← Environmental Law Center← Centro de Derecho Ambiental
Res. 01730-2024 Sala Constitucional · Sala Constitucional · 24/01/2024
OutcomeResultado
The disobedience claim is granted because 5 years have passed since the order without solving the drinking water problem, and the order of immediate compliance is reiterated under warning.Se acoge la gestión de desobediencia porque transcurrieron 5 años desde la orden sin haberse solucionado el problema de agua potable, y se reitera la orden de cumplimiento inmediato bajo apercibimiento.
SummaryResumen
The Constitutional Chamber hears a disobedience claim filed by a resident of Andrómeda III de Atenas against AyA and the Balsa de Atenas ASADA for failing to comply with ruling 2019-4056, which ordered them to solve the community's intermittent drinking water shortage within 18 months and in the meantime guarantee supply via tanker trucks. Five years later, despite AyA's report of progress on technical studies, environmental viability, social outreach and project design, the Chamber finds that the deadline expired in September 2020 and the situation remains unresolved, thus grants the disobedience claim. It reiterates the order of immediate compliance to both authorities, warning that administrative proceedings will be opened against them if they fail to comply, and applies Article 45 of the Constitutional Jurisdiction Law due to the ASADA's failure to submit its report.La Sala Constitucional conoce una gestión de desobediencia interpuesta por una vecina de Andrómeda III de Atenas contra el AyA y la ASADA de Balsa de Atenas, por el incumplimiento de lo ordenado en la sentencia 2019-4056 que dispuso solucionar en 18 meses el desabastecimiento de agua potable en la comunidad y garantizar mientras tanto el suministro mediante camiones cisterna. Cinco años después, pese a que el AyA informa haber avanzado en estudios técnicos, viabilidad ambiental, gestión social y diseño del proyecto, la Sala constata que el plazo venció en septiembre de 2020 y la situación no se ha resuelto, por lo que acoge la desobediencia. Reitera la orden de cumplimiento inmediato a ambas autoridades, bajo apercibimiento de abrir procedimiento administrativo en su contra, y aplica el artículo 45 de la Ley de la Jurisdicción Constitucional ante la omisión de la ASADA de rendir informe.
Key excerptExtracto clave
Thus, the Court considers that although the respondent authorities have taken the necessary actions to fully comply with what was ordered, given that in this case it has been shown that to comply with the claimed ruling the Administration has had to carry out the corresponding technical studies, land acquisition, environmental viability approval and social management of the project, an agreement with the National Technical University (UTN) for the pipeline that must be installed on UTN property, preparation of the project profile document to register it in the Public Investment Project Bank (BPIP) of MIDEPLAN, and that AyA even included in the 2024 budget a sum of 100 million colones to start the bidding process this year, receive offers and award the project in the same year and begin construction in 2025; the fact is that approximately 5 years have passed since this Court ordered a definitive solution to the intermittent drinking water supply problem affecting the claimant and the community of Andrómeda Tres Las Parcelas de Balsa de Atenas, without the situation having been resolved by the date of this filing, it being clear that the elapsed time is excessive and disproportionate, since the granted term expired in September 2020, hence the alleged disobedience is confirmed.Así las cosas, estima este Tribunal que pese a que las autoridades recurridas han realizado las acciones necesarias para cumplir a cabalidad con lo ordenado, siendo que en el caso concreto ha quedado evidenciado que para cumplir con la sentencia que se reclama, la Administración se ha visto en la necesidad de realizar los estudios técnicos correspondientes, adquisición de terrenos, aprobación de la Vialidad ambiental y gestión social del proyecto, convenio con la Universidad Técnica Nacional (UTN) para el paso de tubería que se tiene que instalar en la propiedad de la Universidad Técnica Nacional (UTN), elaboración del documento de Perfil del proyecto para poder inscribirlo en el Banco de Proyectos de Inversión Pública (BPIP) de MIDEPLAN y que incluso el AyA incluyó dentro del presupuesto del 2024, una suma de 100 millones de colones para iniciar el proceso de licitación en el presente año, recibir ofertas y adjudicar el proyecto en el mismo año e iniciar su construcción en el año 2025; lo cierto es que, han transcurrido aproximadamente 5 años desde que este Tribunal ordenó solucionar en forma definitiva, el problema de abastecimiento discontinuo de agua potable que afecta a la recurrente y a la comunidad de Andrómeda Tres Las Parcelas de Balsa de Atenas, sin que a la fecha de la interposición de la presente gestión se haya solventado la situación objeto de este recurso, siendo que, incluso el plazo que ha transcurrido es excesivo y desproporcionado, pues el término otorgado expiró desde el mes de setiembre de 2020, de ahí que, se verifica la desobediencia acusada.
Pull quotesCitas destacadas
"Se acoge la gestión de desobediencia planteada por la recurrente y se le reitera a […] que procedan de manera inmediata al cumplimiento de lo dispuesto en la sentencia No. 2019-4056 […] bajo la advertencia de solicitarse la apertura de un procedimiento administrativo en su contra su no lo hicieren."
"The disobedience claim filed by the petitioner is granted and […] are reiterated to immediately comply with the provisions of ruling No. 2019-4056 […] under the warning that an administrative proceeding will be sought against them should they fail to do so."
Por tanto
"Se acoge la gestión de desobediencia planteada por la recurrente y se le reitera a […] que procedan de manera inmediata al cumplimiento de lo dispuesto en la sentencia No. 2019-4056 […] bajo la advertencia de solicitarse la apertura de un procedimiento administrativo en su contra su no lo hicieren."
Por tanto
"lo cierto es que, han transcurrido aproximadamente 5 años desde que este Tribunal ordenó solucionar en forma definitiva, el problema de abastecimiento discontinuo de agua potable que afecta a la recurrente y a la comunidad de Andrómeda Tres Las Parcelas de Balsa de Atenas, sin que a la fecha de la interposición de la presente gestión se haya solventado la situación objeto de este recurso, siendo que, incluso el plazo que ha transcurrido es excesivo y desproporcionado, pues el término otorgado expiró desde el mes de setiembre de 2020, de ahí que, se verifica la desobediencia acusada."
"The fact is that approximately 5 years have passed since this Court ordered a definitive solution to the intermittent drinking water supply problem affecting the claimant and the community of Andrómeda Tres Las Parcelas de Balsa de Atenas, without the situation having been resolved by the date of this filing, it being clear that the elapsed time is excessive and disproportionate, since the granted term expired in September 2020, hence the alleged disobedience is confirmed."
Considerando III
"lo cierto es que, han transcurrido aproximadamente 5 años desde que este Tribunal ordenó solucionar en forma definitiva, el problema de abastecimiento discontinuo de agua potable que afecta a la recurrente y a la comunidad de Andrómeda Tres Las Parcelas de Balsa de Atenas, sin que a la fecha de la interposición de la presente gestión se haya solventado la situación objeto de este recurso, siendo que, incluso el plazo que ha transcurrido es excesivo y desproporcionado, pues el término otorgado expiró desde el mes de setiembre de 2020, de ahí que, se verifica la desobediencia acusada."
Considerando III
"El artículo 45 de la Ley de la Jurisdicción Constitucional establece que en el caso de que el informe de no fuere rendido dentro del plazo correspondiente, se tendrán por ciertos los hechos y se entrará a resolver el amparo sin más trámite, salvo que el Tribunal estime necesaria alguna averiguación previa, todo sin perjuicio de las responsabilidades en que incurra el servidor omiso en el informe."
"Article 45 of the Constitutional Jurisdiction Law establishes that should the report not be submitted within the corresponding period, the facts shall be deemed true and the amparo shall be decided without further proceedings, unless the Court deems a prior inquiry necessary, all without prejudice to the liabilities incurred by the official who failed to submit the report."
Considerando II
"El artículo 45 de la Ley de la Jurisdicción Constitucional establece que en el caso de que el informe de no fuere rendido dentro del plazo correspondiente, se tendrán por ciertos los hechos y se entrará a resolver el amparo sin más trámite, salvo que el Tribunal estime necesaria alguna averiguación previa, todo sin perjuicio de las responsabilidades en que incurra el servidor omiso en el informe."
Considerando II
Full documentDocumento completo
CONSTITUTIONAL CHAMBER Type of matter: Amparo appeal Rulings from the same expediente Ruling with protected data, in accordance with current regulations CONSTITUTIONAL CHAMBER OF THE SUPREME COURT OF JUSTICE. San José, at ten hours and fifty minutes on January twenty-fourth, two thousand twenty-four.
Proceedings for disobedience (Gestión de desobediencia) being processed in expediente number 18-19353-0007-CO, filed by [Name 001], identity card [Value 001]; against the ADMINISTRATIVE ASSOCIATION OF THE RURAL AQUEDUCT OF BALSA DE ATENAS (ASOCIACIÓN ADMINISTRADORA DEL ACUEDUCTO RURAL DE BALSA DE ATENAS) AND THE COSTA RICAN INSTITUTE OF AQUEDUCTS AND SEWERS (INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS).
WHEREAS:
Drafted by Judge Hess Herrera; and,
Considering:
In this case, the petitioner's claim must be upheld. In ruling No. 2019-4056 at 09:30 hours on March 8, 2019, this Court ordered in what is relevant: “The appeal is partially granted with respect to the Costa Rican Institute of Aqueducts and Sewers, as well as the Administrative Association of the Rural Aqueduct of Balsa de Atenas. Consequently, Annette Henchoz Castro, in her capacity as Deputy General Manager of the Costa Rican Institute of Aqueducts and Sewers, and María Teresa González Porras, in her capacity as President of the Administrative Association of the Rural Aqueduct of Balsa de Atenas, or whoever holds those positions in their stead, are ordered, within the non-extendable period of 18 months counted from the notification of this ruling, to adopt, within the framework of their competencies, the necessary measures, and to carry out the legal and administrative actions that are indispensable so that the problem of discontinuous supply of drinking water that affects the petitioner and the community of Andrómeda Tres Las Parcelas de Balsa de Atenas is definitively resolved.
Likewise, it is ordered that while the problem is comprehensively resolved, the Costa Rican Institute of Aqueducts and Sewers and the ASADA of Balsa de Atenas, in coordination with each other, must guarantee the constant supply of drinking water to that community through tanker trucks or another technically adequate method, if necessary.(…)” which was notified to the Costa Rican Institute of Aqueducts and Sewers on March 19, 2019, and to the Administrative Association of the Rural Aqueduct of Balsa de Atenas on March 28, 2019. Similarly, by ruling No. 2023028220 at 09:45 hours on November 3, 2023, this Chamber resolved as appropriate: “The proceedings for disobedience filed by the petitioner are accepted, and María Alejandra Mora Segura, General Manager of the Costa Rican Institute of Aqueducts and Sewers, and Efraín Ruiz González, President of the Board of Directors of the Administrative Association of the Rural Aqueduct of Balsa de Atenas, or whoever exercises said positions in their stead, are reiterated to proceed immediately to comply with what was ordered in ruling No. 2019-4056 at 09:30 hours on March 8, 2019, under the warning that the opening of an administrative proceeding against them will be requested if they fail to do so. Regarding the request for an extension of the deadline, the filed petition is dismissed.” (sic).
Article 45 of the Law of Constitutional Jurisdiction establishes that in the event that the report is not rendered within the corresponding period, the facts shall be taken as true, and the amparo shall be resolved without further procedure, unless the Court deems a prior investigation necessary, all without prejudice to the liabilities incurred by the servant who fails to submit the report. In the specific case, this Chamber verifies that the resolution at 11:28 a.m. on January 5, 2024, which gave course to this disobedience proceeding, was notified to the President of the Administrative Association of the Rural Aqueduct of Balsa de Atenas, at the email address registered with this Court for such purposes, on January 8, 2023. Furthermore, the respondent authority omitted to render the requested report.
- Now, in the present proceedings for disobedience, the petitioner states that, as of the filing date of the present proceeding, the execution of the ordered works has not been carried out. For their part, the respondent authorities from AyA report under oath that during the last year, they have continued with all the necessary procedures to meet the viabilities, social management to keep the community informed of the project's progress, completion of the design and terms of reference, and they are working on the preparation of the tender specifications for its publication, and in parallel, the registration of the project in the MIDEPLAN Project Bank, which is an indispensable requirement to invest in the project. Finally, they report that regarding the project financing, AyA included within the 2024 budget a sum of 100 million colones to start the bidding process this year, receive offers, and award the project in the same year, and start its construction in 2025.
For its part, given the omission of the respondent ASADA and in application of Article 45 of the Law of Constitutional Jurisdiction \"… in the event that the report is not rendered within the corresponding period, the facts shall be taken as true, and the amparo shall be resolved without further procedure, unless the Court deems a prior investigation necessary, all without prejudice to the liabilities incurred by the servant who fails to submit the report…\" the petitioner's accusations are deemed accredited, that is, non-compliance with what was ordered in rulings No. 2019004056 at 09:30 hours on March 8, 2019, and No. 2023028220 at 09:45 hours on November 3, 2023.
Thus, this Court considers that even though the respondent authorities have carried out the necessary actions to fully comply with what was ordered, given that in this specific case it has been evidenced that to comply with the ruling claimed, the Administration has been forced to conduct the corresponding technical studies, land acquisition, approval of the environmental viability (Vialidad ambiental) and social management of the project, an agreement with the Universidad Técnica Nacional (UTN) for the pipeline section that must be installed on the property of the Universidad Técnica Nacional (UTN), preparation of the project Profile document to register it with the MIDEPLAN Public Investment Project Bank (BPIP), and that even AyA included within the 2024 budget a sum of 100 million colones to start the bidding process this year, receive offers, and award the project in the same year, and start its construction in 2025; the fact is that approximately 5 years have elapsed since this Court ordered a definitive resolution to the problem of discontinuous drinking water supply affecting the petitioner and the community of Andrómeda Tres Las Parcelas de Balsa de Atenas, without the situation that is the subject of this appeal having been resolved as of the filing date of the present proceeding, given that the elapsed time is even excessive and disproportionate, since the granted period expired in September 2020, hence, the alleged disobedience is verified.
Consequently, María Alejandra Mora Segura, General Manager of the Costa Rican Institute of Aqueducts and Sewers, and Efraín Ruiz González, President of the Board of Directors of the Administrative Association of the Rural Aqueduct of Balsa de Atenas, or whoever exercises said positions in their stead, are reiterated to proceed immediately to comply with what was ordered in rulings No. 2019-4056 at 09:30 hours on March 8, 2019, and No. 2023028220 at 09:45 hours on November 3, 2023, under the warning that the opening of an administrative proceeding against them will be requested if they fail to do so.
This Chamber must warn the petitioner that if any document has been provided, whether on paper, as well as objects or evidence backed by any additional device, or by electronic, computer, magnetic, optical, telematic means, or produced by new technologies, these must be removed from the office within a period of 30 business days after receiving notification of this ruling; otherwise, everything will be destroyed in accordance with the provisions of the “Reglamento sobre Expediente Electrónico ante el Poder Judicial”, approved by the Corte Plena in session N° 27-11 of August 22, 2011, article XXVI, and published in Judicial Bulletin number 19 of January 26, 2012, as well as the agreement approved by the Consejo Superior del Poder Judicial, in session N° 43-12 held on May 3, 2012, article LXXXI.
THEREFORE:
María Alejandra Mora Segura, General Manager of the Costa Rican Institute of Aqueducts and Sewers, and Efraín Ruiz González, President of the Board of Directors of the Administrative Association of the Rural Aqueduct of Balsa de Atenas, or whoever exercises said positions in their stead, are reiterated to proceed immediately to comply with what was ordered in rulings No. 2019-4056 at 09:30 hours on March 8, 2019, and No. 2023028220 at 09:45 hours on November 3, 2023, under the warning that the opening of an administrative proceeding against them will be requested if they fail to do so.
Fernando Castillo V.
President Fernando Cruz C.
Paul Rueda L.
Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Ingrid Hess H.
Telephones: 2549-1500 / 800-SALA-4TA (800-7252-482). Fax: 2295-3712 / 2549-1633. Email address: www.poder-judicial.go.cr/salaconstitucional. Address: (Sabana Sur, Calle Morenos, 100 mts. South of the Perpetuo Socorro Church). Reception of matters from vulnerable groups: Edificio Corte Suprema de Justicia, San José, Catedral District, González Lahmann neighborhood, streets 19 and 21, avenues 8 and 6.
It is a faithful copy of the original - Taken from Nexus.PJ on: 05-08-2026 15:09:53.
Sentencias del mismo expediente Sentencia con datos protegidos, de conformidad con la normativa vigente SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las diez horas cincuenta minutos del veinticuatro de enero de dos mil veinticuatro .
Gestión de desobediencia que se tramita en el expediente número 18-19353-0007-CO interpuesto por [Nombre 001], cédula de identidad [Valor 001]; contra la ASOCIACIÓN ADMINISTRADORA DEL ACUEDUCTO RURAL DE BALSA DE ATENAS Y EL INSTITUTO COSTARRICENSE DE ACUEDUCTOS Y ALCANTARILLADOS.
RESULTANDO:
Redacta la Magistrada Hess Herrera; y,
Considerando:
En la especie, el reclamo de la gestionante debe ser acogido. En la sentencia No. 2019-4056 de las 09:30 horas del 8 de marzo de 2019, este Tribunal dispuso en lo que interesa: “Se declara parcialmente con lugar el recurso respecto del Instituto Costarricense de Acueductos y Alcantarillados así como de la Asociación Administradora del Acueducto Rural de Balsa de Atenas. En consecuencia, se ordena a Annette Henchoz Castro en su condición de Subgerente General del Instituto Costarricense de Acueductos y Alcantarillados y a María Teresa González Porras en su calidad de Presidenta de la Asociación Administradora del Acueducto Rural de Balsa de Atenas, o a quienes en su lugar ocupen esos cargos, que dentro del improrrogable plazo de 18 meses contado a partir de la notificación de esta sentencia, adopten dentro del marco de sus competencias las medidas que sean necesarias, y se realicen las acciones legales y administrativas que sean indispensables para que se solucione, en forma definitiva, el problema de abastecimiento discontinuo de agua potable que afecta a la recurrente y a la comunidad de Andrómeda Tres Las Parcelas de Balsa de Atenas.
De igual manera, se ordena que mientras se soluciona integralmente el problema, el Instituto Costarricense de Acueductos y Alcantarillados y la ASADA de Balsa de Atenas, de manera coordinada entre sí, deberán garantizar el abastecimiento constante de agua potable a esa comunidad a través de camiones cisterna u otra forma técnicamente adecuada, si fuere necesario.(…)” la cual fue notificada al Instituto Costarricense de Acueductos y Alcantarillados desde el 19 de marzo de 2019, y a la Asociación Administradora Acueducto Rural de Balsa de Atenas en fecha 28 de marzo de 2019. De igual forma, mediante sentencia No. 2023028220 de las 09:45 horas del 03 de noviembre de 2023, esta Cámara resolvió en lo conducente: “Se acoge la gestión de desobediencia planteada por la recurrente y se le reitera a María Alejandra Mora Segura, Gerente General del Instituto Costarricense de Acueductos y Alcantarillados y a Efraín Ruiz González, Presidente de la Junta Directiva de la Asociación Administradora Acueducto Rural de Balsa de Atenas, o a quienes en sus lugares ejerzan dichos cargos, que procedan de manera inmediata al cumplimiento de lo dispuesto en la sentencia No. 2019-4056 de las 09:30 horas del 8 de marzo de 2019, bajo la advertencia de solicitarse la apertura de un procedimiento administrativo en su contra su no lo hicieren. En cuanto a la solicitud de ampliación del plazo, no ha lugar a la gestión formulada.” (sic).
El artículo 45 de la Ley de la Jurisdicción Constitucional establece que en el caso de que el informe de no fuere rendido dentro del plazo correspondiente, se tendrán por ciertos los hechos y se entrará a resolver el amparo sin más trámite, salvo que el Tribunal estime necesaria alguna averiguación previa, todo sin perjuicio de las responsabilidades en que incurra el servidor omiso en el informe. En el caso concreto esta Sala verifica que la resolución de las 11:28 horas del 05 de enero de 2024, que diera curso a esta gestión de desobediencia, fue notificada al Presidente de la Asociación Administradora del Acueducto Rural de Balsa de Atenas, en el correo electrónico registrado en este Tribunal para tales efectos, en fecha 08 de enero de 2023. Además, que la autoridad accionada, omitió rendir el informe solicitado.
- Ahora bien, en la presente gestión de desobediencia la recurrente refiere que, a la fecha de interposición de la presente gestión, la ejecución de los trabajos ordenados no se ha realizado. Por su parte, las autoridades recurridas del AyA informan bajo juramento durante el último año han continuado con todos los trámites necesarios para cumplir con las viabilidades, gestión social para mantener a la comunidad informada del avance del proyecto, conclusión de los diseño y términos de referencia y se trabaja en la elaboración del cartel, para su publicación y paralelamente la inscripción del proyecto en el Banco del Proyecto de MIDEPLAN, el cual es un requisito indispensable para poder invertir en el proyecto. Finalmente, refieren que en cuanto al financiamiento del proyecto, el AyA incluyó dentro del presupuesto del 2024, una suma de 100 millones de colones para iniciar el proceso de licitación en el presente año, recibir ofertas y adjudicar el proyecto en el mismo año e iniciar su construcción en el año 2025.
Por su parte, ante la omisión de la ASADA accionada y en aplicación del artículo 45 de la Ley de la Jurisdicción Constitucional "…en el caso de que el informe de no fuere rendido dentro del plazo correspondiente, se tendrán por ciertos los hechos y se entrará a resolver el amparo sin más trámite, salvo que el Tribunal estime necesaria alguna averiguación previa, todo sin perjuicio de las responsabilidades en que incurra el servidor omiso en el informe…" se tienen por acreditadas las acusaciones del recurrente, a decir, el incumplimiento de lo ordenado en las sentencias No. 2019004056 de las 09:30 horas del 08 de marzo de 2019 y No. 2023028220 de las 09:45 horas del 03 de noviembre de 2023.
Así las cosas, estima este Tribunal que pese a que las autoridades recurridas han realizado las acciones necesarias para cumplir a cabalidad con lo ordenado, siendo que en el caso concreto ha quedado evidenciado que para cumplir con la sentencia que se reclama, la Administración se ha visto en la necesidad de realizar los estudios técnicos correspondientes, adquisición de terrenos, aprobación de la Vialidad ambiental y gestión social del proyecto, convenio con la Universidad Técnica Nacional (UTN) para el paso de tubería que se tiene que instalar en la propiedad de la Universidad Técnica Nacional (UTN), elaboración del documento de Perfil del proyecto para poder inscribirlo en el Banco de Proyectos de Inversión Pública (BPIP) de MIDEPLAN y que incluso el AyA incluyó dentro del presupuesto del 2024, una suma de 100 millones de colones para iniciar el proceso de licitación en el presente año, recibir ofertas y adjudicar el proyecto en el mismo año e iniciar su construcción en el año 2025; lo cierto es que, han transcurrido aproximadamente 5 años desde que este Tribunal ordenó solucionar en forma definitiva, el problema de abastecimiento discontinuo de agua potable que afecta a la recurrente y a la comunidad de Andrómeda Tres Las Parcelas de Balsa de Atenas, sin que a la fecha de la interposición de la presente gestión se haya solventado la situación objeto de este recurso, siendo que, incluso el plazo que ha transcurrido es excesivo y desproporcionado, pues el término otorgado expiró desde el mes de setiembre de 2020, de ahí que, se verifica la desobediencia acusada.
En consecuencia, se le reitera a María Alejandra Mora Segura, Gerente General del Instituto Costarricense de Acueductos y Alcantarillados y a Efraín Ruiz González, Presidente de la Junta Directiva de la Asociación Administradora Acueducto Rural de Balsa de Atenas, o a quienes en sus lugares ejerzan dichos cargos, que procedan de manera inmediata al cumplimiento de lo dispuesto en las sentencias No. 2019-4056 de las 09:30 horas del 8 de marzo de 2019 y No. 2023028220 de las 09:45 horas del 03 de noviembre de 2023, bajo la advertencia de solicitarse la apertura de un procedimiento administrativo en su contra su no lo hicieren.
Debe prevenir esta Sala a la parte recurrente que de haber aportado algún documento, ya sea en papel, así como objetos o pruebas respaldadas por medio de cualquier dispositivo adicional, o por medio de soporte electrónico, informático, magnético, óptico, telemático o producido por nuevas tecnologías, estos deberán ser retirados del despacho, en un plazo de 30 días hábiles, después de recibida la notificación de esta sentencia, de lo contrario todo ello será destruido de conformidad con lo establecido en el "Reglamento sobre Expediente Electrónico ante el Poder Judicial", aprobado por la Corte Plena en sesión N° 27-11 del 22 de agosto de 2011, artículo XXVI y publicado en Boletín Judicial número 19 del 26 de enero de 2012, así como en el acuerdo aprobado por el Consejo Superior del Poder Judicial, en la sesión N° 43-12 celebrada el 3 de mayo de 2012, artículo LXXXI.
POR TANTO:
Se le reitera a María Alejandra Mora Segura, Gerente General del Instituto Costarricense de Acueductos y Alcantarillados y a Efraín Ruiz González, Presidente de la Junta Directiva de la Asociación Administradora Acueducto Rural de Balsa de Atenas, o a quienes en sus lugares ejerzan dichos cargos, que procedan de manera inmediata al cumplimiento de lo dispuesto en las sentencias No. 2019-4056 de las 09:30 horas del 8 de marzo de 2019 y No. 2023028220 de las 09:45 horas del 03 de noviembre de 2023, bajo la advertencia de solicitarse la apertura de un procedimiento administrativo en su contra su no lo hicieren.
Fernando Castillo V.
Fernando Cruz C.
Paul Rueda L.
Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Ingrid Hess H.