Res. 30839-2026 Sala Constitucional · Sala Constitucional · 12/08/2026
OutcomeResultado
The Constitutional Chamber granted INVU a second 6-month extension (until March 15, 2027) to obtain SETENA's environmental clearance for Plan GAM, keeping the effects of the unconstitutionality declaration of Decreto Ejecutivo No. 38334 in suspension.La Sala otorgó al INVU una segunda prórroga de seis meses (hasta el 15 de marzo de 2027) para obtener la viabilidad ambiental del Plan GAM ante SETENA, manteniendo en suspenso los efectos de la declaratoria de inconstitucionalidad del Decreto Ejecutivo N° 38334.
SummaryResumen
The Constitutional Chamber grants a second 6-month extension to the National Housing and Urban Development Institute (INVU) to comply with Ruling No. 2020-023743, which declared Decreto Ejecutivo No. 38334 (Plan GAM 2013-2030) unconstitutional for violating the principle of singular non-derogation of norms and the right to a healthy environment under Article 50 of the Constitution. The original ruling suspended effects for 36 months to allow SETENA's strategic environmental assessment (EAE-014-2008). After a first 18-month extension in February 2025, the Chamber now grants an additional 6 months (September 15, 2026 – March 15, 2027) because SETENA's third technical review identified methodological gaps in the Environmental Fragility Index (IFA), Environmental Scope Analysis (AAA), and Sustainable Development Regulation (RDS)—three interdependent instruments underpinning the entire environmental component. The process stands at 75% completion across 31 cantons covering 1,778 km².La Sala Constitucional concede una segunda prórroga de seis meses al Instituto Nacional de Vivienda y Urbanismo (INVU) para cumplir con lo ordenado en la Sentencia N° 2020-023743, que declaró inconstitucional el Decreto Ejecutivo N° 38334-PLAN-MINAE-MIVAH-MOPT-S-MAG (Plan GAM 2013-2030) por violación al principio de inderogabilidad singular y al derecho al ambiente sano del artículo 50 constitucional. La sentencia original suspendió los efectos de la inconstitucionalidad por 36 meses para permitir obtener la viabilidad ambiental ante SETENA mediante una evaluación ambiental estratégica (EAE-014-2008). Una primera prórroga de 18 meses fue concedida en febrero de 2025. Ahora, la Sala otorga una segunda extensión de seis meses (del 15 de setiembre de 2026 al 15 de marzo de 2027) porque la tercera revisión técnica de SETENA identificó deficiencias en la cadena metodológica del componente ambiental: el Índice de Fragilidad Ambiental (IFA), el Análisis de Alcance Ambiental (AAA) y el Reglamento de Desarrollo Sostenible (RDS). El proceso registra un avance del 75%, con cobertura de 31 cantones y 1.778 km².
Key excerptExtracto clave
The request for an additional extension is justified by relevant technical aspects that remain pending in order to incorporate the environmental variable into the Regional Urban Plan Project for the Greater Metropolitan Area of Costa Rica. Furthermore, the report of the Technical Operative Criteria Unit for Territorial Planning (UCTOT-IN-006-2026, April 27, 2026) certifies 75% total progress, with 25% remaining, such that despite the pending matter the process reflects significant compliance across the prior procurement process, its execution, and delivery of products to SETENA. It is clear that there is a public interest in the Costa Rican State's task of completing SETENA's environmental clearance for Plan GAM 2012-2030, in order to safeguard the right to a healthy and ecologically balanced environment (Article 50, Constitution), so that in accordance with Article 12 and paragraphs 2 of Articles 88 and 91 of the Constitutional Jurisdiction Law, it is appropriate to extend the previously extended deadline by six additional months to comply with the corrections required by SETENA. The primary purpose is to fully comply with Ruling No. 2020-023743 of December 9, 2020, and to maintain the suspensive effects on the unconstitutionality declaration bearing on Executive Decree No. 38334 of March 10, 2014, extending six months from September 15, 2026, with the deadline set at March 15, 2027. The request filed by Johnny Leiva Badilla, in his capacity as Executive President of the National Housing and Urban Development Institute (INVU), is granted to extend the additional deadline agreed in Resolution No. 2025-003553 of February 5, 2025, and to fully comply with Ruling No. 2020-023743 of December 9, 2020. Accordingly, the requested additional six-month extension is granted as of September 15, 2026.La solicitud para la prórroga adicional se encuentra justificada en aspectos técnicos relevantes que aún penden para obtener la incorporación de la variable ambiental en el Proyecto Plan Regional Urbano de la Gran Área Metropolitana de Costa Rica. Asimismo, se acredita con el informe de la Unidad de Criterios Técnicos Operativos de Ordenamiento Territorial, UCTOT-IN-006-2026 del 27 de abril de 2026 un 75% de avance total, restando un 25% para completarlo, de modo que el proceso a pesar de la pendencia mencionada tiene un cumplimiento importante de todo el proceso licitatorio previo, su ejecución, y durante la entrega de los productos a la SETENA. es claro que existe un interés público en el cometido del Estado costarricense de completar la viabilidad ambiental de la SETENA para el PLAN GAM 2012-2030, con el fin de resguardar el derecho al ambiente sano y ecológicamente equilibrado (artículo 50, Constitucional), de manera que de conformidad con el artículo 12, y los párrafos 2°, de los numerales 88 y 91, de la Ley de la Jurisdicción Constitucional, procede ampliar el plazo anteriormente extendido por seis meses más, para cumplir con las subsanaciones requeridas por la SETENA. La finalidad primordial es dar cumplimiento cabal a la Sentencia N° 2020-023743 de las 12:10 hora del 9 de diciembre de 2020, y mantener los efectos suspensivos sobre la declaratoria de inconstitucionalidad que pesan sobre el Decreto Ejecutivo Nº 38334-PLAN-MINAE-MIVAH-MOPT-S-MOPT del 10 de marzo de 2014, y acordar la extensión por seis meses del 15 de septiembre de 2026, con el vencimiento para el 15 de marzo de 2027. Se acoge la solicitud promovida por Johnny Leiva Badilla, en su condición de presidente ejecutivo del Instituto Nacional de Vivienda y Urbanismo (INVU), para prorrogar el plazo adicional acordado por Sentencia N° 2025-003553 de las 9:45 horas del 5 de febrero de 2025, y dar cabal cumplimiento a la Sentencia N° 2020-023743 de las 12:10 horas del 9 de diciembre de 2020. En consecuencia, se otorga el plazo adicional de seis meses solicitados a partir del 15 de septiembre de 2026.
Pull quotesCitas destacadas
"la Sala declaró con lugar la acción contra el Decreto Ejecutivo Nº 38334-PLAN-MINAE-MIVAH-MOPT-S-MOPT del 10 de marzo de 2014, por violación al principio de inderogabilidad singular de las normas y al derecho al ambiente sano y ecológicamente equilibrado, resguardado en el artículo 50, de la Constitución Política."
"The Chamber ruled in favor of the action against Executive Decree No. 38334 of March 10, 2014, for violation of the principle of singular non-derogation of norms and the right to a healthy and ecologically balanced environment, protected under Article 50 of the Constitution."
Considerando I — referencia a Sentencia N° 2020-023743
"la Sala declaró con lugar la acción contra el Decreto Ejecutivo Nº 38334-PLAN-MINAE-MIVAH-MOPT-S-MOPT del 10 de marzo de 2014, por violación al principio de inderogabilidad singular de las normas y al derecho al ambiente sano y ecológicamente equilibrado, resguardado en el artículo 50, de la Constitución Política."
Considerando I — referencia a Sentencia N° 2020-023743
"Estos instrumentos son interdependientes, en cuanto la consistencia del RDS depende de la solidez del AAA, el que, a su vez, depende de la correcta determinación de los IFA."
"These instruments are interdependent: the consistency of the Sustainable Development Regulation (RDS) depends on the soundness of the Environmental Scope Analysis (AAA), which in turn depends on the correct determination of the Environmental Fragility Indices (IFA)."
Resultando 1 — ruta técnica SETENA
"Estos instrumentos son interdependientes, en cuanto la consistencia del RDS depende de la solidez del AAA, el que, a su vez, depende de la correcta determinación de los IFA."
Resultando 1 — ruta técnica SETENA
"a falta de un mes del cumplimiento del plazo dado por la Sentencias N° 2020-023743 y N° 2025-003553, el PLAN GAM aún carece del instrumento ambiental, el cual no estaría a punto para cumplir el objetivo de la protección del ambiente."
"With one month remaining before the deadline set by Rulings No. 2020-023743 and No. 2025-003553, Plan GAM still lacks the environmental instrument, which would not be ready in time to fulfill the objective of environmental protection."
Considerando I
"a falta de un mes del cumplimiento del plazo dado por la Sentencias N° 2020-023743 y N° 2025-003553, el PLAN GAM aún carece del instrumento ambiental, el cual no estaría a punto para cumplir el objetivo de la protección del ambiente."
Considerando I
"dado que faltan temas claramente técnicos como: geología, hidrogeología, validaciones administrativas, firmas y otros documentos, para una escala regional y de complejidad de 31 cantones, con un área de cobertura de 1.778.08 km²."
"given that clearly technical matters remain outstanding, such as: geology, hydrogeology, administrative validations, signatures and other documents, for a regional scale encompassing 31 cantons with a coverage area of 1,778.08 km²."
Considerando I — requerimientos técnicos pendientes ante SETENA
"dado que faltan temas claramente técnicos como: geología, hidrogeología, validaciones administrativas, firmas y otros documentos, para una escala regional y de complejidad de 31 cantones, con un área de cobertura de 1.778.08 km²."
Considerando I — requerimientos técnicos pendientes ante SETENA
Full documentDocumento completo
Document PJEDITOR SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, at nine hours thirty minutes on the twelfth of August, two thousand twenty-six.
Constitutional challenge (acción de inconstitucionalidad) filed by [Nombre 001], of legal age, married, holding a licentiate degree in Geology (licenciado en Geología) and a doctorate in Natural Sciences, resident of San Rafael de Montes de Oca, bearer of national identity card (cédula de identidad) No. [Valor 001]; [Nombre 002], of legal age, married for the second time, architect with specialties in Urban Planning and Territorial Planning (Ordenamiento Territorial), and a master's degree in Urban Design, resident of San José, bearer of identity card No. [Valor 002]; and [Nombre 003], of legal age, married, attorney, resident of Palmares de Alajuela, bearer of identity card No. [Valor 003]; against Executive Decree No. 38334-PLAN-MINAE-MIVAH-MOPT-S-MAG of March 10, 2014, which approves the Plan GAM 2013-2030, the Update of the Plan Regional de la Gran Área Metropolitana, published in La Gaceta (official gazette) No. 82 of April 30, 2014, and specifically Articles 25, 35, 39, and 69.
Background:
Drafted by Magistrate Salazar Alvarado; and,
Considering:
I.The request for an additional extension is justified on relevant technical grounds that remain pending in order to achieve the incorporation of the environmental variable in the Urban Regional Plan Project for the Gran Área Metropolitana of Costa Rica. Likewise, report UCTOT-IN-006-2026 from the Territorial Planning Technical Operations Criteria Unit (Unidad de Criterios Técnicos Operativos de Ordenamiento Territorial), dated April 27, 2026, certifies 75% total progress, with 25% remaining to be completed, so that the process, despite the pending matters mentioned, reflects significant compliance across the entire prior procurement process, its execution, and the delivery of outputs to SETENA. With all of this, it is affirmed that a shortfall of 25% remains in the technical-environmental process, given that methodological adjustments established in Executive Decree No. 32967-MINAE are required, entailing corrections to the Environmental Fragility Index (IFA), the Environmental Scoping Analysis (AAA), and the Sustainable Development Regulation (RDS) instruments.
In this regard, this means the process is not yet concluded; while it evidences very significant progress, it still requires inputs, corrections, and adjustments to allow it to advance within the additional timeframe. These deficiencies affect SETENA's final resolution depending on the delivery of the required information, or any new observations that may be made, where the fact remains that, with one month left before the deadline set by Sentences No. 2020-023743 and No. 2025-003553, the Plan GAM still lacks the environmental instrument, which would not be ready to fulfill the objective of environmental protection. In this regard, to comply with what SETENA has requested, a third submission is required, given that clearly technical matters remain outstanding, such as: geology, hydrogeology, administrative validations, signatures, and other documents, for a regional scale and the complexity of 31 cantons (cantones), with a coverage area of 1,778.08 km².
It is reiterated that 75% of the activities necessary to obtain environmental viability have been completed, and it is detailed that the remaining 25% of progress is still outstanding (pages 14 et seq. of report UCTOT-IN-006-2026).
Now, to resolve the motion filed by petitioner Leiva Badilla, in his capacity as executive president of the Instituto Nacional de Vivienda y Urbanismo (INVU), it must be noted that, by Sentence No. 2020-023743 of 12:10 hours on December 9, 2020, the Sala declared the constitutional challenge against Executive Decree No. 38334-PLAN-MINAE-MIVAH-MOPT-S-MOPT of March 10, 2014, well-founded (con lugar), on grounds of violation of the principle of singular non-derogation (principio de inderogabilidad singular) of legal norms and of the right to a healthy and ecologically balanced environment, protected under Article 50 of the Constitución Política. The Sala, for the reasons set forth in the decision, maintained the validity of the challenged Executive Decree "… for a period of up to thirty-six months from the full publication of the judgment in the official gazette La Gaceta, so that new regulations may be issued containing a process of strategic environmental assessment (evaluación ambiental estratégica) or other technical study that adequately incorporates the environmental variable into the plan that is the subject of this action, before the Secretaría Técnica Nacional Ambiental.
Should this not occur within that period, Executive Decree No. 38334-PLAN-MINAE-MIVAHMOPT-S-MAG of March 10, 2014 shall be deemed definitively expelled from the legal order." Subsequently, given the impossibility of compliance, the institutional authorities requested a first extension of the deadline, which was granted by resolution of this Sala Constitucional No. 2025-003553 of 9:45 hours on February 5, 2025, commencing March 15, 2025 and expiring September 15, 2026. Accordingly, the suspension of the effects of the declaration of unconstitutionality in Sentence No. 2020-23743 must remain in force beyond the expiration on September 15, 2026. In accordance with what is established in the preceding resolutions, it is clear that there is a public interest in the Costa Rican State's commitment to completing SETENA's environmental viability process for the Plan GAM 2012-2030, with the purpose of safeguarding the right to a healthy and ecologically balanced environment (Article 50, Constitución Política), so that, pursuant to Article 12, and the second paragraphs of Articles 88 and 91, of the Ley de la Jurisdicción Constitucional, it is appropriate to extend the previously extended deadline by six additional months, to comply with the remedial submissions required by SETENA.
The primary purpose is to achieve full compliance with Sentence No. 2020-023743 of 12:10 hours on December 9, 2020, and to maintain the suspensive effects on the declaration of unconstitutionality that weigh upon Executive Decree No. 38334-PLAN-MINAE-MIVAH-MOPT-S-MOPT of March 10, 2014, and to agree on the six-month extension from September 15, 2026, with expiration on March 15, 2027.
The parties are hereby warned that, if they have submitted any paper documents, as well as objects or evidence contained in any additional electronic, computer-based, magnetic, optical, telematic, or new-technology device, these must be retrieved from the office within a maximum period of thirty business days (días hábiles) counted from the notification of this judgment. Otherwise, all material not retrieved within this period will be destroyed, in accordance with the provisions of the "Reglamento sobre Expediente Electrónico ante el Poder Judicial," approved by the Corte Plena at Session No. 27-11 of August 22, 2011, Article XXVI, and published in the Boletín Judicial No. 19 of January 26, 2012, as well as the agreement approved by the Consejo Superior del Poder Judicial at Session No. 43-12 held on May 3, 2012, Article LXXXI.
Therefore:
The motion filed by Johnny Leiva Badilla, in his capacity as executive president of the Instituto Nacional de Vivienda y Urbanismo (INVU), to extend the additional deadline agreed upon by Sentence No. 2025-003553 of 9:45 hours on February 5, 2025, and to achieve full compliance with Sentence No. 2020-023743 of 12:10 hours on December 9, 2020, is granted. Accordingly, the additional period of six months requested is granted, commencing September 15, 2026. Notice, summarize, and publish this resolution in its entirety.- Fernando Castillo V. President Fernando Cruz C.
Paul Rueda L. Luis Fdo. Salazar A.
Jorge Araya G. Anamari Garro V.
Ingrid Hess H.
1
Documento PJEDITOR SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas treinta minutos del doce de agosto de dos mil veintiseis .
Acción de inconstitucionalidad promovida por [Nombre 001], mayor, casado, licenciado en Geología y doctor en Ciencias Naturales, vecino de San Rafael de Montes de Oca, portador de la cédula de identidad N° [Valor 001]; [Nombre 002], mayor, casado en segunda nupcias, arquitecto con especialidades en Planificación Urbana y Ordenamiento Territorial, y máster en Diseño Urbano, vecino de San José, portador de la cédula de identidad N° [Valor 002]; y [Nombre 003], mayor, casado, abogado, vecino de Palmares de Alajuela, portador de la cédula de identidad N° [Valor 003]; contra el Decreto Ejecutivo N° 38334-PLAN-MINAE-MIVAH-MOPT-S-MAG del 10 de marzo de 2014, que aprueba el Plan GAM 2013-2030 Actualización del Plan Regional de la Gran Área Metropolitana, publicado a La Gaceta N° 82 del 30 de abril de 2014, y específicamente los artículos 25, 35, 39 y 69.
Resultando:
Redacta el Magistrado Salazar Alvarado; y,
Considerando:
I.La solicitud para la prórroga adicional se encuentra justificada en aspectos técnicos relevantes que aún penden para obtener la incorporación de la variable ambiental en el Proyecto Plan Regional Urbano de la Gran Área Metropolitana de Costa Rica. Asimismo, se acredita con el informe de la Unidad de Criterios Técnicos Operativos de Ordenamiento Territorial, UCTOT-IN-006-2026 del 27 de abril de 2026 un 75% de avance total, restando un 25% para completarlo, de modo que el proceso a pesar de la pendencia mencionada tiene un cumplimiento importante de todo el proceso licitatorio previo, su ejecución, y durante la entrega de los productos a la SETENA. Con todo ello se afirma que aún hay un faltante del proceso técnico-ambiental que es de un 25%, dado que se requiere de ajustes metodológicos establecidos en el Decreto Ejecutivo N° 32967-MINAE, que implican correcciones a los instrumentos del Índice de Fragilidad Ambiental (IFA), al Análisis de Alcance Ambiental (AAA) y al Reglamento de Desarrollo Sostenible (RDS).
En este sentido, ello significa que el proceso no está aún concluido, que si bien evidencia un avance muy importante aún requiere insumos, correcciones y ajustes que le permita progresar con ese plazo adicional. Dichas carencias inciden en la resolución final de SETENA conforme a la entrega que se haga de la información requerida, o nuevas observaciones que se le hagan, donde lo cierto es que a falta de un mes del cumplimiento del plazo dado por la Sentencias N° 2020-023743 y N° 2025-003553, el PLAN GAM aún carece del instrumento ambiental, el cual no estaría a punto para cumplir el objetivo de la protección del ambiente. En este sentido, para dar cumplimiento de lo solicitado por SETENA se requiere de una tercera entrega, dado que faltan temas claramente técnicos como: geología, hidrogeología, validaciones administrativas, firmas y otros documentos, para una escala regional y de complejidad de 31 cantones, con un área de cobertura de 1.778.08 km².
Se reitera que se ha cumplido con un 75% de las actividades necesarias para la obtención de la viabilidad ambiental, y se detalla que falta el avance de 25% restantes (páginas 14 y ss. del informe UCTOT-IN-006-2026).
Ahora bien, para resolver la petición del gestionante Leiva Badilla, en su condición de presidente ejecutivo del Instituto Nacional de Vivienda y Urbanismo (INVU), se debe traer a colación que, por Sentencia N° 2020-023743 de las 12:10 horas del 9 de diciembre de 2020, la Sala declaró con lugar la acción contra el Decreto Ejecutivo Nº 38334-PLAN-MINAE-MIVAH-MOPT-S-MOPT del 10 de marzo de 2014, por violación al principio de inderogabilidad singular de las normas y al derecho al ambiente sano y ecológicamente equilibrado, resguardado en el artículo 50, de la Constitución Política. La Sala, por las razones explicadas en la decisión, mantuvo la vigencia del Decreto Ejecutivo impugnado “… hasta por un plazo de treinta y seis meses a partir de la publicación íntegra de la sentencia en el diario oficial La Gaceta, para que se emita una nueva normativa que contenga un proceso de evaluación ambiental estratégica u otro estudio técnico que incorpore adecuadamente la variable ambiental al plan objeto de esta acción, ante la Secretaría Técnica Nacional Ambiental.
De no producirse lo anterior, en ese plazo, se tendrá por expulsado -definitivamente- del ordenamiento jurídico el Decreto Ejecutivo N° 38334-PLAN-MINAE-MIVAHMOPT-S-MAG del 10 de marzo de 2014”. Posteriormente, dado la imposibilidad de cumplir las autoridades institucionales solicitaron una primera extensión del plazo, el cual fue concedido por resolución de esta Sala Constitucional N° 2025-003553 de las 9:45 horas del 5 de febrero de 2025, a partir del 15 de marzo de 2025 y con vencimiento al 15 de septiembre de 2026. En consecuencia, la suspensión de los efectos de la declaratoria de inconstitucionalidad de la Sentencia N° 2020-23743 se debe mantener vigente, más allá del vencimiento al 15 de septiembre de 2026. Conforme a lo establecido en las resoluciones precedentes, es claro que existe un interés público en el cometido del Estado costarricense de completar la viabilidad ambiental de la SETENA para el PLAN GAM 2012-2030, con el fin de resguardar el derecho al ambiente sano y ecológicamente equilibrado (artículo 50, Constitucional), de manera que de conformidad con el artículo 12, y los párrafos 2°, de los numerales 88 y 91, de la Ley de la Jurisdicción Constitucional, procede ampliar el plazo anteriormente extendido por seis meses más, para cumplir con las subsanaciones requeridas por la SETENA.
La finalidad primordial es dar cumplimiento cabal a la Sentencia N° 2020-023743 de las 12:10 hora del 9 de diciembre de 2020, y mantener los efectos suspensivos sobre la declaratoria de inconstitucionalidad que pesan sobre el Decreto Ejecutivo Nº 38334-PLAN-MINAE-MIVAH-MOPT-S-MOPT del 10 de marzo de 2014, y acordar la extensión por seis meses del 15 de septiembre de 2026, con el vencimiento para el 15 de marzo de 2027.
Se previene a las partes que de haber aportado algún documento en papel, así como objetos o pruebas contenidas en algún dispositivo adicional de carácter electrónico, informático, magnético, óptico, telemático o producido por nuevas tecnologías, estos deberán ser retirados del despacho en un plazo máximo de treinta días hábiles contados a partir de la notificación de esta sentencia. De lo contrario, será destruido todo aquel material que no sea retirado dentro de este plazo, según lo dispuesto en el "Reglamento sobre Expediente Electrónico ante el Poder Judicial", aprobado por la Corte Plena en Sesión N° 27-11 del 22 de agosto del 2011, artículo XXVI y publicado en el Boletín Judicial número 19 del 26 de enero del 2012, así como en el acuerdo aprobado por el Consejo Superior del Poder Judicial, en la Sesión N° 43-12 celebrada el 3 de mayo del 2012, artículo LXXXI.
Por tanto:
Se acoge la solicitud promovida por Johnny Leiva Badilla, en su condición de presidente ejecutivo del Instituto Nacional de Vivienda y Urbanismo (INVU), para prorrogar el plazo adicional acordado por Sentencia N° 2025-003553 de las 9:45 horas del 5 de febrero de 2025, y dar cabal cumplimiento a la Sentencia N° 2020-023743 de las 12:10 horas del 9 de diciembre de 2020. En consecuencia, se otorga el plazo adicional de seis meses solicitados a partir del 15 de septiembre de 2026. Notifíquese, reséñese y publíquese íntegramente esta resolución.- Fernando Castillo V.
Fernando Cruz C.
Paul Rueda L.
Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Ingrid Hess H.
1