Res. 02839-2025 Sala Constitucional · Sala Constitucional · 31/01/2025

Duty to Remedy Community Aqueduct DeficienciesDeber de solucionar deficiencias del acueducto comunitario

View document ↓ Ver documento ↓ View original source ↗ Ver fuente original ↗

Loading…Cargando…

OutcomeResultado

Partially grantedParcialmente con lugar

The Chamber ordered AyA and the ASADA to coordinate a solution to the water-deficient condition within one month and complete the necessary drinking-water infrastructure within twelve months, while denying the remaining claims.La Sala ordenó al AyA y a la ASADA coordinar en un mes la solución de la zona deficitaria y finalizar en doce meses las obras necesarias para garantizar el servicio de agua potable, pero rechazó los demás extremos del amparo.

SummaryResumen

The Constitutional Chamber partially granted the amparo against AyA and the San Juan de Santa Cruz ASADA because of their prolonged failure to address deficiencies in the community aqueduct’s storage and water-capture capacity. The area had been declared water-deficient in 2020, and the authorities had recommended withholding water-availability certificates until technical improvements were completed. Nevertheless, the ASADA waited almost four years to commission a technical assessment, while AyA—despite retaining technical oversight and legal authority over drinking-water supply—failed to demonstrate effective follow-up. This inaction left residents in prolonged uncertainty and prevented new service connections, violating the right to drinking water and the constitutional principle that public services must function properly. The Chamber ordered the respondents to coordinate a solution within one month and complete the required infrastructure within twelve months. It denied the remaining claims, including the alleged failure by AyA to answer a request, because the claimant had sent that communication to an incorrect email address.La Sala Constitucional declaró parcialmente con lugar el amparo contra el AyA y la ASADA de San Juan de Santa Cruz por la prolongada falta de acciones para superar las deficiencias de almacenamiento y captación del acueducto comunitario. Desde 2020, la zona había sido declarada deficitaria y se había recomendado suspender las constancias de disponibilidad de agua hasta ejecutar mejoras técnicas. Sin embargo, la ASADA tardó casi cuatro años en contratar una evaluación y el AyA, pese a conservar la rectoría técnica y la competencia sobre el suministro de agua potable, no acreditó un seguimiento eficaz. Esa inacción mantuvo a los administrados en incertidumbre e impidió nuevas conexiones, lesionando el derecho al agua potable y el principio de buen funcionamiento de los servicios públicos. La Sala ordenó coordinar una solución dentro de un mes y finalizar en doce meses las obras necesarias. Rechazó los demás extremos, incluida la alegada falta de respuesta del AyA, pues la gestión había sido enviada a una dirección electrónica incorrecta.

Key excerptExtracto clave

Accordingly, both the Institute and the respondent ASADA violated the principle that public services must function properly and the right to drinking-water service by failing to act promptly and jointly to ensure completion of the technical studies and infrastructure works needed for the San Juan aqueduct to have greater water-storage and capture capacity and thereby provide the community with drinking water. Both parties are obligated to safeguard the service’s continuity, quantity, and timely provision, thus upholding the right to health and the human right of access to drinking water and wastewater sanitation. As a consequence of these considerations, the appeal must be partially granted for infringement of the claimant’s rights to health and life, and the respondent authorities must be ordered, within their respective areas of authority, to take the corresponding actions so that improvements to the aqueduct are carried out. The appeal is partially granted solely with respect to the violation of the principle that public services must function properly and the right to drinking-water service. Georgina Garro Mora, in her capacity as Deputy Manager for Delegated Systems Management of the Costa Rican Institute of Aqueducts and Sewers, and Yanner Estiv Ramírez Aguilar, in his capacity as President of the Association Administering the Rural Aqueduct of San Juan de Santa Cruz, are ordered, within ONE MONTH from notice of this judgment, to coordinate the corresponding actions to address and resolve the situation raised by the claimant and to comply with Memorandum No. GSD-UEN-GAR-2020-00667 of February 21, 2020, “Declaration of San Juan, Santa Cruz, Guanacaste as a Water-Deficient Area.” In addition, the infrastructure works determined to be necessary for that purpose must be completed within TWELVE MONTHS from notice of this judgment.De manera, que tanto el Instituto y la Asada recurrida han quebrantado el principio del buen funcionamiento de los servicios públicos y el derecho al servicio de agua potable, al no efectuar de manera célere las acciones conjuntas para garantizar la realización de los estudios técnicos y las obras de infraestructura para que el acueducto de San Juan cuente con mayor almacenamiento del líquido y mejor captación, para garantizar y dotar de agua potable a la comunidad. Lo anterior porque es obligación de ambas partes, velar por la continuidad, la cantidad y la oportunidad del servicio, afirmando el derecho a la salud y el derecho humano de acceso al agua potable y saneamiento de las aguas residuales. Corolario de las consideraciones realizadas, se impone declarar parcialmente con lugar el recurso por infracción a los derechos de la recurrente a la salud y a la vida y ordenarles a las autoridades recurridas que ejecuten las acciones correspondientes, en sus respectivos ámbitos de competencia, para que se realicen las mejoras al acueducto. Se declara parcialmente con lugar el recurso, únicamente en cuanto a la violación del principio del buen funcionamiento de los servicios públicos y el derecho al servicio de agua potable. Se ordena a Georgina Garro Mora, en su condición de Subgerente de Gestión de Sistemas Delegados del Instituto Costarricense de Acueductos y Alcantarillado y a Yanner Estiv Ramírez Aguilar, en su condición de Presidente de la Asociación Administradora del Acueducto Rural de San Juan de Santa Cruz, que dentro del plazo de UN MES, a partir de la notificación de la presente sentencia, procedan a coordinar las acciones correspondientes para que se conozca y solucione la situación planteada por el recurrente, y proceder a cumplir con lo dispuesto en el memorando N°GSD-UEN-GAR-2020-00667, del 21 de febrero de 2020, "Declaratoria de Zona Deficitaria, San Juan, Santa Cruz, Guanacaste”. Además, las obras de infraestructura acordadas como necesarias para tal fin, deberán estar finalizadas dentro del plazo de DOCE MESES, a partir de la notificación de esta sentencia.

Pull quotesCitas destacadas

  • "Precisamente, el recurrente y los demás administrados durante todos estos años han permanecido en una situación de incertidumbre e inseguridad jurídica, a la espera que se efectúen las obras de infraestructura que requiere el acueducto para poder brindar el servicio de agua potable."

    "Throughout all these years, the claimant and the other residents have remained in a state of uncertainty and legal insecurity while waiting for the infrastructure works required for the aqueduct to provide drinking-water service."

    Considerando VIII

  • "Precisamente, el recurrente y los demás administrados durante todos estos años han permanecido en una situación de incertidumbre e inseguridad jurídica, a la espera que se efectúen las obras de infraestructura que requiere el acueducto para poder brindar el servicio de agua potable."

    Considerando VIII

  • "Lo anterior, infringe el derecho fundamental al buen funcionamiento de los servicios públicos, pues existe un retardo injustificado atribuido a la Asada recurrida en acatar las recomendaciones efectuadas por las autoridades del Instituto Costarricense de Acueductos y Alcantarillados y buscar una solución técnica, lo cual se tradujo en una evidente e ilegítima falta de servicio, contraria a los derechos constitucionales del recurrente al agua potable y a los principios constitucionales que rigen el funcionamiento de los servicios públicos."

    "This infringes the fundamental right to the proper functioning of public services because the respondent ASADA unjustifiably delayed implementing the recommendations of the Costa Rican Institute of Aqueducts and Sewers and seeking a technical solution, resulting in a clear and unlawful failure of service contrary to the claimant’s constitutional right to drinking water and the constitutional principles governing public services."

    Considerando VIII

  • "Lo anterior, infringe el derecho fundamental al buen funcionamiento de los servicios públicos, pues existe un retardo injustificado atribuido a la Asada recurrida en acatar las recomendaciones efectuadas por las autoridades del Instituto Costarricense de Acueductos y Alcantarillados y buscar una solución técnica, lo cual se tradujo en una evidente e ilegítima falta de servicio, contraria a los derechos constitucionales del recurrente al agua potable y a los principios constitucionales que rigen el funcionamiento de los servicios públicos."

    Considerando VIII

  • "Nótese, que la zona deficitaria indicada tiene la condición de temporalidad, y está supeditada a la ejecución de las obras de infraestructura que solventarían las necesidades de la zona y el acueducto, siendo que no le consta a la Sala que el Instituto haya realizado algún acto para garantizar el adecuado funcionamiento en la prestación de los servicios que brinda la ASADA recurrida."

    "The declared water-deficient status is temporary and contingent upon execution of the infrastructure works that would address the needs of the area and the aqueduct; however, the Chamber has no evidence that the Institute took any action to ensure the proper operation of the services provided by the respondent ASADA."

    Considerando VIII

  • "Nótese, que la zona deficitaria indicada tiene la condición de temporalidad, y está supeditada a la ejecución de las obras de infraestructura que solventarían las necesidades de la zona y el acueducto, siendo que no le consta a la Sala que el Instituto haya realizado algún acto para garantizar el adecuado funcionamiento en la prestación de los servicios que brinda la ASADA recurrida."

    Considerando VIII

Full documentDocumento completo

Sections

Procedural marks

Document Review Decision No. 2025002839 SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, at nine twenty in the morning on treinta y uno de enero de dos mil veinticinco.

Application for constitutional relief (recurso de amparo) being processed under case number 24-031181-0007-CO, filed by Nombre01, identity card No. NFP01, against the ASOCIACIÓN ADMINISTRADORA DEL ACUEDUCTO RURAL DE SAN JUAN DE SANTA CRUZ and the INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS.

Findings of Fact:

  1. 1In a filing submitted to the Court Chamber’s Clerk’s Office and added to the case file at 15:38 on 05 de noviembre de 2024, the applicant filed an application for constitutional relief against the ASOCIACIÓN ADMINISTRADORA DEL ACUEDUCTO RURAL DE SAN JUAN DE SANTA CRUZ and the INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS. In summary, he states that, since 2020, the residents of San Juan de Santa Cruz de Guanacaste have faced serious difficulties obtaining the water-availability certificate required to complete the procedures for approval of survey plans before the Municipalidad de Santa Cruz, for the purpose of securing lot segregations (segregaciones de lotes), registrations in the Registro Público, and applications for subsidies and building permits. He states that, in his particular case, he purchased a 501-meter lot from parent property (finca madre) N° PRN01, but has been unable to complete the segregation because he lacks the aforementioned certificate.He explains that he intended to build a small workshop in which to practice his profession as an electrical technician; however, to date, he has been unable to carry out that project, and therefore believes that his fundamental rights of access to drinking water, work, and decent housing have been violated. He explains that, according to memorandum N°GSD-UEN-GAR-2020-00667, dated 21 de febrero de 2020, concerning the “Declaration of a Water-Deficient Zone (Declaratoria de Zona Deficitaria), San Juan, Santa Cruz, Guanacaste,” it was recommended that certificates of service availability not be issued for two reasons: first, because the water-supply system (acueducto) lacks sufficient storage capacity, and second, because the well showed a flow-rate decrease of 0,9 l/s in the most recent measurement taken on 20 de enero de 2020, compared with MINAE records. He notes that, although a second well was placed into operation in the rural water-supply system, four years have passed without the water-storage problem being resolved.He adds that the administration of the San Juan rural water-supply system states that it lacks the financial resources to invest in tanks and pipes, and that the Instituto Costarricense de Acueductos y Alcantarillados has provided no response whatsoever. He emphasizes that access to drinking water is a fundamental human right derived from the rights to life and a healthy environment and that, to guarantee this right, the State provides that AyA may develop, use, regulate, and supervise publicly owned waters throughout the national territory, in the exercise of the State’s rights over them, as provided in the Ley de Aguas. He states that this situation affects many low-income individuals who make substantial financial efforts to obtain a registered cadastral plan (plano catastrado) and qualify for a housing subsidy (bono de vivienda). He explains that on 16 de octubre de 2024 he sent an email to ...02 addressed to “Rafael Bardoza Topping,” who is responsible for AyA’s ASADAS Management, requesting his intervention in the reported matter; however, he alleges that, as of the date on which he sought constitutional relief, he had not received a response.
  2. 2By decision issued at 14:01 on 06 de noviembre de 2024, the applicant was ordered to provide certification of the legal representation (personería jurídica) of the respondent Association.
  3. 3At 13:12 on 11 de noviembre de 2024, the applicant complied with the order.
  4. 4By decision issued at 09:21 on 13 de noviembre de 2024, this application was admitted for processing.
  5. 5Georgina Garro Mora, in her capacity as Deputy Manager for Delegated Systems Management of the Instituto Costarricense de Acueductos y Alcantarillado, reports under oath that, according to the person responsible for Región Chorotega: “(…) AyA issued the referenced official letter; the applicant appeared at the Regional Office of Community Water-Supply Systems of Región Chorotega on 9 de octubre de 2024 and submitted the letter included in Anexo 1. In response to that letter, on 9 de octubre, an email was sent asking him to explain his legitimate interest (interés legítimo) in making the request (Anexo 2). On 10 de octubre, an email was received from Nombre01 explaining why he required that document, and on 14 de octubre, a response was sent by email (Anexo 3), together with official letters GSD-UEN-GAR-2020-00668 and GSD-UEN-GAR-2020-0066 […]”; the email address to which he sent it was ...02, whereas Mr.Barboza’s email address is ...01, meaning that it was not that he failed to respond, but rather that the email was misdirected.” She states that the Asociación Administradora del Acueducto Rural de San Juan de Santa Cruz has not signed a delegation agreement (convenio de delegación) with AyA and therefore is not legally authorized to provide water-supply and/or sewerage services in the community. This is because it is implementing the administrative and operational improvements recommended by AyA so that the delegation agreement may be granted. Accordingly, interested persons must request certificates directly from Orac Región Chorotega, so that the Subgerencia de Gestión Sistemas Comunales may issue the appropriate administrative act (acto administrativo). She explains that the water-supply system operated by the Asada de San Juan de Santa Cruz is in a state of technical infeasibility or material impossibility (no factibilidad técnica o imposibilidad material), as stated in memorandum N° GSD-UEN-GAR-2020-00667 dated 21 de febrero del 2020, which recommended the construction of one or more storage tanks and a 72-hour pumping test during the dry season (January through April).She adds that, pursuant to Articles 59 and 61(f) of the Reglamento de ASADAS, these associations obtain their financial resources solely from revenue generated by the rates they charge and use that revenue to invest in the water-supply system. However, those rates have not been increased since 2017, even though system operating costs have risen throughout these years. Consequently, in most cases operators lack sufficient financial resources to implement these system improvements immediately or in the short term and must give priority to maintaining and operating existing services. For this reason, Article 46 of the Reglamento de Asadas authorizes an interested party to carry out the required improvements at their own expense, providing that, when necessary, a person interested in obtaining a new service may, at their own expense, make the improvements required to increase system capacity, in compliance with AyA’s technical regulations.She reasons that the applicant may wait until the respondent Asada, in accordance with its priorities, plans and implements the recommended improvements and conducts the pumping test or, alternatively, the applicant may carry them out at his own expense, in compliance with the provisions approved by AyA, with the understanding that this remains subject to the system’s water capacity (capacidad hídrica), as stated in the technical opinions issued by AyA. She clarifies that, in order to safeguard the rights of the persons currently supplied by the San Juan de Santa Cruz water-supply system, it has restricted the issuance of certificates of service availability and the provision of permanent services, so as to avoid adversely affecting current and future users. She adds that the only request the applicant has submitted to AyA was the one received on 09 de octubre del 2024, in which he requested a copy of the report concerning the water capacity of the Asada San Juan de Santa Cruz.His request was addressed on 14 de octubre of that same year by email, to which documents GSD-UEN-GAR-2020-00668 and GSD-UEN-GAR-2020-00667 were attached. She notes that, with respect to the request of 16 de octubre del 2024 addressed to Eng. Rafael Barboza, the evidence in the electronic case file shows that it was sent to an incorrect email address, because it was sent to ...02, whereas the correct address was ...01. This was an error attributable to the applicant, and it is therefore evident that he would not receive a response to his request because Eng. Barboza never received it. She further adds that the applicant has never requested a certificate of service availability from Orac Región Chorotega; therefore, as of this date, AyA has no pending request from him to address. She asserts that the applicant requests that “the refusal to issue water-availability certificates be annulled”; however, as explained above, AyA cannot take such action until the improvements recommended in memorandum N° GSD-UEN-GAR-2020-00667 are implemented in the San Juan de Santa Cruz water-supply system.Accordingly, granting the applicant’s request at this time would be unlawful, given the technical infeasibility of the San Juan de Santa Cruz water-supply system. She requests that this application be denied in its entirety because the Instituto has taken the required actions, responded to the applicant’s requests, and provided the necessary technical advice to the Asada de San Juan de Santa Cruz, and the institution she represents cannot act contrary to the regulations currently in force.
  6. 6Yanner Estiv Ramírez Aguilar, in his capacity as President of the Asociación Administradora del Acueducto Rural de San Juan de Santa Cruz, states that official letter GSD-UEN-GAR-2020-00667, issued by the Unidad de Gestión de Servicios de Acueductos Rurales on 21de febrero del año 2020, following a series of studies of the system’s water capacity, clearly and bindingly established, with no possibility of disobedience by this ASADA, that:

“1.- The water-supply system lacks sufficient system storage capacity.

  1. 2In the most recent yield test (aforo), conducted on 20 de enero de 2020, the well showed a

decrease in flow rate of 0.9 l/s compared with the registration data held by MINAE.

In light of the foregoing, the water-supply system lacks the technical and legal feasibility (factibilidad técnica y legal) required to provide service.

It is recommended that certificates of service availability or certificates of water capacity NOT be issued while the status of Water-Deficient Zone remains in effect.” It states that the Board of Directors represented by the undersigned took office and began exercising its functions pursuant to minutes number 27 of the assembly held on September 24, 2023, and, in response to the identified problem, undertook a series of procedures aimed at obtaining water-supply feasibility (viabilidad hídrica). It adds that the Liga de Agua conducted a technical study concluding that the ASADA has only one main source supplying the population of the community of San Juan. This was identified as the first weakness, since it creates a water deficit of 20.52 l/s. The other problem identified was insufficient storage, which currently amounts to only 34.7 cubic meters and is inadequate to serve the number of users and support population growth in the area, especially because the technical study highlights a storage deficit of 129.87 cubic meters.

It states that the analysis sets forth a series of recommendations that this newly constituted Board of Directors considers feasible and has committed to implementing in pursuit of that objective. It asserts that, at the request of the new Administrative Board, the Liga Comunal del Agua has prepared projections to resolve the problem, and another study—this time hydrogeological in nature—has been obtained to identify potential sites for drilling and groundwater extraction, as well as for installing a storage tank. The suggested storage tank alone would cost one hundred twenty-nine thousand dollars, funds that this ASADA does not have to carry out such works. It explains that pages 35-36 of that study contain site recommendations for drilling, which is why steps have been taken to acquire land on which the drilling works and storage-tank works may be constructed. The difficulty is that the ASADA lacks sufficient financial resources to carry out those works, and the Instituto Costarricense de Acueductos y Alcantarillados has not entered into an agreement with this ASADA to provide the technical and financial assistance necessary to complete the project.

Given its scale and significance, the project cannot be funded with the money each subscriber pays monthly under the water-consumption tariff. By virtue of the exclusive statutory mandate, responsibility is vested in the aforementioned Institute, which is responsible not only for financing but also for carrying the project forward, since an ASADA’s work is limited to administering and maintaining the service and collecting consumption charges, in order to ensure the timely fulfillment of a fundamental right: water of adequate quality and quantity for human consumption. It asserts that the existence of the problem is not being denied; rather, solutions have been proposed by this newly constituted Board of Directors since it responsibly assumed management of the ASADA. However, it is unacceptable to require an ASADA with limited income to undertake works capable of meeting a community’s sustained growth in water consumption or its projected needs over twenty-five years.

  1. 7The statutory requirements have been observed in the proceedings conducted.

Justice Salazar Alvarado drafts the opinion; and,

Whereas:

I.Subject matter of the amparo proceeding (recurso de amparo). The petitioner alleges that, since 2020, residents of San Juan de Santa Cruz de Guanacaste have faced difficulties in obtaining water-availability certificates (certificados de disponibilidad de agua). She further alleges that, on October 16, 2024, she reported the situation to the respondent Institute and has received no response.

II.Admissibility. Given its exceptional nature, an amparo proceeding against private-law entities requires first determining whether the matter falls within any of the circumstances that render it admissible and, if so, subsequently deciding whether it should be granted. In this regard, Article 57 of the Constitutional Jurisdiction Act (Ley de la Jurisdicción Constitucional) provides that an amparo proceeding against the acts or omissions of a private-law entity is admissible when such entities act or are required to act in the exercise of public functions or powers, or when they are, as a matter of law or fact, in a position of power against which ordinary judicial remedies are clearly insufficient or untimely to safeguard the fundamental rights or freedoms referred to in Article 2°, subsection a), of the same statute. In this particular case, those requirements are clearly satisfied with respect to the Associations Administering Water-Supply Systems (Asociaciones Administradoras de los Acueductos), because they are private-law entities in a position of power against which ordinary judicial remedies may be plainly unsuitable for protecting the petitioner’s fundamental rights. The proceeding must therefore be admitted for review by this Court.

III.Review of this case for infringement of Article 41 of the Political Constitution (Constitución Política). Before examining the merits—concerning the alleged violation of the right to prompt and proper administrative proceedings (procedimiento administrativo pronto y cumplido)—it must be clarified that, since Voto N° 2008-02545 of 8:55 hours on February 22, 2008, this Chamber has referred to the administrative litigation jurisdiction (jurisdicción contencioso administrativa), subject to certain exceptions, matters concerning whether the public administration complied with the time limits established by the General Public Administration Act (Ley General de la Administración Pública) (Articles 261 and 325) or by sector-specific statutes governing special administrative proceedings, either to conclude an administrative proceeding—initiated ex officio or at a party’s request—by issuing a final administrative act, or to decide the applicable administrative appeals. This proceeding presents precisely such an exception, because it concerns the failure to decide an application for potable-water availability. With that point clarified, the Court proceeds to decide the specific situation raised in this amparo proceeding.

IV.Proven facts. The following facts relevant to deciding this matter are deemed duly established, either because they have been proven or because the respondent failed to address them as ordered in the initial ruling:

  • a)By memorandum N°GSD-UEN-GAR-2020-00667, dated February 21, 2020, the respondent Institute issued the “Declaration of San Juan, Santa Cruz, Guanacaste as a Water-Deficient Area” (“Declaratoria de Zona Deficitaria, San Juan, Santa Cruz, Guanacaste”). It recommended that service-availability certificates (constancias de disponibilidad de servicio) not be issued for two reasons: first, the water-supply system lacks sufficient storage capacity; and second, the well showed a flow-rate decrease of 0,9 l/s in the latest measurement performed on January 20, 2020, compared with MINAE records. The water-supply system therefore lacks the technical and legal feasibility to grant services while the area remains classified as water-deficient. It is clarified that the water-deficient designation is temporary and contingent upon completion of the works required to address the area’s needs (see copy of the official letter).
  • b)In February 2020, the official in charge of Rural Water-Supply System Management at the respondent Institute recommended a series of improvements to resolve the problems affecting the San Juan de Santa Cruz water-supply system, including installing and/or constructing one or more storage tanks with a capacity of at least 78 m2 for the next 20 years, and conducting a pumping test lasting at least 24 hours during the dry season, between January and April, since those are the months of highest demand and lowest source production, in order to verify that the system provides the required quantity of water (see copy of memorandum N°GSD-UEN-GAR-2020-00667).
  • c)In May 2022 and June 2023, the Board of the Asociación Administradora del Acueducto informed the various applicants for water availability that the water-supply system had sufficient water capacity but lacked sufficient hydraulic capacity and therefore could not provide any potable-water service because of inadequate storage (see official letters).
  • d)The Asada de San Juan administers the San Juan de Santa Cruz water-supply system, currently has no valid Delegation Agreement (Convenio de Delegación), and has 353 subscribers (see attached documentation).
  • e)To date, the Asada de San Juan de Santa Cruz has not signed a delegation agreement with the respondent Institute. Applications for water-availability certificates must therefore be submitted to the Orac Región Chorotega so that the Subgerencia de Gestión Sistemas Comunales may issue them as appropriate (see report from the respondent authority).
  • f)On June 13, 2024, the petitioner applied to the respondent Asada for a water-availability certificate for a lot (see copy of the application bearing the acknowledgment-of-receipt stamp).
  • g)On June 24, 2024, the respondent Asada entered into a service agreement for the Topographic Survey and geographic information concerning the intake, transmission line, and distribution networks; pumping tests; hydraulic design, including pipe modeling and related matters; a Technical Study and assessment of the requested source intake; and proposed improvements to the system, including: a)-A technical-study report in accordance with the regulations established by A y A; b)-Design of plans and construction details; and c)-A detailed budget for the works, technical diagnosis, and improvements to the water-supply system (see copy of the agreement).
  • h)In July 2024, the contracted company delivered to the respondent Asada the “Hydrogeological Study for the Identification of Potential Groundwater Drilling and Extraction Sites” (“Estudio Hidrogeológico para la definición de Sitios Potenciales de Perforación y Captación de Agua Subterránea”) (see copy of the study).
  • i)On October 16, 2024, the petitioner sent an email to ...02, addressed to “Rafael Bardoza Topping,” the official in charge of ASADAS Management at the respondent Institute, reporting the Asada’s failure to comply with the structural plan (see copy of the email).
  • j)Rafael Barboza’s email address is ...01 (see report from the respondent authority).
  • k)To date, the petitioner has not requested a service-availability certificate from the Oficina Regional de Acueductos Comunales de Chorotega of the respondent Institute (see reports and attached documentation).
  • l)As of December 11, 2024, the person responsible for the requested technical study informed the Asada’s Board of Directors that it remained underway. Field-data collection concluded on June 19; the well was inspected with an endoscope on June 25; a hydrogeological study was conducted on July 9 to identify possible drilling locations for a new well; and, on September 28, during a meeting of the members’ assembly, the preliminary results of the technical study were presented. A 72-hour pumping test of the main well remains pending, awaiting the low-water season (estiaje) (see attached documentation).
  • m)On an unspecified date, the study prepared for the technical assessment of the Acueducto de San Juan de Santa Cruz was delivered to the respondent ASADA together with the relevant improvement recommendations and budget (see copy of the study).
  • n)Upon completion of all necessary stages of the Technical Study, it will be sent to the Oficina Regional de Acueductos Comunales de Chorotega for proper review and approval (see attached documentation).

V. Unproven facts. The following facts relevant to this decision are not deemed established

  • a)That the respondent Institute followed up on the improvements recommended for the proper operation of the water-supply system.
  • b)That the respondent Association disclosed the lack of funding needed to carry out the recommended infrastructure works.

VI.On the drinking-water service. Articles 21 and 50 of the Political Constitution, read together, establish the rights of persons to life, health, and a healthy and ecologically balanced environment, all of which are closely connected, since life, as the supreme constitutional value, requires special protection, because without life, the protection of all other fundamental rights would be of little use. Accordingly, life must be protected in all its dimensions—from the physical and mental perspectives and in relation to one’s surroundings—and it is precisely here that the importance of protecting the environment and natural resources arises, in order to promote people’s well-being. That well-being is achieved, among other means, through the protection and conservation of the quality and quantity of water resources (recursos hídricos), so that the water is safe for human consumption and thus protects people’s health, because, as a resource necessary for hygiene, food, and drinking, its contamination can cause serious harm to public health.

In this regard, the protection and conservation referred to must be provided by the State through the bodies designated for that purpose, which must adopt the measures necessary to guarantee access to that resource for all persons and ensure compliance with those measures. In this context, the right to water (derecho al agua) arises, which may be protected by this Constitutional Court through an amparo proceeding (recurso de amparo) (Judgment N° 2007-005482, at 14:39 hours on April 24, 2007, reiterated in N° 2021005089, at 09:15 hours on March 12, 2021).

VII.On prompt and effective justice (justicia pronta y cumplida). From the review of the record and the established facts, it has been shown that, on October 16, 2024, the appellant sent an email to ...02 reporting the Asada’s failure to comply with the structural plan recommended for the aqueduct; however, the respondent Institute did not deem it received because the correct address is ...01, rather than the one entered by the appellant. In this regard, the authorities of the respondent Institute have not violated any fundamental right of the appellant, and this claim in the appeal must therefore be denied.

VIII.On the right to drinking-water service. The Chamber further found that, since February 2020, the Head of Rural Aqueduct Management at the respondent Institute had recommended that the ASADA Board of Directors undertake a series of improvements to remedy the problems affecting the San Juan de Santa Cruz aqueduct, such as installing and/or constructing one or more higher-capacity storage tanks and conducting a pumping test during the dry season to verify that the aqueduct provides the necessary quantity of water. It was likewise established that the respondent Association has been denying requests for water-availability letters (cartas de disponibilidad de agua) because it is unable to provide drinking-water service due to insufficient storage capacity; although it has sufficient water-resource capacity, it lacks sufficient hydraulic capacity.

In light of the foregoing, the Chamber finds it striking that it was not until almost four years later, in June 2024, that the Association’s Administrative Board engaged services to prepare a technical assessment of the San Juan de Santa Cruz Aqueduct, including recommendations for improvements and a budget, which was delivered to it in December 2024. Throughout all these years, the appellant and the other residents have remained in a state of uncertainty and legal insecurity, awaiting completion of the infrastructure works required by the aqueduct in order to provide drinking-water service. This violates the fundamental right to the proper functioning of public services (buen funcionamiento de los servicios públicos), because the respondent Asada is responsible for an unjustified delay in complying with the recommendations made by the authorities of the Instituto Costarricense de Acueductos y Alcantarillados and in seeking a technical solution, which resulted in a clear and unlawful failure to provide service, contrary to the appellant’s constitutional rights to drinking water and the constitutional principles governing the operation of public services.

The respondent Institute also shares responsibility for that violation because, pursuant to the Ley Constitutiva del Instituto Costarricense de Acueductos y Alcantarillados, Ley N° 2726 of April 14, 1961, it is responsible for directing and overseeing all matters related to providing the inhabitants of the Republic with drinking-water service. Pursuant to Article 2(g) thereof, it may do so even by delegating the administration, operation, maintenance, and development of aqueducts and sewerage systems to organizations duly established for those purposes (administrative associations); however, the Institute remains the governing authority in this field. This is expressly provided in Article 3 of the Reglamento de las Asociaciones Administradoras de Sistemas de Acueductos y Alcantarillados comunales, Nº 42582-S-MINAE, which states as follows:

“Article 3.- Technical governance: AyA, as the technical governing authority for the provision of public aqueduct, sewerage, and/or wastewater-treatment services, shall carry out all activities relating to the control, oversight, supervision, evaluation, standardization, and sectoral planning of drinking-water and wastewater-treatment services, as well as the direction of the management undertaken by the ASADAS, since management of the system is entrusted to the ASADA by delegation from AyA.

The relationship between AyA and the ASADAS shall be based on the principles of social participation, collaboration, cooperation, adaptability or mutability of services, efficiency and effectiveness, supervision, control, evaluation, standardization, and sectoral planning of drinking-water and wastewater-treatment services, as well as the direction of the management undertaken by the ASADAS.” For their part, pursuant to the cited Reglamento, the sole and specific purposes of the ASADAS are to provide drinking-water supply and wastewater-treatment services, contribute to integrated water-resource management, and provide fire-hydrant service under special legislation. Therefore, under the Ley Constitutiva del Instituto Costarricense de Acueductos y Alcantarillados, exclusive authority over the supply of drinking water and the construction of aqueduct systems for that purpose rests with that Institution.

For this reason, the Institute is obligated to follow up on the recommendations made in February 2020 through memorandum GSD-UEN-GAR-2020-00667, which issued the “Declaratoria de Zona Deficitaria, San Juan, Santa Cruz, Guanacaste” and directed that no further certificates of service availability (constancias de disponibilidad de servicio) be issued for two reasons: 1) the aqueduct lacked sufficient storage capacity within its system; and 2) the well showed a decrease in flow of 0,9 l/s in the measurement taken on January 20, 2020. It should be noted that the stated water-deficient zone (zona deficitaria) is temporary in nature and contingent upon completion of the infrastructure works that would address the needs of the area and the aqueduct, and the Chamber has no evidence that the Institute took any action to ensure the proper operation of the services provided by the respondent ASADA.

Consequently, both the Institute and the respondent Asada have violated the principle of the proper functioning of public services and the right to drinking-water service by failing to promptly undertake joint actions to ensure completion of the technical studies and infrastructure works needed for the San Juan aqueduct to have greater water-storage capacity and improved water capture, thereby guaranteeing and supplying drinking water to the community. This is because both parties are obligated to ensure the continuity, quantity, and timely provision of the service, thereby upholding the right to health and the human right of access to drinking water and wastewater treatment.

As a corollary to the foregoing considerations, the appeal must be partially granted due to the violation of the appellant’s rights to health and life, and the respondent authorities must be ordered to take the corresponding actions, within their respective spheres of authority, to ensure that the improvements to the aqueduct are carried out.

IX. DOCUMENTATION SUBMITTED TO THE CASE FILE

The parties are hereby advised that, if they submitted any paper document, as well as objects or evidence contained on any additional electronic, computer, magnetic, optical, or telematic device, or produced using new technologies, they must retrieve them from the court office within a maximum period of thirty business days from notice of this judgment. Otherwise, any material not retrieved within that period shall be destroyed, pursuant to the “Reglamento sobre Expediente Electrónico ante el Poder Judicial,” approved by the Corte Plena at Session N° 27-11, of August 22, 2011, Article XXVI, and published in Boletín Judicial N° 19, of January 26, 2012, as well as the resolution approved by the Consejo Superior del Poder Judicial at Session N° 43-12, held on May 3, 2012, Article LXXXI.

Por tanto:

The appeal is partially granted, solely with respect to the violation of the principle of the proper functioning of public services and the right to drinking-water service. Georgina Garro Mora, in her capacity as Deputy Manager for the Management of Delegated Systems of the Instituto Costarricense de Acueductos y Alcantarillado, and Yanner Estiv Ramírez Aguilar, in his capacity as President of the Asociación Administradora del Acueducto Rural de San Juan de Santa Cruz, are ordered, within UN MES from notice of this judgment, to coordinate the corresponding actions so that the situation raised by the appellant is addressed and resolved, and to comply with the provisions of memorandum N°GSD-UEN-GAR-2020-00667, of February 21, 2020, “Declaratoria de Zona Deficitaria, San Juan, Santa Cruz, Guanacaste.” In addition, the infrastructure works agreed to be necessary for that purpose must be completed within DOCE MESES from notice of this judgment.

The foregoing is ordered with the warning that, pursuant to Article 71 of the Ley de la Jurisdicción Constitucional, anyone who receives an order issued in an amparo proceeding that must be complied with or enforced and fails to comply with or enforce it shall be subject to imprisonment for three months to two years, or a fine of twenty to sixty days, provided that the offense is not subject to a more severe penalty. The appeal is denied in all other respects. The Instituto Costarricense de Acueductos y Alcantarillados and the Asociación Administradora del Acueducto Rural de San Juan de Santa Cruz are ordered to pay the legal costs and damages caused by the facts underlying this ruling, the amounts of which shall be determined during enforcement of the judgment before the civil and administrative-litigation courts.- Fernando Castillo V.

President Fernando Cruz C.

Paul Rueda L.

Luis Fdo. Salazar A.

Jorge Araya G.

Anamari Garro V.

Ingrid Hess H.

CASE FILE N° 24-031181-0007-CO Telephone numbers: 2549-1500 / 800-SALA-4TA (800-7252-482). Fax: 2258-4157 / 2549-1633. Website: www.poder-judicial.go.cr/salaconstitucional. Address: (Dirección03). Filing of matters involving vulnerable groups: Dirección01, Dirección02

Secciones

Marcadores

Revisión del Documento SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas veinte minutos del treinta y uno de enero de dos mil veinticinco .

Recurso de amparo que se tramita en expediente número 24-031181-0007-CO, interpuesto por Nombre01, cédula de identidad NFP01, contra la ASOCIACIÓN ADMINISTRADORA DEL ACUEDUCTO RURAL DE SAN JUAN DE SANTA CRUZ y el INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS.

Resultando:

  1. 1Por escrito presentado en la Secretaría de la Sala y, agregado al expediente a las 15:38 horas del 05 de noviembre de 2024, el recurrente interpone recurso de amparo contra la ASOCIACIÓN ADMINISTRADORA DEL ACUEDUCTO RURAL DE SAN JUAN DE SANTA CRUZ y el INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS. Manifiesta, en resumen, que, desde el año 2020, los vecinos de San Juan de Santa Cruz de Guanacaste han enfrentado una seria problemática para obtener el certificado de disponibilidad de agua que es necesario para realizar los trámites para el visado de planos ante la Municipalidad de Santa Cruz, con el fin de optar por segregaciones de lotes, inscripciones en el Registro Público, así como solicitudes de bonos y permisos de construcción. Indica que, en su caso particular, adquirió un lote de 501 metros de la finca madre N° PRN01; pero no ha podido realizar la segregación debido a la falta del mencionado certificado.Menciona que, su intención era construir un pequeño taller para ejercer su profesión como técnico electricista; no obstante, hasta el momento, no ha logrado materializar ese proyecto, por lo que estima vulnerado sus derechos fundamentales de acceso al agua potable, al trabajo y a una vivienda digna. Explica que, según el memorando N°GSD-UEN-GAR-2020-00667, del 21 de febrero de 2020, relativo a la "Declaratoria de Zona Deficitaria, San Juan, Santa Cruz, Guanacaste", se recomienda no emitir constancias de disponibilidad de servicio señalando dos razones: primero, que el acueducto no cuenta con suficiente almacenamiento en su sistema, y segundo, que el pozo mostró una disminución de caudal de 0,9 l/s en la última medición realizada el 20 de enero de 2020, en comparación con registros del MINAE. Señala que, aunque se puso en funcionamiento un segundo pozo en el acueducto rural, han transcurrido cuatro años sin que se haya solucionado el problema de almacenamiento de agua.Acota que la administración del acueducto rural de San Juan afirma que, ellos no tienen recursos económicos para la inversión en tanques y tuberías y no existe respuesta alguna del Instituto Costarricense de Acueductos y Alcantarillados. Recalca que el acceso al agua potable es un derecho humano fundamental, derivado del derecho a la vida y a un ambiente sano y para garantizar ese derecho, el Estado establece que el AyA puede aprovechar, utilizar, regular y supervisar las aguas de dominio público en todo el territorio nacional, en ejercicio de los derechos que el Estado tiene sobre estas, conforme a lo indicado en la Ley de Aguas. Refiere que, esa situación afecta a muchas personas de escasos recursos, quienes realizan grandes esfuerzos económicos para obtener un plano catastrado y poder acceder a un bono de vivienda. Explica que el 16 de octubre de 2024 envió un correo electrónico a ...02 dirigido a "Rafael Bardoza Topping", encargado de Gestión de ASADAS del AyA, solicitando su intervención en la problemática denunciada; sin embargo, acusa que al día en que acude en amparo no le ha brindado una respuesta.
  2. 2Mediante resolución de las 14:01 horas del 06 de noviembre de 2024, se previno al recurrente aportar certificación de personería jurídica de la Asociación recurrida.
  3. 3A las 13:12 horas el 11 de noviembre de 2024, el recurrente cumplió la prevención.
  4. 4Mediante resolución de las 09:21 horas del 13 de noviembre de 2024, se dio curso al presente recurso.
  5. 5Informa bajo juramento Georgina Garro Mora, en su condición de Sub-Gerente de Gestión de Sistemas Delegados del Instituto Costarricense de Acueductos y Alcantarillado que según lo indicado por el encargado de la Región Chorotega “(…) El AyA emitió el oficio referido, la parte recurrente se presentó a la Oficina Regional de Acueductos Comunales de la Región Chorotega el día 9 de octubre de 2024 y presentó la nota que se presenta en el anexo 1; ante esta nota, el día 9 de octubre se le escribió correo electrónico solicitando explicará el interés legítimo para la solicitud (Anexo 2); el día 10 de octubre se recibe correo del señor Nombre01 con la explicación del por qué requería dicho documento y el día 14 de octubre por medio de correo electrónico (Anexo 3) se respondió con los oficios GSD-UEN-GAR-2020-00668 y GSD-UEN-GAR-2020-0066 […] “ que el correo electrónico al que lo envió es ...02 y el correo electrónico del señor Barboza es ...01 por lo que, no es que no le haya respondido, es que fue mal dirigido”.Señala, que la Asociación Administradora del Acueducto Rural de San Juan de Santa Cruz no cuenta con convenio de delegación firmado con el AyA, por lo cual, no se encuentra legitimada para prestar el servicio de acueducto y/o alcantarillado en la comunidad, esto a que están implementando las mejoras administrativas y de operación que les recomendó el AyA, para poder otorgarles el convenio de delegación, por lo que, las personas interesadas deben de solicitar las constancias directamente en la Orac Región Chorotega, para que sea la Subgerencia de Gestión Sistemas Comunales la que emita el acto administrativo que corresponda. Explica, que el sistema de acueducto operado por la Asada de San Juan de Santa Cruz se encuentra en estado de no factibilidad técnica o imposibilidad material, según lo referido en el memorando N° GSD-UEN-GAR-2020-00667 de fecha 21 de febrero del 2020, donde se recomendó la construcción de uno o varios tanques de almacenamiento y una prueba de bombeo de 72 horas en época seca (meses de enero a abril).Agrega, que según lo disponen los artículos 59 y 61 inciso f) del Reglamento de ASADAS, estas asociaciones solo obtienen sus recursos económicos del ingreso por tarifas cobradas y con esto invierten en el sistema de acueducto, sin embargo, esas tarifas no se aumentan desde el año 2017, pese a que los costos de operación de los sistemas han subido en todos estos años, por lo cual, en la mayoría de los casos los operadores no cuentan con recursos económicos suficientes para la implementación inmediata o a corto plazo de estas mejoras en el sistema, debiendo dar prioridad al mantenimiento y operación de los servicios actuales, por esta razón es que el ordinal 46 del Reglamento de Asadas faculta al interesado para realizar a su costo las mejoras que sean requeridas, indicando que, cuando sea necesario, la persona que esté interesada en un nuevo servicio, podrá realizar a su costo las mejoras necesarias para aumentar la capacidad del sistema, ajustándose a la normativa técnica del AyA.Razona, que el actor tiene la posibilidad de esperar a que la Asada recurrida, dentro de su orden de prioridades, proyecte la implementación de las mejoras recomendadas y realice la prueba de bombeo o en su defecto, puede el recurrente llevarlos a cabo bajo su propio costo, cumpliendo con las disposiciones validadas por el AyA, en el entendido de que se encuentra sujeto a la capacidad hídrica del sistema, según lo señalado en los criterios técnicos emitidos por el AyA. Aclara que, en procura del resguardo de los derechos de las personas que actualmente se abastecen del sistema de acueducto de San Juan de Santa Cruz, ha limitado el otorgamiento de constancias de disponibilidad de servicios y servicios permanentes, con el fin de evitar afectaciones a los actuales y futuros usuarios. Añade que la única gestión que el recurrente ha hecho ante el AyA, fue la solicitud recibida el 09 de octubre del 2024, en la que pidió copia del informe relacionado con la capacidad hídrica de la Asada San Juan de Santa Cruz y se atendió su requerimiento el 14 de octubre del mismo año, por medio de correo electrónico, donde se adjuntaron los documentos GSD-UEN-GAR-2020-00668 y GSD-UEN-GAR-2020-00667.Acota, que la gestión del 16 de octubre del 2024, dirigida al Ing. Rafael Barboza, de la prueba visible en el expediente virtual se colige que la misma fue remitida a un correo electrónico que no corresponde, dado que, se envió a ...02 siendo el correcto ...01, lo cual resulta un yerro atribuible al recurrente, y por ende, es evidente que no iba a recibir respuesta a su petición, pues esta nunca fue recibida por el Ing. Barboza. Adiciona que, el recurrente nunca ha solicitado una constancia de disponibilidad de servicios ante la Orac Región Chorotega, por lo cual, a la fecha no hay gestión pendiente de atenderle por el AyA. Aduce, que el recurrente solicita “se anule el no otorgamiento de certificados de disponibilidad de agua”, sin embrago, según lo anteriormente expuesto, no es posible para el AyA llevar a cabo dicha acción hasta que se implementen en el sistema de acueducto de San Juan de Santa Cruz, las mejoras recomendadas en el memorando N° GSD-UEN-GAR-2020-00667, por lo que, en este momento otorgar a la parte actora lo peticionado, es incurrir en ilegalidad, dada la imposibilidad técnica con la que cuenta el sistema de acueducto de San Juan de Santa Cruz.Solicita se declare sin lugar el presente recurso en todos sus extremos, dado que, el Instituto ha llevado a cabo las actuaciones requeridas, ha respondido las gestiones del recurrente y ha brindado la asesoría técnica necesaria a la Asada de San Juan de Santa Cruz, no pudiendo mi representada ir en contra de la normativa vigente.
  6. 6Manifiesta Yanner Estiv Ramírez Aguilar, en su condición de Presidente de la Asociación Administradora del Acueducto Rural de San Juan de Santa Cruz que mediante oficio GSD-UEN-GAR-2020-00667, emitido por la Unidad de Gestión de Servicios de Acueductos Rurales, en fecha 21de febrero del año 2020, luego de la realización de una serie de estudios de la capacidad hídrica del sistema, se dispuso con claridad vinculante y, sin posibilidad de desobediencia por esta ASADA, que:

“1.- El acueducto no cuenta con suficiente almacenamiento del sistema

  1. 2El pozo en su último aforo realizado el 20 de enero de 2020, presenta una

disminución en el caudal de 0.9 l/s en comparación con los datos de registro del MINAE.

Tomando en cuenta lo anterior, el acueducto no cuenta con factibilidad técnica y legal para el otorgamiento del servicio.

Se recomienda NO brindar constancias de disponibilidad de servicio o constancias de capacidad hídrica, mientras se mantenga el estado de Zona Deficitaria”.

Acota, que la Junta Directiva que el suscrito representa, entró en posesión de su cargo y en ejercicio de sus funciones a partir del acta número 27 de asamblea celebrada el 24 de septiembre de 2023 y atendiendo el problema evidenciado, se avocó a la realización de una serie de trámites para alcanzar el objetivo de obtener viabilidad hídrica. Añade, que se realizó un estudio técnico por parte de la Liga de Agua, en el que se concluyó, que la ASADA cuenta con una única fuente principal, que se encarga de abastecer la población de la comunidad de San Juan, apreciando que se trata del primer aspecto débil detectado, dado que genera un déficit hídrico de 20.52 l/s, siendo el otro problema detectado, que la insuficiencia en el almacenamiento que actualmente es de tan solo 34.7 metros cúbicos, lo que es insuficiente para abastecer la cantidad de usuarios y, dar sostenibilidad al crecimiento poblacional de la zona, sobre todo, porque el estudio técnico resalta que hay un déficit de 129.87 metros cúbicos de almacenamiento.

Acota, que en dicho análisis, se establecen una serie de recomendaciones, que para esta nueva integración de junta directiva son acatables y, así se ha propuesto satisfacer para el logro del objetivo. Asegura, que la Liga Comunal del Agua, ante el pedido de la nueva junta de administración, ha efectuado proyecciones para solucionar el conflicto y, se ha obtenido otro estudio, esta vez de naturaleza hidrogeológica para definir posibles sitios potenciales de perforación y captación de agua subterránea, así como la instalación de un tanque de almacenamiento, siendo que solo el costo del tanque de almacenamiento sugerido es de ciento veintinueve mil dólares, dinero que esta ASADA no cuenta para llevar a cabo tales obras. Expone, que en las páginas 35-36 de dicho estudio se ha informado sobre recomendaciones de sitio para perforar, razón por la cual, se han efectuado gestiones para poder adquirir terrenos donde sea realizada la obra de la perforación y la obra del tanque de almacenamiento, con el inconveniente que. la ASADA no cuenta con recursos económicos suficientes para efectuar dichas obras y, el Instituto Costarricense de Acueductos y Alcantarillados no ha suscrito el convenio con la presente ASADA, para poder brindar asistencia técnica y económica que permita la realización de la obra, que por su magnitud y trascendencia, no puede ser satisfecha con el dinero que cada uno de los abonados cancela mensualmente por su tarifa de consumo de agua y que, por la reserva exclusiva de ley, se concede a dicho Instituto referido, a quien no solo le corresponde su financiamiento sino también la prosecución de la obra, dado que la labor de una ASADA se limita a la administración del servicio, su mantenimiento y recuperación de tarifas de consumo, en aras de brindar de manera puntualmente la satisfacción de un derecho fundamental, como resultar ser el agua de calidad y cantidad para su consumo humano.

Asegura, que no se está negando la existencia del problema, se están proponiendo las soluciones que esta nueva integración de junta directiva ha brindado desde que asume con responsabilidad la dirección de la ASADA; empero, no es de recibo de la ASADA de ingresos limitados deba realizar obras que satisfagan el crecimiento sostenido de consumo de agua de una comunidad o bien, su proyección a veinticinco años.

  1. 7En los procedimientos seguidos se ha observado las prescripciones legales

Redacta el Magistrado Salazar Alvarado; y,

Considerando:

I.Objeto del recurso. La recurrente alega que, desde al año 2020, los vecinos de San Juan de Santa Cruz de Guanacaste han enfrentado una problemática para obtener certificados de disponibilidad de agua. Además, que desde el 16 de octubre de 2024, denunció la situación al Instituto recurrido y no ha obtenido respuesta.

II.Sobre la admisibilidad. Por su excepcional naturaleza, el amparo contra sujetos de derecho privado exige comenzar por examinar si nos encontramos o no ante alguno de los supuestos que lo hacen admisible, para - posteriormente y en caso afirmativo-, dilucidar si es estimable o no. Sobre el particular, la Ley de la Jurisdicción Constitucional, en su artículo 57, estipula que el recurso de amparo contra las acciones u omisiones de un sujeto de Derecho Privado es admisible cuando éstos actúen o deban actuar en ejercicio de funciones o potestades públicas o, se encuentren, de derecho o de hecho, en una posición de poder frente a la cual los remedios jurisdiccionales comunes resulten claramente insuficientes o tardíos para garantizar los derechos o libertades fundamentales a que se refiere el artículo 2°, inciso a), del mismo cuerpo normativo. En el caso concreto, es claro el cumplimiento de esos presupuestos, en lo que respecta a las Asociaciones Administradoras de los Acueductos, toda vez que se trata de sujetos de Derecho Privado que están en una situación de poder, frente a la cual los remedios jurisdiccionales comunes pueden resultar francamente impropios para tutelar los derechos fundamentales del recurrente, por lo que el recurso se debe admitir para su análisis por parte de este Tribunal.

III.Sobre el conocimiento de este caso por lesión al artículo 41, de la Constitución Política. Previo a analizar el fondo del asunto -por la presunta violación del derecho a un procedimiento administrativo pronto y cumplido- debe aclararse que, a partir del Voto N° 2008-02545 de las 8:55 horas de 22 de febrero de 2008, esta Sala ha remitido a la jurisdicción contencioso administrativa -con algunas excepciones- aquellos asuntos en los que se discuta si la administración pública ha cumplido o no los plazos pautados por la Ley General de la Administración Pública (artículos 261 y 325) o las leyes sectoriales para los procedimientos administrativos especiales, para resolver por acto final un procedimiento administrativo -incoado de oficio o a instancia de parte- o conocer de los recursos administrativos procedentes. Precisamente, en este recurso, se plantea un supuesto de excepción pues se está ante la falta de resolución de una solicitud de disponibilidad de agua potable. Aclarado el punto, se entra a resolver, la situación concreta planteada en este amparo.

IV.Hechos probados. De importancia para la decisión de este asunto, se estiman como debidamente demostrados los siguientes hechos, sea porque así han sido acreditados o bien porque el recurrido haya omitido referirse a ellos según lo prevenido en el auto inicial:

  • a)Mediante memorando N°GSD-UEN-GAR-2020-00667, del 21 de febrero de 2020, el Instituto recurrido realizó la "Declaratoria de Zona Deficitaria, San Juan, Santa Cruz, Guanacaste", se recomendó no emitir constancias de disponibilidad de servicio por dos razones: primero, que el acueducto no cuenta con suficiente almacenamiento en su sistema, y segundo, que el pozo mostró una disminución de caudal de 0,9 l/s en la última medición realizada el 20 de enero de 2020, en comparación con registros del MINAE, por lo que el acueducto no cuenta con factibilidad técnica y legal para el otorgamiento de los servicios mientras se mantenga el estado de zona deficitaria. Se aclara que la zona deficitaria tiene una condición de temporalidad supeditada a la ejecución de las obras que solventen las necesidades de la zona (ver copia del oficio).
  • b)En el mes de febrero de 2020, el Encargado de la Gestión de Acueductos Rurales del Instituto recurrido recomendó una serie de mejoras para solventar la problemática del acueducto de San Juan de Santa Cruz, tales como instalar y/o construir uno o varios tanques de almacenamiento, con al menos una capacidad igual o mayor a 78 m2 para los próximos 20 años y realizar una prueba de bombeo de al menos 24 horas, en época seca que sea entre los meses de enero y abril, ya que son los meses de mayor demanda y menor producción de fuente para verificar que cumple con la cantidad de agua necesaria (ver copia del memorando N°GSD-UEN-GAR-2020-00667).
  • c)En mayo de 2022 y junio de 2023, la Junta de la Asociación Administradora del Acueducto informó a los diferentes solicitantes de disponibilidad de agua, que el acueducto contaba con capacidad hídrica más no hidráulica, por lo que no puede brindar ningún servicio de agua potable por falta de almacenamiento (ver oficios).
  • d)La Asada de San Juan administra el acueducto de San Juan de Santa Cruz, actualmente no posee el Convenio de Delegación vigente y cuenta con 353 abonados (ver documentación adjunta).
  • e)A la fecha, la Asada de San Juan de Santa Cruz no ha firmado convenio de delegación con el Instituto recurrido, por lo que las solicitudes de constancia de disponibilidad de agua deben de ser dirigidas a la Orac Región Chorotega, para que sea la Subgerencia de Gestión Sistemas Comunales quien las emita según corresponda (ver informe de la autoridad recurrida).
  • f)El 13 de junio de 2024, el recurrente solicitó ante la Asada recurrida constancia de disponibilidad de agua para un lote (ver copia de la gestión con sello de recibido).
  • g)El 24 de junio de 2024, la Asada recurrida suscribió un contrato de prestación de servicios para el Levantamiento Topográfico e información geográfica de la captación, línea de conducción y redes de distribución; pruebas de Bombeo; diseño hidráulico, en el cual, se contempla la modelación de tuberías y temas conexos; Estudio Técnico y evaluación de captación de la fuente solicitada, así como propuestas de mejoras al sistema, el cual incluye: a)-Informe de estudio técnico según la normativa establecida por el A y A; b)-Diseño de planos y detalles de la obra y c)-Presupuesto detallado de obras. el diagnostico técnico y mejoras en el acueducto (ver copia del contrato).
  • h)En julio de 2024, la empresa contratada entregó a la Asada accionada el “Estudio Hidrogeológico para la definición de Sitios Potenciales de Perforación y Captación de Agua Subterránea.” (ver copia del estudio).
  • i)El 16 de octubre de 2024, el recurrente remitió un correo electrónico a ...02 dirigido a "Rafael Bardoza Topping", encargado de Gestión de ASADAS del Instituto recurrido, una gestión en la que denunció el incumplimiento por parte de la Asada del plan estructural (ver copia del correo electrónico).
  • j)El correo electrónico de Rafael Barboza es ...01 (ver informe de la autoridad recurrida).
  • k)A la fecha, el recurrente no ha solicitado una constancia de disponibilidad de servicios a la Oficina Regional de Acueductos Comunales de Chorotega del Instituto recurrido (ver informes y documentación adjunta).
  • l)Al 11 de diciembre de 2024, el encargado del estudio técnico solicitado comunicó a la Junta Directiva de la Asada que se encontraba en proceso de ejecución, siendo que la recolección de datos de campo finalizó el 19 de junio, la inspección del pozo mediante un endoscopio se realizó el 25 de junio; el 9 de julio se llevó a cabo un estudio hidrogeológico para determinar posibles puntos de perforación de un nuevo pozo; el 28 de septiembre, durante una sesión de la asamblea de asociados, se presentaron los resultados preliminares del estudio técnico siendo que está pendiente la realización de una prueba de bombeo de 72 horas en el pozo principal, esperando la temporada de estiaje (ver documentación adjunta).
  • m)Sin precisar fecha, el estudio elaborado para la evaluación técnica del Acueducto de San Juan de Santa Cruz, le fue entregado a la ASADA accionada junto con las recomendaciones de mejoras pertinentes y presupuesto (ver copia del estudio) n) Al finalizar todas las etapas necesarias del Estudio Técnico le será enviado a la Oficina Regional de Acueductos Comunales de Chorotega para su debido análisis y aprobación (ver documentación adjunta).

V. Hechos no probados. No se estiman demostrados los siguientes hechos de relevancia para esta resolución

  • a)Que el Instituto recurrido haya dado seguimiento a las mejoras recomendadas para el correcto funcionamiento del acueducto.
  • b)Que la Asociación recurrida haya puesto en conocimiento la falta de presupuesto para poder realizar las obras de infraestructura recomendadas.

VI.Sobre el servicio de agua potable. De la relación de los artículos 21 y 50, de la Constitución Política, se desprenden el derecho de las personas a la vida, la salud y a un medio ambiente sano y ecológicamente equilibrado, los cuales se encuentran íntimamente ligados, toda vez, que la vida como valor supremo de la constitución, implica una especial protección, pues sin vida, poca utilidad tendría la protección de los demás derechos fundamentales. Así las cosas, la vida debe ser protegida en todas sus vertientes, desde un aspecto físico, mental y de entorno, y es precisamente ahí donde surge la importancia en proteger el ambiente y los recursos naturales, a fin de procurar el bienestar de las personas. Ahora bien, entre otros aspectos, ese bienestar se logra, a través de la protección y conservación de la calidad y cantidad de los recursos hídricos, para que ésta sea potable para el consumo humano y de esta forma proteger la salud de las personas, ya que al tratarse de un recurso necesario para la higiene, alimento y bebida, su contaminación puede producir graves perjuicios en la salud pública.

En ese sentido, la protección y conservación a la que se hace referencia debe ser brindada por el Estado a través de los órganos que designe al efecto, los cuales deberán adoptar las medidas necesarias para garantizar el acceso de ese recurso a todas las personas, así como velar por el cumplimiento de éstas. Bajo esa tesitura, surge el derecho al agua, el cual puede ser protegido por este Tribunal Constitucional mediante la vía de amparo (Sentencia N° 2007-005482, de las 14:39 horas del 24 de abril del 2007, reiterada en la N° 2021005089, de las 09:15 horas del 12 de marzo de 2021).

VII.Sobre una justicia pronta y cumplida. Del estudio de los autos, y a partir de la relación de hechos probados, se tiene por acreditado, que efectivamente el 16 de octubre de 2024, el recurrente remitió un correo electrónico a ...02 en el que denunció el incumplimiento por parte de la Asada del plan estructural recomendado para el acueducto; sin embargo, el mismo no se tuvo por recibido por parte del Instituto recurrido, dado que la dirección correcta es ...01 y no como la consignó el recurrente. En ese sentido, las autoridades del Instituto recurrido no han lesionado derecho fundamental alguno al recurrente y lo procedente es declarar sin lugar este extremo del recuso.

VIII.Sobre el derecho al servicio de agua potable. Por otra parte, la Sala constató que desde el mes de febrero de 2020, el Encargado de la Gestión de Acueductos Rurales del Instituto recurrido recomendó a la Junta Directiva de la ASADA efectuar una serie de mejoras para solventar la problemática del acueducto de San Juan de Santa Cruz, tales como instalar y/o construir uno o varios tanques de almacenamiento, con mayor capacidad, realizar una prueba de bombeo en época seca, para verificar que cumple con la cantidad de agua necesaria. Asimismo, se verificó que la Asociación recurrida ha estado denegando las solicitudes de cartas de disponibilidad de agua, ya que no les es factible brindar el servicio de agua potable por falta de almacenamiento, pues si bien se cuenta con capacidad hídrica no se tiene la hidráulica.

De lo expuesto, llama la atención a la Sala, que fue hasta casi cuatro años después, o sea en junio de 2024, que la Junta Administradora de la Asociación contrató los servicios para la elaboración de una evaluación técnica del Acueducto de San Juan de Santa Cruz, que incluye las recomendaciones de mejoras y presupuesto, mismo que les fue entregado en el mes de diciembre de 2024. Precisamente, el recurrente y los demás administrados durante todos estos años han permanecido en una situación de incertidumbre e inseguridad jurídica, a la espera que se efectúen las obras de infraestructura que requiere el acueducto para poder brindar el servicio de agua potable. Lo anterior, infringe el derecho fundamental al buen funcionamiento de los servicios públicos, pues existe un retardo injustificado atribuido a la Asada recurrida en acatar las recomendaciones efectuadas por las autoridades del Instituto Costarricense de Acueductos y Alcantarillados y buscar una solución técnica, lo cual se tradujo en una evidente e ilegítima falta de servicio, contraria a los derechos constitucionales del recurrente al agua potable y a los principios constitucionales que rigen el funcionamiento de los servicios públicos.

Por otra parte, el Instituto recurrido también es coparticipe de dicha lesión, ya que de conformidad con la Ley Constitutiva del Instituto Costarricense de Acueductos y Alcantarillados, Ley N° 2726 de 14 de abril de 1961, le corresponde dirigir y vigilar todo lo concerniente para proveer a los habitantes de la república de un servicio de agua potable y esto lo puede hacer, de conformidad con el artículo 2, inciso g), Ibidem, incluso, mediante la delegación, administración, operación, mantenimiento y desarrollo de los acueductos y alcantarillado, en organizaciones debidamente constituidas para tales efectos (asociaciones administradoras); sin embargo, el ente rector en la materia seguirá siendo el Instituto. Así lo dispone, expresamente, el artículo 3, del Reglamento de las Asociaciones Administradoras de Sistemas de Acueductos y Alcantarillados comunales, Nº 42582-S-MINAE, que señala lo siguiente:

“Artículo 3.- Rectoría técnica: El AyA como ente rector técnico en la prestación de los servicios públicos de acueducto, alcantarillado y/o saneamiento de las aguas residuales, ejercerá todas las actividades propias del control, vigilancia, fiscalización, evaluación, normalización, planificación sectorial de los servicios de agua potable y saneamiento de aguas residuales y dirección de la gestión que realizan las ASADAS, ya que la gestión del sistema corresponde a la ASADA por delegación del AyA.

La relación entre el AyA y las ASADAS estará basada en los principios de participación social, colaboración, cooperación, adaptabilidad o mutabilidad de los servicios, eficiencia y eficacia, fiscalización, control, evaluación, normalización, planificación sectorial de los servicios de agua potable y saneamiento de aguas residuales y dirección de la gestión que realizan las ASADAS”.

Por su parte, de conformidad con lo dispuesto en el Reglamento citado, las ASADAS tienen como únicos y específicos fines la prestación de los servicios de abastecimiento de agua potable y saneamiento de aguas residuales, contribuir en la gestión integrada del recurso hídrico y brindar el servicio de hidrantes por ley especial. Entonces, de conformidad con la Ley Constitutiva del Instituto Costarricense de Acueductos y Alcantarillados, la competencia privativa en materia de suministro de agua potable, así como la construcción de los sistemas de acueducto con ese propósito, le corresponde a esa Institución. Razón por la cual, el Instituto tiene la obligación de dar seguimiento a las recomendaciones efectuadas en febrero de 2020, mediante el memorando GSD-UEN-GAR-2020-00667, en el que se hizo la "Declaratoria de Zona Deficitaria, San Juan, Santa Cruz, Guanacaste", en las que se dispuso no emitir más constancias de disponibilidad de servicio por dos razones: 1) el acueducto no contaba con suficiente almacenamiento en su sistema; y 2) que el pozo mostró una disminución de caudal de 0,9 l/s en la medición realizada el 20 de enero de 2020.

Nótese, que la zona deficitaria indicada tiene la condición de temporalidad, y está supeditada a la ejecución de las obras de infraestructura que solventarían las necesidades de la zona y el acueducto, siendo que no le consta a la Sala que el Instituto haya realizado algún acto para garantizar el adecuado funcionamiento en la prestación de los servicios que brinda la ASADA recurrida.

De manera, que tanto el Instituto y la Asada recurrida han quebrantado el principio del buen funcionamiento de los servicios públicos y el derecho al servicio de agua potable, al no efectuar de manera célere las acciones conjuntas para garantizar la realización de los estudios técnicos y las obras de infraestructura para que el acueducto de San Juan cuente con mayor almacenamiento del líquido y mejor captación, para garantizar y dotar de agua potable a la comunidad. Lo anterior porque es obligación de ambas partes, velar por la continuidad, la cantidad y la oportunidad del servicio, afirmando el derecho a la salud y el derecho humano de acceso al agua potable y saneamiento de las aguas residuales.

Corolario de las consideraciones realizadas, se impone declarar parcialmente con lugar el recurso por infracción a los derechos de la recurrente a la salud y a la vida y ordenarles a las autoridades recurridas que ejecuten las acciones correspondientes, en sus respectivos ámbitos de competencia, para que se realicen las mejoras al acueducto.

IX. DOCUMENTACIÓN APORTADA AL EXPEDIENTE

Se previene a las partes que, de haber aportado algún documento en papel, así como objetos o pruebas contenidas en algún dispositivo adicional de carácter electrónico, informático, magnético, óptico, telemático o producido por nuevas tecnologías, estos deberán ser retirados del despacho en un plazo máximo de treinta días hábiles, contados a partir de la notificación de esta sentencia. De lo contrario, será destruido todo aquel material que no sea retirado dentro de este plazo, según lo dispuesto en el "Reglamento sobre Expediente Electrónico ante el Poder Judicial", aprobado por la Corte Plena en Sesión N° 27-11, del 22 de agosto del 2011, artículo XXVI y publicado en el Boletín Judicial N° 19, del 26 de enero del 2012, así como en el acuerdo aprobado por el Consejo Superior del Poder Judicial, en la Sesión N° 43-12, celebrada el 3 de mayo del 2012, artículo LXXXI.

Por tanto:

Se declara parcialmente con lugar el recurso, únicamente en cuanto a la violación del principio del buen funcionamiento de los servicios públicos y el derecho al servicio de agua potable. Se ordena a Georgina Garro Mora, en su condición de Subgerente de Gestión de Sistemas Delegados del Instituto Costarricense de Acueductos y Alcantarillado y a Yanner Estiv Ramírez Aguilar, en su condición de Presidente de la Asociación Administradora del Acueducto Rural de San Juan de Santa Cruz, que dentro del plazo de UN MES, a partir de la notificación de la presente sentencia, procedan a coordinar las acciones correspondientes para que se conozca y solucione la situación planteada por el recurrente, y proceder a cumplir con lo dispuesto en el memorando N°GSD-UEN-GAR-2020-00667, del 21 de febrero de 2020, "Declaratoria de Zona Deficitaria, San Juan, Santa Cruz, Guanacaste”. Además, las obras de infraestructura acordadas como necesarias para tal fin, deberán estar finalizadas dentro del plazo de DOCE MESES, a partir de la notificación de esta sentencia.

Lo anterior, bajo el apercibimiento que con base en lo establecido en el artículo 71, de la Ley de la Jurisdicción Constitucional, se impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo y no la cumpliere o no la hiciere cumplir, siempre que el delito no esté más gravemente penado. En los demás extremos se declara sin lugar el recurso. Se condena al Instituto Costarricense de Acueductos y Alcantarillados y a la Asociación Administradora del Acueducto Rural de San Juan de Santa Cruz el pago de las costas, daños y perjuicios causados con los hechos que sirven de base a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo civil y contencioso administrativo.- Fernando Castillo V.

Fernando Cruz C.

Paul Rueda L.

Luis Fdo. Salazar A.

Jorge Araya G.

Anamari Garro V.

Ingrid Hess H.

Document not found. Documento no encontrado.

Implementing decreesDecretos que afectan

    TopicsTemas

    • Water Law — Sources, Setbacks, and ConcessionsLey de Aguas — Fuentes, Retiros y Concesiones

    Concept anchorsAnclajes conceptuales

      Spanish key termsTérminos clave en español

      News & Updates Noticias y Actualizaciones

      All articles → Todos los artículos →

      Weekly Dispatch Boletín Semanal

      Field reporting and policy analysis from Costa Rica's forests. Reportajes y análisis de política desde los bosques de Costa Rica.

      ✓ Subscribed. ✓ Suscrito.

      One email per week. No spam. Unsubscribe in one click. Un correo por semana. Sin spam. Cancela en un clic.

      Or WhatsApp channelO canal de WhatsApp →
      Coalición Floresta © 2026 · All rights reserved © 2026 · Todos los derechos reservados

      Stay Informed Mantente Informado

      Conservation news and action alerts, straight from the field Noticias de conservación y alertas de acción, directo desde el campo

      Email Updates Actualizaciones por Correo

      Weekly updates, no spam Actualizaciones semanales, sin spam

      Successfully subscribed! ¡Suscripción exitosa!

      WhatsApp Channel Canal de WhatsApp

      Join to get instant updates on your phone Únete para recibir actualizaciones instantáneas en tu teléfono

      Join Channel Unirse al Canal
      Coalición Floresta Coalición Floresta © 2026 Coalición Floresta. All rights reserved. © 2026 Coalición Floresta. Todos los derechos reservados.
      🙏