Res. 37108-2025 Sala Constitucional · Sala Constitucional · 11/11/2025
OutcomeResultado
The non-compliance petition is granted due to disobedience of the 2016 judgment, ordering the current mayor of San José to complete the works required to prevent flooding in Ciudadela Calderón Muñoz.Se acoge la gestión de inejecución por desobediencia de la sentencia de 2016, ordenando al actual alcalde de San José cumplir las obras necesarias para evitar inundaciones en Ciudadela Calderón Muñoz.
SummaryResumen
The Constitutional Court grants a non-compliance petition regarding repeated disobedience of the 2016 ruling, which ordered the Municipality of San José to conduct hydraulic studies of the Ocloro River and execute infrastructure works to prevent flooding in the Ciudadela Calderón Muñoz. More than nine years have elapsed and serious omissions persist. The current mayor is ordered to comply under penalty of sanctions. The original ruling protected rights to health and a healthy environment against flooding carrying sewage and solid waste.La Sala Constitucional acoge una gestión de inejecución por desobediencia reiterada de la sentencia de 2016, que ordenó a la Municipalidad de San José realizar estudios hidráulicos del río Ocloro y ejecutar obras para evitar inundaciones en la Ciudadela Calderón Muñoz. Han transcurrido más de nueve años y persisten omisiones graves. Se ordena al actual alcalde cumplir lo dispuesto bajo apercibimiento de sanciones. La sentencia original protegió derechos a la salud y a un ambiente sano ante inundaciones con arrastre de aguas residuales y residuos sólidos.
Key excerptExtracto clave
"Thus, despite the main judgment in this matter dating from June 3, 2016, and the deadline to comply with its orders having expired on April 11, 2018, that is, more than seven years ago, it is not verified that the flooding problem in Ciudadela Calderón Muñoz has been duly resolved, as works remain unfinished. Consequently, the non-compliance petition is granted. Now, given that the current mayor of San José differs from the person originally ordered, it is appropriate to order compliance by whoever currently holds the position..." "...regarding the petitioner’s disagreements about the works undertaken by the respondent local authority, arguing they would not adequately resolve the problem, it must be noted that this matter is not to be resolved in this ordinary jurisdictional proceeding, especially since this Chamber did not define how the order must be fulfilled, but rather ordered the implementation of 'the infrastructure works required to prevent flooding in the Ciudadela Calderón Muñoz sector', which does not mean that such solution must be exactly the one sought by the plaintiff.""Así las cosas, pese a que la sentencia principal de este asunto data del 3 de junio de 2016 y que el plazo para cumplir lo ahí ordenado feneció desde el 11 de abril de 2018, a saber, hace más de siete años, no se verifica que se haya solventado debidamente la problemática relacionada con las inundaciones de la Ciudadela Calderón Muñoz, toda vez que faltan obras por terminar. Por tal motivo, se acoge la gestión de inejecución planteada. Ahora bien, dado que la persona que actualmente funge como alcalde de San José difiere de a quien se le giró la orden en cuestión en otras ocasiones, lo procedente es ordenar el cumplimiento de lo dispuesto en la sentencia mencionada a quien en la actualidad desempeña el cargo..." "...en cuanto a las disconformidades externadas por la gestionante atinentes a las obras ejecutadas por la corporación local recurrida, ya que estima que no resolverían adecuadamente la problemática objeto de este asunto, adviértase que ello no corresponde ser dilucidado en esta vía jurisdiccional ordinaria, máxime que esta Cámara no definió la manera en que se debe cumplir la orden supramencionada, sino que lo dispuesto es que se implementen 'las obras de infraestructura que se requieran para evitar las inundaciones en el sector Ciudadela Calderón Muñoz', lo que no implica que tal solución deba ser específicamente la pretendida por la parte amparada."
Pull quotesCitas destacadas
"Se acoge la gestión de desobediencia formulada."
"The non-compliance petition is granted."
Por tanto
"Se acoge la gestión de desobediencia formulada."
Por tanto
"Tratándose de materia ambiental, como ocurre en el sub examine, resulta admisible la legitimación vicaria, de conformidad con lo establecido en el artículo 105 de la Ley de Biodiversidad..."
"In environmental matters, as in the case at hand, vicarious standing is admissible, in accordance with Article 105 of the Biodiversity Law..."
Considerando IX
"Tratándose de materia ambiental, como ocurre en el sub examine, resulta admisible la legitimación vicaria, de conformidad con lo establecido en el artículo 105 de la Ley de Biodiversidad..."
Considerando IX
"Esta Cámara no definió la manera en que se debe cumplir la orden supramencionada, sino que lo dispuesto es que se implementen “las obras de infraestructura que se requieran para evitar las inundaciones en el sector Ciudadela Calderón Muñoz”, lo que no implica que tal solución deba ser específicamente la pretendida por la parte amparada."
"This Chamber did not define the manner in which the order must be fulfilled, but rather ordered the implementation of 'the infrastructure works required to prevent flooding in the Ciudadela Calderón Muñoz sector', which does not mean that such solution must be exactly the one sought by the plaintiff."
Considerando IX
"Esta Cámara no definió la manera en que se debe cumplir la orden supramencionada, sino que lo dispuesto es que se implementen “las obras de infraestructura que se requieran para evitar las inundaciones en el sector Ciudadela Calderón Muñoz”, lo que no implica que tal solución deba ser específicamente la pretendida por la parte amparada."
Considerando IX
Full documentDocumento completo
Resulting:
- As part of those aspects that the company Nombre47898 could not study or analyze at the time of preparing the report requested by the Municipality of San José, and which are of vital importance for the comprehensive solution required, the following must be noted: First, it is necessary to indicate to this Presidency that the final version of the study carried out by the company Nombre47898 INGENIEROS CONSULTORES S.A. was delivered to the Municipality of San José on November 27, 2018. Almost seven years have elapsed to date. At that time, the company stated in that report, among other things: (…) On this point, it should be noted that in 2015 the Municipality of Montes de Oca built a new storm sewer system on the streets of Los Yoses, called the Nuevo Colector Pluvial Los Yoses, which discharges in Dirección2719 where the Rio Ocloro is located. In 2018, a new pipe was added to this collector, with the aim of collecting, in the area of Dirección87, the water that pooled at the bus stops.
These are the works referred to by Nombre47898 in the preceding paragraph. On the other hand, in 2019, the Municipality of Montes de Oca lined the dry channels that are bypasses of the Río Ocloro, which pass between homes in Los Yoses along Dirección2720. In addition to the above, it should be noted that from 2016 to date, 14 condominium towers have been built in the district of El Carmen, within the jurisdiction of the Municipality of San José, which issued the construction permits and authorized the discharge of their stormwater into the Río Ocloro, near the Mall San Pedro, an area belonging to the Municipality of Montes de Oca. The study by Nombre47898 considered the stormwater from the northern part of the Río Ocloro, which corresponds to the jurisdiction of the Municipality of San José, leaving aside what discharges into the Río Ocloro and belongs to the jurisdiction of the Municipality of Montes de Oca, which is the largest tributary of stormwater to that river (…) In the case at hand, that Management Plan has never been carried out.
This recommendation was omitted by the Municipality of San José, which in this matter should have involved the Municipality of Montes de Oca, since the waters that will discharge into the Río Ocloro, in their vast majority, come from that sector. This therefore requires a comprehensive plan that both municipalities must carry out, but which to date has not been done, with the most affected population being that of the San José sector. For this reason, if the Municipality of San José does not seek to coordinate with its counterpart in Montes de Oca, it will be difficult to find the comprehensive solution that the Constitutional Chamber ordered back in 2016: (…) We assume that the latest studies contracted by the Municipality of San José are focused on complying with these recommendations. In the case of the company RIVER-ING DE COSTA RICA S.A., the issue of underground culverts has been addressed, especially in the Ciudadela Calderón Muñoz area.
Furthermore, another study contracted by the Municipality of San José, prior to the one by River-Ing de Costa Rica S.A., was carried out by the company INGENIERIA TECNICA DE PROYECTOS ITP, under the charge of Eng. Nombre47891, which mentioned the problem of not having updated topographic studies. TWENTY-FIRST: Last year, after the new Mayor of San José assumed office, we sent him a chronology of the problems that our communities continued to face due to the flooding caused by the Río Ocloro and the slow solution that the MSJ had been providing to this problem. Likewise, I requested a meeting, because I knew that Mr. Nombre47893 was indeed aware of this problem, but unfortunately more than a year later it has not been possible to obtain an appointment to meet with him and to present our concerns on the matter, and see if it is possible to obtain a faster solution to this issue that has been awaiting resolution for years, for the reasons we have set forth in this document.
Evidence marked #16 and #17. With the due respect I have for the Presidency of this Constitutional Chamber, and for the entire composition of the Chamber in general, I request that the complaints set forth in this document be taken into consideration, complaints which arise from non-compliance attributable, in this case, to the Municipality of San José, which in our opinion has acted negligently in the case of the communities of Barrio Luján and the Ciudadela Calderón Muñoz and the problem of floods that have afflicted them for more than 60 years, but which have worsened in recent years due to demographic growth, as well as the large amount of infrastructure that has been built in recent decades in this area of the province of San José. The lack of compliance with what was ordered by this Chamber through two different but coinciding resolutions demonstrates the Municipality of San José's lack of interest in the problem of our communities, and disobedience to the Authority stemming from the orders issued by this Chamber. As evident and manifest reason for this, I request that the necessary measures be taken to make effective the mandates of this esteemed Chamber.”
Drafted by Magistrate Nombre41880; and,
Considering:
“IV.- Regarding the specific case. From the study of the case file, it is established that on November 11, 2015, the petitioner raised 2 complaints concerning the collapse of the sewer system (alcantarillado) and the overflow of sewage and garbage in her community, which she stated caused severe damage to her property on October 27, 2015, and was repeated on November 11, 2015; she requested that measures be taken to prevent what happened in the future, that she be informed of what was intended to be done about it, and that she be compensated for the damages caused. It must be stated beforehand to the protected party that it is not within the purview of this Jurisdiction to determine whether the administration should be held civilly liable for the attributed damages and compensate the protected party. Therefore, any potential disagreement with the rejection of her claim in that regard by the respondent authority is a dispute that must be raised through ordinary legal channels, should the petitioner so choose. Regarding the alleged lack of attention to the mentioned health and environmental problem, and her management thereof, we shall proceed to resolve on the merits.
Indeed, the petitioner alleges that despite the serious consequences of what occurred in October 2015 due to the overflow of the Río Ocloro, the required measures have not been taken to prevent a similar situation from occurring. In this regard, the respondent Municipality emphatically stated, under oath, that the severe floods produced on October 27, 2015, were the result of an extraordinary rainfall event, in which the Ocloro and María Aguilar rivers, as well as the Pavas and Rivera streams, reached their maximum level and, in places where they did not overflow, exceeded the levels of the discharge points of the stormwater drainage system (sistema pluvial), which caused the water not to flow through said pipes until the downpour passed; which was not a result of the condition of the sewer system. Likewise, they indicated that the Storm Drainage Construction and Maintenance Section worked jointly with the Municipal Disaster Risk Management Office and the National Emergency Commission to formulate an Atención de la Cuenca del río Ocloro program; and they stated they are ready to tender a study of the Ocloro micro-watershed, in order to scientifically determine the hydraulic condition of that river and propose infrastructure works to mitigate the floods.
However, on this last point, despite 7 months having passed since the flood that occurred on October 27, 2015, the respondent Municipality does not even currently allude to an already established schedule to verify the real situation of the Río Ocloro's containment capacity in the face of a potential natural event like the one that has already occurred, which is essential according to what was indicated by the Governing Health Area (Área Rectora de Salud), which, in report CS-URS-471-2016 of May 25, 2016, concluded:
"4.1. Regarding the verification requested by the Constitutional Chamber as to whether the homes in the sector are at any danger of flooding due to obstruction by garbage. The answer is that during the occurrence of intense rainfall, it is to be expected that the river will also drag all types of solid waste found along its basin: which in turn increases the risk of obstructions occurring mainly in the sectors where the river is underground in culverts (entubado); that is, the culverted sectors are the most vulnerable to obstructions due to the space limitations in their sections, which does not occur with the sectors of the river with an open channel (cauce abierto): based on what has been said, there is a reasonable probability of flooding occurring at the site due to obstructions in the culverted sectors. Regarding the next consultation on whether floods occur due to deficiencies in the sewer system or poor water disposal and channeling of the Río Ocloro; an accurate answer to this consultation depends on the hydrological and hydraulic studies available to the competent body, in this case the Municipality.
Based on the results of these studies and design calculations, it is possible to define whether the occurrence of the floods is due to the existence of reduced areas in the existing drainage sections and/or defects in the design of the stormwater drainage system, so it is necessary to review the entire route of the watershed (cuenca). 4.2. Regarding the request of the Minister, Madam, to the effect of determining and concluding whether the area denounced by Mrs. Nombre47885 represents a danger to the public health of the inhabitants of that sector. The answer is that the river is contaminated with wastewater and when this water reaches the interior of homes as a result of a river overflow, it will generate an unhealthy condition, so every time a flood occurs, there will be a real danger to the health of the residents of the place. Regarding the recommendations requested by the Minister, Madam.
This Governing Body advises requesting the respective technical studies, plans, and activity schedules of works that the Municipality has promised the community to resolve the flooding problems we are dealing with." According to what the respondent authority reported under oath, what happened was an extraordinary event that was not foreseen. However, in the sub examine, as of what happened, at least from October 2015 to date, the administration knows what can happen if rainfall like that of that time occurs again, and consequently, it is obliged to take, in a timely and responsible manner, all necessary measures to mitigate the effects and disasters that are already known to potentially occur again – which was a public and notorious fact. In the inspection carried out by the Ministry of Health, the following was also determined:
"3.4. -Between the bridge and the West sector of the parking lot of the Dos Pinos branch in Bo. Lujan [Dirección2559], the river channel was observed to be partially obstructed with organic waste and possibly with sediment…Notwithstanding this condition and in the event that an overflow occurs at this point, it is the opinion of the undersigned that the event would not affect the Ciudadela Calderón Muñoz, due to the fact that there is a separation distance of about 600 m between both sites and, on the other hand, due to the prevailing topography at the site, it is to be expected that the overflow returns to the river channel without traveling more than 100 m. 3.5. -At an approximate distance of 400 m downstream from the reference point indicated in the previous section, the CEDESSO building is located, and it is precisely at this site that a culverted section of the river begins, which ends about 25 m West of the Multifamily buildings of the Ciudadela Calderón Muñoz, which borders the East sector of Lomas de Ocloro.
The CEDESSO building is located specifically Northeast of the Clínica Carlos Durán and is the closest open-channel sector of the Río Ocloro to the Ciudadela Calderón Muñoz, at an approximate distance of 100 m…On the crown of the culvert where the river flows and on the boundaries of the CEDESSO building property, a perimeter mesh fence was built, on which evidence of organic waste material transported by the river that was trapped in the perimeter mesh of the building in question could be observed, reaching heights between 1.0 and 1.5 m above the crown of the culvert... Said evidence is the result of the occurrence of an extraordinary flood event, which, probably associated or not with some obstruction of the culvert, it is possible that this type of event, aided by the proximity and favorable topographic conditions, could cause floods to the Ciudadela Calderón Muñoz, the petitioner's place of residence. 3.6.-Based on the visual field inspection conducted today in the area described in photograph #1, it was determined that the river also transports mostly domestic-type wastewater." Thus, this Court considers that the petitioner is correct in pointing out that there are sufficient indications that the floods she has been subject to could occur again, due to the failure to attend to what is required in a timely manner, at least to mitigate their effects.
It is not sufficient to indicate that a study of the micro-watershed is being scheduled, if its tender, programming, and execution have not even been finalized. On the other hand, the respondent Ministry also warned of other obstruction problems on the perimeter mesh of the Edificio Cendesso that may worsen in the face of greater rainfall, and which must be addressed constantly and promptly by the respondent Municipality. Consequently, the amparo remedy must be granted regarding this aspect.
V.Regarding the procedures filed by the petitioner on November 19, 2015, it is established that through official communications ALCALDIA 06493-2015 and ALCALDIA06497-2015, both dated November 20, 2015, the respondent Mayor's Office informed the protected party that her procedure was being forwarded to the respective departments and that, given its characteristics, the response would take longer than established by law, which was notified to her at email ...443. Through official communication ALCALDIA 00689-2016 dated March 1, 2016, the Mayoress rejected the petitioner's claim regarding the payment of damages suffered due to the flood of October 27, 2015, for lack of evidence, which was notified to her at the email address ...443; in this respect, this Court reiterates to the petitioner that she may resort to ordinary jurisdiction to challenge said result, if she is in disagreement with what was resolved regarding that aspect.
However, even though almost 6 months have passed since her procedures, the respondent authority omitted to inform her about the measures that said Municipality would adopt to prevent floods in the area in question, their scheduling, whether there were investigations into the works performed, and the solution that would be given to the case, as she expressly requested. Consequently, there are aspects of mere information that were not addressed, and others related to the solution of the denounced problem, about which she was also not informed. Consequently, the remedy must also be granted in this sense. (…)
Therefore:
The remedy is granted.
It is ordered to Nombre1010, in his capacity as Municipal Mayor of San José, or to whoever holds the office, to proceed within the non-extendable period of 6 months counted from the notification of this judgment, to carry out the studies required to scientifically verify the hydraulic condition of the Ocloro River, and in the 6 months following said period, to implement the infrastructure works required to prevent floods at Dirección2723. Likewise, the respondent is ordered to immediately adopt all necessary and possible measures that help mitigate the floods that may occur in said location, while the studies and works in question are being carried out; as well as, he must answer and notify the appellant, within a period not exceeding 3 business days from the notification of this pronouncement, the remainder of the information requested in the petitions filed on November 19, 2015, which were not addressed by the respondent in official letter ALCALDIA 00689-2016 of March 1, 2016.
The respondent authority is warned that, in accordance with the provisions of Article 71 of the Ley de la Jurisdicción Constitucional, imprisonment of three months to two years or a fine of twenty to sixty days shall be imposed on anyone who receives an order that must be complied with or enforced, issued within a recurso de amparo, and does not comply with it or does not enforce it, provided the offense is not more severely penalized. The Municipality of San José is ordered to pay the costs, damages, and losses caused by the facts serving as the basis for this declaration, which shall be liquidated in enforcement of judgment in contentious-administrative proceedings. Notify this resolution personally to Nombre1010, in his capacity as Municipal Mayor of San José, or to whoever holds the office. Judge Nombre5236 dissents and rejects the recurso outright. Judge Nombre33846 makes a note.” That pronouncement was personally notified to the Municipal Mayor of San José on June 8, 2016.
“II.- In the sub lite, the appellant alleges disobedience to what was ordered by this Court, given that the respondent authority has not taken immediate measures to mitigate the floods occurring in the Calderón Muñoz housing development; given that, on June 8 and 10, 2016, the Ocloro River overflowed and caused floods at the location. In this regard, the Municipal Mayor of San José reported that he has issued various immediate actions. He indicated that the Storm Drain Network Maintenance and Construction Section (Sección de Mantenimiento y Construcción de Red Pluvial), in official letter SCMRP-420-2016 of June 17, 2016, provided the Mitigation Measures Plan to Reduce Flooding throughout the Ocloro River micro-basin for the comprehensive management of the problem, and works are currently being executed in the riverbed with municipal crews. Now, based on what was reported under oath and the evidence provided by the appellant, this Chamber considers that the petition of the amparo petitioner must be dismissed.
The foregoing, since from what was reported—with timely warning of the consequences, including criminal ones, provided for in Article 44 of the Ley de la Jurisdicción Constitucional—it clearly follows that the respondent Municipality has not evaded what was ordered by this Court, given that according to what was reported by the respondent, there is a management plan for the entire Ocloro River basin and thereby a solution for the floods occurring in the Calderón Muñoz sector; in turn, there are Municipal crews working in the riverbed in question to address the problem in the short term; furthermore, work is being done to carry out the bidding processes for the scientific studies and bridge construction, and as stated in official letter SCMRP-420-2016 of June 17, 2016, through which the Mitigation Measures Plan to Reduce Flooding throughout the Ocloro River micro-basin was provided, there is a budget of 200,000,000.00 colones for this; equally, this Court notes that the respondent administration is within the granted 6-month period to carry out the necessary works to address the floods occurring in the area of Ciudadela Calderón Muñoz.
As things stand, the Chamber verifies that there have been actions to carry out what was ordered by the Chamber. Consequently, the appropriate course is to dismiss the petition as it is premature. (…)
Therefore:
The petition filed is denied.”
“Therefore: The time period granted in judgment No. 2016-007570 at 9:05 a.m. on June 3, 2016, is extended, for which reason Nombre1010, in his capacity as Municipal Mayor of San José, or whoever holds said office, is granted until April 11, 2018, to carry out the studies required to scientifically verify the hydraulic condition of the Ocloro River, and in the 6 months following said date, they must implement the infrastructure works required to prevent floods in the Ciudadela Calderón Muñoz sector. In all other respects, the petition filed is denied.”
“VI.- Regarding the non-execution petition. In the sub lite, the petitioners allege non-compliance with what was ordered by this Chamber through judgment No. 2016-007570 at 9:05 a.m. on June 3, 2016, in which it was ordered that within a period of 6 months the respondent authority must carry out the studies required to scientifically verify the hydraulic condition of the Ocloro River, and in the 6 months following said period, implement the infrastructure works required to prevent floods in the Ciudadela Calderón Muñoz sector. It must first be noted that the petition was indeed filed prematurely, because when they came to the Chamber—March 12, 2018—the administration still had the period granted by this Chamber to address the situation raised. In any case, the respondent authority reported that the company Nombre47898 Ingenieros Consultores carried out a study comprising the hydrological analysis of the external contributing basins to the Ocloro River micro-basins.
Said study included the morphometric and hydrological characterization of said external contributions, the characterization of historical rainfall in the study area, and the generation of hydrographs produced by the aforementioned rainfall, for subsequent use in the hydraulic analysis of the drainage systems of the micro-basin in question. The Las Arias ditch (acequia Las Arias) was included within the general analysis; however, it has no external contributions, so its hydrology was considered within the hydraulic analysis report. From the report submitted under oath, it was verified that, regarding the Barrio Luján sector, four works must be carried out with varying degrees of priority, and in the Calderón Muñoz Sector, it was certified that five works must be carried out within different timeframes—short, medium, and long-term. Likewise, that with the purpose of addressing what was ordered by this Chamber and initiating the mitigation works in the affected sectors, the respondent municipality promoted at the end of 2017 the abbreviated bidding process No. 2017LA-000057-0015499999, for the installation of two pipes of 2.44 m in diameter so that by the winter of 2018 there would be greater hydraulic capacity, and thus be able to mitigate the flood risk in the Barrio Luján sector.
In this regard, the respondent municipality acknowledges that the installation of these two pipes is not the definitive solution, and that should greater capacity be required, the necessary works will be carried out, which in this case will be the placement of a third pipe, as calculated by the company DEHC. The aforementioned bidding process was promoted under the protection of Decreto 3l849-MINAE-SMOPT-MAG-MEIC of 2004 and its amendments, and Decreto 37803-MINAE-SMOPT-MAG-MEIC of 2013, based on which Municipalities are exempted from carrying out environmental feasibility (viabilidad ambiental) and environmental impact (impacto ambiental) procedures for storm sewer maintenance works; however, from the petition filed and the report given under oath, it is evident that there was opposition from the neighbors to carrying out the works, and they went to the Ombudsman's Office (Defensoría de Los Habitantes), which to date has not issued its report; furthermore, the neighbors appealed to SETENA and the Water Directorate (Dirección de Aguas) to prevent the actions of the respondent municipality.
On this aspect, it was verified that the Water Directorate of MINAE opposed the mentioned works and indicated to the respondent municipality that the works they were carrying out require approval from that entity and from SETENA. A situation that forced the respondent to suspend the works, the execution of which would now depend on what was determined by the Water Directorate of MINAE, SETENA, and SINAC. On this matter, it follows that the study ordered in the judgment has already been carried out, and that some of the works that the Municipality of San José was carrying out to implement the respective measures were suspended as a result of the complaints filed by the neighbors and the prior procedures they must complete; however, they are addressing what was ordered. On the other hand, the petitioners must be warned that this jurisdiction is not competent to determine whether what was recommended in the technical study represents the best measures to adopt, or whether another particular work, different from the one recommended, should be carried out. The foregoing is a matter of legality that must be verified by the administration itself and the other bodies responsible for supervising and authorizing the works.
VII.On the other hand, the petitioners question that the respondent municipality intends to favor the economic interests of private companies, specifically the Cooperativa de Productores de Leche Dos Pinos, and the developer Nombre47897, the latter of which is advancing a project for the company 3-101-687989 S.A. Mixed Vertical Condominium Torres Trío. They question why the municipality must bear the works of said companies for the eventual damages they may cause, and that if so, the respective disciplinary and civil responsibilities must be established for the officials who have promoted it. They denounce that this last company presented hydrological and hydraulic studies prepared by “Geotecnia y Construcción,” made for the Torres Trío condominium, and not for the Ocloro River Basin. Likewise, they denounce that on March 2, 2018, a crew of employees of the respondent municipality cut down trees on the banks of the riverbed in the El Cerrito municipal park, which is a reserve for the Ocloro River basin in Dirección73, without obtaining permits from the National System of Conservation Areas (Sistema de Áreas de Conservación, SINAC).
The foregoing for the purpose of initiating the alleged 200-meter culverting work (entubado) that the respondent municipality intends to carry out, and which is not a product of the technical study conducted. In this regard, this Court agrees with the respondent authority, in the sense that such allegations constitute new facts that were not invoked in the initial brief of this recurso de amparo, therefore, the proper course is for such matters to be heard in a new recurso. Due to the foregoing, the proper course is to detach (desglosar) the filed brief, so that such matters may be resolved as appropriate in another recurso.
Therefore:
The petition filed is denied. Detach the brief added to this case file at 09:04 a.m. on March 12, 2018, so that the aspects indicated in Considerando VII are processed as a new matter.”
“V.- Regarding the non-execution petition. In the sub lite, the amparo petitioner files a disobedience petition in relation to judgment No. 2016007570 at 9:05 a.m. on June 3, 2016, in which it was ordered that within a period of 6 months the respondent authority must carry out the studies required to scientifically verify the hydraulic condition of the Ocloro River, and in the 6 months following said period, implement the infrastructure works required to prevent floods in the Ciudadela Calderón Muñoz sector. The petitioner claims that currently none of the works proposed in the study carried out by DEHC have been built. She asserts that only one mitigation work with stormwater pipes was carried out within the neighborhood, which does not guarantee being free from danger from eventual floods. She adds that only 10 million colones have been processed for topographical studies for the work corresponding to the replacement of the corrugated culvert. She alleges that the period ordered for the construction of the works benefiting Ciudadela Calderón Muñoz has already expired. She requests that the execution of the nine works proposed in the final report by DEHC be ordered.
In this regard, from the report submitted by the authority it follows that the ordered hydraulic studies were carried out by the company DEHC, which authorized the geometric variations in the already built works. Likewise, it is indicated that the execution of work No. 6 remains pending, since the corresponding procedures are being processed before the Water Directorate (Dirección de Aguas) and SETENA. Regarding work No. 7, it is stated that its execution concerns the MOPT-CONAVI. For its part, work No. 8 will be included in the 2024 budget, while No. 9 constitutes a long-term work.
From this perspective, although the authority reports that actions are being processed in pursuit of executing all the proposed works, it is also acknowledged that works Nos. 6, 7, 8, and 9 have not been fully executed.
Furthermore, note that by resolution at 12:27 p.m. on September 2, 2022, the respondent mayor was ordered as evidence for a better decision: “send to this Court a schedule, indicating the pending works to resolve what was ordered by the Chamber, as well as the actions taken to complete such works and the dates on which they will be finished.” In this regard, the respondent limited himself to providing official letter SCMRP-475-2022 of September 7, 2022, signed by the head of the Storm Drain Network Construction and Maintenance Section (Sección de Construcción y Mantenimiento de Red Pluvial), in which he stated:
"That through budget code 5131900000-00452-00000 called 'SUST. ALCANTARILLA COSTADO OESTE CLINICA CARLOS DURAN RIO OCLORO'; the budget funds were allocated for the execution of the corresponding works, the Nombre5649 allocated amounts to a total of ¢132,126,364.09. The technical area in charge of the projects decided to execute the works under the modality of 'work by administration' (obra por administración), so a budget modification was requested and the funds were distributed as follows, in order to process the purchases of materials and contracting of required engineering services:
Nombre5649 Nombre de la Partida Nombre del Objeto del Gasto Justificación (Bien o servicio a adquirir) Telf3459 2- Materiales y Suministros MATERIALES Y PRODUCTOS MINERALES Y ASFALTICOS Purchase of aggregates (sand, stone, cement, ready-mix concrete) for the execution of the project.
Telf3460 1- Servicios ALQUILER DE MAQUINARIA, EQUIPO Y MOBILIARIO Rental of equipment (dump trucks, back hoe) for the execution of the project.
Telf3461 2- Materiales y Suministros MATERIALES Y PRODUCTOS METALICOS Purchase of metallic materials (rebar of various diameters, nails, formwork) for the execution of the project.
Telf1154 2- Materiales y Suministros MADERA Y SUS DERIVADOS Purchase of wood (planks, strips) for use in the execution of the project.
Telf3462 1- Servicios OTROS ALQUILERES Rental of portable toilets for use by crew workers; they will be placed at the project site.
Telf3462 2- Materiales y Suministros MATERIALES Y PRODUCTOS DE PLASTICO Purchase of pipes of various diameters for installation in the project.
Telf3463 1- Servicios SERVICIOS GENERALES Contracting of security and surveillance at the project site, for the safeguarding of the Section's machinery and equipment and construction materials.
500 000,00 2- Materiales y Suministros UTILES Y MATERIALES DE RESGUARDO Y SEGURIDAD For purchase of flashlights and safety equipment for the crew workers who will be in the execution of the project.
Currently, the direct hiring process 2022CD-000698-0015499999 called 'Geometric Design, structural and geotechnical studies of the Ocloro channel' is being processed. The contractual object of this hiring is the Geometric Design, structural and geotechnical studies of the Ocloro River channel, Dirección2724. A budget reservation of ¢10,000,000.00 is available (SIAM request #11715), for the contracting thereof. This study aims to carry out a topographical survey and final construction design of the hydraulic mitigation work in Dirección73, specifically on the Ocloro River; this study must compile the engineering information necessary for its construction; it is not omitted to indicate that the study in question is in the award process. Once the aforementioned contract is awarded, and the balance of the budget reservation is released, a new budget reservation will be processed to handle the contracting of the necessary Environmental Supervision (Regencia Ambiental), as well as the permits before the Water Directorate (Dirección de Aguas) and Setena.
In addition, from the information that will be obtained from the studies of contract 2022CD000698-0015499999, it will be possible to determine with greater accuracy the final designs as well as the quantity of materials required for the execution of the works. Thus, purchase requests can be processed as appropriate. In addition to the above, it is clarified that intervention stages numbers 8, 9, and 10 are the responsibility of the Municipality of San José, so what proceeds for the year 2023 is the planning of the designs, and depending on said designs, the corresponding budget procedures can be carried out.” As things stand, note that the municipal corporation did not provide the requested schedule or the scheduled dates for the completion of the works required to comply with the provisions of judgment No. 2016-007570 at 9:05 a.m. on June 3, 2016, a situation that is aggravated considering that even by interlocutory judgment No. 2018-001791 at 9:40 a.m. on February 6, 2018, the initially granted period had already been extended, and even that extension has been expired for more than three years.
Consequently, disobedience to what was ordered in judgment No. 2016-007570 at 9:05 a.m. on June 3, 2016, is proven.
VI.Finally, it must be clarified to the petitioner that this jurisdiction is not competent to determine whether what was recommended in the technical study represents the best measures to adopt, or whether another particular work, different from the one recommended, should be carried out. The foregoing is a matter of legality that must be verified by the administration itself and the other bodies responsible for supervising and authorizing the works.
As things stand, it is appropriate to declare this aspect of the petition denied. (...)
Therefore:
The petition filed is partially granted only regarding the omission in the total execution of the works ordered in judgment No. 2016-007570 at 9:05 a.m. on June 3, 2016. Nombre1010, in his capacity as mayor of San José, or whoever holds the office, is reiterated the immediate compliance with the provisions of judgment No. 2016-007570 at 9:05 a.m. on June 3, 2016, under warning that a certification of documents (testimonio de piezas) will be ordered sent to the Public Prosecutor's Office (Ministerio Público) against him if he fails to do so. In all other respects, the petition filed is denied. Notify this judgment personally to Nombre1010, in his capacity as mayor of San José.” That pronouncement was personally notified to Nombre1010, in his capacity as mayor of San José, on September 20, 2022.
“VI.- Regarding the non-execution petition. In the sub lite, the petitioners file a joinder (coadyuvancia) request within this process.
In this regard, the Chamber notes that the requested joinder was filed after the issuance of judgment No. 2016007570 at 9:05 a.m. on June 3, 2016, by means of which this Chamber resolved the sub lite.
In situations such as the one described above, the Chamber has resolved as follows:
“I- REGARDING THE REQUESTED JOINDER. In accordance with Article 34, of the Ley de la Jurisdicción Constitucional, third parties to the process may file a joinder request, which is a form of adhesive intervention that occurs when a person acts in a process, adhering to the claims of one of the main parties. Consequently, anyone having a direct interest in the outcome of the recurso is entitled to act as a coadjuvant; however, not being the main party, the coadjuvant would not be directly affected by the judgment, that is, the effectiveness of the latter could not reach him/her directly and immediately, nor does the res judicata status of the pronouncement affect him/her (See, among others, judgments numbers 3235 at 09:20 a.m. on October 30, 1992, and 2010-000254 at 11:28 a.m. on January 8, 2010). Now, in the present case, it is not verified that the interested parties appeared as coadjuvants in this amparo process while it was pending, but rather it is only now, almost 9 years later, that they come to request said joinder. Consequently, given the procedural status of this matter, the aforementioned joinder request is inadmissible, and it is so declared.” (See vote No. 2018-019513 at 9:45 a.m. on November 27, 2018).
In the identical sense, through judgment No. 2020-018870 at 9:40 a.m. on November 13, 2018, the Chamber resolved:
“IV.- Regarding the joinder request of the petitioners. In accordance with Article 34 of the Ley de la Jurisdicción Constitucional, whoever has a legitimate interest in the outcome of the recurso may appear and intervene in the case file as a coadjuvant of the plaintiff or the defendant. However, the truth is that the appropriate procedural moment to appear as such is prior to the issuance of the judgment. On the other hand, this Court has repeatedly pointed out that the coadjuvant, not being the main party, will not be directly affected by the judgment, that is, the effectiveness thereof cannot reach him/her directly and immediately, nor does the res judicata status of the pronouncement affect him/her, although in amparo matters the effectiveness of what was resolved may favor him/her, due to the erga omnes nature of the jurisprudence and precedents of the constitutional jurisdiction (see judgment No. 2015-3569). Due to the foregoing, the request to have them as coadjuvants and directly affected parties is rejected as improper, since the joinder petition was filed after the judgment was issued in this recurso, and as already indicated, its effects would only favor them indirectly.” Thus, the Chamber finds no merit whatsoever to vary the stated criterion, so the filed joinder request is rejected (…)
Therefore:
The petition filed is denied.”
“VII.- Regarding the non-execution petition. In the sub lite, the petitioners file a subsequent petition in relation to judgment No. 2016007570 at 9:05 a.m. on June 3, 2016. They allege that, because the Municipality of San José did not execute the works ordered by this Chamber, on June 26, 2023, they suffered a flood, in which the water reached 1.70 centimeters. They point out that the force of the water was such that it tore off gates, doors, and walls; even several neighbors were trapped in their houses and vehicles, so they had to be rescued by firefighters. They add that elderly persons in the area could not leave their houses by their own means, and other individuals suffered panic attacks, as a result of which they had to be assisted. They relate that as a result of the flood they lost various belongings, including vehicles, white goods, clothing, food, and the houses suffered severe damage; furthermore, disease outbreaks appeared with symptoms such as diarrhea and vomiting.
They claim that they have not received any visit from the respondent mayor or engineer in order to offer them a definitive solution to the problem presented. They state that their concern is aggravated, since the rainiest months are August, September, October, November, and December, so they fear that the housing development will flood again. They consider that this situation has caused them psychological damages and violates their fundamental rights. They request that the recurso de amparo be granted and the respondent authorities be ordered to complete the pertinent works to prevent floods in Ciudadela Calderón Muñoz. In this regard, the Chamber observes that none of the petitioners is a party in this process. Now, regardless of the foregoing, they describe a situation containing facts subsequent to those resolved in the sub lite. For this reason, the brief received in the Chamber Secretariat on August 9, 2023, is detached, so that it be processed as a new matter (…)
Therefore: Detach the brief received in the Chamber Secretariat on August 9, 2023, so that, in the terms of Considerando VII of this pronouncement in fine, it be processed as a new matter.”
“VIII.- REGARDING THE FILED PETITION. In the case, the mayor of San José provides official letter No. SCMRP-111-2024, in which it reads: “I proceed to inform you that according to the deadlines stipulated by the Constitutional Chamber of the Supreme Court of Justice in the recursos de amparo filed by the neighbors of both the Ocloro River and Ciudadela Calderón Muñoz (Table No. 1), I must state to you the need for the Chamber to become aware of and consider the extension of the already stipulated deadlines, since the work required in those places cannot be carried out during the winter period; building this type of works in winter is very dangerous and exposes the lives of the people who will work on this project, in addition to exposing the population to floods, once again we appeal to your discernment and we inform the Chamber of this high risk and we again set forth the schedule of dates (Table No. 2), to be met under realistic deadlines not only adapted to the nature of the climate, but to due process and adhering to the laws governing our legal system regarding contracting law, environmental procedures, and budget management: (…) I do not omit to also state to you that, by the end of the First Half of 2024, the studies and designs for obtaining plans will be concluding; said studies were contracted through the following SICOP procedures: (…) It is reported that the budget is being requested for the execution of stage 10 A, so that the bidding process can be carried out in this second half of 2024 and execution can begin in January 2025, as mentioned in table 2.
All of the foregoing with the objective of making this situation known to the Constitutional Chamber and, at the same time, requesting an extension of deadlines to complete works in the affected areas correctly and without putting the population at risk." SECOND: Pursuant to what was expressed by the Storm Drain Network Maintenance Section (Sección de Mantenimiento de la Red Pluvial), through official letter SCMRP-111-2024, this Municipality respectfully requests that Honorable Constitutional Chamber extend the time period granted in the Resolutions cited above.” In this regard, although a schedule is provided, where works to be completed up to 2028 are observed, note that the extension request is openly improper. In this sense, note that almost eight years have elapsed since the issuance of judgment No. 2016007570 at 9:05 a.m. on June 3, 2016, without the corresponding actions to resolve the situation subject to this recurso having materialized to date.
Indeed, an extension of time already occurred, which was granted through interlocutory resolution No. 2018001791 at 9:40 a.m. on February 6, 2018. Therefore, it is unreasonable for the respondent now to seek, according to the provided schedule, a four-year extension more for compliance with what was ordered by the Chamber. Consequently, the filed request is dismissed. (…)
Therefore:
The petition filed is denied.”
In the sub lite matter, Nombre47883 files a non‑execution petition with respect to judgment no. 2016007570 of 9:05 a.m. on June 3, 2016.
First, it is appropriate to note that, although the petitioner is not a party to the proceeding, it is no less true that this Tribunal has repeatedly held that, in environmental matters, as in the sub examine case, vicarious standing (legitimación vicaria) is admissible, pursuant to Article 105 of the Biodiversity Law (Ley de Biodiversidad), which provides that “Any person shall have standing to bring actions in administrative or judicial venues in defense and protection of biodiversity.” Therefore, this non‑execution petition shall be heard on the merits.
Second, recall that the principal judgment in the sub lite matter ordered: “Nombre1010, in his capacity as Municipal Mayor of San José, or whoever occupies that office, is ordered to carry out, within a non‑extendable period of 6 months from notification of this judgment, the studies necessary to scientifically verify the hydraulic condition of the Ocloro River, and within the 6 months following that period, to implement the infrastructure works (obras de infraestructura) required to prevent flooding in the Ciudadela Calderón Muñoz sector.” Now, from both the interlocutory orders previously issued by this Chamber in this matter and the evidence on the record, it can be inferred that the local government of San José has undertaken actions aimed at resolving the flooding problem affecting Ciudadela Calderón Muñoz. For example, this Tribunal has verified the completion of works 1, 2, 3, 4, and 5.
However, the respondent authority itself acknowledges that the local corporation has not completed all of the actions necessary to address the problem at issue. In that regard, the procedure denominated “FLUVIAL MITIGATION WORK, OCLORO RIVER CHANNEL, Dirección2722” is currently being processed, the purpose of which is the relocation of a 600‑mm sanitary sewer pipe that runs along the path of the future stormwater channel. Additionally, in the year 2027 it is expected that the relocation of the sanitary, potable water, and National Power and Light Company (Compañía Nacional de Fuerza y Luz) easements will be carried out on Dirección2725. Further, this Chamber was informed that in the year 2026 works will be designed that may possibly be executed in 2027 or 2028, related to a widening of the channel that passes along national route no. 209.
Thus, despite the fact that the principal judgment in this matter dates from June 3, 2016, and that the period to comply with what was ordered therein expired on April 11, 2018 — that is, more than seven years ago — it is not apparent that the flooding problem of Ciudadela Calderón Muñoz has been duly resolved, given that works remain to be completed. For that reason, the non‑execution petition filed is granted. Now, given that the person currently serving as mayor of San José is different from the person to whom the order in question was previously directed, the proper course is to order compliance with the provisions of the aforementioned judgment to whoever currently holds that office, as has been ordered in similar situations (see judgments nos. 2024019235 of 9:30 a.m. on July 9, 2024, 2024019556 of 9:20 a.m. on July 12, 2024, 2025026975 of 9:30 a.m. on August 26, 2025, 2025031855 of 9:20 a.m. on October 1, 2025, and 2025034689 of 9:20 a.m. on October 24, 2025, among many others).
Finally, as to the objections raised by the petitioner concerning the works executed by the respondent local corporation, since she considers that they would not adequately resolve the issue that is the subject of this matter, it should be noted that this is not to be resolved in this ordinary judicial pathway, especially considering that this Chamber did not define the manner in which the above‑mentioned order must be fulfilled; rather, what was ordered is the implementation of “the infrastructure works required to prevent flooding in the Ciudadela Calderón Muñoz sector,” which does not imply that the solution must be specifically the one sought by the amparo petitioner.
The parties are advised that if any paper document has been provided, as well as objects or evidence contained in any electronic, computer, magnetic, optical, telematic device or one produced by new technologies, these must be removed from the office within a maximum period of 30 business days from notification of this judgment. It is warned that any material not removed within this period will be destroyed, in accordance with the provisions of the “Reglamento sobre Expediente Electrónico ante el Poder Judicial,” approved by the Corte Plena in article XXVI of session no. 27-11 of August 22, 2011, published in the Boletín Judicial no. 19 of January 26, 2012, as well as in the agreement of the Consejo Superior del Poder Judicial, approved in article LXXXI of session no. 43-12 held on May 3, 2012.
Por tanto:
The non‑execution petition filed is granted. Nombre47884, in his capacity as mayor of San José, or whoever exercises that office in his stead, is ordered to comply with the provisions of judgment no. 2016007570 of 9:05 a.m. on June 3, 2016. The respondent party is warned that, pursuant to Article 71 of the Constitutional Jurisdiction Law (Ley de la Jurisdicción Constitucional), a person who receives an order that must be complied with or enforced, issued in an amparo proceeding, and does not comply with it or does not enforce it, shall be punished by imprisonment of three months to two years, or a fine of twenty to sixty days, provided that the offense is not more severely penalized. This judgment shall be personally notified to Nombre47884, in his capacity as mayor of San José, or to whoever exercises that office in his stead.
Nombre210.
Nombre211 a.i Paul Rueda L.
Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Ingrid Hess H.
Jose Roberto Garita N.
SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas cuarenta minutos del once de noviembre de dos mil veinticinco .
Gestión posterior planteada por Nombre47883, en relación con la sentencia nro. 2016007570 de las 9:05 horas de 3 de junio de 2016.
Resultando:
Redacta el Magistrado Nombre41880; y,
Considerando:
“IV.- Sobre el caso concreto. Del estudio de los autos, se tiene que el pasado 11 de noviembre de 2015, la recurrente planteó 2 reclamos en relación con el colapso del sistema de alcantarillado y desbordamiento de aguas negras y basura en su comunidad, que según indicó, le produjo graves daños en su propiedad el 27 de octubre de 2015, y que se repitió el 11 de noviembre de 2015; pidió que se tomaran medidas para evitar lo sucedido a futuro, que se le informara de lo que se pretendía realizar al respecto, y que se le indemnizara por los daños producidos. Debe indicarse de previo a la amparada, que no le corresponde a esta Jurisdicción determinar si la administración debe ser tenida como responsable civil de los daños atribuidos e indemnizar a la amparada, por lo que la eventual disconformidad con el rechazo de su reclamo en tal sentido por parte de la recurrida, es una discusión que corresponde ser planteada en la vía de legalidad, si así lo tiene a bien la recurrente. En cuanto a la acusada falta de atención al problema de salud y ambiental referido, y de su gestión en este sentido, se procede a resolver por el fondo.
En efecto, la recurrente acusa que a pesar de las graves secuelas de lo ocurrido en octubre de 2015 por el desbordamiento del Río Ocloro, no se han tomado las medidas requeridas para evitar que ocurra una situación similar. Al respecto, la Municipalidad recurrida fue enfática en señalar, bajo fe de juramento, que las graves inundaciones producidas el 27 de octubre de 2015, fueron producto de un evento extraordinario de lluvia, en el que los ríos Ocloro y María Aguilar, así como las quebradas Pavas y Rivera, alcanzaron su máximo nivel y en aquellos lugares donde no se desbordaron, superaron los niveles de los puntos de descarga del sistema pluvial, lo que provocó que el agua no fluyera por dichas tuberías, sino pasado el aguacero; lo cual no fue producto de la condición del alcantarillado. Asimismo, señalaron que la Sección Construcción y Mantenimiento de la Red Pluvial trabajó en conjunto con la Oficina de Gestión Municipal de Riesgo a Desastres y la Comisión Nacional de Emergencias para formular un programa de Atención de la Cuenca del río Ocloro; e indican estar prontos a licitar un estudio de la microcuenca del Ocloro, con el fin de determinar científicamente la condición hidráulica de ese río y proponer obras de infraestructura que mitigaran las inundaciones.
No obstante, sobre este último aspecto, a pesar de que han transcurrido 7 meses desde la inundación ocurrida el 27 de octubre de 2015, la Municipalidad recurrida ni siquiera hace alusión actualmente a un cronograma ya establecido para verificar la situación real de la contención del Río Ocloro ante un eventual hecho natural como el que ya se produjo, lo cual es primordial según con lo señalado por el Área Rectora de Salud, quien en el informe CS-URS-471-2016 del 25 de mayo de 2016 concluyó:
“4.1. Con relación a la verificación que solicita la Sala Constitucional en cuanto a si las viviendas del sector corren algún peligro de inundación por obstrucción de basuras. La respuesta es que durante la ocurrencia de precipitaciones intensas, es de esperar que el río también arrastre todo tipo de residuos sólidos que se encuentre a lo largo de su cuenca: lo cual a su vez, incrementa el riesgo de que se presenten obstrucciones principalmente en los sectores en que el río se encuentra entubado; es decir, los sectores entubados son los más vulnerables a obstrucciones en razón de las limitaciones de espacio en sus secciones, lo cual no ocurre con los sectores del río con cauce abierto: con base en lo dicho, existe una razonable probabilidad de ocurrencia de inundaciones en el sitio por obstrucciones en los sectores entubados. Con relación a la siguiente consulta de que ocurran inundaciones por deficiencias en el alcantarillado o mala disposición de las aguas y canalización del río Ocloro; una respuesta certera a esta consulta está en función de estudios hidrológicos e hidráulicos con que cuente el órgano competente, en este caso la Municipalidad.
A partir de los resultados de estos estudios y memorias de cálculo es posible definir si la ocurrencia de las inundaciones obedece a la existencia de áreas reducidas en las secciones de evacuación existente y/o a defectos en el diseño del sistema pluvial, por lo que es necesario revisar todo el trayecto de la cuenca. 4.2. En cuanto a la solicitud de la señora Ministra en el sentido de llegar a determinar y concluir si el área denunciada por la señora Nombre47885, representa un peligro para la salud pública de los habitantes de ese sector. La respuesta es que el río se encuentra contaminado con aguas residuales y al llegar estas aguas al interior de las viviendas producto de un desbordamiento del río se va a generar una condición insalubre, por lo que cada vez que ocurra una inundación va a existir un peligro real para la salud de los residentes del lugar. Con relación a las recomendaciones que solicita la señora Ministra.
Esta Rectoría aconseja solicitarle a la Municipalidad los respectivos estudios técnicos, planes y cronogramas de actividades de obras que le han prometido a la comunidad para resolver los problemas de inundaciones que nos ocupan.” Según informó bajo juramento la autoridad recurrida, lo ocurrido fue un evento extraordinario no previsto. Sin embargo, en el sub examine, a partir de lo sucedido, al menos de octubre de 2015 a la fecha, la administración sabe lo que puede llegar a ocurrir de volver a tener precipitaciones como las de entonces, y en consecuencia, está obligada a tomar oportuna y responsablemente todas las medidas necesarias, a fin mitigar los efectos y desastres que ya se conoce pueden llegar a ocurrir de nuevo –lo cual fue un hecho público y noticioso-. En la inspección realizada por el Ministerio de Salud, también se determinó lo siguiente:
“3.4. -Entre el puente y el sector Oeste del estacionamiento de la sucursal de la Dos Pinos en Bo. Lujan [Dirección2559] se pudo observar el cauce del río parcialmente obstruido con desechos orgánicos y posiblemente con sedimentos…No obstante esta condición y en el caso de que ocurra un desbordamiento en este punto, es criterio del suscrito que el evento no afectaría a la Ciudadela Calderón Muñoz, en razón de que entre ambos sitios existe una distancia de separación de unos 600 m y por otro lado, por la topografía imperante en el sitio, es de esperar que el desbordamiento regrese al cauce del rio sin recorrer más de 100 m. 3.5. -A una distancia aproximada de unos 400 m aguas abajo respecto al punto de referencia indicado en la sección anterior, se encuentra el edificio CEDESSO y justamente en este sitio se inicia un tramo entubado del río que termina a unos 25 m al Oeste de los Multifamiliares de la Ciudadela Calderón Muñoz, la cual colinda con el sector Este de Lomas de Ocloro.
El edificio CEDESSO se ubica específicamente al Noreste de la Clínica Carlos Durán y es el sector del cauce abierto del río Ocloro más cercano a la Ciudadela Calderón Muñoz, encontrándose a una distancia aproximada de 100 m…Sobre la corona del ducto por donde fluye el río y en los linderos de la propiedad del edificio CEDESSO se construyó una malla perimetral en la cual se pudo apreciar la evidencia de material de desecho orgánico transportado por el río que quedó atrapado en la malla perimetral del edificio en cuestión, alcanzando alturas entre 1.0 y 1.5 m sobre la corona del ducto... Dicha evidencia es el resultado de la ocurrencia de una avenida extraordinaria que probablemente asociada o no con alguna obstrucción del entubamiento es posible que este tipo de eventos coadyuvados por la cercanía y condiciones topográficas favorables lleguen a causar inundaciones a la Ciudadela Calderón Muñoz, sitio de residencia de la denunciante. 3.6.-Fundamentado en la inspección visual de campo realizada en este día en la zona descrita en la fotografía #1 se pudo determinar que el río también transporta aguas residuales del tipo doméstico en su mayor parte.” Así las cosas, considera este Tribunal que lleva razón la recurrente en señalar, desecho orgánico transportado por el río que quedó atrapado en la malla perimetral del edificio en cuestión, alcanzando alturas entre 1.0 y 1.5 m sobre la corona del ducto...
Dicha evidencia es el resultado de la ocurrencia de una avenida extraordinaria que probablemente asociada o no con alguna obstrucción del entubamiento es posible que este tipo de eventos coadyuvados por la cercanía y condiciones topográficas favorables lleguen a causar inundaciones a la Ciudadela Calderón Muñoz, sitio de residencia de la denunciante. 3.6.-Fundamentado en la inspección visual de campo realizada en este día en la zona descrita en la fotografía #1 se pudo determinar que el río también transporta aguas residuales del tipo doméstico en su mayor parte.” Así las cosas, considera este Tribunal que lleva razón la recurrente en señalar, que existen suficientes indicios de que puedan volver a ocurrir las inundaciones de las que ha sido objeto, por no atenderse de forma oportuna lo requerido, para al menos aminorar sus efectos. No basta con indicar que se está programando realizar un estudio de la microcuenca, si ni siquiera se ha concretado su licitación, programación y ejecución.
Por otro lado, el Ministerio recurrido también advirtió otros problemas de obstaculización en la malla perimetral del Edificio Cendesso que pueden agravarse ante precipitaciones mayores, y que deben ser atendidos constante y oportunamente por la Municipalidad recurrida. Por consiguiente, el amparo debe ser declarado con lugar en cuanto a este extremo se refiere.
V.Sobre las gestiones planteadas por la recurrente el 19 de noviembre de 2015, se tiene que mediante oficios ALCALDIA 06493-2015 y ALCALDIA06497-2015, ambos del 20 de noviembre de 2015, la Alcaldía recurrida le comunicó a la amparada que su gestión estaba siendo trasladada a las dependencias respectivas y que dadas las características de esta, la respuesta tomaría más tiempo de lo que establece la ley, lo cual le fue notificado al correo ...443. Por oficio ALCALDIA 00689-2016 del 1 de marzo de 2016, la Alcaldesa rechazó el reclamo de la recurrente en cuanto al pago de los daños sufridos por la inundación del 27 de octubre de 2015, por falta de prueba, lo cual le notificó a la dirección electrónica ...443; respecto de lo cual, reitera este Tribunal a la recurrente, puede acudir a la vía ordinaria a impugnar dicho resultado, de encontrarse disconforme con lo resuelto en cuanto a dicho aspecto se refiere.
Sin embargo, aun cuando han transcurrido casi 6 meses desde sus gestiones, la autoridad recurrida omitió informarle sobre las medidas que adoptaría dicho Municipio para evitar las inundaciones en la zona en cuestión, la programación de las mismas, si existían investigaciones sobre los trabajos realizados y la solución que se daría al caso, tal como lo solicitó ella expresamente. Por consiguiente, hay aspectos de mera información que no fueron atendidos y otros relativos a la solución de la problemática denunciada, de los que tampoco informó a la amparada. En consecuencia, el recurso también debe ser declarado con lugar, en este sentido. (…)
Por tanto:
Se declara con lugar el recurso. Se ordena a Nombre1010, en su condición de Alcalde Municipal de San José, o a quien ocupe el cargo, que proceda en el plazo improrrogable de 6 meses contado a partir de la notificación de esta sentencia, a realizar los estudios que se requieran para verificar científicamente la condición hidráulica del Río Ocloro, y en los 6 meses siguientes a dicho plazo, implementar las obras de infraestructura que se requieran para evitar las inundaciones en el Dirección2723. Asimismo, se ordena al recurrido adoptar de inmediato todas las medidas necesarias y posibles que coadyuven a mitigar las inundaciones que puedan producirse en dicho lugar, mientras se realizan los estudios y las obras en cuestión; así como también, deberá contestar y notificar a la recurrente, en un plazo no mayor a 3 días hábiles a partir de la notificación de este pronunciamiento, el resto de la información solicitada en las gestiones planteadas el 19 de noviembre de 2015, que no fueron atendidas por el recurrido en el oficio ALCALDIA 00689-2016 del 1 de marzo de 2016.
Se advierte a la autoridad recurrida, que de conformidad con lo establecido por el artículo 71 de la Ley de la Jurisdicción Constitucional se impondrá prisión de tres meses a dos años o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada dentro de un recurso de amparo y no la cumpliere o no la hiciere cumplir, siempre que el delito no esté más gravemente penado. Se condena a la Municipalidad de San José al pago de las costas, daños y perjuicios ocasionados con los hechos que sirven de base a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso administrativo. Notifíquese esta resolución a Nombre1010, en su condición de Alcalde Municipal de San José, o a quien ocupe el cargo, en forma personal. La Magistrada Nombre5236 salva el voto y rechaza de plano el recurso. El magistrado Nombre33846 pone nota.”.
Tal pronunciamiento fue notificado de manera personal al alcalde Municipal de San José el 8 de junio de 2016.
“II.- En el sub lite, el recurrente acusa desobediencia a lo ordenado por este Tribunal, toda vez que la autoridad recurrida no ha tomado medidas inmediatas para mitigar las inundaciones que se presentan en la ciudadela Calderón Muñoz; toda vez, que el 8 y 10 de junio de 2016 el Rio Ocloro se desbordó y produjo inundaciones en el lugar. Al respecto, informó el Alcalde Municipal de San José , que ha emitido diferentes acciones inmediatas. Indicó que la Sección de Mantenimiento y Construcción de Red Pluvial, en el oficio SCMRP-420-2016 del 17 de junio de 2016, dispuso el Plan de Medidas de Mitigación para Reducir las Inundaciones en toda la microcuenca del Rio Ocloro para la atención integral de la problemática y están en ejecución actualmente trabajos en el cauce con cuadrillas del municipio. Ahora bien, de lo informado bajo juramento y la prueba aportada por el recurrente, esta Sala considera que debe desestimarse la gestión del amparado.
Lo anterior, ya que de lo informado -con oportuno apercibimiento de las consecuencias, incluso penales, previstas en el artículo 44 de la Ley de la Jurisdicción Constitucional-, se desprende con claridad, que la Municipalidad recurrida no ha eludido lo ordenado por este Tribunal, toda vez que según informó el recurrido, existe un plan de atención para toda la cuenca del Rio Ocloro y con ello la solución de las inundaciones que se presentan en el sector de Calderón Muñoz; a su vez, se encuentran cuadrillas de la Municipalidad trabajando en el cauce del rio en cuestión para atender la problemática en su corto plazo; además, se trabaja para efectuar las licitaciones de los estudios científicos, construcción de puentes, y tal como consta en el oficio SCMRP-420-2016 del 17 de junio de 2016, mediante el cual se dispuso el Plan de Medidas de Mitigación para Reducir las Inundaciones en toda la microcuenca del Rio Ocloro, para ello se cuenta con un presupuesto de 200.000.000.00 colones; igualmente, este Tribunal contempla que la administración recurrida se encuentra dentro del plazo otorgado de 6 meses para llevar a cabo las obras necesarias para la atención de las inundaciones que se presentan en la zona de la Ciudadela Calderón Muñoz. Así las cosas, la Sala verifica que han existido actuaciones para que se lleve a cabo lo ordenado por la Sala. En consecuencia lo procedente es desestimar la gestión ya que deviene en prematura. (…)
Por tanto:
No ha lugar a la gestión formulada”.
“Por tanto: Se amplía el plazo conferido en la sentencia No. 2016-007570 de las 9:05 horas del 3 de junio de 2016, razón por la cual se le otorga a Nombre1010, en su condición de Alcalde Municipal de San José, o a quien ocupe dicho cargo, plazo hasta el 11 de abril de 2018 para realizar los estudios que se requieren para verificar científicamente la condición hidráulica del Río Ocloro, y en los 6 meses siguientes a dicha fecha, deberán implementar las obras de infraestructura que se requieran para evitar las inundaciones en el sector Ciudadela Calderón Muñoz. En lo demás, no ha lugar a la gestión planteada”.
“VI.- Sobre la gestión de inejecución. En el sub lite, las gestionantes acusan el incumplimiento a lo ordenado por esta Sala mediante sentencia No. 2016- 007570 de las 9:05 horas del 3 de junio de 2016, en la que se dispuso que en el plazo de 6 meses la autoridad recurrida debía realizar los estudios que se requirieran para verificar científicamente la condición hidráulica del Río Ocloro, y en los 6 meses siguientes a dicho plazo, implementar las obras de infraestructura que se requieran para evitar las inundaciones en el sector Ciudadela Calderón Muñoz. De previo debe advertirse, que en efecto la gestión fue planteada prematuramente, pues cuando acudieron a la Sala -12 de marzo de 2018-, la administración aún contaba con el plazo concedido por esta Sala para atender la situación planteada. En todo caso, la autoridad recurrida informó que la empresa Nombre47898 Ingenieros Consultores realizó un estudio que comprende el análisis hidrológico de las cuencas de aporte externo a las microcuencas del Río Ocloro.
Dicho estudio incluyó la caracterización morfométrica e hidrológica de dichos aportes externos, la caracterización de precipitaciones históricas en la zona de estudio y la generación de los hidrogramas producidos por las precipitaciones anteriormente mencionadas, para su posterior uso en el análisis hidráulico de los sistemas de drenaje de la microcuenca en cuestión. Se incluyó dentro del análisis general la acequia Las Arias; sin embargo, la misma no presenta aportes externos por lo que la hidrología de esta se consideró dentro del informe del análisis hidráulico. Del informe rendido bajo juramento se constató, que con respecto al sector de Barrio Luján se deben realizar cuatro obras con distinto grado de prioridad y en el Sector Calderón Muñoz se acreditó que se deben realizar cinco obras en distintos plazos –corto, mediado y a largo plazo-. Asimismo, que con la finalidad de atender lo ordenado por esta Sala e iniciar las obras de mitigación en los sectores afectados, la municipalidad accionada promovió a finales de 2017 la licitación abreviada No. 2017LA-000057-0015499999, para la instalación de dos tuberías de 2.44 m. de diámetro para que en el invierno del año 2018 se tuviera una mayor capacidad hidráulica, y poder mitigar así, el riesgo de inundaciones en el sector de Barrio Luján.
Al respecto, la municipalidad recurrida reconoce que la instalación de esas dos tuberías no es la solución definitiva, y que en caso de requerir mayor capacidad se realizarán los trabajos necesarios que en este caso será la colocación de una tercera tubería, según lo ha calculado la empresa DEHC. La licitación supra citada se promovió al amparo del Decreto 3l849-MINAE-SMOPT-MAG-MEIC de 2004 y sus reformas y el Decreto 37803-MINAE-SMOPT-MAG-MEIC de 2013 con sustento en los cuales se exime a las Municipalidades de realizar los trámites de viabilidad ambiental e impacto ambiental en obras de mantenimiento de alcantarillado pluvial; no obstante, de la gestión planteada y del informe dado bajo juramento se extrae, que existió oposición por parte de los vecinos para la realización de las obras y acudieron a la Defensoría de Los Habitantes quien a la fecha no ha emitido su informe, además los vecinos recurrieron a SETENA y la Dirección de Aguas para impedir las acciones del municipio recurrido.
Sobre este aspecto, se constató que la Dirección de Aguas del MINAE se opuso a los trabajos mencionados y le indicó a la municipalidad accionada que las obras que estaban llevando a cabo requieren de la aprobación de esa entidad y de SETENA. Situación que obligó a la recurrida a suspender las obras, cuya ejecución ahora dependería de lo que dictaminen la Dirección de Aguas del MINAE, SETENA y SINAC. Sobre el particular se desprende, que el estudio ordenado en sentencia ya fue realizado, y que algunas de las obras que la Municipalidad de San José estaba llevando a cabo para implementar las medidas respectivas, fueron suspendidas producto de las denuncias planteadas por los vecinos y los trámites previos que deben realizar; empero, están atendiendo lo prevenido. Por otro lado, debe advertirse a los gestionantes, que esta jurisdicción no es la competente para determinar si lo recomendado en el estudio técnico son las mejores medidas a adoptar, o si debe realizarse otra obra en particular, diversa a la recomendada. Lo anterior es una cuestión de legalidad que debe ser verificada por la propia administración y los demás órganos encargados de fiscalizar y autorizar las obras.
VII.Por otro lado, las gestionantes cuestionan que la municipalidad recurrida pretende favorecer los intereses económicos de empresas privadas, específicamente la Cooperativa de Productores de Leche Dos Pinos, y la Desarrolladora Nombre47897, esta última, quien lleva adelante un proyecto para la empresa 3-101-687989 S.A. Condominio Vertical Mixto Torres Trío. Cuestionan que la municipalidad no tiene porqué asumir las obras de dichas empresas ante los eventuales daños que produzcan y que de ser así, deben sentarse las responsabilidades disciplinarias y civiles respectivas a los funcionarios que lo han propiciado. Denuncian que esta última empresa, presentó estudios hidrológicos e hidráulicos confeccionados por “Geotecnia y Construcción”, hechos para el condominio Torres Trío, y no para la Cuenca del Río Ocloro. Asimismo, denuncian que el 2 de marzo de 2018, una cuadrilla de empleados del municipio accionado cortaron árboles en las orillas del cauce del parque municipal El Cerrito, que es reserva de la cuenta del Río Ocloro en Dirección73, sin contar con los permisos del Sistema de Áreas de Conservación (SINAC).
Lo anterior con la finalidad de iniciar el supuesto entubado de 200 metros que pretende realizar la municipalidad accionada, y que no es producto del estudio técnico realizado. Al respecto, este Tribunal coincide con la autoridad recurrida, en el sentido de que tales alegatos constituyen hechos nuevos, que no fueron invocados en el escrito de interposición de este recurso de amparo, por lo que, lo procedente es que sea en nuevo recurso donde se conozcan tales extremos. En razón de lo anterior, lo procedente es desglosar el escrito planteado, a los efectos de que tales extremos sean resueltos como corresponda en otro recurso.
Por tanto:
No ha lugar a la gestión formulada. Desglósese el escrito agregado a este expediente a las 09:04 horas del 12 de marzo de 2018, a fin de que se tramite como un asunto nuevo los aspectos indicados en el considerando VII.”
“V.- Sobre la gestión de inejecución. En el sub lite, la amparada plantea gestión de desobediencia en relación con la sentencia n.° 2016007570 de las 9:05 horas de 3 de junio de 2016, en la que se dispuso que en el plazo de 6 meses la autoridad recurrida debía realizar los estudios que se requirieran para verificar científicamente la condición hidráulica del río Ocloro, y en los 6 meses siguientes a dicho plazo, implementar las obras de infraestructura que se requieran para evitar las inundaciones en el sector Ciudadela Calderón Muñoz. La gestionante reclama que actualmente no se ha construido ninguna de las obras propuestas en el estudio realizado por DEHC. Asevera que únicamente se dio una obra de mitigación con tuberías pluviales dentro del vecindario, lo que no garantiza el librarse de peligro ante eventuales inundaciones. Añade que solo se han tramitado 10 millones de colones para estudios topográficos en la obra que corresponden al reemplazo de la alcantarilla corrugada. Alega que el plazo ordenado para la construcción de las obras a favor de la Ciudadela Calderón Muñoz ya venció. Solicita que se ordene ejecutar las nueve obras propuestas en el informe final de DEHC.
Al respecto, del informe rendido por la autoridad se desprende que, los estudios hidráulicos ordenados fueron llevados a cabo por la empresa DEHC, quien autorizó las variaciones geométricas en las obras ya construidas. Asimismo, se indica que resta la ejecución de la obra n.° 6, ya que se están gestionando los trámites correspondientes ante la Dirección de Aguas y SETENA. Con respecto a la obra n.° 7, se manifiesta que su ejecución atañe al MOPT-CONAVI. Por su parte; la obra n.° 8 será incluida en el presupuesto del 2024, mientras que la n.° 9 constituye una obra a largo plazo.
Desde este panorama, si bien la autoridad informa que se están gestionando acciones en aras de ejecutar la totalidad de las obras propuestas, véase que también se reconoce que las obras nros. 6, 7, 8 y 9 no han sido ejecutadas a cabalidad.
Además, nótese que mediante resolución de las 12:27 horas del 2 de setiembre de 2022, se ordenó como prueba para mejor resolver al alcalde accionado: “remitir a este Tribunal un cronograma, en el que se indiquen las obras pendientes para solventar lo ordenado por la Sala, así como las acciones realizadas para cumplir tales obras y las fechas en que estarán finalizadas”. Al respecto, el accionado se limitó a aportar el oficio SCMRP-475-2022 del 7 de setiembre de 2022 suscrito por el jefe de la Sección de Construcción y Mantenimiento de Red Pluvial, en el que indicó:
"Que mediante el código presupuestario 5131900000-00452-00000 denominado "SUST. ALCANTARILLA COSTADO OESTE CLINICA CARLOS DURAN RIO OCLORO"; se asignaron los fondos presupuestarios para la ejecución de las obras correspondientes, el Nombre5649 destinado es por un total de ¢132.126.364,09. El área técnica a cargo de los proyectos tomó la decisión de ejecutar las obras bajo la modalidad de "obra por administración", por lo que se solicitó una modificación presupuestaria y los fondos se distribuyeron de la siguiente manera, a fin de poder tramitar las compras de los materiales y contratación de servicios de ingeniería requeridos:
Nombre5649 Nombre de la Partida Nombre del Objeto del Gasto Justificación (Bien o servicio a adquirir) Telf3459 2- Materiales y Suministros MATERIALES Y PRODUCTOS MINERALES Y ASFALTICOS Compra de agregados (arena piedra, cemento, concreto premezclado) para la ejecución del proyecto.
Telf3460 1- Servicios ALQUILER DE MAQUINARIA, EQUIPO Y MOBILIARIO Alquiler de equipo (vagonetas, back hoe) para la ejecución del proyecto Telf3461 2- Materiales y Suministros MATERIALES Y PRODUCTOS METALICOS Compra de materiales metálicos (varillas en varios diámetros, clavos, formaleta) para la ejecución del proyecto Telf1154 2- Materiales y Suministros MADERA Y SUS DERIVADOS Compra de madera (tabla, regla) para uso en la ejecución del proyecto.
Telf3462 1- Servicios OTROS ALQUILERES Alquiler de cabinas sanitarias para uso de los funcionarios de las cuadrillas, se colocarán en el sitio del proyecto Telf3462 2- Materiales y Suministros MATERIALES Y PRODUCTOS DE PLASTICO Compra de tubería en varios diámetros para instalación en el proyecto Telf3463 1- Servicios SERVICIOS GENERALES Contratación de seguridad y vigilancia en el sitio del proyecto, para el resguardo de la maquinaria y equipo de la Sección y los materiales de construcción.
500 000,00 2- Materiales y Suministros UTILES Y MATERIALES DE RESGUARDO Y SEGURIDAD Para compra de linternas y equipo de seguridad para los funcionarios de las cuadrillas que estarán en la ejecución del proyecto.
Actualmente, se está tramitando la contratación directa 2022CD-000698-0015499999 denominada "Diseño Geométrico, estructural y estudios geotécnicos del canal del Ocloro". El objeto contractual de dicha contratación es el Diseño Geométrico, estructural y estudios geotécnicos del canal del Río Ocloro, Dirección2724. Se cuenta con una reserva presupuestaria de ¢10.000.000,00 (solicitud de SIAM #11715), para la contratación de lo mismo. Este estudio tiene como objetivo realizar un levantamiento y diseño constructivo final de la obra de mitigación hidráulica en el Dirección73, propiamente en el Río Ocloro, este estudio debe recopilar la información ingenieril necesaria para su construcción, no se omite indicar que el estudio en mención se encuentra en trámite de adjudicación. Una vez que se adjudique la contratación antes mencionada, y se libere el saldo de la reserva presupuestaria, se procederá a gestionar una nueva reserva presupuestaria para tramitar la contratación de la Regencia Ambiental necesaria, así como los permisos ante la Dirección de Aguas y Setena.
Además, de la información que se obtendrá de los estudios de la contratación 2022CD000698-0015499999; se podrá determinar con mayor exactitud los diseños finales como también la cantidad de materiales requeridos para la ejecución de las obras. Así se podrán tramitar las solicitudes de compra según sea el caso. Aunado a lo anterior, se aclara que las etapas de intervención números 8, 9 y 10 son responsabilidad de la Municipalidad de San José, por lo que procede para el año 2023 es el planteamiento de los diseños y dependiendo de dichos diseños se podrán realizar las gestiones presupuestarias correspondientes”.
Así las cosas, nótese que la corporación municipal no aportó el cronograma solicitado ni las fechas programadas para la finalización de las obras requeridas para cumplir lo dispuesto en la sentencia n.° 2016-007570 de las 9:05 horas de 3 de junio de 2016, situación que se agrava teniendo en cuenta que incluso ya mediante sentencia interlocutoria n.° 2018-001791 de las 9:40 horas de 6 de febrero de 2018 se había ampliado el plazo inicialmente otorgado e incluso tal ampliación se encuentra fenecida hace más de tres años.
En consecuencia, se acredita la desobediencia a lo ordenado en la sentencia n.° 2016-007570 de las 9:05 horas de 3 de junio de 2016.
VI.Finalmente, cabe aclararle a la gestionante que esta jurisdicción no es la competente para determinar si lo recomendado en el estudio técnico son las mejores medidas a adoptar, o si debe realizarse otra obra en particular, diversa a la recomendada. Lo anterior es una cuestión de legalidad que debe ser verificada por la propia administración y los demás órganos encargados de fiscalizar y autorizar las obras.
Así las cosas, procede declarar no ha lugar este extremo de la gestión. (...)
Por tanto:
Se acoge parcialmente la gestión formulada solo en cuanto a la omisión en la ejecución total de las obras ordenadas en la sentencia n.º 2016-007570 de las 9:05 horas de 3 de junio de 2016. Se reitera a Nombre1010, en su condición de alcalde de San José, o a quien ocupe el cargo, el cumplimiento inmediato de lo dispuesto en la sentencia n.° 2016-007570 de las 9:05 horas de 3 de junio de 2016, bajo la advertencia de ordenarse el testimonio de piezas ante el Ministerio Público en su contra si no lo hiciere. En todo lo demás, no ha lugar a la gestión formulada. Notifíquese esta sentencia a Nombre1010, en su condición de alcalde de San José, en forma personal”.
Tal pronunciamiento fue notificado personalmente a Nombre1010, en su condición de alcalde de San José el 20 de setiembre de 2022.
“VI.- Sobre la gestión de inejecución. En el sub lite, los gestionantes plantean solicitud de coadyuvancia dentro de este proceso.
Al respecto, la Sala advierte que la coadyuvancia solicitada fue formulada con posterioridad al dictado de la sentencia nro. 2016007570 de las 9:05 horas de 3 de junio de 2016, por medio de la cual esta Sala resolvió el sub lite.
En situaciones como la supra descrita, la Sala ha resuelto de esta forma:
“I- SOBRE LA COADYUVANCIA SOLICITADA. De conformidad con el artículo 34, de la Ley de la Jurisdicción Constitucional, terceros al proceso pueden interponer una solicitud de coadyuvancia, que es una forma de intervención adhesiva que se da, cuando una persona actúa en un proceso, adhiriéndose a las pretensiones de algunas de las partes principales. En consecuencia, se encuentra legitimado para actuar como coadyuvante quien ostente un interés directo en el resultado del recurso; sin embargo, al no ser actor principal, el coadyuvante no resultaría directamente afectado por la sentencia, es decir, la eficacia de ésta no podría alcanzarle de manera directa e inmediata, ni le afecta la condición de cosa juzgada del pronunciamiento (Véanse, entre otras, las sentencias números 3235 de las 09:20 horas del 30 de octubre de 1992 y la 2010-000254 de las 11:28 horas el 08 de enero de 2010). Ahora bien, en el presente caso no se constata que los interesados se apersonaran como coadyuvantes en el presente proceso de amparo mientras este se encontraba en trámite, sino que es hasta este momento, sea casi 9 años después, que acuden a solicitar la referida coadyuvancia. En consecuencia, dado el estado procesal del presente asunto, resulta inadmisible la referida solicitud de coadyuvancia, y así se declara”. (Ver voto nro. 2018-019513 de las 9:45 horas del 27 de noviembre de 2018).
En idéntico sentido, por medio de la sentencia nro. 2020-018870 de las 9:40 horas del 13 de noviembre de 2018, la Sala resolvió:
“IV.- Sobre la solicitud de coadyuvancia de las gestionantes. De conformidad con el artículo 34 de la Ley de la Jurisdicción Constitucional, quien tuviere un interés legítimo en el resultado del recurso puede apersonarse e intervenir en el expediente como coadyuvante del actor o del demandado. No obstante, lo cierto es que el momento procesal oportuno para apersonarse como tal, es previo al dictado de la sentencia. Por otro lado, en reiteradas ocasiones este Tribunal ha señalado, que el coadyuvante al no ser el actor principal, no resultará directamente afectado por la sentencia, es decir, la eficacia de esta no podrá alcanzarle de manera directa e inmediata, ni le afecta la condición de cosa juzgada del pronunciamiento, aunque en materia de amparo pueda favorecerle la eficacia de lo resuelto, debido al carácter de erga omnes que tiene la jurisprudencia y precedentes de la jurisdicción constitucional (ver sentencia No. 2015-3569). En razón de lo anterior, se rechaza por improcedente la solicitud de tenerlas como coadyuvantes y afectadas directas, ya que la gestión de coadyuvancia fue presentada luego de emitida la sentencia en este recurso, y según ya se indicó, sus efectos solo le favorecerían indirectamente”.
De este modo, la Sala no encuentra mérito alguno para variar el criterio vertido, por lo que se rechaza la solicitud de coadyuvancia formulada (…)
Por tanto:
No ha lugar a la gestión formulada”.
“VII.- Sobre la gestión de inejecución. En el sub lite, los gestionantes plantean gestión posterior en relación con la sentencia nro. 2016007570 de las 9:05 horas de 3 de junio de 2016. Alegan que, debido a que la Municipalidad de San José no ejecutó las obras que ordenó esta Sala, el 26 de junio de 2023 sufrieron una inundación, en la que el agua alcanzó 1.70 centímetros. Señalan que la fuerza del agua fue de tal magnitud, que arrancó portones, puertas y paredes; incluso, varios vecinos quedaron atrapados en sus casas y vehículos, por lo que debieron ser rescatados por los bomberos. Agregan que las personas adultas mayores de la zona no podían salir de sus casas por sus propios medios y otros sujetos sufrieron ataques de pánico, a causa de lo cual tuvieron que ser auxiliados. Refieren que producto de la inundación perdieron varios bienes, entre ellos, vehículos, línea blanca, ropa, alimentos y las casas sufrieron fuertes daños; además, se presentaron brotes de enfermedades con síntomas como diarrea y vómito.
Reclaman que no han recibido visita alguna por parte del alcalde ni del ingeniero accionados a fin de ofrecerles una solución definitiva al problema expuesto. Manifiestan que su preocupación se agrava, ya que los meses más lluviosos son agosto, setiembre, octubre, noviembre y diciembre, de manera que temen que se vuelva a inundar la ciudadela. Estiman que esta situación les ha generado daños psicológicos y vulnera sus derechos fundamentales. Solicitan que se acoja el recurso de amparo y se ordene a las autoridades recurridas culminar las obras pertinentes para evitar inundaciones en Ciudadela Calderón Muñoz. Al respecto, la Sala observa que ninguno de los gestionantes es parte en este proceso. Ahora, independientemente de lo anterior, estos describen una situación que contiene hechos posteriores a los resueltos en el sub lite. Por tal motivo, se desglosa el escrito recibido en la Secretaría de la Sala el 9 de agosto de 2023, a fin de que sea tramitado como un asunto nuevo (…)
Por tanto: Desglósese el escrito recibido en la Secretaría de la Sala el 9 de agosto de 2023, a los efectos de que, en los términos del considerando VII de este pronunciamiento in fine, sea tramitado como un asunto nuevo”.
“VIII.- SOBRE LA GESTIÓN FORMULADA. En la especie, el alcalde de San José aporta el oficio nro. SCMRP-111-2024, en el que se lee: “Procedo a informarle que según los plazos estipulados por la Sala Constitucional de la Corte Suprema de Justicia en los recursos de amparo interpuestos por los vecinos tanto del Río Ocloro como de la Ciudadela Calderón Muñoz (Cuadro No. 1), he de manifestarle al necesidad de que la Sala tome conciencia y en consideración la ampliación de los plazos ya estipulados por cuanto los trabajos requeridos en esos lugares no es posible llevarlos a cabo en periodo de invierno, construir este tipo de obras en invierno es muy peligroso y expone las vidas de las personas que laboraran en este proyecto, además, de exponer a inundaciones a la población, una vez más apelamos a su discernimiento y damos por informada a la Sala sobre este alto riesgo y exponemos nuevamente el cronograma de fechas (Cuadro No. 2), a cumplir bajo plazos reales no sólo adaptados a la naturaleza del clima, sino al debido proceso y apegados a las leyes que rigen nuestro ordenamiento jurídico en materia de ley de contratación, trámites ambientales y manejos presupuestario: (…) No omito manifestarle también que, para finales del I Semestre del 2024, se estará concluyendo con los estudios y diseños para la obtención de planos, dichos estudios se contrataron mediante los siguientes procedimientos SICOP: (…) Se informa que se está solicitando el presupuesto para la ejecución de la etapa 10 A, para que se realice el proceso de licitación en este segundo semestre del 2024 e iniciar ejecución en enero del 2025, tal y como se menciona en el cuadro 2.
Todo lo anterior con el objetivo de hacer del conocimiento a la Sala. Constitucional de dicha situación y a la vez, solicitar ampliación de plazos para concluir obras en las zonas de afectación de la manera correcta y sin poner en riesgo a la población." SEGUNDO: Conforme a lo exteriorizado por la Sección de Mantenimiento de la Red Pluvial, mediante el oficio SCMRP-111-2024, esta Municipalidad solicita respetuosamente a esa Honorable Sala Constitucional, la ampliación del plazo otorgado en la Resoluciones supra citadas”. Al respecto, si bien se aporta un cronograma, donde se observan obras a finalizar hasta 2028, adviértase que la solicitud de ampliación resulta abiertamente improcedente. En este sentido, nótese que han transcurrido casi ocho años desde el dictado de la sentencia nro. 2016007570 de las 9:05 horas de 3 de junio de 2016, sin que a la fecha se hayan concretado las acciones correspondientes para solventar la situación objeto de este recuro.
Incluso, ya medió una ampliación de plazo que se concedió mediante resolución interlocutoria nro. 2018001791 de las 9:40 horas de 6 de febrero de 2018. Por ende, resulta irrazonable que ahora el recurrido pretenda, según el cronograma aportado, una ampliación de cuatro años más para el cumplimiento de lo ordenado por la Sala. En consecuencia, se desestima la solicitud planteada. (…)
Por tanto:
No ha lugar a la gestión formulada”.
En el sub lite, Nombre47883 formula una gestión de inejecución respecto de la sentencia nro. 2016007570 de las 9:05 horas de 3 de junio de 2016.
Primeramente, conviene advertir que, aun cuando la gestionante no constituye parte del proceso, no menos cierto es que este Tribunal ha indicado de forma reiterada que, tratándose de materia ambiental, como ocurre en el sub examine, resulta admisible la legitimación vicaria, de conformidad con lo establecido en el artículo 105 de la Ley de Biodiversidad, según el cual “Toda persona estará legitimada para accionar en sede administrativa o jurisdiccional, en defensa y protección de la biodiversidad”. Por ende, procede conocer por el fondo esta gestión de inejecución.
De segundo, recuérdese que en la sentencia principal del sub lite se dispuso: “Se ordena a Nombre1010, en su condición de Alcalde Municipal de San José, o a quien ocupe el cargo, que proceda en el plazo improrrogable de 6 meses contado a partir de la notificación de esta sentencia, a realizar los estudios que se requieran para verificar científicamente la condición hidráulica del Río Ocloro, y en los 6 meses siguientes a dicho plazo, implementar las obras de infraestructura que se requieran para evitar las inundaciones en el sector Ciudadela Calderón Muñoz”.
Ahora bien, tanto de las resoluciones interlocutorias emitidas previamente por esta Cámara en este asunto como de la prueba que consta en autos, se colige que el gobierno local de San José ha emprendido acciones tendentes a solucionar la problemática de las inundaciones que afectan a la Ciudadela Calderón Muñoz. Verbigracia, este Tribunal ha verificado la finalización de las obras 1, 2, 3, 4 y 5. Sin embargo, la propia autoridad accionada reconoce que la corporación local no ha culminado la totalidad de las acciones necesarias para atender el referido problema. En este sentido, se encuentra en trámite el procedimiento denominado “OBRA DE MITIGACIÓN FLUVIAL, CANAL RIO OCLORO, Dirección2722 ”, cuyo propósito es la recolocación de una tubería sanitaria de 600mm que pasa en la trayectoria del futuro canal pluvial. Además, en el año 2027 se prevé efectuar la recolocación de las previstas sanitarias, potables y de la Compañía Nacional de Fuerza y Luz en la Dirección2725. Aunado a lo anterior, se informó a esta Sala que en el año 2026 se diseñarán obras que posiblemente se ejecutarán en el 2027 o 2028, relacionadas con una ampliación del canal que pasa por la ruta nacional nro. 209.
Así las cosas, pese a que la sentencia principal de este asunto data del 3 de junio de 2016 y que el plazo para cumplir lo ahí ordenado feneció desde el 11 de abril de 2018, a saber, hace más de siete años, no se verifica que se haya solventado debidamente la problemática relacionada con las inundaciones de la Ciudadela Calderón Muñoz, toda vez que faltan obras por terminar. Por tal motivo, se acoge la gestión de inejecución planteada. Ahora bien, dado que la persona que actualmente funge como alcalde de San José difiere de a quien se le giró la orden en cuestión en otras ocasiones, lo procedente es ordenar el cumplimiento de lo dispuesto en la sentencia mencionada a quien en la actualidad desempeña el cargo, tal como se ha dispuesto en situaciones de la misma índole (véanse las sentencias nros. 2024019235 de las 9:30 horas del 9 de julio de 2024, 2024019556 de las 9:20 horas del 12 de julio de 2024, 2025026975 de las 9:30 horas del 26 de agosto de 2025, 2025031855 de las 9:20 horas del 1° de octubre de 2025 y 2025034689 de las 9:20 horas del 24 de octubre de 2025, entre muchas otras).
Por último, en cuanto a las disconformidades externadas por la gestionante atinentes a las obras ejecutadas por la corporación local recurrida, ya que estima que no resolverían adecuadamente la problemática objeto de este asunto, adviértase que ello no corresponde ser dilucidado en esta vía jurisdiccional ordinaria, máxime que esta Cámara no definió la manera en que se debe cumplir la orden supramencionada, sino que lo dispuesto es que se implementen “las obras de infraestructura que se requieran para evitar las inundaciones en el sector Ciudadela Calderón Muñoz”, lo que no implica que tal solución deba ser específicamente la pretendida por la parte amparada.
Se previene a las partes que de haber aportado algún documento en papel, así como objetos o pruebas contenidos en algún dispositivo de carácter electrónico, informático, magnético, óptico, telemático o producido por nuevas tecnologías, estos deberán ser retirados del despacho en el plazo máximo de 30 días hábiles contado a partir de la notificación de esta sentencia. Se advierte que será destruido todo aquel material no retirado dentro de este plazo, según lo dispuesto en el "Reglamento sobre Expediente Electrónico ante el Poder Judicial", aprobado por la Corte Plena en el artículo XXVI de la sesión nro. 27-11 del 22 de agosto de 2011, publicado en el Boletín Judicial nro. 19 del 26 de enero de 2012, así como en el acuerdo de Consejo Superior del Poder Judicial, aprobado en el artículo LXXXI de la sesión nro. 43-12 celebrada el 3 de mayo de 2012.
Por tanto:
Se acoge la gestión de desobediencia formulada. Se le ordena a Nombre47884, en su condición de alcalde de San José, o a quien en su lugar ejerza ese cargo, cumplir lo dispuesto en la sentencia nro. 2016007570 de las 9:05 horas de 3 de junio de 2016. Se advierte a la parte recurrida que, de conformidad con el artículo 71 de la Ley de la Jurisdicción Constitucional, se impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo y no la cumpliere o no la hiciere cumplir, siempre que el delito no esté más gravemente penado. Notifíquese esta sentencia a Nombre47884, en su condición de alcalde de San José, o a quien en su lugar ejerza ese cargo, en forma personal.
Nombre210.
Nombre211 a.i Paul Rueda L.
Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Ingrid Hess H.
Jose Roberto Garita N.