Res. 16068-2025 Sala Constitucional · Sala Constitucional · 30/05/2025
OutcomeResultado
The non-compliance claim against CONAVI is upheld for partial failure to construct and enable wildlife crossings on National Route 32; the order is reiterated with warnings of administrative and criminal sanctions.Se acoge la gestión de desobediencia contra CONAVI por incumplimiento parcial de la orden de construir y habilitar pasos de fauna en la Ruta Nacional 32, reiterando la orden bajo apercibimiento de medidas administrativas y penales.
SummaryResumen
The Constitutional Chamber addresses a non-compliance claim against the National Road Council (CONAVI) for failing to fully execute Judgment 2021001189, which mandated the construction and activation of wildlife crossings on National Route 32. Despite reported progress —29 underpasses built but lacking functional adaptations, and only 2 of 20 overpasses— the Chamber finds partial and insufficient compliance. It denies a further time extension as disproportionate, noting a prior three-year extension had already been granted. The non-compliance claim is upheld, and the order is reiterated, with warnings of administrative and criminal liability under Articles 53 and 71 of the Constitutional Jurisdiction Law.La Sala Constitucional resuelve una gestión de desobediencia contra el Consejo Nacional de Vialidad (CONAVI) por el incumplimiento de la sentencia 2021001189, que ordenaba la construcción y habilitación de pasos de fauna en la Ruta Nacional N.º 32. A pesar de los avances reportados —29 pasos inferiores construidos pero sin adaptaciones funcionales, y solo 2 de 20 pasos aéreos—, la Sala determina que persiste un cumplimiento parcial e insuficiente. Rechaza una nueva solicitud de ampliación de plazo por considerarla desproporcionada, dado que ya se había concedido una prórroga de tres años. Acoge la gestión de desobediencia y reitera la orden, bajo apercibimiento de responsabilidad administrativa y penal conforme a los artículos 53 y 71 de la Ley de la Jurisdicción Constitucional.
Key excerptExtracto clave
Thus, this Tribunal determines that despite the respondent authorities having undertaken efforts to comply, the provisions of Judgment 2021001189 have not yet been fully executed. Accordingly, the non-compliance claim is upheld, and the respondent authorities are ordered to comply with what was decided by this Chamber in Judgment 2021001189 at 9:15 a.m. on January 22, 2021. Therefore: The non-compliance claim is upheld. Efraím Zeledón Leiva, in his capacity as Executive Director of the National Road Council, or whoever holds that position, is ordered to proceed to comply with the provisions of this Chamber in Judgment 2021001189 at 9:15 a.m. on January 22, 2021, meaning that the wildlife crossings in the sections of National Route 32 that were already intervened in the rehabilitation and expansion project must be built and enabled. Likewise, they shall arrange for the design and planning, within the same term, of the remaining wildlife crossings in the sections of the same route to be intervened shortly, as foreseen by SETENA, and, in due course, their proper construction shall be carried out. The foregoing under warning that, if non-compliance is proven, administrative proceedings may be initiated against the official who fails to comply with this Chamber's ruling, and, additionally, certified copies may be sent to the Public Prosecutor's Office for the possible crime of disobedience (Articles 53 and 71 of the Constitutional Jurisdiction Law).Así las cosas, este Tribunal determina que a pesar de que las autoridades recurridas han realizado gestiones con el fin de cumplir con lo ordenado aún no ha sido cumplido de forma integra lo dispuesto en la sentencia No. 2021001189. En consecuencia, se acoge la gestión de desobediencia y se procede a ordenarles a las autoridades recurridas dar cumplimiento de lo ordenado por esta Sala en la sentencia No. 2021001189 de las 9:15 horas del 22 de enero de 2021. Por tanto: Se acoge la gestión de desobediencia. Se reitera a Efraím Zeledón Leiva, en su condición de Director Ejecutivo del Consejo Nacional de Vialidad, o a quien en su lugar ocupe el cargo, que proceda a dar cumplimiento de lo dispuesto por esta Sala en la sentencia No. 2021001189 de las 9:15 horas del 22 de enero de 2021, en el sentido de que se construyan y habiliten los pasos de fauna en los tramos de la Ruta Nacional No. 32 que ya fueron intervenidos en el proyecto de rehabilitación y ampliación de esa vía. Asimismo, que disponga lo correspondiente para que, en el mismo plazo, se diseñe y planifique la construcción de los demás pasos de fauna en los tramos de la misma ruta que serán intervenidos próximamente, de la forma en que lo ha previsto SETENA, y, en su momento, se ejecute su debida construcción. Lo anterior, bajo la advertencia que, de acreditarse la desobediencia, se podrá ordenar la apertura de un procedimiento administrativo contra el funcionario remiso a cumplir con lo resuelto por esta Sala y, además, ordenar testimoniar piezas ante el Ministerio Público por la eventual comisión del delito de desobediencia (artículos 53 y 71 de la ley de la jurisdicción constitucional).
Pull quotesCitas destacadas
"En aplicación del principio precautorio, resulta prudente acoger la recomendación de la responsabilidad ambiental en relación al estudio de la propuesta de modificación de los pasos de fauna aéreos."
"In application of the precautionary principle, it is prudent to accept the recommendation of environmental responsibility regarding the study of the proposed modification of the aerial wildlife crossings."
Escrito del recurrente del 2 de mayo de 2025
"En aplicación del principio precautorio, resulta prudente acoger la recomendación de la responsabilidad ambiental en relación al estudio de la propuesta de modificación de los pasos de fauna aéreos."
Escrito del recurrente del 2 de mayo de 2025
"La vida animal tiene un valor intrínseco, y los atropellos por la ausencia de pasos de fauna efectivos no solo representan un sufrimiento físico innecesario para los animales, sino que suponen un riesgo por los accidentes de tránsito."
"Animal life has intrinsic value, and roadkill due to the absence of effective wildlife crossings not only represents unnecessary physical suffering for animals but also poses a risk of traffic accidents."
Escrito del recurrente del 2 de mayo de 2025
"La vida animal tiene un valor intrínseco, y los atropellos por la ausencia de pasos de fauna efectivos no solo representan un sufrimiento físico innecesario para los animales, sino que suponen un riesgo por los accidentes de tránsito."
Escrito del recurrente del 2 de mayo de 2025
"Se acoge la gestión de desobediencia. Se reitera a Efraím Zeledón Leiva... que proceda a dar cumplimiento de lo dispuesto por esta Sala en la sentencia No. 2021001189."
"The non-compliance claim is upheld. Efraím Zeledón Leiva... is ordered to proceed to comply with the provisions of this Chamber in Judgment 2021001189."
Por tanto
"Se acoge la gestión de desobediencia. Se reitera a Efraím Zeledón Leiva... que proceda a dar cumplimiento de lo dispuesto por esta Sala en la sentencia No. 2021001189."
Por tanto
Full documentDocumento completo
Constitutional Chamber Case File: 20-020651-0007-CO Type of matter: Amparo petition CONSTITUTIONAL CHAMBER OF THE SUPREME COURT OF JUSTICE. San José, at nine hours twenty minutes on the thirtieth of May of two thousand twenty-five.
Petition for non-compliance filed by Nombre01, identity card No. CED01, against the NATIONAL ROAD COUNCIL (CONAVI).
Whereas:
Drafted by Magistrate Araya García; and,
Considering:
I.Regarding what was ordered by this Chamber. Through judgment No. 2021001189 of 9:15 hours on January 22, 2021, this Court ordered the following:
"Therefore:
The petition is partially granted, solely against CONAVI. Mario Rodríguez Vargas, in his capacity as Executive Director of the National Road Council (CONAVI), or whoever holds that position, is ordered to take the corresponding measures so that within the period of THREE MONTHS, counted from the notification of this judgment, the wildlife crossings (pasos de fauna) be built and enabled on the sections of National Route No. 32 that have already been intervened in the rehabilitation and expansion project of that road. Likewise, that he make the corresponding provisions so that, within the same period, the construction of the other wildlife crossings on the sections of the same route that will be intervened shortly be designed and planned, in the manner that SETENA has foreseen, and, in due course, their proper construction be executed. The foregoing under the warning that, in accordance with the provisions of Article 71 of the Law on Constitutional Jurisdiction (Ley de la Jurisdicción Constitucional), imprisonment of three months to two years, or a fine of twenty to sixty days, will be imposed on anyone who receives an order that must be complied with or enforced, issued in an amparo petition, and does not comply with it or have it complied with, provided that the crime is not more severely punished.
CONAVI is ordered to pay the costs, damages, and losses caused by the facts that serve as the basis for this declaration, which will be liquidated in the execution of judgment of the contentious-administrative proceedings. In all other respects, the petition is denied. Magistrate Hernández López issues a dissenting vote and denies the petition in all its aspects. Magistrate Salazar Alvarado issues a dissenting vote and denies the petition in all its aspects. Notify." The above judgment was notified to the respondent authorities on January 25, 2021.
Through interlocutory resolution No. 2021012521 of 9:45 hours on June 1, 2021, this Chamber considered a request for an extension of the deadline to comply with what was ordered in judgment No. 2021001189, thus ordering the following:
"II.- Regarding the request for an extension of the deadline. In the present case, the Chamber observes that the authorities of the National Road Council request an extension of the three-month period granted in judgment No. 2021-001189 of 09:15 hours on January 22, 2021, for budgetary reasons, since the resources to finance the construction of the wildlife crossings must be managed, in addition, the contracting process for the company that will build said works must be carried out and, subsequently, the stage of execution or construction of these must take place.
First, it is important to denote that judgment No. 2021-001189 of 09:15 hours on January 22, 2021 was notified to the respondent authority on January 25, 2021, in which a period of three months was granted for its compliance, which expired on April 25, 2021.
On this matter, it should be noted that, from the evidence provided in the case file, and the report rendered under oath, it is verified that the authority involved has carried out various actions, in order to comply with what was ordered by this Chamber. In this sense, it is recorded that the following actions have been carried out: a) the pertinent studies were carried out that generated the location, number, and characteristics of the wildlife crossing points; b) the search for updated scientific information support to locate or relocate the wildlife points was carried out; c) the formation of the Technical Committee for the study of wildlife points was materialized and formalized, which, based on the study "Verification of Environmental Measures to reduce the presence of wildlife on the expansion of the National Road Ruta 32 Limón, Costa Rica. 2016.", identified nine points for the possible location of wildlife crossings; d) in March 2021, one of its study products was implemented with the implementation of a mitigation measure, while the wildlife crossings are built; e) warning signs of the presence of wildlife were placed along the road, at distances of 200 to 300 meters from historical roadkill zones, a total of 38 signs.
In spite of the foregoing, and although it is accredited that the respondent authority has carried out actions in order to comply with what was ordered, the fact is that the works executed, to date, have not been sufficient to give full compliance with what was ordered by this Chamber in the aforementioned judgment; however, this Court understands the environment that the development and construction of the works in question entails, so it is considered that the justifications regarding the delay incurred by CONAVI in complying with what was ordered are admissible by this Chamber.
It should be clarified that, in this particular case, based on the technical report provided by the respondent authority, where a period of thirty-nine months is requested, this Court considers it appropriate to extend the granted period by a maximum period of thirty-six months, and during said period they must inform this Chamber, on a semi-annual basis, of the actions they carry out during that period in order to accredit full compliance with what was ordered.
By virtue of the foregoing, it is appropriate to extend the period, for the fulfillment of what was ordered in judgment No. 2021-001189 of 09:15 hours on January 22, 2021. (…)
Therefore:
Mario Rodríguez Vargas, in his capacity as Executive Director of the National Road Council, or whoever occupies that position in his place, is granted a non-extendable period of THIRTY-SIX MONTHS, counted from the notification of this resolution, to faithfully comply with the provisions of judgment No. 2021-001189 of 09:15 hours on January 22, 2021, under the warning that they must submit semi-annual compliance reports to this Court, in which the actions crediting full compliance with what was ordered by this Chamber in the aforementioned judgment are recorded. Furthermore, what was indicated in the cited judgment regarding Article 71 of the Law on Constitutional Jurisdiction is reiterated. Notify." The above resolution was notified to the respondent authorities on June 2, 2021.
Through interlocutory resolution No. 2024028850 of 9:20 hours on October 4, 2024, this Court considered a second request for an extension of the deadline to comply with what was ordered in judgment No. 2021001189, thus ordering the following:
"II.- Regarding the petition filed. In the present matter, the Executive Director of the National Road Council requests for the second time an extension of the deadline of at least one year to complete the construction of the remaining works related to the wildlife crossings.
That being said, it is proven in the case file that judgment No. 2021-001189 of 9:15 hours on January 22, 2021, was notified to the respondent authority on January 20, 2021, therefore, as of that date, the respondent had a term of three months to build and enable the wildlife crossings on the sections of National Route No. 32 that had already been intervened in the rehabilitation and expansion project of that road. Likewise, to make the corresponding provisions so that, within the same period, the construction of the other wildlife crossings on the sections of the same route that will be intervened shortly be designed and planned, in the manner that SETENA has foreseen, and, in due course, their proper construction be executed.
Subsequently, through interlocutory resolution No. 2021-012521 of 9:45 hours on June 1, 2021, this Chamber considered a request for an extension of the period to comply with the order issued in the aforementioned judgment No. 2021-001189, and upon determining that a series of actions aimed at complying with what was ordered had been carried out and the efforts made had been understood, as well as the difficulties that had arisen in completing the tasks necessary to resolve the situation alleged by the petitioner, the period was extended by an additional thirty-six months, to fully comply with what was ordered, which began to run from the notification of said resolution, namely June 2, 2021.
By virtue of the foregoing, this Chamber verifies that as of the date this petition was filed–namely April 10, 2024–the granted period had not yet elapsed. This Chamber does not observe that, in this case, there are reasons of relevance to grant the National Road Council what was requested. Thus, it is not considered appropriate to extend the granted period.
Given that the respondent authority has not fully complied with what was ordered in the judgment, it is reiterated that they must comply with what was ordered by this Chamber in judgment No. 2021-001189 of 9:15 hours on January 22, 2021. (…)
Therefore:
Efraím Zeledón Leiva, in his capacity as Executive Director of the National Road Council, or whoever holds the position, is reiterated the compliance with the provisions of this Chamber in judgment No. 2021-001189 of 9:15 hours on January 22, 2021, in the sense that the wildlife crossings (pasos de fauna) be built and enabled on the sections of National Route No. 32 that have already been intervened in the rehabilitation and expansion project of that road. Likewise, that he make the corresponding provisions so that, within the same period, the construction of the other wildlife crossings on the sections of the same route that will be intervened shortly be designed and planned, in the manner that SETENA has foreseen, and, in due course, their proper construction be executed. In all other respects, the petition filed is declared without merit. The foregoing, under the warning of ordering, as appropriate, the opening of a disciplinary administrative procedure, based on the provisions of Article 53 of the Law on Constitutional Jurisdiction, in case of non-compliance, and, in addition, to certify copies of proceedings to the Public Prosecutor's Office in accordance with the provisions of Article 71 of the Law on Constitutional Jurisdiction. Notify.- The above resolution was notified to the respondent authorities on October 9, 2024.
II.Regarding the non-execution petition. In the present matter, the petitioner alleges non-compliance with what was ordered by this Chamber in judgment No. 2021001189 of 9:15 hours on January 22, 2021. She points out that as of today, of the 21 wildlife crossings, only 2 have been built. She points out that the respondent authority did not agree to build them with the design donated by the School of Construction Engineering of the ITCR and the Commission for Roads and Wildlife.
In this regard, this Chamber ordered the following in judgment No. 2021001189: "(…) take the corresponding measures so that within the period of THREE MONTHS, counted from the notification of this judgment, the wildlife crossings be built and enabled on the sections of National Route No. 32 that have already been intervened in the rehabilitation and expansion project of that road. Likewise, that he make the corresponding provisions so that, within the same period, the construction of the other wildlife crossings on the sections of the same route that will be intervened shortly be designed and planned, in the manner that SETENA has foreseen, and, in due course, their proper construction be executed" (the highlighting does not correspond to the original).
Through interlocutory resolution No. 2021012521, this Chamber considered a request for an extension of the period to comply with the order issued in the aforementioned judgment No. 2021001189, and upon determining that a series of actions aimed at complying with what was ordered had been carried out and the efforts made had been understood, as well as the difficulties that had arisen in completing the tasks necessary to resolve the situation alleged by the petitioner, the period was extended by an additional thirty-six months, to fully comply with what was ordered, which began to run from the notification of said resolution, namely June 2, 2021.
Additionally, through interlocutory resolution No. 2024028850, this Court considered a second request for an extension of the deadline to comply with what was ordered in judgment No. 2021001189; however, upon determining that as of the date said petition was filed–namely April 10, 2024–the granted period had not yet elapsed; therefore, no reasons of relevance existed to grant the National Road Council what was requested.
That being said, the Executive Director of the National Road Council reported the following to this Chamber:
"In May 2022, out of the 20 lower wildlife crossings on the definitive list, a total of 16 completed structures were recorded (including the case of the crossing near the Earth University at km 81+767, which is known as the jaguar crossing). Likewise, the completion of construction of one of the sections of the bridges at Río Hondo (km107+800) and Río Blanco (km 145+200) is also reported, in which the dry berm on the riprap will be used as a wildlife crossing.
Other advances are related to:
• Technical studies necessary for defining the location of structures and procedures before SETENA. For example, SETENA resolved through Resolution No. 1044- 2023 of July 12, 2023, '…Update the location of the established lower and upper wildlife crossings... in accordance with the proposal provided by CONAVI as the project developer and under the professional responsibility of the consultant Adolfo Artavia Rodríguez.' • Installation of new definitive vertical signage to warn about the presence of wildlife crossings in the sectors already delivered to the Administration.
In accordance with the foregoing, significant and firm progress is observed in the fulfillment of what was ordered by the Constitutional Chamber by the Executing Unit for National Route Number 32.
However, difficulties have arisen in securing the budgetary resources to complete all of these additional wildlife crossing works. Current efforts are aimed at finalizing an addendum to the contract, in order to allocate project funds for the construction of the lower crossings, as a result of the financial differential that may arise from the construction of roundabouts. The addendum is in the negotiation process and is estimated to take around 4 months for its formalization. Likewise, "...in parallel, work is being carried out in coordination with civil society actors who have an interest and proposals for the protection of wildlife, who have voluntarily approached the Ruta 32 project to collaborate with the optimization of wildlife crossings in consensus with CONAVI and wish to issue their recommendations mainly on the subject of aerial crossings that are pending execution..." (…)
For the reasons stated, we request that CONAVI and its Executing Unit for National Route Number 32 be granted an extension of the deadline of at least one year to complete the construction of the remaining works related to the wildlife crossings" (the highlighting does not correspond to the original).
For the reasons stated above, this Chamber considers it proven that the respondent authorities have indeed carried out a series of actions aimed at complying with what was ordered in judgment No. 2021001189.
In that regard, this constitutional body understands the efforts undertaken, as well as the difficulties that have arisen, but the request made to extend the deadline for an additional year is clearly disproportionate, since the deadline had already been extended for an additional thirty-six months (3 years) by interlocutory resolution No. 2021012521. In light of the foregoing, it is not deemed appropriate to extend the granted deadline.
Thus, this Court determines that, despite the fact that the respondent authorities have taken steps to comply with what was ordered, the provisions of judgment No. 2021001189 have not yet been fully complied with. Consequently, the petition of disobedience is granted, and the respondent authorities are hereby ordered to comply with what was ordered by this Chamber in judgment No. 2021001189 of 9:15 a.m. on January 22, 2021.
III- Documentation provided to the case file (expediente). The parties are warned that if any paper documents have been provided, as well as objects or evidence contained in any additional electronic, computer, magnetic, optical, telematic device or one produced by new technologies, these must be withdrawn from the office within a maximum period of 30 business days counted from the notification of this judgment. Otherwise, all material not withdrawn within this period will be destroyed, pursuant to the provisions of the “Reglamento sobre Expediente Electrónico ante el Poder Judicial”, approved by the Corte Plena in session No. 27-11 of August 22, 2011, article XXVI and published in Boletín Judicial number 19 of January 26, 2012, as well as the agreement approved by the Consejo Superior del Poder Judicial, in session No. 43-12 held on May 3, 2012, article LXXXI.
Por tanto:
The petition of disobedience is granted. Efraím Zeledón Leiva, in his capacity as Director Ejecutivo of the Consejo Nacional de Vialidad, or whoever holds the position in his stead, is reiterated to proceed to comply with what was ordered by this Chamber in judgment No. 2021001189 of 9:15 a.m. on January 22, 2021, in the sense that wildlife crossings (pasos de fauna) must be built and enabled on the sections of Ruta Nacional No. 32 that have already been intervened in the rehabilitation and expansion project of that road. Likewise, he must order what is necessary so that, within the same period, the construction of the other wildlife crossings on the sections of the same route that will be intervened soon is designed and planned, in the manner provided by SETENA, and, in due course, their proper construction is executed. The foregoing, under the warning that, if disobedience is proven, the opening of an administrative procedure may be ordered against the official who is reluctant to comply with what was decided by this Chamber and, additionally, certification of documents (testimoniar piezas) to the Ministerio Público may be ordered for the potential commission of the crime of disobedience (articles 53 and 71 of the Ley de la Jurisdicción Constitucional). Notifíquese.- Fernando Castillo V.
Fernando Cruz C.
Luis Fdo. Salazar A.
Jorge Araya G.
Ingrid Hess H.
Ronald Salazar Murillo Jose Roberto Garita N.
SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas veinte minutos del treinta de mayo de dos mil veinticinco .
Gestión de desobediencia presentada por Nombre01, cédula de identidad No. CED01, contra el CONSEJO NACIONAL DE VIALIDAD (CONAVI).
Resultando:
Redacta el Magistrado Araya García; y,
Considerando:
I.Sobre lo dispuesto por esta Sala. Mediante la sentencia No. 2021001189 de las 9:15 horas del 22 de enero de 2021, este Tribunal dispuso los siguiente:
“Por tanto:
Se declara parcialmente con lugar el recurso, únicamente contra el CONAVI. Se ordena a Mario Rodríguez Vargas, en condición de Director Ejecutivo del Consejo Nacional de Vialidad (CONAVI), o a quien ejerza tal cargo, tomar las medidas correspondientes para que en el plazo de TRES MESES, contado a partir de la notificación de esta sentencia, se construyan y habiliten los pasos de fauna en los tramos de la Ruta Nacional No. 32 que ya fueron intervenidos en el proyecto de rehabilitación y ampliación de esa vía. Asimismo, que disponga lo correspondiente para que, en el mismo plazo, se diseñe y planifique la construcción de los demás pasos de fauna en los tramos de la misma ruta que serán intervenidos próximamente, de la forma en que lo ha previsto SETENA, y, en su momento, se ejecute su debida construcción. Lo anterior bajo la advertencia que, de conformidad con lo establecido en el artículo 71 de la Ley de la Jurisdicción Constitucional, se impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo, y no la cumpliere o hiciere cumplir, siempre que el delito no esté más gravemente penado.
Se condena al CONAVI al pago de las costas, daños y perjuicios causados con los hechos que sirven de base a la presente declaratoria, los cuales se liquidarán en ejecución de sentencia de lo contencioso administrativo. En lo demás se declara sin lugar el recurso. La Magistrada Hernández López salva el voto y declara sin lugar el recurso en todos los extremos. El Magistrado Salazar Alvarado salva el voto y declara sin lugar el recurso en todos sus extremos. Notifíquese”.
La anterior sentencia le fue notificada a las autoridades recurridas el 25 de enero de 2021.
Mediante la resolución interlocutoria No. 2021012521 de las 9:45 horas del 1º de junio de 2021, esta Sala entró a conocer una solicitud de ampliación del plazo para cumplir con lo ordenado en la sentencia No. 2021001189, por lo que se dispuso los siguiente:
“II.-Sobre la solicitud de ampliación del plazo. En la especie, la Sala observa que las autoridades del Consejo Nacional de Vialidad solicitan una ampliación del plazo de tres meses concedido en la sentencia No. 2021-001189 de las 09:15 horas del 22 de enero de 2021, ello por motivos de presupuesto, ya que deben gestionarse los recursos para financiar la construcción de los pasos de fauna, además, debe realizarse el proceso de contratación de la empresa que construya dichas obras y, posteriormente, debe llevarse a cabo la etapa de ejecución o construcción de estas.
En primer lugar, es importante denotar que la sentencia No. 2021-001189 de las 09:15 horas del 22 de enero de 2021 fue notificada a la autoridad recurrida el 25 de enero de 2021, en la cual se concedió un plazo de tres meses para el cumplimiento de esta, el cual venció el 25 de abril de 2021.
Sobre el particular, cabe resaltar que, de las pruebas aportadas en autos, y el informe rendido bajo juramento, se constata que la autoridad involucrada ha llevado a cabo diversas actuaciones, en aras de acatar lo ordenado por esta Sala. En ese sentido consta que se han llevado a cabo las siguientes acciones: a) se realizaron los estudios pertinentes que generaron la ubicación, el número y las características de los puntos de pasos de fauna; b) se efectuó la búsqueda del apoyo de información científica actualizada para ubicar o reubicar los puntos de fauna; c) se concretó y formalizó la conformación del Comité Técnico para el estudio de los puntos de fauna, la cual, con base en el estudio “Verificación de Medidas Ambientales para disminuir la presencia de fauna silvestre en la ampliación de la Carretera Nacional Ruta 32 Limón, Costa Rica. 2016.”, se ubicaron nueve puntos para la posible ubicación de pasos de fauna; d) en marzo de 2021, se ejecutó uno de sus productos del estudio con la implementación de una medida de mitigación, en el tanto se construyen los pasos de fauna; e) se colocaron de rótulos de advertencia de la presencia de fauna a lo largo de la carretera, a distancias de 200 a 300 metros de las zonas de atropellos históricos un total de 38 señales.
A pesar de lo anterior, y si bien se tiene por acreditado que la autoridad recurrida ha llevado a cabo acciones en aras de dar cumplimiento a lo ordenado, lo cierto es que las obras ejecutadas, a la fecha, no han sido suficientes para dar cabal cumplimiento con lo ordenado por esta Sala en la sentencia supra indicada; no obstante, este Tribunal entiende el entorno que conlleva el desarrollo y construcción de las obras en cuestión, por lo que se estima que las justificaciones respecto de la demora en la que ha incurrido el CONAVI para cumplir lo ordenado son de recibo por esta Sala.
Cabe aclarar que, en el caso particular, con base en el informe técnico aportado por la autoridad recurrida, donde se solicita una plazo de treinta y nueve meses, este Tribunal estima que lo procedente es ampliar el plazo otorgado por un plazo máximo de treinta y seis meses, siendo que durante dicho plazo deberán informar, de manera semestral, a esta Sala las acciones que vayan realizando durante dicho periodo a efectos de acreditar el pleno cumplimiento a lo ordenado.
En virtud de lo anterior, lo procedente es ampliar el plazo, para el cumplimiento de lo ordenado en la sentencia No. 2021-001189 de las 09:15 horas del 22 de enero de 2021. (…)
Por tanto:
Se le confiere a Mario Rodríguez Vargas, en su condición de director ejecutivo del Consejo Nacional de Vialidad, o a quien en su lugar ocupe dicho cargo, un plazo improrrogable de TREINTA Y SEIS MESES, contado a partir de la notificación de la presente resolución, para dar fiel cumplimiento a lo dispuesto en la sentencia No. 2021-001189 de las 09:15 horas del 22 de enero de 2021, bajo el apercibimiento de que deberán remitir informes semestrales de cumplimiento a este Tribunal, en los que consten las acciones que acrediten el pleno cumplimiento a lo ordenado por esta Sala en la sentencia supra indicada. Se reitera, además, lo señalado en la sentencia de cita respecto del artículo 71 de la Ley de la Jurisdicción Constitucional. Notifíquese”.
La anterior resolución le fue notificada a las autoridades recurridas el 2 de junio de 2021.
Mediante la resolución interlocutoria No. 2024028850 de las 9:20 horas del 4 de octubre de 2024, este Tribunal entró a conocer una segunda solicitud de ampliación del plazo para cumplir con lo ordenado en la sentencia No. 2021001189, por lo que se dispuso los siguiente:
“II.- Sobre la gestión presentada. En el presente asunto, el Director Ejecutivo del Consejo Nacional de Vialidad, solicita por segunda vez una extensión del plazo de al menos un año para cumplir con la construcción de las obras restantes relativas a los pasos de fauna.
Ahora bien, de los autos se tiene por demostrado que la sentencia No. 2021-001189 de las 9:15 horas del 22 de enero de 2021, le fue notificada a la autoridad recurrida el 20 de enero de 2021, por lo que a partir de esa fecha, la accionada contaba con el término de tres meses para construir y habilitar los pasos de fauna en los tramos de la Ruta Nacional No. 32 que ya fueron intervenidos en el proyecto de rehabilitación y ampliación de esa vía. Asimismo, que disponga lo correspondiente para que, en el mismo plazo, se diseñe y planifique la construcción de los demás pasos de fauna en los tramos de la misma ruta que serán intervenidos próximamente, de la forma en que lo ha previsto SETENA, y, en su momento, se ejecute su debida construcción.
Posteriormente, mediante resolución interlocutoria No. 2021-012521 de las 9:45 horas del 1º de junio de 2021, esta Sala entró a conocer una solicitud de ampliación del plazo para cumplir con la orden emitida en la supra citada sentencia No. 2021-001189, por lo que al determinarse que se habían realizado una serie de acciones tendentes a dar cumplimiento a lo ordenado y se había comprendido los esfuerzos realizados, así como las dificultades que se les habían presentado para concluir las labores necesarias para solventar la situación aducida por el recurrente, se procedió ampliar el plazo por treinta y seis meses adicionales, para cumplir a cabalidad lo dispuesto, el cual empezó a correr a partir de la notificación de dicha resolución, sea el 2 de junio de 2021.
En virtud de lo anterior, esta Sala logra constatar que a la fecha de interpuesta la presente gestión –sea el 10 de abril de 2024, aún no ha transcurrido el plazo otorgado. No observa esta Sala que, en la especie, medien motivos de relevancia para conceder al Consejo Nacional de Vialidad lo peticionado. Así las cosas, no se estima procedente ampliar el plazo otorgado.
Dado que la autoridad recurrida no ha cumplido íntegramente con lo ordenado en la sentencia, se le reitera dar cumplimiento de lo ordenado por esta Sala en la sentencia No. 2021-001189 de las 9:15 horas del 22 de enero de 2021. (…)
Por tanto:
Se le reitera a Efraím Zeledón Leiva, en su condición de Director Ejecutivo del Consejo Nacional de Vialidad, o a quien ocupe el cargo, el cumplimiento de lo dispuesto por esta Sala en la sentencia No. 2021-001189 de las 9:15 horas del 22 de enero de 2021, en el sentido de que se construyan y habiliten los pasos de fauna en los tramos de la Ruta Nacional No. 32 que ya fueron intervenidos en el proyecto de rehabilitación y ampliación de esa vía. Asimismo, que disponga lo correspondiente para que, en el mismo plazo, se diseñe y planifique la construcción de los demás pasos de fauna en los tramos de la misma ruta que serán intervenidos próximamente, de la forma en que lo ha previsto SETENA, y, en su momento, se ejecute su debida construcción. En lo demás, se declara no ha lugar a la gestión formulada. Lo anterior, bajo la advertencia de ordenar, según corresponda, la apertura de un procedimiento administrativo disciplinario, con base en lo dispuesto el artículo 53 de la Ley de la Jurisdicción Constitucional, en caso de no hacerlo y, además, testimoniar piezas al Ministerio Público conforme lo dispuesto en el artículo 71 de la Ley de la Jurisdicción Constitucional. Notifíquese.- La anterior resolución le fue notificada a las autoridades recurridas el 9 de octubre de 2024.
II.Sobre la gestión de inejecución. En el presente asunto, la gestionante acusa la desobediencia a lo ordenado por esta Sala en la sentencia No. 2021001189 de las 9:15 horas del 22 de enero de 2021. Señala que a la fecha de los 21 pasos de fauna, solamente han construido 2. Señala que la autoridad recurrida no aceptó construirlos con el diseño que la Escuela de Ingeniería de la Construcción del ITCR y la Comisión de Vías y Vida Silvestre, donó.
Al respecto, esta Sala en la sentencia No. 2021001189 dispuso lo siguiente: “(…) tomar las medidas correspondientes para que en el plazo de TRES MESES, contado a partir de la notificación de esta sentencia, se construyan y habiliten los pasos de fauna en los tramos de la Ruta Nacional No. 32 que ya fueron intervenidos en el proyecto de rehabilitación y ampliación de esa vía. Asimismo, que disponga lo correspondiente para que, en el mismo plazo, se diseñe y planifique la construcción de los demás pasos de fauna en los tramos de la misma ruta que serán intervenidos próximamente, de la forma en que lo ha previsto SETENA, y, en su momento, se ejecute su debida construcción” (el resaltado no corresponde al original).
Mediante la resolución interlocutoria No. 2021012521, esta Sala entró a conocer una solicitud de ampliación del plazo para cumplir con la orden emitida en la supra citada sentencia No. 2021001189, por lo que al determinarse que se habían realizado una serie de acciones tendentes a dar cumplimiento a lo ordenado y se había comprendido los esfuerzos realizados, así como las dificultades que se les habían presentado para concluir las labores necesarias para solventar la situación aducida por el recurrente, se procedió ampliar el plazo por treinta y seis meses adicionales, para cumplir a cabalidad lo dispuesto, el cual empezó a correr a partir de la notificación de dicha resolución, sea el 2 de junio de 2021.
Adicionalmente, mediante la resolución interlocutoria No. 2024028850, este Tribunal entró a conocer una segunda solicitud de ampliación del plazo para cumplir con lo ordenado en la sentencia No. 2021001189; no obstante, al determinarse que a la fecha de interpuesta dicha gestión –sea el 10 de abril de 2024, aún no había transcurrido el plazo otorgado; por lo que no mediaron motivos de relevancia para conceder al Consejo Nacional de Vialidad lo peticionado.
Ahora bien, el Director Ejecutivo del Consejo Nacional de Vialidad i informó a esta Sala lo siguiente:
“En mayo de 2022, de los 20 pasos de fauna inferiores del listado definitivo, se tenían un total de 16 estructuras terminadas (incluido el caso del paso cercano a la Universidad Earth en el km 81+767, el cual se conoce como el paso del jaguar). Asimismo, se reporta también la finalización de la construcción de una de las secciones de los puentes en Río Hondo (km107+800) y Río Blanco (km 145+200), en los cuales se utilizará la berma seca sobre las escolleras como paso de fauna.
Otros avances están relacionados con:
• Estudios técnicos necesarios para la definición de ubicación de las estructuras y trámites ante SETENA. Por ejemplo, SETENA resolvió mediante resolución N°1044- 2023 del 12 de julio de 2023, “…Actualizar la ubicación de los pasos de fauna inferiores y superiores establecidos... de acuerdo con la propuesta aportada por el CONAVI como desarrollador del proyecto y bajo la responsabilidad profesional del consultor Adolfo Artavia Rodríguez.” • Colocación de nueva señalización vertical definitiva para advertir sobre la presencia de pasos de fauna en los sectores ya entregados a la Administración.
Conforme lo anterior, se observa un avance significativo y firme en el cumplimiento de lo ordenado por la Sala Constitucional por parte de la Unidad Ejecutora de Ruta Nacional Número 32.
No obstante, se han presentado dificultades para la consecución de los recursos presupuestarios para concluir la totalidad de estas obras adicionales de pasos de fauna. Los esfuerzos actuales están encaminados a concretar una adenda al contrato, a fin de destinar fondos del proyecto para la construcción de los pasos inferiores, como resultado del diferencial financiero que pueda surgir de la construcción de rotondas. La adenda está en proceso de negociación y se estimada alrededor de 4 meses para su formalización. Asimismo, “...en paralelo se está trabajando en coordinación con actores de la sociedad civil que tienen interés y propuestas para la protección de la fauna, quienes voluntariamente se han acercado al proyecto Ruta 32 para colaborar con la optimización de los pasos de fauna en consenso con el CONAVI y desean emitir sus recomendaciones principalmente en el tema de pasos aéreos que están pendientes de ejecutar...” (…)
En razón de lo señalado, se ruega otorgar al CONAVI y su Unidad Ejecutora de Ruta Nacional Número 32, una extensión del plazo de al menos un año para cumplir con la construcción de las obras restantes relativas a los pasos de fauna” (el resaltado no corresponde al original).
En razón de lo anterior, esta Sala tiene por demostrado que las autoridades recurridas ciertamente han realizado una serie de acciones tendentes a dar cumplimiento a lo ordenado en la sentencia No. 2021001189. En ese sentido, este órgano constitucional comprende los esfuerzos realizados, así como las dificultades que se les ha presentado, pero la solicitud planteada para que se amplíe el plazo por un año adicional, es a todas luces desproporcionada, ya que mediante la resolución interlocutoria No. 2021012521 ya se había ampliado el plazo por treinta y seis meses adicionales (3 años). En virtud de lo expuesto, no se estima procedente ampliar el plazo otorgado.
Así las cosas, este Tribunal determina que a pesar de que las autoridades recurridas han realizado gestiones con el fin de cumplir con lo ordenado aún no ha sido cumplido de forma integra lo dispuesto en la sentencia No. 2021001189. En consecuencia, se acoge la gestión de desobediencia y se procede a ordenarles a las autoridades recurridas dar cumplimiento de lo ordenado por esta Sala en la sentencia No. 2021001189 de las 9:15 horas del 22 de enero de 2021.
III- Documentación aportada al expediente. Se previene a las partes que de haber aportado algún documento en papel, así como objetos o pruebas contenidas en algún dispositivo adicional de carácter electrónico, informático, magnético, óptico, telemático o producido por nuevas tecnologías, estos deberán ser retirados del despacho en un plazo máximo de 30 días hábiles contados a partir de la notificación de esta sentencia. De lo contrario, será destruido todo aquel material que no sea retirado dentro de este plazo, según lo dispuesto en el “Reglamento sobre Expediente Electrónico ante el Poder Judicial”, aprobado por la Corte Plena en sesión No. 27-11 del 22 de agosto de 2011, artículo XXVI y publicado en el Boletín Judicial número 19 del 26 de enero de 2012, así como en el acuerdo aprobado por el Consejo Superior del Poder Judicial, en la sesión No. 43-12 celebrada el 3 de mayo de 2012, artículo LXXXI.
Por tanto:
Se acoge la gestión de desobediencia. Se reitera a Efraím Zeledón Leiva, en su condición de Director Ejecutivo del Consejo Nacional de Vialidad, o a quien en su lugar ocupe el cargo, que proceda a dar cumplimiento de lo dispuesto por esta Sala en la sentencia No. 2021001189 de las 9:15 horas del 22 de enero de 2021, en el sentido de que se construyan y habiliten los pasos de fauna en los tramos de la Ruta Nacional No. 32 que ya fueron intervenidos en el proyecto de rehabilitación y ampliación de esa vía. Asimismo, que disponga lo correspondiente para que, en el mismo plazo, se diseñe y planifique la construcción de los demás pasos de fauna en los tramos de la misma ruta que serán intervenidos próximamente, de la forma en que lo ha previsto SETENA, y, en su momento, se ejecute su debida construcción. Lo anterior, bajo la advertencia que, de acreditarse la desobediencia, se podrá ordenar la apertura de un procedimiento administrativo contra el funcionario remiso a cumplir con lo resuelto por esta Sala y, además, ordenar testimoniar piezas ante el Ministerio Público por la eventual comisión del delito de desobediencia (artículos 53 y 71 de la ley de la jurisdicción constitucional). Notifíquese.- Fernando Castillo V.
Fernando Cruz C.
Luis Fdo. Salazar A.
Jorge Araya G.
Ingrid Hess H.
Ronald Salazar Murillo Jose Roberto Garita N.