Res. 36588-2025 Sala Constitucional · Sala Constitucional · 07/11/2025
OutcomeResultado
The amparo is granted, and the Municipality of Alajuela is ordered to take all necessary measures to resolve the complaint regarding contamination of the Los Herrera spring within a maximum of six months.Se declara con lugar el amparo y se ordena a la Municipalidad de Alajuela adoptar las medidas necesarias para resolver la denuncia de contaminación de la naciente Los Herrera en un plazo máximo de seis meses.
SummaryResumen
The Constitutional Chamber hears an amparo filed by development associations from La Garita, Alajuela, against the Municipality of Alajuela. Since 2012, petitioners have reported ongoing contamination of drinking water from the Los Herrera spring caused by flooding from a stormwater channel collecting runoff from the El Coyol industrial zone. The Municipality acknowledged the issue, conducted hydrological studies, designed technical solutions, built perimeter protection works for the spring, and advanced a channelization project, yet had not achieved a definitive solution in over thirteen years. In 2023, the Municipal Council refused to declare the necessary expropriation for a drainage easement of public interest, temporarily blocking that route. At the time of filing, the Municipality was in the process of awarding a contract for a concrete barrier and a new tender, but provided no timeline for resolution. The Chamber finds that the delay exceeding ten years without resolving the complaint constitutes a disproportionate violation of the right to a prompt and concluded proceeding and the right to a healthy environment, grants the amparo, and orders the Municipality to take all actions within its powers to resolve the complaint within six months, under penalty of disobedience.La Sala Constitucional conoce un recurso de amparo interpuesto por asociaciones de desarrollo de La Garita de Alajuela contra la Municipalidad de Alajuela. Los recurrentes denuncian que desde 2012 han alertado sobre la contaminación constante del agua potable proveniente de la naciente Los Herrera, ocasionada por el desbordamiento de un canal pluvial que recoge aguas de la zona industrial de El Coyol. La Municipalidad reconoció el problema, realizó estudios hidrológicos, diseñó soluciones técnicas, ejecutó obras de protección perimetral de la naciente y gestionó un proyecto de canalización, pero no ha logrado una solución definitiva en más de trece años. El Concejo Municipal rechazó en 2023 declarar de interés público la expropiación necesaria para una servidumbre pluvial, bloqueando temporalmente esa vía. Al momento del recurso, la administración municipal se encontraba en proceso de adjudicación de una pantalla de concreto y una nueva licitación, sin ofrecer un plazo concreto para resolver. La Sala determina que el transcurso de más de diez años sin resolver la denuncia constituye una violación desproporcionada del derecho a un procedimiento pronto y cumplido y del derecho a un ambiente sano, declara con lugar el amparo y ordena a la Municipalidad realizar las actuaciones necesarias para atender definitivamente la denuncia en un plazo máximo de seis meses, bajo apercibimiento de desobediencia.
Key excerptExtracto clave
Consequently, this Chamber finds that the time that has elapsed to resolve the complaint filed by the protected party and communicate the corresponding decision to the respondents is disproportionate, given that more than ten years have passed since the first complaint was filed by the petitioners without a resolution to date, aggravated by the fact that the alleged harm remains ongoing. For these reasons, this Chamber considers that the appeal should be granted, with the considerations set forth in the operative part of this judgment. The appeal is granted. Roberto Hernán Thompson Chacón and Roy Delgado Alpízar, in their respective capacities as Mayor and Director of Infrastructure Planning and Construction of the Municipality of Alajuela, or their successors, are ordered to take all actions within their powers and establish the necessary actions and coordination, so that within a maximum period of six months from notification of this judgment, the necessary contracts and works are executed and the appropriate administrative measures and decisions are adopted to address the complaint filed by the petitioners and to communicate the corresponding outcome to them. Respondents are warned that failure to comply with this order will result in the crime of disobedience…En consecuencia, estima esta Sala que el plazo que ha transcurrido para resolver la denuncia planteada por la parte tutelada y comunicarle lo respectivo por parte de las autoridades recurridas es desproporcionado, por cuanto, ha transcurrido un plazo de, más de diez años, desde la presentación de la primera denuncia por parte de los recurrentes, sin que a la fecha esta haya sido resuelta, con el agravante que la presunta afectación denunciada continúa vigente. Bajo esta inteligencia, considera esta Sala que el recurso debe ser declarado con lugar, con las consideraciones que se dirán en la parte dispositiva de esta sentencia. Se declara con lugar el recurso. Se ordena a Roberto Hernán Thompson Chacón y Roy Delgado Alpízar, por su orden Alcalde y Director de Planeamiento y Construcción de Infraestructura Municipal, ambos de la Municipalidad de Alajuela, o a quienes ocupen el cargo, que realicen las actuaciones que estén dentro del ámbito de sus competencias y establezcan las acciones y coordinaciones necesarias, para que en el plazo máximo de seis meses contados a partir de la notificación de esta sentencia, se ejecuten las contrataciones y obras que se estime necesarias y se adopten las medidas y resoluciones administrativas pertinentes, para atender la denuncia planteada por los recurrentes y se les comunique lo que corresponda. Se les advierte a los recurridos que, de no acatar la orden dicha, incurrirán en el delito de desobediencia…
Pull quotesCitas destacadas
"En consecuencia, estima esta Sala que el plazo que ha transcurrido para resolver la denuncia planteada por la parte tutelada y comunicarle lo respectivo por parte de las autoridades recurridas es desproporcionado, por cuanto, ha transcurrido un plazo de, más de diez años, desde la presentación de la primera denuncia por parte de los recurrentes, sin que a la fecha esta haya sido resuelta, con el agravante que la presunta afectación denunciada continúa vigente."
"Consequently, this Chamber finds that the time that has elapsed to resolve the complaint filed by the protected party and communicate the corresponding decision to the respondents is disproportionate, given that more than ten years have passed since the first complaint was filed by the petitioners without a resolution to date, aggravated by the fact that the alleged harm remains ongoing."
Considerando IV
"En consecuencia, estima esta Sala que el plazo que ha transcurrido para resolver la denuncia planteada por la parte tutelada y comunicarle lo respectivo por parte de las autoridades recurridas es desproporcionado, por cuanto, ha transcurrido un plazo de, más de diez años, desde la presentación de la primera denuncia por parte de los recurrentes, sin que a la fecha esta haya sido resuelta, con el agravante que la presunta afectación denunciada continúa vigente."
Considerando IV
"Se declara con lugar el recurso. Se ordena a […] la Municipalidad de Alajuela, o a quienes ocupen el cargo, que realicen las actuaciones que estén dentro del ámbito de sus competencias y establezcan las acciones y coordinaciones necesarias, para que en el plazo máximo de seis meses contados a partir de la notificación de esta sentencia, se ejecuten las contrataciones y obras que se estime necesarias y se adopten las medidas y resoluciones administrativas pertinentes, para atender la denuncia planteada por los recurrentes y se les comunique lo que corresponda."
"The appeal is granted. The Municipality of Alajuela, or its successors, is ordered to take all actions within its powers and establish the necessary actions and coordination, so that within a maximum period of six months from notification of this judgment, the necessary contracts and works are executed and the appropriate administrative measures and decisions are adopted to address the complaint filed by the petitioners and to communicate the corresponding outcome to them."
Por tanto
"Se declara con lugar el recurso. Se ordena a […] la Municipalidad de Alajuela, o a quienes ocupen el cargo, que realicen las actuaciones que estén dentro del ámbito de sus competencias y establezcan las acciones y coordinaciones necesarias, para que en el plazo máximo de seis meses contados a partir de la notificación de esta sentencia, se ejecuten las contrataciones y obras que se estime necesarias y se adopten las medidas y resoluciones administrativas pertinentes, para atender la denuncia planteada por los recurrentes y se les comunique lo que corresponda."
Por tanto
"Se les advierte a los recurridos que, de no acatar la orden dicha, incurrirán en el delito de desobediencia y, que de conformidad con el artículo 71 de la Ley de esta jurisdicción, se le impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo y no la cumpliere o no la hiciere cumplir, siempre que el delito no esté más gravemente penado."
"Respondents are warned that failure to comply with this order will result in the crime of disobedience and, pursuant to Article 71 of the Law of this jurisdiction, anyone who receives an order that must be obeyed or enforced, issued in an amparo proceeding, and fails to obey or enforce it, shall be punished with imprisonment from three months to two years, or a fine of twenty to sixty days, unless the offense is more severely punished."
Por tanto
"Se les advierte a los recurridos que, de no acatar la orden dicha, incurrirán en el delito de desobediencia y, que de conformidad con el artículo 71 de la Ley de esta jurisdicción, se le impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo y no la cumpliere o no la hiciere cumplir, siempre que el delito no esté más gravemente penado."
Por tanto
Full documentDocumento completo
Constitutional Chamber Date of Resolution: November 7, 2025, at 09:30 Type of case: Amparo action Judgment with separate note Relevance Indicators Relevant judgment Judgment with protected data, in accordance with current regulations Content of Interest: Strategic Themes: Right to health, Economic social cultural and environmental rights Type of content: Majority vote Branch of Law: 4. GUARANTEE MATTERS Topic: PUBLIC SERVICES Subtopics: DRINKING WATER.
036588-25. PUBLIC SERVICES. RESIDENTS OF LA GARITA DE ALAJUELA ACCUSE CONSTANT CONTAMINATION PROBLEMS OF THE DRINKING WATER FROM THE SPRINGS AND WATER INTAKES FROM THE SPRING KNOWN AS "LOS HERRERA". THE MUNICIPALITY OF ALAJUELA IS ORDERED TO CARRY OUT THE ACTIONS WITHIN THE SCOPE OF ITS COMPETENCIES AND ESTABLISH THE NECESSARY ACTIONS AND COORDINATIONS, SO THAT WITHIN A MAXIMUM PERIOD OF SIX MONTHS, THE CONTRACTING AND WORKS DEEMED NECESSARY ARE EXECUTED AND THE PERTINENT ADMINISTRATIVE MEASURES AND RESOLUTIONS ARE ADOPTED TO ADDRESS THE COMPLAINT FILED BY THE PETITIONERS AND THEY ARE NOTIFIED ACCORDINGLY. VCG11/2025
"(...) IV.- Regarding the specific case. In the case at hand, the petitioner accuses that since 2012, they have filed complaints before the Municipality of Alajuela regarding constant contamination problems of the drinking water, from the springs (nacientes) and water intakes from the spring known as "Los Herrera". They assert that, as of the date this action is filed, the complaint has not been definitively resolved by the respondent authorities, which they deem harmful to their fundamental rights.
In this regard, this Chamber verifies that, in the specific case, there is indeed knowledge of a complaint filed before the Municipality of Alajuela by the petitioners at different times, the first during 2012, and subsequently, on May 10, 2020, January 5, 2024, and June 4, 2024, regarding the contamination problem occurring at the "Los Herrera" spring, a situation that the respondent municipal authorities have been fully aware of for 13 years.
Certainly, it was possible to verify that, although the respondent authorities have been aware of the reported situation since 2012 and have attempted to carry out actions to correct the problem, it is no less true that, as of the filing date of this action, the complaint had not been definitively addressed, and it was even possible to confirm that the authorities are aware that the work carried out in the past does not in any way solve the problem in question, given that they acknowledge in the report submitted to this Chamber that: "1. Initially, the conflict arose because there are constructions in the El Coyol industrial zone, discharging their stormwater by means of a 'ditch' (caño) that did not have the capacity for such activity. 2. As already reported, the problem worsens because it also affects the service provided by the Municipal Aqueduct to the residents of La Garita and Lagos del Coyol, since said stormwater reaches very close to the sources captured by the Municipality and because the receiving body does not have sufficient capacity to evacuate it, right where the Los Herrera Spring is located the land floods, putting the potability of the water from the captured sources at risk. 3.
This Municipal Aqueducts and Sewers Process carried out a project for the construction of Protection works for the Los Herrera Spring; work that was satisfactorily completed, as established in the bidding documents for abbreviated tender No. 2011LA-00006-01. • Said works consisted of providing protection against unscrupulous persons, as well as protection against possible surface contamination from stormwater or wastewater. • To prevent the entry of persons to the catchment manholes (cajas de registro de las captaciones), concrete walls and chain-link mesh were built surrounding them, with access only through a gate with its respective padlock. • The most likely points of surface runoff entry, due to a flood event, were precisely the manholes of the catchments and the collection tanks (tanques de reunión). Therefore, to eliminate this risk, the existing manholes were repaired and also made taller, so that water levels in the event of a possible flood would not exceed the height of these manholes. • Since some of the metal covers of the manholes were in poor condition, they were repaired or completely replaced, in addition to securing them with a screw.
This prevents any improper access from surface water, animals, or persons. 4. However, the protection works carried out allow the Municipality of Alajuela to ensure that the water from the Los Herrera Spring will not be contaminated by runoff water typical of the area, nor by vandalism, or by animals that approach to drink water in the stream (quebrada). 5. Nevertheless, the case at hand involves an amount of stormwater that cannot be controlled solely by the works carried out by the Aqueduct, since, as indicated, it is a problem of storm sewerage and permits granted in the industrial zone without considering the capacity of the existing stormwater infrastructure. 6. On the other hand, the Municipal Aqueduct, through the civil maintenance crew, annually performs preventive and corrective maintenance of the springs, including the Los Herreras Springs, according to the attached work orders (see annexes page 1 to page 60), copies of which are attached. 7.
It is important to emphasize that this process in August 2024 began managing the tender process No. 2024LY-000004-0000500001 'Installation of Conduction and Distribution Networks for Drinking Water, Inestimable Amount', through which it was planned to change the conduction pipes coming from the Los Herreras Springs, since they have reached the end of their useful life and in order to avoid any possible future risk of contamination. Thus, the reconsideration of the technical analysis requested by the Comptroller's Office was carried out, and said document is currently in the Municipal Procurement Department in the final preparation of the adjudication process to be sent to the Honorable Municipal Council for approval." Additionally, it was established that the Planning and Infrastructure Construction Process of the Municipality of Alajuela "is in the process of awarding the concrete screen (pantalla de concreto), a structure that will prevent the mixing of stormwater with that of the catchment sites of the springs. • The need for a comprehensive solution requiring inter-institutional coordination and extraordinary resources remains" (emphasis not in original).
In this sense, while this constitutional jurisdiction understands that it is a long-standing problem that has been addressed by the respondent authorities in the past, it is no less true that, currently, the processes to provide a definitive solution to the complaint filed are in the process of adjudication and tender, and the municipal authorities do not provide, in the report submitted to this Chamber, an estimate of when the described situation will be resolved. For this reason, this Constitutional Court must intervene in order to protect the residents of the area who are being affected by the contamination of the "Los Herrera" spring and the lack of potability in the water they consume.
Consequently, this Chamber considers that the time elapsed to resolve the complaint filed by the protected party and to notify them accordingly by the respondent authorities is disproportionate, since a period of more than ten years has elapsed since the presentation of the first complaint by the petitioners, without it having been resolved to date, with the aggravating factor that the alleged harm reported remains ongoing. Under this understanding, this Chamber considers that the action must be upheld, with the considerations stated in the operative part of this judgment. (...)" ... See more Content of Interest: Type of content: Majority vote Branch of Law: 1. POLITICAL CONSTITUTION WITH JURISPRUDENCE Topic: 041- Effective judicial protection. Prompt and complete justice Subtopics: NOT APPLICABLE.
ARTICLE 41 OF THE POLITICAL CONSTITUTION
"(...) I.- Preliminary Matter. Before analyzing the merits of the matter—for the alleged violation of the right to a prompt and complete procedure—it must be clarified that, based on judgment No. 2008-02545 of 8:55 a.m. on February 22, 2008, this Chamber has referred to the administrative contentious jurisdiction—with some exceptions—those matters in which it is disputed whether the public administration has or has not complied with the deadlines set by the General Law of Public Administration (articles 261 and 325) or sectoral laws for special administrative procedures, to resolve by final act an administrative procedure—initiated ex officio or at the request of a party—or to hear the appropriate administrative appeals. Precisely, in this case, an exception is raised, since it involves an environmental complaint for contamination of a spring, which, allegedly, has not been resolved within a reasonable time by the respondent authorities. Having clarified this point, we proceed to resolve the specific situation raised in this amparo action. (...)" VCG11/2025
... See more Content of Interest: Type of content: Separate note Branch of Law: 4. GUARANTEE MATTERS Topic: PUBLIC SERVICES Subtopics: DRINKING WATER.
In environmental matters, it is the undersigned's criterion that, if the Public Administration has already intervened, its knowledge and resolution corresponds to the administrative contentious jurisdiction. However, I do proceed to hear the merits of the matter when other rights of the persons affected by the source of contamination are at stake, among them, health, quality of life, and the right to enjoy a healthy and contamination-free environment (article 50 of the Political Constitution), as occurs in this case, in which the petitioners report the alleged contamination of the drinking water, of the springs and water intakes coming from the spring known as "Los Herrera", located in the district of La Garita. They argue that since 2012, they have filed complaints before the Municipality of Alajuela, without obtaining an effective solution.
The described situation constitutes an exception to my general position on this matter, which is why I consider it necessary for this Constitutional Court to analyze the merits of the matter, in order to verify or dismiss the allegations of the petitioner.
VCG11/2025 ... See more CONSTITUTIONAL CHAMBER OF THE SUPREME COURT OF JUSTICE. San José, at nine hours thirty minutes on November seventh, two thousand twenty-five.
Amparo action filed by Nombre91390, identification number CED51628, acting as President with powers of Unlimited General Attorney-in-Fact of the INTEGRAL DEVELOPMENT ASSOCIATION OF LA GARITA (ASOCIACIÓN DE DESARROLLO INTEGRAL DE LA GARITA) and Nombre91391, identification number CED51629, acting as President with powers of Unlimited General Attorney-in-Fact of the SPECIFIC DEVELOPMENT ASSOCIATION OF LAGOS DEL COYOL (ASOCIACIÓN DE DESARROLLO ESPECIFICA DE LAGOS DEL COYOL), against the MUNICIPALITY OF ALAJUELA.
Whereas:
Therefore, to eliminate this risk, the existing boxes were repaired and also made taller, so that water levels in the event of a possible flood would not exceed the height of these boxes. • Given that some of the metal covers of the manholes (cajas de registro) were in poor condition, they were repaired or completely replaced, and also secured with a screw. This prevents any undue access by surface water, animals, or persons. 4. However, the protection works carried out allow the Municipality of Alajuela to ensure that the water from the Los Herrera Spring (Naciente Los Herrera) will not be contaminated by the area's own runoff water, nor by vandalism, or by animals that approach to drink water in the stream. 5. Nonetheless, the case at hand concerns an amount of stormwater (agua pluvial) that is not possible to control with only the works carried out by the Aqueduct, since, as I have indicated, it is a problem of stormwater drainage and permits that were granted in the industrial zone without considering the capacity of the existing stormwater infrastructure. 6.
Moreover, the Municipal Aqueduct, through the civil maintenance crew, carries out annual preventive and corrective maintenance of the springs (nacientes), including the Los Herreras Springs, according to the attached work orders (see annexes page 1 to page 60), a copy of which is attached. 7. It is important to emphasize that this process, in August 2024, began to manage bidding process (proceso de licitación) No. 2024LY-000004-0000500001 “Instalación de Redes de Conducción y Distribución de Agua Potable Cuantía Inestimable”, through which it was planned to change the conduction pipes coming from the Los Herreras Springs, given that they have already reached the end of their useful life and in order to avoid any possible risk of contamination in the future; as such, the reconsideration of the technical analysis requested by the comptroller's office was carried out, and said document is currently in the Municipal Procurement Department (Proveeduría Municipal) in the final preparation of the adjudication process to be submitted to the Honorable Municipal Council for approval. 8.
Finally, this Process is willing and committed to providing quality service to our users in accordance with current water quality regulations; however, given the situation, the Municipal Aqueduct has carried out physical-chemical and microbiological analyses of the Los Herrera System, according to reports AG-351-2025 and AG-433-2025, which are attached; furthermore, for Monday, August 11, the UNA Environmental Analysis Laboratory is scheduled to carry out a new sampling of physical-chemical and microbiological analyses of said system.” Subsequently, Ing. Roy Delgado Alpízar, Director of the Infrastructure Planning and Construction Process, in official communication No. MA-PPCI-0578-2025 dated August 4, 2025, stated the following: “(…) In response to official communication MA-PSJ-1368-2025, by which a report is requested related to the amparo appeal filed by Nombre91390 and Nombre91391, under file No. 25-021011-0007-CO, I hereby render this technical report, in my capacity as Director of the Infrastructure Planning and Construction Process of the Municipality of Alajuela, under oath and pursuant to Articles 44 and 45 of the Constitutional Jurisdiction Act. 1.
Technical Background. Since 2012, this unit has identified the need to channel the stormwater (aguas pluviales) affecting the Los Herrera springs, located in the district of La Garita. Hydrological studies and technical designs were carried out, and permits were processed with SETENA and MINAE to channel the course of the Santa Marta stream. 2. Actions Taken. • Official communication MA-PPCI-0798-2012: channeling was proposed and the contracting of environmental services (servicios ambientales) was requested. • Official communication MA-PPCI-0896-2023: it was requested that the technical solution be declared of public interest. • Official communication MA-SCM-2203-2023: the Public Works Commission recommended continuing the project, although the Council rejected the expropriation required to install the pipeline starting from the channel located on public land, through private properties, to the discharge point in the Santa Marta stream. 3.
Limitations Encountered. • The Municipal Council's refusal to declare the expropriation of public interest prevented progress with the execution of the project. • However, the administration has continued seeking technical and legal alternatives to resolve the problem. 4. Current Situation. • A partial diversion of the channel was executed in 2025 as a temporary measure. • The concrete barrier (pantalla de concreto) is in the process of being adjudicated, a structure that will prevent the mixing of stormwater (aguas pluviales) with the water from the spring capture sites (sitios de captación de las nacientes). • There remains a need for a comprehensive solution that requires inter-institutional coordination and extraordinary resources. 5. Institutional Commitment. The Infrastructure Planning and Construction Process reiterates its commitment to protecting water resources and public health, and is prepared to collaborate with judicial and administrative authorities to implement the appropriate measures. 6.
Complementary Actions Underway. Additionally, as indicated, it is reported that Ing. Jeffry Alvarado Cruz, Cantonal Risk Prevention and Management Promoter, who is part of the Infrastructure Planning and Construction Process under this Directorate, has arranged a contract for the installation of a containment barrier (pantalla de contención), whose objective is to divert the stormwater that currently affects the Los Herrera springs. This measure seeks to significantly mitigate the immediate impact while progress is made toward implementing a comprehensive solution. The barrier is designed to redirect the flow toward less vulnerable zones, significantly reducing the risk of infiltration and direct contamination of the water intakes. Likewise, it is communicated that this Directorate is currently conducting a feasibility and cost-benefit analysis of once again requesting the required expropriation, in order to make the execution of the stormwater channeling project and protection of the springs viable, or alternatively, to propose an equivalent solution.
This action responds to the urgent need to guarantee safe access to drinking water and to address the technical recommendations previously issued.” Based on the reports rendered, it is verified that the situation denounced by the appellants has been addressed for many years prior to the notification of this appeal. This was evidenced by the technical opinion issued by Ing. Delgado Alpízar, since the Municipality identified the need to channel the stormwater affecting the spring that is the subject of this appeal. It is confirmed that the Municipality, for years, has worked on carrying out hydrological studies and technical designs, and processed permits with SETENA and MINAE to channel the course of the Santa Marta stream, proposing the channeling of said waters and, at the time, requesting the contracting of environmental services. Subsequently, in 2023, the Municipal Council was asked to declare the technical solution of public interest, and it was then, by agreement of the Municipal Council, that official communication No. MA-SCOP-51-2023 was accepted, but the request for a declaration of public interest for the expropriation was rejected, as can be seen in the following manner (information that can be seen in ordinary minutes No. 35-2023 held by this Corporation of the Central Canton of Alajuela, at six o'clock in the evening on Tuesday, August 29, 2023) (…) However, it should be noted that, despite the Municipal Council's refusal to declare the expropriation of public interest, and according to the technical opinion issued, that situation did not prevent the administration from continuing to seek alternatives to resolve the problem.
Despite this inconvenience, a partial diversion of the channel was executed as a temporary measure, and the concrete barrier is currently in the process of being adjudicated, which is the structure that will prevent stormwater from mixing with the water from the spring capture sites. In addition, the Cantonal Risk Prevention and Management Promoter has arranged a contract for the installation of a containment barrier, whose objective is to divert the stormwater that currently affects the Los Herrera springs. The foregoing is carried out with the objective of significantly mitigating the immediate impact, while progress is made in the implementation of a comprehensive solution, since said barrier is designed to redirect the flow toward less vulnerable zones, reducing the risk of infiltration and direct contamination of the water intakes. In addition to the foregoing, the Municipality, with the collaboration of the infrastructure planning and construction department, is currently conducting a feasibility and cost-benefit analysis of once again requesting the required expropriation, in order to make the execution of the stormwater channeling project and protection of the springs viable, this with the aim of guaranteeing safe access to drinking water and addressing the respective technical recommendations.
With what has been indicated above, it is also verified that the subjective arguments made by the appellants, to the effect that “(…) And currently the problem has worsened and the authorities have not carried out effective implementation tasks to solve the contamination problems of the springs (…)” and when they indicated that “(…) They presume there has been technical, legal, and administrative incapacity on the part of the Municipality, as well as a lack of will to execute the necessary solutions, maintaining a constant threat to the springs and the drinking water supply (…)”, are not true, since what is evident is a complete lack of knowledge of the internal processes that must be carried out at the municipal level with respect to these specific issues, which are extremely complex and exhaustive. It is verified, and the appellants themselves acknowledge, that the municipal administration has always kept them informed of the situation that occurred, making it clear that actions have indeed been taken to remedy the problem that occurred, yet situations beyond our control have arisen, which is why the administration declared itself “unable,” but it should be clarified that this is not due to a capricious matter on the part of the administration, but rather it is verified that an important action for the continuation of the project was rejected by the Municipal Council.
It is important to mention that it is demonstrated that there is no omission or “inaction” on the part of the Municipality; however, with the subjective arguments given by the appellants, we reiterate, what they evidence is a clear lack of knowledge of the internal administrative procedures to be followed in this Municipality, procedures that are in accordance with meeting the respective legal requirements, respecting the competencies of each of the corresponding bodies (…)” They request the appeal be dismissed.
Written by Magistrate Araya García; and,
Considering:
I.Preliminary Matter. Before analyzing the merits of the case —regarding the alleged violation of the right to a prompt and completed procedure— it must be clarified that, based on judgment No. 2008-02545 of 8:55 a.m. on February 22, 2008, this Chamber has referred to the contentious-administrative jurisdiction —with some exceptions— those matters in which it is debated whether the public administration has complied or not with the deadlines established by the General Public Administration Act (Articles 261 and 325) or sectoral laws for special administrative procedures, to resolve by final act an administrative procedure —initiated ex officio or at the request of a party— or to hear the pertinent administrative appeals. Precisely, in this case, an exceptional situation is raised, as it involves an environmental complaint for pollution of a spring (naciente), which, allegedly, has not been resolved within a reasonable time by the respondent authorities. Having clarified this point, we proceed to resolve the specific situation raised in this amparo.
II.Object of the Appeal. The appellants claim that since 2012 they have filed complaints before the Municipality of Alajuela about the constant contamination problems of the drinking water, from the springs and water intakes coming from the spring known as “Los Herrera”. They assert that, as of the date they filed this appeal, the complaint has not been definitively resolved by the respondent authorities, which they consider harmful to their fundamental rights.
Therefore, to eliminate this risk, the existing boxes were repaired and also made taller, so that water levels in the event of a possible flood would not exceed the height of these boxes. • Given that some of the metal covers of the manholes were in poor condition, they were repaired or completely replaced, and also secured with a screw. This prevents any undue access by surface water, animals, or persons. 4. However, the protection works carried out allow the Municipality of Alajuela to ensure that the water from the Los Herrera Spring will not be contaminated by the area's own runoff water, nor by vandalism, or by animals that approach to drink water in the stream. 5. Nonetheless, the case at hand concerns an amount of stormwater that is not possible to control with only the works carried out by the Aqueduct, since, as I have indicated, it is a problem of stormwater drainage and permits that were granted in the industrial zone without considering the capacity of the existing stormwater infrastructure. 6.
Moreover, the Municipal Aqueduct, through the civil maintenance crew, carries out annual preventive and corrective maintenance of the springs, including the Los Herreras Springs, according to the attached work orders (see annexes page 1 to page 60), a copy of which is attached. 7. It is important to emphasize that this process, in August 2024, began to manage bidding process No. 2024LY-000004-0000500001 “Instalación de Redes de Conducción y Distribución de Agua Potable Cuantía Inestimable”, through which it was planned to change the conduction pipes coming from the Los Herreras Springs, given that they have already reached the end of their useful life and in order to avoid any possible risk of contamination in the future; as such, the reconsideration of the technical analysis requested by the comptroller's office was carried out, and said document is currently in the Municipal Procurement Department in the final preparation of the adjudication process to be submitted to the Honorable Municipal Council for approval. 8.
Finally, this Process is willing and committed to providing quality service to our users in accordance with current water quality regulations; however, given the situation, the Municipal Aqueduct has carried out physical-chemical and microbiological analyses of the Los Herrera System, according to reports AG-351-2025 and AG-433-2025, which are attached” (see report rendered by the respondent authority and evidence provided to the file).
IV.Regarding the Specific Case. In the sub iudice case, the appellant party alleges that since 2012 they have filed complaints before the Municipality of Alajuela about the constant contamination problems of the drinking water, from the springs and water intakes coming from the spring known as “Los Herrera”. They assert that, as of the date they filed this appeal, the complaint has not been definitively resolved by the respondent authorities, which they consider harmful to their fundamental rights.
In this regard, this Chamber verifies that, in the specific case, indeed, there is knowledge of a complaint filed before the Municipality of Alajuela by the appellants at different times, the first during 2012, and subsequently, on May 10, 2020, January 5, 2024, and June 4, 2024, concerning the contamination problem occurring at the “Los Herrera” spring, a situation of which the respondent municipal authorities have been fully aware for 13 years.
Certainly, it was possible to verify that, despite the fact that the respondent authorities have been aware of the denounced situation since 2012 and have attempted to carry out actions to correct the problem, it is no less true that, as of the date this appeal was filed, the complaint had not been definitively addressed; moreover, it was possible to verify that the authorities are aware that the works carried out in the past do not in any way solve the problem in question, since they acknowledge in the report rendered before this Chamber that: “1. Initially, the conflict arose because there are constructions in the El Coyol industrial zone, discharging their stormwater through a “ditch” that did not have the capacity for such activity. 2. As has already been reported, the problem is exacerbated because it also affects the service provided by the Municipal Aqueduct to the residents of La Garita and Lagos del Coyol, since said stormwater reaches very close to the sources captured by the Municipality and because the receiving body does not have sufficient capacity to evacuate them, precisely where the Los Herrera Spring is located, the land floods, putting the potability of the water from the captured sources at risk. 3.
This Municipal Aqueducts and Sewers Process carried out a project for the construction of Protection Works for the Los Herrera Spring; work that was completed satisfactorily, according to the terms of abbreviated bidding No. 2011LA-00006-01. • Said works consisted of providing protection against unscrupulous individuals, as well as protection against possible surface contamination from stormwater or wastewater. • To prevent the entry of persons into the manholes of the intakes, concrete walls and chain-link fencing were built surrounding them, with access only through a gate with its respective padlock. • The most likely points of entry for surface runoff, due to a flood event, were precisely the manholes of the intakes and the collection tanks. Therefore, to eliminate this risk, the existing boxes were repaired and also made taller, so that water levels in the event of a possible flood would not exceed the height of these boxes. • Given that some of the metal covers of the manholes were in poor condition, they were repaired or completely replaced, and also secured with a screw.
This prevents any undue access by surface water, animals, or persons. 4. However, the protection works carried out allow the Municipality of Alajuela to ensure that the water from the Los Herrera Spring will not be contaminated by the area's own runoff water, nor by vandalism, or by animals that approach to drink water in the stream. 5. Nonetheless, the case at hand concerns an amount of stormwater that is not possible to control with only the works carried out by the Aqueduct, since, as I have indicated, it is a problem of stormwater drainage and permits that were granted in the industrial zone without considering the capacity of the existing stormwater infrastructure. 6. Moreover, the Municipal Aqueduct, through the civil maintenance crew, carries out annual preventive and corrective maintenance of the springs, including the Los Herreras Springs, according to the attached work orders (see annexes page 1 to page 60), a copy of which is attached. 7.
It is important to emphasize that this process, in August 2024, began to manage bidding process No. 2024LY-000004-0000500001 “Instalación de Redes de Conducción y Distribución de Agua Potable Cuantía Inestimable”, through which it was planned to change the conduction pipes coming from the Los Herreras Springs, given that they have already reached the end of their useful life and in order to avoid any possible risk of contamination in the future; as such, the reconsideration of the technical analysis requested by the comptroller's office was carried out, and said document is currently in the Municipal Procurement Department in the final preparation of the adjudication process to be submitted to the Honorable Municipal Council for approval”. Additionally, it was accredited that the Infrastructure Planning and Construction Process of the Municipality of Alajuela “is in the adjudication process for the concrete barrier, a structure that will prevent the mixing of stormwater with the water from the spring capture sites. • There remains a need for a comprehensive solution that requires inter-institutional coordination and extraordinary resources” (emphasis does not belong to the original).
In this sense, although this constitutional jurisdiction understands that it is a long-standing problem that has been addressed by the respondent authorities in the past, it is no less true that the processes currently underway to provide a definitive solution to the complaint filed are in the adjudication and bidding stages, and the municipal authorities do not provide, in the report rendered before this Chamber, an estimated timeframe for when the described situation will be resolved. For this reason, this Constitutional Court must intervene in order to protect the residents of the area who are being affected by the contamination of the “Los Herrera” spring and by the lack of potability in the water they consume.
Consequently, this Chamber finds that the time elapsed to resolve the complaint filed by the protected party and to communicate the corresponding response by the respondent authorities is disproportionate, given that a period of more than ten years has elapsed since the first complaint was filed by the appellants, without it having been resolved to date, with the aggravating factor that the alleged harm denounced remains ongoing. Under this reasoning, this Chamber considers that the appeal must be granted, with the considerations that will be stated in the operative part of this judgment.
In environmental matters, it is the opinion of the undersigned that, if the Public Administration has already intervened, its knowledge and resolution corresponds to the contentious-administrative jurisdiction. However, I do proceed to examine the merits of the matter when other rights of the persons affected by the source of contamination are at stake, among them, health, quality of life, and the right to enjoy a healthy environment free from pollution (Article 50 of the Political Constitution), as is the case here, in which the appellants denounce the alleged contamination of the drinking water, from the springs and water intakes coming from the spring known as “Los Herrera”, located in the district of La Garita. They argue that since 2012, they have filed complaints before the Municipality of Alajuela, without obtaining an effective solution.
The described situation constitutes an exception to my general position on this matter, and I therefore deem it necessary for this Constitutional Court to analyze the merits of the case, in order to verify or dismiss the allegations of the appellant party.
The party is warned that, if they have submitted any document on paper, as well as objects or evidence contained in any additional electronic, computer, magnetic, optical, telematic device or one produced by new technologies, these must be retrieved from the office within a maximum period of 30 business days counted from the notification of this judgment. Otherwise, any material not retrieved within this period will be destroyed, as provided in the “Reglamento sobre Expediente Electrónico ante el Poder Judicial,” approved by the Corte Plena in session No. 27-11 of August 22, 2011, article XXVI and published in Boletín Judicial number 19 of January 26, 2012, as well as in the agreement approved by the Consejo Superior del Poder Judicial, in session No. 43-12 held on May 3, 2012, article LXXXI.
Por tanto:
The appeal is declared with merit. Roberto Hernán Thompson Chacón and Roy Delgado Alpízar, in their order Mayor and Director of Planning and Municipal Infrastructure Construction, both of the Municipalidad de Alajuela, or whoever holds those positions, are ordered to carry out the actions within the scope of their competencies and establish the necessary actions and coordination, so that within a maximum period of six months counted from the notification of this judgment, the contracts and works deemed necessary are executed and the pertinent administrative measures and resolutions are adopted, to address the complaint filed by the appellants and communicate what is appropriate to them. The respondents are warned that, should they fail to comply with said order, they will incur the crime of disobedience and that, in accordance with article 71 of the Law of this jurisdiction, whoever receives an order that they must comply with or enforce, issued in an amparo appeal, and does not comply with it or does not enforce it, shall be subject to imprisonment of three months to two years, or a fine of twenty to sixty days, provided the offense is not more severely punished.
The Municipalidad de Alajuela is ordered to pay the costs, damages, and losses caused by the facts that serve as the basis for this declaration, which shall be liquidated in execution of judgment of the contentious-administrative proceeding. Judge Salazar Alvarado records a note. Notifíquese.- Fernando Cruz C.
Presidente a.i Luis Fdo. Salazar A.
Jorge Araya G.
Ingrid Hess H.
Ronald Salazar Murillo Ileana Sánchez N.
Jose Roberto Garita N.
Clasificación elaborada por SALA CONSTITUCIONAL del Poder Judicial. Prohibida su reproducción y/o distribución en forma onerosa.
Sentencia con nota separada Indicadores de Relevancia Sentencia relevante Sentencia con datos protegidos, de conformidad con la normativa vigente Contenido de Interés:
Temas Estrategicos: Derecho a la salud,Der Económicos sociales culturales y ambientales Tipo de contenido: Voto de mayoría Rama del Derecho: 4. ASUNTOS DE GARANTÍA Tema: SERVICIOS PÚBLICOS Subtemas:
AGUA POTABLE.
036588-25. SERVICIOS PÚBLICOS. VECINOS DE LA GARITA DE ALAJUELA, ACUSAN LOS PROBLEMAS DE CONTAMINACIÓN CONSTANTE DEL AGUA POTABLE DE LAS NACIENTES Y TOMAS DE AGUA PROVENIENTES DE LA NACIENTE CONOCIDA COMO “LOS HERRERA”. SE ORDENA A LA MUNICIPALIDAD DE ALAJUELA, REALIZAR LAS ACTUACIONES QUE ESTÉN DENTRO DEL ÁMBITO DE SUS COMPETENCIAS Y ESTABLEZCAN LAS ACCIONES Y COORDINACIONES NECESARIAS, PARA QUE EN EL PLAZO MÁXIMO DE SEIS MESES, SE EJECUTEN LAS CONTRATACIONES Y OBRAS QUE SE ESTIME NECESARIAS Y SE ADOPTEN LAS MEDIDAS Y RESOLUCIONES ADMINISTRATIVAS PERTINENTES, PARA ATENDER LA DENUNCIA PLANTEADA POR LOS RECURRENTES Y SE LES COMUNIQUE LO QUE CORRESPONDA. VCG11/2025 “(…) IV.- Sobre el caso concreto. En el sub lite, la parte recurrente acusa que desde el año 2012 denunciaron ante la Municipalidad de Alajuela, por los problemas de contaminación constante del agua potable, de las nacientes y tomas de agua proveniente de la naciente conocida como “Los Herrera”. Aseguran que, a la fecha en que presentan este recurso, la denuncia no ha sido resuelta de manera definitiva por parte de las autoridades recurridas, lo que estima lesivo de sus derechos fundamentales.
Al respecto, esta Sala verifica que, en el caso concreto, efectivamente, se tiene conocimiento de una denuncia realizada ante la Municipalidad de Alajuela por parte de los recurrentes en diferentes momentos, la primera durante el año 2012, y posteriormente, el 10 de mayo de 2020, 5 de enero de 2024 y el 4 de junio de 2024, por el problema de contaminación que se da en la naciente “Los Herrera”, situación que es de pleno conocimiento de las autoridades municipales recurridas desde hace 13 años.
Ciertamente, se pudo verificar que, pese a que las autoridades recurridas tuvieron conocimiento de la situación denunciada desde el año 2012 y han intentado realizar actuaciones para corregir la problemática, no menos cierto es que, a la fecha de presentación de este recurso no se había atendido de manera definitiva la denuncia e incluso, se pudo comprobar que, las autoridades son conscientes de que los trabajos realizados en el pasado, no solucionan de manera alguna la problemática en cuestión, puesto que, reconocen en el informe rendido ante esta Sala que “1. Inicialmente el conflicto se presentó dado que existen construcciones en la zona industrial de El Coyol, evacuando sus aguas pluviales por medio de un “caño” que no contaba con capacidad para tal actividad. 2. Como ya se ha informado, el problema se acrecienta debido a que también afecta el servicio que brinda el Acueducto Municipal a los vecinos de La Garita y de Lagos del Coyol, pues dichas aguas pluviales llegan muy cerca de las fuentes que capta la Municipalidad y como el cuerpo receptor no cuenta con capacidad suficiente para evacuarlas, justo en donde está la Naciente Los Herrera el terreno se inunda, poniendo en riesgo la potabilidad del agua de las fuentes captadas. 3.
Este Proceso de Acueductos y Alcantarillados Municipales llevó a cabo un proyecto para construcción de obras de Protección de la Naciente Los Herrera; trabajo que fue concluido de forma satisfactoria, según lo establecido en el cartel de la licitación abreviada N° 2011LA-00006-01. • Dichos trabajos consistieron en brindar, tanto protección contra personas inescrupulosas, así como protección contra posible contaminación superficial de aguas pluviales o servidas. • Para impedir al ingreso de personas a las cajas de registro de las captaciones, se construyeron muros de concreto y malla ciclón rodeando las mismas, con accesos únicamente mediante portón con su respectivo candado. • Los puntos más probables de ingreso de escorrentía superficial, debido a algún evento de inundación eran precisamente las cajas de registro de las captaciones y de los tanques de reunión. Por tanto, para eliminar este riesgo, se procedió a reparar las cajas existentes y también hacerlas más altas, para que los niveles de agua frente a una posible inundación no sobrepasaran la altura de estas cajas. • Dado que algunas de las tapas metálicas de las cajas de registro se encontraban en mal estado, se procedió a reparar o sustituir del todo las mismas, además de asegurarlas con Tornillo.
Esto previene cualquier acceso indebido tanto de agua superficial, animales o personas. 4. Sin embargo, las obras de protección ejecutadas lo que permite a la Municipalidad de Alajuela es asegurar que el agua de la Naciente Los Herrera no será contaminada por las aguas de escorrentía propias de la zona, ni por vandalismo, o por los animales que se acercan a tomar agua en la quebrada. 5. No obstante, el caso que nos ocupa trata de una cantidad de agua pluvial que no es posible controlar con solo las obras realizadas por el Acueducto, pues como lo he indicado, se trata de un problema de alcantarillado pluvial y de permisos que se otorgaron en la zona industrial, sin tomar en consideración la capacidad de infraestructura pluvial existente. 6. Por otra parte, el Acueducto Municipal mediante la cuadrilla de mantenimiento civil realiza de forma anual mantenimientos preventivos y correctivos de las nacientes, entre ellas las Nacientes Los Herreras, según ordenes de trabajos adjuntas (ver anexos página 1 a página 60), las cuales se adjunta copia. 7.
Es importante recalcar que este proceso en agosto de 2024 comenzó a gestionar el proceso de licitación N° 2024LY-000004-0000500001 “Instalación de Redes de Conducción y Distribución de Agua Potable Cuantía Inestimable”, mediante la cual se planificó cambiar las tuberías de conducción provenientes de la Nacientes Los Herreras, dado que las mismas ya cumplieron su vida útil y con el fin evitar a futuro cualquier posible riesgo de contaminación, así las cosas se realizó la reconsideración del análisis técnico solicitado por la contraloría, y dicho documento actualmente se encuentra en Proveeduría Municipal en la elaboración final del proceso de adjudicación para ser remitido al Honorable Concejo Municipal para su aprobación”. Adicionalmente, se tuvo por acreditado que, el Proceso de Planeamiento y Construcción de Infraestructura de la Municipalidad de Alajuela “está en proceso de adjudicación de la pantalla de concreto, estructura que evitará la mezcla de las aguas pluviales con las de los sitios de captación de las nacientes. • Se mantiene la necesidad de una solución integral que requiere coordinación interinstitucional y recursos extraordinarios” (el resaltado no pertenece al original).
En este sentido, si bien esta jurisdicción constitucional comprende que se trata de un problema de larga data y que ha sido atendido por las autoridades recurridas en el pasado, no menos cierto es que, actualmente los procesos para brindar una solución definitiva a la denuncia planteada se encuentra en proceso de adjudicación y de licitación y las autoridades municipales no brindan en el informe rendido ante esta Sala un aproximado de cuándo será solucionada la situación descrita, razón por la cual, este Tribunal Constitucional debe intervenir en aras de proteger a los vecinos de la zona que se están viendo afectados por la contaminación de la naciente “Los Herrera” y de la falta de potabilidad en el agua que consumen.
En consecuencia, estima esta Sala que el plazo que ha transcurrido para resolver la denuncia planteada por la parte tutelada y comunicarle lo respectivo por parte de las autoridades recurridas es desproporcionado, por cuanto, ha transcurrido un plazo de, más de diez años, desde la presentación de la primera denuncia por parte de los recurrentes, sin que a la fecha esta haya sido resuelta, con el agravante que la presunta afectación denunciada continúa vigente. Bajo esta inteligencia, considera esta Sala que el recurso debe ser declarado con lugar, con las consideraciones que se dirán en la parte dispositiva de esta sentencia. (…)” ... Ver más Contenido de Interés:
Tipo de contenido: Voto de mayoría Rama del Derecho: 1. CONSTITUCIÓN POLÍTICA CON JURISPRUDENCIA Tema: 041- Tutela judicial efectiva. Justicia pronta y cumplida Subtemas:
NO APLICA.
ARTÍCULO 41 DE LA CONSTITUCIÓN POLÍTICA “(…) I.- Cuestión Preliminar. De previo a analizar el fondo del asunto -por la presunta violación del derecho a un procedimiento pronto y cumplido- debe aclararse que, a partir de la sentencia No. 2008-02545 de las 8:55 horas de 22 de febrero de 2008, esta Sala ha remitido a la jurisdicción contencioso administrativa -con algunas excepciones-, aquellos asuntos en los que se discute si la administración pública ha cumplido o no los plazos pautados por la Ley General de la Administración Pública (artículos 261 y 325) o las leyes sectoriales para los procedimientos administrativos especiales, para resolver por acto final un procedimiento administrativo -instruido de oficio o a instancia de parte- o conocer de los recursos administrativos procedentes. Precisamente, en este caso, se plantea un supuesto de excepción, pues, se está ante una denuncia ambiental por contaminación de una naciente, la cual, presuntamente, no ha sido resuelta dentro de un plazo razonable por parte de las autoridades recurridas. Aclarado el punto, se entra a resolver la situación concreta planteada en este amparo. (…)” VCG11/2025 ... Ver más Contenido de Interés:
Tipo de contenido: Nota separada Rama del Derecho: 4. ASUNTOS DE GARANTÍA Tema: SERVICIOS PÚBLICOS Subtemas:
AGUA POTABLE.
En asuntos ambientales, es criterio del suscrito, que, si ya ha habido intervención de la Administración Pública, su conocimiento y resolución corresponde a la jurisdicción contenciosa administrativa. No obstante, sí entro a conocer el fondo del asunto cuando están de por medio otros derechos de las personas afectadas por el foco de contaminación, entre ellos, la salud, la calidad de vida y el derecho a gozar de un ambiente sano y libre de contaminación (artículo 50, de la Constitución Política), tal y como sucede en este caso, en el que los recurrentes denuncian la presunta contaminación, del agua potable, de las nacientes y tomas de agua proveniente de la naciente conocida como “Los Herrera”, ubicada en el distrito de La Garita. Aducen que desde el año 2012, han planteado denuncias ante la Municipalidad de Alajuela, sin obtener una solución efectiva.
La situación descrita constituye una excepción a mi posición general en esta materia, por lo que estimo necesario que este Tribunal Constitucional analizara por el fondo el asunto, con el fin de verificar o descartar los alegatos de la parte recurrente.
VCG11/2025 ... Ver más SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas treinta minutos del siete de noviembre de dos mil veinticinco .
Recurso de amparo interpuesto por Nombre91390, cédula de identidad CED51628, en su condición de Presidenta con facultades de Apoderada Generalísima sin límite de suma de la ASOCIACIÓN DE DESARROLLO INTEGRAL DE LA GARITA y Nombre91391, cédula de identidad CED51629, en su condición de Presidente con facultades de Apoderado Generalísimo sin límite de suma de la ASOCIACIÓN DE DESARROLLO ESPECIFICA DE LAGOS DEL COYOL, contra la MUNICIPALIDAD DE ALAJUELA.
Resultando:
Redacta el Magistrado Araya García; y,
Considerando:
I.Cuestión Preliminar. De previo a analizar el fondo del asunto -por la presunta violación del derecho a un procedimiento pronto y cumplido- debe aclararse que, a partir de la sentencia No. 2008-02545 de las 8:55 horas de 22 de febrero de 2008, esta Sala ha remitido a la jurisdicción contencioso administrativa -con algunas excepciones-, aquellos asuntos en los que se discute si la administración pública ha cumplido o no los plazos pautados por la Ley General de la Administración Pública (artículos 261 y 325) o las leyes sectoriales para los procedimientos administrativos especiales, para resolver por acto final un procedimiento administrativo -instruido de oficio o a instancia de parte- o conocer de los recursos administrativos procedentes. Precisamente, en este caso, se plantea un supuesto de excepción, pues, se está ante una denuncia ambiental por contaminación de una naciente, la cual, presuntamente, no ha sido resuelta dentro de un plazo razonable por parte de las autoridades recurridas. Aclarado el punto, se entra a resolver la situación concreta planteada en este amparo.
II.Objeto del recurso. Alegan los recurrentes que desde el año 2012 denunciaron ante la Municipalidad de Alajuela, por los problemas de contaminación constante del agua potable, de las nacientes y tomas de agua proveniente de la naciente conocida como “Los Herrera”. Aseguran que, a la fecha en que presentan este recurso, la denuncia no ha sido resuelta de manera definitiva por parte de las autoridades recurridas, lo que estima lesivo de sus derechos fundamentales.
III.Hechos probados. De importancia para la decisión de este asunto, se estiman como debidamente demostrados los siguientes hechos:
Por tanto, para eliminar este riesgo, se procedió a reparar las cajas existentes y también hacerlas más altas, para que los niveles de agua frente a una posible inundación no sobrepasaran la altura de estas cajas. • Dado que algunas de las tapas metálicas de las cajas de registro se encontraban en mal estado, se procedió a reparar o sustituir del todo las mismas, además de asegurarlas con Tornillo. Esto previene cualquier acceso indebido tanto de agua superficial, animales o personas. 4. Sin embargo, las obras de protección ejecutadas lo que permite a la Municipalidad de Alajuela es asegurar que el agua de la Naciente Los Herrera no será contaminada por las aguas de escorrentía propias de la zona, ni por vandalismo, o por los animales que se acercan a tomar agua en la quebrada. 5. No obstante, el caso que nos ocupa trata de una cantidad de agua pluvial que no es posible controlar con solo las obras realizadas por el Acueducto, pues como lo he indicado, se trata de un problema de alcantarillado pluvial y de permisos que se otorgaron en la zona industrial, sin tomar en consideración la capacidad de infraestructura pluvial existente. 6.
Por otra parte, el Acueducto Municipal mediante la cuadrilla de mantenimiento civil realiza de forma anual mantenimientos preventivos y correctivos de las nacientes, entre ellas las Nacientes Los Herreras, según ordenes de trabajos adjuntas (ver anexos página 1 a página 60), las cuales se adjunta copia. 7. Es importante recalcar que este proceso en agosto de 2024 comenzó a gestionar el proceso de licitación N° 2024LY-000004-0000500001 “Instalación de Redes de Conducción y Distribución de Agua Potable Cuantía Inestimable”, mediante la cual se planificó cambiar las tuberías de conducción provenientes de la Nacientes Los Herreras, dado que las mismas ya cumplieron su vida útil y con el fin evitar a futuro cualquier posible riesgo de contaminación, así las cosas se realizó la reconsideración del análisis técnico solicitado por la contraloría, y dicho documento actualmente se encuentra en Proveeduría Municipal en la elaboración final del proceso de adjudicación para ser remitido al Honorable Concejo Municipal para su aprobación. 8.
Por ultimo este Proceso esta anuente y comprometido por brindar un servicio de calidad a nuestros usuarios en apego a la reglamentación de la calidad del agua vigente, sin embargo, ante la problemática el Acueducto municipal ha realizado análisis físicos-químicos y microbiológicos del Sistema Los Herrera, según reportes AG-351-2025 y AG-433-2025 mismos que se adjuntan” (ver informe rendido por la autoridad recurrida y prueba aportada al expediente).
IV.Sobre el caso concreto. En el sub lite, la parte recurrente acusa que desde el año 2012 denunciaron ante la Municipalidad de Alajuela, por los problemas de contaminación constante del agua potable, de las nacientes y tomas de agua proveniente de la naciente conocida como “Los Herrera”. Aseguran que, a la fecha en que presentan este recurso, la denuncia no ha sido resuelta de manera definitiva por parte de las autoridades recurridas, lo que estima lesivo de sus derechos fundamentales.
Al respecto, esta Sala verifica que, en el caso concreto, efectivamente, se tiene conocimiento de una denuncia realizada ante la Municipalidad de Alajuela por parte de los recurrentes en diferentes momentos, la primera durante el año 2012, y posteriormente, el 10 de mayo de 2020, 5 de enero de 2024 y el 4 de junio de 2024, por el problema de contaminación que se da en la naciente “Los Herrera”, situación que es de pleno conocimiento de las autoridades municipales recurridas desde hace 13 años.
Ciertamente, se pudo verificar que, pese a que las autoridades recurridas tuvieron conocimiento de la situación denunciada desde el año 2012 y han intentado realizar actuaciones para corregir la problemática, no menos cierto es que, a la fecha de presentación de este recurso no se había atendido de manera definitiva la denuncia e incluso, se pudo comprobar que, las autoridades son conscientes de que los trabajos realizados en el pasado, no solucionan de manera alguna la problemática en cuestión, puesto que, reconocen en el informe rendido ante esta Sala que “1. Inicialmente el conflicto se presentó dado que existen construcciones en la zona industrial de El Coyol, evacuando sus aguas pluviales por medio de un “caño” que no contaba con capacidad para tal actividad. 2. Como ya se ha informado, el problema se acrecienta debido a que también afecta el servicio que brinda el Acueducto Municipal a los vecinos de La Garita y de Lagos del Coyol, pues dichas aguas pluviales llegan muy cerca de las fuentes que capta la Municipalidad y como el cuerpo receptor no cuenta con capacidad suficiente para evacuarlas, justo en donde está la Naciente Los Herrera el terreno se inunda, poniendo en riesgo la potabilidad del agua de las fuentes captadas. 3.
Este Proceso de Acueductos y Alcantarillados Municipales llevó a cabo un proyecto para construcción de obras de Protección de la Naciente Los Herrera; trabajo que fue concluido de forma satisfactoria, según lo establecido en el cartel de la licitación abreviada N° 2011LA-00006-01. • Dichos trabajos consistieron en brindar, tanto protección contra personas inescrupulosas, así como protección contra posible contaminación superficial de aguas pluviales o servidas. • Para impedir al ingreso de personas a las cajas de registro de las captaciones, se construyeron muros de concreto y malla ciclón rodeando las mismas, con accesos únicamente mediante portón con su respectivo candado. • Los puntos más probables de ingreso de escorrentía superficial, debido a algún evento de inundación eran precisamente las cajas de registro de las captaciones y de los tanques de reunión. Por tanto, para eliminar este riesgo, se procedió a reparar las cajas existentes y también hacerlas más altas, para que los niveles de agua frente a una posible inundación no sobrepasaran la altura de estas cajas. • Dado que algunas de las tapas metálicas de las cajas de registro se encontraban en mal estado, se procedió a reparar o sustituir del todo las mismas, además de asegurarlas con Tornillo.
Esto previene cualquier acceso indebido tanto de agua superficial, animales o personas. 4. Sin embargo, las obras de protección ejecutadas lo que permite a la Municipalidad de Alajuela es asegurar que el agua de la Naciente Los Herrera no será contaminada por las aguas de escorrentía propias de la zona, ni por vandalismo, o por los animales que se acercan a tomar agua en la quebrada. 5. No obstante, el caso que nos ocupa trata de una cantidad de agua pluvial que no es posible controlar con solo las obras realizadas por el Acueducto, pues como lo he indicado, se trata de un problema de alcantarillado pluvial y de permisos que se otorgaron en la zona industrial, sin tomar en consideración la capacidad de infraestructura pluvial existente. 6. Por otra parte, el Acueducto Municipal mediante la cuadrilla de mantenimiento civil realiza de forma anual mantenimientos preventivos y correctivos de las nacientes, entre ellas las Nacientes Los Herreras, según ordenes de trabajos adjuntas (ver anexos página 1 a página 60), las cuales se adjunta copia. 7.
Es importante recalcar que este proceso en agosto de 2024 comenzó a gestionar el proceso de licitación N° 2024LY-000004-0000500001 “Instalación de Redes de Conducción y Distribución de Agua Potable Cuantía Inestimable”, mediante la cual se planificó cambiar las tuberías de conducción provenientes de la Nacientes Los Herreras, dado que las mismas ya cumplieron su vida útil y con el fin evitar a futuro cualquier posible riesgo de contaminación, así las cosas se realizó la reconsideración del análisis técnico solicitado por la contraloría, y dicho documento actualmente se encuentra en Proveeduría Municipal en la elaboración final del proceso de adjudicación para ser remitido al Honorable Concejo Municipal para su aprobación”. Adicionalmente, se tuvo por acreditado que, el Proceso de Planeamiento y Construcción de Infraestructura de la Municipalidad de Alajuela “está en proceso de adjudicación de la pantalla de concreto, estructura que evitará la mezcla de las aguas pluviales con las de los sitios de captación de las nacientes. • Se mantiene la necesidad de una solución integral que requiere coordinación interinstitucional y recursos extraordinarios” (el resaltado no pertenece al original).
En este sentido, si bien esta jurisdicción constitucional comprende que se trata de un problema de larga data y que ha sido atendido por las autoridades recurridas en el pasado, no menos cierto es que, actualmente los procesos para brindar una solución definitiva a la denuncia planteada se encuentra en proceso de adjudicación y de licitación y las autoridades municipales no brindan en el informe rendido ante esta Sala un aproximado de cuándo será solucionada la situación descrita, razón por la cual, este Tribunal Constitucional debe intervenir en aras de proteger a los vecinos de la zona que se están viendo afectados por la contaminación de la naciente “Los Herrera” y de la falta de potabilidad en el agua que consumen.
En consecuencia, estima esta Sala que el plazo que ha transcurrido para resolver la denuncia planteada por la parte tutelada y comunicarle lo respectivo por parte de las autoridades recurridas es desproporcionado, por cuanto, ha transcurrido un plazo de, más de diez años, desde la presentación de la primera denuncia por parte de los recurrentes, sin que a la fecha esta haya sido resuelta, con el agravante que la presunta afectación denunciada continúa vigente. Bajo esta inteligencia, considera esta Sala que el recurso debe ser declarado con lugar, con las consideraciones que se dirán en la parte dispositiva de esta sentencia.
En asuntos ambientales, es criterio del suscrito, que, si ya ha habido intervención de la Administración Pública, su conocimiento y resolución corresponde a la jurisdicción contenciosa administrativa. No obstante, sí entro a conocer el fondo del asunto cuando están de por medio otros derechos de las personas afectadas por el foco de contaminación, entre ellos, la salud, la calidad de vida y el derecho a gozar de un ambiente sano y libre de contaminación (artículo 50, de la Constitución Política), tal y como sucede en este caso, en el que los recurrentes denuncian la presunta contaminación, del agua potable, de las nacientes y tomas de agua proveniente de la naciente conocida como “Los Herrera”, ubicada en el distrito de La Garita. Aducen que desde el año 2012, han planteado denuncias ante la Municipalidad de Alajuela, sin obtener una solución efectiva.
La situación descrita constituye una excepción a mi posición general en esta materia, por lo que estimo necesario que este Tribunal Constitucional analizara por el fondo el asunto, con el fin de verificar o descartar los alegatos de la parte recurrente.
VI.Documentación aportada al expediente. Se previene a la parte que, de haber aportado algún documento en papel, así como objetos o pruebas contenidas en algún dispositivo adicional de carácter electrónico, informático, magnético, óptico, telemático o producido por nuevas tecnologías, éstos deberán ser retirados del despacho en un plazo máximo de 30 días hábiles contados a partir de la notificación de esta sentencia. De lo contrario, será destruido todo aquel material que no sea retirado dentro de este plazo, según lo dispuesto en el “Reglamento sobre Expediente Electrónico ante el Poder Judicial”, aprobado por la Corte Plena en sesión No. 27-11 de 22 de agosto de 2011, artículo XXVI y publicado en el Boletín Judicial número 19 de 26 de enero de 2012, así como en el acuerdo aprobado por el Consejo Superior del Poder Judicial, en la sesión No. 43-12 celebrada el 3 de mayo de 2012, artículo LXXXI.
Por tanto:
Se declara con lugar el recurso. Se ordena a Roberto Hernán Thompson Chacón y Roy Delgado Alpízar, por su orden Alcalde y Director de Planeamiento y Construcción de Infraestructura Municipal, ambos de la Municipalidad de Alajuela, o a quienes ocupen el cargo, que realicen las actuaciones que estén dentro del ámbito de sus competencias y establezcan las acciones y coordinaciones necesarias, para que en el plazo máximo de seis meses contados a partir de la notificación de esta sentencia, se ejecuten las contrataciones y obras que se estime necesarias y se adopten las medidas y resoluciones administrativas pertinentes, para atender la denuncia planteada por los recurrentes y se les comunique lo que corresponda. Se les advierte a los recurridos que, de no acatar la orden dicha, incurrirán en el delito de desobediencia y, que de conformidad con el artículo 71 de la Ley de esta jurisdicción, se le impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo y no la cumpliere o no la hiciere cumplir, siempre que el delito no esté más gravemente penado.
Se condena a la Municipalidad de Alajuela al pago de las costas, daños y perjuicios causados con los hechos que sirven de base a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso administrativo. El Magistrado Salazar Alvarado consigna nota. Notifíquese.- Fernando Cruz C.
Presidente a.i Luis Fdo. Salazar A.
Jorge Araya G.
Ingrid Hess H.
Ronald Salazar Murillo Ileana Sánchez N.
Jose Roberto Garita N.
Clasificación elaborada por SALA CONSTITUCIONALdel Poder Judicial. Prohibida su reproducción y/o distribución en forma onerosa.
Document not found. Documento no encontrado.