Res. 02069-2014 Sala Constitucional · Sala Constitucional · 18/02/2014
OutcomeResultado
The amparo is granted due to violation of the right to prompt administrative justice; the Municipality of Alajuela is ordered to resolve the environmental complaint within two months and is liable for costs and damages.Se declara con lugar el amparo por violación al derecho a justicia administrativa pronta y cumplida; se ordena resolver la denuncia ambiental en dos meses y se condena a la Municipalidad de Alajuela al pago de costas, daños y perjuicios.
SummaryResumen
The Constitutional Chamber reviews a writ of amparo filed by Álvaro Sagot Rodríguez against the Municipality of Alajuela for its failure to resolve an environmental complaint. The petitioner, on September 18, 2013, reported the construction of a cell phone tower without the required SETENA permits, alleging a violation of environmental regulations and constitutional precedent. After four months, the municipality had taken no formal action nor notified the complainant. The Chamber finds that the respondent authority only moved to act upon notification of the amparo, confirming that the tower lacked a construction permit and that proceedings had barely begun. The ruling establishes an injury to the right to prompt and effective administrative justice under Articles 41 and 50 of the Constitution. The amparo is granted; the municipality is ordered to resolve the complaint within two months and is liable for costs and damages.La Sala Constitucional conoce un recurso de amparo presentado por Álvaro Sagot Rodríguez contra la Municipalidad de Alajuela por la falta de resolución de una denuncia ambiental. El recurrente denunció el 18 de setiembre de 2013 la construcción de una torre de telefonía celular sin los permisos de la SETENA, lo que a su juicio vulnera la normativa ambiental y la jurisprudencia constitucional. Tras cuatro meses, la municipalidad no había iniciado procedimiento alguno ni notificado avances. La Sala constata que la autoridad recurrida solo actuó a raíz de la notificación del amparo, confirmando que la torre carecía de permiso de construcción y apenas se estaban iniciando las diligencias. Se acredita una lesión al derecho a una justicia administrativa pronta y cumplida, protegido por los artículos 41 y 50 de la Constitución Política. Se declara con lugar el recurso, ordenando resolver la denuncia en un plazo de dos meses y condenando en costas, daños y perjuicios a la municipalidad.
Key excerptExtracto clave
III. REGARDING THE SPECIFIC CASE: From examination of the record it is clear that the petitioner indeed reported to the respondent authorities, as of September 18, 2013, the construction of a telecommunications tower without first meeting SETENA requirements to safeguard the environment and public health. However, it was only in response to notification of this amparo that the respondents informed the petitioner that it had been confirmed that said tower indeed lacked the corresponding construction permit and that the competent Department had already been notified for due diligence. Thus, with four months having passed since the petitioner’s action, not only is the lack of construction requirements confirmed, but appropriate proceedings to bring the reported situation into legal compliance had only just begun. This undoubtedly warrants granting the amparo, as the petitioner’s right to prompt and effective administrative justice has been injured. Consequently, although the petitioner was informed regarding the processing of his complaint, it has not been resolved; accordingly, the amparo must be granted, and the respondent authorities ordered resolve the matter within the time period to be specified.III. SOBRE EL CASO CONCRETO: Del estudio de los autos se tiene que, en efecto, el recurrente denunció ante las autoridades recurridas desde el 18 de setiembre de 2013, la construcción de una torre de telecomunicaciones sin haber cumplido previamente con los requisitos de SETENA, que garanticen la no afectación del ambiente y de la salud de las personas. Sin embargo, es en atención a la notificación de este recurso, que los recurridos procedieron a notificarle al amparado que se había comprobado, que efectivamente dicha torre incluso no cuenta con el permiso de construcción correspondiente y que ya se había notificado al Departamento competente para su debida diligencia. De manera que, habiendo transcurrido 4 meses desde la gestión del amparado, no solo se le confirma la falta de requisitos de la construcción de dicha torre, sino que apenas iniciaron los procedimientos pertinentes para ajustar a derecho la situación denunciada. Lo anterior, sin duda alguna, amerita declarar con lugar el recurso, al constatarse la lesión del amparado a obtener justicia administrativa pronta y cumplida. En consecuencia, si bien le comunicaron al recurrente del trámite de su denuncia, pero esta no ha sido resuelta, lo pertinente es acoger el recurso y ordenar a las autoridades recurridas resolver lo correspondiente en el plazo que será indicado.
Pull quotesCitas destacadas
"se constató que las torres referidas no tienen permiso tramitado o aprobado de construcción para ese tipo de estructuras"
"it was confirmed that the referenced towers have no processed or approved construction permit for that type of structures"
Hechos Probados b)
"se constató que las torres referidas no tienen permiso tramitado o aprobado de construcción para ese tipo de estructuras"
Hechos Probados b)
"apenas iniciaron los procedimientos pertinentes para ajustar a derecho la situación denunciada."
"the appropriate proceedings to bring the reported situation into legal compliance had only just begun."
Considerando III
"apenas iniciaron los procedimientos pertinentes para ajustar a derecho la situación denunciada."
Considerando III
"Lo anterior, sin duda alguna, amerita declarar con lugar el recurso, al constatarse la lesión del amparado a obtener justicia administrativa pronta y cumplida."
"This undoubtedly warrants granting the amparo, as the petitioner’s right to prompt and effective administrative justice has been injured."
Considerando III
"Lo anterior, sin duda alguna, amerita declarar con lugar el recurso, al constatarse la lesión del amparado a obtener justicia administrativa pronta y cumplida."
Considerando III
"Se condena a la Municipalidad de Alajuela al pago de las costas, daños y perjuicios causados con los hechos que sirven de fundamento a esta declaratoria"
"The Municipality of Alajuela is ordered to pay costs and damages arising from the facts that serve as the basis for this declaration"
Por tanto
"Se condena a la Municipalidad de Alajuela al pago de las costas, daños y perjuicios causados con los hechos que sirven de fundamento a esta declaratoria"
Por tanto
Full documentDocumento completo
Constitutional Chamber Date of Resolution: February 18, 2014 at 14:30 Docket: 14-000687-0007-CO Type of matter: Amparo appeal Judgment with protected data, in accordance with current regulations Docket: 14-000687-0007-CO CONSTITUTIONAL CHAMBER OF THE SUPREME COURT OF JUSTICE. San José, at fourteen hours and thirty minutes on the eighteenth of February, two thousand fourteen.
Amparo appeal filed by Álvaro Sagot Rodríguez against the Municipality of Alajuela.
Whereas:
Drafted by Magistrate Cruz Castro; and,
Considering:
The appellant claims that since October 18, 2013, he filed a complaint before the Municipality of Alajuela – a complaint related to the construction of a telephone tower that did not have the SETENA permits – and that to date he has not received a response, an action that violates the content of articles 41 and 50 of the Political Constitution.
Of importance for the decision in this matter, the following facts are deemed duly proven, either because they have been so credited or because the respondent has omitted to refer to them as provided in the initial order:
From the study of the case records, it is determined that, indeed, the appellant denounced before the respondent authorities, as of September 18, 2013, the construction of a telecommunications tower without having previously complied with the SETENA requirements, which guarantee the non-affectation of the environment and the health of persons. However, it is in response to the notification of this appeal that the respondents proceeded to notify the petitioner that it had been verified that said tower indeed does not even have the corresponding construction permit and that the competent Department had already been notified for its due diligence. Therefore, having elapsed 4 months since the petitioner's action, not only is the lack of requirements for the construction of said tower confirmed to him, but the pertinent procedures to bring the denounced situation into compliance with the law have only just begun. The foregoing, without a doubt, warrants granting the appeal, as the violation of the petitioner's right to obtain prompt and complete administrative justice is confirmed. Consequently, even though they communicated the processing of his complaint to the appellant, but it has not been resolved, what is pertinent is to uphold the appeal and order the respondent authorities to resolve the matter within the period that will be indicated.
Therefore:
The appeal is granted. Roberto Hernán Thompson Chacón and William Quirós Selva, in their order, Mayor and President of the Municipal Council of Alajuela, or whomever exercises the position in their stead, are ordered to resolve the complaint filed by the appellant on September 18, 2013, and to notify the resolution within a period of two months counted from the notification of this resolution, under the warning that based on the provisions of article 71 of the Law of Constitutional Jurisdiction, imprisonment of three months to two years, or a fine of twenty to sixty days, will be imposed on anyone who receives an order that must be complied with or enforced, issued in an amparo appeal, and does not comply with it or does not enforce it, provided that the offense is not more severely punished. The Municipality of Alajuela is ordered to pay the costs, damages, and losses caused by the facts that serve as the basis for this declaration, which will be liquidated in the execution of judgment in the administrative contentious jurisdiction. Notify this resolution to Roberto Hernán Thompson Chacón and William Quirós Selva, in their order, Mayor and President of the Municipal Council of Alajuela, or whomever exercises the position in their stead, IN PERSON.
SCIJ of Hacienda SCIJ of the Office of the Attorney General
Sentencia con datos protegidos, de conformidad con la normativa vigente SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las catorce horas treinta minutos del dieciocho de febrero de dos mil catorce.
Recurso de amparo presentado por Álvaro Sagot Rodríguez contra la Municipalidad de Alajuela.
Resultando:
Redacta el Magistrado Cruz Castro; y,
Considerando:
El recurrente alega que desde el 18 de octubre del 2013 presentó una denuncia ante la Municipalidad de Alajuela –denuncia relacionada con la construcción de una torre de telefonía que no contaba con los permisos de la SETENA-, siendo que a la fecha no ha recibido respuesta, actuación que vulnera el contenido de los artículos 41 y 50 de la Constitución Política.
De importancia para la decisión de este asunto, se estiman como debidamente demostrados los siguientes hechos, sea porque así han sido acreditados o bien porque el recurrido haya omitido referirse a ellos según lo prevenido en el auto inicial:
Del estudio de los autos se tiene que, en efecto, el recurrente denunció ante las autoridades recurridas desde el 18 de setiembre de 2013, la construcción de una torre de telecomunicaciones sin haber cumplido previamente con los requisitos de SETENA, que garanticen la no afectación del ambiente y de la salud de las personas. Sin embargo, es en atención a la notificación de este recurso, que los recurridos procedieron a notificarle al amparado que se había comprobado, que efectivamente dicha torre incluso no cuenta con el permiso de construcción correspondiente y que ya se había notificado al Departamento competente para su debida diligencia. De manera que, habiendo transcurrido 4 meses desde la gestión del amparado, no solo se le confirma la falta de requisitos de la construcción de dicha torre, sino que apenas iniciaron los procedimientos pertinentes para ajustar a derecho la situación denunciada. Lo anterior, sin duda alguna, amerita declarar con lugar el recurso, al constatarse la lesión del amparado a obtener justicia administrativa pronta y cumplida. En consecuencia, si bien le comunicaron al recurrente del trámite de su denuncia, pero esta no ha sido resuelta, lo pertinente es acoger el recurso y ordenar a las autoridades recurridas resolver lo correspondiente en el plazo que será indicado.
Por tanto:
Se declara con lugar el recurso. Se ordena a Roberto Hernán Thompson Chacón y a William Quirós Selva, por su orden, Alcalde y Presidente del Concejo Municipal de Alajuela, o a quienes en su lugar ejerzan el cargo, resolver la denuncia presentada por el recurrente el 18 de setiembre del 2013 de 2013 y notificarle lo resuelto del plazo de dos meses contado a partir de la notificación de esta resolución, bajo el apercibimiento de que con base en lo establecido en el artículo 71 de la Ley de la Jurisdicción Constitucional, se impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo y no la cumpliere o no la hiciere cumplir, siempre que el delito no esté más gravemente penado. Se condena a la Municipalidad de Alajuela al pago de las costas, daños y perjuicios causados con los hechos que sirven de fundamento a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso administrativo. Notifíquese esta resolución a Roberto Hernán Thompson Chacón y a William Quirós Selva, por su orden, Alcalde y Presidente del Concejo Municipal de Alajuela, o a quienes en su lugar ejerzan el cargo, EN FORMA PERSONAL.