Coalición Floresta Logo Coalición Floresta Search Buscar
Language: English
About Acerca de Contact Contacto Search Buscar Notes Notas Donate Donar Environmental Law Derecho Ambiental
About Acerca de Contact Contacto Search Buscar Notes Notas Donate Donar Environmental Law Derecho Ambiental
Language: English
Beta Public preview Vista previa

← Environmental Law Center← Centro de Derecho Ambiental

Res. 01045-2011 Sala Constitucional · Sala Constitucional · 28/01/2011

Mandatory Aqueduct Construction to Guarantee Drinking WaterConstrucción obligatoria de acueducto para garantizar agua potable

View document ↓ Ver documento ↓ View original source ↗ Ver fuente original ↗

Loading…Cargando…

OutcomeResultado

GrantedCon lugar

The Chamber ordered AyA and ICE to coordinate the construction and implementation, within ten months, of the three-phase power line and aqueduct required to provide drinking water to Purires.La Sala ordenó a AyA y al ICE coordinar la construcción e implementación, dentro de diez meses, de la línea trifásica y del acueducto necesarios para brindar agua potable a Purires.

SummaryResumen

The Constitutional Chamber granted an amparo filed by a Purires resident over the delay in providing drinking water to the community. It recognized access to water as a fundamental right connected to human life and health, although service may be conditioned on compliance with general requirements and the existence of material and technical capacity. AyA had conducted studies, identified water sources, and assessed alternatives since 2008, but nearly three years later no definitive solution existed. The selected alternative required pumping equipment and a three-phase power line that did not exist between Ojo de Agua de Puriscal and Purires. Given the elapsed time and the essential nature of the service, the Chamber ordered AyA and ICE to coordinate immediately so that the three-phase line and aqueduct would be constructed and put into operation within ten months. It also ordered AyA to pay costs and compensation for the resulting damages.La Sala Constitucional declaró con lugar el amparo interpuesto por una vecina de Purires ante la demora en dotar de agua potable a esa comunidad. Reconoció que el acceso al agua es un derecho fundamental vinculado con la vida y la salud, aunque su prestación puede condicionarse al cumplimiento de requisitos generales y a la existencia de capacidad material y técnica. AyA había realizado estudios, identificado fuentes y evaluado alternativas desde 2008, pero casi tres años después aún no existía una solución definitiva. La alternativa seleccionada requería equipos de bombeo y una línea eléctrica trifásica inexistente entre Ojo de Agua de Puriscal y Purires. Debido al tiempo transcurrido y al carácter esencial del servicio, la Sala ordenó a AyA y al ICE coordinar inmediatamente la construcción e implementación de la línea trifásica y del acueducto dentro de diez meses. Además, condenó a AyA al pago de costas, daños y perjuicios.

Key excerptExtracto clave

Accordingly, taking into consideration the time elapsed since the relevant technical assessments began, and in order to prevent the requesting communities from continuing to lack drinking-water service, this constitutional action must be granted, ordering the Costa Rican Institute of Aqueducts and Sewers and the Costa Rican Electricity Institute to establish the necessary coordination so that the three-phase power line and the aqueduct supplying drinking water to the community of Purires are constructed and put into operation within ten months following notice of this judgment. The amparo is granted. Víctor Calvo Balma, in his capacity as Director of the Central Western Region of the Costa Rican Institute of Aqueducts and Sewers, and Ileana Camacho Rodríguez, in her capacity as Special Judicial Representative of the Costa Rican Electricity Institute, or whoever holds their positions, are ordered immediately to initiate the coordination procedures falling within their respective spheres of authority, so that within ten months from notice of this judgment the three-phase power line between the communities of Ojo de Agua de Puriscal and Purires is constructed and put into operation, together with the aqueduct required to provide drinking-water service in Purires.De tal forma, tomando en consideración el tiempo transcurrido desde el inicio de las evaluaciones técnicas pertinentes, y con el propósito de evitar que las comunidades requirentes continúen ayunas del servicio de agua potable, se impone declarar con lugar esta acción de garantía, ordenando al Instituto Costarricense de Acueductos y Alcantarillados y al Instituto Costarricense de Electricidad, establecer las coordinaciones pertinentes para que la línea trifásica y el acueducto para dotar de agua potable a la comunidad de Purires, sean construidos e implementados en el transcurso de los diez meses siguientes a la notificación de esta sentencia. Se declara con lugar el recurso. Se ordena a Víctor Calvo Balma, en su condición de Director de la Región Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados, y a Ileana Camacho Rodríguez, en su condición de Apoderada Especial Judicial del Instituto Costarricense de Electricidad, o a quienes ocupen sus cargos, que de inmediato interpongan las instancias de coordinación que se encuentren dentro de sus ámbitos de competencia, para que dentro del plazo de diez meses contados a partir de la notificación de esta sentencia se construya e implemente la línea eléctrica de configuración trifásica ente las comunidades de Ojo de Agua de Puriscal y Purires, así como el acueducto para prestar el servicio de agua potable en la localidad de Purires.

Pull quotesCitas destacadas

  • "La jurisprudencia de la Sala es reiterada en reconocer el denominado derecho fundamental al agua, por el cual debe concederse a todas las personas la posibilidad de acceder en condiciones de igualdad a los servicios de agua potable, toda vez que la misma resulta esencial para la vida y la salud humanas."

    "The Chamber's case law has consistently recognized the fundamental right to water, under which every person must be afforded the possibility of equal access to drinking-water services, since water is essential to human life and health."

    Considerando II

  • "La jurisprudencia de la Sala es reiterada en reconocer el denominado derecho fundamental al agua, por el cual debe concederse a todas las personas la posibilidad de acceder en condiciones de igualdad a los servicios de agua potable, toda vez que la misma resulta esencial para la vida y la salud humanas."

    Considerando II

  • "No obstante, este carácter de derecho fundamental no implica un acceso irrestricto a los servicios de agua, ya que la administración válidamente puede establecer requisitos generales de necesario cumplimiento por cada solicitante para valorar su particular requerimiento."

    "Nevertheless, its status as a fundamental right does not entail unrestricted access to water services, because the administration may validly establish general requirements that each applicant must satisfy so that the particular request can be assessed."

    Considerando II

  • "No obstante, este carácter de derecho fundamental no implica un acceso irrestricto a los servicios de agua, ya que la administración válidamente puede establecer requisitos generales de necesario cumplimiento por cada solicitante para valorar su particular requerimiento."

    Considerando II

  • "Se entiende entonces, que si bien existe un derecho fundamental al agua que puede ser exigido a la administración correspondiente, la prestación del servicio bien puede sujetarse al cumplimiento de los requisitos establecidos para su otorgamiento y a que exista posibilidad material de suministro."

    "It follows that, although there is a fundamental right to water enforceable against the responsible administration, provision of the service may be subject to compliance with the established requirements and to the material feasibility of supply."

    Considerando II

  • "Se entiende entonces, que si bien existe un derecho fundamental al agua que puede ser exigido a la administración correspondiente, la prestación del servicio bien puede sujetarse al cumplimiento de los requisitos establecidos para su otorgamiento y a que exista posibilidad material de suministro."

    Considerando II

  • "En este sentido, es claro que la autoridad recurrida fue cumpliendo de manera paulatina los diferentes pasos que técnicamente debía realizar para definir la viabilidad y el tipo de obras para implementar un acueducto para la comunidad de Purires que cumpliera con los estándares de calidad y potabilidad requeridos por el Instituto Costarricense de Acueductos y Alcantarillados."

    "In this regard, it is clear that the respondent authority gradually completed the different technical steps required to determine the feasibility and type of works needed for an aqueduct serving Purires that would meet the quality and potability standards required by the Costa Rican Institute of Aqueducts and Sewers."

    Considerando III

  • "En este sentido, es claro que la autoridad recurrida fue cumpliendo de manera paulatina los diferentes pasos que técnicamente debía realizar para definir la viabilidad y el tipo de obras para implementar un acueducto para la comunidad de Purires que cumpliera con los estándares de calidad y potabilidad requeridos por el Instituto Costarricense de Acueductos y Alcantarillados."

    Considerando III

Full documentDocumento completo

Sections

Procedural marks

SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, at nine twenty-one a.m. on January twenty-eighth, two thousand eleven.

Application for amparo relief (recurso de amparo) filed by Marlen Agüero Jiménez, of legal age, holder of identity card number 1-985-107, against the Instituto Costarricense de Acueductos y Alcantarillados.

Background 1-. In a brief received by the Court Clerk’s Office at three fifty-nine p.m. on November 17, 2009, the applicant filed an application for amparo relief, alleging a violation of her right to potable water. She states that on April 21, 2008, residents of the community of Purires requested that the Dirección Regional Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados provide them with potable-water service. In response to that request, the Directorate required the appointment of a community representative, which was done. She adds that in the first week of July 2008m, technical personnel from the Instituto conducted a field visit and identified possible water intake points, but the recommendations of those officials remain unknown to date. She further states that on September first, 2008, they submitted another request indicating that a viable short-term solution would be to construct a tank and pump the water from there to the communities.

That request was answered by means of an official letter dated October 27 of the same year, explaining that the potable-water problem in that area could not be resolved quickly. Accordingly, on the following December 4, the residents sent another communication reiterating that the tank solution could indeed be implemented within a few months and urging that the problem be resolved. She indicates that the situation even warranted the intervention of the Defensoría de los Habitantes, which found that the ICAA was indeed taking steps to resolve the matter. She mentions that in September 2009, the Instituto announced the commencement of works to supply potable water in the metropolitan area and Puerto Viejo de Limón, but the projects initiated did not include the commitment undertaken by the Dirección Regional Central Oeste, and they therefore continue without having the service installed. She requests that the application be granted.

  1. 2In a brief received by the Court Clerk’s Office at three twenty-seven p.m. on December 9, 2009 (folio 32), Leonel Coto Brenes, Director de la Región Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados, reported under oath that, pursuant to the decision adopted by the Junta Directiva del Instituto on October 30, 2007, the administration of the Purires aqueduct was assumed in March 2008 because the ASADA was unable to provide that community or neighboring communities with water meeting the potability standards provided by the Instituto. Consequently, on June 25, 2008, the residents were informed that a field inspection would be conducted to determine the actual condition of the supply system; its findings are set forth in a report dated July 17, 2009, which reflects the actual conditions of each operating system when its administration was transferred. He explains that the recommendation or possibility of constructing a tank, proposed by the residents in a note dated September first, 2008, is wholly unrelated to any directive issued by the Instituto, and therefore such works cannot be considered without the necessary studies and budgetary allocation.Accordingly, on October 27 of the same year, the affected residents were officially informed that a solution to the problem would have to await the completion of preliminary studies to quantify the project’s implementation, the funding for which would be included in the 2009 Investment Budget; this did not mean that the project would be carried out during that period, given both economic and technical constraints. Thus, since October 17, 2009, the project’s inclusion in the Instituto’s Investment Plan has been requested in order to determine what improvements must be made and quantify them, so that the physical execution of the works may be included in the corresponding budgetary allocation. Regarding the metropolitan-area and Puerto Viejo projects, he explains that they date from 2004 and were not formalized until 2007, but improvements to the supply system for the communities of Purires, Camino Los Pérez, and Quebrada La Plata cannot be included in that project because those systems were not transferred to the Instituto until March 2008.He states that assuming the administration of a rural or municipal aqueduct requires a reasonable period to bring the service into legal and technical-operational compliance, including the preparation of preliminary technical studies, such as engineering and environmental reports, the preparation of plans, water laboratory studies, the performance of physical works, the conduct of censuses, and the inclusion and amendment of budgetary allocations, some of which even fall outside the institution’s authority. For that reason, he considers that the administrative action cannot be deemed delayed, because the physical measures began to be implemented following the Initial Report of February 4, 2008. He requests that the application be denied.
  2. 3By a ruling of this Court issued at one forty-seven p.m. on November 25, 2010 (folio 110), the Director de la Región Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados was requested to provide additional evidence for adjudication.
  3. 4In a brief received by the Court Clerk’s Office at three thirty-two p.m. on December 2, 2010 (folio 111), Víctor Calvo Balma, Director de la Región Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados, reported under oath that the construction and development of the aqueduct required to supply the community of Purires was not included in the 2010 budget. He reiterates that a solution to the potable-water supply problem affecting that community must await the completion of preliminary studies so that the implementation of a project capable of meeting the area’s basic needs can be quantified. He indicates that, as previously reported to the Court, the implementation of those studies was included in this year’s investment budget, and the document entitled Informe Técnico Preliminar del Proyecto de Abastecimiento de las Comunidades de San Pablo de Turrubares was issued. He states that this report covers the basic studies required to determine the necessary infrastructure works and the investment cost of an aqueduct capable of comprehensively supplying the communities of Purires, Calle Los Pérez, and the Quebrada La Plata sector.He explains that there are two alternatives for this purpose, but both require the installation of a pumping system, which presents the difficulty that there are no three-phase electrical transmission lines in the area, the nearest being twelve kilometers away. For that reason, by official letter CCO-OM-2010-125, the Dirección de Planificación y Desarrollo de la Región Central del Instituto Costarricense de Electricidad was asked to state whether there was any investment plan providing for the extension of three-phase lines from Ojo de Agua de Puriscal to San Pablo de Turrubares, as well as a possible completion timeframe. In response to this request, the Instituto Costarricense de Electricidad stated that construction of the Garita-Turrubares project was scheduled for 2012 and that the project did include a three-phase electrical line, provided that budgetary conditions allowed it. Regarding the applicant’s service, he states that her home is supplied through NIS 5337373, provides the location number, and indicates that billing is in the name of Sigifredo Jiménez Agüero; he notes that this service has been included in the OPEN Integrated Commercial System since March 10, 2008, under a special residential rate.
  4. 5By a ruling of this Court issued at eleven ten a.m. on December 7, 2010 (folio 140), the Presidente Ejecutivo del Instituto Costarricense de Electricidad was requested to provide additional evidence for adjudication.
  5. 6In a brief received by the Court Clerk’s Office at five p.m. on December 22, 2010 (folio 144), Ileana Camacho Rodríguez, general judicial attorney-in-fact of the Instituto Costarricense de Electricidad, reported under oath that construction of a thirty-four-kilometer three-phase circuit between Ojo de Agua de Puriscal and San Pablo de Turrubares was scheduled for the second half of 2011. She states that although this work had been scheduled for completion in 2012 with BID IV financing, in November 2010 it was agreed that it would be carried out that same year with ICE financing. Regarding the possibility of providing the ICAA with three-phase electrical power to operate pumping equipment in the communities of Ojo de Agua de Puriscal, San Pablo de Turrubares, and Purires, she indicates that a three-phase line currently exists in Ojo de Agua, but not in Purires or San Pablo de Turrubares. Consequently, the only option would be for the ICAA to contract for construction of the works, including financing the materials, in which case the ICE would provide assistance with the project’s design, topographic staking, and inspection. She requests that the application be denied.
  6. 7The legal requirements have been observed in the proceedings conducted.

Justice Ulate Chacón drafted the opinion; and,

Considerations

I. Proven facts. The following facts are deemed duly established and relevant to the determination of this matter

1. Pursuant to Article 6, subsection d), of ordinary session number 2007-066 of the Junta Directiva del Instituto Costarricense de Acueductos y Alcantarillados, held on October 30, 2007, it was agreed that the administration, operation, maintenance, and development of the San Pablo and San Pedro de Turrubares aqueduct system would be assumed through the Dirección Regional Central Oeste del Instituto (folio 61).

2. The Instituto Costarricense de Acueductos y Alcantarillados assumed administration of the San Pedro and San Pablo de Turrubares aqueduct beginning in March 2008 (folio 34).

3. By a note dated April 21, 2008, received by the Instituto Costarricense de Acueductos y Alcantarillados on June 11 of the same year, residents of Purires requested that the Dirección Regional Central Oeste del Instituto provide them with potable-water service, just as it had been provided to the community of San Pablo, in view of the transfer of the ASADA de Turrubares aqueduct to the Instituto (folio 41).

4. By official letter number CCO 2008-157, dated June 25, 2008, the Dirección Regional Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados informed the residents of Purires that technical personnel would be sent to assess the case and determine the most viable alternative for improving the quality of the water service (folio 42).

5. By a note dated September first, 2008, residents of Purires reiterated to the Dirección Regional Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados their request for potable-water service provided by the Instituto and suggested what they considered a possible solution (folio 46).

6. On 17 de octubre de 2008, through an internal request within the Instituto Costarricense de Acueductos y Alcantarillados, it was proposed that the Purires, San Pedro Especial, and San Pablo Especial water-supply systems be included in the 2009 basic studies and designs program, with the intention that the resources necessary to construct the proposed works be allocated for 2010 (folio 49).

7. By official letter number CCO-2008-240 from the Dirección Regional Central Oeste of the Instituto Costarricense de Acueductos y Alcantarillados, dated 27 de octubre de 2008, the residents of Purires were informed that the water-supply system had been included in the 2009 investment budget for the preparation of basic studies, plans, and specifications, after which it would be included in the construction program (folio 50).

8. By a letter dated 4 de diciembre de 2008, received by the Instituto Costarricense de Acueductos y Alcantarillados on 17 de diciembre de 2008, residents of the Purires community reiterated to the Instituto their request for potable water service and what they believed should be done to solve the problem (folio 55).

9. Report number IT-RCOM-2009-02 of the Instituto Costarricense de Acueductos y Alcantarillados, dated 17 de junio de 2009, identifies the sources that may be used for the Purires and Calle Pérez water-supply systems (folio 43).

10. The construction and development of the water-supply system serving the Purires community was not included in the 2010 budget (folio 111).

11. By official letter number CCO-OM-2010-125, dated 3 de agosto de 2010, the Dirección de la Región Central Oeste of the Instituto Costarricense de Acueductos y Alcantarillados requested information from the Director de Planificación y Desarrollo de la Región Central de Alajuela of the Instituto Costarricense de Electricidad concerning the existence of an investment plan and implementation period for extending a three-phase branch line from Ojo de Agua de Puriscal to San Pablo de Turrubares (folio 118).

12. By official letter number 1300-768-2010 from the Área de Desarrollo RC of the Instituto Costarricense de Electricidad, dated 19 de agosto de 2010, the Dirección de la Región Central Oeste of the Instituto Costarricense de Acueductos y Alcantarillados was informed that construction of a three-phase line between Ojo de Agua in Puriscal and San Pablo de Turrubares was scheduled for 2010, budgetary conditions permitting (folio 116).

13. In octubre de 2010, the Subgerencia Ambiental, Investigación y Desarrollo of the Instituto Costarricense de Acueductos y Alcantarillados issued the Technical Report “Water Supply Project for the San Pablo de Turrubares Communities,” concluding that there were two alternative solutions to the problem of supplying potable water to the affected communities, as well as a third possibility that would solve the problem in Calle Pérez (folios 119, 138 y 139).

14. A three-phase line currently exists in the Ojo de Agua de Puriscal community, but not in Purires or San Pablo de Turrubares (folio 146).

15. The Instituto Costarricense de Electricidad will construct a three-phase circuit between Ojo de Agua de Puriscal and San Pablo de Turrubares during the second half of 2011 (folio 145).

II.The right to water and the requirements applicable to requests for water service. The Sala has consistently recognized the so-called fundamental right to water, under which all persons must be afforded the opportunity to access potable water services on equal terms, since water is essential to human life and health. Nevertheless, its status as a fundamental right does not entail unrestricted access to water services, because the public administration may validly establish general requirements that each applicant must meet so that the applicant’s particular request may be assessed. Thus, in judgment number 2006-1898, issued at nueve horas cincuenta y tres minutos on 17 de febrero de 2006—and reiterated, among others, in judgments numbers 2007-13310, issued at diez horas cincuenta y siete minutos on 14 de setiembre de 2007, and 2008-16311, issued at diecisiete horas treinta minutos on 30 de octubre de 2008—the Sala held:

“The appellant (recurrente) alleges (…) that, despite the requests and efforts made, the respondent Instituto has refused to provide them with potable water service, arguing that it is an informal settlement (precario) and that its inhabitants do not have a segregation plan (plano de segregación) establishing that they own the properties. In this regard, the case record establishes, on the basis of the report submitted under oath by the respondent authority, that potable water service cannot be installed in individual homes in the community where the appellant resides for two specific reasons: the lack of adequate infrastructure and the interested parties’ failure to submit applications meeting the legal requirements (...). In judgment No. 2004-12185, issued at 13:31 horas on 29 de octubre del 2004, in a case similar to this one, this Sala stated that the Instituto Costarricense de Acueductos y Alcantarillados could not be compelled to disregard the provisions of its Reglamento de Prestación de Servicios a los Clientes or the Ley General de Agua Potable.

Therefore, unless the protected party (amparado) satisfies the conditions and requirements established therein, regular service cannot be provided to him, even though potable water service must be accessible to everyone because it is an essential service. Given the existence of those two objective reasons why regular potable water service cannot be supplied to the claimant (accionante)—his failure to meet the requirements for connecting a new service, beginning with the submission of an application, and the lack of adequate infrastructure in the area—there is no basis for concluding that the respondent Instituto’s refusal to provide regular service is due to the fact that the protected party and his neighbors lack title to the properties they possess. It should also be added that, under article 33 of the aforementioned Reglamento, the lack of title does not appear to be an obstacle to requesting the connection of new potable water service, provided that the requirements specified in that provision are met.

In any event, it has also been established that, although regular potable water service has not been supplied, the appellant and the other residents have access to a public standpipe (fuente pública) installed by the Instituto so that they can obtain water for their basic needs. Accordingly, this Tribunal finds that it was the failure of the appellant and the local residents themselves—who have not shown that they submitted applications for the installation of new potable water service in the community where they reside—that prevented their situation from being assessed to determine whether, upon compliance particularly with the requirements of article 33 of the Reglamento de Prestación de Servicios a los Clientes, the infrastructure limitations could be overcome in their case and regular potable water service could be provided to them.” It is therefore understood that, although there is a fundamental right to water that may be asserted against the corresponding public administration, provision of the service may properly be made subject to compliance with the requirements established for granting it and to the material feasibility of supplying it; that is, there must be no technical circumstances that prevent or counsel against the public administration’s provision of potable water service.

Consequently, the public administration is under no obligation to provide potable water service where technical reasons counsel against or prevent it from doing so, but it must adequately inform the applicant of the reasons why the request cannot be granted.

III.The specific case. The situation of the protected petitioner (amparada). From a review of the record (autos) and the report submitted under oath, the Chamber finds it established that, beginning in March 2008, the Instituto Costarricense de Acueductos y Alcantarillados assumed the administration, operation, maintenance, and development of the San Pablo and San Pedro de Turrubares water-supply system (acueducto), which until then had been the responsibility of the local ASADA. Following that transfer of the administration and operation of the water-supply system, on 11 de junio de 2008 the residents of the community of Purires requested that the Instituto’s Dirección Regional Central Oeste also provide them with drinking-water service, as had been done for the community of San Pablo. The respondent administration addressed that request by means of an official letter dated 25 de junio siguiente, informing the residents of Purires that technical personnel would be sent to assess the case and determine the most viable alternative for improving the quality of drinking-water service.

This is because, as reported, the administration must conduct the relevant technical studies to determine the actual condition of the water-supply system, the improvements that must be made, its service capacity, and, of course, the preparation of action plans, the corresponding budget allocation, and, finally, the physical execution of the works, all of which, by their very nature, cannot be completed immediately but instead constitute a process carried out in stages. The residents of that community reiterated their request in a letter dated primero de setiembre de 2008, suggesting what they considered a possible solution for the prompt provision of service. Meanwhile, the Instituto continued with the internal procedures previously announced to the applicants, and therefore, on 17 de octubre de 2008, an internal request was made to include the Purires water-supply system in the 2009 basic studies and designs program, with the intention of allocating the resources necessary for its construction in 2010.

Additionally, on 27 de octubre siguiente, a further response was provided to the residents, specifically informing them of the steps being taken internally to determine which works had to be carried out. Thus, it was not until 17 de junio de 2009 that, in response to the request for studies, a technical report was issued identifying the water sources that could be used for the Purires and Calle Pérez water-supply systems and determining that those waters could not be made potable using chlorine. In this regard, it is clear that the respondent authority gradually completed the various steps technically required to determine the feasibility and type of works needed to implement a water-supply system for the community of Purires that would meet the quality and potability standards required by the Instituto Costarricense de Acueductos y Alcantarillados. However, the corresponding assessments have now taken nearly three years, and no definitive option exists to date, since it is now reported that a three-phase electrical line is required to permit installation of the necessary pumping equipment, which in turn requires the intervention of the Instituto Costarricense de Electricidad, because no line with that configuration currently exists and, consequently, the solution contemplated by the ICAA cannot be implemented.

In this regard, ICE reports that such a three-phase line does exist, but only in the community of Ojo de Agua de Puriscal, and not from that locality to Purires and San Pablo de Turrubares; that extension is included in the infrastructure plans for the second half of the year. Accordingly, at this precise time, the only option available to the ICAA for providing drinking-water service to those communities within a reasonable period is for the ICAA itself to contract for construction of the works, for which purpose ICE undertakes to assist with the project’s design, topographic staking, and inspection. Therefore, considering the time elapsed since the relevant technical assessments began, and in order to prevent the requesting communities from continuing to lack drinking-water service, this constitutional protection action (acción de garantía) must be granted, ordering the Instituto Costarricense de Acueductos y Alcantarillados and the Instituto Costarricense de Electricidad to establish the necessary coordination so that the three-phase line and the water-supply system needed to provide drinking water to the community of Purires are constructed and implemented within the ten months following notification of this judgment.

Por tanto

The amparo petition (recurso) is granted. Víctor Calvo Balma, in his capacity as Director of the Región Central Oeste of the Instituto Costarricense de Acueductos y Alcantarillados, and Ileana Camacho Rodríguez, in her capacity as Apoderada Especial Judicial of the Instituto Costarricense de Electricidad, or whoever holds their respective offices, are ordered to immediately initiate the coordination procedures falling within their respective spheres of authority so that, within ten months from notification of this judgment, the three-phase electrical line between the communities of Ojo de Agua de Puriscal and Purires, as well as the water-supply system for providing drinking-water service in the locality of Purires, are constructed and implemented. Víctor Calvo Balma and Ileana Camacho Rodríguez, or whoever holds their respective offices, are warned that failure to comply with this order will constitute the offense of disobedience and that, pursuant to Article 71 of the Law governing this jurisdiction, anyone who receives an order issued in an amparo proceeding (recurso de amparo) that must be complied with or enforced and fails to comply with or enforce it shall be sentenced to imprisonment for three months to two years, or a fine of twenty to sixty days, provided that the offense is not subject to a more severe penalty.

The Instituto Costarricense de Acueductos y Alcantarillados is ordered to pay the costs, damages, and losses caused by the facts underlying this ruling, the amounts of which shall be determined during enforcement of the judgment (ejecución de sentencia) before the contentious-administrative courts (vía contencioso administrativo). This judgment shall be personally served on Víctor Calvo Balma, in his capacity as Director of the Región Central Oeste of the Instituto Costarricense de Acueductos y Alcantarillados, and on Ileana Camacho Rodríguez, in her capacity as Apoderada Especial Judicial of the Instituto Costarricense de Electricidad, or whoever holds their respective offices. Let notice be given.- Ana Virginia Calzada M.

Presiding Justice Gilbert Armijo S.

Fernando Cruz C.

Fernando Castillo V.

Rosa Esmeralda Blanco M.

Roxana Salazar C.

Enrique Ulate C.

Secciones

Marcadores

SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas y veintiuno minutos del veintiocho de enero del dos mil once.

Recurso de amparo presentado por Marlen Agüero Jiménez, mayor, portadora de la cédula de identidad número 1-985-107, contra el Instituto Costarricense de Acueductos y Alcantarillados.

Resultando

1-. Por escrito recibido en la Secretaría de la Sala a las quince horas cincuenta y nueve minutos del 17 de noviembre de 2009, la recurrente presenta recurso de amparo aduciendo violación a su derecho al agua potable. Señala que el 21 de abril de 2008, vecinos de la comunidad de Purires solicitaron a la Dirección Regional Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados que se les suministrara el servicio de agua potable. Ante esa petición, la Dirección requirió que se nombrara a un representante de la comunidad, lo cual se hizo. Agrega que en la primera semana de julio de 2008m, personal técnico del Instituto realizó una visita de campo, determinando las posibles tomas de agua, pero a la fecha se desconoce las recomendaciones de esos funcionarios. Añade que el primero de setiembre de 2008, remitieron una nueva solicitud indicando que una solución viable a corto plazo sería la construcción de un tanque y desde allí bombear el líquido a las comunidades.

Esa gestión fue respondida mediante oficio del 27 de octubre del mismo año, explicándoles que la solución al problema de agua potable en esa zona no se podía resolver en poco tiempo. Es por ello que el 4 de diciembre siguiente, los vecinos enviaron una nueva comunicación reiterando que la solución del tanque sí podía realizarse en pocos meses, por lo que instaban la solución al problema. Indica que la situación incluso ameritó la intervención de la Defensoría de los Habitantes, entidad que consideró que el ICAA sí estaba realizando los trámites para solventar el tema. Menciona que en setiembre de 2009, el Instituto anunció el inicio de obras para el abastecimiento de agua potable en el área metropolitana y Puerto Viejo de Limón, pero dentro de los proyectos que iniciaron no se detalló el compromiso adquirido por la Dirección Regional Central Oeste, por lo que continúan sin que se les instale el servicio. Solicita declarar con lugar el recurso.

  1. 2Mediante escrito recibido en la Secretaría de la Sala a las quince horas veintisiete minutos del 9 de diciembre de 2009 (folio 32), informa bajo fe de juramento Leonel Coto Brenes, Director de la Región Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados, quien señala que según lo dispuesto por la Junta Directiva del Instituto el 30 de octubre de 2007, se asumió la administración del acueducto de Purires en marzo de 2008, esto por la incapacidad de la ASADA, quien no brindaba a dicha comunidad ni a otras vecinas, la calidad de potabilidad que brinda el Instituto. Por eso, el 25 de junio de 2008 se comunicó a los vecinos que se realizaría una inspección de campo para determinar la situación real del sistema de abastecimiento, cuyo resultado consta en un informe de 17 de julio de 2009, el cual refleja las condiciones reales en que se encontraba cada sistema operativo al momento del traspaso de la administración.Explica que la recomendación o posibilidad de construir un tanque, planteada por los vecinos mediante nota del primero de setiembre de 2008, es totalmente ajena a cualquier disposición emitida por el Instituto, por lo que no se puede considerar realizar esas obras sin los estudios y el contenido presupuestario necesario. Por eso, el 27 de octubre del mismo año, se comunica oficialmente a los administrados, que la solución al problema debe esperar hasta la realización de los estudios previos, para cuantificar la implementación del proyecto, cuyo contenido sería incluido en el Presupuesto de Inversión de 2009, lo que no significa que el proyecto se ejecutaría en ese período, tanto por imposibilidad económica como técnica. Así, desde el 17 de octubre de 2009, se solicitó la inclusión del proyecto en el Plan de Inversión del Instituto, para determinar qué tipo de mejoras se debe efectuar, así como su cuantificación, de manera que la ejecución material se pueda incluir en el contenido presupuestario respectivo.Sobre los proyectos del área metropolitana y Puerto Viejo, explica que los mismos datan de 2004, y fue hasta el 2007 que logró formalizarse, pero en el mismo no puede incluirse las mejoras en el sistema de abastecimiento de las comunidades de Purires, Camino Los Pérez y Quebrada La Plata, porque fue hasta marzo de 2008 que pasaron al Instituto. Afirma que el asumir la administración de un acueducto rural o municipal, conlleva un tiempo prudencial para ajustar el servicio de manera legal y técnica-operativa, lo que incluye la elaboración de los estudios técnicos preliminares, como los informes de ingeniería y ambientales, la constitución de planos, los estudios de laboratorio de aguas, la ejecución de obras materiales, la realización de censos, inclusiones y modificaciones de contenidos presupuestarios, los cuales son incluso competencia ajena a la institución. Es por esa razón que estima que no se puede juzgar que la actuación administrativa haya sido retardada, porque desde el Informe Inicial de 4 de febrero de 2008, se comenzaron a concretar las actuaciones materiales. Solicita declarar sin lugar el recurso.
  2. 3Por resolución de esta Sala, de las trece horas cuarenta y siete minutos del 25 de noviembre de 2010 (folio 110), se solicita prueba para mejor resolver al Director de la Región Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados.
  3. 4Mediante escrito recibido en la Secretaría de la Sala a las quince horas treinta y dos minutos del 2 de diciembre de 2010 (folio 111), informa bajo fe de juramento Víctor Calvo Balma, Director de la Región Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados, quien señala que la construcción y desarrollo del acueducto necesario para abastecer la comunidad de Purires no fue incluido en el presupuesto del año 2010. Reitera que la solución al problema de abastecimiento de agua potable que se presenta en esa comunidad, debe esperar a que se ejecuten los estudios previos, para poder cuantificar la implementación de un proyecto que permita cubrir las necesidades básicas de la zona. Indica que tal como se informó previamente a la Sala, la implementación de esos estudios se incluyó en el presupuesto de inversión de este año, y se emitió el denominado Informe Técnico Preliminar del Proyecto de Abastecimiento de las Comunidades de San Pablo de Turrubares.Afirma que este informe contempla los estudios básicos para determinar las obras de infraestructura requeridas y el costo de la inversión de un acueducto que permita de forma integral abastecer a las comunidades de Purires, Calle Los Pérez y el sector de Quebrada La Plata. debe instaurarse un sistema de bombeo, lo cual tiene el inconveniente de que no existe en la zona líneas de transmisión eléctrica en configuración trifásica, pues la más cercana se encuentra a doce kilómetros de distancia. Es por esta razón, que mediante oficio CCO-OM-2010-125, se solicitó a la Dirección de Planificación y Desarrollo de la Región Central del Instituto Costarricense de Electricidad, pronunciarse sobre la existencia de algún plan de inversión que contemple la extensión de líneas trifásicas desde la localidad de Ojo de Agua de Puriscal hasta San Pablo de Turrubares, así como un posible plazo de ejecución.A esta solicitud, el Instituto Costarricense de Electricidad respondió que para el año 2012 se tiene programada la construcción del proyecto Garita-Turrubares, que sí contempla una línea eléctrica trifásica, siempre y cuando las condiciones presupuestarias lo permitan. Sobre el servicio de la recurrente, manifiesta que su vivienda se abastece del NIS 5337373, indica el número de localización y que se factura a nombre de Sigifredo Jiménez Agüero; refiere que este servicio se incluyó en el Sistema Comercial Integrado OPEN desde el 10 de marzo de 2008, con tarifa especial domiciliar.
  4. 5Por resolución de esta Sala de las once horas diez minutos del 7 de diciembre de 2010 (folio 140), se solicita prueba para mejor resolver al Presidente Ejecutivo del Instituto Costarricense de Electricidad.
  5. 6Mediante escrito recibido en la Secretaría de la Sala a las diecisiete horas del 22 de diciembre de 2010 (folio 144), informa bajo fe de juramento Ileana Camacho Rodríguez, apoderada general judicial del Instituto Costarricense de Electricidad, quien señala que se tiene programada la construcción de un circuito trifásico entre Ojo de Agua de Puriscal y San Pablo de Turrubares para el segundo semestre de 2011, con una extensión de treinta y cuatro kilómetros. Afirma que a pesar que esta obra estaba prevista a realizarse con financiamiento BID IV para el año 2012, en noviembre de 2010 se acordó ejecutarla con financiamiento ICE para este mismo año. Con respecto a las posibilidades para que el ICAA pueda contar con energía en configuración trifásica para operar equipos de bombeo en las comunidades de Ojo de Agua de Puriscal, San Pablo de Turrubares y Purires, indica que actualmente se cuenta con línea trifásica en Ojo de Agua, pero no en Purires ni San Pablo de Turrubares, por lo que la única opción sería que el ICAA contratara la construcción de la obra, incluyendo el financiamiento de los materiales, y en ese caso el ICE brindaría su colaboración para el diseño, marcación topográfica e inspección del proyecto. Solicita declarar sin lugar el recurso.
  6. 7En los procedimientos seguidos se ha observado las prescripciones legales.

Redacta el Magistrado Ulate Chacón; y,

Considerando

I.Hechos probados. De importancia para la decisión de este asunto, se estiman como debidamente demostrados los siguientes hechos:

1. Mediante artículo 6, inciso d), de la sesión ordinaria de la Junta Directiva del Instituto Costarricense de Acueductos y Alcantarillados, número 2007-066, de 30 de octubre de 2007, se acordó asumir la administración, operación, mantenimiento y desarrollo del sistema de acueducto de San Pablo y San Pedro de Turrubares, a través de la Dirección Regional Central Oeste del Instituto (folio 61).

2. El Instituto Costarricense de Acueductos y Alcantarillados asumió la administración del acueducto de San Pedro y San Pablo de Turrubares a partir de marzo de 2008 (folio 34).

3. Mediante nota de 21 de abril de 2008, recibida por el Instituto Costarricense de Acueductos y Alcantarillados el 11 de junio del mismo año, vecinos de Purires solicitan a la Dirección Regional Central Oeste del Instituto, que en virtud del traspaso del acueducto de la ASADA de Turrubares al Instituto, se les suministre el servicio de agua potable al igual que se le facilitó a la comunidad de San Pablo (folio 41).

4. Por oficio número CCO 2008-157, de 25 de junio de 2008, la Dirección Regional Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados, comunica a los vecinos de Purires que se enviará personal técnico para valorar el caso y determinar la alternativa más viable para mejorar la calidad del servicio de agua (folio 42).

5. Mediante nota de primero de setiembre de 2008, vecinos de Purires reiteran a la Dirección Regional Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados la solicitud de contar con el servicio de agua potable provisto por el Instituto y sugieren lo que estiman como posible solución (folio 46).

6. El 17 de octubre de 2008, mediante solicitud interna dentro del Instituto Costarricense de Acueductos y Alcantarillados, se plantea incluir en el programa de estudios básicos y diseños de 2009, los sistemas de acueducto de Purires, San Pedro Especial y San Pablo Especial, con la intención de que para el año 2010 se asignen los recursos necesarios para la construcción de las obras que se propongan (folio 49).

7. Por oficio de la Dirección Regional Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados, número CCO-2008-240, de 27 de octubre de 2008, se comunica a los vecinos de Purires que el acueducto se incluyó en el presupuesto de inversiones del año 2009, para efectuar los estudios básicos, planos y especificaciones, para luego incluirlos en el programa de construcción (folio 50).

8. Mediante nota de 4 de diciembre de 2008, recibida por el Instituto Costarricense de Acueductos y Alcantarillados el 17 de diciembre de 2008, vecinos de la comunidad de Purires reiteran al Instituto su solicitud del servicio de agua potable y lo que estiman debe hacerse para solucionar el problema (folio 55).

9. El informe del Instituto Costarricense de Acueductos y Alcantarillados, número IT-RCOM-2009-02, de 17 de junio de 2009, identifica las fuentes que pueden ser utilizadas para los acueductos de Purires y Calle Pérez (folio 43).

10. La construcción y desarrollo del acueducto para abastecer la comunidad de Purires no fue incluido en el presupuesto del año 2010 (folio 111).

11. Por oficio número CCO-OM-2010-125, de 3 de agosto de 2010, la Dirección de la Región Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados, solicita al Director de Planificación y Desarrollo de la Región Central de Alajuela, del Instituto Costarricense de Electricidad, información sobre la existencia de un plan de inversión y plazo de ejecución sobre la extensión de un ramal trifásico desde Ojo de Agua de Puriscal hasta San Pablo de Turrubares (folio 118).

12. Mediante oficio del Área de Desarrollo RC del Instituto Costarricense de Electricidad, número 1300-768-2010, de 19 de agosto de 2010, se informa a la Dirección de la Región Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados, que para el año 2010 se encuentra programada la construcción de una línea trifásica entre Ojo de Agua en Puriscal, y San Pablo de Turrubares, si las condiciones presupuestarias lo permiten (folio 116).

13. En octubre de 2010, la Subgerencia Ambiental, Investigación y Desarrollo del Instituto Costarricense de Acueductos y Alcantarillados emite el Informe Técnico “Proyecto de Abastecimiento de las Comunidades San Pablo de Turrubares”, concluyendo que existen dos alternativas de solución al problema de dotación de agua potable en las comunidades afectadas, y una tercera posibilidad que soluciona el problema en la localidad de Calle Pérez (folios 119, 138 y 139).

14. En la actualidad existe línea trifásica en la comunidad de Ojo de Agua de Puriscal, pero no en Purires ni San Pablo de Turrubares (folio 146).

15. El Instituto Costarricense de Electricidad construirá un circuito trifásico entre Ojo de Agua de Puriscal y San Pablo de Turrubares en el segundo semestre de 2011 (folio 145).

II.Sobre el derecho al agua y los requisitos exigibles en la solicitud de servicios de agua. La jurisprudencia de la Sala es reiterada en reconocer el denominado derecho fundamental al agua, por el cual debe concederse a todas las personas la posibilidad de acceder en condiciones de igualdad a los servicios de agua potable, toda vez que la misma resulta esencial para la vida y la salud humanas. No obstante, este carácter de derecho fundamental no implica un acceso irrestricto a los servicios de agua, ya que la administración válidamente puede establecer requisitos generales de necesario cumplimiento por cada solicitante para valorar su particular requerimiento. Así, en sentencia número 2006-1898, de las nueve horas cincuenta y tres minutos del 17 de febrero de 2006 –reiterada, entre otras, por sentencias números 2007-13310, de las diez horas cincuenta y siete minutos del 14 de setiembre de 2007, y 2008-16311, de las diecisiete horas treinta minutos del 30 de octubre de 2008- estableció la Sala que:

“El recurrente alega (…) que pese a las solicitudes y esfuerzos hechos, el Instituto recurrido se ha negado a brindarles el servicio de agua potable aduciendo que se trata de un precario y que sus habitantes no cuentan con un plano de segregación que establezca que son propietarios de los inmuebles. Al respecto, se encuentra acreditado en autos, con base en el informe rendido bajo juramento por la autoridad recurrida, que existe una imposibilidad para instalar servicios de agua potable domiciliaria en la comunidad que habita el recurrente por dos motivos específicos: la falta de una infraestructura adecuada y de presentación de solicitudes con cumplimiento de requisitos legales por parte de los interesados (...). Esta Sala, en la sentencia No. 2004-12185 de las 13:31 horas del 29 de octubre del 2004, en un caso similar al presente, señaló que no era posible obligar al Instituto Costarricense de Acueductos y Alcantarillados a eludir lo dispuesto en su Reglamento de Prestación de Servicios a los Clientes ni en la Ley General de Agua Potable.

De ahí que, en el tanto el amparado, no reúna las condiciones y requisitos ahí exigidos, aunque el servicio de agua potable debe estar al alcance de toda persona por tratarse de un servicio esencial, no se le puede proveer de manera regular. Dada la existencia de esos dos motivos objetivos por los cuales no es posible suministrar un servicio de agua potable regular al accionante: su falta de cumplimiento de requerimientos para la conexión de un servicio nuevo, empezando, por la presentación de la solicitud y la existencia de una infraestructura adecuada en la zona, no existe motivo alguno para entender que la denegatoria de la prestación del servicio regular por parte del Instituto recurrido se deba al hecho que el amparado y sus vecinos no cuentan con títulos de propiedad sobre los inmuebles que poseen. A lo anterior cabe agregar que con base en el artículo 33 del Reglamento referido, la falta de un título de propiedad no parece ser un obstáculo para solicitar la conexión de un servicio nuevo de agua potable, en tanto se cumplan los requerimientos que indica esa norma.

En todo caso, se encuentra acreditado también que aunque no se ha suministrado el servicio regular de agua potable, el recurrente y demás vecinos cuentan con fuente pública que el Instituto instaló para que puedan abastecerse, para sus necesidades básicas. De ahí que considere este Tribunal que ha sido la propia omisión del recurrente y de los vecinos de la localidad, quienes no acreditan haber presentado las solicitudes para la instalación de un servicio nuevo de agua potable en la comunidad donde habitan, la que ha impedido que se valore su situación a efectos de determinar si, cumpliendo, sobre todo los requerimientos del artículo 33 del Reglamento de Prestación de Servicios a los Clientes, las limitaciones de infraestructura pueden ser superadas en su caso y se les puede proveer de un servicio regular de agua potable.” Se entiende entonces, que si bien existe un derecho fundamental al agua que puede ser exigido a la administración correspondiente, la prestación del servicio bien puede sujetarse al cumplimiento de los requisitos establecidos para su otorgamiento y a que exista posibilidad material de suministro, esto es, que no existan situaciones técnicas que imposibiliten o desaconsejen a la administración a brindar el servicio de agua potable, situación que determina que la administración carece de la obligación de prestar el servicio de agua potable en caso de existir razones técnicas que lo desaconsejen o imposibiliten, debiendo informar adecuadamente al gestionante las razones por las cuales no puede atenderse su solicitud.

III.El caso concreto. La situación de la amparada. Del estudio de los autos y del informe rendido bajo fe de juramento, la Sala tiene por acreditado que a partir de marzo de 2008, el Instituto Costarricense de Acueductos y Alcantarillados asumió la administración, operación, mantenimiento y desarrollo del acueducto de San Pablo y San Pedro de Turrubares, el cual hasta entonces era responsabilidad de la ASADA del lugar. Ante ese traspaso en la administración y operación de dicho acueducto, el 11 de junio de 2008 los vecinos de la comunidad de Purires solicitaron a la Dirección Regional Central Oeste del Instituto que también a ellos se les suministrara el servicio de agua potable, tal como se le había facilitado a la comunidad de San Pablo. Esa gestión fue atendida por la administración recurrida mediante oficio del 25 de junio siguiente, informando a los vecinos de Purires que para tales efectos se enviaría personal técnico para valorar el caso y determinar la alternativa más viable para mejorar la calidad del servicio de prestación de agua potable.

Esto es así pues tal como se informa, la administración requiere realizar los estudios técnicos pertinentes para definir la condición real del acueducto, las mejoras que debe introducirse, la capacidad de prestación del servicio, y, por supuesto, la elaboración de los planes de acción, la definición presupuestaria que corresponda, y, finalmente, la ejecución material de las obras, aspectos todos que por su propia naturaleza distan de ser de realización inmediata para ser, por el contrario, un proceso que se cumple por etapas. Los vecinos de esa comunidad reiteraron su petición mediante nota del primero de setiembre de 2008, sugiriendo lo que ellos estimaron como una posible solución para la pronta prestación del servicio. Mientras tanto, el Instituto prosiguió con los trámites internos anunciados a los gestionantes, por lo que el 17 de octubre de 2008 se hizo internamente la petición de incluir el acueducto de Purires en el programa de estudios básicos y diseños del año 2009, con la intención que se asignaran los recursos necesarios para su construcción para el año 2010.

Adicionalmente, el 27 de octubre siguiente se dio nueva respuesta a los vecinos, informándoles precisamente los gestiones que internamente se estaban realizando para determinar las obras que debía ejecutarse. Es así que recién el 17 de junio de 2009, en atención a aquella petición de estudios, se rinde un informe técnico que identifica las fuentes de agua que pueden ser utilizadas para los acueductos de Purires y Calle Pérez, determinando que tales aguas no se pueden potabilizar con cloro. En este sentido, es claro que la autoridad recurrida fue cumpliendo de manera paulatina los diferentes pasos que técnicamente debía realizar para definir la viabilidad y el tipo de obras para implementar un acueducto para la comunidad de Purires que cumpliera con los estándares de calidad y potabilidad requeridos por el Instituto Costarricense de Acueductos y Alcantarillados. Sin embargo, las evaluaciones correspondientes han dilatado ya cerca de tres años, sin que a la fecha exista una opción definitiva, ya que ahora se informa de la necesidad de contar con una línea eléctrica de configuración trifásica que permita la instalación de los equipos de bombeo necesarios, para lo cual se requiere la necesaria intervención del Instituto Costarricense de Electricidad, pues actualmente es inexistente una línea con esa configuración, y, por ende, imposible de implementar la solución prevista por el ICAA.

Sobre el particular, informa el ICE que sí existe tal línea trifásica pero sólo en la comunidad de Ojo de Agua de Puriscal, no así desde esa localidad hacia Purires y San Pablo de Turrubares, extensión que está incluida en los planes de infraestructura para el segundo semestre de año, razón por la cual en este preciso momento, la única opción que tiene el ICAA para en un período razonable brindar el servicio de agua potable en esas comunidades, es que el propio ICAA contrate la construcción de la obra, y para ello el ICE se compromete a prestar su colaboración para el diseño, la marcación topográfica y la inspección del proyecto. De tal forma, tomando en consideración el tiempo transcurrido desde el inicio de las evaluaciones técnicas pertinentes, y con el propósito de evitar que las comunidades requirentes continúen ayunas del servicio de agua potable, se impone declarar con lugar esta acción de garantía, ordenando al Instituto Costarricense de Acueductos y Alcantarillados y al Instituto Costarricense de Electricidad, establecer las coordinaciones pertinentes para que la línea trifásica y el acueducto para dotar de agua potable a la comunidad de Purires, sean construidos e implementados en el transcurso de los diez meses siguientes a la notificación de esta sentencia.

Por tanto

Se declara con lugar el recurso. Se ordena a Víctor Calvo Balma, en su condición de Director de la Región Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados, y a Ileana Camacho Rodríguez, en su condición de Apoderada Especial Judicial del Instituto Costarricense de Electricidad, o a quienes ocupen sus cargos, que de inmediato interpongan las instancias de coordinación que se encuentren dentro de sus ámbitos de competencia, para que dentro del plazo de diez meses contados a partir de la notificación de esta sentencia se construya e implemente la línea eléctrica de configuración trifásica ente las comunidades de Ojo de Agua de Puriscal y Purires, así como el acueducto para prestar el servicio de agua potable en la localidad de Purires. Se advierte a Víctor Calvo Balma e Ileana Camacho Rodríguez, o a quienes ocupen sus cargos, que de no acatar la orden dicha, incurrirá en el delito de desobediencia y, que de conformidad con el artículo 71 de la Ley de esta jurisdicción, se le impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo y no la cumpliere o no la hiciere cumplir, siempre que el delito no esté más gravemente penado.

Se condena al Instituto Costarricense de Acueductos y Alcantarillados al pago de las costas, daños y perjuicios causados con los hechos que sirven de base a esta declaratoria, los que se liquidarán en ejecución de sentencia en la vía contencioso administrativo. Notifíquese esta sentencia a Víctor Calvo Balma, en su condición de Director de la Región Central Oeste del Instituto Costarricense de Acueductos y Alcantarillados, y a Ileana Camacho Rodríguez, en su condición de Apoderada Especial Judicial del Instituto Costarricense de Electricidad, o a quienes ocupen sus cargos, en forma personal. Comuníquese.- Ana Virginia Calzada M.

Presidenta Gilbert Armijo S.

Fernando Cruz C.

Fernando Castillo V.

Rosa Esmeralda Blanco M.

Roxana Salazar C.

Enrique Ulate C.

Document not found. Documento no encontrado.

Implementing decreesDecretos que afectan

    TopicsTemas

    • Water Law — Sources, Setbacks, and ConcessionsLey de Aguas — Fuentes, Retiros y Concesiones

    Concept anchorsAnclajes conceptuales

      Spanish key termsTérminos clave en español

      News & Updates Noticias y Actualizaciones

      All articles → Todos los artículos →

      Weekly Dispatch Boletín Semanal

      Field reporting and policy analysis from Costa Rica's forests. Reportajes y análisis de política desde los bosques de Costa Rica.

      ✓ Subscribed. ✓ Suscrito.

      One email per week. No spam. Unsubscribe in one click. Un correo por semana. Sin spam. Cancela en un clic.

      Or WhatsApp channelO canal de WhatsApp →
      Coalición Floresta © 2026 · All rights reserved © 2026 · Todos los derechos reservados

      Stay Informed Mantente Informado

      Conservation news and action alerts, straight from the field Noticias de conservación y alertas de acción, directo desde el campo

      Email Updates Actualizaciones por Correo

      Weekly updates, no spam Actualizaciones semanales, sin spam

      Successfully subscribed! ¡Suscripción exitosa!

      WhatsApp Channel Canal de WhatsApp

      Join to get instant updates on your phone Únete para recibir actualizaciones instantáneas en tu teléfono

      Join Channel Unirse al Canal
      Coalición Floresta Coalición Floresta © 2026 Coalición Floresta. All rights reserved. © 2026 Coalición Floresta. Todos los derechos reservados.
      🙏