Res. 09450-2025 Sala Constitucional · Sala Constitucional · 28/03/2025
OutcomeResultado
MOPT ordered to formally respond to the August 2024 petition and to complete pending water‑related works in Area 1 by June 2025.Se ordena al MOPT dar respuesta formal a la gestión de agosto 2024 y finalizar obras hídricas pendientes en el Área 1 a más tardar en junio 2025.
SummaryResumen
The Constitutional Chamber reviewed an amparo filed by landowners in San Nicolás de Ochomogo, Cartago, whose properties border the ‘Taras-La Lima’ road project. They claimed that from the start of construction, poor stormwater management and lack of proper drainage caused recurrent flooding. They also complained about tree removal that eliminated a natural noise and dust barrier, dust and noise pollution, access difficulties, and loss of privacy. They further alleged that the Ministry of Public Works (MOPT) had not formally responded to their August 20, 2024 petition. The Chamber partially granted the amparo: it ordered MOPT to formally respond within five days and to complete pending works in ‘Area 1’ by June 2025 to definitively resolve the water problem. It denied the claims regarding noise, dust, access, and compensation, directing the latter to the administrative courts. CONAVI and the Municipality of Cartago were found not responsible.La Sala Constitucional conoció un amparo interpuesto por propietarios de fincas en San Nicolás de Ochomogo, Cartago, colindantes con el proyecto vial ‘Taras-La Lima’. Alegaron que desde el inicio de las obras, el mal manejo de aguas pluviales y la falta de alcantarillado adecuado provocaban inundaciones recurrentes en sus propiedades. También denunciaron la tala de árboles que servían de barrera natural, contaminación por polvo y ruido, dificultades de acceso y pérdida de privacidad. Además, señalaron que el MOPT no había dado respuesta formal a su gestión del 20 de agosto de 2024. La Sala estimó parcialmente el recurso: ordenó al MOPT responder formalmente en cinco días y finalizar las obras pendientes del ‘Área 1’ a más tardar en junio de 2025 para solucionar definitivamente el problema de aguas. Declaró sin lugar los reclamos sobre contaminación sónica, polvo, acceso y la pretensión indemnizatoria, remitiendo esta última a la vía contenciosa. Eximió de responsabilidad al CONAVI y a la Municipalidad de Cartago.
Key excerptExtracto clave
V. REGARDING THE WATER PROBLEM ON THE PROPERTIES OF THE PROTECTED PERSONS. … From the foregoing, this Chamber finds a violation of the fundamental rights of the amparo petitioners, since it has been demonstrated that since November 2024 they have requested the respondent ministry authorities to provide a solution to the problem afflicting them due to poor water management from the aforementioned construction, and as of the date they filed this amparo, the authorities had not provided a comprehensive and definitive solution. However, as noted, upon being notified of the commencement of these proceedings, the MOPT authorities took steps to address the reported problem, determining that the issue lies in two areas, with Area 2 already resolved and works pending in Area 1, which they report will be completed by June of this year. Accordingly, the amparo must be granted, with an order to respect the indicated date. VI. Furthermore, the evidence in the record shows that on August 20, 2024, the petitioners sent a communication by email … to the Advisory Unit and Administration and Supervision Committee PIT and PIV-APP of MOPT, raising questions and concerns about the problems caused by the works. However, although the respondent authorities informed the Chamber that they have maintained constant communication with the petitioners to keep them informed of the progress of the works, it is not established that the petitioners’ inquiry received a formal response as requested. Therefore, the amparo is granted on this point as well.V.- SOBRE EL PROBLEMA DE AGUAS EN LA PROPIEDAD DE LOS TUTELADOS. … De lo expuesto, esta Sala acredita la afectación de los derechos fundamentales de los amparados, esto por cuanto ha quedado demostrado que desde el mes de noviembre de 2024 han solicitado a las autoridades del ministerio accionado, se les dé una solución al problema que les aqueja, debido al mal manejo de aguas que provienen de la construcción señalada, y a la fecha en que acuden en amparo éstas no le habían dado una solución integral y definitiva al problema; sin embargo, como se indicó que con ocasión a la notificación que dio curso al proceso las autoridades accionadas del MOPT realizaron las acciones correspondientes, a fin de atender la problemática denunciada, siendo que al detectarse que el problema radica en dos puntos, y que la parte 2 ya fue resuelta, quedando pendiente la ejecución de las obras en lo que respecta en el área 1, y que se informa que ésta finalizará en el mes de junio del presente año, lo que procede es declarar con lugar el recurso, con la orden de que se respete la fecha que fue indicada. VI.- De otra parte, de la prueba aportada al expediente se desprende que el 20 de agosto de 2024 los accionantes enviaron una nota al correo electrónico … de la Unidad Asesora y Comité de Administración y Supervisión PIT y PIV-APP del MOPT, con consultas e inquietudes sobre la problemática que les aqueja, producto de las obras señaladas; sin embargo, si bien las autoridades recurridas informan a la Sala que se han mantenido en constante comunicación con los recurrentes, a fin de mantenerlos informados respecto al avance de las obras que se están realizando, lo cierto es que no se acredita que a la gestión planteada por los interesados se les haya dado una respuesta formal, tal como fue solicitada. Así, en cuanto a este extremo se declara con lugar el recurso.
Pull quotesCitas destacadas
"De lo expuesto, esta Sala acredita la afectación de los derechos fundamentales de los amparados, esto por cuanto ha quedado demostrado que desde el mes de noviembre de 2024 han solicitado a las autoridades del ministerio accionado, se les dé una solución al problema que les aqueja, debido al mal manejo de aguas que provienen de la construcción señalada, y a la fecha en que acuden en amparo éstas no le habían dado una solución integral y definitiva al problema."
"From the foregoing, this Chamber finds a violation of the fundamental rights of the amparo petitioners, since it has been demonstrated that since November 2024 they have requested the respondent ministry authorities to provide a solution to the problem afflicting them due to poor water management from the aforementioned construction, and as of the date they filed this amparo, the authorities had not provided a comprehensive and definitive solution."
Considerando V
"De lo expuesto, esta Sala acredita la afectación de los derechos fundamentales de los amparados, esto por cuanto ha quedado demostrado que desde el mes de noviembre de 2024 han solicitado a las autoridades del ministerio accionado, se les dé una solución al problema que les aqueja, debido al mal manejo de aguas que provienen de la construcción señalada, y a la fecha en que acuden en amparo éstas no le habían dado una solución integral y definitiva al problema."
Considerando V
"Se declara parcialmente con lugar el recurso, únicamente por la falta de respuesta a la gestión de fecha 20 de agosto de 2024 y a la falta de acción por la problemática de aguas en la propiedad de los tutelados."
"The amparo is partially granted, solely for the lack of response to the petition dated August 20, 2024, and for the failure to act on the water problem affecting the petitioners' property."
Por tanto
"Se declara parcialmente con lugar el recurso, únicamente por la falta de respuesta a la gestión de fecha 20 de agosto de 2024 y a la falta de acción por la problemática de aguas en la propiedad de los tutelados."
Por tanto
Full documentDocumento completo
File No. 24-031349-0007-CO CONSTITUTIONAL CHAMBER OF THE SUPREME COURT OF JUSTICE. San José, at nine fifteen o'clock on the twenty-eighth of March, two thousand twenty-five.
Amparo action processed under file number No. 24-031349-0007-CO, filed by Nombre105832, identity card CED59462, Nombre105833, identity card CED59463, Nombre105834, identity card CED59464, Nombre105833, identity card CED59465, Nombre105833, identity card CED59466, Nombre105835, identity card CED59467, and Nombre105836, identity card CED59468, against the MINISTERIO DE OBRAS PÚBLICAS Y TRANSPORTES and the MUNICIPALIDAD DE CARTAGO.
WHEREAS:
They request the intervention of the Chamber.
Drafted by Magistrate Hess Herrera; and,
WHEREAS:
Before analyzing the merits of the matter – due to the alleged violation of the right to a prompt and fulfilled procedure – it must be clarified that, based on ruling No. 2008-02545 at 8:55 a.m. on February 22, 2008, this Chamber has referred to the administrative contentious jurisdiction – with some exceptions – those matters in which it is disputed whether the public administration has complied or not with the deadlines set by the General Law of Public Administration (articles 261 and 325) or by the sectoral laws relating to special administrative procedures, both to resolve by final act an administrative procedure – initiated ex officio or at the request of a party – and to hear the appropriate administrative appeals. Precisely, in this case, an exception is raised, as it concerns a lack of response and action by the respondent authority in resolving a complaint made regarding environmental, integrity, and safety problems caused to the petitioners by the project for the “Construction of the interchanges between the intersection of National Routes No. 2 and No. 236 (Taras) and the intersection of National Routes No. 2 and No. 10 (Cartago), including the Improvement of National Route No. 2, Section: Taras-La Lima”. Having clarified this point, we proceed to resolve the specific situation raised in this amparo.
The appellants file an amparo alleging that the project for the “Construction of the interchanges between the intersection of National Routes No. 2 and No. 236 (Taras) and the intersection of National Routes No. 2 and No. 10 (Cartago), including the improvement of National Route No. 2, Section: Taras-La Lima”, has generated a series of problems affecting their fundamental rights. They state that since November 2024, they have sent notes to the respondent ministry to resolve the problems afflicting them. The following claims are detailed: a) that when the construction in question began, significant mobilization of fill material was required to raise the road, leaving the properties and buildings in the area at lower levels compared to the new asphalt layer, which caused their properties to be at a significant grade difference from the road, receiving water coming from it; and that, in relation to the above, in neither of the two islands have the necessary sewers for channeling both residual and rainwater been created by the State to date, so their families had to make ditches with their own resources around the properties to channel the water and provide the respective maintenance each year to prevent their homes from flooding.
Thus, the sewer crossing the street in front of their houses, which receives all the water from the Alto de Ochomogo de Cartago community and collapses at certain times, causes the water to cross the road as it seeks its course to lower levels and floods their houses, generally crossing through the properties; b) that in September 2022, the officials present at the site proceeded to cut down all the trees that surrounded the perimeter of their properties and served as a natural barrier against noise and pollution to their benefit; consequently, they proceeded to inquire about the reasons for this action and the mitigating measures that would be provided in response; as a result, they were told that this measure was required to proceed with the construction of the overpass in the Taras sector and that the company in charge of this road intervention had to place construction mesh (sarán), especially in the case of the island or segment of the Nombre105833 and Aguilar Rojas Family, which was insufficient to ensure the security and privacy of their properties; and that as a result of the work in question, being close to their houses causes: noise, pollution, dust, a situation that affects their health, and that the construction being so close to their houses affects their privacy; c) that as a result of this construction, there are sections where it is difficult for them to leave and enter their properties.
They state that as a result of the described problem, they sent notes to the MOPT authorities to obtain a solution to their problem; however, as of the date they file the amparo, the visits made by said authority have not generated a positive result that resolves the indicated problem. They request the intervention of this Constitutional Court.
Of importance for the decision in this matter, the following facts are deemed duly demonstrated:
1. The appellant Nombre105833 is the owner of the properties with cadastral plan numbers C-0313896-1996 and C-540792-9; the appellant Nombre105835 of the property with cadastral plan No. C-5923034-99, No. C-596021- 99 and C-; the appellant Nombre105834 of the property with cadastral plan No. C 5923034-99 and No. C-596021-99; the appellant Nombre105836 of the property with cadastral plan No. 3-888082-2003 and C-1078936-2006; the appellant Nombre105833 of the property with cadastral plan No. 3-888151-2003 and No. C-1078936-2006; the appellant Nombre105833, of the property with cadastral plan No. C-304483-1978 and No. Telf8781, all located in the province of Cartago, San Nicolás de Ochomogo. (undisputed fact); 2. The construction project for the interchanges between the intersection of National Routes No. 2 and No. 236 (Taras) and the intersection of National Routes No. 2 and No. 10 (Cartago), including the improvement of National Route No. 2, Section: Taras-La Lima, is under the responsibility of the Ministry of Public Works and Transport.
(report rendered by the respondent authorities CONAVI and the Municipality of Cartago); 3. On Dirección6013 the plaintiffs sent a note to the email address ...3, to the Advisory Unit and Administration and Supervision Committee PIT and PIV-APP of the MOPT, regarding queries and concerns about the problem afflicting them as a result of the indicated works. (see evidence provided); 4. That the appellants have been informed about the solutions for the adequate management of the project's stormwater runoff (escorrentía pluvial), the improvements implemented in the project to guarantee that their properties will have a collection point for rainwater. This is why, once the works at the upper level of the Taras Interchange have been completed, as well as the beginning of the summer season, it will allow the construction of various works at the lower level of the interchange, which will guarantee the adequate functioning of the project's storm drainage outlets (desfogues pluviales) and the adjacent properties.
(see official communication DM-PACAS-2024-0720 dated November 25, 2024, signed by the director of the Advisory Unit for Transportation Infrastructure Programs (PIT) and Road Infrastructure and Public-Private Partnership Promotion (PIV-APP) of the MOPT); 5. That part of the work carried out temporarily at the sites where water accumulation occurred included: enabling an existing collector that allows water to drain in that sector; in addition, a channel was temporarily built to also allow drainage of water accumulating in the sector, as well as berms (camellones) to prevent water from accessing the properties. Temporary solutions that did not completely eliminate the impact, due to the impossibility of executing the work definitively. (see official communication DM-PACAS-2024-0720 dated November 25, 2024); 6. That for the construction of the works at the site, tree felling and cleaning are being carried out.
Given that, in order to provide a boundary, adjacent persons were offered the placement of temporary construction mesh (sarán), because a wall will ultimately be placed in this sector that will also serve to delimit the right-of-way. (see official communication DM-PACAS-2024-0720 dated November 25, 2024); 7. Regarding noise pollution (contaminación sónica): That this is the responsibility of the Traffic Police Directorate. The Law on Transit on Public Land Roads and Road Safety, No. 9078, establishes a series of requirements that vehicles must meet to circulate safely on roads. Once the project is completed, measurements will be taken to confirm that the noise is within the limit range, and in case of detecting any non-compliance, the respective communication will be made to the Transit Police so that appropriate measures are taken. (see official communication DM-PACAS-2024-0720 dated November 25, 2024); 8.
That with the filing of the amparo, the MOPT commits to issuing instructions to review the indicated impacts and to implement the necessary temporary mitigation measures to minimize the problem afflicting the protected parties. (see official communication DM-PACAS-2024-0720 dated November 25, 2024); 9. That among the environmental mitigation measures is the dust control protocol, which in turn references the OBIS P-010 protocol for Soil Management and particle control. The purposes of which are: To prevent air contamination from particle emissions due to the transport and hauling of construction materials, debris, and excavation. To prevent the deterioration of air quality due to the increased concentration of suspended particles. To prevent air contamination with particulate matter from the transport and hauling of construction materials. To control dust levels in the dry season caused by earthworks (movimientos de tierra) and other activities during the construction stage.
(see official communication DM-PACAS-2024-0720 dated November 25, 2024); 10. The work in question is in charge of the Contractor Consorcio HSolis – Estrella, and verified in its compliance by the Supervisory Unit CONSORCIO APPLUS NORCONTROL S.L.U., INGELOG CONSULTORES DE INGENIERÍA Y SISTEMAS S.A. E INGELOG COSTA RICA S.A. through a Major Works contract. (see official communication DM-PACAS-2024-0720 dated November 25, 2024); 11. That the indicated project has always guaranteed access to the properties, it being likely that at some point there will be impacts to the accesses while works are carried out in front of the properties; however, these will be communicated in a timely manner by the OGAS team. (see official communication DM-PACAS-2024-0720 dated November 25, 2024); Through official communication A-1063-CON-942-UEP-2024, signed by the Supervisory Unit of the CONSORCIO APPLUS NORCONTROL S.L.U., INGELOG CONSULTORES DE INGENIERÍA Y SISTEMAS S.A. E INGELOG COSTA RICA S.A., addressed to the MOPT, the following deadlines and works to be performed are indicated, in order to solve the reported water problem:
- Construction of a longitudinal open drain (cuneta), the purpose of which is to evacuate surface water from the lower part of the fill and convey it to a nearby sewer, so that the water from the roads, both carriageways routing users from Cartago-San José and vice versa, and from the projected service road (marginal) as a Cartago-Cartago return. This will achieve adequate management of surface water falling on the surface, preventing it from improperly flowing onto any property. (see official communication DM-PACAS-2024-0720 dated November 25, 2024).
- The project contemplates the construction of a collection and conveyance system for surface water at the property level, with adequate capacity. (see official communication DM-PACAS-2024-0720 dated November 25, 2024).
Report rendered by the MOPT as evidence for a better resolution. Through official communication CARTA-MOPT-DM-PACAS-2025-0106 dated March 13, 2025, signed by the director of the MOPT Advisory Unit, the following is reported:
12. During the months of November 2024, December 2024, January 2025, and February 2025, work was carried out with the purpose of resolving the reported problem; however, the works encompass 2 intervention areas; area number 2 corresponds to the work on the lower elevation part, and where the greatest impacts were occurring, this work has already been completed. This work is definitive, therefore the reported impact would be resolved.
13. The work in area 1 is pending execution, because the design of a wall and the construction of the stormwater runoff (escorrentía pluvial) management system are pending. The plan is to begin these tasks in April 2025, with a 4-month execution schedule, so the works should be completed by July 2025. It is reported that this work will be definitive.
14. That assistance has continued to be provided to the Nombre105836 family, regarding the assistance provided, as well as a meeting with public security forces seeking support and attention to possible invasions in the sector. Likewise, explanations of the designs that will contain the solutions for the adequate management of the project's stormwater runoff (escorrentía pluvial), improvements implemented in the project to guarantee that their properties will have a collection point for rainwater. (report rendered by the MOPT).
ONLY) That the respondent MOPT authorities have formally communicated to the appellants about the actions taken regarding the request filed on August 20, 2024.
In the case at hand, the appellants file an amparo alleging that the project for the “Construction of the interchanges between the intersection of National Routes No. 2 and No. 236 (Taras) and the intersection of National Routes No. 2 and No. 10 (Cartago), including the improvement of National Route No. 2, Section: Taras-La Lima”, has generated a series of problems affecting their fundamental rights. This is because when the construction of the indicated project began, a significant mobilization of fill material was required to raise the road, leaving the properties and buildings in the area at lower levels compared to the new asphalt layer, which caused their properties to be at a significant grade difference from the road, receiving the water that comes from it. Likewise, that to date, in neither of the two islands have the necessary sewers for channeling both residual and rainwater been created, so they had to make ditches with their own resources around the properties to channel the water and provide the respective maintenance each year to prevent their homes from flooding.
They allege that the sewer crossing the street in front of their houses, which receives all the water from the Alto de Ochomogo de Cartago community, collapses at certain times and causes the water to cross the road as it seeks its course to lower levels, and floods their houses by crossing through the properties.
In this regard, the respondent authority, the Ministry of Public Works and Transport, reports that although at the beginning of the works temporary measures were taken at the sites where water accumulation occurred, such as an existing collector that allows water to drain in that sector, and a channel was temporarily built to also allow the drainage of water accumulating in the sector, as well as berms (camellones) to prevent water from accessing the properties, these actions did not completely eliminate the impact. Likewise, they state that on the occasion of the filing of this amparo, that authority committed to solving the reported problem, and that as of the date the last report requested as evidence for a better resolution was rendered, that is, March 14 of the current year, it was stated to the Chamber under oath that during the months of November 2024, December 2024, January 2025, and February 2025, work was carried out with the purpose of resolving the reported problem; however, the project encompasses 2 intervention areas, and area number 2, which corresponds to the work on the lower elevation part and where the greatest impacts were occurring, this has already been completed and is definitive work, which would resolve the reported impact.
Meanwhile, regarding the work in "area 1", they indicate that it is pending execution because the design of a wall and the construction of the stormwater runoff (escorrentía pluvial) management system are pending, so the start of the works is scheduled for April 2025, with a completion date of July 2025, and these will be definitive works, in order to solve the problem reported due to the project's stormwater runoff (escorrentía pluvial), to guarantee that the properties of the protected persons are not affected by the collection of rainwater. This situation was communicated to the interested parties.
From the foregoing, this Chamber certifies the violation of the fundamental rights of the protected parties, as it has been demonstrated that since November 2024, they have requested the authorities of the respondent ministry to provide a solution to the problem afflicting them due to the poor water management resulting from the indicated construction, and as of the date they filed the amparo, the authorities had not provided an integral and definitive solution to the problem; however, as indicated, on the occasion of the notification granting leave to proceed, the respondent MOPT authorities took the corresponding actions to address the reported problem, and upon detecting that the problem lies in two points, and that part 2 has already been resolved, with the execution of works in area 1 pending, and it being reported that this will be completed in June of this year, the appropriate action is to grant the appeal, with the order that the indicated date be respected.
VI.On the other hand, from the evidence provided to the file, it is clear that on August 20, 2024, the plaintiffs sent a note to the email address ...3, of the Advisory Unit and Administration and Supervision Committee PIT and PIV-APP of the MOPT, with queries and concerns about the problem afflicting them as a result of the indicated works; however, although the respondent authorities report to the Chamber that they have maintained constant communication with the appellants to keep them informed about the progress of the works being carried out, the truth is that it is not proven that a formal response was given to the request filed by the interested parties, as was requested. Thus, regarding this point, the appeal is granted.
VII.Furthermore, from the filing document it is clear that the plaintiffs allege that the indicated work generates a series of additional situations beyond the one previously indicated, which affect their quality of life, summarized as follows: that for the construction of the works, trees that served as a natural barrier against noise and dust were cut down. Likewise, that they experience difficulty in leaving and entering their properties as a result of the construction.
In this regard, the respondent ministry authority reports that for the construction of the works at the site, tree felling and cleaning are being carried out, and that, in order to provide a boundary, adjacent persons were offered the placement of temporary construction mesh (sarán), because a wall will ultimately be placed in this sector that will also serve to delimit the right-of-way. Thus, on this point, no violation of the rights of the protected parties is observed, so the appeal is dismissed.
Regarding noise pollution (contaminación sónica), the respondent authority states that this is the responsibility of the Traffic Police Directorate. It indicates that the Law on Transit on Public Land Roads and Road Safety, No. 9078, establishes a series of requirements that vehicles must meet to circulate safely on roads, and that once the project is completed, measurements will be taken to confirm that the noise is within the limit range, and in case of detecting any non-compliance, the respective communication will be made to the Transit Police so that appropriate measures are taken. Based on the foregoing, on this point, as no violation of the fundamental rights of the protected parties is observed, the appeal is dismissed.
Regarding environmental mitigation measures for dust problems. It was reported that the project has a dust control protocol, which in turn references the “OBIS P-010 protocol for Soil Management and particle control”, whose purpose is to prevent air contamination from particle emissions due to the transport and hauling of construction materials, debris, and excavation; to prevent the deterioration of air quality due to the increased concentration of suspended particles; to prevent air contamination with particulate matter from the transport and hauling of construction materials; to control dust levels in the dry season caused by earthworks (movimientos de tierra) and other activities during the construction stage. For the above reasons, on this point, no violation of the rights of the protected parties is observed, so the appeal is dismissed.
In turn, regarding the claim by the appellants that as a result of this construction there are sections where it is difficult for them to leave and enter their properties. On this point, the respondent MOPT authority reports under oath that access to the properties in the area has always been guaranteed, and that if at any time work is carried out that affects the accesses, while works are performed in front of the properties, this will be communicated in a timely manner by the OGAS team. Thus, regarding this point, no violation of the rights of the protected parties is observed, so the appeal is dismissed.
VIII.Finally, the petitioners' claims suggest the appointment of an expert (perito) to determine the corresponding compensation for the affected properties due to the indicated works. Likewise, that the installation of visible and effective signage be ordered on the road, clearly indicating the safe conditions to access the commercial premises “Embutidos artesanales El Gaucho”, promoting and encouraging the safety of customers and residents in both the Cartago-San José and San José-Cartago directions. That adequate compensation be considered for the economic losses due to the problems and changes in road sections that reduced customer traffic to the commercial premises “El Gaucho”, interrupting normal commercial activity as a result of the variability and continuous delays of the project works. Regarding these claims, the appellant parties are warned that such disagreement or request must – if they deem it appropriate – be raised before the respondent authorities or in the competent jurisdictional venue, as it is not for this Court to rule on the matter. Consequently, on this point, the appeal is dismissed.
IX.Finally, regarding the National Roadway Council (Consejo Nacional de Vialidad) and the Municipality of Cartago, this Chamber does not observe that they have incurred in acts or omissions that warrant the intervention of this Court, as it was proven that said authorities have no involvement in the works alleged here. Thus, regarding these authorities, the appeal is dismissed.
I have supported the thesis of this Court that when the claimant alleges a violation of the right to prompt and fulfilled justice in administrative proceedings, those who must hear the legal dispute are the Administrative-Contentious Courts and not this Chamber. However, with the recent enactment of Law No. 9097, Law Regulating the Right of Petition, it has been established that this right is susceptible to judicial protection through the amparo remedy established by Article 32 of the Law of Constitutional Jurisdiction, in relation to Article 27 of the Political Constitution of the Republic of Costa Rica, in those cases where the petitioner considers that the material actions of the Administration, its administrative acts, or its response are affecting their fundamental rights. In my view, the recently enacted regulation does not imply that this Court must modify its jurisprudential line, which, based on numeral 7 of its Law, has the exclusive authority to define its own jurisdiction.
Therefore, except for those legal-constitutional controversies that this same Chamber has recognized as exceptional cases, which may be heard in this jurisdiction through the constitutional amparo guarantee process, in all other cases, and for the reasons given by this Court (ruling No. 2008-02545 at 8:55 a.m. on February 22, 2008), the competent judges are those of the administrative-contentious jurisdiction, all of which is in accordance with numeral 25 of the American Convention on Human Rights, the Constitution's Law (values, principles, and norms), and the corresponding legal norms based on a logical, systemic, and teleological interpretation of the legal system.
In principle, I consider that cases related to the inactivity of the Public Administration in the repair, construction, modification, or demolition of any infrastructure work must be dismissed, as such omission constitutes a matter of legality, the discussion of which corresponds to the ordinary jurisdiction, before which the interested person can debate their disagreements with greater scope.
However, when that omissive administrative conduct results in a violation of other fundamental rights protected in this constitutional jurisdiction, or affects groups considered vulnerable, I do proceed to hear the merits of the matter, as this situation constitutes an exception to my position on this subject, just as in this amparo, which discusses the effects of the works, as well as the lack thereof and necessary precautions in the project for the “Construction of interchanges between the intersection of National Routes No. 2 and No. 236 (Taras) and the intersection of National Routes No. 2 and No. 10 (Cartago), including the Improvement of National Route No. 2, Section: Taras-La Lima.” As a result of all this, problems of water runoff, and other complications due to the lack of works, arise that affect the residents along the route, all of which represents a risk to property, physical integrity, and health.
The appellant is warned that if any document has been submitted on paper, as well as objects or evidence contained in any additional electronic, computer, magnetic, optical, telematic device or one produced by new technologies, these must be retrieved from the office within a maximum period of 30 working days from the notification of this judgment. Otherwise, all material not retrieved within this period shall be destroyed, pursuant to the provisions of the “Reglamento sobre Expediente Electrónico ante el Poder Judicial,” approved by the Corte Plena in session No. 27-11 of August 22, 2011, article XXVI and published in the Judicial Bulletin No. 19 of January 26, 2012, as well as the agreement approved by the Consejo Superior del Poder Judicial, in session No. 43-12 held on May 3, 2012, article LXXXI.
POR TANTO:
The recurso is partially granted, solely for the lack of response to the petition dated August 20, 2024, and the lack of action regarding the water problem on the petitioners' property. Efraím Zeledón Leiva, Minister of Public Works and Transport, or whoever holds the office, is ordered to take the corresponding measures and carry out the coordination actions deemed necessary, within the scope of his competence, so that: a) Within FIVE DAYS from the notification of this judgment, the appellants shall be informed of the actions taken regarding the petition dated August 20, 2024; b) By no later than the month of June 2025, the pending works in “Area 1” shall be completed, in order to resolve the problem reported here resulting from water affecting the petitioners’ property, as was reported to this Chamber. The foregoing, under the warning that, in accordance with the provisions of article 71 of the Ley de la Jurisdicción Constitucional, a prison term of three months to two years, or a fine of twenty to sixty days, shall be imposed upon anyone who receives an order that must be fulfilled or enforced, issued in an amparo proceeding, and fails to fulfill it or cause it to be fulfilled, provided the offense is not more severely punished.
The State is ordered to pay the costs, damages, and losses caused by the facts that serve as the basis for this declaration, which shall be liquidated in the execution of the sentence of the contentious-administrative court. Judge Castillo Víquez sets down a note. Judge Salazar Alvarado sets down a note. As for the Consejo Nacional de Vialidad and the Municipalidad de Cartago and the other claims asserted, the recurso is denied. Let it be notified.
Fernando Castillo V. President Fernando Cruz C.
Paul Rueda L.
Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Ingrid Hess H.
SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas quince minutos del veintiocho de marzo de dos mil veinticinco .
Recurso de amparo que se tramita en expediente número No. 24-031349-0007-CO, interpuesto por Nombre105832, cédula de identidad CED59462, Nombre105833, cédula de identidad CED59463, Nombre105834, cédula de identidad CED59464, Nombre105833, cédula de identidad CED59465, Nombre105833, cédula de identidad CED59466, Nombre105835, cédula de identidad CED59467 y Nombre105836, cédula de identidad CED59468, contra el MINISTERIO DE OBRAS PÚBLICAS Y TANSPORTES y la MUNICIPALIDAD DE CARTAGO.
RESULTANDO:
Redacta la Magistrada Hess Herrera; y,
CONSIDERANDO:
Antes de analizar el fondo del asunto –por la presunta violación del derecho a un procedimiento pronto y cumplido– debe aclararse que, a partir de la sentencia nro. 2008-02545 de las 8:55 horas del 22 de febrero de 2008, esta Sala ha remitido a la jurisdicción contencioso administrativa –con algunas excepciones– aquellos asuntos en los que se discute si la administración pública ha cumplido o no los plazos, pautados por la Ley General de la Administración Pública (artículos 261 y 325) o por las leyes sectoriales relativas a los procedimientos administrativos especiales, tanto para resolver por acto final un procedimiento administrativo –instruido de oficio o a instancia de parte– como para conocer de los recursos administrativos procedentes. Precisamente, en este caso se plantea un supuesto de excepción, pues se trata de falta de respuesta y acción por parte de la autoridad accionada, en resolver una denuncia realizada por problemas ambientales, de integridad y seguridad que les genera a los tutelados, producto del proyecto de “Construcción de los intercambios entre la intersección de las Rutas Nacionales N° 2 y N° 236 (Taras) y la intersección de las Rutas Nacionales N° 2 y N° 10 (Cartago), incluyendo el Mejoramiento de la Ruta Nacional N° 2, Sección: Taras-La Lima”. Aclarado el punto, se entra a resolver la situación concreta planteada en este amparo.
Los recurrentes acuden en amparo y alegan, que el proyecto de “Construcción de los intercambios entre la intersección de las Rutas Nacionales N° 2 y N° 236 (Taras) y la intersección de las Rutas Nacionales N° 2 y N° 10 (Cartago), incluyendo el mejoramiento de la Ruta Nacional N° 2, Sección: Taras-La Lima”, les ha generado una serie de problemas, que les afecta sus derechos fundamentales. Nombre774, que desde noviembre de 2024 han enviado notas al ministerio accionado a fin de que se les resuelva la problemática que les aqueja. Se desglosan los siguientes reclamos: a) que al momento de iniciarse la construcción en cuestión, se requirió una importante movilización de material de relleno para elevar la carretera, dejando a las propiedades e inmuebles de la zona, con niveles más bajos con respecto a la nueva capa asfáltica, lo cual causó que sus propiedades quedaran a un importante desnivel de la carretera, recibiendo las aguas que provienen de ésta, y que en relación con lo anterior, en ninguna de las dos islas se han creado, hasta el día de hoy, las alcantarillas necesarias para la canalización de las aguas, tanto residuales como llovidas, por parte del Estado, por lo que sus familias tuvieron que hacer zanjas con sus propios recursos, en los alrededores de las propiedades para encausar las aguas y darles cada año el respectivo mantenimiento para evitar que sus hogares se inundaran.
Así, la alcantarilla cruzando la calle al frente de sus casas, que recibe todas las aguas de la comunidad del Alto de Ochomogo de Cartago, y que en algunas épocas se colapsa, hace que las aguas crucen la vía, al buscar su cauce a niveles inferiores, e inunden sus casas atravesando, generalmente, las propiedades; b) que en setiembre de 2022 los funcionarios presentes en la obra, procedieron a talar todos los árboles que rodeaban el perímetro de sus propiedades y servían de barrera natural contra el ruido y la contaminación a su favor, ante ello, procedieron a consultar sobre las razones de esa acción y las medidas paliativas que se brindarían ante ello; producto de eso, se les indicó que esa medida fue requerida para poder proceder con la construcción del paso a desnivel en el sector de Taras y que la empresa a cargo de esa intervención vial, debía colocar sarán, especialmente en el caso de la isla o segmento de la Familia Nombre105833 y Aguilar Rojas, lo cual resultaba insuficiente para asegurar la seguridad y privacidad de sus propiedades; y que producto de la obra en cuestión, al estar cerca de sus casa les ocasiona: ruidos, contaminación, polvo, situación que les afecta la salud, y que al estar la construcción tan cerca de sus casas se les afecta la privacidad; c) que producto de esta construcción hay tramos que se le dificultan salir y entrar de sus propiedades.
Nombre774, que a raíz de la problemática descrita enviaron notas a las autoridades del MOPT a fin de que se les dé una solución a su problema; sin embargo, a la fecha en que acuden en amparo, las visitas realizadas por parte de dicha autoridad, no han generado un resultado positivo que les resuelva la problemática señalada. Solicitan la intervención de este Tribunal Constitucional.
De importancia para la decisión de este asunto, se estiman como debidamente demostrados los siguientes hechos:
1. La recurrente Nombre105833 es propietaria de las fincas con planos catastrados números C-0313896-1996 y C-540792-9; la recurrente Nombre105835 de la finca con plano catastro No. C-5923034-99, No. C-596021- 99 y C-; el recurrente Nombre105834 de la finca con plano catastro No. C 5923034-99 y No. C-596021-99; la recurrente Nombre105836 de la propiedad con plano catastro No. 3-888082-2003 y C-1078936-2006; la recurrente Nombre105833 de la propiedad con plano catastro No. 3-888151-2003 y No. C-1078936-2006; la recurrente Nombre105833, de la propiedad con plano catastro No. C-304483-1978 y No. Telf8781, todas ubicadas en la provincia de Cartago, San Nicolás de Ochomogo. (hecho no controvertido); 2. El proyecto de construcción de los intercambios entre la intersección de las Rutas Nacionales N° 2 y N° 236 (Taras) y la intersección de las Rutas Nacionales N° 2 y N° 10 (Cartago), incluyendo el mejoramiento de la Ruta Nacional N° 2, Sección: Taras-La Lima, está a cargo del Ministerio de Obras Públicas y Transportes.
(informe rendido por las autoridades recurridas del CONAVI y de la Municipalidad de Cartago); 3. El Dirección6013 los accionantes enviaron nota al correo electrónico ...3, a la Unidad Asesora y Comité de Administración y Supervisión PIT y PIV-APP del MOPT, respecto a consultas e inquietudes sobre la la problemática que les aqueja, producto de las obras señaladas. (ver prueba aportada); 4. Que a los recurrentes se les ha indicado sobre las soluciones para el manejo adecuado de la escorrentía pluvial del proyecto, las mejoras implementadas en proyecto, para garantizar que sus propiedades tendrán un punto de captación de las aguas producto de las lluvias. Es por esto, que una vez que se haya culminado las obras a nivel superior en el Intercambio de Taras, así como la entrada de la época de verano, permitirá con la construcción de diversas obras en el nivel inferior del intercambio, que garantizarán el adecuado funcionamiento de los desfogues pluviales del proyecto y los predios aledaños.
(ver oficio DM-PACAS-2024-0720 con fecha de 25 de noviembre de 2024 suscrito por el director de la Unidad Asesora de Programas de Infraestructura de Transporte (PIT) y de Infraestructura Vial y promoción de Asociaciones Público-Privadas (PIV-APP) del MOPT); 5. Que parte de los trabajos realizados de manera temporal en los sitios donde se presentó acumulación de agua, fueron: la habilitación un colector existente que permite que las aguas desfoguen en ese sector, además se ha construido temporalmente un canal que también permita el escurrimiento de las aguas que se acumulan en el sector, así como camellones que impidieran el acceso del agua a las propiedades. Soluciones temporales que no eliminaron la afectación totalmente, debido a la imposibilidad de ejecutar los trabajos de manera definitiva. (ver oficio DM-PACAS-2024-0720 con fecha de 25 de noviembre de 2024); 6. Que para la construcción de las obras en el lugar, se encuentra la ejecución de la tala de árboles y limpieza.
Siendo que a las personas colindantes se les propuso con el fin de brindar una delimitación, colocar sarán de manera temporal, debido a que finamente en este sector se colocará un muro que cumpliría función también de la delimitación del derecho de vía. (ver oficio DM-PACAS-2024-0720 con fecha de 25 de noviembre de 2024); 7. En lo que respecta a la contaminación sónica: Que le corresponde a Dirección de la Policía de Tránsito. La Ley de Tránsito por Vías Públicas Terrestres y Seguridad Vial, N° 9078, establece una serie de requisitos que deben tener los vehículos para circular de manera segura en carretera. Una vez el proyecto finalice se realizará medición para confirmar que el ruido se encuentre dentro del rango límite, y en caso de detectar algún incumplimiento, se realizará la respectiva comunicación a la Policía de Tránsito, para que se tomen las medidas correspondientes. (ver oficio DM-PACAS-2024-0720 con fecha de 25 de noviembre de 2024); 8.
Que con la interposición del amparo el MOPT se compromete a girar las instrucciones para que realicen la revisión de las afectaciones indicadas, y que además se implementen las medidas de mitigación temporales necesarias para minimizar la problemática que les aqueja a las partes amparadas. (ver oficio DM-PACAS-2024-0720 con fecha de 25 de noviembre de 2024); 9. Que dentro de las medidas de mitigación ambiental, se encuentra el protocolo de control del polvo, el que a su vez tiene como referencia el protocolo OBIS P-010 de Manejo de suelo y control de partículas. Los cuales tiene como propósito: Prevenir la contaminación del aire con emisión de partículas por el transporte y acarreo de materiales tanto de construcción, escombros, y excavación. Prevenir el deterioro de la calidad del aire por el aumento de concentración de partículas en suspensión. Prevenir la contaminación del aire con material particulado por el transporte y acarreo de materiales de construcción.
Controlar los niveles de polvo en la época seca provocados por los trabajos de movimientos de tierra y otros durante la etapa constructiva. (ver oficio DM-PACAS-2024-0720 con fecha de 25 de noviembre de 2024); 10. La obra en cuestión está a cargo del Contratista Consorcio HSolis – Estrella, y verificados en su cumplimiento por la Unidad Supervisora CONSORCIO APPLUS NORCONTROL S.L.U., INGELOG CONSULTORES DE INGENIERÍA Y SISTEMAS S.A. E INGELOG COSTA RICA S.A. Mediante contrato de Obra Mayor. (ver oficio DM-PACAS-2024-0720 con fecha de 25 de noviembre de 2024); 11. Que el proyecto indicado siempre ha garantizado el acceso a las propiedades, siendo probable que en algún momento se realicen afectaciones a los accesos, mientras se realizan las obras en el frente de los predios; sin embargo, las mismas serán comunicadas oportunamente por el equipo OGAS. (ver oficio DM-PACAS-2024-0720 con fecha de 25 de noviembre de 2024); Mediante oficio A-1063-CON-942-UEP-2024, suscrito por la Unidad Supervisora del CONSORCIO APPLUS NORCONTROL S.L.U., INGELOG CONSULTORES DE INGENIERÍA Y SISTEMAS S.A. E INGELOG COSTA RICA S.A., dirigido al MOPT, se indican los siguientes plazos y obras a realizar, a fin de solucionar la problemática de aguas denunciado:
- Construcción de un drenaje abierto longitudinal (cuneta), cuyo fin de evacuar las aguas superficiales de la parte baja del relleno y concluirlas a una alcantarilla cercana, para que las aguas de las carreteras, tanto de calzadas que enrutan a los usuarios de Cartago- San José, como viceversa y de la marginal proyectada como retorno Cartago- Cartago. Esto logrará un adecuado manejo de las aguas superficiales que caen sobre la superficie, evitando que estas se dirijan a alguna propiedad de manera inadecuada. (ver oficio DM-PACAS-2024-0720 con fecha de 25 de noviembre de 2024).
- El proyecto tiene contemplado la construcción de un sistema de captación y conclusión de aguas superficiales a nivel de la propiedad, con una capacidad adecuada. (ver oficio DM-PACAS-2024-0720 con fecha de 25 de noviembre de 2024).
Informe rendido por parte del MOPT de prueba para mejor resolver. Mediante oficio CARTA-MOPT-DM-PACAS-2025-0106 de fecha 13 de marzo de 2025 suscrito por el director de la Unidad Asesora del MOPT, se informa lo siguiente:
12. Durante los meses de noviembre 2024, diciembre 2024, enero 2025 y febrero 2025 se realizaron trabajos con la finalidad de solucionar la problemática denunciada; sin embargo, las obras abarcan 2 áreas intervención; siendo el área número 2 que corresponde a los trabajos de la parte de menor elevación, y que era donde se presentaban las mayores afectaciones, estos trabajos ya fueron realizados. Estos trabajos son definitivos, por lo que se estaría solucionando la afectación denunciada.
13. Los trabajos del área 1 están pendientes de ejecución, debido a que se encuentra pendiente el diseño de un muro y la construcción del manejo de la escorrentía pluvial. El plan es iniciar con estas labores en el mes de abril 2025 y se tiene una programación de ejecución de 4 meses, por lo que las obras deberían estar finalizando en el mes de julio 2025. Se informa que estos trabajos serán definitivos.
14. Que se ha continuado brindando atención a la familia Nombre105836, de las atenciones realizadas, así como reunión con fuerza pública buscando el respaldo y la atención a posibles invasiones en el sector. Asimismo, explicaciones de los diseños, que tendrán las soluciones para el manejo adecuado de la escorrentía pluvial del proyecto, mejoras implementadas en proyecto, para garantizar que sus propiedades tendrán un punto de captación de las aguas producto de las lluvias. (informe rendido por el MOPT).
ÚNICO) Que las autoridades recurridas del MOPT hayan comunicado de manera formal a los recurrentes, sobre las actuaciones realizadas respecto a la gestión planteada el 20 de agosto de 2024.
En el sub lite, los recurrentes acuden en amparo y alegan, que el proyecto de “Construcción de los intercambios entre la intersección de las Rutas Nacionales N° 2 y N° 236 (Taras) y la intersección de las Rutas Nacionales N° 2 y N° 10 (Cartago), incluyendo el mejoramiento de la Ruta Nacional N° 2, Sección: Taras-La Lima”, les ha generado una serie de problemas que afectan sus derechos fundamentales. Lo anterior, porque que al momento de iniciarse la construcción del proyecto indicado, se requirió una importante movilización de material de relleno para elevar la carretera, dejando a las propiedades e inmuebles de la zona con niveles más bajos con respecto a la nueva capa asfáltica, lo cual causó que sus propiedades quedaran a un importante desnivel de la carretera, recibiendo las aguas que provienen de ésta. Asimismo, que en ninguna de las dos islas se han creado, hasta el día de hoy, las alcantarillas necesarias para la canalización de las aguas tanto residuales como llovidas, por lo que tuvieron que hacer zanjas con sus propios recursos, en los alrededores de las propiedades para encausar las aguas y darles cada año el respectivo mantenimiento para evitar que sus hogares se inunden.
Alegan, que la alcantarilla cruzando la calle al frente de sus casas, que recibe todas las aguas de la comunidad del Alto de Ochomogo de Cartago, y que en algunas épocas se colapsa y hace que las aguas crucen la vía al buscar su cauce a niveles inferiores, e inunden sus casas atravesando las propiedades.
Al respecto, informa la autoridad accionada del Ministerio de Obras Públicas y Transportes, que si bien al inicio de las obras se realizaron trabajos de manera temporal en los sitios donde se presentó acumulación de agua, como un colector existente que permite que las aguas desfoguen en ese sector, además se construyó de manera temporal un canal que también permita el escurrimiento de las aguas que se acumulan en el sector, así como camellones que impidieran el acceso del agua a las propiedades, estas acciones no eliminaron la afectación totalmente. Asimismo, Nombre774 que con ocasión a la interposición de este amparo, esa autoridad se comprometió a solucionar el problema que se acusa, siendo que a la fecha en que se rindió el último informe que fue solicitado en la prueba para mejor resolver, sea el 14 de marzo del año en curso, se indicó a la Sala bajo juramento que durante los meses de noviembre 2024, diciembre 2024, enero 2025 y febrero 2025 se realizaron trabajos con la finalidad de solucionar la problemática denunciada; sin embargo, que el proyecto abarca 2 áreas intervención, siendo que el área número 2, que corresponde a los trabajos de la parte de menor elevación y que era donde se presentaban las mayores afectaciones, estos ya fueron realizados y que son trabajos definitivos, que estaría solucionando la afectación denunciada.
Por su parte, con respecto a los trabajos del “área 1” Nombre774 que se encuentran pendientes de ejecución, debido a que se encuentra pendiente el diseño de un muro y la construcción del manejo de la escorrentía pluvial, por lo que el inicio de las obras está previsto para el mes de abril 2025 y con fecha de finalización para el mes de julio 2025, siendo que serán obras de manera definitiva, a fin de solucionar la problemática denunciada por la escorrentía pluvial del proyecto, para garantizar que las propiedades de los tutelados no se vean afectados de la captación de las aguas producto de las lluvias. Situación que les fue comunicado a los interesados.
De lo expuesto, esta Sala acredita la afectación de los derechos fundamentales de los amparados, esto por cuanto ha quedado demostrado que desde el mes de noviembre de 2024 han solicitado a las autoridades del ministerio accionado, se les dé una solución al problema que les aqueja, debido al mal manejo de aguas que provienen de la construcción señalada, y a la fecha en que acuden en amparo éstas no le habían dado una solución integral y definitiva al problema; sin embargo, como se indicó que con ocasión a la notificación que dio curso al proceso las autoridades accionadas del MOPT realizaron las acciones correspondientes, a fin de atender la problemática denunciada, siendo que al detectarse que el problema radica en dos puntos, y que la parte 2 ya fue resuelta, quedando pendiente la ejecución de las obras en lo que respecta en el área 1, y que se informa que ésta finalizará en el mes de junio del presente año, lo que procede es declarar con lugar el recurso, con la orden de que se respete la fecha que fue indicada.
VI.De otra parte, de la prueba aportada al expediente se desprende que el 20 de agosto de 2024 los accionantes enviaron una nota al correo electrónico ...3, de la Unidad Asesora y Comité de Administración y Supervisión PIT y PIV-APP del MOPT, con consultas e inquietudes sobre la problemática que les aqueja, producto de las obras señaladas; sin embargo, si bien las autoridades recurridas informan a la Sala que se han mantenido en constante comunicación con los recurrentes, a fin de mantenerlos informados respecto al avance de las obras que se están realizando, lo cierto es que no se acredita que a la gestión planteada por los interesados se les haya dado una respuesta formal, tal como fue solicitada. Así, en cuanto a este extremo se declara con lugar el recurso.
VII.Por otra parte, del escrito de interposición se desprende que los accionantes alegan que la obra señalada les genera una serie de situaciones adicionales a la anterior indicada, que les afecta su calidad de vida, de las cuales se reduce en las siguientes: que para la construcción de las obras se talaron árboles que servían de barrera natural contra el ruido y el polvo. Asimismo, que presentan dificultad en salir y entrar de sus propiedades producto de la construcción.
Al respecto, informa la autoridad del ministerio accionado que para la construcción de las obras en el lugar, se encuentra la ejecución de la tala de árboles y limpieza, siendo que a las personas colindantes se les propuso con el fin de brindar una delimitación, colocar sarán de manera temporal, debido a que en este sector se colocará un muro que cumpliría función también de la delimitación del derecho de vía. Así, en cuanto a este extremo, no se observa una afectación a los derechos de los amparados, por lo que se declara sin lugar el recurso.
En lo que respecta a la contaminación sónica, señala la autoridad accionada que esto le corresponde a Dirección de la Policía de Tránsito. Indica que La Ley de Tránsito por Vías Públicas Terrestres y Seguridad Vial, N° 9078, establece una serie de requisitos que deben tener los vehículos para circular de manera segura en carretera, y que una vez el proyecto finalice se realizará medición para confirmar que el ruido se encuentre dentro del rango límite, y en caso de detectar algún incumplimiento, se realizará la respectiva comunicación a la Policía de Tránsito, para que se tomen las medidas correspondientes. Por lo expuesto, en cuanto a este extremo, al no se observa una afectación a los derechos fundamentales de los amparados, el recurso se declara sin lugar el recurso.
Sobre las medidas de mitigación ambiental, por problemas por el polvo. Se informó que el proyecto cuenta con el protocolo de control del polvo, el que a su vez tiene como referencia el “protocolo OBIS P-010 de Manejo de suelo y control de partículas”, que tiene como propósito, prevenir la contaminación del aire con emisión de partículas por el transporte y acarreo de materiales tanto de construcción, escombros, y excavación, prevenir el deterioro de la calidad del aire por el aumento de concentración de partículas en suspensión, prevenir la contaminación del aire con material particulado por el transporte y acarreo de materiales de construcción, controlar los niveles de polvo en la época seca provocados por los trabajos de movimientos de tierra y otros durante la etapa constructiva. En razón de lo anterior, en cuanto a este extremo, no se observa una afectación a los derechos de los amparados, por lo que se declara sin lugar el recurso.
Por su parte, en cuanto a lo alegado por los recurrentes de que producto de esta construcción hay tramos donde se le dificulta salir y entrar de sus propiedades. Sobre este punto, informa bajo juramento la autoridad accionada del MOPT, que siempre se ha garantizado el acceso a las propiedades de la zona, y que si en algún momento se realizan trabajos que afecten los accesos, mientras se realizan las obras en el frente de los predios, esto será comunicado oportunamente por el equipo OGAS. Así las cosas, en cuanto a este extremo, no se observa una afectación a los derechos de los amparados, por lo que se declara sin lugar el recurso.
VIII.Finalmente, en las pretensiones de los recurrentes, se desprende que se nombre a un perito para que determine la indemnización correspondiente de los inmuebles afectados, por las obras señaladas. Asimismo, que se ordene la instalación de señalización visible y efectiva en la carretera, que indique claramente las condiciones seguras para acceder al local comercial “Embutidos artesanales El Gaucho”, que promueva y estimule la seguridad de los clientes y habitantes en los sentidos tanto Cartago-San José como San José-Cartago. Que se contemple una compensación adecuada por las pérdidas a nivel económico debido a los problemas y cambios en los tramos de carretera que redujeron el tráfico de clientes al local comercial “El Gaucho”, interrumpiendo la 14 actividad comercial normal, producto de la variabilidad y continuos atrasos de las obras del proyecto. Sobre estas pretensiones, se le advierte a las partes accionantes, que dicha disconformidad, o solicitud deberán –si a bien lo tienen-, plantearlas ante las autoridades recurridas o en la vía jurisdiccional competente, ya que no le compete a este Tribunal pronunciarse al respecto. En consecuencia, en cuanto a este extremo, se declara sin lugar el recurso.
IX.Por último, en cuanto al Consejo Nacional de Vialidad y a la Municipalidad de Cartago, esta Sala no observa que hayan incurrido en actos u omisiones que ameriten la intervención de este Tribunal, pues se acreditó que dichas autoridades no tienen participación de las obras que aquí se alegan. Así, en cuanto a estas autoridades, se declara sin lugar el recurso.
He apoyado la tesis de este Tribunal, de que cuando el justiciable alega una vulneración al derecho a una justicia pronta y cumplida en sede administrativa, quienes deben conocer la controversia jurídica son los Tribunales de lo Contencioso-Administrativo y no esta Sala. Ahora bien, con la reciente promulgación de la Ley n.° 9097, Ley de Regulación del Derecho de Petición, se ha establecido que ese derecho es susceptible de tutela judicial por medio del recurso de amparo establecido por el artículo 32 de la Ley de la Jurisdicción Constitucional, en relación con el artículo 27 de la Constitución Política de la República de Costa Rica, en aquellos casos en que el peticionario considere que las actuaciones materiales de la Administración, sus actos administrativos o su respuesta le estén afectando sus derechos fundamentales. A mi modo de ver, la normativa recién promulgada no implica que este Tribunal deba modificar su línea jurisprudencial, quien, con base en el numeral 7 de su Ley, le corresponde definir exclusivamente su propia competencia.
Por ende, salvo aquellas controversias jurídico-constitucionales que han sido reconocidas por esta misma Sala como supuestos de excepción, que sí proceden ser conocidas en esta jurisdicción a través del proceso constitucional de garantía del amparo, en los demás casos, y por las razones que ha dado este Tribunal (sentencia N° 2008-02545 de las 8:55 horas de 22 de febrero de 2008), los competentes son los Jueces de la jurisdicción de lo contencioso-administrativo, todo lo cual es conforme al numeral 25, de la Convención Americana sobre Derechos Humanos, el Derecho de la Constitución (valores, principios y normas) y las normas legales correspondientes con base en una interpretación lógica, sistémica y teleológica del ordenamiento jurídico.
En tesis de principio, considero que los casos relacionados con la inactividad de la Administración Pública en la reparación, construcción, modificación o demolición de cualquier obra de infraestructura, deben ser desestimados, por constituir, esa omisión, un tema de legalidad, cuya discusión corresponde a la jurisdicción ordinaria, ante la cual la persona interesada puede debatir, con mayor amplitud, sus disconformidades. Sin embargo, cuando de aquella conducta administrativa omisiva se derive alguna violación a otros derechos fundamentales tutelados en esta jurisdicción constitucional, o se afecten grupos considerados vulnerables, sí entro a conocer el fondo del asunto, por constituir esta situación una excepción a mi posición en esta materia, tal y como sucede en este amparo, en el que se discute los efectos de las obras, así como la falta de ellas y previsiones necesarias en el proyecto de “Construcción de los intercambios entre la intersección de las Rutas Nacionales N° 2 y N° 236 (Taras) y la intersección de las Rutas Nacionales N° 2 y N° 10 (Cartago), incluyendo el Mejoramiento de la Ruta Nacional N° 2, Sección: Taras-La Lima”. En razón de todo ello, surgen problemas de la escorrentía de aguas, y otras complicaciones por falta de obras, que afectan a los vecinos del trayecto, todo lo cual representa un riesgo para la propiedad, integridad física y la salud.
Se previene a la parte recurrente que de haber aportado algún documento en papel, así como objetos o pruebas contenidas en algún dispositivo adicional de carácter electrónico, informático, magnético, óptico, telemático o producido por nuevas tecnologías, éstos deberán ser retirados del despacho en un plazo máximo de 30 días hábiles contados a partir de la notificación de esta sentencia. De lo contrario, será destruido todo aquel material que no sea retirado dentro de este plazo, según lo dispuesto en el "Reglamento sobre Expediente Electrónico ante el Poder Judicial", aprobado por la Corte Plena en sesión N° 27-11 del 22 de agosto del 2011, artículo XXVI y publicado en el Boletín Judicial número 19 del 26 de enero del 2012, así como en el acuerdo aprobado por el Consejo Superior del Poder Judicial, en la sesión N° 43-12 celebrada el 3 de mayo del 2012, artículo LXXXI.
POR TANTO:
Se declara parcialmente con lugar el recurso, únicamente por la falta de respuesta a la gestión de fecha 20 de agosto de 2024 y a la falta de acción por la problemática de aguas en la propiedad de los tutelados. Se ordena a Efraím Zeledón Leiva, ministro de Obras Públicas y Transportes, o a quien ocupe el cargo, tomar las medidas correspondientes y se realicen las acciones de coordinación que se estimen necesarias, dentro del ámbito de su competencia, para que: a) En el plazo de CINCO DÍAS contados a partir de la notificación de esta sentencia se le comunique a los recurrentes las gestiones realizadas respecto a la gestión con fecha 20 de agosto de 2024; b) Que a más tardar para el mes de junio de 2025 se finalicen los trabajos que se encuentran pendientes por realizar en el “Área 1”, a fin de resolver la problemática aquí denunciada producto de aguas que afectan la propiedad de los tutelados, tal como fue informado a esta Sala.
Lo anterior, bajo la advertencia de que, de conformidad con lo establecido en el artículo 71, de la Ley de la Jurisdicción Constitucional, se impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo y no la cumpliere o no la hiciere cumplir, siempre que el delito no esté más gravemente penado. Se condena al Estado al pago de las costas, daños y perjuicios causados con los hechos que sirven de base a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso administrativo. El magistrado Castillo Víquez consigna nota. El magistrado Salazar Alvarado pone nota. En cuanto al Consejo Nacional de Vialidad y a la Municipalidad de Cartago y los demás extremos reclamados, se declara sin lugar el recurso. Notifíquese.
Fernando Castillo V.
Fernando Cruz C.
Paul Rueda L.
Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Ingrid Hess H.