← Environmental Law Center← Centro de Derecho Ambiental
Res. 35858-2025 Sala Constitucional · Sala Constitucional · 31/10/2025
OutcomeResultado
The Constitutional Chamber denied the amparo after confirming that seven of the ten protected parties already had service installed and the remaining three had not completed the required procedure, with no violation of fundamental rights.La Sala Constitucional declaró sin lugar el recurso de amparo al constatar que siete de los diez amparados ya tenían el servicio instalado y los tres restantes no habían completado el trámite requerido, sin violación a derechos fundamentales.
SummaryResumen
The Constitutional Chamber reviewed an amparo action filed by a resident of Santa Fe de Cóbano against the Costa Rican Institute of Aqueducts and Sewers (AyA). The petitioner claimed that despite the formal inauguration of an aqueduct project, AyA had subjected residents to unjustified administrative delays in connecting drinking water service, affecting dozens of families and the local school. Delays were imposed for inspections and meter connections, and later it was argued that the network had not been entered into internal systems, while third parties were being issued availability certificates. The respondent authority reported that out of ten protected parties, seven had fulfilled regulatory requirements and had service installed between October 8 and 10, 2025, before notification of the action. The other three had not submitted new service applications. The Chamber found no violation of fundamental rights and declared the amparo without merit.La Sala Constitucional conoció un recurso de amparo interpuesto por un vecino de la comunidad de Santa Fe de Cóbano contra el Instituto Costarricense de Acueductos y Alcantarillados (AyA). El recurrente alegó que, pese a la inauguración formal de un proyecto de acueducto, el AyA había sometido a los vecinos a demoras administrativas injustificadas para la conexión del servicio de agua potable, afectando a decenas de familias y a la escuela local. Señaló que se impusieron plazos de espera para inspecciones y conexión de medidores, y luego se adujo que la red no estaba ingresada en los sistemas internos, mientras que a terceros sí se les emitían constancias de disponibilidad. La autoridad recurrida informó que de los diez amparados, siete ya habían cumplido con los requisitos reglamentarios y se les había instalado el servicio entre el 8 y 10 de octubre de 2025, antes de la notificación del recurso. Los otros tres no habían presentado la solicitud de nuevo servicio. La Sala concluyó que no existía violación a derechos fundamentales y declaró sin lugar el recurso.
Key excerptExtracto clave
III.- ON THE MERITS. From the report rendered under oath by the respondent authority, with the criminal consequences provided for in article 44 of the Constitutional Jurisdiction Law, an infringement of the fundamental rights of the petitioner is ruled out, based on the considerations set forth below. In this regard, it is certified that Technical Report No. GSP-RPC-CO-2025-00242, prepared by Licda. Francela Quesada Mairena as head of the Cóbano Cantonal Office of AyA, stated: Third: As a third point, it is indicated that from the documentary evidence provided by Mr. Nombre86949, only 7 persons (see image 03) have submitted the application for new services and have complied with the regulatory requirements; however, the parties Bienes y Raíces R&E del Cerro S.R.L., Kimberly Mora Marín, Gerardo Barboza Murillo (see image 04) have not submitted the application for new service, which is why the required connection has not been completed for them. It is worth noting that the installation of new services will be carried out once the applicants complete the new service connection form and provide the corresponding regulatory requirements. Images 05, 06, 07, 08 are provided, showing the moment when drinking water service is installed in Santa Fe (see table in proven fact a). Note that the installation of the seven new services for the petitioners who did comply with the regulatory requirements was carried out between October 8 and 10, 2025, that is, before the order issued in this proceeding was notified, which occurred on October 14, 2025. Furthermore, the respondent authority reported that Bienes y Raíces R&E del Cerro S.R.L., Kimberly Mora Marín, Gerardo Barboza Murillo have not submitted the new service application, which is why the required connection has not been completed for them. Thus, this appeal must be dismissed, as is hereby ordered.III.- SOBRE EL FONDO. Del informe rendido bajo juramento por la autoridad recurrida, con las consecuencias incluso penales que prevé el numeral 44 de la Ley de la Jurisdicción Constitucional se descarta una infracción a los derechos fundamentales de la parte recurrente, con fundamento en las consideraciones que a continuación se exponen. Al respecto, se acredita que en Informe Técnico No. GSP-RPC-CO-2025-00242, elaborado por la Licda. Francela Quesada Mairena como encargada de la Cantonal de Cóbano del AyA, se indicó: Tercero: Como tercer punto, se indica que, de la prueba documental aportada por el señor Nombre86949 únicamente 7 personas (ver imagen 03) han realizado la solicitud de nuevos servicios y han cumplido con los requisitos reglamentarios, no obstante, los señores Bienes y Raíces R&E del Cerro S.R.L, Kimberly Mora Marín, Gerardo Barboza Murillo (ver imagen 04) no han efectuado la solicitud de nuevo servicio, razón por la cual no se les ha materializado la conexión requerida. Es menester señalar que, la instalación de nuevos servicios se ejecutará una vez que los recurrentes, llenen el formulario de conexión de nuevo servicio y aporten los requisitos reglamentario-correspondientes. Se aportan las imágenes 05, 06 ,07, 08, en donde se puede observar el momento donde se instalan servicio de agua potable en Santa Fe (ver cuadro en el hecho probado a). Nótese que la instalación de los siete nuevos servicios de la parte recurrente que si cumplieron con los requisitos reglamentarios se llevó a cabo entre el 8 al 10 de octubre de 2025, es decir, con anterioridad a que se notificara la resolución de curso emitida dentro del presente recurso, lo cual se efectuó hasta el 14 de octubre de 2025. Por otra parte los autoridad recurrida informó que los señores Bienes y Raíces R&E del Cerro S.R.L, Kimberly Mora Marín, Gerardo Barboza Murillo no han efectuado la solicitud de nuevo servicio, razón por la cual no se les ha materializado la conexión requerida. Así las cosas, el presente recurso debe ser declarado sin lugar, como en efecto se ordena.
Pull quotesCitas destacadas
"Se acredita que en Informe Técnico No. GSP-RPC-CO-2025-00242... únicamente 7 personas han realizado la solicitud de nuevos servicios y han cumplido con los requisitos reglamentarios... los señores Bienes y Raíces R&E del Cerro S.R.L, Kimberly Mora Marín, Gerardo Barboza Murillo no han efectuado la solicitud de nuevo servicio, razón por la cual no se les ha materializado la conexión requerida."
"It is certified that in Technical Report No. GSP-RPC-CO-2025-00242... only 7 persons have submitted the application for new services and have complied with the regulatory requirements... Bienes y Raíces R&E del Cerro S.R.L., Kimberly Mora Marín, Gerardo Barboza Murillo have not submitted the application for new service, which is why the required connection has not been completed for them."
Considerando III
"Se acredita que en Informe Técnico No. GSP-RPC-CO-2025-00242... únicamente 7 personas han realizado la solicitud de nuevos servicios y han cumplido con los requisitos reglamentarios... los señores Bienes y Raíces R&E del Cerro S.R.L, Kimberly Mora Marín, Gerardo Barboza Murillo no han efectuado la solicitud de nuevo servicio, razón por la cual no se les ha materializado la conexión requerida."
Considerando III
"Nótese que la instalación de los siete nuevos servicios de la parte recurrente que si cumplieron con los requisitos reglamentarios se llevó a cabo entre el 8 al 10 de octubre de 2025, es decir, con anterioridad a que se notificara la resolución de curso emitida dentro del presente recurso."
"Note that the installation of the seven new services for the petitioners who did comply with the regulatory requirements was carried out between October 8 and 10, 2025, that is, before the order issued in this proceeding was notified."
Considerando III
"Nótese que la instalación de los siete nuevos servicios de la parte recurrente que si cumplieron con los requisitos reglamentarios se llevó a cabo entre el 8 al 10 de octubre de 2025, es decir, con anterioridad a que se notificara la resolución de curso emitida dentro del presente recurso."
Considerando III
"Así las cosas, el presente recurso debe ser declarado sin lugar, como en efecto se ordena."
"Thus, this appeal must be dismissed, as is hereby ordered."
Por tanto
"Así las cosas, el presente recurso debe ser declarado sin lugar, como en efecto se ordena."
Por tanto
Full documentDocumento completo
Constitutional Chamber Date of Resolution: October 31, 2025, at 09:30 Type of matter: Amparo appeal CONSTITUTIONAL CHAMBER OF THE SUPREME COURT OF JUSTICE. San José, at nine hours and thirty minutes on the thirty-first of October of two thousand twenty-five.
Amparo appeal filed by Nombre86949, identification card CED16005, against the COSTA RICAN INSTITUTE OF AQUEDUCTS AND SEWERS
WHEREAS:
Drafted by Judge Salazar Murillo; and,
Considering:
The appellant states that approximately three months ago, the President of the Republic and the Executive President of the Costa Rican Institute of Aqueducts and Sewers formally inaugurated an aqueduct project intended to supply the community of Santa Fe, in the district of Cóbano. They complain that AyA has subjected the residents to a series of unjustified administrative delays and excuses, since initially, it was indicated that they had to wait a period of one month for the corresponding inspections to be carried out before approving the water availability requests. They comment that, once that period had elapsed and the requests were approved, a second month of waiting was imposed for the connection of the meters. After both periods had elapsed, the recent justification by the Costa Rican Institute of Aqueducts and Sewers for not proceeding with the service connection is a purely bureaucratic and unforeseeable obstacle for the administered parties. They complain that the new aqueduct network in the community of Santa Fe was not entered into its internal systems, and consequently, the inspection by engineers must be awaited to carry out said procedure.
Of relevance for resolving this amparo appeal, the following are accredited:
For such purposes, the following conditions must be observed: a. That the distribution and collection networks pass in front of the property boundaries or have direct access via public road or easement (servidumbre) of passage from the property for which a service is requested. b. That the systems have sufficient water, hydraulic, potabilization, and treatment capacity to grant new services. c. That the system meets the established quality attributes. d. That it complies with the corresponding environmental regulations. Subsection 31. Service availability certificate (Constancia de disponibilidad de servicios): Document issued by the operating entity in which it certifies the real and current existence of water capacity, hydraulic capacity, as well as collection and treatment, at one of the boundaries of a specific property, based on the flow and/or discharge demand required by the real estate project verified by the operator, which will eventually allow the installation of potable water, collection, and wastewater treatment services.
The foregoing with the foresight of not affecting the demand of existing services. Article 36.- Of the issuance of the service availability certificate. Once the requirements and conditions established in article 30 of this regulation have been reviewed and verified to AyA's satisfaction, the service availability certificate shall be issued within a maximum period of up to 15 business days, both for individual housing and commerce cases, and for residential, industrial, and commercial urban development projects. Said certificate shall indicate at least the following: date, sequential number, real folio number, exact address of the property, cadastral or survey plan, nature of the project, quantity of assigned flow, number of services considered, type of measurement, technical criterion, sequential number, signature and stamp in case the document is issued physically. The technical criterion that will substantiate the certificate must refer to the conditions of water and hydraulic capacity that the aqueduct and/or sanitation system presents, which by coverage correspond to the property indicated in the request; additionally, it must contain the verification and analysis, solely of the aspects established in the official procedure approved and disclosed by AyA.
When there is no planned sanitary sewer network, and in order to address another type of sanitary solution, homes may be exempted; likewise, the construction of wastewater treatment plants will be recommended when applicable. In the case of requests referring to properties belonging to ministries, institutions attached to the central government, autonomous institutions, and education boards, that present any delinquency on the property indicated in the proceeding, AyA will issue the certificate, on the understanding that the payment proceeding is in the process of being applied in favor of AyA. The certificates shall be issued by the Operational Deputy Managements of Systems Management or by the Deputy Management of Delegated Systems Management, respectively as applicable according to the established procedure. Regarding requests made by third parties in good faith who receive service provision from another type of non-legalized operator, the provisions of article 46 of this regulation shall apply.
It shall correspond to the Deputy Management of Delegated Systems Management to issue certificates for the ASADAS that do not have a Delegation Agreement or have an expired legal status. The issuance of this certificate shall not accrue any pecuniary cost for the applicant. (Thus amended by Board of Directors Agreement No. 2023 – 48, published in the Official Gazette La Gaceta No. 74, of April 28, 2023). It is stated that once the Improvements to the Cóbano System Stage II project is started, users must make the potable water availability request before the Institute; once the availability is approved, the new services form must be completed and the corresponding requirements must be submitted in accordance with those established in articles 67 and 68 of the current Institutional regulations. Article 67- Of the general conditions for processing a permanent connection. For the granting of service, the property for which it is requested must previously have a positive service availability certificate associated with the purposes, nature, and objectives for which it was approved.
In the event that registry movements related to the property's ownership are detected, AyA will process the request with respect to the owner legitimized for such purpose. In case of cadastral variations, such as modification of areas and/or boundaries that may affect the flow and number of services defined for the granting of the service availability certificate, the interested party must carry out the procedure indicated in article 30 of this regulation. Article 68- Of the requirements and conditions for requesting permanent connections on registered land. For the request of a permanent connection, the property owner, or the authorized applicant or their legal representative, as provided in article 15 of this Regulation, must submit before the physical or virtual platforms that AyA or the delegated operator offers, whether in physical or digital form, the following requirements: a. Request form, provided by AyA, completed and signed by the owner, the authorized applicant, or their legal representative. b. Identification document of the owner, authorized applicant, or their legal representative.
If there is access to the technological platform of the Civil Registry where the photo and signature of the interested party are displayed, AyA will exempt them from presenting this requirement and it will only be necessary to provide the identification number of the identity card. c. Cadastral plan. In the event that the property does not have a cadastral plan, or is in the process of a segregation or subdivision (fraccionamiento), a survey plan must be presented that complies with the provisions of Article No. 2, subsection q) of the Executive Decree (Decreto Ejecutivo) No. 34331, Regulation of the current National Cadastre Law with its respective submission memorandum and the corresponding seal of the Federated College of Engineers and Architects (CFIA) in accordance with the provisions of the Special Regulation of the Topography Project Administrator (APT) of the CFIA in force and its amendments or the regulations that replace them.
If technological feasibility exists, AyA will exempt the applicant from presenting this requirement. d. Project Number processed before the Construction Project Administration (APC) platform of the CFIA, duly approved so that AyA verifies the existence of the valid construction permit requirement, in case of a property to be built. The permit must coincide with the flow and purposes for which the availability was approved. e. Payment of the connection fee, as established in article 76 of this regulation. f. In the case of requests for new services, for activities that generate special type wastewater, the interested party must present a sworn statement indicating that the discharge to the sanitary sewer will comply with the regulation and the approval note from the Ministry of Health, describing the type of activity to be carried out, as well as the quantity and quality of the discharge to be poured; also the specification of the treatment system to comply with current environmental regulations. g. In those cases where the public service must be provided, in territories of the country with special characteristics, under the modality of territories administered by the State or its institutions with a special legal regime such as in the maritime terrestrial zone, border zones, leased zones, indigenous territories, tourist development poles, areas within the railway right-of-way, among others, the applicants must present the express authorization of the corresponding Entity, according to the regulation that governs them.
In accordance with the verification of the conditions necessary for the approval of services generally indicated in article 15 of this Regulation, it corresponds to AyA to verify the requirements broken down therein, as well as the general conditions established therein for all procedures. When an administered party appears before AyA to request sanitation and/or water service for population use on an agricultural, forestry, or livestock parcel, and for the purpose of constructing the dwellings or buildings authorized by the Regulation for the National Control of Subdivisions (Fraccionamientos) and Urbanizations of the INVU in force, they must comply with the requirements requested for such purpose in the present regulations for each scenario. Once the submission of all requirements is completed, the Institution will have a period of 15 business days for the resolution of the request. Third: As a third point, it is indicated that, from the documentary evidence provided by Mr.
Nombre86949, only 7 people (see image 03) have made the request for new services and have complied with the regulatory requirements; however, the parties Bienes y Raíces R&E del Cerro S.R.L, Kimberly Mora Marín, Gerardo Barboza Murillo (see image 04) have not made the new service request, which is why the required connection has not been materialized for them. It is necessary to point out that the installation of new services will be carried out once the appellants complete the new service connection form and provide the corresponding regulatory requirements. Images 05, 06, 07, 08 are provided, where the moment of potable water service installation in Santa Fe can be observed.
NEW SERVICES INSTALLED SANTA FE SECTORS
| Number of request | Name | ID | Nis | F. installation |
|---|---|---|---|---|
| CED51863 | Nombre91715 | Telf72305568704 | 5 | |
| CED51864 | Nombre24920 | 1-630-0710 | 5568700 | 08/10725 |
| CED51864 | Nombre24920 | 1-630-0710 | 5568701 | 08/10725 |
| CED51865 | Botanic Lab | 3-102-847123 | 5567721 | 08/10725 |
| CED51866 | Nombre91716 | 1-1534-0030 | 5568748 | 09/10725 |
| CED51866 | Nombre91717 | 9-0061-499 | 5568695 | 08/10725 |
| CED51867 | Nombre91718 | Telf72315568765 | 5 |
From the report rendered under oath by the respondent authority, with the consequences, including criminal ones, provided for in numeral 44 of the Law of Constitutional Jurisdiction, an infringement of the fundamental rights of the appealing party is ruled out, based on the considerations set forth below. In this regard, it is accredited that in Technical Report No. GSP-RPC-CO-2025-00242, prepared by Licda. Francela Quesada Mairena as head of the Cóbano Cantonal Office of AyA, it was indicated: Third: As a third point, it is indicated that, from the documentary evidence provided by Mr. Nombre86949, only 7 people (see image 03) have made the request for new services and have complied with the regulatory requirements; however, the parties Bienes y Raíces R&E del Cerro S.R.L, Kimberly Mora Marín, Gerardo Barboza Murillo (see image 04) have not made the new service request, which is why the required connection has not been materialized for them.
It is necessary to point out that the installation of new services will be carried out once the appellants complete the new service connection form and provide the corresponding regulatory requirements. Images 05, 06, 07, 08 are provided, where the moment of potable water service installation in Santa Fe can be observed (see table in proven fact a). Note that the installation of the seven new services for the appealing party members who did comply with regulatory requirements was carried out between October 8 and 10, 2025, that is, prior to the notification of the resolution admitting the present appeal, which was effected until October 14, 2025. Furthermore, the respondent authority reported that the parties Bienes y Raíces R&E del Cerro S.R.L, Kimberly Mora Marín, Gerardo Barboza Murillo have not made the new service request, which is why the required connection has not been materialized for them. Thus, the present appeal must be declared without merit, as is hereby ordered.
The parties are advised that if they have provided any paper document, as well as objects or evidence contained in any additional electronic, computer, magnetic, optical, telematic device or one produced by new technologies, these must be withdrawn from the office within a maximum period of 30 business days counted from the notification of this judgment. Otherwise, any material not withdrawn within this period will be destroyed, according to the provisions of the "Regulation on Electronic Case Files before the Judicial Branch", approved by the Full Court in session number 27-11 of August 22, 2011, article XXVI and published in the Judicial Bulletin number 19 of January 26, 2012, as well as the agreement approved by the Superior Council of the Judicial Branch, in session number 43-12 held on May 3, 2012, article LXXXI.
THEREFORE:
The appeal is declared without merit.
Fernando Cruz C. Interim President Paul Rueda L.
Luis Fdo. Salazar A.
Jorge Araya G.
Ingrid Hess H.
Ronald Salazar Murillo Ileana Sánchez N.
Telephones: Telf09 / 800-SALA-4TA (Telf10). Fax: Telf07 / Telf08. Electronic address: www.poder-judicial.go.cr/salaconstitucional. Address: (Dirección09, Dirección05, 100 mts. South of the Perpetuo Socorro church).
It is a faithful copy of the original - Taken from Nexus.PJ on: 05-08-2026 11:42:49.
SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas treinta minutos del treinta y uno de octubre de dos mil veinticinco .
Recurso de amparo interpuesto por Nombre86949, cédula de identidad CED16005, contra el INSTITUTO COSTARRICENSE DE ACUEDUCTO Y ALCANTARILLADOS
RESULTANDO:
Redacta el Magistrado Salazar Murillo; y,
Considerando:
El recurrente manifiesta que hace aproximadamente tres meses, el Presidente de la República y el Presidente Ejecutivo del Instituto Costarricense de Acueductos y Alcantarillados inauguraron formalmente un proyecto de acueducto destinado a abastecer a la comunidad de Santa Fe, en el distrito de Cóbano. Reclama que el AyA ha sometido a los vecinos a una serie de demoras y excusas administrativas injustificadas, pues inicialmente, se indicó que debían esperar el plazo de un mes para la realización de las inspecciones correspondientes antes de aprobar las solicitudes de disponibilidad de agua. Comenta que, una vez cumplido ese plazo y aprobadas las solicitudes, se procedió a imponer un segundo mes de espera para la conexión de los medidores. Tras transcurrir ambos plazos, la reciente justificación del Instituto Costarricense de Acueductos y Alcantarillados para no prolongar la conexión del servicio es un obstáculo puramente burocrático e imprevisible para los administrados. Reclama que la nueva red de acueducto en la comunidad de Santa Fe no fue ingresada en sus sistemas internos, y en consecuencia, se debe esperar la inspección de ingenieros para realizar dicho trámite.
De relevancia para dirimir el presente recurso de amparo, se tienen por acreditados los siguientes:
Para tales efectos se deberán de observar las siguientes condiciones: a. Que las redes de distribución y de recolección pasan frente a linderos del inmueble o tenga acceso directo por vía pública o servidumbre de paso del inmueble para el cual se solicita un servicio. b. Que los sistemas cuenten con capacidad hídrica, hidráulica, de potabilización y de tratamiento, suficientes para otorgar nuevos servicios. c. Que el sistema cumple con los atributos de calidad establecidos. d. Que cumple con la normativa ambiental correspondiente. Inciso 31. Constancia de disponibilidad de servicios: Documento que emite el ente operador en el que hace constar la existencia real y actual en cuanto a capacidad hídrica, capacidad hidráulica, así como de recolección y tratamiento, en alguno de los linderos de un inmueble determinado, en función de la demanda de caudal y/o descarga que requiera el proyecto inmobiliario verificado por el operador, que permitirá eventualmente la instalación de los servicios de agua potable, recolección y tratamiento de las aguas residuales.
Lo anterior previendo no afectar la demanda de los servicios existentes. Artículo 36.- De la emisión de la constancia de disponibilidad de servicios. Una vez revisados y verificados a satisfacción de AyA los requisitos y condiciones establecidos en el artículo 30 del presente reglamento, se emitirá la constancia de disponibilidad de servicios dentro de un plazo máximo de hasta 15 días hábiles, tanto para los casos de vivienda y comercio individuales, como para proyectos de desarrollos urbanísticos habitacionales, industriales y comerciales. En dicha constancia se indicará como mínimo lo siguiente: fecha, número de consecutivo, número de folio real, dirección exacta de la propiedad, plano catastrado o de agrimensura, naturaleza del proyecto, cantidad de caudal asignado, número de servicios considerados, tipo de medición, criterio técnico, número de consecutivo, firma y sello en caso de que se extienda el documento de forma física.
El criterio técnico que fundamentará la constancia deberá referirse a las condiciones de capacidad hídrica e hidráulica que presenta el sistema de acueducto y/o saneamiento, que por cobertura corresponden al inmueble indicado en la solicitud; adicionalmente deberá contener la verificación y análisis, únicamente de los aspectos establecidos en el procedimiento oficial aprobado y divulgado por AyA. Cuando no exista red de alcantarillado sanitario prevista, y con el fin de atender otro tipo de solución sanitaria, se podrá exonerar a las viviendas, asimismo se recomendará la construcción de plantas de tratamiento de aguas residuales cuando corresponda. Para el caso de solicitudes referidas a inmuebles pertenecientes a ministerios, instituciones adscritas al gobierno central, instituciones autónomas y juntas de educación, que presenten alguna morosidad en la finca indicada en la gestión, AyA emitirá la constancia, en el entendido de que la gestión de pago se encuentra en proceso de aplicación a favor de AyA.
Las constancias serán emitidas por las Subgerencias Operativas de Gestión de Sistemas o por la Subgerencia de Gestión de Sistemas delegados, respectivamente según corresponda conforme al procedimiento establecido. En cuanto a solicitudes que realicen terceros de buena fe que reciban la prestación del servicio por parte de otro tipo de operador no legalizado, se aplicará lo establecido en el artículo 46 del presente reglamento. Corresponderá a la Subgerencia de Gestión de Sistemas delegados emitir las constancias para las ASADAS que no cuenten con Convenio de Delegación o tengan la personería vencida. La emisión de esta constancia no devengará ningún costo pecuniario para el solicitante. (Así reformado mediante Acuerdo de Junta Directiva No. 2023 – 48, publicado en el Diario La Gaceta No. 74, del 28 de abril del 2023). Se manifiesta que una vez puesta en marcha el proyecto de Mejoras al Sistema de Cóbano.
Etapa II los usuarios deben de efectuar ante el Instituto la solicitud de disponibilidad de agua potable, una vez aprobada la disponibilidad se debe llenar el formulario de nuevo servicios y aportar los requisitos correspondientes de conformidad con el establecidos en los artículos 67 y 68 de la normativa vigente Institucional. Artículo 67- De las condiciones generales para el trámite de una conexión permanente. Para el otorgamiento del servicio, el inmueble para el cual se solicita debe contar previamente con la disponibilidad de servicios positiva y asociada a los fines, naturaleza y propósitos para lo que fue aprobada. En caso de que se detecten movimientos registrales relacionados con la titularidad del inmueble, AyA tramitará la solicitud respecto al titular legitimado para tal efecto. Ante variaciones catastrales, tales como modificación de áreas y/o linderos que pueden incidir en el caudal y número de servicios definidos para el otorgamiento de la constancia de disponibilidad de servicios, deberá el interesado realizar el trámite señalado en el artículo 30 de este reglamento.
Artículo 68- De los requisitos y condiciones para la solicitud de conexiones permanentes en terrenos inscritos. Para la solicitud de una conexión permanente, el propietario del inmueble, o el solicitante autorizado o su representante legal, conforme lo dispone el artículo 15 de este Reglamento, deberá presentar ante las plataformas físicas o virtuales que AyA o el operador delegado ofrezca, ya sea forma física o digital, los siguientes requisitos: a. Formulario de solicitud, proporcionado por AyA, completo y firmado por el propietario, el solicitante autorizado, o su representante legal. b. Documento de identificación del propietario, solicitante autorizado o su representante legal. De existir acceso a la plataforma tecnológica del Registro Civil en el que se despliegue la foto y firma del interesado, AyA lo eximirá de la presentación de este requisito y únicamente será necesario que proporcione el número de identificación de la cédula de identidad. c. Plano catastrado.
En caso de que el inmueble no cuente con plano catastrado, o bien, se encuentre en proceso de una segregación o fraccionamiento, deberá de presentar un plano de agrimensura que cumpla con lo estipulado en el Artículo N°2 inciso q) del Decreto Ejecutivo No. 34331, Reglamento de la Ley de Catastro Nacional vigente con su respectiva minuta de presentación y el correspondiente sello del Colegio Federado de Ingenieros y Arquitectos (CFIA) conforme a lo dispuesto en el Reglamento Especial del Administrador de Proyectos de Topografía (APT) del CFIA vigente y sus reformas o las normativas que los sustituya. De existir factibilidad tecnológica, AyA eximirá al solicitante de la presentación de este requisito. d. Número de Proyecto tramitado ante la plataforma Administración de Proyectos de Construcción (APC) del CFIA, debidamente aprobado con el fin de que AyA constate la existencia del requisito del permiso de construcción vigente, en caso de que se trate de un inmueble por edificar.
El permiso deberá ser coincidente con el caudal y fines para el que se aprobó la disponibilidad. e. El pago de la tarifa de conexión, conforme a lo establecido en el artículo 76 de este reglamento. f. En el caso de solicitudes de nuevos servicios, para actividades que generen aguas residuales de tipo especiales, el interesado deberá presentar, una declaración jurada en la que indique que la descarga al alcantarillado sanitario, cumplirá con el reglamento y nota de aprobación del Ministerio de Salud, que describa el tipo de actividad a desarrollar, así como la cantidad y calidad de la descarga a verter; asimismo la especificación del sistema de tratamiento para cumplir con la normativa ambiental vigente. g. En aquellos casos en que se deba brindar el servicio público, en territorios del país con características especiales, bajo la modalidad de territorios administrados por el Estado o sus instituciones con régimen jurídico especial como en la zona marítimo terrestre, en las zonas fronterizas, en las zonas en arriendo, en los territorios indígenas, en los polos de desarrollo turístico, en las áreas dentro del derecho de vía férrea, entre otros, los solicitantes deberán presentar la autorización expresa del Ente correspondiente, según la norma que los regule.
De acuerdo con la verificación de las condiciones necesarias para la aprobación de los servicios indicada de manera general en el artículo 15 de este Reglamento, le corresponde a AyA verificar los requisitos ahí desglosados, así como las condiciones generales ahí establecidas para todos los trámites. Cuando el administrado se apersone ante el AyA a solicitar el servicio de saneamiento y/o agua para uso poblacional en una parcela agrícola, forestal o pecuaria, y para efectos de construir las viviendas o edificaciones que autoriza el Reglamento para el Control Nacional de Fraccionamientos y Urbanizaciones del INVU vigente, deberá el cumplir con los requisitos que para tal fin se solicitan en la presente normativa para cada supuesto. Cumplida la presentación de la totalidad de requisitos; la Institución contará con un plazo de 15 días hábiles para la resolución de la solicitud. Tercero: Como tercer punto, se indica que, de la prueba documental aportada por el señor Nombre86949 únicamente 7 personas (ver imagen 03) han realizado la solicitud de nuevos servicios y han cumplido con los requisitos reglamentarios, no obstante, los señores Bienes y Raíces R&E del Cerro S.R.L, Kimberly Mora Marín, Gerardo Barboza Murillo (ver imagen 04) no han efectuado la solicitud de nuevo servicio, razón por la cual no se les ha materializado la conexión requerida.
Es menester señalar que, la instalación de nuevos servicios se ejecutará una vez que los recurrentes, llenen el formulario de conexión de nuevo servicio y aporten los requisitos reglamentario-correspondientes. Se aportan las imágenes 05, 06 ,07, 08, en donde se puede observar el momento donde se instalan servicio de agua potable en Santa Fe SERVICIOS NUEVOS INSTALADOS SECTOS SANTA FE Número de solicitud Nombre Cédula Nis F. instalación Nombre91715 Telf7230 5568704 5 Nombre24920 1-630-0710 5568700 08/10725 Nombre24920 1-630-0710 5568701 08/10725 Botanic Lab 3-102-847123 5567721 08/10725 Nombre91716 1-1534-0030 5568748 09/10725 Nombre91717 9-0061-499 5568695 08/10725 Nombre91718 Telf7231 5568765 5 b) Que la resolución de curso emitida dentro del presente recurso fue notificada a la autoridad recurrida el 14 de octubre de 2025 (expediente digital).
Del informe rendido bajo juramento por la autoridad recurrida, con las consecuencias incluso penales que prevé el numeral 44 de la Ley de la Jurisdicción Constitucional se descarta una infracción a los derechos fundamentales de la parte recurrente, con fundamento en las consideraciones que a continuación se exponen. Al respecto, se acredita que en Informe Técnico No. GSP-RPC-CO-2025-00242, elaborado por la Licda. Francela Quesada Mairena como encargada de la Cantonal de Cóbano del AyA, se indicó: Tercero: Como tercer punto, se indica que, de la prueba documental aportada por el señor Nombre86949 únicamente 7 personas (ver imagen 03) han realizado la solicitud de nuevos servicios y han cumplido con los requisitos reglamentarios, no obstante, los señores Bienes y Raíces R&E del Cerro S.R.L, Kimberly Mora Marín, Gerardo Barboza Murillo (ver imagen 04) no han efectuado la solicitud de nuevo servicio, razón por la cual no se les ha materializado la conexión requerida.
Es menester señalar que, la instalación de nuevos servicios se ejecutará una vez que los recurrentes, llenen el formulario de conexión de nuevo servicio y aporten los requisitos reglamentario-correspondientes. Se aportan las imágenes 05, 06 ,07, 08, en donde se puede observar el momento donde se instalan servicio de agua potable en Santa Fe (ver cuadro en el hecho probado a). Nótese que la instalación de los siete nuevos servicios de la parte recurrente que si cumplieron con los requisitos reglamentarios se llevó a cabo entre el 8 al 10 de octubre de 2025, es decir, con anterioridad a que se notificara la resolución de curso emitida dentro del presente recurso, lo cual se efectuó hasta el 14 de octubre de 2025. Por otra parte los autoridad recurrida informó que los señores Bienes y Raíces R&E del Cerro S.R.L, Kimberly Mora Marín, Gerardo Barboza Murillo no han efectuado la solicitud de nuevo servicio, razón por la cual no se les ha materializado la conexión requerida. Así las cosas, el presente recurso debe ser declarado sin lugar, como en efecto se ordena.
Se previene a las partes que de haber aportado algún documento en papel, así como objetos o pruebas contenidas en algún dispositivo adicional de carácter electrónico, informático, magnético, óptico, telemático o producido por nuevas tecnologías, estos deberán ser retirados del despacho en un plazo máximo de 30 días hábiles contados a partir de la notificación de esta sentencia. De lo contrario, será destruido todo aquel material que no sea retirado dentro de este plazo, según lo dispuesto en el "Reglamento sobre Expediente Electrónico ante el Poder Judicial", aprobado por la Corte Plena en sesión número 27-11 del 22 de agosto de 2011, artículo XXVI y publicado en el Boletín Judicial número 19 del 26 de enero de 2012, así como en el acuerdo aprobado por el Consejo Superior del Poder Judicial, en la sesión número 43-12 celebrada el 3 de mayo de 2012, artículo LXXXI.
POR TANTO:
Se declara sin lugar el recurso.
Fernando Cruz C.
Presidente a.i Paul Rueda L.
Luis Fdo. Salazar A.
Jorge Araya G.
Ingrid Hess H.
Ronald Salazar Murillo Ileana Sánchez N.
Document not found. Documento no encontrado.