Res. 00529-2014 Sala Constitucional · Sala Constitucional · 17/01/2014
OutcomeResultado
The amparo is granted against the Municipality of Cartago, ordering the completion of the sewerage and wastewater treatment system and the start of its operation no later than January 5, 2017.Se declara con lugar el amparo contra la Municipalidad de Cartago, ordenando concluir el sistema de alcantarillado y tratamiento de aguas negras e iniciar su funcionamiento a más tardar el 5 de enero de 2017.
SummaryResumen
The Constitutional Chamber reviewed an amparo filed by a resident of Cartago against the Municipality of Cartago and the Ministry of Health, alleging violation of the right to health and a healthy environment due to the prolonged lack of a sanitary sewerage and wastewater treatment system in the canton. Despite multiple prior resolutions ordering a solution since 2007, the works remained uncompleted. The Chamber found that although the Municipality had made budgetary and technical efforts, nearly seven years had passed without complying with the original order, exceeding the granted deadlines without requesting an extension. The amparo is granted against the Municipality, ordering it to complete the sewerage system and begin operations no later than January 5, 2017, according to the timeline submitted by the Municipality itself. The Municipality is ordered to pay costs, damages, and losses. Regarding the Ministry of Health, the amparo is dismissed as no arbitrary omission was proven.La Sala Constitucional conoce un amparo interpuesto por un vecino de Cartago contra la Municipalidad de Cartago y el Ministerio de Salud, alegando violación al derecho a la salud y a un ambiente sano por la prolongada falta de un sistema de alcantarillado sanitario y tratamiento de aguas negras en el cantón. El recurrente señala que a pesar de múltiples resoluciones previas de la Sala que ordenaron solucionar el problema desde 2007, las obras no se han completado. La Sala constata que, si bien la Municipalidad ha realizado gestiones presupuestarias y técnicas, han transcurrido casi siete años sin cumplir la orden original, excediendo los plazos concedidos sin solicitar prórroga. Se declara con lugar el recurso contra la Municipalidad, ordenándole concluir el sistema de alcantarillado e iniciar su funcionamiento a más tardar el 5 de enero de 2017, según el cronograma aportado por la propia institución. Se condena a la Municipalidad al pago de costas, daños y perjuicios. Respecto al Ministerio de Salud, se declara sin lugar al no acreditarse omisión arbitraria de su parte.
Key excerptExtracto clave
IV.- From the foregoing it is fully verifiable that the respondent Municipality has indeed managed and included in its budget various items to comply with the order of this Chamber. While the respondent authority is right in pointing out that achieving the operation of an adequate sewerage and wastewater treatment system for the central canton of the Province of Cartago has been a complex matter due to the technical studies and budget involved, the truth is that not only has the one-year period given by this Chamber elapsed—without any request for an extension in that regard—but to date nearly 7 years have passed since the Chamber ordered its implementation without it having been made effective. It should be noted that in February 2009, said Municipality informed this Chamber that it would provide a comprehensive solution to the problem within 4 years; however, that deadline passed and now the Mayor reports—according to the submitted timeline—that the start of the System's operation is scheduled from September 7, 2015 to January 5, 2017. In view of the factual scenario described, the Chamber finds a violation of the right to health, since while the respondent authority has taken steps to provide the canton of Cartago with a sewerage and wastewater treatment system, it has exceeded the deadlines granted by this Chamber without requesting any extension, and has indicated different moments for the project's completion, which creates uncertainty. V.- Regarding the Ministry of Health, the amparo must be dismissed, as no omission or arbitrary action to the detriment of the petitioner has been found in the sub examine. Therefore: The amparo is granted for violation of Articles 21 and 50 of the Constitution against the Municipality of Cartago. Consequently, Rolando Rodríguez Brenes and Adrián Leandro Marín, respectively Mayor and Council President, both of the Municipality of Cartago, or whoever holds those positions, are ordered to complete the sewerage and wastewater treatment system in the central canton of Cartago, and to begin its operation according to the dates indicated in the attached timeline, which sets January 5, 2017 as the maximum date.IV.- De lo anterior es plenamente constatable, que la Municipalidad recurrida efectivamente ha gestionado e incluido en su presupuesto diversas partidas para dar cumplimiento a lo ordenado por este Tribunal. Si bien lleva razón la autoridad recurrida al señalar que lograr la operación de un sistema adecuado de alcantarillado y tratamiento de aguas negras para el cantón Central de la Provincia de Cartago ha sido un asunto complejo por los estudios técnicos que implica y el presupuesto que este conlleva, lo cierto es que no solo ha transcurrido el año dado por este Tribunal para hacerlo –sin que conste solicitud de prórroga alguna en ese sentido-, sino que a la fecha han transcurrido casi 7 años desde que la Sala ordenó su implementación sin que se haya hecho efectivo. Debe advertirse que en el mes de febrero de 2009, dicho Municipio informó a este Tribunal que en 4 años daría una solución integral al problema; sin embargo, este plazo transcurrió y actualmente el Alcalde informa -según el cronograma aportado-, que está previsto el inicio de la operación del Sistema del 7 de setiembre de 2015 al 5 de enero de 2017. Ante el cuadro fáctico señalado la Sala constata la vulneración del derecho a la salud, toda vez que si bien la autoridad recurrida ha gestionado con el objeto de dotar al cantón de Cartago de un sistema de alcantarillado y tratamiento de aguas negras, lo cierto es que se ha excedido en los plazos concedidos por este Tribunal sin gestionar prórroga alguna, así como ha indicado diferentes momentos de culminación del proyecto lo cual genera incerteza. V.- Respecto al Ministerio de Salud procede declarar sin lugar el recurso, por no haberse constatado en el sub examine omisión o actuación arbitraria alguna en perjuicio del recurrente. Por tanto: Se declara con lugar el recurso por violación a los artículos 21 y 50 constitucionales contra la Municipalidad de Cartago. En consecuencia, se ordena a Rolando Rodríguez Brenes y a Adrián Leandro Marín, por su orden Alcalde y Presidente del Concejo, ambos de la Municipalidad de Cartago, o a quienes ocupen esos cargos, concluir el sistema de alcantarillado y tratamiento de aguas negras en el cantón central de Cartago, e iniciar su funcionamiento a partir de las fechas señaladas en el cronograma adjunto, que dispone como fecha máxima el 5 de enero de 2017.
Pull quotesCitas destacadas
"Ante el cuadro fáctico señalado la Sala constata la vulneración del derecho a la salud, toda vez que si bien la autoridad recurrida ha gestionado con el objeto de dotar al cantón de Cartago de un sistema de alcantarillado y tratamiento de aguas negras, lo cierto es que se ha excedido en los plazos concedidos por este Tribunal sin gestionar prórroga alguna, así como ha indicado diferentes momentos de culminación del proyecto lo cual genera incerteza."
"In view of the factual scenario described, the Chamber finds a violation of the right to health, since while the respondent authority has taken steps to provide the canton of Cartago with a sewerage and wastewater treatment system, it has exceeded the deadlines granted by this Chamber without requesting any extension, and has indicated different moments for the project's completion, which creates uncertainty."
Considerando IV
"Ante el cuadro fáctico señalado la Sala constata la vulneración del derecho a la salud, toda vez que si bien la autoridad recurrida ha gestionado con el objeto de dotar al cantón de Cartago de un sistema de alcantarillado y tratamiento de aguas negras, lo cierto es que se ha excedido en los plazos concedidos por este Tribunal sin gestionar prórroga alguna, así como ha indicado diferentes momentos de culminación del proyecto lo cual genera incerteza."
Considerando IV
"Se declara con lugar el recurso por violación a los artículos 21 y 50 constitucionales contra la Municipalidad de Cartago."
"The amparo is granted for violation of Articles 21 and 50 of the Constitution against the Municipality of Cartago."
Por tanto
"Se declara con lugar el recurso por violación a los artículos 21 y 50 constitucionales contra la Municipalidad de Cartago."
Por tanto
Full documentDocumento completo
CONSTITUTIONAL CHAMBER OF THE SUPREME COURT OF JUSTICE. San José, at nine hours and five minutes on the seventeenth of January of two thousand fourteen.
Appeal for protection (Recurso de amparo) processed in case file number 13-007252-0007-CO, filed by JULIO GOMEZ CARBALLO, identity card 0302170069, against THE MUNICIPALITY OF CARTAGO AND THE MINISTRY OF HEALTH.
Whereas:
Drafted by Judge Rueda Leal; and,
Considering:
I.Object of the appeal. The appellant alleges that the Municipality of Cartago has not carried out actions aimed at definitively solving the problem of blackwater treatment, which he considers injures his right to health and to a healthy environment, despite the repeated pronouncements of this Tribunal.
II.Proven facts. Of importance for the decision of this matter, the following facts are deemed duly demonstrated, either because they have been so accredited or because the respondent has omitted to refer to them as provided in the initial order:
(see attached evidence) c) On October 8, 2008, the respondent Municipal Mayor presented to the Chamber, in case file No. 07-007071-0007-CO, the Memorandum of Understanding signed for the Development of the Potable Water and Sanitation Program at the sub-national level, which they submitted to the Presidency of the Republic for its signature. (see attached evidence) d) On October 1, 2008, the BID signed the Non-reimbursable Technical Cooperation Agreement with the respondent Municipality. (see attached evidence) e) The Municipality of Cartago included in the ordinary budget for 2009, the line item “Construction and Improvements of the Sewer System” for an amount of 672,753,838 colones and informed this Tribunal that the total project had an approximate execution period of 4 years to provide a comprehensive solution to the problem. (see attached evidence) f) The Council of the Sanitary Sewer Project carried out a diagnosis and began the search for resources to implement the sewer system of Cartago, among them, a potential loan with Banco Crédito Agrícola de Cartago for 500,000,000 colones, destined for the purchase of piping and other expenses of the first stage of the project.
(see attached evidence) g) For the ordinary budget 2013, the respondent Municipality allocated 139,500,000 colones, of which 112,500,000 would be for the registration in the Stock Exchange for the first bond series that will finance the first stage of the project and 27,000,000 colones for the underwriting contract for the bond issuance; as well as 400,000,000 colones as trust funds for capital expenses. (see attached evidence) h) The Ministry of Health approved in 2013 the Sanitary Sewer Project in question. (see report rendered by the Ministry of Health) i) From the budgetary period 2008 until 2013, the respondent Municipality has incorporated in its budgets 1,632,651,367.72 colones for the construction of the Sanitary Sewer System of the canton of Cartago. (see report rendered by the Comptroller General of the Republic) j) On December 16, 2013, the Institute for Municipal Development and Advisory (Instituto de Fomento y Asesoría Municipal) approved the credit for 6,193,868,315.09 colones, so that the Municipality of Cartago can carry out the first stage of the Sanitary Sewer Project in the central canton of Cartago.
(see attached official letter SG-301-13) k) The sanitary sewer project of Cartago has the environmental viability (viabilidad ambiental) issued by SETENA in November 2013. (see attached official letter AAF-OF-386-13 of December 17, 2013) l) The contracting to carry out the first stage of the project has been planned by the respondent Municipality from January 14, 2014, to October 15, 2014, the Construction of the first stage of the Toyogres System from January 22, 2015, to January 5, 2017, and the start of the System's operation from September 7, 2015, to January 5, 2017. (see schedule attached by the Municipality of Cartago)
III.On the merits. Indeed, the problematic situation alleged by the appellant has been the object of consideration by this Tribunal since 2007, including in a previous appeal filed by the appellant and granted by this Tribunal in resolution No. 2012-4636. Since judgment No. 2007-17007 at 18:11 hours on November 21, 2007, the Chamber determined the violation of the right to a healthy environment because the central canton of Cartago lacked a sewer and blackwater treatment system, which is why it ordered at that time, the Municipal Mayor of Cartago and the Minister of Health to adopt the measures necessary to provide a comprehensive solution to the problem of the sewer system and blackwater treatment in the central canton of Cartago. Likewise, the Municipal Mayor of Cartago was ordered to proceed immediately to manage a budgetary amendment if the resources were not available at that time, so that within a period of one year counted from the notification of that judgment, he would begin and conclude on his own account the commissioning of an adequate sewer and blackwater treatment system in the Central canton of the Province of Cartago.
In compliance with what was ordered, the Municipality of Cartago submitted repeated reports to case file No. 07-007071-007-CO. According to the content of these reports, since 2008 the respondent Municipality began coordination with IFAM and ICAA to achieve technical cooperation from the BID. On January 28, 2008, it reported to this Tribunal that the project would tentatively take 4 and a half years. On October 8, 2008, it presented the Memorandum of Understanding signed for the Development of the Potable Water and Sanitation Program at the sub-national level, which they submitted to the Presidency of the Republic for its signature. On December 10, 2008, it reported that on October 1, 2008, the BID signed the Non-reimbursable Technical Cooperation Agreement, so that once the necessary resources existed, the project could begin. On February 27, 2009, it was reported that for the ordinary budget of 2009, the line item "Construction and Improvements of the Sewer System" was included for an amount of 672,753,838 colones and that the total project had an approximate execution period of 4 years to provide a comprehensive solution to the problem.
On April 30, 2010, the Mayor reported to this Tribunal that by agreement of the Council of the Sanitary Sewer Project, a diagnosis was carried out and the search for resources began, among them, a potential loan with Banco Crédito Agrícola de Cartago for 500,000,000 colones, destined for the purchase of piping and other expenses of the first stage of the project. On July 9 and August 20, both in 2013, the respondent authorities reported that the Municipality has continuously addressed the denounced problem and is in the implementation and execution phase of the already approved technical solutions, but they clarify that this is such a complex matter that it requires a long-term process. They point out that for the ordinary budget 2013, 139,500,000 colones were budgeted, of which 112,500,000 will be for the registration in the Stock Exchange for the first bond series that will finance the first stage of the project and 27,000,000 colones for the underwriting contract for the bond issuance; as well as 400,000,000 colones as trust funds for capital expenses.
As the Ministry of Health also indicated, this dependency already approved the Sanitary Sewer Project in question, but the Municipality clarified that it would be implemented starting in the year 2014, because they do not have the necessary resources. For its part, the Comptroller General of the Republic reported that from the budgetary period 2008 until 2013, the respondent Municipality has incorporated in its budgets 1,632,651,367.72 colones for the construction of the Sanitary Sewer System of the canton of Cartago. In consideration of the evidence requested in this appeal, it is additionally proven that on December 16, 2013, the Institute for Municipal Development and Advisory (Instituto de Fomento y Asesoría Municipal) approved the credit for 6,193,868,315.09 colones, so that the Municipality of Cartago can carry out the first stage of the Sanitary Sewer Project in the central canton of Cartago, and that the project in question has the environmental viability (viabilidad ambiental) issued by SETENA since November 2013.
Likewise, the respondent Municipality provided a schedule to this Tribunal regarding the planning, construction, and implementation phases of the Project in question, according to which the contracting phase to carry out the first stage of the project has been planned by the respondent Municipality from January 14, 2014, to October 15, 2014, the Construction of the first stage of the Toyogres System, from January 22, 2015, to January 5, 2017, and the start of the System's operation, from September 7, 2015, to January 5, 2017.
IV.From the foregoing, it is fully verifiable that the respondent Municipality has effectively managed and included in its budget various line items to comply with what was ordered by this Tribunal. Although the respondent authority is correct in pointing out that achieving the operation of an adequate sewer and blackwater treatment system for the Central canton of the Province of Cartago has been a complex matter due to the technical studies it implies and the budget it entails, the truth is that not only has the year given by this Tribunal to do so elapsed – without any request for extension in that regard being on record – but to date almost 7 years have passed since the Chamber ordered its implementation without it having been made effective. It must be noted that in the month of February 2009, said Municipality informed this Tribunal that in 4 years it would provide a comprehensive solution to the problem; however, this period elapsed and the Mayor currently reports - according to the attached schedule - that the start of the System's operation is planned from September 7, 2015, to January 5, 2017.
Given the factual situation indicated, the Chamber verifies the violation of the right to health, since although the respondent authority has taken steps to provide the canton of Cartago with a sewer and blackwater treatment system, the truth is that it has exceeded the deadlines granted by this Tribunal without managing any extension, and has indicated different moments for the project's completion, which generates uncertainty. Under these considerations, the amparo must be granted; however, taking into account the complexity of the project and the deadlines set by the respondent authority itself in the attached schedule, this Tribunal urges the Municipality of Cartago to conclude the sewer and blackwater treatment system in the Central canton of the Province of Cartago and to begin its operation from the dates indicated in the attached plan, with January 5, 2017, as the maximum date.
V.Regarding the Ministry of Health, it is appropriate to dismiss the appeal, as no omission or arbitrary action detrimental to the appellant has been verified in the sub examine.
Therefore:
The appeal is granted for violation of constitutional articles 21 and 50 against the Municipality of Cartago. Consequently, Rolando Rodríguez Brenes and Adrián Leandro Marín, in their order Mayor and President of the Council, both of the Municipality of Cartago, or whoever occupies those positions, are ordered to conclude the sewer and blackwater treatment system in the central canton of Cartago, and to begin its operation from the dates indicated in the attached schedule, which establishes January 5, 2017, as the maximum date. The Municipality of Cartago is ordered to pay the costs, damages, and losses caused by the facts that serve as the basis for this declaration, which shall be liquidated in the execution of judgment of the contentious-administrative court. Regarding the Ministry of Health, the appeal is dismissed. Let this resolution be notified to Rolando Rodríguez Brenes and Adrián Leandro Marín, in their order Mayor and President of the Council, both of the Municipality of Cartago, or to whoever occupies those positions, in person. Communicate.-
SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas cinco minutos del diecisiete de enero de dos mil catorce.
Recurso de amparo que se tramita en expediente número 13-007252-0007-CO, interpuesto por JULIO GOMEZ CARBALLO, cédula de identidad 0302170069, contra LA MUNICIPALIDAD DE CARTAGO Y EL MINISTERIO DE SALUD.
Resultando:
Redacta el Magistrado Rueda Leal; y,
Considerando:
I.Objeto el recurso. El recurrente acusa que la Municipalidad de Cartago, no ha realizado acciones tendientes a solucionar de forma definitiva el problema del tratamiento de aguas negras, lo que considera lesiona su derecho a la salud y a un medio ambiente sano, a pesar de los reiterados pronunciamientos de este Tribunal.
II.Hechos probados. De importancia para la decisión de este asunto, se estiman como debidamente demostrados los siguientes hechos, sea porque así han sido acreditados o bien porque el recurrido haya omitido referirse a ellos según lo prevenido en el auto inicial:
(ver pruebas adjuntas) c) El 8 de octubre de 2008, el Alcalde Municipal recurrido presentó a la Sala en el expediente No. 07-007071-0007-CO, la Carta de Entendimiento suscrita para el Desarrollo del Programa de Agua Potable y saneamiento a nivel sub-nacional, la cual remitieron a la Presidencia de la República para su firma. (ver pruebas adjuntas) d) El 1 de octubre de 2008, el BID suscribió el Convenio de Cooperación Técnica no reembolsable con la Municipalidad recurrida. (ver pruebas adjuntas) e) La Municipalidad de Cartago incluyó en el presupuesto ordinario de 2009, la partida “Construcción y Mejoras del Alcantarillado” por un monto de 672.753.838 colones e informó a este Tribunal, que el proyecto total tenía un plazo de ejecución aproximado de 4 años para dar una solución integral al problema. (ver pruebas adjuntas) f) El Concejo del Proyecto de Alcantarillado Sanitario levantó un diagnóstico e inició la búsqueda de recursos para implementar el sistema de alcantarillado de Cartago, entre ellos, un eventual empréstito con el Banco Crédito Agrícola de Cartago por 500.000.000 colones, destinados a la compra de tubería y otros gastos de la primera etapa del proyecto.
(ver pruebas adjuntas) g) Para el presupuesto ordinario 2013, la Municipalidad recurrida destinó 139.500.000 colones, de los cuales 112.500.000 serían para la inscripción en la Bolsa de Valores para la primera serie de bonos que financiarán la primera etapa del proyecto y 27.000.000 colones para el contrato underwritting para la emisión de bonos; así como 400.000.000 colones como fondos al fideicomiso para gastos de capital. (ver pruebas adjuntas) h) El Ministerio de Salud aprobó en el 2013 el Proyecto de Alcantarillado Sanitario en cuestión. (ver informe rendido por el Ministerio de Salud)) i) Desde el período presupuestario 2008 hasta el 2013, la Municipalidad recurrida ha incorporado en sus presupuestos 1.632.651.367.72 colones para la construcción del Alcantarillado Sanitario del cantón de Cartago. (ver informe rendido por la Contraloría General de la República) j) El 16 de diciembre de 2013, el Instituto de Fomento y Asesoría Municipal aprobó el crédito por 6.193.868.315.09 colones, para que la Municipalidad de Cartago lleve a cabo la primera etapa del proyecto del Alcantarillado Sanitario en el cantón central de Cartago.
(ver oficio SG-301-13 adjunto) k) El proyecto de alcantarillado sanitario de Cartago cuenta con la viabilidad ambiental expedida por SETENA en noviembre de 2013. (ver oficio AAF-OF-386-13 del 17 de diciembre de 2013 adjunto) l) La contratación para llevar a cabo la primera etapa del proyecto ha sido prevista por la Municipalidad recurrida del 14 de enero de 2014 al 15 de octubre de 2014, la Construcción de la primera etapa del Sistema de Toyogres del 22 de enero de 2015 al 5 de enero de 2017 y el inicio de la operación del Sistema del 7 de setiembre de 2015 al 5 de enero de 2017. (ver cronograma adjunto por la Municipalidad de Cartago)
III.Sobre el fondo. En efecto, la problemática que acusa el recurrente ha sido objeto de conocimiento por parte de este Tribunal desde el 2007, incluso en anterior recurso presentado por el recurrente y estimado por este Tribunal en la resolución No. 2012-4636. Desde la sentencia No. 2007-17007 de las 18:11 horas del 21 de noviembre de 2007, la Sala determinó la vulneración del derecho a un ambiente sano al no contar el cantón central de Cartago con un sistema de alcantarillado y tratamiento de aguas negras, motivo por el cual dispuso en aquella oportunidad, ordenar al Alcalde Municipal de Cartago y a la Ministra de Salud, adoptar las medidas que fuesen necesarias para darle una solución integral al problema de alcantarillado y tratamiento de las aguas negras en el cantón central de Cartago. Asimismo, se ordenó al Alcalde Municipal de Cartago, que procediera de inmediato a gestionar una modificación presupuestaria si no contaba con los recursos en ese momento, para que dentro del plazo de un año contado a partir de la notificación de esa sentencia, iniciara y concluyera por cuenta propia la puesta en operación de un sistema adecuado de alcantarillado y tratamiento de aguas negras en el cantón Central de la Provincia de Cartago.
En cumplimiento de lo ordenado, la Municipalidad de Cartago remitió reiterados informes al expediente No. 07-007071-007-CO. Según el contenido de estos informes, desde el 2008 el Municipio recurrido inició coordinaciones con el IFAM y el ICAA para lograr la cooperación técnica del BID. El 28 de enero de 2008, reportó a este Tribunal que tentativamente el proyecto tardaría 4 años y medio. El 8 de octubre de 2008, presentó la Carta de Entendimiento suscrita para el Desarrollo del Programa de Agua Potable y saneamiento a nivel sub-nacional, la cual remitieron a la Presidencia de la República para su firma. El 10 de diciembre de 2008 informó que el 1 de octubre de 2008 el BID suscribió el Convenio de Cooperación Técnica no reembolsable, para que una vez que existan los recursos necesarios se iniciara el proyecto. El 27 de febrero de 2009, se informó que para el presupuesto ordinario del 2009 se encontraba incluida la partida “Construcción y Mejoras del Alcantarillado” por un monto de 672.753.838 colones y que el proyecto total tenía un plazo de ejecución aproximado de 4 años para dar una solución integral al problema.
El 30 de abril de 2010, el Alcalde informó a este Tribunal que por acuerdo del Concejo del Proyecto de Alcantarillado Sanitario se levantó un diagnóstico y se inició la búsqueda de recursos, entre ellos, un eventual empréstito con el Banco Crédito Agrícola de Cartago por 500.000.000 colones, destinados a la compra de tubería y otros gastos de la primera etapa del proyecto. El 9 de julio y el 20 de agosto, ambos de 2013, las autoridades recurridas informaron que la Municipalidad en forma continua ha atendido el problema denunciado y que se encuentra en fase de implementación y ejecución de las soluciones técnicas ya aprobadas, pero aclaran que se está ante un asunto tan complejo que requiere un proceso de largo plazo. Señalan que para el presupuesto ordinario 2013 se presupuestaron 139.500.000 colones, de los cuales 112.500.000 serán para la inscripción en la Bolsa de Valores para la primera serie de bonos que financiarán la primera etapa del proyecto y 27.000.000 colones para el contrato underwritting para la emisión de bonos; así como 400.000.000 colones como fondos al fideicomiso para gastos de capital.
Según indicó también el Ministerio de Salud, esta dependencia ya aprobó el Proyecto de Alcantarillado Sanitario en cuestión, pero el Municipio aclaró que se implementaría a partir del año 2014, debido a que no cuentan con los recursos necesarios. Por su parte, la Contraloría General de la República informó que desde el período presupuestario 2008 hasta el 2013, la Municipalidad recurrida ha incorporado en sus presupuestos 1.632.651.367.72 colones para la construcción del Alcantarillado Sanitario del cantón de Cartago. En atención a la prueba solicitada en este recurso, se tiene adicionalmente por demostrado, que el 16 de diciembre de 2013, el Instituto de Fomento y Asesoría Municipal aprobó el crédito por 6.193.868.315.09 colones, para que la Municipalidad de Cartago lleve a cabo la primera etapa del proyecto del Alcantarillado Sanitario en el cantón central de Cartago y que el proyecto en cuestión cuenta con la viabilidad ambiental expedida por SETENA desde noviembre de 2013.
Asimismo, la Municipalidad recurrida aportó un cronograma a este Tribunal relativo a las fases de planeación, construcción e implementación del Proyecto en cuestión, según el cual la fase de contratación para llevar a cabo la primera etapa del proyecto ha sido prevista por la Municipalidad recurrida del 14 de enero de 2014 al 15 de octubre de 2014, la Construcción de la primera etapa del Sistema de Toyogres, del 22 de enero de 2015 al 5 de enero de 2017 y el inicio de la operación del Sistema, del 7 de setiembre de 2015 al 5 de enero de 2017.
IV.De lo anterior es plenamente constatable, que la Municipalidad recurrida efectivamente ha gestionado e incluido en su presupuesto diversas partidas para dar cumplimiento a lo ordenado por este Tribunal. Si bien lleva razón la autoridad recurrida al señalar que lograr la operación de un sistema adecuado de alcantarillado y tratamiento de aguas negras para el cantón Central de la Provincia de Cartago ha sido un asunto complejo por los estudios técnicos que implica y el presupuesto que este conlleva, lo cierto es que no solo ha transcurrido el año dado por este Tribunal para hacerlo –sin que conste solicitud de prórroga alguna en ese sentido-, sino que a la fecha han transcurrido casi 7 años desde que la Sala ordenó su implementación sin que se haya hecho efectivo. Debe advertirse que en el mes de febrero de 2009, dicho Municipio informó a este Tribunal que en 4 años daría una solución integral al problema; sin embargo, este plazo transcurrió y actualmente el Alcalde informa -según el cronograma aportado-, que está previsto el inicio de la operación del Sistema del 7 de setiembre de 2015 al 5 de enero de 2017.
Ante el cuadro fáctico señalado la Sala constata la vulneración del derecho a la salud, toda vez que si bien la autoridad recurrida ha gestionado con el objeto de dotar al cantón de Cartago de un sistema de alcantarillado y tratamiento de aguas negras, lo cierto es que se ha excedido en los plazos concedidos por este Tribunal sin gestionar prórroga alguna, así como ha indicado diferentes momentos de culminación del proyecto lo cual genera incerteza. Bajo esas consideraciones el amparo debe ser estimado; sin embargo, tomando en consideración la complejidad del proyecto y los plazos fijados por la propia autoridad recurrida en el cronograma aportado, este Tribunal conmina a la Municipalidad de Cartago, a concluir el sistema de alcantarillado y tratamiento de aguas negras en el cantón Central de la Provincia de Cartago y a iniciar su funcionamiento a partir de las fechas señaladas en el plano adjunto, teniendo como fecha máxima 5 de enero de 2017.
V.Respecto al Ministerio de Salud procede declarar sin lugar el recurso, por no haberse constatado en el sub examine omisión o actuación arbitraria alguna en perjuicio del recurrente.
Por tanto:
Se declara con lugar el recurso por violación a los artículos 21 y 50 constitucionales contra la Municipalidad de Cartago. En consecuencia, se ordena a Rolando Rodríguez Brenes y a Adrián Leandro Marín, por su orden Alcalde y Presidente del Concejo, ambos de la Municipalidad de Cartago, o a quienes ocupen esos cargos, concluir el sistema de alcantarillado y tratamiento de aguas negras en el cantón central de Cartago, e iniciar su funcionamiento a partir de las fechas señaladas en el cronograma adjunto, que dispone como fecha máxima el 5 de enero de 2017. Se condena a la Municipalidad de Cartago al pago de las costas, daños y perjuicios causados con los hechos que sirven de base a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso administrativo. En cuanto al Ministerio de Salud se declara sin lugar el recurso. Notifíquese esta resolución a Rolando Rodríguez Brenes y a Adrián Leandro Marín, por su orden Alcalde y Presidente del Concejo, ambos de la Municipalidad de Cartago, o a quienes ocupen esos cargos, en forma personal. Comuníquese.-