Res. 19545-2024 Sala Constitucional · Sala Constitucional · 12/07/2024
OutcomeResultado
The Chamber ordered the Municipality of Parrita to implement the Brisa Bonita stormwater drainage plan within twelve months, report to the claimant, and bear the resulting costs, damages, and losses.La Sala ordenó a la Municipalidad de Parrita ejecutar en doce meses el plan de canalización de aguas pluviales de Brisa Bonita, informar al recurrente y responder por las costas, daños y perjuicios.
SummaryResumen
The Constitutional Chamber granted an amparo action against the Municipality of Parrita concerning persistent stormwater and wastewater accumulation in the Brisa Bonita community. Reported repeatedly since 2016, the problem caused flooding in the claimant’s home, health hazards, foul odors, and difficulty leaving for medical care. Although the municipality had inspected the area, installed survey monuments, and formulated a comprehensive sewer and drainage project, it had not implemented a solution. The Chamber acknowledged that the flooding had a climatic component but concluded that its effects were aggravated by inadequate stormwater channeling, infrastructure for which the municipal government was responsible. The municipality’s prolonged delay, despite its longstanding knowledge of the problem and the resident’s repeated requests, warranted constitutional relief. The Chamber ordered the relevant municipal authorities to coordinate and implement the drainage plan within twelve months, report the measures taken to the claimant, and pay the costs, damages, and losses arising from the violations.La Sala Constitucional declaró con lugar el recurso de amparo presentado contra la Municipalidad de Parrita por la persistente acumulación de aguas pluviales y residuales en el sector de Brisa Bonita. La situación, denunciada desde 2016, provocaba inundaciones en la vivienda del recurrente, riesgos sanitarios, malos olores y dificultades para desplazarse a recibir atención médica. Aunque el municipio había inspeccionado el sitio, construido mojones y formulado un proyecto integral de alcantarillado, la solución seguía sin ejecutarse. La Sala reconoció que las inundaciones tienen un componente climático, pero concluyó que sus efectos se agravaban por la falta de canalización adecuada, cuya atención correspondía a la corporación municipal. La prolongada demora, pese al conocimiento del problema y a las reiteradas solicitudes vecinales, justificó la tutela constitucional. Se ordenó coordinar y ejecutar en doce meses el plan municipal de drenaje y alcantarillado, informar al recurrente y pagar las costas, daños y perjuicios.
Key excerptExtracto clave
By the date on which the protected party came before this constitutional jurisdiction, the matter had not been resolved; indeed, the report submitted by Nombre20665 acknowledged the persistence of the situation affecting local residents. Although it results from climatic action, it is aggravated by the lack of adequate stormwater channeling, works that in this case are the responsibility of the municipal government. Accordingly, this Chamber must grant the action because it was established that, although the municipal authorities have long known about the problem and have implemented some measures to solve it, it persists to this day, with the added danger it poses to the safety of residents in the area and, specifically, to the claimant, who has requested municipal intervention on several occasions. From this perspective, the action must be granted as set forth in the operative part of this judgment.A la fecha en que el amparado acudió a esta jurisdicción constitucional, el asunto no ha sido solventado, siendo que, incluso, en el informe rendido por el Nombre20665 se reconoció la persistencia de la situación que afecta a los pobladores, el cual, si bien, es producto de la acción climática, se ve agravado por la falta de una adecuada canalización de las aguas pluviales, obras que corresponden a la corporación municipal en este caso. De ahí entonces que para esta Sala el asunto debe ser acogido pues quedó acreditado que, aunque es un problema conocido de larga data por las autoridades municipales y que se han implementado algunas medidas para solucionarlo, a la fecha, persiste con el agravante que representa para la seguridad de las personas pobladoras de la zona y, en específico el recurrente quien, en varias oportunidades, ha solicitado la intervención municipal. Desde esta perspectiva, el asunto debe ser estimado conforme se dirá en la parte dispositiva de esta sentencia.
Pull quotesCitas destacadas
"Se declara con lugar el recurso."
"The amparo action is granted."
Por tanto
"Se declara con lugar el recurso."
Por tanto
"Se ordena a Randall Rojas Piedra, Freddy Garro Arias y Luis Edmond Acuña Godínez, por su orden, presidente del Concejo Municipal, Nombre20665 y Director de la Unidad Técnica de Gestión Vial, todos de la Municipalidad de Parrita, o a quienes ocupen esos cargos, adoptar las instancias de coordinación necesarias para que, en el plazo de doce meses contado a partir de la notificación de esta sentencia, se ejecute el plan diseñado por la Unidad Técnica de Gestión Municipal de Parrita en relación con el problema de canalización de aguas pluviales en el sector de Brisa Bonita y se informe al recurrente lo actuado."
"Randall Rojas Piedra, Freddy Garro Arias, and Luis Edmond Acuña Godínez, respectively president of the Municipal Council, Nombre20665, and director of the Road Management Technical Unit, all of the Municipality of Parrita, or whoever holds those offices, are ordered to undertake the necessary coordination so that, within twelve months of notice of this judgment, the plan designed by the Municipality of Parrita’s Technical Management Unit concerning the stormwater channeling problem in Brisa Bonita is implemented and the claimant is informed of the actions taken."
Por tanto
"Se ordena a Randall Rojas Piedra, Freddy Garro Arias y Luis Edmond Acuña Godínez, por su orden, presidente del Concejo Municipal, Nombre20665 y Director de la Unidad Técnica de Gestión Vial, todos de la Municipalidad de Parrita, o a quienes ocupen esos cargos, adoptar las instancias de coordinación necesarias para que, en el plazo de doce meses contado a partir de la notificación de esta sentencia, se ejecute el plan diseñado por la Unidad Técnica de Gestión Municipal de Parrita en relación con el problema de canalización de aguas pluviales en el sector de Brisa Bonita y se informe al recurrente lo actuado."
Por tanto
"Se condena a la Municipalidad de Parrita al pago de las costas, daños y perjuicios causados con los hechos que sirven de base a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso administrativo."
"The Municipality of Parrita is ordered to pay the costs, damages, and losses caused by the events underlying this judgment, to be assessed during enforcement proceedings before the administrative courts."
Por tanto
"Se condena a la Municipalidad de Parrita al pago de las costas, daños y perjuicios causados con los hechos que sirven de base a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso administrativo."
Por tanto
Full documentDocumento completo
Document Review *230237990007CO* Decision No. 2024019545 CONSTITUTIONAL CHAMBER OF THE SUPREME COURT OF JUSTICE. San José, at nine twenty a.m. on July twelfth, two thousand twenty-four.
Amparo proceeding (recurso de amparo) filed by [Nombre62 001], identity card [Valor CED01], against the MUNICIPALIDAD DE PARRITA.
BACKGROUND
Justice Araya García drafts the opinion; and,
WHEREAS:
The petitioner, a resident of Brisa Bonita de Parrita who has a physical disability, alleges that, despite the requests for intervention submitted to the Municipalidad de Parrita to resolve the stormwater accumulation problem in that sector, as of the date on which he filed this amparo proceeding (recurso de amparo), no comprehensive solution had been provided. This particularly affects him because, during the rainy season, his home is flooded by water reaching up to 40 centimeters above floor level. He considers his fundamental rights to have been violated.
Before examining the merits of the matter—concerning the alleged violation of the right to prompt and proper proceedings—it must be clarified that, since Judgment No. 2008-02545 issued at 8:55 on 22 de febrero de 2008, this Chamber has referred to the Contentious-Administrative Jurisdiction (Jurisdicción Contencioso Administrativa), with certain exceptions, matters in which the issue is whether the Public Administration has complied with the time limits established by the Ley General de la Administración Pública (Articles 261 and 325) or by sector-specific laws governing special administrative proceedings, either to conclude an administrative proceeding—initiated ex officio or at the request of a party—by means of a final administrative act, or to hear the applicable administrative appeals.
This case presents an exception because it concerns an environmental problem caused by flooding in the sector, affecting the physical integrity of the petitioner—who has a disability—and the dwelling in which he resides. According to the allegations, to date, the municipality has not resolved within a reasonable period the requests for intervention submitted by the petitioner regarding this problem; accordingly, the Court proceeds to decide the specific situation raised in this amparo proceeding.
The following facts are deemed proven and relevant to the decision in this matter:
I spoke with Nombre67639 (sic) about the matter, and he told me that the Municipality discharged water onto unoccupied properties. This cannot be allowed to happen. It is not fair for them to discharge the water toward my property. I dug a ditch to drain my water, not so that they could discharge more water into it. I have never seen this anywhere. He says that you had authorized him to discharge the water onto the vacant lots; he said it, and I stand by that in front of the gentleman. Why do they not make this ditch? This ditch is on private property; it is not even on the street. I made it so that the water would drain away and not reach my property, but the person who did it entered my property to connect the drain, because . I do not know who was operating the machine at that time, but my entire property gets flooded” (see document).
Second Half of 2024. Review and possible formulation and preparation of administrative procurement requests for construction materials through deliveries on demand, including wood, reinforcing steel, granular aggregates, cement, among others. 6. First Half of 2025. On-site construction of the solution, in accordance with the design. 7. Second Half of 2025. Commissioning and post-construction monitoring of the on-site solution.” (see the Mayor’s report).
The following is deemed relevant: SOLE FACT.- That, to date, a definitive solution has been provided for the stormwater accumulation problem in the Brisa Bonita sector that affects the petitioner.
In this matter, the petitioner, who has a physical disability and is a resident of Brisa Bonita de Parrita, alleges that, despite the requests for intervention submitted to the Municipalidad de Parrita to resolve the stormwater accumulation problem in that sector, as of the date on which he filed this amparo proceeding, no comprehensive solution had been provided. This particularly affects him because, during the rainy season, his home is flooded by water reaching up to 40 centimeters above floor level.
Regarding this matter, a hearing (audiencia) was granted to the President of the Municipal Council and Nombre20665, who consistently acknowledged the stormwater accumulation problem that has affected the residents of that area for several years and, specifically, the appellant. Although in their reports the authorities stated that “It is not known whether the residence of Mr. [Nombre62 001] is the one described in the first fact. He does not appear as holding property in the Municipality of Parrita’s registration databases, either as an owner with title recorded in the Property Registry or as the owner of unregistered property. Nor does he appear as an occupant, possessor, or any similar status that would make him liable as a taxpayer under the Real Property Tax Law in the canton of Parrita,” the documentary evidence included in the case file shows that they were fully aware of the situation reported by the protected party and that, at no time, was the reason asserted in this amparo proceeding (recurso de amparo) raised by the municipal administration at the administrative level as grounds for failing to address the problem in question.
Having said that, it has been established that, on an unspecified date in 2016, the appellant requested a hearing before the Municipal Council to discuss the matter described as follows: “when the street was repaired, they dug a ditch and discharged the water into a drain that I built on my property to drain my property” (see document incorporated into the electronic case file), and he was received at ordinary session 075-2016 of 21 de noviembre de 2016, at which it was decided to refer the protected party’s case to the Municipal Road Management Technical Unit so that it could inspect the site and prepare a report on the matter. In official letter GDUS-UTGV0014-2017 of 16 de enero de 2017, the Municipal Road Management Technical Unit issued its report on the discharge of water from road Dirección05 into a channel on private property in Comunidad de Brisa Bonita, stating: “In response to the provisions of Resolution N°04, first Article, Public Hearings.
Matter N°3, of Ordinary Session N°075-2016, in which Mr. [Nombre62 001] submitted a complaint regarding the connection of the side ditches of road C6-09-021-00 to a channel built on his property, which he claims causes his lot to flood, notice is hereby given that the problem has already been corrected. As stated in inspection report N" UTGV-IDI-002-2017, attached to this official letter, the outlet for the water from the road’s side ditches that connected to the channel which Mr. [Nombre62 001] states he maintains on his property was closed. Photographs of the reported situation are included, along with photographs of the same location where the connection carrying this water was eliminated.” (see document). That technical report was brought to the protected party’s attention through official letter CM-SM-022-2017 of 17 de enero de 2016 (see document bearing the claimant’s acknowledgment of receipt).
Because the problem persisted, the Municipality of Parrita, through the Municipal Road Management Technical Unit, decided to construct a surface-runoff collection and road 21 storm-sewer system to resolve the stormwater accumulation problem in the Brisa Bonita area. This called for the construction of five survey monuments (mojones) to establish benchmarks for the corresponding survey and design, to perform construction control of elevations and gradients, and to verify that the work was properly built (see official letter GDUS-UTGV-165-2021). Accordingly, during the last half of 2021, the five survey monuments were constructed to establish benchmarks along the project corridor for a precision-level survey; however, a subsequent municipal inspection found that two of those survey monuments had been removed (see documentary evidence).
Again, in a letter submitted on 27 de junio de 2022, the appellant requested a hearing with the Municipal Council to explain the aforementioned problem. In response, through official letter GDUS-UTGV-211-2022 of 28 de julio de 2022, Parrita’s Municipal Management Technical Unit issued a report on the “status of the project for construction of the stormwater management system Dirección7470,” stating that: “with regard to the development of this project, the personnel of the technical department responsible for Road Management will first be asked to replace the missing survey monuments by rebuilding them. Thereafter, the corresponding survey will be conducted so that the appropriate design can be prepared and the budget required for this project can be determined. This will be presented to the Road Board so that it may decide whether or not the project will be carried out, subject to any modifications that this collegial body may request” (see attached document).
As of the date on which the protected party applied to this constitutional jurisdiction, the matter had not been resolved. Indeed, even the report submitted by Nombre20665 acknowledged that the situation affecting residents persisted. Although it is the product of climatic activity, it is aggravated by the lack of adequate stormwater channeling, works for which the municipal government is responsible in this case. In fact, the municipal executive stated that, to address the reported situation, the Municipality of Parrita’s Road Management Technical Unit had prepared the following schedule: “II Semester 2023. Construction and replacement of survey monuments or benchmarks for design and control on Dirección7469, Brisa Bonita area, as indicated in the corresponding report, and maintenance of existing markers. 2. I Semester of 2024. Soil, hydrological/hydraulic, topographic, and other studies.
Design of a comprehensive drainage and sewerage system solution for Comunidad de Brisa Bonita, including estimates of materials and budget. 3. I Semester of 2024. Formulation, preparation, and request for an administrative procurement process for a contract to supply reinforced concrete piping through deliveries on demand. 4. II Semester of 2024. Request for funds to purchase the materials required to build the necessary solution, to be included in the 2025 ordinary budget. 5. II Semester of 2024. Review and, where appropriate, formulation and preparation of administrative procurement requests for construction materials through deliveries on demand, including wood, reinforcing steel, granular aggregates, cement, among others. 6. I Semester of 2025. On-site construction of the solution according to the design. 7. ll Semester of 2025. Commissioning and post-construction monitoring of the on-site solution.” (see the mayor’s report).
Accordingly, this Chamber finds that the petition must be granted, because it was established that, although this is a longstanding problem known to the municipal authorities and some measures have been implemented to resolve it, it persists to date, with the aggravating risk it poses to the safety of residents of the area and, specifically, the appellant, who has requested municipal intervention on several occasions. From this perspective, the petition must be granted as set forth in the operative portion of this judgment.
The parties are hereby advised that, if they submitted any paper document, as well as objects or evidence contained on any additional electronic, computer, magnetic, optical, or telematic device or produced using new technologies, these must be collected from the court office within a maximum period of thirty business days from notification of this judgment. Otherwise, any material not collected within that period will be destroyed, pursuant to the “Reglamento sobre Expediente Electrónico ante el Poder Judicial,” approved by the Full Court at Session N° 27-11 of 22 de agosto del 2011, article XXVI, and published in Judicial Bulletin N° 19 of 26 de enero del 2012, as well as the resolution approved by the Superior Council of the Judiciary at Session N° 43-12 held on 3 de mayo del 2012, article LXXXI.
POR TANTO:
The petition is granted. Randall Rojas Piedra, Freddy Garro Arias, and Luis Edmond Acuña Godínez, respectively, in their capacities as President of the Municipal Council, Nombre20665, and Director of the Road Management Technical Unit, all of the Municipality of Parrita, or whoever may hold those offices, are ordered to undertake the necessary coordination measures so that, within twelve months from notification of this judgment, the plan prepared by Parrita’s Municipal Management Technical Unit concerning the stormwater channeling problem in the Brisa Bonita area is implemented and the appellant is informed of the actions taken. They are hereby warned that, pursuant to article 71 of the Law Governing this Jurisdiction, anyone who receives an order issued in an amparo proceeding that they are required to comply with or enforce and fails to comply with or enforce it shall be punished by imprisonment for three months to two years, or by a fine of twenty to sixty days, provided that the offense is not subject to a more severe penalty. The Municipality of Parrita is ordered to pay the costs, damages, and losses caused by the facts underlying this ruling, which shall be assessed during enforcement of the judgment before the Contentious-Administrative Court. Let notice be given.- Fernando Castillo V.
President Paul Rueda L.
Luis Fdo. Salazar A.
Jorge Araya G.
Alejandro Delgado F.
Alexandra Alvarado P.
Jose Roberto Garita N.
*F72LHTURW3M61* CASE FILE N° 23-023799-0007-CO Telephone numbers: Telf01/ ALA-4TA (800-7252-482). Fax: Telf02 / Telf03. Website: www.poder-judicial.go.cr/salaconstitucional. Address: (Dirección06, Dirección07, 100 meters south of the Perpetuo Socorro church). Filing office for matters involving vulnerable groups: Edificio Corte Suprema de Justicia, San José, Dirección08, Dirección09, streets 19 and 21, Dirección17
Revisión del Documento *230237990007CO* SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas veinte minutos del doce de julio de dos mil veinticuatro .
Recurso de amparo interpuesto por [Nombre62 001], cédula de identidad [Valor CED01], contra la MUNICIPALIDAD DE PARRITA.
RESULTANDO
Redacta el Magistrado Araya García; y,
CONSIDERANDO:
El recurrente, vecino de Brisa Bonita de Parrita y con discapacidad física, acusa que, pese a las solicitudes de intervención planteadas a la Municipalidad de Parrita para que solucione el problema de acumulación de aguas pluviales en ese sector, a la fecha en que acude en amparo, no se ha dado una solución integral, lo que le afecta particularmente, pues durante la época lluviosa su vivienda sufre inundaciones de hasta 40 centímetros de altura desde el nivel del piso. Estima lesionados sus derechos fundamentales.
De previo a analizar el fondo del asunto -por la presunta violación del derecho a un procedimiento pronto y cumplido- debe aclararse que, a partir de la Sentencia N° 2008-02545 de las 8:55 horas de 22 de febrero de 2008, esta Sala ha remitido a la Jurisdicción Contencioso Administrativa -con algunas excepciones-, aquellos asuntos en los que se discute si la Administración Pública ha cumplido o no los plazos pautados por la Ley General de la Administración Pública (artículos 261 y 325) o las leyes sectoriales para los procedimientos administrativos especiales, para resolver por acto final un procedimiento administrativo -instruido de oficio o a instancia de parte- o conocer de los recursos administrativos procedentes.
En este caso se plantea un supuesto de excepción pues se está ante una problemática ambiental por las inundaciones que se producen en el sector, afectando la integridad del recurrente -quien presenta una discapacidad- y la vivienda que habita. Según lo alegado, a la fecha, las solicitudes de intervención planteadas por el actor a la municipalidad en relación con este problema, no han sido resueltas dentro de un plazo razonable, por lo que se entra a resolver la situación concreta planteada en este amparo.
De importancia para la decisión de este asunto, se estiman como demostrados los siguientes hechos:
Construcción y reposición de mojones o bancos de nivel para diseño y control en el Dirección7469 , sector Brisa Bonita, según lo señalado en el informe correspondiente, y mantenimiento de hitos existentes. 2. I Semestre de 2024. Estudios de suelos, hidrológico/hidráulico, topográfico, entre otros. Diseño de solución integral de sistema de drenaje y alcantarillado para comunidad de Brisa Bonita, con estimación de materiales y presupuesto. 3. I Semestre de 2024. Formulación, elaboración y solicitud de proceso de contratación administrativa para contrato de suministro de tubería de concreto reforzado por entregas según demanda. 4. II Semestre de 2024. Solicitud de recursos para compra de materiales necesarios para la construcción de la solución requerida, para ser incluidos en el presupuesto ordinario 2025. 5. II Semestre de 2024. Revisión y eventual formulación y elaboración de solicitudes de contratación administrativa de materiales para construcción por entregas según demanda, entre ellos, madera, acero de refuerzo, agregados granulares, cemento, entre otros. 6. ISemestre de 2025. Construcción de solución en sitio, según diseño. 7. ll Semestre de 2025. Puesta en operación y control post construcción de solución en sitio.” (ver informe del Alcalde).
De relevancia se tiene el siguiente: ÚNICO.- Que, a la fecha, se haya dado una solución definitiva al problema de acumulación de aguas pluviales en el sector de Brisa Bonita que afecta al recurrente.
En este asunto, el recurrente, con discapacidad física y vecino de Brisa Bonita de Parrita, acusa que, pese a las solicitudes de intervención planteadas a la Municipalidad de Parrita para que solucione el problema de acumulación de aguas pluviales en ese sector, a la fecha en que acude en amparo, no se ha dado una solución integral, lo que le afecta particularmente, pues durante la época lluviosa su vivienda sufre inundaciones de hasta 40 centímetros de altura desde el nivel del piso.
Sobre el particular, se concedió audiencia al Presidente del Concejo y al Nombre20665, quienes fueron consistentes en reconocer el problema de acumulación de aguas pluviales que aqueja a las personas habitantes de ese sector desde hace varios años y, en concreto, al recurrente. Aunque en los informes, las autoridades indicaron que “Se desconoce que la residencia del señor [Nombre62 001] sea la descrita en el hecho primero. Siendo que no registra propiedad en las bases de registros de la Municipalidad de Parrita, ni como propietario con título inscrito en el Registro de Propiedades o como propiedad sin inscribir. Ni como ocupante o poseedor u otro similar para que ostente la titularidad de sujeto pasivo según la Ley de Impuesto sobre los Bienes Inmuebles, en el cantón de Parrita.”, lo cierto es que de la prueba documental adjunta a los autos, se desprende que la situación acusada por el amparado ha sido de su pleno conocimiento y, en ningún momento, la razón aducida en este amparo, fue alegada en sede administrativa por la administración municipal para desatender el problema en cuestión.
Dicho lo anterior, se acredita que, en efecto, en fecha no precisa de 2016 el recurrente solicitó una audiencia al Concejo Municipal, para tratar el asunto descrito: “en el momento que se reparó la calle realizaron un zanjo y echaron las aguas en un caño que hice en mi propiedad para desaguar mi propiedad” (ver documento incorporado al expediente electrónico), siendo recibido en la sesión ordinaria 075-2016 del 21 de noviembre de 2016, en la que se dispuso trasladar ante la Unidad Técnica de Gestión Vial Municipal, el caso del amparado para que realice una visita al lugar y realice un informe al respecto. En oficio GDUS-UTGV0014-2017 del 16 de enero de 2017 la Unidad Técnica de Gestión Vial Municipal rindió el informe sobre desfogue de aguas del camino Dirección05 a canal en propiedad privada, Comunidad de Brisa Bonita, indicándose: “En respuesta a lo dispuesto en el Acuerdo N°04, Artículo primero, Atención al público.
Asunto N°3, de la Sesión Ordinaria N°075-2016, donde el señor [Nombre62 001] presenta queja por la conexión de las cunetas laterales del camino C6-09-021-00 a un canal construido en su propiedad, razón por la que indica que se inunda su predio, se comunica que el problema ya fue corregido. Según lo indicado en el informe de inspección N" UTGV-IDI-002-2017, adjunto a este oficio, se cerró la salida de las aguas de las cunetas laterales del camino que conectada con el canal que indica en señor [Nombre62 001] que mantiene en su propiedad. Se incluyen fotografías de la situación expuesta, además de fotografías del mismo sitio donde se eliminó la conexión de estas aguas.” (ver documento). Ese informe técnico fue puesto en conocimiento del amparado en oficio CM-SM-022-2017 del 17 de enero de 2016 (ver documento con acuse de recibido del actor).
Ante la persistencia del problema, para solventar el problema de acumulación de aguas pluviales en el sector de Brisa Bonita, la Municipalidad de Parrita, a través de la Unidad Técnica de Gestión Vial Municipal dispuso la construcción de un sistema colector de aguas de escorrentía superficial y alcantarillado del camino 21, para lo cual se proyectó la construcción de cinco mojones para establecer los bancos de nivel para el respectivo levantamiento y diseño y realizar el control constructivo de nivelación y pendientes y verificar la adecuada construcción de la obra (ver oficio GDUS-UTGV-165-2021). Por esto, en el último semestre de 2021 se construyeron los cinco mojones para el establecimiento de bancos de nivel en el tramo de desarrollo del proyecto, para el levantamiento con nivel de precisión; sin embargo, en una inspección municipal posterior se constató que dos de esos mojones fueron removidos (ver prueba documental).
Nuevamente, en nota presentada el 27 de junio de 2022 el recurrente solicitó audiencia con el Concejo Municipal para exponer el problema de cita. En atención a lo anterior, por medio del oficio GDUS-UTGV-211-2022 del 28 de julio de 2022, la Unidad Técnica de Gestión Municipal de Parrita rindió informe sobre el “estado de proyecto de construcción de sistema de manejo de aguas pluviales Dirección7470 , ”, indicándose que: “en lo que corresponde al desarrollo de este proyecto, se solicitará en primera instancia al personal de la dependencia técnica encargada de la Gestión Vial la reposición de esos mojones faltantes, construyéndolos nuevamente, posterior a esto se realizará el levantamiento respectivo para proceder a realizar el diseño correspondiente y determinar el presupuesto requerido asociado a este proyecto, lo cual se expondrá ante la Junta Vial para que se determine si se realiza o no la ejecución del mismo, con las modificaciones que eventualmente solicite este órgano colegiado” (ver documento adjunto).
A la fecha en que el amparado acudió a esta jurisdicción constitucional, el asunto no ha sido solventado, siendo que, incluso, en el informe rendido por el Nombre20665 se reconoció la persistencia de la situación que afecta a los pobladores, el cual, si bien, es producto de la acción climática, se ve agravado por la falta de una adecuada canalización de las aguas pluviales, obras que corresponden a la corporación municipal en este caso. De hecho, el ejecutivo municipal adujo que para atender la situación expuesta, la Unidad Técnica de Gestión Vial de la Municipalidad de Parrita ha elaborado el siguiente cronograma: “II Semestre 2023. Construcción y reposición de mojones o bancos de nivel para diseño y control en el Dirección7469 , sector Brisa Bonita, según lo señalado en el informe correspondiente, y mantenimiento de hitos existentes. 2. I Semestre de 2024. Estudios de suelos, hidrológico/hidráulico, topográfico, entre otros.
Diseño de solución integral de sistema de drenaje y alcantarillado para comunidad de Brisa Bonita, con estimación de materiales y presupuesto. 3. I Semestre de 2024. Formulación, elaboración y solicitud de proceso de contratación administrativa para contrato de suministro de tubería de concreto reforzado por entregas según demanda. 4. II Semestre de 2024. Solicitud de recursos para compra de materiales necesarios para la construcción de la solución requerida, para ser incluidos en el presupuesto ordinario 2025. 5. II Semestre de 2024. Revisión y eventual formulación y elaboración de solicitudes de contratación administrativa de materiales para construcción por entregas según demanda, entre ellos, madera, acero de refuerzo, agregados granulares, cemento, entre otros. 6. I Semestre de 2025. Construcción de solución en sitio, según diseño. 7. ll Semestre de 2025. Puesta en operación y control post construcción de solución en sitio.” (ver informe del alcalde).
De ahí entonces que para esta Sala el asunto debe ser acogido pues quedó acreditado que, aunque es un problema conocido de larga data por las autoridades municipales y que se han implementado algunas medidas para solucionarlo, a la fecha, persiste con el agravante que representa para la seguridad de las personas pobladoras de la zona y, en específico el recurrente quien, en varias oportunidades, ha solicitado la intervención municipal. Desde esta perspectiva, el asunto debe ser estimado conforme se dirá en la parte dispositiva de esta sentencia.
Se previene a las partes que de haber aportado algún documento en papel, así como objetos o pruebas contenidas en algún dispositivo adicional de carácter electrónico, informático, magnético, óptico, telemático o producido por nuevas tecnologías, estos deberán ser retirados del despacho en un plazo máximo de treinta días hábiles contados a partir de la notificación de esta sentencia. De lo contrario, será destruido todo aquel material que no sea retirado dentro de este plazo, según lo dispuesto en el "Reglamento sobre Expediente Electrónico ante el Poder Judicial", aprobado por la Corte Plena en Sesión N° 27-11 del 22 de agosto del 2011, artículo XXVI y publicado en el Boletín Judicial N° 19 del 26 de enero del 2012, así como en el acuerdo aprobado por el Consejo Superior del Poder Judicial, en la Sesión N° 43-12 celebrada el 3 de mayo del 2012, artículo LXXXI.
POR TANTO:
Se declara con lugar el recurso. Se ordena a Randall Rojas Piedra, Freddy Garro Arias y Luis Edmond Acuña Godínez, por su orden, presidente del Concejo Municipal, Nombre20665 y Director de la Unidad Técnica de Gestión Vial, todos de la Municipalidad de Parrita, o a quienes ocupen esos cargos, adoptar las instancias de coordinación necesarias para que, en el plazo de doce meses contado a partir de la notificación de esta sentencia, se ejecute el plan diseñado por la Unidad Técnica de Gestión Municipal de Parrita en relación con el problema de canalización de aguas pluviales en el sector de Brisa Bonita y se informe al recurrente lo actuado. Se advierte que de conformidad con el artículo 71 de la Ley de esta Jurisdicción, se impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo y no la cumpliere o no la hiciere cumplir, siempre que el delito no esté más gravemente penado. Se condena a la Municipalidad de Parrita al pago de las costas, daños y perjuicios causados con los hechos que sirven de base a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso administrativo. Notifíquese.- Fernando Castillo V.
Paul Rueda L.
Luis Fdo. Salazar A.
Jorge Araya G.
Alejandro Delgado F.
Alexandra Alvarado P.
Jose Roberto Garita N.
*F72LHTURW3M61*