatts (5 MW).

8

Additionally, the CNFL will develop a detailed study of the impact on the distribution system to establish the technical conditions that the distributed generator must meet to guarantee reliable and safe integration to the distribution system and safeguard the efficiency, reliability, continuity and security of the electric service. The study must be paid for by the interested party and varies depending on the conditions of the project and the circuit, so they must request a quote from CNFL. In said quote, in addition to the cost, the time required for its execution will be indicated.

9

For the registration of the energy generated by the PDER and the application of the corresponding tariffs, a generation meter must be installed, which must comply with the current AR-RT-SUINAC regulation of ARESEP. The generation meter may be sold to the interested party by CNFL and must be paid for along with the interconnection cost, prior to the signing of the interconnection contract. In the event that the interested party provides their own metering system, it must comply with the ARESEP standard AR-NT-SUMEL and have a calibration certificate issued by an Accredited and current Laboratory, a document that must be endorsed by the Laboratorio de Sistemas de Medición de Energía Eléctrica (LASIMEE) of CNFL and delivered by the manufacturer or supplier of the meter to LASIMEE, located in La Uruca, next to Capris.

10

As established in the Procedure for DER penetration capacity (capacidad de penetración) per distribution circuit that are integrated with the distribution networks of the SEN, established by the ARESEP, while the penetration studies are being developed, CNFL will use as a maximum capacity criterion not to exceed fifteen percent (15%) of the maximum demand of the circuit. Maximum demand is considered as that measured at the output of the substation to which the circuit is connected under normal operating conditions of the same; the power associated with backup circuits is not considered. This does not apply to cases without delivery of excess energy (excedentes).

Responsibilities

CHAPTER II

11
  • a)To manage distributed energy resources for self-consumption in compliance with Ley 10086, its regulation and the regulatory instruments established by the ARESEP, establishing the additional conditions that are required until they are established by the ARESEP or the OS, ensuring the safeguarding of the efficiency, reliability, continuity and security of the electric service and the greater public interest.
  • b)To comply with the deadlines established in this regulation for the different stages.
  • c)To implement on the CNFL website a space showing:

1. The procedures, requirements, technical conditions, tariffs and any other requirement necessary to address the activity.

2. Maximum demand, power of interconnected distributed energy resources and DER penetration capacity (capacidad de penetración) per circuit.

3. The service channels for the PDER for queries or complaints.

  • d)To carry out the interconnection of the generation systems to the electrical network, this prior to the fulfillment of the requirements established in this regulation.
  • e)To attend to the queries or claims presented by customers (personas abonadas) with DER.

CNFL is exempted from all responsibility for the differences that may arise between the Company's customers (abonados) and the owners of the properties where the DER equipment is located or any third party related to the system.

12
  • a)To comply with what is established in Ley 10086, its regulation Decreto 43879-MINAE, the regulatory instruments established by the ARESEP, this regulation and the interconnection contract signed with CNFL.
  • b)Prior to installing the distributed generation system for self-consumption, they must obtain authorization from CNFL (approval of the interconnection application and engineering studies and initial inspection).
  • c)To submit the complete information in each of the stages necessary for the interconnection of the DER.
  • d)To allow and facilitate the access of CNFL personnel to the area where the distributed generation system is located.
  • e)To attend to the queries and recommendations that CNFL makes to them in compliance with this regulation and the technical standards.

Procedure and Requirements

CHAPTER III

13

For the interconnection of distributed generation systems for self-consumption with delivery of excess energy (excedentes), the following stages must be completed:

1. Interconnection application and engineering studies and initial inspection 2. Final inspection and commissioning (puesta en marcha) 3. Reinspection (in case the inspection results in a rejection) 4. Signing of the interconnection contract 5. Installation of the generation meter and interconnection

14

For the interconnection of distributed resources (generation with or without storage) for self-consumption without delivery of excess energy (excedentes), the following stages must be completed:

1. Interconnection application and engineering studies and initial inspection 2. Final inspection and commissioning (puesta en marcha) 3. Reinspection (in case the inspection results in a rejection) 4. Submission of the sworn statement (declaración jurada).

5. Installation of the generation meter and interconnection

15

Additionally, the service must not have totalized metering (medición totalizada).

16

The interested party must submit, at the respective CNFL Branches or through the Virtual Agency, the application for power availability in the circuit or interconnection application and engineering studies and initial inspection, by presenting the following requirements:

  • a)Form F-087 Interconnection application and engineering studies and initial inspection available on the CNFL Web page.
  • b)Calculation report (Memoria de cálculo) that must contain: general description of the project, energy source to be used and particular considerations, for example: historical records of solar radiation, water flows, volumes and type of solid waste, average wind speed or power (historical data must be taken from competent entities), calculation of the power to be installed (for all purposes, the nominal capacity of the system shall be the power of the generating element and in the case of photovoltaic systems it shall be the peak power of the panels), average monthly and annual generation power and expected savings. The power to be installed must be calculated according to the average consumption of at least six months and the total energy generated may not exceed 100% of consumption. In the case of services with less than 6 months in definitive condition, a detailed calculation report (memoria de cálculo) of the monthly and annual consumption of the property must be presented. The proposed distributed generation system for self-consumption must have the same electrical characteristics (number of phases, voltages and frequency) as the electric service of the interested party.
  • c)Payment receipt for the interconnection application and engineering studies and initial inspection (CNFL carries out the two stages in a single step) according to the current tariffs established by ARESEP.
  • d)Administrative documents: if the owner of the electric service is an individual, provide a copy of their identity card. In the event that the electric service is owned by a legal entity, provide the current legal certificate (personería jurídica) issued no more than thirty calendar days ago and the copy of the identity card of the corresponding person or persons, as indicated in the representation of the legal certificate (personería jurídica).
  • e)In the event that the procedures are carried out by a third party, present an authorization. Only those who are authorized may carry out formalities on behalf of the person who owns the service.
  • f)Technical specifications: the technical data sheets of the equipment to be used must be provided (solar panels and inverters in the case of a photovoltaic system, generator for the case of other systems, and batteries if used).
  • g)Certificate of compliance with the IEEE 1547 standard for the generation system to be installed. For the case of photovoltaic systems, the certificates demonstrating compliance with the specific UL 1741 standard for the inverter or inverters to be used must be provided.

If there is availability in the circuit, the interested party will have three months counted from the notification date to finalize or implement the distributed resources project and request the final inspection and commissioning (puesta en marcha). If, in order to interconnect the GD project, network adaptation is required, the interested party must cover the corresponding costs.

All information submitted is the responsibility of the interested party who owns the service and of the professional engineer in charge of the work, which the electric company will use to verify the eventual interconnection of the project. Any data that is changed or that induces error may be grounds for rejection of the application. The information indicated in this article must be submitted completely. Any missing information may result in the rejection of the interconnection application and engineering studies and initial inspection due to incomplete information.

CNFL will determine the approval or rejection of the application within a period not exceeding 15 business days. In the event that it is approved, the interested party may proceed with the installation of the distributed energy resources system for self-consumption.

17

The interconnection application and engineering studies and initial inspection may imply the need to generate a design for an additional electrical network to adapt the network to the project, or the communication interconnection between the project and CNFL, mainly due to the magnitude of the installed power, as indicated below:

  • a)For systems greater than 250 kVA, a communication interconnection between the distributed generation system and the CNFL SCADA is required. This connection must be for both the protection of the generation system and the signal manager of the inverters (Data Manager). To do this, the requirements must be requested (protocols, communication medium, electrical variables, among others).
  • b)For systems with a nominal capacity greater than the nameplate capacity of the transformer, the interested party must process an electrical network design for the replacement of the transformer with one of equal or greater capacity than the distributed generation system for self-consumption to be installed. This applies to CNFL transformers. In the event that the transformer is private, it is the responsibility of the engineer in charge of the work.
  • c)If the service is fed with a three-phase system formed by a bank of two transformers, an electrical network design must be processed to complete the bank of transformers.

Said design, materials and execution of the works are at the expense of the interested party and must comply with CNFL requirements for the design and execution of works on the distribution system. The execution of these works must be within the validity period of the interconnection application and engineering studies and initial inspection.

18

They must submit a written note, 10 business days prior to the expiration date, indicating the reasons and the new date of entry into operation. CNFL must respond whether it grants the requested extension within a maximum period of 10 business days.

19

Once the construction of the distributed energy resources system is finished and within the validity period of the interconnection application and engineering studies and initial inspection, the interested party must request the inspection and commissioning (puesta en marcha) from CNFL. CNFL will review the system to verify that it meets the technical standards for parallel operation with the electrical distribution system. For this, it must be considered that:

  • a)Prior to the inspection, the interested party must pay the amount established by ARESEP for the final inspection and commissioning (puesta en marcha) stage.
  • b)In the event that the inspection results in a rejection, the corresponding corrections must be made and a reinspection must be processed, for which the interested party must pay the amount established by ARESEP.
  • c)Both the required adjustments and the reinspection must be carried out within the validity period of the interconnection application and engineering studies and initial inspection.
  • d)In the event that any modification is required to the distribution network or communication interconnection of the generation system with CNFL, prior to requesting the inspection and commissioning (puesta en marcha), the PDER must comply with those requirements.
  • e)Once the documents with the respective technical information have been verified and the project inspection has been carried out, if no technical issues or changes in the capacity or characteristics of the equipment are found, the interconnection of the distributed energy resources will be approved.
  • f)If there are changes in the specifications or models of the equipment or a variation in the capacity of the project, with respect to what was approved in the interconnection application and engineering studies and initial inspection, the application will be rejected and a new interconnection application and engineering studies and initial inspection must be submitted.
  • g)CNFL will have a period of 15 business days to carry out the verification of the requirements and the inspection.
20

Once the inspection is approved, the respective Branch will proceed with the notification (by official letter) of the result within a period not exceeding 5 business days after the execution of the inspection. The signing of the interconnection contract will be convened, which can be done physically at the respective Branch or by means of digital signature. In both cases, the following must be complied with:

  • a)Present the identity card or current legal certificate (personería jurídica) (issued no more than thirty calendar days ago), as applicable.
  • b)In the event that the signing of the contract is carried out by a third party, a notarized special power of attorney must be presented.
  • c)Present the CFIA form (boleta) of the responsible professional.
  • d)The signing of the interconnection contract must be carried out at least 10 days before the meter reading date, the day on which the metering systems must be installed.

If this is a case with no surplus delivery to the grid, after the notification of inspection approval, the sworn declaration of zero injection must be submitted (in the medium and format established by CNFL) and the signing of an interconnection contract is not required. The sworn declaration must be submitted at least 10 days before the meter reading date, the day on which the metering systems must be installed.

Contract and Contract Modifications

CHAPTER IV

21

Once the inspection has been approved, the signing of the interconnection contract will proceed, and the commissioning of the interconnection will be scheduled. The technical study that CNFL approved will be an integral part of the contract.

22

The interconnection contract is accessory in nature to the electricity supply contract that exists between the service owner and CNFL; therefore, the termination of the interconnection contract or its breach does not affect the validity and effectiveness of the principal contract.

23

The interconnection contract that is signed will be valid until ARESEP establishes the procedures, methodologies, requirements, and regulatory instruments indicated in Law No. 10086. The PDER must comply with the deadline set by ARESEP for its DERs to meet what the corresponding regulatory instrument establishes and proceed with signing a new contract. If ARESEP does not specify the deadline, it will be 3 months from the entry into force.

Penalties

CHAPTER V

24

CNFL may reject, suspend, interrupt, or disconnect the DER for the reasons set forth in Article 27 of Decree 43879-MINAE and for non-compliance with this regulation.

Effectiveness

CHAPTER VI

25

This regulation will take effect upon its publication in the Official Gazette La Gaceta.

Artículos

en la totalidad del texto - Texto Completo Norma 0 Reglamento temporal para la atención de los recursos energéticos distribuidos para autoconsumo en la CNFL COMPAÑÍA NACIONAL DE FUERZA Y LUZ S. A (Esta norma fue derogada por el artículo 25 del Reglamento para la atención de los recursos energéticos distribuidos (DER) para autoconsumo en la CNFL, publicado en La Gaceta N° 38 del 26 de febrero del 2025) GERENCIA GENERAL DIRECCIÓN DISTRIBUCIÓN DE LA ENERGÍA DIRECCIÓN COMERCIALIZACIÓN REGLAMENTO TEMPORAL PARA LA ATENCIÓN DE LOS RECURSOS ENERGÉTICOS DISTRIBUIDOS PARA AUTOCONSUMO EN LA CNFL 04/10/2023

  1. 1Que el 7 de enero del 2022 se publicó en el Diario Oficial La Gaceta la Ley N° 10086 Promoción y regulación de recursos energéticos distribuidos a partir de fuentes renovables.
  2. 2Que el 1 de febrero del 2023 se publicó en el diario oficial La Gaceta el Decreto Ejecutivo 43879MINAE Reglamento a la Ley de promoción y regulación de recursos energéticos distribuidos a partir de fuentes renovables, N° 10086 del siete de enero del 2022.
  3. 3Que el Decreto 43879-MINAE en su artículo 29 establece que:

Se deroga en su totalidad el Decreto Ejecutivo N° 39220-MINAE, denominado "Reglamento Generación distribuida para autoconsumo con fuentes renovables modelo de contratación neta sencilla" del 14 de setiembre de 2015, publicado en La Gaceta N° 196 del 08 de octubre del 2015.

  1. 4Que la Ley N° 10086 establece como objetivo:

La presente ley tiene como objetivo establecer las condiciones necesarias para promover y regular, bajo un régimen especial de integración eficiente, segura y sostenible, las actividades relacionadas con el acceso, la instalación, la conexión, la interacción y el control de recursos energéticos distribuidos basados en fuentes de energía renovables.

  1. 5Que la Ley N° 10086 establece en su artículo 9 la declaratoria de interés público:

Se declara de interés público la investigación y el fomento de los recursos energéticos distribuidos, las energías de fuentes renovables y los sistemas de almacenamiento de energía que resulten de beneficio para la integralidad del SEN y la mejor satisfacción del interés público.

  1. 6Que la Ley N° 10086 establece en su artículo 6 la responsabilidad de la Autoridad Reguladora de los Servicios Públicos (ARESEP) de establecer las tarifas, procedimientos, metodologías, requisitos e instrumentos regulatorios para la implementación y cumplimiento de la ley 10086.
  2. 7Que a la fecha de publicación del Decreto 43879-MINAE no se cuenta con las tarifas, procedimientos, metodologías, requisitos e instrumentos regulatorios para la implementación y cumplimiento de la Ley N° 10086.
  3. 8Que la Ley N° 6227 Ley General de la Administración Pública establece en sus artículos 11, 12, 15 y 16 que:

CAPÍTULO I

Disposiciones generales

Considerando:

11

1. La Administración Pública actuará sometida al ordenamiento jurídico y sólo podrá realizar aquellos actos o prestar aquellos servicios públicos que autorice dicho ordenamiento, según la escala jerárquica de sus fuentes.

2. Se considerará autorizado el acto regulado sea en forma imprecisa.

12

1. Se considerará autorizado un servicio público cuando se haya indicado el sujeto y el fin del mismo. En este caso el ente encargado podrá prestarlo de acuerdo con sus propios reglamentos sobre los demás aspectos de la actividad, bajo el imperio del Derecho.

15

1. La discrecionalidad podrá darse incluso por ausencia de ley en el caso concreto, pero estará sometida en todo caso a los límites que le impone el ordenamiento expresa o implícitamente, para lograr que su ejercicio sea eficiente y razonable.

16

1. En ningún caso podrán dictarse actos contrarios a reglas unívocas de la ciencia o de la técnica, o a principios elementales de justicia, lógica o conveniencia.

Otorgando la potestad que la ley le da al administrador, para regularse con el fin de poder cumplir con los actos en consecución de un fin público ordenado por la ley.

  1. 9Que según resolución RE-0076-JD-2023 Metodología tarifaria derivada de la ley N° 10086 referente a: a) Fijación de los cargos de interconexión a las redes de distribución aplicable a los recursos energéticos distribuidos, b) Tarifa de acceso a las redes de distribución por parte del generador distribuido, c) Compra-venta de excedentes y reconocimiento económico entre empresas distribuidoras, así como por parte de los generadores distribuidos a la empresa distribuidora, d) Reconocimiento de los costos, rentabilidad, inversiones y canon en que incurren las empresas distribuidoras para la integración de recursos energéticos distribuidos al SEN (tarifa T-DER), a los casos sin entrega de excedentes a la red se les debe aplicar las etapas 1 ,2 y 4 (Etapa 1: Solicitud de interconexión (variable CSInt+1,e)), (Etapa 2: Estudios de ingeniería e inspección inicial (variable CEIt+1,e)) y (Etapa 4: Reinspección en caso de la etapa 3 resulte infructuosa- (variable CRIt+1,e)).

10.-Que el 14 de setiembre de 2023 se publicó en el alcance N° 174 a La Gaceta N° 169 las resoluciones RE-0103- IE-2023, RE-0104-IE-2023, RE-0105-IE-2023 y RE-0106- IE-2023 de la ARESEP, referentes a la fijación de las tarifas para recursos energéticos distribuidos, según la ley N° 10086.

11.-Que el 14 de setiembre de 2023 se publicó en el alcance N° 174 a La Gaceta N° 169 la resolución RE0095- JD-2023 de la ARESEP, correspondiente al Procedimiento de capacidad de penetración de DER por circuito de distribución que se integran con las redes de distribución del SEN. Por tanto; Con el fin de dar cumplimiento a lo establecido en la Ley N° 10086 y el Decreto 43879-MINAE se establece el Reglamento temporal para la atención de los Recursos Energéticos Distribuidos para autoconsumo en la CNFL.

Este reglamento establece los requisitos, procedimientos y demás detalles necesarios para la operatividad e interconexión de los Recursos Energéticos Distribuidos, en adelante DER, para autoconsumo en la Compañía Nacional de Fuerza y Luz S.A., en adelante CNFL, mientras la ARESEP publica lo correspondiente.

Conforme la ARESEP publique instrumentos regulatorios, este reglamento se ajustará, con el fin de adaptarse sin obstaculizar el desarrollo de los recursos energéticos distribuidos y garantizando el cumplimiento de la normativa vigente en cada momento.

A partir del momento de publicación de los instrumentos regulatorios aplicables a los DER por parte de la ARESEP o el Operador del Sistema Eléctrico Nacional (OS), las personas propietarias tendrán un plazo de 3 meses para su cumplimiento o bien el plazo que se indique en dichos instrumentos regulatorios, incluyendo la firma de un nuevo contrato de interconexión o adenda al ya existente, según lo que establezca la ARESEP.

1

Complementar lo dispuesto en la Ley N° 10086, el decreto 43879-MINAE y los instrumentos regulatorios emitidos por la ARESEP, así como regular los aspectos no normados en éstas, con el fin de integrar los DER para autoconsumo que interactúen con el sistema de distribución de la CNFL hasta que la ARESEP establezca los procedimientos, metodologías, requisitos e instrumentos regulatorios para la implementación y cumplimiento de la ley 10086.

2

Este reglamento aplica a las personas abonadas, sean físicas o jurídicas, que deseen instalar recursos energéticos distribuidos para autoconsumo conectadas al sistema de distribución de la CNFL en las modalidades de operación con y sin entrega de excedentes a la red. Una vez que la ARESEP establezca los requerimientos para los sistemas de operación con y sin entrega de excedentes a la red, los PDER deben adaptarse a dicha regulación.

3

Para los efectos del presente reglamento se tendrán las siguientes abreviaturas:

ARESEP Autoridad Reguladora de los Servicios Públicos CNFL Compañía Nacional de Fuerza y Luz S. A.

CFIA Colegio Federado de Ingenieros y Arquitectos DER Recursos Energéticos Distribuidos por sus siglas en inglés GD Generación Distribuida IVA Impuesto al Valor Agregado kVA Unidad de medida de potencia aparente, kilo volt ampere LASIMEE Laboratorio de Sistemas de Medición de Energía Eléctrica de la CNFL MINAE Ministerio de Ambiente y Energía MW Unidad de medida de potencia real, mega watt OS Operador del Sistema Eléctrico Nacional PDER Persona física o jurídica propietaria de un DER SAE Sistema de Almacenamiento de Energía SCADA Supervisión, Control y Adquisición de Datos SEN Sistema Eléctrico Nacional UL Underwriters Laboratories

4

Para la aplicación del presente reglamento los términos que se mencionan tendrán el siguiente significado:

. Autoconsumo: aprovechamiento de la energía generada por parte del PDER para abastecer su propia demanda en el mismo sitio donde la produce.

. Capacidad de penetración: capacidad máxima de cada circuito eléctrico del SEN para poder aceptar recursos energéticos distribuidos sin que estos afecten su operación, de conformidad con la normativa vigente aplicable que emita la ARESEP al efecto.

. Contrato de interconexión: es el instrumento legal accesorio suscrito entre la CNFL y el PDER que establece las condiciones generales y especificas bajo las cuales interactuará un DER con la red de distribución y su afectación al SEN en el punto de interconexión común, las condiciones comerciales y regulatorias de acceso. La finalización de contrato de interconexión o su incumplimiento no afecta la validez y vigencia del contrato de suministro eléctrico.

. Contrato principal o contrato de suministro de energía: es el contrato principal suscrito entre la CNFL y la persona abonada para el suministro de electricidad, en el que se establecen las condiciones, requisitos técnicos y comerciales bajo los cuales se brindará el servicio eléctrico, así como las obligaciones, derechos, deberes y sanciones a que se comprometen las partes, en estricto apego a la normativa y leyes vigentes.

. Excedentes: energía eléctrica generada a partir de fuentes de energía renovables e inyectada a la red eléctrica de distribución, una vez que el generador distribuido ha satisfecho su propia demanda.

. Generación distribuida para autoconsumo: conjunto de tecnologías o equipos necesarios para la generación de energía eléctrica a partir de fuentes de energía renovable utilizados por el generador distribuido.

. Generador distribuido: persona física o jurídica que posea y opere un sistema de generación distribuida para autoconsumo a pequeña escala, a partir de fuentes de energía renovables, en la modalidad de operación con entrega de excedentes a la red y operación sin entrega de excedentes a la red . Operación con entrega de excedentes a la red: modalidad de generación distribuida para autoconsumo, en la cual el sistema de generación distribuida está interconectado con el SEN, de manera que puede permitir la inyección de excedentes en la red de distribución.

. Operación sin entrega de excedentes a la red: modalidad de generación distribuida para autoconsumo, en la cual los sistemas de generación distribuida disponen de mecanismos tecnológicos para gestionar los excedentes en el punto de generación e imposibilitan la entrega de excedentes mientras opera en paralelo con el SEN.

. Operador del Sistema Eléctrico Nacional (OS): unidad técnica que tiene la responsabilidad de planificar, dirigir y coordinar la operación del sistema eléctrico nacional y del mercado eléctrico nacional para satisfacer la demanda eléctrica del país, así como la coordinación y ejecución del trasiego de energía a nivel regional, según lo dispuesto en la regulación nacional y regional.

. Persona abonada: persona física o jurídica que ha suscrito uno o más contratos para el aprovechamiento de la energía eléctrica.

. Recursos energéticos distribuidos (DER): son tecnologías de generación y almacenamiento conectadas directamente a la red de distribución, capaces de exportar potencia eléctrica activa. A los efectos del presente reglamento se entienden como DER: (a) los sistemas de generación distribuida para autoconsumo y (b) los sistemas de almacenamiento de energía . Sistema Eléctrico Nacional (SEN): es el sistema de potencia compuesto por los siguientes elementos conectados entre sí: las plantas de generación, la red de transmisión, las redes de distribución, los sistemas de almacenamiento y las cargas eléctricas de los usuarios.

5

Los sistemas de generación distribuida para autoconsumo con potencia mayor a 500 kVA deberán gestionar la viabilidad ambiental ante la Secretaría Técnica Nacional Ambiental (SETENA).

6

Será responsabilidad de la persona abonada, por medio de una persona profesional debidamente incorporada y autorizada por el CFIA para asumir la responsabilidad según el tipo de obras, para dimensionar el DER de acuerdo con su consumo histórico. Para nuevos consumos o inmuebles que no posean historial de consumo, la persona responsable del diseño deberá desarrollar la memoria de cálculo detallada para determinar la capacidad de los sistemas para autoconsumo a instalar.

7

La máxima capacidad de sistema de generación distribuida para autoconsumo permitida es 5000 kilowatts (5 MW).

8

Adicionalmente, la CNFL desarrollará un estudio detallado del impacto en el sistema de distribución para establecer las condiciones técnicas que debe cumplir el generador distribuido para garantizar la integración confiable y segura al sistema de distribución y salvaguardar la eficiencia, confiabilidad, continuidad y seguridad del servicio eléctrico. El estudio debe ser costeado por la persona interesada y varía en función de las condiciones del proyecto y el circuito, por lo que deberá solicitar una cotización a la CNFL. En dicha cotización se indicará además del costo, el plazo requerido para su ejecución.

9

Para el registro de la energía generada por el PDER y la aplicación de las tarifas que correspondan, se deberá instalar un medidor de generación el cual deberá cumplir con el reglamento AR-RT-SUINAC de ARESEP vigente. El medidor de generación podrá ser vendido a la persona interesada, por parte de la CNFL y deberá ser cancelado junto con el costo de interconexión, previo a la suscripción del contrato de interconexión. En caso de que la persona interesada aporte su propio sistema de medición, el mismo deberá cumplir con la norma de ARESEP AR-NT-SUMEL y contar con un certificado de calibración emitido por un Laboratorio Acreditado y vigente, documento que deberá ser avalado por el Laboratorio de Sistemas de Medición de Energía Eléctrica (LASIMEE) de la CNFL y ser entregado por parte del fabricante o proveedor del medidor a LASIMEE, ubicado en La Uruca, contiguo a Capris.

10

Según se establece en el Procedimiento de capacidad de penetración de DER por circuito de distribución que se integran con las redes de distribución del SEN, establecido por la ARESEP, mientras se desarrollan los estudios de penetración, la CNFL utilizará como criterio de capacidad máxima, no exceder el quince por ciento (15%) de la demanda máxima del circuito. Se considera demanda máxima, como aquella medida a la salida de la subestación a la cual está conectado el circuito bajo condiciones de operación normal del mismo, no se considera la potencia asociada a los circuitos de respaldo. Esto no aplica para casos sin entrega de excedentes.

Responsabilidades

CAPÍTULO II

11
  • a)Gestionar los recursos energéticos distribuidos para autoconsumo en acatamiento a la Ley 10086, su reglamento y los instrumentos regulatorios establecidos por la ARESEP, estableciendo las condiciones adicionales que sean requeridas hasta que sean establecidas por la ARESEP o el OS, velando por salvaguardar la eficiencia, confiabilidad, continuidad y seguridad del servicio eléctrico y el mayor interés público.
  • b)Cumplir con los plazos establecidos en este reglamento para las diferentes etapas.
  • c)Implementar en el sitio web de la CNFL un espacio donde se muestre:

1. Los procedimientos, requisitos, condiciones técnicas, tarifas y cualquier otro requerimiento necesario para atender la actividad.

2. Demanda máxima, potencia de recursos energéticos distribuidos interconectados y capacidad de penetración de DER por circuito.

3. Los canales de atención al PDER para consultas o quejas.

  • d)Realizar la interconexión de los sistemas de generación a la red eléctrica, esto previo al cumplimiento de los requisitos establecidos en este reglamento.
  • e)Atender las consultas o reclamaciones que presenten las personas abonadas con DER.

Se exime de toda responsabilidad a la CNFL por las diferencias que pudieren surgir entre los abonados de la Empresa y los propietarios de los inmuebles donde se ubiquen los equipos de los DER o cualquier tercero relacionado con el sistema.

12
  • a)Cumplir con lo establecido en la Ley 10086, su reglamento Decreto 43879-MINAE, los instrumentos regulatorios establecidos por la ARESEP, este reglamento y el contrato de interconexión suscrito con la CNFL.
  • b)Previo a instalar el sistema de generación distribuida para autoconsumo deberá obtener la autorización por parte de la CNFL (aprobación de la solicitud de interconexión y estudios de ingeniería e inspección inicial).
  • c)Presentar la información completa en cada una de las etapas necesarias para la interconexión del DER.
  • d)Permitir y facilitar el acceso del personal de la CNFL al área donde se ubique el sistema de generación distribuida.
  • e)Atender las consultas y recomendaciones que la CNFL le realice en cumplimiento con este reglamento y las normas técnicas.

Procedimiento y requisitos

CAPÍTULO III

13

Para la interconexión de sistemas de generación distribuida para autoconsumo con entrega de excedentes se deberá cumplir las siguientes etapas:

1. Solicitud de interconexión y estudios de ingeniería e inspección inicial 2. Inspección final y puesta en marcha 3. Reinspección (en caso de que la inspección resulte en un rechazo) 4. Firma del contrato de interconexión 5. Instalación del medidor de generación e interconexión

14

Para la interconexión de recursos distribuidos (generación con o sin almacenamiento) para autoconsumo sin entrega de excedentes se deberá cumplir las siguientes etapas:

1. Solicitud de interconexión y estudios de ingeniería e inspección inicial 2. Inspección final y puesta en marcha 3. Reinspección (en caso de que la inspección resulte en un rechazo) 4. Presentación de la declaración jurada.

5. Instalación del medidor de generación e interconexión

15

Además, el servicio no debe contar con medición totalizada.

16

La persona interesada debe presentar en las Sucursales de la CNFL respectiva o mediante la Agencia Virtual, la solicitud de disponibilidad de potencia en el circuito o solicitud de interconexión y estudios de ingeniería e inspección inicial, mediante la presentación de los siguientes requisitos:

  • a)Formulario F-087 Solicitud de interconexión y estudios de ingeniería e inspección inicial disponible en la página Web de la CNFL.
  • b)Memoria de cálculo que debe contener: descripción general del proyecto, fuente de energía a usar y consideraciones particulares, por ejemplo: registros históricos de radiación solar, caudales de agua, volúmenes y tipo de desechos sólidos, velocidad o potencia media del viento (los datos históricos deben ser tomados de entes competentes), cálculo de la potencia a instalar (para todos los efectos, la capacidad nominal del sistema será la potencia del elemento generador y en el caso de sistemas fotovoltaicos será la potencia pico de los paneles), potencia promedio de generación mensual y anualmente y ahorros esperados. La potencia por instalar debe calcularse según el promedio de consumos de al menos seis meses y la energía total generada no podrá superar el 100% del consumo. En caso de servicios con menos de 6 meses en condición definitiva, se deberá presentar una memoria de cálculo detallada del consumo mensual y anual del inmueble. El sistema de generación distribuida para autoconsumo propuesto debe tener las mismas características eléctricas (cantidad de fases, tensiones y frecuencia) del servicio eléctrico de la persona interesada.
  • c)Recibo de pago por la solicitud interconexión y estudios de ingeniería e inspección inicial (la CNFL realiza las dos etapas en un solo paso) según las tarifas vigentes establecidas por ARESEP.
  • d)Documentos administrativos: si el propietario del servicio eléctrico es una persona física, aportar copia de cédula de identidad. En caso de que el servicio eléctrico sea propiedad de una persona jurídica, aportar la personería jurídica vigente con no más de treinta días naturales de emitida y la copia de la cédula de identidad de la persona o personas que corresponda, según lo indicado en la representación de la personería jurídica.
  • e)En caso de que los trámites los realice un tercero, presentar una autorización. Únicamente podrán hacer gestiones a nombre de la persona propietaria del servicio, quienes estén autorizados.
  • f)Especificaciones técnicas: se debe aportar fichas técnicas de los equipos a utilizar (paneles solares e inversores en el caso de sistema fotovoltaico, generador para el caso del resto de sistemas y baterías si se utilizan).
  • g)Certificado del cumplimiento del estándar IEEE 1547 para el sistema de generación a instalar. Para el caso de sistemas fotovoltaicos, se debe aportar los certificados que demuestren el cumplimiento de la norma UL 1741 específica del inversor o inversores a utilizar.

De haber disponibilidad en el circuito, la persona interesada tendrá tres meses contados a partir de la fecha de notificación, para concretar o implementar el proyecto de recursos distribuidos y solicitar la inspección final y puesta en marcha. Si para interconectar el proyecto de GD se requiere adecuación de la red, el interesado o la interesada deberá cubrir los costos que correspondan.

Toda información que se presente es responsabilidad de la persona interesada propietaria del servicio y de la persona profesional en ingeniería a cargo de la obra, la cual la empresa eléctrica utilizará para verificar la eventual interconexión del proyecto. Cualquier dato que se varíe o que induzca a error podrá ser causal del rechazo de la solicitud. La información indicada en este artículo deberá ser presentada de manera completa. Cualquier faltante puede generar el rechazo de la solicitud de interconexión y estudios de ingeniería e inspección inicial por información incompleta.

La CNFL determinará la aprobación o rechazo de la solicitud en un plazo no mayor a 15 días hábiles. En caso de que sea aprobada, la persona interesada podrá proceder con la instalación del sistema de recursos energéticos distribuidos para autoconsumo.

17

La solicitud de interconexión y estudios de ingeniería e inspección inicial puede implicar que se requiera generar un diseño de red eléctrica adicional para adecuar la red al proyecto, o bien la interconexión de comunicación entre el proyecto y la CNFL, principalmente por la magnitud de la potencia instalada, según se indica a continuación:

  • a)Para sistemas mayores a 250 kVA se requiere una interconexión de comunicación entre el sistema de generación distribuida y el SCADA de la CNFL. Esta conexión debe ser tanto de la protección del sistema de generación como del gestor de señales de los inversores (Data Manager). Para ello deberá solicitar los requisitos (protocolos, medio de comunicación, variables eléctricas, entre otros).
  • b)Para sistemas con capacidad nominal superior a la capacidad de placa del transformador, la persona interesada deberá gestionar un diseño de red eléctrica para el remplazo del transformador por uno con capacidad igual o mayor al sistema de generación distribuida para autoconsumo a instalar. Esto aplica para transformadores de CNFL. En caso de que el transformador sea privado, es responsabilidad del ingeniero a cargo de la obra.
  • c)Si el servicio es alimentado con un trifásico formado por un banco de dos transformadores, deberá gestionar un diseño de red eléctrica para completar el banco de transformadores.

Dicho diseño, materiales y ejecución de las obras corren por cuenta de la persona interesada y deben cumplir con los requisitos de la CNFL para el diseño y ejecución de obras en el sistema de distribución. La ejecución de estas obras deberá ser dentro del plazo de vigencia de la solicitud de interconexión y estudios de ingeniería e inspección inicial.

18

Deberá presentar una nota escrita, con 10 días hábiles de anticipación al vencimiento, indicando las razones y la nueva fecha de entrada de operación. La CNFL deberá responder si concede la prórroga solicitada en un plazo máximo de 10 días hábiles.

19

Una vez que se finalice la construcción del sistema de recursos energéticos distribuidos y dentro del plazo de vigencia de solicitud de interconexión y estudios de ingeniería e inspección inicial, la persona interesada deberá solicitar a la CNFL la inspección y puesta en marcha. La CNFL revisará el sistema para verificar que cumple las normas técnicas para la operación en paralelo con el sistema de distribución eléctrica. Para esto se debe considerar que:

  • a)Previo a la inspección, la persona interesada deberá cancelar el monto establecido por la ARESEP para la etapa de inspección final y puesta en marcha.
  • b)En caso de que la inspección resulte en un rechazo, se deberá atender las correcciones que corresponda y gestionar una reinspección, por la cual la persona interesada deberá cancelar el monto establecido por la ARESEP.
  • c)Tanto los ajustes requeridos como la reinspección deberán realizarse dentro del plazo de vigencia de la solicitud de interconexión y estudios de ingeniería e inspección inicial.
  • d)En caso de que se requiera alguna modificación a la red de distribución o interconexión de comunicación del sistema de generación con la CNFL, previo a la solicitud de inspección y puesta en marcha, el PDER deberá cumplir con esos requisitos.
  • e)Una vez verificados los documentos con la información técnica respectiva y realizada la inspección del proyecto, de no encontrarse inconvenientes técnicos o cambios en la capacidad o características de los equipos, se aprobará la interconexión de los recursos energéticos distribuidos.
  • f)De existir cambios en las especificaciones o modelos de los equipos o una variación de la capacidad del proyecto, de acuerdo con lo aprobado en la solicitud de interconexión y estudios de ingeniería e inspección inicial, se desestimará la solicitud y se deberá realizar una nueva solicitud de interconexión y estudios de ingeniería e inspección inicial.
  • g)La CNFL tendrá un plazo de 15 días hábiles para realizar la verificación de los requisitos y la inspección.
20

Una vez aprobada la inspección, la Sucursal respectiva procederá con la notificación (mediante oficio) del resultado en un plazo no mayor a 5 días hábiles posterior a la ejecución de la inspección. Se convocará para la firma del contrato de interconexión, la cual puede ser de manera física en la Sucursal respectiva o por medio de firma digital. En ambos casos se deberá cumplir con lo siguiente:

  • a)Presentar la cédula de identidad o personería jurídica vigente (con no más de treinta días naturales de haberse emitido) según corresponda.
  • b)En caso de que la firma del contrato la realice un tercero deberá presentar un poder especial autenticado.
  • c)Presentar la boleta del CFIA de la persona profesional responsable.
  • d)La firma del contrato de interconexión debe realizarse como mínimo 10 días antes de la fecha de lectura del medidor, día en que debe instalarse los sistemas de medición.

Si se trata de un caso sin entrega de excedentes a la red, posterior a la notificación de aprobación de la inspección, se debe presentar la declaración jurada de cero inyección (según el medio y formato establecido por la CNFL) y no se requiere de la firma de contrato de interconexión. La presentación de la declaración jurada debe realizarse como mínimo 10 días antes de la fecha de lectura de medidor, día en que debe instalarse los sistemas de medición.

Contrato y Modificaciones al Contrato

CAPÍTULO IV

21

Una vez aprobada la inspección se procederá a la firma del contrato de interconexión, y se programará la puesta en servicio de la interconexión. El estudio técnico que aprobó la CNFL será parte integral del contrato.

22

El contrato de interconexión es de naturaleza accesoria al contrato de suministro eléctrico que existe entre la persona propietaria del servicio y la CNFL, por lo que la finalización del contrato de interconexión o su incumplimiento, no afecta la validez y vigencia del contrato principal.

23

El contrato de interconexión que se firme será válido hasta que la ARESEP establezca, los procedimientos, metodologías, requisitos e instrumentos regulatorios que se indican en la Ley N° 10086. El PDER deberá cumplir con el plazo que fije la ARESEP para que sus DER cumplan con lo que establezca el instrumento regulatorio correspondiente y proceder con la firma de un nuevo contrato. En caso de que la ARESEP no indique el plazo, será de 3 meses a partir de la entrada en vigencia.

Sanciones

CAPÍTULO V

24

La CNFL podrá rechazar, suspender, interrumpir o desconectar el DER por los motivos establecidos en el artículo 27 del Decreto 43879-MINAE y por el incumplimiento a este reglamento.

Vigencia

CAPÍTULO VI

25

Este reglamento rige a partir de su publicación en El Diario Oficial La Gaceta.

Document not found. Documento no encontrado.

Implementing decreesDecretos que afectan

    TopicsTemas

    • Environmental Law 7554 — EIA, SETENA, and Public ParticipationLey Orgánica del Ambiente 7554 — EIA, SETENA y Participación Pública
    • Off-topic (non-environmental)Fuera de tema (no ambiental)

    Concept anchorsAnclajes conceptuales

    • Ley N° 10086 Art. 9
    • Ley N° 10086 Art. 6
    • Decreto 43879-MINAE Art. 29
    • Ley General de la Administración Pública (Ley N° 6227) Arts. 11, 12, 15, 16

    Spanish key termsTérminos clave en español

    News & Updates Noticias y Actualizaciones

    All articles → Todos los artículos →

    Weekly Dispatch Boletín Semanal

    Field reporting and policy analysis from Costa Rica's forests. Reportajes y análisis de política desde los bosques de Costa Rica.

    ✓ Subscribed. ✓ Suscrito.

    One email per week. No spam. Unsubscribe in one click. Un correo por semana. Sin spam. Cancela en un clic.

    Or WhatsApp channelO canal de WhatsApp →
    Coalición Floresta © 2026 · All rights reserved © 2026 · Todos los derechos reservados

    Stay Informed Mantente Informado

    Conservation news and action alerts, straight from the field Noticias de conservación y alertas de acción, directo desde el campo

    Email Updates Actualizaciones por Correo

    Weekly updates, no spam Actualizaciones semanales, sin spam

    Successfully subscribed! ¡Suscripción exitosa!

    WhatsApp Channel Canal de WhatsApp

    Join to get instant updates on your phone Únete para recibir actualizaciones instantáneas en tu teléfono

    Join Channel Unirse al Canal
    Coalición Floresta Coalición Floresta © 2026 Coalición Floresta. All rights reserved. © 2026 Coalición Floresta. Todos los derechos reservados.
    🙏