Res. 33635-2023 Sala Constitucional · Sala Constitucional · 22/12/2023
OutcomeResultado
The Chamber ordered the Municipality of Nandayure, MOPT, and the National Emergency Commission to submit a coordinated plan within two months and permanently resolve the Nandayure River flooding affecting the community within one year.La Sala ordenó a la Municipalidad de Nandayure, al MOPT y a la CNE presentar en dos meses un plan coordinado y resolver definitivamente en un año las inundaciones del río Nandayure que afectan a la comunidad.
SummaryResumen
The Constitutional Chamber granted an amparo filed by a resident of San Pablo de Nandayure whose home and community were exposed to flooding and erosion caused by the Nandayure River. Although the Municipality of Nandayure, the Ministry of Public Works and Transport, and the National Emergency Commission had undertaken dredging, cleaning, channeling, and other temporary mitigation measures, the problem had persisted for approximately five years. The Chamber found those interventions insufficient and concluded that the institutions had failed to timely pursue a comprehensive, permanent solution capable of safeguarding the community. It ordered the three entities to coordinate within their respective powers, prepare within two months a plan containing a binding schedule, and definitively resolve the problem within one year. It also ordered the State, the municipality, and the Commission to pay costs and damages. One justice disagreed only as to which court should oversee and enforce compliance with the judgment.La Sala Constitucional declaró con lugar el amparo interpuesto por una vecina de San Pablo de Nandayure cuya vivienda y comunidad estaban expuestas a las inundaciones y a la erosión causadas por el río Nandayure. Aunque la Municipalidad de Nandayure, el MOPT y la CNE habían ejecutado dragados, limpiezas, canalizaciones y otras medidas paliativas, el problema persistía desde hacía aproximadamente cinco años. La Sala consideró insuficientes esas intervenciones y concluyó que las instituciones no habían gestionado oportunamente una solución integral, definitiva y capaz de garantizar la seguridad de la comunidad. Ordenó a las tres entidades coordinar sus competencias, diseñar en dos meses un plan con un cronograma vinculante y resolver definitivamente el problema en el plazo de un año. También condenó al Estado, a la municipalidad y a la CNE al pago de costas, daños y perjuicios. Una magistrada discrepó únicamente sobre la sede judicial encargada de ejecutar y supervisar el fallo.
Key excerptExtracto clave
Having clarified that background, it should be noted that, although almost five years have elapsed, the flooding situation still persists and the works necessary to achieve a comprehensive and permanent solution have not been carried out. In this regard, although the respondent authorities have performed various temporary mitigation works, such as dredging and other cleaning and channeling activities, it is nonetheless true that those actions have proved insufficient. The respondent municipality itself acknowledges that greater efforts are needed to implement durable works capable of resolving the reported problem. Thus, even though the authorities have known about the problem for approximately five years and have performed certain temporary works, they have not taken the necessary steps to achieve a comprehensive and permanent solution that guarantees the safety of the San Nombre41 de Nandayure community. Accordingly, the amparo must be granted in order to ensure a comprehensive solution within a reasonable period.Aclarado ese panorama, nótese que a pesar de que han transcurrido casi 5 años, se aprecia que aún persiste la situación de las inundaciones, y que no se han ejecutado las obras necesarias para alcanzar una solución integral y definitiva. En tal sentido, si bien las autoridades accionadas han realizado distintas obras paliativas como dragados y otros trabajos de limpieza y canalización, no menos cierto es que tales acciones han resultado insuficientes. Al respecto, la propia municipalidad accionada reconoce que es necesario ejecutar mayores esfuerzos para la implementación de obras duraderas que solventen el problema acusado. Así las cosas, pese a que desde al menos hace aproximadamente 5 años las autoridades conocen el problema de marras y han realizado determinados trabajos paliativos, no han gestionado lo pertinente para alcanzar una solución integral y definitiva garantice la seguridad de la comunidad de San Nombre41 de Nandayure. De tal manera, lo procedente es declarar con lugar el recurso, a fin de garantizar una solución integral dentro de un plazo razonable.
Pull quotesCitas destacadas
"Se declara con lugar el recurso."
"The amparo is granted."
Por tanto
"Se declara con lugar el recurso."
Por tanto
"En tesis de principio, considero que los casos relacionados con la inactividad de la Administración Pública en la reparación, construcción, modificación o demolición de cualquier obra de infraestructura deben ser desestimados, por constituir, esa omisión, un tema de legalidad, cuya discusión corresponde a la jurisdicción ordinaria, ante la cual la persona interesada puede debatir, con mayor amplitud, sus disconformidades."
"As a matter of principle, I consider that cases concerning the Public Administration's inaction in repairing, constructing, modifying, or demolishing infrastructure should be dismissed because such an omission is a matter of legality whose adjudication belongs to the ordinary courts, where the interested person may present their objections more fully."
Nota del Magistrado Salazar Alvarado
"En tesis de principio, considero que los casos relacionados con la inactividad de la Administración Pública en la reparación, construcción, modificación o demolición de cualquier obra de infraestructura deben ser desestimados, por constituir, esa omisión, un tema de legalidad, cuya discusión corresponde a la jurisdicción ordinaria, ante la cual la persona interesada puede debatir, con mayor amplitud, sus disconformidades."
Nota del Magistrado Salazar Alvarado
"Sin embargo, cuando de aquella conducta administrativa omisiva se derive alguna violación a otros derechos fundamentales tutelados en esta jurisdicción constitucional, o se afecten grupos considerados vulnerables, sí entro a conocer el fondo del asunto, por constituir esta situación una excepción a mi posición en esta materia, tal y como sucede en este caso."
"However, when such administrative inaction results in a violation of other fundamental rights protected by this constitutional jurisdiction, or affects groups considered vulnerable, I do examine the merits because that situation constitutes an exception to my position on this matter, as occurs in this case."
Nota del Magistrado Salazar Alvarado
"Sin embargo, cuando de aquella conducta administrativa omisiva se derive alguna violación a otros derechos fundamentales tutelados en esta jurisdicción constitucional, o se afecten grupos considerados vulnerables, sí entro a conocer el fondo del asunto, por constituir esta situación una excepción a mi posición en esta materia, tal y como sucede en este caso."
Nota del Magistrado Salazar Alvarado
"El presupuesto ya fue presentado ante el Concejo Municipal, lastimosamente dicho presupuesto fue improbado por parte de ellos."
"The budget was already submitted to the Municipal Council; unfortunately, it was rejected by that body."
Informe municipal
"El presupuesto ya fue presentado ante el Concejo Municipal, lastimosamente dicho presupuesto fue improbado por parte de ellos."
Informe municipal
Full documentDocumento completo
*CO* Case: 23-007675-0007-CO Decision No. 2023033635 SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, at thirteen hours and fifteen minutes on veintidós de diciembre de dos mil veintitrés.
Application for amparo relief (recurso de amparo) being processed under expediente nro. 23-007675-0007-CO, filed by [Nombre62 001], identity card [Valor CED63], against the MUNICIPALIDAD DE Nombre20770, the MINISTERIO DE OBRAS PÚBLICAS Y TRANSPORTES (MOPT), and the COMISIÓN NACIONAL DE PREVENCIÓN DE RIESGOS Y ATENCIÓN DE EMERGENCIA (CNE).
Findings of Fact:
FACTS The background set forth in the initial filing of the amparo proceeding is summarized and addressed in the same order: FIRST: She states that the river’s normal course was altered and has caused irreversible damage. This Commission cannot determine the truth of the allegations concerning this fact. Nor can authorship of the problem described be attributed to it. Furthermore, there are institutions with jurisdiction over the matter that can determine whether environmental damage exists; accordingly, the CNE has no knowledge that the petitioner’s statement is true. SECOND: She refers to studies by professionals retained privately so that assistance may be provided to her. The CNE’s ordinary and extraordinary powers do not include carrying out works at the request of a party, because it serves the public interest and not private interests. Furthermore, the performance of works and related activities is strictly tied to a declaration of national emergency issued by the Executive Branch as a result of one or more unforeseeable and unavoidable events.
On various occasions, the Constitutional Chamber has reiterated the distinction between a genuine state of emergency and mere urgency, the latter of which, in this particular case, must be addressed through the ordinary work of each local government. THIRD: She refers to rainfall-density reports. No opinion is offered on this point because it concerns reports apparently issued by the Instituto Meteorológico Nacional. FOURTH: Technical memorandum prepared by the geologist at the petitioner’s request. The petitioner refers to a technical study conducted privately; however, no assessment of it can be made because the information was not generated by this Commission or by an institution with jurisdiction over the matter. FIFTH: Preliminary estimate for the protection of property on the left bank of the Nandayure River. As with Fact Four, this is a privately conducted study; therefore, no opinion can be offered on it because the information was not generated by this Commission or by an institution with jurisdiction over the matter.
SIXTH: Request that the work recommended by the professionals in their respective fields be carried out. It is important to state that the CNE must reject what is requested under this Fact because the institution’s authority is strictly defined pursuant to the principle of legality and the application of Ley Nacional de Emergencias y Prevención del Riesgo N°8488. Furthermore, any works it carries out must be authorized under a current Emergency Decree and must arise from the existence of a causal nexus. Therefore, when a national emergency has been declared, any appropriate works are performed on the basis of its own studies or those issued by institutions with jurisdiction over the matter.
ORDER TO CURE: With respect to the order to cure issued by the Constitutional Chamber to the petitioner, which appears in the record, and according to her statements, it must be taken into consideration that she has not submitted requests to the CNE or approached it to present her problem. Nevertheless, in response to a separate request concerning a complaint filed with the Defensoría de los Habitantes, the CNE’s Unidad de Análisis e Investigación del riesgo, which is responsible for issuing such reports to local governments, issued report N°CNE-UIAR-INF-1193- 2021.
Each municipal government has a duty, through planning and the exercise of its authority, to ensure that urban development complies with safety, public-health, and environmental-sustainability criteria. This serves to safeguard citizens’ rights. The Constitución Política, the Código Municipal, the Ley de Planificación Urbana, the Ley de Construcciones, and related regulations provide that municipalities bear absolute and exclusive responsibility for land-use planning within their jurisdictions. This has been further explained in opinions of the Procuraduría General de la República, including C-155-2009 dated 01 de junio de 2009 and C-091-2010 dated 03 de mayo de 2010, among many others. Additionally, the Constitutional Chamber has affirmed that responsibility in decisions such as 2004-09439, 2005-04002 and 2005-07516, among many others. In this regard, jurist Eduardo Ortiz Ortiz, quoted in Opinion C-032-98 dated 25 de febrero de 1998 of the Procuraduría General de la República, stated: “Municipal authority to enact urban-development plans derives from statute, because it encompasses a matter constitutionally reserved to statute, but it also has a constitutional basis because it is a local matter.
This means that the statute may delegate such authority only to the Municipality and that a statute providing otherwise and empowering, for example, the Executive Branch would be unconstitutional because it would violate municipal autonomy.” The Tribunal de lo Contencioso Administrativo y Civil de Hacienda, for its part, has issued judgments adopting the same position as the Procuraduría General and emphasizing the absolute responsibility of local governments for land-use planning. Lastly, at Special Session N° 10-11, held on 09 de noviembre de 2011, the Board of Directors of the Comisión Nacional de Prevención de Riesgos y Atención de Emergencias adopted Resolution N° 0443-2011, which was published in the Gaceta N° 230 on 30 de noviembre de 2011. The relevant portion of that resolution provides: a. Recommend to all mayors in the country: i. That, pursuant to the duties and powers imposed upon them by Articles 50 and 169 of the Constitución Política, the Código Municipal, the Ley de Planificación Urbana, the Ley de Construcciones, the Ley Orgánica del Ambiente, Article 33 of the Ley Forestal, related regulations, the Ley General de Salud, and the extensive case law on the subject, they immediately proceed to evict the occupants of areas known to pose an imminent risk and danger, demolish the buildings located therein, and ensure that those areas are not reoccupied by human settlements, applying the procedural sequence cited in Considerando IV, which is taken from Constitutional Chamber decision Nº 12485-2010. ii.
That, in view of the binding nature attributed to them by the Constitutional Chamber, they immediately implement the recommendations concerning specific and timely measures to safeguard human life in areas known to pose an imminent risk and danger, which CNE technicians and academic institutions have repeatedly provided to them over many years and of which they are aware. The studies and technical recommendations historically issued in each case shall be made available to the municipalities at the CNE’s offices. (…)” Accordingly, it should be recalled that, by constitutional mandate, the administration of the local interests and services of each canton falls within the jurisdiction of each Local Government, which has full legal capacity to perform all types of acts and enter into all contracts necessary to fulfill its assigned purposes. It should be noted that the CNE issued the corresponding technical report on the Nombre20770 River through official letter N° CNE-UIAR-INF1193-2021.
Therefore, under the cited provision, the local government is responsible for complying with the recommendations issued by this Commission, and the relief requested by the petitioner is not the responsibility of the entity I represent.
Article 46 bis of the Ley Nacional de Emergencias y Prevención del Riesgo: Article 1° of law N° 9907 dated veintisiete de octubre del año dos mil veinte added Article 46 bis to Law N° 8488, concerning the use of the three percent previously required to be transferred to the Commission by the municipal system. This article provides that municipalities and district municipal councils shall calculate the three percent (3%) of the unrestricted budget surplus provided for in Article 46 bis on the basis of the budget settlement as of 30 de junio del año en curso, after the obligations actually undertaken during the previous period have been completed, in accordance with Article 116 of Law N° 7794, Código Municipal, dated treinta de abril de mil novecientos noventa y ocho. These resources shall be administered by each municipal entity and used exclusively to strengthen technical capacity and municipal risk-management processes (gestión del riesgo), as well as for emergency prevention and response, including emergencies not covered by an emergency decree. The corresponding local government, in coordination with the Ministerio de Obras Públicas y Transportes’ Departamento de Aguas Fluviales y Pluviales, must provide a permanent solution to the problem described in the proceeding filed.
The Comisión Nacional de Prevención de Riesgos y Atención de Emergencias (CNE) is the lead public institution responsible for coordinating work involving the prevention of situations of imminent risk, mitigation, and emergency response. Law N° 8488, “Ley Nacional de Emergencias y Prevención del Riesgo,” has granted the Comisión Nacional de Prevención de Riesgos y Atención de Emergencias ordinary powers (Article 14) and extraordinary powers (Article 15). Its ordinary powers under Law N° 8488 include the following obligation: Article 14°—The Commission’s ordinary preventive powers. The Commission shall be the lead entity for risk prevention and preparedness to respond to emergency situations.
It shall perform the following duties: (…) h) Advise municipalities regarding the management of information on the risk conditions affecting them, such as guidance for an effective land-use policy and territorial planning (ordenamiento territorial). Such advice shall contribute to the preparation of regulatory plans (planes reguladores), the adoption of control measures, and the promotion of organization aimed at reducing people’s vulnerability, considering that, at the municipal level, the responsibility for addressing this problem rests in the first instance. (…)”. Likewise, its extraordinary powers are defined in Article 15 of Law No. 8488, which states verbatim: Article 15.—Extraordinary powers of the Commission. Once the state of emergency established in Article 29 of this Law has been declared, the Commission shall be responsible for planning, coordinating, directing, and overseeing actions aimed at meeting urgent needs and implementing protection, rescue, and rehabilitation programs and activities.
To that end, it shall carry out, at a minimum, the following actions: a) The coordination, direction, and oversight of the response to emergencies declared as such by the Executive Branch shall be conducted in accordance with the phases defined in Article 30 of this Law; for this purpose, the Commission, through the Executive Directorate, shall prepare the General Emergency Plan, under the terms set forth in Chapter VI of this Law.” (…) Under the regulations cited, the CNE cannot act as asserted by the petitioner, because the actions of the Administration must strictly adhere to the principle of legality (principio de legalidad). Along the same lines, the CNE has acted within its powers, as demonstrated by official communications No. CNE-UIAR-INF-1193-2021 and No. CNE-UGPR-OF-0669-2023. 3.1. UNDECLARED OR FIRST-IMPACT EMERGENCIES: It should be noted that the aforementioned Law, as part of the extraordinary powers, authorizes the CNE to respond to local and minor emergencies through the “First Impacts” (Primeros Impactos) mechanism set forth in the final paragraph of section 15, which states: “(…) Except as provided in the preceding subsections, the Commission shall respond, without an emergency declaration by the Executive Branch, to local and minor emergencies that, because of the high frequency with which they occur and the serious harm they cause to communities, require the provision of a first-impact humanitarian service consisting of the delivery of blankets, food, and sleeping mats and, if necessary, the procurement of materials to restore basic services and establish shelters, as well as the contracting of a maximum of one hundred machine-hours to clean the most severely affected area of the zone.
(Emphasis added) This is noted because the only two interventions carried out by this Commission in the Nombre20770 River were conducted through this mechanism, which applies when the Municipality lacks the administrative or operational capacity to respond to the event. Nevertheless, it must be stated that these interventions concern exceptional situations and do not entail an obligation to assume the ordinary responsibilities and powers of the Municipalities. IV. THE SPECIFIC CASE: Based on the factual and legal arguments presented in this report, the CNE has acted, within the scope of its institutional powers, within the limits permitted by law. Consider the statements made in report No. CNE-UIAR-INF-1193-2021 of the Unidad de Investigación y Análisis de Riesgo, which refers in part to the Nandayure River and contains recommendations to the Municipalidad de Nandayure that it act within its jurisdiction and take the measures necessary to mitigate the impact of the river channel (cauce) on neighboring communities.
As mentioned above, compliance with those recommendations is the responsibility of the Municipality. Furthermore, by official communication No. CNEUGPR-OF-0669-2023, the Unidad de Gestión de Procesos de Reconstrucción refers, among other matters, to the interventions carried out by the CNE under the first-impact mechanism described above, demonstrating that the issue underlying the amparo proceeding (recurso de amparo) is not the result of those contracts. Moreover, carrying out the works necessary to provide a permanent solution to the problem described by the petitioner does not fall within the CNE’s powers, because this is an ordinary responsibility of the Local Government, as this is not a national emergency, for the reasons explained throughout this report. It is important to indicate that, after consulting the institutional records, the area described in the proceeding—the canton of Nandayure—is not covered by any emergency declaration currently in force, and the CNE is therefore unable to intervene in the area; nevertheless, as stated, the CNE’s Unidad de Investigación y Análisis del Riesgo has already issued a technical report regarding the area.
With respect to the professionals retained by the petitioner, it should be noted that it is not possible to address the substance of their submissions because they are based on assumptions that have not been proven, and therefore cannot be considered by the party I represent. In accordance with the foregoing, it is requested that the proceeding filed against the CNE be dismissed, because the CNE has acted within its statutory powers and the facts described must be addressed through the ordinary framework of the Local Government. V. RELIEF SOUGHT Por tanto, I request that this report be deemed duly submitted; that this Amparo Proceeding be dismissed as to the Comisión Nacional de prevención de Riesgos y Atención de Emergencias (CNE); and, with all due respect, that the Honorable Justices close the case file and absolve the party I represent of constitutional liability, pursuant to Article 9 of the Ley de la Jurisdicción Constitucional”.
Justice Hess Herrera writes the opinion; and,
Considering:
Given that the mayor of Nombre20770 failed to submit the report within the period set by this Court in the order admitting this matter for consideration, pursuant to Article 45 of the Constitutional Jurisdiction Law (Ley de la Jurisdicción Constitucional), the constitutionality of the matter shall be analyzed based on the other elements entered into the record.
The petitioner states that she is a resident of San Nombre41 de Nombre20770 and that her property is located within the area affected by flooding caused by the Nandayure River. She alleges that, in 2018, the respondent authorities performed dredging work (trabajos de dragado) on that river; however, the work was performed improperly because it altered the river’s natural course, with the result that the rains destroyed the works that same year. She asserts that the dredging redirected the river toward the rear of her home and therefore fears that the flow may sweep away her house. She alleges that, in August 2022, she went to the Comisión Nacional de Emergencias, where she was told that the matter fell within the jurisdiction of MOPT. She states that in September 2022 she went to the Departamento de Aguas Fluviales y Pluviales del MOPT, but was told there that they had no budget and that “the river can only be accessed through an appeal for constitutional relief (recurso de amparo).” She explains that the residents and the Municipalidad de Nombre20770 have held meetings regarding the problem and that, on April 12, 2023, they were informed that mitigation works (obras paliativas) would begin on the following May 1, but that permanent works to resolve the problem could not be carried out because the Comisión Nacional de Emergencias had authorized only 300 hours of work.
She adds that, in 2022, the problem worsened because the river current swept away trees and fences, causing severe ecological damage. She requests a permanent, rather than merely temporary, solution to the problem involving the Nandayure River, which is threatening her home as well as those of 26 other families, who are already placing their belongings on pallets to avoid losing them during the next rainy season.
The following facts are deemed duly established and relevant to the resolution of this matter:
C. The assessed zone in the community of San Nombre41 Viejo de Nombre20770 has flat, undulating topography and is located at the point where the channel ceases to be confined within the river canyon and opens onto the alluvial plain. It has varied cover, with scattered trees and some residential structures built within zones that have been affected by waterlogging in the past. A local road also runs parallel to the channel and is affected when overflow events occur. D. In the assessed sector running parallel to the channel of the Río Nombre20770, severe lateral erosion is observed along the banks because the flow strikes the zones with great force. Throughout the lower section of the river, there is substantial sedimentation and accumulation of materials that have completely filled it, causing a significant loss of hydraulic capacity and contributing to overflow events during heavy rainfall.
E. The overflight conducted using an unmanned aerial vehicle (drone) revealed evidence of overflow events, waterlogging, and debris deposits along the banks of the plain, where several homes are located. There is evidence of material carried by the current and of debris contained in the flow as it crosses the municipal road leading to San Nombre41 Viejo and continues toward adjacent land. F. At the Pozas stream, which crosses the road leading to San Nombre41 Viejo, problems are observed at the crossing bridge, which becomes obstructed by debris and causes the flow to overflow. This problem blocks passage, isolates the community, and leaves residents with no means of departure because this is the only route into the community (…) Recommendations. A. The Municipalidad de Nombre20770 must coordinate with Obras Fluviales del MOPT and MINAE regarding the possibility of properly channelizing the Río Nombre20770 at the assessed sites presenting problems, in order to remove the accumulated material that reduces the hydraulic capacity of the sections, and must also carry out protective works (obras de protección) to reduce lateral erosion along the banks and protective dikes.
B. The Municipalidad de Nombre20770 must construct adequate protective and retaining works along the banks of the Nandayure River, using materials that will not be eroded by extraordinary floods and that will protect the sectors. C. The Municipalidad de Nombre20770 must restrict land use (uso de suelo) for residential or commercial purposes within the protection zones of the Nandayure River, pursuant to Article 33 of Ley Forestal 7575, as well as within areas identified as potentially affected by flooding, according to the CNE natural-hazard maps. D. The protective works implemented along the affected banks must be supervised by a professional affiliated with the Colegio Federado de Ingenieros y Arquitectos de Costa Rica, in accordance with the standards established by the Código Sísmico, Código de Cimentaciones y Reglamento de Construcciones, Código Municipal, and other legislation in force.
E. The Municipalidad de Nombre20770 must periodically carry out proper channelization, according to the accumulation of materials in the channel of the Río Nombre20770 and in all waterways draining the canton, to help restore the hydraulic capacity of the channel and reduce the threat of flooding in each sector. F. The Municipalidad de Nombre20770 must remain vigilant over zones at high risk of flooding or susceptible to landslides and must not grant construction permits or allow the development of informal housing settlements in such zones. G. Any irregularity involving construction techniques or failure to comply with the recommendations described herein SHALL BE THE SOLE RESPONSIBILITY of the institutions granting the permits, the engineer or person responsible for the work, and the respective Municipality if it fails to request the corresponding reports, inspections, and corrections.” (See documentary evidence).
The type of intervention carried out consists of contracting machine hours to remove material and sediment from the center of the river channel (cauce), piling it along the banks, thereby facilitating better channeling of the water flow and reducing the risk of the river overflowing. These interventions were performed in response to requests and damage reports issued by the Municipality, which is also responsible for supervising and properly using the contracted hours. 4. This type of intervention does not involve changing the course or redirecting the channel of the body of water because, to our knowledge, interventions of this kind require a series of studies, surveys, and modeling, including topographic, hydrological and hydraulic, and geological studies, among others. For this reason, in cases involving interventions financed by the CNE, the appellant’s assertion that the river’s course was changed or that the ‘… dredging redirected the river toward the rear of her house …’ is rejected, particularly since no supporting materials or evidence have been provided to substantiate assertions of this kind. 5.
Many of the assertions made by the appellant are based on assumptions that have not been verified. One example is the ‘Technical Memorandum’ prepared by geologist Wagner Valverde Mora, which states in several passages that one factor that may have contributed to erosion of the bank adjoining the appellant’s property was the possibility that, at some point, a ‘dike’ may have existed on the opposite bank and that, had this been the case, it would have contributed to the erosive action on the bank of the appellant’s property. It should even be noted that section 3 CONCLUSIONS of that Technical Memorandum states: ‘– It is possible that some structure may have been built from the right bank toward the center of the channel (“dike”), …’ 6. In addition to the foregoing, factors contributing to increased flow in the Nandayure River do not appear to have been considered, including climate change, deforestation, the soil’s absorption capacity, the La Niña phenomenon, and many others that will cause the flow of the Nombre20770 River to increase at specific times.
It must likewise be remembered that the Nombre20770 River, like all bodies of water, undergoes changes in its dynamics, widens or narrows its cross-sections, and may alter its course depending on the conditions and characteristics existing at any particular time. Responsibility or blame for the effects of erosive action should therefore not be assigned on the basis of assumptions or subjective assessments. To supplement the foregoing response, the following table shows the interventions carried out in the Nombre20770 River in the community of San Nombre41 ID PROCEDURE NUMBER CONTRACT PURPOSE PROVINCE CANTON DISTRICT Nombre62 CONTRACTOR AWARDED AMOUNT 1 2019PI-000008-0006500001 Rental of machinery to address the emergency in the community of San Pablo, Nandayure River, Nombre20770 Guanacaste Nombre20770 San Nombre41 Constructora Hermanos Herrera Barrantes ₡ 14 823 650, 00 2 2020PI-000374-0006500001 Cleaning and re-excavation of the Nandayure River channel to prevent further river overflows that could affect communities and infrastructure Guanacaste Nombre20770 San Nombre41 Constructora MECO, S.A ₡22 093 647, 00 TOTAL ₡ 36 917 297,00 .” (See documentary evidence).
This fluvial mobility poses a danger to engineering works located on and near the riverbed (lecho fluvial), which by their very nature must be stable. In other words, the scale of the problem cannot be addressed solely by dredging (dragado) the channel; we must go further. The work carried out in recent years has consisted of channelization works (obras de encauzamiento) formed by parallel dikes (diques), and when the flow rates (caudales) are sufficiently high, they destroy the works constructed using material from the channel; because of the river’s sinuosity, the water overflows and directly strikes the protective barriers constructed using specialized equipment. • Assessment of the Situation and Municipal Action We understand the concerns of all the communities adjoining the Río Nandayure; this has generated a municipal commitment to seek longer-lasting solutions, duly coordinated with the competent institutions, Comisión Nacional de Emergencias and Ministerio de Obras Públicas y Transportes.
We note that we have worked on this problem in coordination with those institutions, but the synergy has not been sufficient to provide a lasting, comprehensive solution. We continue using the same dredging techniques and hourly machinery work, which provide a solution only for the winter season—and most of the time not even for that period—and work is performed only at critical erosion-prone points, without assessing other aspects of the management and development of fluvial morphology. By this, we intend to highlight and acknowledge the efforts that we have individually made in seeking solutions; however, Comisión Nacional de Emergencias and Ministerio de Obras Públicas y Transportes—the latter being the governing authority for fluvial matters—must participate more actively, with their professionals, machinery, and equipment, in the various hydrological and hydraulic studies required to provide solutions that endure over time and contribute to the regeneration of the area’s native natural environment.
Comisión Nacional de Emergencias CNE has made countless visits over time to the channel of the Río Nandayure, for which we are grateful, but we believe that what is stated in the document–report INFORME TÉCNICO CNE-UIAR-INF-1193-2021, risk assessment (valoración de riesgo) along the banks of the Río Nombre20770 in the locality of San Nombre41 Viejo due to problems of lateral erosion and flooding of the sector, is not sufficient. Its assessment is of critical importance, but we require greater support and more resources for the emergencies that have occurred. Indeed, through the initial-impact reports prepared under the Decreto de Nate, we have requested consideration of the inclusion of major preventive and corrective works to minimize the latent risk suffered each winter by the communities of Carmona and Puerto San Pablo. Accordingly, we call for teamwork among the three institutions, not merely to provide basic preventive solutions, but rather to create a professional interinstitutional working team to contribute more lasting and efficient hydraulic solutions for the benefit of the affected communities. • Municipal Proposal, 2020 Period In June 2020, work was performed jointly with Ministerio de Obras Públicas y Transportes.
The scope of the work was the dredging of the channel in the community of San Nombre41, both upstream and downstream from the referenced point; MOPT supplied specialized equipment, an excavator, and a crawler tractor to construct the lateral containment dikes or protective barriers for the adjoining properties. However (sic), because the same sandy material from the river was used, runoff (escorrentías) occurring during previous periods affected (sic) the parallel containment structures; that work was performed directly behind the property of Ms. [Nombre62 001], as can be seen in the following photograph (sic). (…) Work performed in 2020: protection of adjoining properties with parallel dikes to prevent the Río Nandayure from overflowing. Subsequently, in July 2022, Municipalidad de Nombre20770 performed dredging work in the channel specifically at the site known as San Pablo, to improve the hydraulic area (área hidráulica) (sic) of the channel section, because at this point the river overflows, cutting off passage along the cantonal road (sic) connecting to Puerto San Pablo.
In this manner, we have worked in coordination with the water directorate of MINAE to obtain the corresponding authorization and thus address the most critical points; nevertheless, we emphasize that the works performed are insufficient to contain and dissipate the water’s energy. (…) Municipal Proposal, 2023 Period In following up on the problem affecting the channel of the Río Nandayure, Municipalidad de Nombre20770 has been working on its critical sections, carrying out dredging and channelization and forming a lateral dike with material from the channel itself, which helps improve and strengthen the channeling (sic) of the flow. It should be noted that in April 2023, work using municipal equipment began at coordinates (sic) N 10 2 6.704 W 85 13 25.525, with the objective of reinforcing with material those areas prone to overflow, as can be seen in the following photographs. (…) In this manner, the Municipality will continue working along the Río Nombre20770, including in the area affecting the property of Ms. [Nombre62 001], using the excavator to form dikes with their respective crests (coronas) and respecting the channel’s original meanders.
On 18 de agosto de 2022, a visit to each of the critical points in the channel of the Río Nandayure, primarily in the community of Puerto San Pablo, was coordinated and arranged with CNE technical personnel; this resulted in a series of technical recommendations to prevent the river from overflowing. Those recommendations require the preparation of a work plan accompanied by technical and financial resources from Ministerio de Obras Públicas y Transportes (MOPT), Comisión Nacional de Emergencias (CNE), and this municipality. • Municipal Technical Proposal to Minimize Flood Risk (sic) The Municipality (sic) has been analyzing the technical and financial (sic) feasibility of using (sic) a structure known as a high-strength, weather-resistant (sic), prismatic textile structural hydroblock geocontainer (geocontendor estructural textil hidroblock prismático), which is filled with material existing in the channel by mechanical or hydraulic means, using the gravel-type soil at the site, to create large-volume mass units that can be arranged flexibly on the terrain.
Because of their shape and size, they are used in the construction of gravity structures (estructuras de gravedad), on the faces of walls in reinforced soils, in hydraulic-control structures, for bank erosion control, rehabilitation of eroded banks, lining of dikes, embankments (terraplenes), channel slopes (taludes de cauces), bank raising, crest raising on hydraulic-control structures, and pipeline protection. This solution is feasible for strengthening the channel sections that exhibit severe erosion of the natural slopes adjoining yards and homes that have been affected by flooding of the Río Nandayure. Its cost is significant and requires an extraordinary budget; the advantage of this structure is that its cost as an input or component is offset by the use of on-site material, since we would not have to purchase a large quantity of oversized granular material, which would exponentially increase project costs. • Technical Proposal with the Support of CNE–MOPT–MINAE–MUNICIPALIDAD We require interinstitutional support, based on the following areas of authority, to address the critical points through short- and medium-term scheduling according to the resources available to each institution.
Requirements to be requested from MOPT • Hydrological Studies • Hydraulic Studies • Availability of Machinery and Equipment • Professional Technical Support Requirements to be requested from CNE: • Financial resources to purchase prismatic textile structural hydroblock geocontainers. • Continue the vulnerability study and risk assessment along the banks of the Río Nandayure for the remaining sector between Puente Carmona and the community of San Pablo. • Professional Technical Support • Availability of Machinery and Equipment (machinery hours). • Follow up on the commitments arising from the Decreto Nate, which remains (sic) in force and could be used to secure the resources necessary to contribute to the proposed solution. Requirements to be requested from MINAE: • Conduct the studies necessary to perform works in a publicly owned channel (cauce de dominio público). • Professional Technical Support Requirements to be requested from Municipalidad Nandayure: • Financial resources to purchase prismatic textile structural hydroblock geocontainers. • Availability of Machinery and Equipment • Professional Technical Support • Liaison coordination (sic) among the specified institutions.
Regarding the implementation time frames for the 2023 period As a Municipality, we have begun the preliminary-design study (estudio de anteproyecto) of the points to be addressed in order to estimate the costs of each subproject. An extraordinary budget will now be submitted for the purchase of approximately 3.393 prismatic hydroblock units to address the most critical points where the Río Nombre20770 overflows. We reiterate that, as a Municipality, we do not have all the necessary resources, and therefore insist that a working commission be created to plan and execute the works within an appropriate time frame to prevent further tragedies (sic) affecting the residents of Carmona, San Nombre41, and Puerto San Nombre41.” (See documentary evidence (prueba documental)).
Regarding the use of the system known as Hydroblock, it should be noted that when Mr. Nombre11504, the appellant’s husband, appeared at the Municipalidad to inquire about the status of the river works, he was told that personnel had attended training to learn about a new construction system called Hydroblock. The system and how it works were explained to him, and he was also informed that efforts were being made to include it in the budget so that these bags could be purchased and testing could begin at some of the most problematic locations in the canton, provided the budget was approved. However, at no time was he told that it would be used on his property because, as mentioned above, tests first had to be performed to determine whether the system would be functionally suitable for solving the problem that exists not only on the gentleman’s land but also at other locations along the river, which has a problematic channel (cauce) extending for slightly more than 13 kilometers, at least from the bridge at the entrance to the city of Carmona to its mouth at Puerto de San Pablo.
The attached figure shows that the Nombre20770 River has two potential flood areas that directly affect the Comunidad de Carmona, a population center, and the community of Puerto San Pablo. The river flows from a high point toward a very flat area, a situation that causes the channel to overflow and consequently directly affects adjoining properties. Over the past 10 years, the channel of the Nombre20770 River has undergone changes in its fluvial morphology (morfología fluvial). Because of the river’s mobility, the adjoining areas lack stability and permanence; they shift and change more than might ordinarily be imagined, given the river’s aforementioned inherent characteristics (its movement from a high point toward a very flat area). This fluvial mobility poses a danger to engineering works located on and near the riverbed (lecho fluvial), which by their very nature must be stable. In other words, the magnitude of the problem cannot be resolved solely by dredging the channel; we must go further.
The work performed in recent years has consisted of channelization works (obras de encauzamiento) formed by parallel levees (diques), but because the flows are sufficiently large, they destroy the works constructed with materials from the channel and, due to the river’s sinuosity, overflow and strike head-on the defenses built using specialized equipment. 2. State whether the budget has already been requested or approved. The budget was submitted to the Concejo Municipal; unfortunately, it was rejected by that body. This is compounded by the rejection of the most recent budgets by the Contraloría General de la República. 3. When are the works expected to begin? The works may be performed once budgetary funds are available and the corresponding permits for intervention in the river have been processed before the Dirección de Aguas del Ministerio del Ambiente y Energía (MINAE). 4. What is the current condition of the channel of the Nandayure River?
The river is currently prone to overflowing in certain sectors, as stated above; however, as regards the land and home of Ms. [Nombre62 001], the home is outside the river’s protection zone (zona de protección) and, to date, is not at any risk of flooding. 5. Have the residents been contacted to explain the works to be performed and the applicable timeframe? I must state that no large meeting has been held with the residents to explain the works to be performed. However, when other intervention work has been carried out at certain points along the channel, in coordination among the Municipalidad de Nandayure, MOPT, and the Comisión de Emergencias, the residents have indeed been informed. In fact, only approximately 15 days ago, the area where the appellant’s home is located was visited, and I met with her and her husband. They were informed of the work that might be performed in the medium term, as well as the problems affecting the Nombre20770 River throughout its channel, primarily from the bridge at the entrance to Ciudad Carmona to the river’s mouth at Puerto San Pablo, which is precisely the problematic flat section because of the force of the river’s flow.
They have also been informed that we currently have no permit to intervene in the river, although we are presently processing an initial impact authorization for the river so that intervention may be undertaken at the most critical points along it.” (See report submitted).
This Court has previously examined the situation caused by the Nandayure River. Thus, in judgment no. 2022027316, issued at 9:29 on November 18, 2022, it held:
“III.- REGARDING THE SPECIFIC CASE. In the sub lite, the appellant states that he is a resident of San Nombre41 de Nandayure, an area affected by flooding caused by the Nandayure River. He alleges that he has requested assistance from the respondent authorities so that the necessary works may be performed to solve the flooding problem; nevertheless, the situation remains unchanged. He adds that, during the current year, the aforementioned river destroyed trees, fences, utility poles, and crops.
The case file establishes that the respondent municipality reports that Río Nombre20770 has two flood zones (áreas de inundación), which affect the communities of Carmona and San Pablo. In March 2020, the MOPT River Works Directorate carried out clearing and channelization (canalización) work on Río Nandayure as part of the measures to mitigate the effects of rainfall. The president of the CNE reports: “From 2018 to date, this Commission processed the following requests from the Municipalidad de Nandayure: 1) 2019PI-000008-0006500001 ‘Rental of Machinery to Respond to the Emergency in the Community of San Pablo, Río Nandayure, Nombre20770 5th Occasion,’ awarded on 23 de enero de 2019 to Empresa Hermanos Herrera Barrantes Constructora, Sociedad Anónima, for 150 effective hours of an excavator and 150 effective hours of a tractor, for the purpose of clearing and re-excavating Río Nandayure and piling material along the sides in the form of a dike, in order to prevent or mitigate overflows and further impacts in the area of the community of San Nombre41; and 2) 2020PI-000374-0006500001 ‘Rental of Machinery to Address Impacts in San Pablo, Overflow of Río Nandayure,’ awarded on 11 de diciembre de 2020 to Constructora Meco, Sociedad Anónima, for 150 effective hours of a tractor and 150 effective hours of an excavator, in order to address the undeclared emergency, with the purpose of clearing and re-excavating the riverbed (cauce) of Río Nombre20770 in the community of San Pablo, Nandayure, so as to prevent further river overflows that could affect the communities and infrastructure.” Technical report no. CNE-UIAR-INF-1193-2021 of septiembre de 2022, issued by the CNE Risk Research and Analysis Unit, stated: “Risk assessment (valoración de riesgo) along the banks of Río Nombre20770 in the locality of San Nombre41 Viejo, due to problems of lateral erosion and waterlogging in the area (…) Conclusions: A. According to the CNE Potential Natural Hazards Map, the evaluated zones are located within the area directly affected by potential flooding when the flow of Río Nombre20770 and its tributaries overflows in the plain, generally as a result of intense rainfall in the upper part of the micro-watersheds due to the influence of extreme hydrometeorological phenomena.
B. The evaluated area in the locality of San Nombre41 Viejo is located within the Río Nandayure micro-watershed, on the left bank. The evaluated zone lies within the area corresponding to the riverbed and alluvial plain (planicie aluvial), along the edges of alluvial terraces formed through the accretion of sediments deposited after extraordinary flooding events. C. The evaluated zone in the village of San Nombre41 Viejo de Nombre20770 has flat, rolling topography and is located at the point where the riverbed ceases to be confined within the river canyon and opens onto the alluvial plain. It has varied vegetation cover, with scattered trees and some residential structures built within zones that have been affected by waterlogging in the past. In addition, a local road runs parallel to the riverbed and is affected when overflow events occur. D. In the evaluated area running parallel to the riverbed of Río Nombre20770, severe lateral erosion is observed along the banks because the flow strikes these zones with great force.
Throughout the river’s lower section, there is a high degree of sedimentation and accumulation of materials that have completely filled it, causing a significant loss of hydraulic capacity (capacidad hidráulica) and facilitating overflow events when heavy rainfall occurs. E. The overflight conducted using unmanned aerial equipment (drone) revealed evidence of overflow events, waterlogging, and debris deposits along the banks of the plain, where several homes are located. There is evidence of the current and the debris carried by the flow crossing the municipal road leading to San Nombre41 Viejo and continuing toward neighboring lands. F. At Quebrada Pozas, which crosses the road leading to San Nombre41 Viejo, problems are observed at the crossing bridge, which becomes obstructed by debris and causes the flow to overflow. This problem blocks passage, isolates the village, and leaves residents with no way out because this is the only road providing access to the community (…) Recommendations.
A. The Municipalidad de Nandayure shall coordinate with the MOPT River Works Directorate and MINAE regarding the possibility of carrying out proper channelization of the riverbed of Río Nombre20770 at the evaluated sites where problems exist, in order to remove the accumulated material that reduces the hydraulic capacity of the sections, and shall also construct protective works (obras de protección) to reduce lateral erosion along the banks and protective dikes. B. The Municipalidad de Nombre20770 shall construct adequate protective and retaining works along the banks of Río Nandayure, using materials that will not be eroded by extraordinary floods and that will protect the affected areas. C. The Municipalidad de Nombre20770 shall restrict land use (uso de suelo) for residential or commercial purposes within the protected zones (zonas de protección) of Río Nandayure, pursuant to Article 33 of Ley Forestal 7575, as well as within areas identified as potentially affected by flooding according to the CNE natural hazard maps.
D. Protective works implemented along the affected banks must be supervised by a professional affiliated with the Colegio Federado de Ingenieros y Arquitectos de Costa Rica, in accordance with the standards established by the Código Sísmico, Código de Cimentaciones y Reglamento de Construcciones, Código Municipal, and other legislation in force. E. The Municipalidad de Nombre20770 shall periodically carry out proper channelization, according to the extent of material accumulation in the riverbed of Río Nombre20770 and all other watercourses draining the canton, to help restore the hydraulic capacity of the riverbed and reduce the threat of flooding in each area. F. The Municipalidad de Nombre20770 shall remain vigilant over zones at high risk of flooding and susceptible to landslides and shall not grant construction permits or allow the development of informal residential settlements within them.
G. Any irregularity concerning construction techniques or any failure to follow the recommendations described herein SHALL BE THE SOLE RESPONSIBILITY of the institutions granting the permits, the engineer or person responsible for the work, and the respective municipality if it fails to request the corresponding reports, inspections, and corrections.” The mayor of the Municipalidad de Nombre20770 states that dredging (dragado) techniques and other work have been carried out to counteract flooding during the rainy season; however, those actions have proved insufficient, and a lasting comprehensive solution has not been achieved. On 18 de agosto de 2022, the Municipalidad de Nombre20770 and the CNE visited each of the critical points in the community of San Pablo. The respondent municipality reports that it has begun studying a preliminary project (anteproyecto) for intervention in the river; however, it requires the participation of the other respondent agencies to plan and execute the respective works in order to resolve the problem alleged.
In this regard, it is important to emphasize that, in Judgment no. 2019018960 issued at 9:20 hours on 4 de octubre de 2019, this Court ruled on an amparo proceeding (recurso de amparo) filed by the petitioner concerning the problems affecting Río Nandayure. That decision stated:
“I.- Subject matter of the proceeding. The petitioners allege that they have submitted several requests seeking the dredging of Río Nandayure in the San Pablo area and, to date, have received no response, nor have the corresponding actions been carried out (…)
IV.Merits. In light of Article 41 of the Political Constitution, the Administration has an obligation to guarantee the public prompt and effective justice, without denial thereof. In the field of administrative justice, this entails its obligation to decide claims filed by members of the public diligently and expeditiously, such that its decision is consistent with the matters alleged, and to notify the interested parties of that decision, all within a reasonable period. In the case under review, the Chamber finds a violation of Article 41 of the Political Constitution because the respondent party had not resolved the petitions filed by the petitioners and other residents since 6 de noviembre de 2018 and reiterated on 26 de abril and 13 de junio, both in 2019, which demonstrates a violation of the fundamental right to prompt and effective justice. Moreover, it was only upon service of this amparo proceeding that the respondent authority proceeded to decide the petitioners’ request. Consequently, the proceeding is granted with respect to this claim.
V.Furthermore, although the record does not currently establish that Río Nombre20770 must be dredged in the area identified by the petitioners, since certainty in that regard requires technical studies by the competent authorities, the fact remains that, given the uncertainty and because flooding last year damaged the work already completed, the ‘principle of prudent avoidance or precautionary principle’ (principio de evitación prudente o precautorio) must be applied with respect to the potential harm that an overflow of the riverbed could cause to the health and physical integrity of the people living in that community, as well as to their homes, including ecosystem disruption, erosion, destruction of roads and crops, and harm to the health and well-being of wildlife and livestock, among other effects. Accordingly, under that principle, and given the evidence that there may be a risk of serious or irreversible harm, the proper course is to act so as to minimize, to the greatest extent possible, the risks that this situation may cause.
In addition, the petitioners seek the clearing and deepening of the river in question in the San Pablo area, as well as the removal of rocks and sediment to increase its depth. Translating that request into constitutional terms, the Chamber must therefore grant the proceeding and order the Municipal Mayor, in coordination with the competent agencies of the River Works Directorate and the Regional Directorate of the Ministerio de Obras Públicas y Transportes, to conduct the technical studies identified by those authorities—namely, a hydrological study (estudio hidrológico) and two-dimensional hydraulic modeling (modelación hidráulica en dos dimensiones)—to determine with certainty the type of hydraulic structure to be constructed and whether the existing infrastructure is located within the river’s protected zone, so that the problem may be resolved. The foregoing is based on Article 15 of the ‘Declaración de Río,’ adopted by the United Nations Conference on Environment and Development in junio de 1992, which provides:
‘In order to protect the environment, States shall broadly apply the precautionary approach according to their capabilities. Where there is a risk of serious or irreversible harm, the lack of absolute scientific certainty shall not be used as a reason for postponing cost-effective measures to prevent environmental degradation.’” In accordance with the foregoing, it is necessary to emphasize that adherence to a principle may be rational or irrational, and the case of prudent avoidance is no exception. Indeed, it is clear that the principle in question, as “prudent avoidance,” is merely a recommendation, temporarily in force, that certain preventive measures be implemented. Thus, by virtue of the foregoing and in application of the precautionary principle (principio precautorio), the appropriate course is to grant the petition, solely with respect to this issue.
Por tanto:
The petition is granted. Giovanni Jiménez Gómez, in his capacity as Mayor of the Municipalidad de Nandayure, or whoever holds that office, is ordered, within EIGHT MONTHS of service of this judgment, in coordination with the authorities of the Dirección de Obras Fluviales and the Macro Región de Guanacaste, both of the Ministerio de Obras Públicas y Transportes, to conduct and obtain the results of the applicable hydrological study (estudio hidrológico) and hydraulic modeling (modelación hidráulica), in order to determine with certainty the type of hydraulic structure (obra hidráulica) to be built and to identify whether the existing infrastructure is located within the protection zone (zona de protección) of the río Nadanyure, for the purpose of resolving the overflow problem occurring in the San Pablo area. The foregoing is ordered with the warning that failure to comply may constitute the offense provided for in artículo 71, of the Ley de la Jurisdicción Constitucional.
The Municipalidad de Nandayure is ordered to pay the costs, damages, and losses caused by the facts underlying this ruling, which shall be assessed in proceedings to enforce the judgment before the administrative-law court. This decision shall be personally served on the respondent, as well as on Jenaro Ruiz Chacón and Alonso Mora Arroyo, respectively Acting Director of the Dirección de Obras Fluviales and Director of the Macro Región de Guanacaste, both of the Ministerio de Obras Públicas y Transportes, or whoever holds those offices.” Now then, as may be seen, in the precedent transcribed supra, the conduct of certain studies that were pending at that time and that would serve to address the flooding problem in the river at issue was ordered. Nevertheless, approximately 3 years later, the flooding situation evidently persists, and the works necessary to achieve a comprehensive and definitive solution have not been carried out.
In this regard, although the Municipalidad de Nombre20770 and the Dirección de Obras Fluviales of MOPT have carried out various mitigation works (obras paliativas), such as dredging (dragados) and other cleaning and channelization work (canalización), it is equally true that those actions have proved insufficient. In this respect, the respondent municipality itself acknowledges that greater efforts are necessary to carry out lasting works that remedy the alleged problem. Likewise, technical report CNE-UIAR-INF-1193-2021 of septiembre de 2022, issued by the Unidad de Investigación y Análisis de Riesgo of CNE, stated that greater interventions and actions by the respondent municipality were necessary.
Accordingly, although the authorities of the Municipalidad de Nombre20770 and the Dirección de Obras Fluviales of MOPT have known of the problem at issue for at least 3 years and have performed certain mitigation work, they have not taken the necessary action to achieve a comprehensive and definitive solution that guarantees the safety of the community of San Nombre41 de Nandayure.
Thus, the appropriate course is to grant the petition with respect to those agencies, in order to guarantee a comprehensive solution within a reasonable period.
IV- On the other hand, with respect to the Comisión Nacional de Prevención de Riesgos y Atención de Emergencias, a priori, there is no omission warranting a ruling through this summary proceeding (vía sumaria).
In this regard, it was reported under oath that the requests for assistance processed by the Municipalidad de Nombre20770 were duly addressed, and the procurements requested in proceedings 2019PI-000008-0006500001 and 2020PI-000374-0006500001 were carried out. Likewise, the respective inspection was conducted, and report CNE-UIAR-INF-1193-2021 of septiembre de 2022 detailed the recommendations pertaining to the works that the aforementioned municipality must perform.
Consequently, the appropriate course is to deny the petition with respect to this issue. However, the President of the Comisión Nacional de Prevención del Riesgo y Atención de Emergencias shall take note so that, if requested, within the scope of its authority, it may assist the Municipalidad de Nombre20770 and the Dirección de Obras Fluviales of MOPT in resolving the problem that is the subject of this petition. (…)
Por tanto:
The petition is partially granted, solely with respect to the Municipalidad de Nombre20770 and the Ministerio de Obras Públicas y Transportes. Jenaro Ruiz Chacón and Giovanni Jiménez Gómez, respectively Acting Director of the Dirección de Obras Fluviales of the Ministerio de Obras Públicas y Transportes and Mayor of Nandayure, or whoever respectively holds those offices, are ordered to coordinate the relevant actions, issue the pertinent orders, and take all measures within the scope of their respective authority so that, within a maximum period of TWELVE MONTHS from service of this judgment, all necessary measures and works are undertaken to resolve comprehensively and definitively the flooding problem of the Río Nandayure, which affects the community of San Nombre41 de Nandayure. They are warned that, pursuant to artículo 71, of the Ley de la Jurisdicción Constitucional, imprisonment for three months to two years, or a fine of twenty to sixty days, shall be imposed on anyone who receives an order issued in an amparo action (recurso de amparo) that must be complied with or enforced and fails to comply with or enforce it, provided that the offense is not subject to a more severe penalty.
The State and the Municipalidad de Nombre20770 are ordered to pay the costs, damages, and losses caused by the facts underlying this ruling, which shall be assessed in proceedings to enforce the judgment before the administrative-law court. In all other respects, the petition is denied. The Comisión Nacional de Prevención de Riesgos y Atención de Emergencias shall take note of what is stated in fine in recital IV (considerando IV) of this judgment. Justice Garro Vargas dissents with respect to the enforcement of this judgment and, pursuant to artículo 56 of the Ley de la Jurisdicción Constitucional, orders that enforcement be conducted before the Área de Ejecución del Tribunal Contencioso Administrativo y Civil de Hacienda, under the enforcement rules established in artículos 155 et seq. of the Código Procesal Contencioso Administrativo. She further orders that a copy of the judgment be transmitted thereto so that proceedings to enforce this ruling may be initiated. Let notice be given.”
In this case, the petitioner states that she is a resident of San Nombre41 de Nombre20770 and that her property lies within the area affected by flooding caused by the río Nandayure. She alleges that, in the year 2018, the respondent authorities performed dredging work in that river; however, the work was performed defectively because it altered the river’s normal course, with the result that the rains destroyed the works that same year. She asserts that the dredging redirected the river toward the rear of her home and that she therefore fears the flow will wash away her house. She alleges that in agosto de 2022 she went to the Comisión Nacional de Emergencias, where she was told that the matter fell within the authority of MOPT. She recounts that in setiembre de 2022 she approached the Departamento de Aguas Fluviales y Pluviales of MOPT, but was told there that it had no budget and that “the river can be accessed only through an amparo action.” She explains that the residents and the Municipalidad de Nombre20770 have held meetings concerning the problem and that, on 12 de abril de 2023, they were informed that mitigation works would begin on the following 1° de mayo, but that definitive works to resolve the problem could not be carried out because the Comisión Nacional de Emergencias had authorized only 300 hours of work.
She adds that, in the year 2022, the problem worsened because the river current swept away trees and fences, causing severe ecological damage. She requests a definitive, rather than mitigative, solution to the problem involving the río Nandayure, which is threatening her home as well as those of 26 other families, who are already raising their belongings onto pallets to avoid losing them during the next rainy season.
In this regard, the Chamber finds it proven that the Río Nombre20770 has two flood areas (áreas de inundación), which affect the communities of Carmona and San Pablo. In julio de 2018, the Dirección de Obras Fluviales of the Ministerio de Obras Públicas y Transportes carried out cleaning and channelization of the Río Nandayure as mitigation work in the locality of San Pablo. On 6 de noviembre de 2018, the residents of San Nombre41 de Nombre20770 requested that the Municipalidad de Nombre20770 dredge the river because its flow had risen and destroyed the work performed. On 13 de junio de 2019, the residents asked the respondent mayor to dredge the río Nombre20770 in the San Pablo sector because the heavy rains of the previous year had destroyed the work performed and, when the river rises, water enters their homes. In marzo de 2020, the Dirección de Obras Fluviales of MOPT performed cleaning and channelization work in the Río Nandayure as part of the measures to mitigate the effects of the rains.
Subsequently, technical report No. CNE-UIAR-INF-1193-2021 of septiembre de 2022, issued by the CNE Risk Research and Analysis Unit, stated: “Risk assessment (valoración de riesgo) along the banks of the Nombre20770 River in the locality of San Nombre41 Viejo, due to lateral erosion (erosión lateral) and waterlogging (anegamiento) in the sector (…) Conclusions: A. According to the CNE Potential Natural Hazards Map (Mapa de Amenazas Naturales Potenciales), the evaluated areas are located within the area directly affected by potential flooding (inundaciones potenciales) when the Nombre20770 River and its tributaries overflow in the plains area, generally when intense rainfall occurs in the upper portion of the micro-watersheds (microcuencas) due to the influence of extreme hydrometeorological phenomena. B. The sector evaluated in the locality of San Nombre41 Viejo is located within the Nandayure River micro-watershed, on the left bank.
The evaluated area lies within the river channel (cauce del río) and alluvial plain (planicie aluvial), along the edges of the alluvial terraces (terrazas aluvionales) formed through the accretion of sediments deposited following extraordinary flood events. C. The area evaluated in the village of San Nombre41 Viejo de Nombre20770 has flat, undulating topography and is located at the point where the channel transitions from being confined within the river canyon to opening onto the alluvial plain. It has varied ground cover, with scattered trees and some residential structures built within areas that have been affected by waterlogging in the past. In addition, a local road runs parallel to the channel and is affected when overflow events occur. D. In the evaluated sector running parallel to the channel of the Nombre20770 River, severe lateral erosion is observed along the banks because the flow strikes these areas with great force.
Throughout the river’s lower section, there is extensive sedimentation and infilling (colmatación) by materials that have completely filled it, causing a significant loss of hydraulic capacity (capacidad hidráulica) and facilitating overflow events during heavy rainfall. E. The overflight conducted using an unmanned aerial vehicle (drone) revealed evidence of overflow events, waterlogging, and debris deposits along the banks on the plain, where several homes are located. There is evidence of the current and the debris carried by the flow crossing the municipal road leading to San Nombre41 Viejo and continuing toward adjacent land. F. At Pozas Creek, which crosses the road leading to San Nombre41 Viejo, problems are observed at the crossing bridge, which becomes blocked by debris and causes the flow to overflow. This problem interrupts passage, isolates the village, and leaves residents with no way out because this is the only access route to the community (…) Recommendations.
A. The Municipality of Nombre20770 shall coordinate with the MOPT River Works Division and MINAE regarding the possibility of carrying out proper channelization (canalización) of the Nombre20770 River channel at the evaluated sites experiencing problems, in order to remove the accumulated material that reduces the hydraulic capacity of the sections and, additionally, to undertake protective works (obras de protección) to reduce lateral erosion along the banks and protective levees (diques de protección). B. The Municipality of Nombre20770 shall construct appropriate bank-protection and retaining works along the banks of the Nandayure River, using materials that will not be eroded by extraordinary floods and that will protect the sectors. C. The Municipality of Nombre20770 shall restrict land use (uso de suelo) for residential or commercial purposes within the protection zones (zonas de protección) of the Nandayure River, pursuant to Article 33 of Ley Forestal 7575, as well as in areas identified as potentially affected by flooding, according to the CNE natural hazard maps.
D. The protective works implemented along the affected banks must be supervised by a professional registered with the Colegio Federado de Ingenieros y Arquitectos de Costa Rica, in accordance with the standards established by the Seismic Code (Código Sísmico), Foundations Code (Código de Cimentaciones), Construction Regulations (Reglamento de Construcciones), Municipal Code (Código Municipal), and other legislation in force. E. Depending on the degree of material accumulation in the Nombre20770 River channel and all other channels draining the canton, the Municipality of Nombre20770 shall periodically carry out proper channelization to help restore the channel’s hydraulic capacity and reduce the flood hazard (amenaza de inundación) in each sector. F. The Municipality of Nombre20770 shall remain vigilant over high-risk areas (zonas de alto riesgo), flood-prone areas, and areas susceptible to landslides, and shall not grant construction permits or allow the development of informal housing settlements in those areas.
G. Any irregularity concerning construction techniques or failure to comply with the recommendations described herein SHALL BE THE SOLE RESPONSIBILITY of the institutions granting the permits, the engineer or person responsible for the works, and the respective Municipality should it fail to request the corresponding reports, inspections, and corrections.” Likewise, in official letter CNE-UGPR-OF-0669-2023 of 21 de abril de 2023, the CNE Reconstruction Process Management Unit stated: “With reference to the amparo proceeding (Recurso de Amparo), expediente 23-007675-0007- CO, filed by Ms. [Nombre62 001], a resident of the community of San Nombre41 in Nandayure, against the Municipality of Nombre20770 concerning the damage caused to her property by the overflowing of the Nombre20770 River and the dredging work that has been performed, the following is reported: 1. To date, the CNE has addressed all impacts reported at the time by the Municipality of Nombre20770 in the sector, most of which involved requests for intervention through the processes known as initial-impact response (primeros impactos), regulated within the legal framework of Ley 8488, Ley Nacional de Emergencias y Prevención del Riesgo. 2.
The canton of Nandayure is not included among the decrees currently in force. 3. The type of intervention carried out consists of contracting machine hours to remove material and sediment from the center of the channel and pile it along the banks, thereby facilitating better channeling of the water flow and reducing the risk of the river overflowing. These interventions were performed in response to the request and impact report issued by the Municipality, which is also responsible for supervising and properly using the contracted hours. 4. This type of intervention does not involve changing the course or redirecting the channel of the body of water, since we are aware that interventions of this kind require a series of studies, surveys, and models, including topographical, hydrological and hydraulic, and geological studies, among others. For that reason, with respect to interventions financed by the CNE, the appellant’s assertion that the course was changed or that the ‘… dredging redirected the river toward the rear of her house …’ is rejected, particularly since no supporting documentation or evidence was submitted to substantiate such assertions. 5.
Many of the assertions made by the appellant are based on assumptions that have not been verified. One example is the ‘Technical Note’ prepared by geologist Wagner Valverde Mora, which indicates in several excerpts that one factor that may have contributed to erosion of the bank adjoining the appellant’s property was the supposition that a ‘levee’ (dique) may at some point have existed on the opposite bank and that, if it did, this may have contributed to the erosive action along the bank on the appellant’s property. Indeed, section 3 CONCLUSIONS of that Technical Note states: ‘– It is possible that some structure may have been built from the right bank toward the center of the channel (“levee”), …’ 6. In addition to the foregoing, it appears that no consideration is given to factors that increase the flow of the Nandayure River, including climate change, deforestation, the soil’s absorption capacity, the La Niña phenomenon, and many others that cause the flow of the Nombre20770 River to increase at particular times.
Likewise, it must be remembered that the Nombre20770 River, like all bodies of water, varies in its dynamics, widens or narrows its sections, and may change course depending on the conditions and characteristics existing at each particular time. Responsibility or blame for the effects of erosive action should therefore not be assigned on the basis of assumptions or subjective assessments. To supplement the foregoing response, the following table shows the interventions carried out in the Nombre20770 River in the community of San Nombre41 ID PROCEDURE NUMBER CONTRACT PURPOSE PROVINCE CANTON DISTRICT Nombre62 AWARDEE AMOUNT AWARDED 1 2019PI-000008-0006500001 Rental of machinery to address the emergency in the community of San Pablo, Nandayure River, Nombre20770 Guanacaste Nombre20770 San Nombre41 Constructora Hermanos Herrera Barrantes ₡ 14 823 650, 00 2 2020PI-000374-0006500001 Cleaning and re-excavation of the Nandayure River channel to prevent further river overflows that could affect communities and infrastructure Guanacaste Nombre20770 San Nombre41 Constructora MECO, S.A ₡22 093 647, 00 TOTAL ₡ 36 917 297,00 Furthermore, it is established that, by means of official letter AM-AA-0441-2023 dated 28 de abril de 2023, the mayor of Nombre20770 stated: “Greetings; below, we will respond to the proceeding filed by Ms. [Nombre62 001] regarding the work performed in the channel (cauce) of the Río Nombre20770 in 2020, as well as our commitment to and monitoring of the natural problem affecting the Río Nandayure, specifically from the Puente de Carmona to its mouth at Puerto de San Pablo. • General Considerations As may be seen in the attached figure, the Río Nombre20770 has two areas potentially subject to flooding, which directly affect the town center of the Comunidad de Carmona and the Comunidad de Puerto San Pablo.
The river flows from a high point toward a very flat area, causing the channel to overflow and, consequently, directly affecting adjoining properties. Over the last 10 years, the channel of the Río Nombre20770 has undergone changes in its fluvial morphology (morfología fluvial); because of its mobility, the adjoining areas have neither stability nor permanence and shift and change more than is commonly imagined. This fluvial mobility poses a danger to engineering works located on and near the riverbed (lecho fluvial), which, by their very nature, must remain stable. In other words, the scale of the problem cannot be addressed solely by dredging (dragado) the channel; we must go further. The work carried out in recent years has consisted of channelization works (obras de encauzamiento) formed by parallel dikes, but when flows are sufficiently high, they destroy the works built using material from the channel; because of the river’s sinuosity, the flows overflow and strike head-on against the defenses constructed using specialized equipment. • Assessment of the Situation and Municipal Action We understand the concerns of all the communities adjoining the Río Nandayure; this has led the municipality to undertake to seek longer-lasting solutions, duly coordinated with the competent institutions, Comisión Nacional de Emergencias and Ministerio de Obras Públicas y Transportes.
We must note that we have worked on this problem in coordination with those institutions, but the synergy has not been sufficient to provide a lasting, comprehensive solution. We continue using the same dredging techniques and hourly machinery work, which provide a solution only for the winter season—and, most of the time, not even for that period—and work is performed only at critical erosion-prone points, without evaluating other aspects of the management and development of fluvial morphology. By this, we intend to acknowledge and highlight the efforts we have individually made in seeking solutions. Nevertheless, Comisión Nacional de Emergencias and Ministerio de Obras Públicas y Transportes—the latter being the governing authority for river matters—must participate more actively through their professionals, machinery, and equipment in the various hydrological and hydraulic studies required to provide lasting solutions that contribute to the regeneration of the area’s native natural environment.
Comisión Nacional de Emergencias CNE has conducted countless visits over time to the channel of the Río Nandayure, for which we are grateful; however, we believe that what is stated in the document/report INFORME TÉCNICO CNE-UIAR-INF-1193-2021, a risk assessment (valoración de riesgo) of the banks of the Río Nombre20770 in the locality of San Nombre41 Viejo due to problems of lateral erosion and flooding of the sector, is insufficient. Its assessment is crucial, but we require greater support and resources for the emergencies that have occurred. Indeed, through the initial-impact reports prepared pursuant to the Decreto de Nate, we have requested consideration of the inclusion of major preventive and corrective works to minimize the latent risk faced each winter by the communities of Carmona and Puerto San Pablo. Accordingly, we call for teamwork among the three institutions, not merely to provide basic preventive solutions, but rather to create a professional interinstitutional working group to contribute longer-lasting and more efficient hydraulic solutions for the benefit of the affected communities. • Municipal Proposal for the 2020 Period In June 2020, work was carried out jointly with Ministerio de Obras Públicas y Transportes.
The scope of the work was the dredging of the channel in the community of San Nombre41, both upstream and downstream from the referenced point. MOPT provided specialized equipment—an excavator and a crawler tractor—to construct lateral containment dikes or protective barriers for adjoining properties. However (sic), because the same sandy material from the river was used, runoff occurring during previous periods affected (sic) the parallel containment structures. This work was performed directly behind the property of Ms. [Nombre62 001], as may be seen in the following photograph (sic). (…) Work performed in 2020: protection of adjoining properties with parallel dikes to prevent the Río Nandayure from overflowing. Subsequently, in July 2022, the Municipalidad de Nombre20770 performed dredging work in the channel at the site known as San Pablo to improve the hydraulic area (sic) of the channel cross-section, because at this point the river overflows and blocks the cantonal road (sic) leading to Puerto San Pablo.
We have thus worked in coordination with the water directorate of MINAE to obtain the respective authorization and thereby address the most critical points. Nevertheless, we reiterate that the works performed are insufficient to contain and dissipate the water’s energy. (…) Municipal Proposal for the 2023 Period As part of the ongoing response to the problem affecting the channel of the Río Nandayure, Municipalidad de Nombre20770 has been working on its critical sections, carrying out dredging and channelization and forming a lateral dike with material from the channel itself, which helps (sic) improve and (sic) strengthen the channeling (sic) of the flow. It should be noted that, in April 2023, work using municipal equipment began at coordinates (sic) N 10 2 6.704 W 85 13 25.525, with the aim of reinforcing with material those areas prone to overflowing, as may be seen in the following photographs.
(…) In this manner, the Municipality will continue working (sic) along the Río Nombre20770, including in the area affecting the property of Ms. [Nombre62 001], using the excavator to construct dikes with their respective crests and respecting the channel’s original meanders. On 18 de agosto de 2022, a visit to each of the critical points along the channel of the Río Nandayure, primarily in the community of Puerto San Pablo, was coordinated (sic) and arranged with CNE technical personnel. The visit yielded a series of technical recommendations to prevent the river from overflowing. Those recommendations require the preparation of a work plan supported by the technical and financial resources of Ministerio de Obras Públicas y Transportes (MOPT), Comisión Nacional de Emergencias (CNE), and this municipality. • Municipal Technical Proposal to Minimize Flood Risk (sic) The Municipality (sic) has been analyzing the technical and financial (sic) feasibility of using (sic) a structure known as a high-weather-resistance prismatic textile structural Hydroblock geocontainer (sic), which is filled with the material available in the channel, using mechanical or hydraulic means and on-site gravel-type soil, to obtain large-volume mass units that can be arranged flexibly on the ground.
Because of their shape and size, they are used to construct gravity structures, wall facings in reinforced soils, hydraulic-control structures, shoreline erosion-control works, rehabilitation of eroded banks, dike linings, embankments, channel slopes, bank raising, crest raising on hydraulic-control structures, and pipeline protection. This solution is feasible for strengthening sections of the channel where the natural slopes adjoining yards and homes are undergoing severe erosion as a result of flooding by the Río Nandayure. Its cost is significant and requires an extraordinary budget. The advantage of this structure is that its cost as a component or input is offset by the use of on-site material, since we would not have to purchase a large quantity of oversized granular material, which would exponentially increase project costs. • Technical Proposal with Support from CNE-MOPT-MINAE-MUNICIPALIDAD We require interinstitutional support involving the following areas of competence to address the critical points through short- and medium-term planning, according to the resources available to each institution.
Requirements to be requested from MOPT • Hydrological Studies • Hydraulic Studies • Availability of Machinery and Equipment • Professional Technical Support Requirements to be requested from CNE: • Financial resources to purchase prismatic textile structural Hydroblock geocontainers. • Continue the vulnerability study and risk assessment of the banks of the Río Nandayure for the remaining sector between Puente Carmona and the community of San Pablo. • Professional Technical Support • Availability of Machinery and Equipment (machinery hours). • Follow up on the commitments arising from the Decreto Nate, which remains (sic) in effect and could be used to secure the resources necessary to contribute to the proposed solution. Requirements to be requested from MINAE: • Conduct the studies necessary to perform works in a public-domain channel (cauce de dominio público). • Professional Technical Support Requirements to be requested from Municipalidad Nandayure: • Financial resources to purchase prismatic textile structural Hydroblock geocontainers. • Availability of Machinery and Equipment • Professional Technical Support • Liaison coordination (sic) among the institutions indicated.
Implementation Time Frames for the 2023 Period As a Municipality, we have begun the preliminary-project study (estudio de anteproyecto) of the points where intervention is planned in order to estimate the cost of each subproject. An extraordinary budget will now be submitted for the purchase of approximately 3.393 prismatic Hydroblock units to address the most critical points where the Río Nombre20770 overflows. We reiterate that, as a Municipality, we do not possess all the necessary resources; we therefore insist that a working committee be established to plan and perform the works within an appropriate time frame so as to prevent further tragedies (sic) affecting the residents of Carmona, San Nombre41, and Puerto San Nombre41.” Finally, in response to a request for evidence to aid adjudication (prueba para mejor resolver), the mayor of Nombre20770 reported: “In accordance with the ruling issued at 14:57 on 18 de octubre del 2023, and as evidence to aid adjudication, I hereby report: 1.
For some time now (sic), work has been under way on a solution to the problem reported by the petitioner, consisting of the installation of a structure known as a prismatic hydroblock textile structural geocontainer. Efforts to dredge (dragado) the Nombre20770 River have been under way since 2017; the river was dredged in 2017 and 2019 to mitigate the damage it causes until more comprehensive work can be performed, which has been limited by the high cost of environmental and other studies. Since 2022, the Municipalidad de Nombre20770 and other entities have been working to obtain permits to conduct another dredging operation and intervene in the river. Unfortunately, those permits have not been granted for reasons beyond our institution’s control, although the necessary steps have been taken in coordination with the Comisión de Emergencias. With respect to the implementation of the system known as hydroblok, it should be noted that when Mr.
Nombre11504, the petitioner’s husband, appeared at the Municipalidad to inquire about the status of the river works, he was informed that personnel had attended training to learn about a new construction system called hydroblok. The system and how it works were explained to him, and he was also told that efforts were being made to include it in the budget so that these bags could be purchased and testing could begin at some of the most problematic locations in the canton, provided that the budget was approved. At no time, however, was he told that it would be used on the portion adjoining his property because, as stated above, tests first had to be conducted to determine whether the system was functionally suitable for addressing the problem affecting not only his property but also other locations along the river. The problematic river channel (cauce) extends for slightly more than 13 kilometers, at least from the bridge at the entrance to the city of Carmona to its mouth at Puerto de San Pablo.
The attached figure shows that the Nombre20770 River has two areas potentially subject to flooding, which directly affect the Comunidad de Carmona, the population center, and the community of Puerto San Pablo. The river flows from a high point toward a very flat area, causing the channel to overflow and thereby directly affecting adjoining properties. Over the past 10 years, the channel of the Nombre20770 River has changed its fluvial morphology (morfología fluvial). Because of its mobility, the adjoining areas lack stability and permanence; they shift and change more than is commonly imagined, given the river’s aforementioned characteristics (flowing from a high point toward a very flat area). This fluvial mobility poses a danger to engineering works located on or near the riverbed, which by their very nature must remain stable. In other words, the scale of the problem cannot be resolved solely by dredging the channel; we must go further.
The work performed in recent years has consisted of channeling works (obras de encauzamiento) formed by parallel levees, but because the flow volumes are sufficiently large, they destroy the works constructed with materials from the channel and overflow due to the river’s winding course, striking head-on the protective structures created using specialized equipment. 2. State whether the budget has already been requested or approved. The budget was already submitted to the Concejo Municipal; unfortunately, it was rejected by that body. This is compounded by the Contraloría General de la República’s rejection of the most recent budgets. 3. When are the works expected to begin? The works may be performed once budgetary funding is available and the corresponding permits for intervention in the river have been processed before the Dirección de Aguas del Ministerio del Ambiente y Energía (MINAE). 4.
What is the current condition of the channel of the Nandayure River? The river is currently prone to overflowing in some sectors, as stated above. However, as regards the property and home of Mrs. [Nombre62 001], the home is located outside the river’s protection zone (zona de protección) and, to date, is not at any risk of flooding. 5. Whether the residents have been contacted to explain the works to be performed and the applicable timeframe. I must state that no large-scale meeting has been held with residents to explain the works to be performed. However, when other intervention work has been conducted at certain points along the channel through coordination among the Municipalidad de Nandayure, MOPT, and the Comisión de Emergencias, the residents have been informed. Indeed, approximately 15 days ago, I visited the area where the petitioner’s home is located and met with her and her husband.
They were informed about the work that could be performed in the medium term, as well as the problems affecting the Nombre20770 River throughout its entire channel, particularly from the bridge at the entrance to Ciudad Carmona to the river’s mouth at Puerto San Pablo, which is precisely the problematic flat section because of the force of the river’s flow. They have also been informed that we currently have no permit to intervene in the river, although we are presently processing an initial intervention in the river, so that work may be undertaken at the most critical points along it.” Having clarified that situation, it should be noted that, although nearly 5 years have elapsed, the flooding situation persists and the works necessary to achieve a comprehensive and permanent solution have not been carried out.
In that regard, although the respondent authorities have carried out various mitigation works, such as dredging and other cleaning and channeling work, it is nonetheless true that those measures have proved insufficient. In this respect, the respondent municipality itself acknowledges that greater efforts are required to implement lasting works capable of resolving the reported problem. Accordingly, even though the authorities have known about the problem at issue for at least approximately 5 years and have performed certain mitigation work, they have not taken the appropriate steps to achieve a comprehensive and permanent solution that ensures the safety of the community of San Nombre41 de Nandayure.
Consequently, the appropriate course is to grant the petition (recurso) in order to ensure a comprehensive solution within a reasonable period.
VI.Note by Justice Salazar Alvarado. As a matter of principle, I consider that cases concerning the Public Administration’s failure to repair, construct, modify, or demolish any infrastructure work should be dismissed because such an omission concerns a matter of legality, the adjudication of which falls within the jurisdiction of the ordinary courts, before which the interested party may challenge the matter more fully. However, when such administrative inaction results in a violation of other fundamental rights protected within this constitutional jurisdiction, or affects groups considered vulnerable, I do address the merits of the matter because such circumstances constitute an exception to my position on this issue, as occurs in this case, in which the petitioner alleges that the respondent authorities performed dredging work in the river; however, that work was performed improperly because it altered the river’s normal course, with the result that the rains destroyed the works that same year. She claims that the dredging redirected the river toward the rear of her home and therefore fears that the flow may sweep away her dwelling.
Although I agree with the majority of the Chamber that the petition should be granted, I disagree as to where the enforcement phase of the matter should be assigned, due to the absence of adequate mechanisms under the rules governing this constitutional jurisdiction for monitoring compliance with a judgment involving highly complex technical matters, as in this case, in which the flooding caused by the Nombre20770 River in the community of San Nombre41 de Nandayure must be resolved within one year from service of this judgment. By contrast, the provisions of the Código Procesal Contencioso-Administrativo governing enforcement (Article 155 et seq.) offer clear advantages, such as the ability to require schedules, impose fines, determine liability, monitor stages of compliance, and so forth. Therefore, pursuant to Article 56 of the Ley de Jurisdicción Constitucional, I consider that the enforcement phase should be conducted before the Área de Ejecución del Tribunal Contencioso Administrativo y Civil de Hacienda, under the judgment-enforcement rules of that Code.
The parties are advised that, if they submitted any paper document, as well as any objects or evidence stored on an additional electronic, computerized, magnetic, optical, or telematic device or produced using new technologies, they must retrieve them from the court office within a maximum period of 30 business days from service of this judgment. Otherwise, any material not retrieved within that period will be destroyed, pursuant to the “Reglamento sobre Expediente Electrónico ante el Poder Judicial,” approved by the Corte Plena at session N° 27-11 of 22 de agosto del 2011, Article XXVI, and published in Boletín Judicial number 19 of 26 de enero del 2012, as well as the resolution approved by the Consejo Superior del Poder Judicial at session N° 43-12 held on 3 de mayo del 2012, Article LXXXI.
Therefore:
The application is granted. Giovanni Jiménez Gómez and Faride Beirute Cárdenas, in their respective capacities as mayor and head of the Municipal Engineering Department, both of the Municipalidad de Nandayure; Luis Esteban Amador Jiménez and Óscar Salgado Portuguez, in their respective capacities as minister and director of River Works, both of the Ministerio de Obras Públicas y Transportes; and Alejandro José Picado Eduarte, in his capacity as president of the Comisión Nacional de Prevención de Riesgos y Atención de Emergencias, or whoever may hold those offices, are ordered to coordinate the necessary measures and undertake all actions falling within the scope of their respective authority so that: i) within TWO MONTHS from notification of this ruling, a plan is designed to address the problem at issue in this application, which plan shall be submitted to this Court and shall include a schedule detailing the dates on which the activities will be carried out, the deadlines for which must be observed, for the purpose of resolving that problem; and 2) pursuant to this schedule, the problem at issue in this amparo proceeding (amparo) must be definitively resolved within ONE YEAR from notification of this ruling.
The respondent authorities are advised that, pursuant to Article 71 of the Ley de la Jurisdicción Constitucional, anyone who receives an order issued in an amparo proceeding that they are required to comply with or enforce, and who fails to comply with or enforce it, shall be punished by imprisonment for three months to two years, or by a fine of twenty to sixty days, provided that the offense is not subject to a more severe penalty. The State, the Municipalidad de Nombre20770, and the Comisión Nacional de Prevención de Riesgos y Atención de Emergencias are ordered to pay the legal costs, damages, and losses caused by the acts underlying this declaration, the amounts of which shall be determined during enforcement of the judgment (ejecución de sentencia) before the contentious-administrative jurisdiction (jurisdicción contencioso-administrativa). Justice Salazar Alvarado files a separate note.
Justice Garro Vargas dissents with respect to the enforcement of this judgment and, pursuant to Article 56 of the Ley de la Jurisdicción Constitucional, orders that enforcement be conducted before the Área de Ejecución del Tribunal Contencioso Administrativo y Civil de Hacienda, in accordance with the enforcement rules established in Articles 155 et seq. of the Código Procesal Contencioso Administrativo. She further orders that a copy of the judgment be forwarded thereto so that proceedings to enforce this ruling may be initiated.
Fernando Cruz C.
Acting President Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Nombre5659 H.
Nombre5272 A.
Alexandra Alvarado A.
*CO* SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las trece horas quince minutos del veintidós de diciembre de dos mil veintitrés.
Recurso de amparo que se tramita en expediente nro. 23-007675-0007-CO, interpuesto por [Nombre62 001], cédula de identidad [Valor CED63], contra la MUNICIPALIDAD DE Nombre20770, el MINISTERIO DE OBRAS PÚBLICAS Y TRANSPORTES (MOPT) y la COMISIÓN NACIONAL DE PREVENCIÓN DE RIESGOS Y ATENCIÓN DE EMERGENCIA (CNE).
Resultando:
Redacta la Magistrada Hess Herrera; y,
Considerando:
En vista de que el alcalde de Nombre20770 omitió rendir el informe dentro del plazo fijado por este Tribunal en la resolución de curso de este asunto, de conformidad con el artículo 45 de la Ley de la Jurisdicción Constitucional se procede a analizar la constitucionalidad del asunto con base en los demás elementos aportados a los autos.
La accionante indica que es vecina de San Nombre41 de Nombre20770 y su inmueble se encuentra dentro de la zona afectada por las inundaciones provocadas por el río Nandayure. Alega que, en el año 2018, las autoridades recurridas realizaron trabajos de dragado en tal río; sin embargo, estos fueron efectuados defectuosamente, toda vez que cambiaron su curso normal, de modo que, ese mismo año, las lluvias destruyeron las obras. Aduce que el dragado redirigió el río a la parte trasera de su casa de habitación, por lo que teme que el caudal arrase con su vivienda. Alega que, en agosto de 2022 fue a la Comisión Nacional de Emergencias, donde le indicaron que el problema era competencia del MOPT. Relata que en setiembre de 2022 acudió ante el Departamento de Aguas Fluviales y Pluviales del MOPT, pero ahí le indicaron que no tenían presupuesto y que "solo con un recurso de amparo se puede ingresar al río".
Detalla que los vecinos y la municipalidad de Nombre20770 han sostenido reuniones sobre la problemática y el 12 de abril de 2023 se les indicó que el 1° de mayo siguiente iniciaban obras paliativas, pero que no pueden efectuar obras definitivas para resolver el problema porque la Comisión Nacional de Emergencias solo autorizó 300 horas de trabajos. Acota que, en el año 2022, la problemática se acrecentó, pues la corriente del río arrasó con árboles y cercas, provocando severos daños ecológicos. Solicita una solución definitiva y no paliativa del problema con el río Nandayure, el cual está amenazando su casa, así como de otras 26 familias, quienes ya están subiendo sus pertenencias a tarimas para no perderlas en la próxima época lluviosa.
De importancia para la decisión de este asunto, se estiman como debidamente demostrados los siguientes hechos:
C. La zona evaluada en el poblado de San Nombre41 Viejo de Nombre20770 presenta una topografía plana ondulada, se ubica en el punto donde el cauce cambia su condición encajonada en el cañón del río y se abre hacia la llanura aluvial, posee cobertura variada con árboles dispersos y algunas infraestructuras habitacionales construidas dentro de las zonas que se ha visto afectadas por anegamientos en el pasado, además, paralelo al cauce corre un camino vecinal que se ve impactado cuando ocurren los eventos de desbordamiento. D. En el sector evaluado que va paralelo al cauce del río Nombre20770 se observa una fuerte erosión lateral sobre las márgenes, debido a que el caudal impacta con gran fuerza las zonas. Se observa en toda la sección baja del río una alta sedimentación y colmatación de materiales que lo han rellenado por completo, generando una pérdida importante de la capacidad hidráulica y favoreciendo los eventos de desbordamiento cuando se dan lluvias fuertes.
E. Mediante el sobrevuelo realizado con un equipo aéreo no tripulado (drone), se observan evidencias de eventos de desbordamientos, anegamientos y depósito de escombros sobre las márgenes en la planicie, donde se ubican varias viviendas. Se observan evidencias del arrastre de la corriente y los escombros que contenía el flujo cuando atraviesa el camino municipal que lleva a San Nombre41 Viejo, y que continua hacia terrenos aledaños. F. En la quebrada Pozas, la cual atraviesa el camino que lleva a San Nombre41 Viejo, se observan problemas en el puente de paso, el cual se obstruye por arrastre de escombros y provoca el desbordamiento del caudal. Esta problemática interrumpe el paso, deja incomunicado al poblado y sin opción de salir debido a que solo existe esta vía para ingresar a la comunidad (…) Recomendaciones. A. La Municipalidad de Nombre20770 deberá coordinar con Obras Fluviales del MOPT y el MINAE la posibilidad de realizar una adecuada canalización sobre el cauce del río Nombre20770 en los sitios evaluados que presentan problemas, para remover la cantidad de material acumulado que disminuye la capacidad hidráulica de las secciones, además, realizar obras de protección para disminuir la erosión lateral sobre las márgenes y los diques de protección.
B. La Municipalidad de Nombre20770 deberá realizar la construcción de adecuadas obras de protección y contención en las márgenes del río Nandayure, con materiales que no sean erosionados por las crecidas extraordinarias y protejan los sectores. C. Restringir por parte de la Municipalidad de Nombre20770 el uso de suelo con fines habitacionales o de comercio en las zonas de protección del río Nandayure, según el artículo 33 de la ley forestal 7575, así como en las áreas identificadas con potencial afectación por inundaciones; según los mapas de amenazas naturales de la CNE. D. Las obras de protección que se implementen sobre las márgenes afectadas deben ser supervisadas por un profesional agremiado al Colegio Federado de Ingenieros y Arquitectos de Costa Rica, con base en las normas establecidas por el Código Sísmico, Código de Cimentaciones y Reglamento de Construcciones, Código Municipal y otra legislación vigente.
E. La Municipalidad de Nombre20770 deberá realizar periódicamente, según las condiciones de acumulación de materiales en el cauce del río Nombre20770 y todos aquellos que drenan el cantón, una adecuada canalización que ayude a recuperar la capacidad hidráulica del cauce y disminuya la amenaza de inundación en cada sector. F. La Municipalidad de Nombre20770 deberá permanecer vigilante de las zonas de alto riesgo, inundación y susceptibles al deslizamiento, no otorgar permisos constructivos o desarrollo de asentamientos informales de viviendas en ellos. G. Cualquier anomalía en cuanto a técnicas de construcción u omisión a las recomendaciones aquí descritas, QUEDA BAJO TOTAL RESPONSABILIDAD de las instituciones que otorgan los permisos, del ingeniero o responsable de la obra y de la Municipalidad respectiva de no solicitar los informes, inspecciones y correcciones correspondientes”. (Ver prueba documental).
El tipo de intervención que se ha efectuado, consiste en la contratación de horas máquina para retirar material y sedimento del centro del cauce, apilándolo en las márgenes, propiciando una mejor canalización del flujo del agua y disminuyendo el riesgo del desbordamiento del río. Este tipo de intervenciones fueron ejecutadas a razón de la solicitud y el reporte de afectaciones emitido por parte de la Municipalidad, quien además es responsable de la supervisión y el empleo adecuado de las horas contratadas. 4. En este tipo de intervenciones se descarta cambiar el curso o redirigir el cauce del cuerpo del agua, pues es de nuestro conocimiento, que para poder efectuar intervenciones de este tipo son necesarios una serie de estudios, levantamientos, modulaciones, entre los que se puede señalar el topográfico, el hidrológico e hidráulico, el geológico, entre otros. Es por tal razón, que, en los casos de las intervenciones financiadas por la CNE, se rechaza lo indicado por la recurrente al aseverar que se ha cambiado el curso o que el “… dragado redirigió el río a la parte trasera de su casa …”; máxime que no se aporten respaldos ni pruebas que puedan sustentar este tipo de aseveraciones. 5.
Gran parte de las aseveraciones planteadas por la recurrente, se fundamentan en supuestos que no han sido comprobados, a modo de ejemplo se cita la “Nota Técnica” confeccionada por el geólogo Wagner Valverde Mora, en el que en varios extractos del documento, indica que uno de los aspectos que pudo incidir en la erosión de la margen colindante a la propiedad de la recurrente, ha sido el supuesto, que en algún momento pudo haber existido un “dique” en la margen opuesta, y que en caso de que así hubiese sido, esto hubiese contribuido a la acción erosiva de la margen en la propiedad de la recurrente; nótese incluso que en el apartado 3 CONCLUSIONES, de dicha Nota Técnica, se señala: “ – Cabe la posibilidad de que alguna estructura haya sido construida desde la margen derecha hacia el centro del cauce (“dique”), …” 6. Aunado a lo anterior, pareciera que no se consideran aspectos que inducen el incremento del caudal del río Nandayure, el cambio climático, la deforestación, la capacidad de absorción del suelo, el fenómeno de la Niña, entre muchos otros, por los cuales el caudal del río Nombre20770 se incrementará en momentos específicos.
Así mismo, debe recordase que el río Nombre20770 como todos los cuerpos de agua, varían sus dinámicas, amplían o disminuyen sus secciones, puede modificar su rumbo, dependiendo de las condiciones y características en cada momento en específico, por lo que no se debería responsabilizar o culpar el efecto de la acción erosiva, en base a supuestos o apreciaciones subjetivas. Para complementar la respuesta anterior, a continuación, se muestra un cuadro con las intervenciones que se han realizado en el río Nombre20770 en la comunidad de San Nombre41 ID NUMERO PROCEDIMIENTO OBJETO CONTRACTUAL PROVINCIA CANTÓN DISTRITO Nombre62 ADJUTICATARIO MONTO ADJUDICADO 1 2019PI-000008-0006500001 Alquiler de Maquinaria para atender la emergencia en la comunidad de San Pablo, río Nandayure, Nombre20770 Guanacaste Nombre20770 San Nombre41 Constructora Hermanos Herrera Barrantes ₡ 14 823 650, 00 2 2020PI-000374-0006500001 Limpieza y Recava del cauce del río Nandayure, con el fin de evitar nuevos desbordamientos del río, que ocasionen afectaciones a las comunidades e infraestructura Guanacaste Nombre20770 San Nombre41 Constructora MECO, S.A ₡22 093 647, 00 TOTAL ₡ 36 917 297,00 ”. (Ver prueba documental).
El Cauce del Río Nombre20770 en los últimos 10 años ha cambiado su morfología fluvial, por su movilidad las áreas colindantes no tienen estabilidad ni permanencia, se desplazan y modifican más de lo que suele imaginarse. Esta movilidad fluvial representa un peligro para las obras de ingeniería ubicadas sobre el lecho fluvial y en sus inmediaciones, las que por su propia naturaleza deben ser estables. Es decir, la magnitud del problema no se soluciona únicamente con el dragado del cauce, debemos de ir más allá, lo que se ha realizado en los últimos años se ha justificado en obras de encauzamiento formado por diques paralelos, y al ser caudales lo suficientemente grandes los mismos destruyen las obras generadas con los materiales del cauce; desbordan debido a su sinuosidad atacando frontalmente las defensas creadas por equipo especial. • Criterio de la Situación y a la Actuación Municipal Entendemos la preocupación de todas las comunidades que colindan con el Río Nandayure; lo que ha generado el compromiso municipal en buscar soluciones más duraderas y debidamente coordinadas con las instituciones competentes Comisión Nacional de Emergencias y el Ministerio de Obras Públicas y Transportes.
No omitimos indicar que hemos trabajado este problema coordinadamente con dichas instituciones pero la sinergia no ha sido la suficiente para poder dar una solución integral duradera, seguimos utilizando las mismas técnicas de dragados, trabajos por horas maquinaria que solo resuelven para el período de invierno y la mayoría de las veces ni para ese período, y se trabaja solo en los puntos críticos erosionables, dejando de valorar otros aspectos de la gestión y desarrollo de la morfología fluvial. Con esto pretendemos indicar y rescatar los esfuerzos que individualmente hemos realizado en la búsqueda de soluciones, sin embargo es requerido que la Comisión Nacional de Emergencias y el Ministerio de Obras Públicas y Transportes, este último como rector en la material fluvial participe más activamente con sus profesionales, maquinaria y equipo, en los diferentes estudios hidrológicos e hidráulicos que son requeridos para dar soluciones que perduren en el tiempo y que contribuyan con la regeneración de la naturaleza autóctona de la zona.
La Comisión Nacional de Emergencias CNE; ha generado infinidad de visitas a lo largo del tiempo, al Cauce sobre el Río Nandayure; lo cual agradecemos pero sentimos que no es suficiente lo que se indica en el documento – informe INFORME TÉCNICO CNE-UIAR-INF-1193-2021 valoración de riesgo en las márgenes del río Nombre20770 en la localidad de San Nombre41 Viejo, por problemas erosión lateral y anegamiento del sector, su criterio es trascendental, pero requerimos de más apoyo y recursos para las emergencias que se han suscitado, de hecho a través de los informes de primer impacto realizados y amparados en el Decreto de Nate, hemos solicitado que se valore la inclusión de obras mayores preventivas y correctivas para minimizar el riesgo latente que cada invierno sufren las comunidades de Carmona y Puerto San Pablo. De manera tal que apelamos al trabajo en equipo de las tres instituciones, no solamente en razón de soluciones preventivas básicas, si no más bien ha generar un equipo de trabajo interinstitucional profesional para contribuir con soluciones hidráulicas más duraderas y eficientes, en beneficio de las comunidades afectadas. • Propuesta Municipal período 2020 En el mes de junio del año 2020, se ejecutó un trabajo en conjunto con el Ministerio de Obras Públicas y Transportes, el alcance del trabajo fue el dragado del Cauce en la comunidad de San Nombre41 tanto aguas arriba como aguas abajo del punto referenciado; el MOPT, aporto equipo especial, una excavadora y un tractor de oruga, para la conformación de los diques laterales de contención o barreras protectoras a las propiedades colindantes.
Sin emabrgo (sic) al utilizarse el mismo material del río tipo arenoso con las escorrentías suscitadas en periodos anteriores las mismas afectarón (sic) las estructuras paralelas de contención; dichos trabajos fueron realizados exactamente detrás de la propiedad de la Señora [Nombre62 001], tal y como se puede apreciar en la siguiente fotográfia (sic). (…) Trabajos realizados en el año 2020, protección con diques paralelos a propiedades colindantes para evitar el desbordamiento del Río Nandayure. Posteriormente en el mes de julio de 2022, la Municipalidad de Nombre20770 realizo trabajos de dragado del cauce propiamente en el sitio conocido como San Pablo, para mejorar el área hidraúlica (sic) de la sección de cauce dado a que en este punto el río se desborda cortando el paso del caminio (sic) cantonal que comunica con Puerto San Pablo. De esta forma hemos trabajado en coordinación con la dirección de aguas del Minae para poder contar con la autorización respectiva y así poder impactar los puntos más críticos, sin embargo insistimos que las obras ejecutadas no son suficientes para contener y disipar la energía del agua.
(…) Propuesta Municipal período 2023 En seguimiento de la problemática que se presenta en el cauce del Río Nandayure; la Municipalidad de Nombre20770 ha estado trabajando en los tramos críticos del mismo, ejecutando labores de dragado y encausamiento formando un dique lateral con el material propio del cauce, lo cual contribuye ha mejorar y ha fortalecer el encusamiento (sic) del flujo. Cabe mencionar que en el mes de abril de 2023, se iniciaron las labores con equipo municipal en las coordenas (sic) N 10 2 6.704 W 85 13 25.525, con la objetividad de reforzar con material aquellas zonas propensas de desbordamiento tal y como se puede evidenciar en las siguientes fotografías. (…) De esta forma la Municipalidad continuará trabjando (sic) a lo largo del Río Nombre20770 inclusive en el área que afecta la propiedad de la Señora [Nombre62 001], mediante la utilización de la excavadora para la conformación de los diques con sus respetivas coronas y respetando los meandros originales del cauce.
El 18 de agosto de 2022, se coordino (sic) y gestionó con personal técnico de la CNE; la visita a cada uno de los puntos críticos del Cauce del Río Nandayure, principalmente en la comunidad de Puerto San Pablo, el mismo desprende una serie de recomendaciones técnicas para evitar el desbordamiento del río. Recomendaciones que requieren de la elaboración de un plan de trabajo acompañado de los recursos técnicos y financieros del Ministerio de Obras Públicas y Transportes (MOPT) y de la Comisión Nacional de Emergencias (CNE), así como también de éste municipio. • Propuesta Técnica Municipal para minimizar el riesgo de Innundación (sic) La Municiaplidad (sic) ha estado analizando la viabilidad técnica y finaciera (sic) de la apliación (sic) de una estructura llamada un geocontendor estructural textil hidroblock prismático de alta resistencia a la interperie (sic) el cual es llenado mediante el material existente en el cauce, mediante medios mecánicos o hidráulicos con el suelo del sitio tipo grava, para obtener unidades de masa de gran volumen que se acomoden sobre el terreno de manera versátil.
Por su forma y tamaño se utilizan en la construcción de estructuras de gravedad, en la fachada de muros en suelos reforzados, en estructuras de control hidráulico, control de erosión en orillas, rehabilitación de orillas erosionadas, revestimiento de diques, terraplenes, taludes de cauces, realce de orillas, realce de corona en estructuras de control hidráulico, y protección de tuberías Esta solución es viable para fortalecer las secciones del cauce que presentan alta erosión de los taludes naturales que colindan con los patios, casas de habitación, que se han visto afectados por las crecidas del Río Nandayure, su costo es importante y se requiere de un presupuesto extraordinario, la ventaja que presenta esta estructura es que su costo como insumo, elemento, se ve compensado con el material se sitio, pues no tendríamos que comprar gran cantidad de material granular sobre tamaño que incrementaría exponencialmente los costos del proyecto. • Propuesta Técnica acompañamiento CNE- MOPT- MINAE- MUNICIPALIDAD Requerimos del acompañamiento interinstitucional con las siguientes competencias para poder impactar los puntos críticos mediante una programación a corto y mediano plazo según la disponibilidad de recursos de cada institución.
Requerimiento a solicitar la MOPT • Estudios Hidrológicos • Estudios Hidráulicos • Disponibilidad de Maquinaria y Equipo • Apoyo Técnico profesional Requerimiento a solicitar a la CNE: • Recursos financieros para compra geocontendor estructural textil hidroblock prismático. • Continuar con el estudio de vulnerabilidad valoración de riesgo en las márgenes del río Nandayure, del sector faltante entre el Puente Carmona hacia la comunidad de San Pablo. • Apoyo Técnico profesional • Disponibilidad de Maquinaria y Equipo (horas maquinaria). • Dar seguimiento a los compromisos que se generaron con el Decreto Nate, el mismo esta (sic) activo y se podría gestionar los recursos necesarios para contribuir con la solución planteada. Requerimiento a solicitar la MINAE: • Realizar los estudios para realizar obras en cauce de dominio público. • Apoyo Técnico profesional Requerimiento a la solicitar la Municipalidad Nandayure: • Recursos financieros para compra geocontendor estructural textil hidroblock prismático. • Disponibilidad de Maquinaria y Equipo • Apoyo Técnico profesional • Coordinación de enalce (sic) entre las instituciones indicadas.
De los plazos de ejecución periódo 2023 Como Municipalidad hemos iniciado con el estudio de anteproyecto de los puntos a intervenir para poder estimar los costos de cada sub proyecto, actualmente se presentará el presupuesto extraordinario para la compra de aproximadamente 3.393 bloques hidroblock prismático; para impactar los puntos más críticos donde el Río Nombre20770 presenta desbordamiento. Reiteramos que como Municipalidad no contamos con todos los recursos, por lo que insistimos que se debe de crear una comisión de trabajo para poder planear, y ejecutar las obras en un plazo adecuado para evitar mayores trajedias (sic) a los ciudadanos de Carmona y San Nombre41 y Puerto San Nombre41”. (Ver prueba documental).
Con respecto a la aplicación del sistema denominado hydroblok, debe indicarse que cuando el señor Nombre11504 , esposo de la recurrente, se apersonó a la Municipalidad para preguntar sobre el estado para los trabajos del río, se le comento que se había ido a una capacitación para el conocimiento de un nuevo sistema constructivo llamado hydroblok, se le explico en qué consiste y cómo funciona, además se le externó que se estaba tratando de incluirlo dentro del presupuesto, para la compra de estas bolsas para iniciar pruebas en algunos de los puntos más problemáticos que teníamos en el cantón siempre y cuando se aprobara el presupuesto, pero en ningún momento se le dijo que eso iba a ser usado en la parte de su propiedad porque como se mencionó́ antes, se debían realizar pruebas para saber si eran funcionalmente aceptables para la solución del problema que tenemos no solo en el terreno del señor, si no en otros puntos a lo largo del rio, con un cauce problemático que tiene poco más de 13 kilómetros, al menos desde el Puente a la entrada a la ciudad de Carmona hasta su desembocadura en el Puerto de San Pablo.
En la figura adjunta, se puede observar que el río Nombre20770 presenta dos áreas de inundación potenciales y que afectan directamente a la Comunidad de Carmona, centro de población y a la comunidad de Puerto San Pablo, el río se desplaza de un punto alto hacia una zona muy plana situación que provoca el desbordamiento del cauce y por ende la afectación directa a las propiedades colindantes. El cauce del Río Nombre20770 en los últimos 10 años ha cambiado su morfología fluvial, por su movilidad las áreas colindantes no tienen estabilidad ni permanencia, se desplazan y modifican más de lo que suele imaginarse, dadas las características propias del mismo antes mencionadas (desplazamiento de un punto alto hacia una zona muy plana). Esta movilidad fluvial representa un peligro para las obras de ingeniería ubicadas sobre el lecho fluvial y en sus inmediaciones, las que por su propia naturaleza deben ser estables.
Es decir, la magnitud del problema no se soluciona únicamente con el dragado del cauce, debemos de ir más allá́, lo que se ha realizado en los últimos años se ha justificado en obras de encauzamiento formado por diques paralelos, y al ser caudales lo suficientemente grandes los mismos destruyen las obras generadas con los materiales del cauce, desbordan debido a su sinuosidad atacando frontalmente las defensas creadas por equipo especial. 2. Indicar si ya se solicitó́ el presupuesto, o si ya se aprobó́ el presupuesto. El presupuesto ya fue presentado ante el Concejo Municipal, lastimosamente dicho presupuesto fue improbado por parte de ellos. A lo anterior se suma la improbación de los últimos presupuestos por parte de la Contraloría General de la República. 3. Para cuándo se pretende iniciar las obras. Las obras se podrán realizar en cuanto exista el contenido presupuestario y se logren tramitar los permisos correspondientes ante la Dirección de Aguas del Ministerio del Ambiente y Energía (MINAE) para intención del río. 4.
Cuál es el estado actual del cauce de dicho río Nandayure. El estado actual del río es propenso a desbordarse en algunos sectores, como se indicó́ supra, pero en lo que respecta al terreno y vivienda de la señora [Nombre62 001] la vivienda se encuentra fuera de la zona de protección de este y hasta el momento no tiene peligro alguno de inundación. 5. Si se han comunicados con los vecinos para explicarles las obras a realizar y en qué plazo. Como decir que se haya efectuado una reunión masiva con los vecinos para explicarles las obras a realizar debo indicar que se no se ha efectuado, sin embargo, cuando se han hecho otros trabajos de intervención en algunos puntos del cauce, en coordinación entre la Municipalidad de Nandayure, el MOPT y la Comisión de Emergencias, si se ha informado los vecinos. Incluso, hace escasos unos 15 días más o menos, se visitó́ la zona donde se ubica la casa de la recurrente, reuniéndome con la misma y su esposo, a quien se les comunicó sobre los trabajos que se podrían efectuar a mediano plazo, así́ como sobre la problemática que presenta el río Nombre20770 en todo su cauce, principalmente desde el puente a la entrada a Ciudad Carmona hasta la desembocadura en Puerto San Pablo, que es precisamente la parte llana problemática por la fuerza que el mismo presenta.
También se les ha comunicado que actualmente no tenemos ningún permiso para intervención del rio, aunque actualmente nos encontramos tramitando un primer impacto sobre el rio, pero para ser intervenido en los puntos más críticos a lo largo del río”. (Ver informe rendido).
Este Tribunal conoció en otras ocasiones la situación causada por el río Nandayure. Así, en sentencia nro. 2022027316 de las 9:29 horas del 18 de noviembre de 2022, se dispuso:
“III.- SOBRE EL CASO CONCRETO. En el sub lite, el recurrente manifiesta que es vecino de San Nombre41 de Nandayure, zona afectada por las inundaciones que provoca el Río Nandayure. Alega que ha solicitado ayuda a las autoridades recurridas para que se realicen las obras necesarias para solucionar el problema de las inundaciones; empero, aún la situación es la misma. Añade que, en el año en curso, el río aludido destruyó árboles, cercas, postes y cosechas.
Del estudio de los autos se tiene demostrado, que la municipalidad accionada informa que el Río Nombre20770 presenta dos áreas de inundación, que afectan a las comunidades de Carmona y San Pablo. En marzo de 2020, la Dirección de Obras Fluviales del MOPT realizó trabajos de limpieza y canalización en el Río Nandayure, como parte de las medidas para mitigar los efectos de las lluvias. El presidente de la CNE informa: “esta Comisión desde el año 2018 a la fecha tramitó las siguientes solicitudes por parte de la Municipalidad de Nandayure: 1) 2019PI-000008-0006500001 “Alquiler de Maquinaria para atender la emergencia en la comunidad de San Pablo, río Nandayure, Nombre20770 5ta Ocasión”, donde se adjudicó en fecha 23 de enero de 2019 a la Empresa Hermanos Herrera Barrantes Constructora, Sociedad Anónima, 150 horas efectivas de una excavadora y 150 horas efectivas de un Tractor, cuyo fin era la limpieza, recava del río Nandayure, apilación de material a los costados, tipo dique con el fin de evitar o mitigar desbordamientos y mayor afectación en el sector de la comunidad de San Nombre41 y 2) 2020PI-000374-0006500001 “Alquiler de Maquinaria para atender afectaciones en San Pablo, desbordamiento río Nandayure”, donde en fecha 11 de diciembre de 2020, se adjudicó a la Constructora Meco, Sociedad Anónima, 150 horas efectivas de un tractor y 150 horas efectivas de una excavadora, con el fin de atender la emergencia no declarada cuya finalidad era la limpieza y recavar el cauce del río Nombre20770 en la comunidad de San Pablo, Nandayure, con el fin de evitar nuevos desbordamientos del río, que ocasionen afectaciones a la comunidades e infraestructura.”.
En el informe técnico nro. CNE-UIAR-INF-1193-2021 de septiembre de 2022 de la Unidad de Investigación y Análisis de Riesgo de la CNE, se consignó: “Valoración de riesgo en las márgenes del río Nombre20770 en la localidad de San Nombre41 Viejo, por problemas erosión lateral y anegamiento del sector(…) Conclusiones: A. Según el Mapa de Amenazas Naturales Potenciales de la CNE, las zonas evaluadas se encuentran dentro del área con afectación directa por inundaciones potenciales cuando ocurren desbordamientos del caudal del río Nombre20770 y sus afluentes en la zona de planicie, generalmente ocurridos cuando se dan lluvias intensas en la zona alta de las microcuencas por influencia de fenómenos hidrometereológicos extremos. B. El sector evaluado en la localidad de San Nombre41 Viejo se localiza dentro de la microcuenca del río Nandayure, sobre la margen izquierda. La zona evaluada se ubica dentro de lo que corresponde con el área del cauce del río y planicie aluvial, en los bordes de las terrazas aluvionales construidas por la acreción de sedimentos depositados luego de eventos de crecidas extraordinarias.
C. La zona evaluada en el poblado de San Nombre41 Viejo de Nombre20770 presenta una topografía plana ondulada, se ubica en el punto donde el cauce cambia su condición encajonada en el cañón del río y se abre hacia la llanura aluvial, posee cobertura variada con árboles dispersos y algunas infraestructuras habitacionales construidas dentro de las zonas que se ha visto afectadas por anegamientos en el pasado, además, paralelo al cauce corre un camino vecinal que se ve impactado cuando ocurren los eventos de desbordamiento. D. En el sector evaluado que va paralelo al cauce del río Nombre20770 se observa una fuerte erosión lateral sobre las márgenes, debido a que el caudal impacta con gran fuerza las zonas. Se observa en toda la sección baja del río una alta sedimentación y colmatación de materiales que lo han rellenado por completo, generando una pérdida importante de la capacidad hidráulica y favoreciendo los eventos de desbordamiento cuando se dan lluvias fuertes.
E. Mediante el sobrevuelo realizado con un equipo aéreo no tripulado (drone), se observan evidencias de eventos de desbordamientos, anegamientos y depósito de escombros sobre las márgenes en la planicie, donde se ubican varias viviendas. Se observan evidencias del arrastre de la corriente y los escombros que contenía el flujo cuando atraviesa el camino municipal que lleva a San Nombre41 Viejo, y que continua hacia terrenos aledaños. F. En la quebrada Pozas, la cual atraviesa el camino que lleva a San Nombre41 Viejo, se observan problemas en el puente de paso, el cual se obstruye por arrastre de escombros y provoca el desbordamiento del caudal. Esta problemática interrumpe el paso, deja incomunicado al poblado y sin opción de salir debido a que solo existe esta vía para ingresar a la comunidad (…) Recomendaciones. A. La Municipalidad de Nandayuredeberá coordinar con Obras Fluviales del MOPT y el MINAE la posibilidad de realizar una adecuada canalización sobre el cauce del río Nombre20770 en los sitios evaluados que presentan problemas, para remover la cantidad de material acumulado que disminuye la capacidad hidráulica de las secciones, además, realizar obras de protección para disminuir la erosión lateral sobre las márgenes y los diques de protección.
B. La Municipalidad de Nombre20770 deberá realizar la construcción de adecuadas obras de protección y contención en las márgenes del río Nandayure, con materiales que no sean erosionados por las crecidas extraordinarias y protejan los sectores. C. Restringir por parte de la Municipalidad de Nombre20770 el uso de suelo con fines habitacionales o de comercio en las zonas de protección del río Nandayure, según el artículo 33 de la ley forestal 7575, así como en las áreas identificadas con potencial afectación por inundaciones; según los mapas de amenazas naturales de la CNE. D. Las obras de protección que se implementen sobre las márgenes afectadas deben ser supervisadas por un profesional agremiado al Colegio Federado de Ingenieros y Arquitectos de Costa Rica, con base en las normas establecidas por el Código Sísmico, Código de Cimentaciones y Reglamento de Construcciones, Código Municipal y otra legislación vigente.
E. La Municipalidad de Nombre20770 deberá realizar periódicamente, según las condiciones de acumulación de materiales en el cauce del río Nombre20770 y todos aquellos que drenan el cantón, una adecuada canalización que ayude a recuperar la capacidad hidráulica del cauce y disminuya la amenaza de inundación en cada sector. F. La Municipalidad de Nombre20770 deberá permanecer vigilante de las zonas de alto riesgo, inundación y susceptibles al deslizamiento, no otorgar permisos constructivos o desarrollo de asentamientos informales de viviendas en ellos. G. Cualquier anomalía en cuanto a técnicas de construcción u omisión a las recomendaciones aquí descritas, QUEDA BAJO TOTAL RESPONSABILIDAD de las instituciones que otorgan los permisos, del ingeniero o responsable de la obra y de la Municipalidad respectiva de no solicitar los informes, inspecciones y correcciones correspondientes.”. El alcalde de la Municipalidad de Nombre20770 señala que se han realizado técnicas de dragado y otros trabajos para contrarrestar las inundaciones en época de invierno; empero, tales acciones resultan insuficientes y no se ha podido alcanzar una solución integral duradera.
El 18 de agosto de 2022, la Municipalidad de Nombre20770 y la CNE efectuaron una visita a cada uno de los puntos críticos en la comunidad de San Pablo. La municipalidad accionada informa que ha iniciado con el estudio de un anteproyecto para la intervención del río; empero, requiere la participación de las demás dependencias accionadas para planear y ejecutar las obras respectivas, a fin de solucionar el problema acusado.
Sobre el particular, interesa resaltar que, en la sentencia nro. 2019018960 de las 9:20 horas de 4 de octubre de 2019, este Tribunal resolvió un recurso de amparo interpuesto por el recurrente, atinente a la problemática del Río Nandayure. En esa resolución, se indicó:
“I.- Objeto del recurso. Los recurrentes alegan, que han presentado varias gestiones solicitando el dragado del río Nandayure, en el sector de San Pablo, y a la fecha, no han recibido respuesta ni se han realizado los actos correspondientes (…)
IV.Sobre el fondo. La Administración, a la luz del artículo 41, de la Constitución Política, tiene la obligación de garantizarle a la ciudadanía el cumplimiento de la justicia pronta y cumplida, sin denegación, lo que implica, en el ámbito de la justicia administrativa, su obligación de decidir con diligencia y celeridad los reclamos planteados por los administrados, de tal manera que su resolución sea congruente con los extremos alegados, así como de comunicarles a los interesados lo dispuesto, todo ello dentro de un plazo razonable. En el caso bajo estudio, la Sala acredita una infracción a lo dispuesto en el artículo 41, de la Constitución Política, toda vez que la parte recurrida no había resuelto las gestiones interpuestas por los recurrentes y demás vecinos, desde el 6 de noviembre de 2018, y reiteradas, el 26 de abril y el 13 de junio, ambos del 2019, lo que evidencia una lesión al derecho fundamental a la justicia pronta y cumplida. Además, fue con la notificación del presente recurso de amparo, que la autoridad recurrida procedió a resolver la gestión a lo solicitado por los gestionantes. En consecuencia, en cuanto este extremo se declara con lugar el recurso.
V.Por otra parte, si bien a la fecha, no consta que se requiera hacer el dragado del río Nombre20770 en el sector solicitado por los recurrentes, pues para tener certeza de ello, se requiere realizar los estudios técnicos, por parte de la autoridades competentes; lo cierto es que, ante la duda, y dado que el año pasado se produjeron inundaciones que dañaron los trabajos ya realizados, se debe aplicar el "principio de evitación prudente o precautorio", con respecto a la posible afectación que podría causar el desbordamiento del cauce del río, a la salud e integridad de las personas que habitan dicha comunidad así como a sus viviendas, la alteración de ecosistemas, erosión, la destrucción de caminos, cultivos, la afectación de la salud y el bienestar de la vida silvestre y el ganado, entre otros. De manera, que en aplicación a dicho principio, y dada la evidencia de que se podría estar en presencia de un peligro de daño grave o irreversible, lo correcto es actuar minimizando en lo posible las situaciones de riesgo que pueda provocar dicha situación.
Además, la pretensión de los recurrentes es que se realice una limpieza y ahondamiento del río en cuestión, en la zona de San Pablo, así como la remoción de rocas y sedimentos, para aumentar la profundidad, por lo que traduciendo dicha petición al terreno de lo constitucional, lo procedente es que la Sala acoja el recurso y ordene al Alcalde Municipal en coordinación con los entes competentes de la Dirección de Obras Fluviales y de la Región, del Ministerio de Obras Públicas y Transportes, que se realicen los estudios técnicos, señalados por dichas autoridades, a saber, un estudio hidrológico y una modelación hidráulica en dos dimensiones para saber con certeza el tipo de obra hidráulica a construir e identificar, si la infraestructura existente, se encuentra dentro de la zona de protección del río para la solución del problema. Lo anterior se fundamenta en lo dispuesto en el artículo 15, de la "Declaración de Río", adoptada por la Conferencia de las Naciones Unidas sobre el Medio Ambiente y el Desarrollo, en junio de 1992, que reza:
"Con el fin de proteger el medio ambiente, los Estados deberán aplicar ampliamente el criterio de precaución conforme a sus capacidades. Cuando haya peligro de daño grave o irreversible, la falta de certeza científica absoluta no deberá utilizarse como razón para postergar la adopción de medidas eficaces en función de los costos para impedir la degradación del medio ambiente" .
Acorde con lo anterior, es necesario insistir en que la observancia de un principio puede ser racional o irracional, y el caso de la evitación prudente no es excepción. De hecho, está claro que el principio en cuestión, como "evitación prudente" es únicamente una recomendación, de vigencia transitoria, para que se apliquen determinadas medidas preventivas. Así, en virtud de lo expuesto, y en aplicación del principio precautorio, lo procedente es acoger el recurso, únicamente en cuanto a este extremo.
Por tanto:
Se declara con lugar el recurso. Se ordena a Giovanni Jiménez Gómez, en su condición de Alcalde de la Municipalidad de Nandayure, o a quien ocupe dicho cargo, que en el plazo de OCHO MESES, a partir de la notificación de esta sentencia, deberá, de manera coordinada con las autoridades de la Dirección de Obras Fluviales y de la Macro Región de Guanacaste, ambos del Ministerio de Obras Públicas y Transportes, deberán realizar y obtener los resultados del estudio hidrológico y de la modelación hidráulica, que corresponda, para saber con certeza el tipo de obra hidráulica a construir e identificar, si la infraestructura existente se encuentra dentro de la zona de protección del río Nadanyure, con el fin de solucionar el problema de desbordamiento que se presenta en la zona de San Pablo. Lo anterior, bajo la advertencia de incurrir en el delito previsto por el artículo 71, de la Ley de la Jurisdicción Constitucional, en caso de no hacerlo.
Se condena a la Municipalidad de Nandayure, al pago de las costas, daños y perjuicios causados con los hechos que sirven de base a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso administrativo. Notifíquese esta resolución a la parte recurrida, así como a Jenaro Ruiz Chacón y a Alonso Mora Arroyo, por su orden Director a.i. de la Dirección de Obras Fluviales y Director Macro Región de Guanacaste, ambos del Ministerio de Obras Públicas y Transportes, o a quienes ocupen dichos cargos, en forma personal”.
Ahora bien, como se aprecia, en el precedente transcrito supra se ordenó la realización de determinados estudios que en ese momento estaban pendientes y que servirían para atender el problema de las inundaciones en el río de marras. No obstante, aproximadamente 3 años después, se aprecia que aún persiste la situación de las inundaciones, y que no se han ejecutado las obras necesarias para alcanzar una solución integral y definitiva.
En tal sentido, si bien la Municipalidad de Nombre20770 y la Dirección de Obras Fluviales del MOPT han realizado distintas obras paliativas como dragados y otros trabajos de limpieza y canalización, no menos cierto es que tales acciones han resultado insuficientes. Al respecto, la propia municipalidad accionada reconoce que es necesario ejecutar mayores esfuerzos para ejecutar obras duraderas que solventen el problema acusado. Asimismo, en el informe técnico CNE-UIAR-INF-1193-2021 de septiembre de 2022 de la Unidad de Investigación y Análisis de Riesgo de la CNE se consignó que mayores intervenciones y acciones eran necesarias por parte de la municipalidad accionada.
Así las cosas, pese a que desde al menos hace 3 años las autoridades de la Municipalidad de Nombre20770 y de la Dirección de Obras Fluviales del MOPT conocen el problema de marras y han realizado determinados trabajos paliativos, no han ejecutado lo pertinente para alcanzar una solución integral y definitiva garantice la seguridad de la comunidad de San Nombre41 de Nandayure.
De tal manera, lo procedente es declarar con lugar el recurso en cuanto a tales dependencias, a fin de garantizar una solución integral dentro de un plazo razonable.
IV- Por otra parte, en relación con la Comisión Nacional de Prevención de Riesgos y Atención de Emergencias, a priori se descarta alguna omisión que amerite ser declarada en esta vía sumaria.
En tal sentido, se informó bajo juramento que las solicitudes de ayuda tramitadas por la Municipalidad de Nombre20770 fueron debidamente atendidas, y se ejecutaron las contrataciones solicitadas en las gestiones 2019PI-000008-0006500001 y 2020PI-000374-0006500001. Asimismo, se efectuó la respectiva inspección y mediante el informe CNE-UIAR-INF-1193-2021 de septiembre de 2022 se detallaron las recomendaciones atinentes a las obras que la referida municipalidad debe ejecutar.
En consecuencia, lo procedente es declarar sin lugar el recurso en cuanto a este extremo. Sin embargo, deberá tomar nota el presidente de la Comisión Nacional de Prevención del Riesgo y Atención de Emergencias, a fin de que, en caso de ser requerido, dentro del marco de sus competencias se coadyuve con la Municipalidad de Nombre20770 y con la Dirección de Obras Fluviales del MOPT en la solución del problema objeto de este recurso. (…)
Por tanto:
Se declara parcialmente con lugar el recurso, únicamente en cuanto a la Municipalidad de Nombre20770 y al Ministerio de Obras Públicas y Transportes. Se ordena a Jenaro Ruiz Chacón y a Giovanni Jiménez Gómez, por su orden, director a.i. de la Dirección de Obras Fluviales del Ministerio de Obras Públicas y Transportes y alcalde de Nandayure, o a quienes respectivamente ocupen tales cargos, que coordinen lo correspondiente, giren las órdenes pertinentes y lleven a cabo todas las actuaciones que estén dentro del ámbito de sus respectivas competencias para que, dentro del plazo máximo de DOCE MESES, contado a partir de la notificación de esta sentencia, se realicen todas las gestiones y obras pertinentes para solucionar de manera integral y definitiva el problema de inundaciones del Río Nandayure, que afecta a la comunidad de San Nombre41 de Nandayure. Se advierte que, de conformidad con lo establecido en el artículo 71, de la Ley de la Jurisdicción Constitucional, se impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo, y no la cumpliere o hiciere cumplir, siempre que el delito no esté más gravemente penado.
Se condena al Estado y a la Municipalidad de Nombre20770 al pago de las costas, daños y perjuicios causados con los hechos que sirvieron de base a la presente declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso-administrativo. En lo demás, se declara sin lugar el recurso. Tome nota la Comisión Nacional de Prevención de Riesgos y Atención de Emergencias de lo consignado in fine del considerando IV de esta sentencia. La magistrada Garro Vargas salva el voto respecto a la ejecución de esta sentencia y, de conformidad con el artículo 56 de la Ley de la Jurisdicción Constitucional, dispone que debe realizarse ante el Área de Ejecución del Tribunal Contencioso Administrativo y Civil de Hacienda, bajo las reglas de ejecución, establecidos en los artículos 155 y siguientes del Código Procesal Contencioso Administrativo. Asimismo, ordena que se le remita copia de la sentencia para que se inicie los procedimientos de ejecución de este fallo. Notifíquese”.
En la especie, la accionante indica que es vecina de San Nombre41 de Nombre20770 y su inmueble se encuentra dentro de la zona afectada por las inundaciones provocadas por el río Nandayure. Alega que, en el año 2018, las autoridades recurridas realizaron trabajos de dragado en tal río; sin embargo, estos fueron efectuados defectuosamente, toda vez que cambiaron su curso normal, de modo que, ese mismo año, las lluvias destruyeron las obras. Aduce que el dragado redirigió el río a la parte trasera de su casa de habitación, por lo que teme que el caudal arrase con su vivienda. Alega que, en agosto de 2022 fue a la Comisión Nacional de Emergencias, donde le indicaron que el problema era competencia del MOPT. Relata que en setiembre de 2022 acudió ante el Departamento de Aguas Fluviales y Pluviales del MOPT, pero ahí le indicaron que no tenían presupuesto y que "solo con un recurso de amparo se puede ingresar al río".
Detalla que los vecinos y la municipalidad de Nombre20770 han sostenido reuniones sobre la problemática y el 12 de abril de 2023 se les indicó que el 1° de mayo siguiente iniciaban obras paliativas, pero que no pueden efectuar obras definitivas para resolver el problema porque la Comisión Nacional de Emergencias solo autorizó 300 horas de trabajos. Acota que, en el año 2022, la problemática se acrecentó, pues la corriente del río arrasó con árboles y cercas, provocando severos daños ecológicos. Solicita una solución definitiva y no paliativa del problema con el río Nandayure, el cual está amenazando su casa, así como de otras 26 familias, quienes ya están subiendo sus pertenencias a tarimas para no perderlas en la próxima época lluviosa.
Al respecto, la Sala tiene por demostrado que el Río Nombre20770 presenta dos áreas de inundación, que afectan a las comunidades de Carmona y San Pablo. En julio de 2018, la Dirección de Obras Fluviales del Ministerio de Obras Públicas y Transportes realizó una limpieza y canalización del Río Nandayure, como obra de mitigación, en la localidad de San Pablo. El 6 de noviembre de 2018, los vecinos San Nombre41 de Nombre20770 solicitaron a la Municipalidad de Nombre20770 el dragado del río, pues se dio el crecimiento del caudal y destruyó el trabajo realizado. El 13 de junio de 2019, los vecinos solicitaron al alcalde recurrido el dragado del río Nombre20770 en el sector de San Pablo, pues debido a las fuertes lluvias del año anterior, se destruyó el trabajo realizado y cuando crece, el agua ingresa a sus viviendas. En marzo de 2020, la Dirección de Obras Fluviales del MOPT realizó trabajos de limpieza y canalización en el Río Nandayure, como parte de las medidas para mitigar los efectos de las lluvias.
Posteriormente, en el informe técnico nro. CNE-UIAR-INF-1193-2021 de septiembre de 2022 de la Unidad de Investigación y Análisis de Riesgo de la CNE, se consignó: “Valoración de riesgo en las márgenes del río Nombre20770 en la localidad de San Nombre41 Viejo, por problemas erosión lateral y anegamiento del sector (…) Conclusiones: A. Según el Mapa de Amenazas Naturales Potenciales de la CNE, las zonas evaluadas se encuentran dentro del área con afectación directa por inundaciones potenciales cuando ocurren desbordamientos del caudal del río Nombre20770 y sus afluentes en la zona de planicie, generalmente ocurridos cuando se dan lluvias intensas en la zona alta de las microcuencas por influencia de fenómenos hidrometereológicos extremos. B. El sector evaluado en la localidad de San Nombre41 Viejo se localiza dentro de la microcuenca del río Nandayure, sobre la margen izquierda. La zona evaluada se ubica dentro de lo que corresponde con el área del cauce del río y planicie aluvial, en los bordes de las terrazas aluvionales construidas por la acreción de sedimentos depositados luego de eventos de crecidas extraordinarias.
C. La zona evaluada en el poblado de San Nombre41 Viejo de Nombre20770 presenta una topografía plana ondulada, se ubica en el punto donde el cauce cambia su condición encajonada en el cañón del río y se abre hacia la llanura aluvial, posee cobertura variada con árboles dispersos y algunas infraestructuras habitacionales construidas dentro de las zonas que se ha visto afectadas por anegamientos en el pasado, además, paralelo al cauce corre un camino vecinal que se ve impactado cuando ocurren los eventos de desbordamiento. D. En el sector evaluado que va paralelo al cauce del río Nombre20770 se observa una fuerte erosión lateral sobre las márgenes, debido a que el caudal impacta con gran fuerza las zonas. Se observa en toda la sección baja del río una alta sedimentación y colmatación de materiales que lo han rellenado por completo, generando una pérdida importante de la capacidad hidráulica y favoreciendo los eventos de desbordamiento cuando se dan lluvias fuertes.
E. Mediante el sobrevuelo realizado con un equipo aéreo no tripulado (drone), se observan evidencias de eventos de desbordamientos, anegamientos y depósito de escombros sobre las márgenes en la planicie, donde se ubican varias viviendas. Se observan evidencias del arrastre de la corriente y los escombros que contenía el flujo cuando atraviesa el camino municipal que lleva a San Nombre41 Viejo, y que continua hacia terrenos aledaños. F. En la quebrada Pozas, la cual atraviesa el camino que lleva a San Nombre41 Viejo, se observan problemas en el puente de paso, el cual se obstruye por arrastre de escombros y provoca el desbordamiento del caudal. Esta problemática interrumpe el paso, deja incomunicado al poblado y sin opción de salir debido a que solo existe esta vía para ingresar a la comunidad (…) Recomendaciones. A. La Municipalidad de Nombre20770 deberá coordinar con Obras Fluviales del MOPT y el MINAE la posibilidad de realizar una adecuada canalización sobre el cauce del río Nombre20770 en los sitios evaluados que presentan problemas, para remover la cantidad de material acumulado que disminuye la capacidad hidráulica de las secciones, además, realizar obras de protección para disminuir la erosión lateral sobre las márgenes y los diques de protección.
B. La Municipalidad de Nombre20770 deberá realizar la construcción de adecuadas obras de protección y contención en las márgenes del río Nandayure, con materiales que no sean erosionados por las crecidas extraordinarias y protejan los sectores. C. Restringir por parte de la Municipalidad de Nombre20770 el uso de suelo con fines habitacionales o de comercio en las zonas de protección del río Nandayure, según el artículo 33 de la ley forestal 7575, así como en las áreas identificadas con potencial afectación por inundaciones; según los mapas de amenazas naturales de la CNE. D. Las obras de protección que se implementen sobre las márgenes afectadas deben ser supervisadas por un profesional agremiado al Colegio Federado de Ingenieros y Arquitectos de Costa Rica, con base en las normas establecidas por el Código Sísmico, Código de Cimentaciones y Reglamento de Construcciones, Código Municipal y otra legislación vigente.
E. La Municipalidad de Nombre20770 deberá realizar periódicamente, según las condiciones de acumulación de materiales en el cauce del río Nombre20770 y todos aquellos que drenan el cantón, una adecuada canalización que ayude a recuperar la capacidad hidráulica del cauce y disminuya la amenaza de inundación en cada sector. F. La Municipalidad de Nombre20770 deberá permanecer vigilante de las zonas de alto riesgo, inundación y susceptibles al deslizamiento, no otorgar permisos constructivos o desarrollo de asentamientos informales de viviendas en ellos. G. Cualquier anomalía en cuanto a técnicas de construcción u omisión a las recomendaciones aquí descritas, QUEDA BAJO TOTAL RESPONSABILIDAD de las instituciones que otorgan los permisos, del ingeniero o responsable de la obra y de la Municipalidad respectiva de no solicitar los informes, inspecciones y correcciones correspondientes”.
Asimismo, por oficio CNE-UGPR-OF-0669-2023 del 21 de abril de 2023, la Unidad de Gestión de Procesos de Reconstrucción de la CNE consignó: “En referencia al Recurso de Amparo con número de expediente 23-007675-0007- CO, interpuesto por la señora [Nombre62 001], vecina de la comunidad de San Nombre41 en Nandayure, en contra de la Municipalidad de Nombre20770 por las afectaciones ocasionadas en su inmueble al desbordarse el río Nombre20770 y los trabajos de dragado que se han realizado, se informa: 1. A la fecha, en la CNE se han gestionado todas las afectaciones reportadas en su momento por la Municipalidad de Nombre20770 en el sector, en su mayoría solicitudes para la intervención mediante los procesos conocidos como primeros impactos, regulados en el marco legal de la Ley 8488, Ley Nacional de Emergencias y Prevención del Riesgo. 2. Entre los decretos vigentes, no está incluido el cantón de Nandayure. 3.
El tipo de intervención que se ha efectuado, consiste en la contratación de horas máquina para retirar material y sedimento del centro del cauce, apilándolo en las márgenes, propiciando una mejor canalización del flujo del agua y disminuyendo el riesgo del desbordamiento del río. Este tipo de intervenciones fueron ejecutadas a razón de la solicitud y el reporte de afectaciones emitido por parte de la Municipalidad, quien además es responsable de la supervisión y el empleo adecuado de las horas contratadas. 4. En este tipo de intervenciones se descarta cambiar el curso o redirigir el cauce del cuerpo del agua, pues es de nuestro conocimiento, que para poder efectuar intervenciones de este tipo son necesarios una serie de estudios, levantamientos, modulaciones, entre los que se puede señalar el topográfico, el hidrológico e hidráulico, el geológico, entre otros. Es por tal razón, que, en los casos de las intervenciones financiadas por la CNE, se rechaza lo indicado por la recurrente al aseverar que se ha cambiado el curso o que el “… dragado redirigió el río a la parte trasera de su casa …”; máxime que no se aporten respaldos ni pruebas que puedan sustentar este tipo de aseveraciones. 5.
Gran parte de las aseveraciones planteadas por la recurrente, se fundamentan en supuestos que no han sido comprobados, a modo de ejemplo se cita la “Nota Técnica” confeccionada por el geólogo Wagner Valverde Mora, en el que en varios extractos del documento, indica que uno de los aspectos que pudo incidir en la erosión de la margen colindante a la propiedad de la recurrente, ha sido el supuesto, que en algún momento pudo haber existido un “dique” en la margen opuesta, y que en caso de que así hubiese sido, esto hubiese contribuido a la acción erosiva de la margen en la propiedad de la recurrente; nótese incluso que en el apartado 3 CONCLUSIONES, de dicha Nota Técnica, se señala: “ – Cabe la posibilidad de que alguna estructura haya sido construida desde la margen derecha hacia el centro del cauce (“dique”), …” 6. Aunado a lo anterior, pareciera que no se consideran aspectos que inducen el incremento del caudal del río Nandayure, el cambio climático, la deforestación, la capacidad de absorción del suelo, el fenómeno de la Niña, entre muchos otros, por los cuales el caudal del río Nombre20770 se incrementará en momentos específicos.
Así mismo, debe recordase que el río Nombre20770 como todos los cuerpos de agua, varían sus dinámicas, amplían o disminuyen sus secciones, puede modificar su rumbo, dependiendo de las condiciones y características en cada momento en específico, por lo que no se debería responsabilizar o culpar el efecto de la acción erosiva, en base a supuestos o apreciaciones subjetivas. Para complementar la respuesta anterior, a continuación, se muestra un cuadro con las intervenciones que se han realizado en el río Nombre20770 en la comunidad de San Nombre41 ID NUMERO PROCEDIMIENTO OBJETO CONTRACTUAL PROVINCIA CANTÓN DISTRITO Nombre62 ADJUTICATARIO MONTO ADJUDICADO 1 2019PI-000008-0006500001 Alquiler de Maquinaria para atender la emergencia en la comunidad de San Pablo, río Nandayure, Nombre20770 Guanacaste Nombre20770 San Nombre41 Constructora Hermanos Herrera Barrantes ₡ 14 823 650, 00 2 2020PI-000374-0006500001 Limpieza y Recava del cauce del río Nandayure, con el fin de evitar nuevos desbordamientos del río, que ocasionen afectaciones a las comunidades e infraestructura Guanacaste Nombre20770 San Nombre41 Constructora MECO, S.A ₡22 093 647, 00 TOTAL ₡ 36 917 297,00 Además, se constata que mediante oficio AM-AA-0441-2023 del 28 de abril de 2023, el alcalde de Nombre20770 consignó: “Saludos cordiales; seguidamente daremos respuesta al proceso presentado por la Señora [Nombre62 001]; en relación a los trabajos ejecutados en el cauce del Río Nombre20770 en el año 2020; así como también de nuestro compromiso y seguimiento al problema natural que presenta el Río Nandayure, propiamente desde el Puente de Carmona hasta su desembocadura en el Puerto de San Pablo. • Consideraciones Generales Se puede observar en la figura adjunta, que el Río Nombre20770 presenta dos áreas de inundación potenciales y que afectan directamente a la Comunidad de Carmona centro de población y a la Comunidad de Puerto San Pablo, el río se desplaza de un punto alto hacia una zona muy plana situación que provoca el desbordamiento del cauce y por ende la afectación directa a las propiedades colindantes.
El Cauce del Río Nombre20770 en los últimos 10 años ha cambiado su morfología fluvial, por su movilidad las áreas colindantes no tienen estabilidad ni permanencia, se desplazan y modifican más de lo que suele imaginarse. Esta movilidad fluvial representa un peligro para las obras de ingeniería ubicadas sobre el lecho fluvial y en sus inmediaciones, las que por su propia naturaleza deben ser estables. Es decir, la magnitud del problema no se soluciona únicamente con el dragado del cauce, debemos de ir más allá, lo que se ha realizado en los últimos años se ha justificado en obras de encauzamiento formado por diques paralelos, y al ser caudales lo suficientemente grandes los mismos destruyen las obras generadas con los materiales del cauce; desbordan debido a su sinuosidad atacando frontalmente las defensas creadas por equipo especial. • Criterio de la Situación y a la Actuación Municipal Entendemos la preocupación de todas las comunidades que colindan con el Río Nandayure; lo que ha generado el compromiso municipal en buscar soluciones más duraderas y debidamente coordinadas con las instituciones competentes Comisión Nacional de Emergencias y el Ministerio de Obras Públicas y Transportes.
No omitimos indicar que hemos trabajado este problema coordinadamente con dichas instituciones pero la sinergia no ha sido la suficiente para poder dar una solución integral duradera, seguimos utilizando las mismas técnicas de dragados, trabajos por horas maquinaria que solo resuelven para el período de invierno y la mayoría de las veces ni para ese período, y se trabaja solo en los puntos críticos erosionables, dejando de valorar otros aspectos de la gestión y desarrollo de la morfología fluvial. Con esto pretendemos indicar y rescatar los esfuerzos que individualmente hemos realizado en la búsqueda de soluciones, sin embargo es requerido que la Comisión Nacional de Emergencias y el Ministerio de Obras Públicas y Transportes, este último como rector en la material fluvial participe más activamente con sus profesionales, maquinaria y equipo, en los diferentes estudios hidrológicos e hidráulicos que son requeridos para dar soluciones que perduren en el tiempo y que contribuyan con la regeneración de la naturaleza autóctona de la zona.
La Comisión Nacional de Emergencias CNE; ha generado infinidad de visitas a lo largo del tiempo, al Cauce sobre el Río Nandayure; lo cual agradecemos pero sentimos que no es suficiente lo que se indica en el documento – informe INFORME TÉCNICO CNE-UIAR-INF-1193-2021 valoración de riesgo en las márgenes del río Nombre20770 en la localidad de San Nombre41 Viejo, por problemas erosión lateral y anegamiento del sector, su criterio es trascendental, pero requerimos de más apoyo y recursos para las emergencias que se han suscitado, de hecho a través de los informes de primer impacto realizados y amparados en el Decreto de Nate, hemos solicitado que se valore la inclusión de obras mayores preventivas y correctivas para minimizar el riesgo latente que cada invierno sufren las comunidades de Carmona y Puerto San Pablo. De manera tal que apelamos al trabajo en equipo de las tres instituciones, no solamente en razón de soluciones preventivas básicas, si no más bien ha generar un equipo de trabajo interinstitucional profesional para contribuir con soluciones hidráulicas más duraderas y eficientes, en beneficio de las comunidades afectadas. • Propuesta Municipal período 2020 En el mes de junio del año 2020, se ejecutó un trabajo en conjunto con el Ministerio de Obras Públicas y Transportes, el alcance del trabajo fue el dragado del Cauce en la comunidad de San Nombre41 tanto aguas arriba como aguas abajo del punto referenciado; el MOPT, aporto equipo especial, una excavadora y un tractor de oruga, para la conformación de los diques laterales de contención o barreras protectoras a las propiedades colindantes.
Sin emabrgo (sic) al utilizarse el mismo material del río tipo arenoso con las escorrentías suscitadas en periodos anteriores las mismas afectarón (sic) las estructuras paralelas de contención; dichos trabajos fueron realizados exactamente detrás de la propiedad de la Señora [Nombre62 001], tal y como se puede apreciar en la siguiente fotográfia (sic). (…) Trabajos realizados en el año 2020, protección con diques paralelos a propiedades colindantes para evitar el desbordamiento del Río Nandayure. Posteriormente en el mes de julio de 2022, la Municipalidad de Nombre20770 realizo trabajos de dragado del cauce propiamente en el sitio conocido como San Pablo, para mejorar el área hidraúlica (sic) de la sección de cauce dado a que en este punto el río se desborda cortando el paso del caminio (sic) cantonal que comunica con Puerto San Pablo. De esta forma hemos trabajado en coordinación con la dirección de aguas del Minae para poder contar con la autorización respectiva y así poder impactar los puntos más críticos, sin embargo insistimos que las obras ejecutadas no son suficientes para contener y disipar la energía del agua.
(…) Propuesta Municipal período 2023 En seguimiento de la problemática que se presenta en el cauce del Río Nandayure; la Municipalidad de Nombre20770 ha estado trabajando en los tramos críticos del mismo, ejecutando labores de dragado y encausamiento formando un dique lateral con el material propio del cauce, lo cual contribuye ha (sic) mejorar y ha (sic) fortalecer el encusamiento (sic) del flujo. Cabe mencionar que en el mes de abril de 2023, se iniciaron las labores con equipo municipal en las coordenas (sic) N 10 2 6.704 W 85 13 25.525, con la objetividad de reforzar con material aquellas zonas propensas de desbordamiento tal y como se puede evidenciar en las siguientes fotografías. (…) De esta forma la Municipalidad continuará trabjando (sic) a lo largo del Río Nombre20770 inclusive en el área que afecta la propiedad de la Señora [Nombre62 001], mediante la utilización de la excavadora para la conformación de los diques con sus respetivas coronas y respetando los meandros originales del cauce.
El 18 de agosto de 2022, se coordino (sic) y gestionó con personal técnico de la CNE; la visita a cada uno de los puntos críticos del Cauce del Río Nandayure, principalmente en la comunidad de Puerto San Pablo, el mismo desprende una serie de recomendaciones técnicas para evitar el desbordamiento del río. Recomendaciones que requieren de la elaboración de un plan de trabajo acompañado de los recursos técnicos y financieros del Ministerio de Obras Públicas y Transportes (MOPT) y de la Comisión Nacional de Emergencias (CNE), así como también de éste municipio. • Propuesta Técnica Municipal para minimizar el riesgo de Innundación (sic) La Municiaplidad (sic) ha estado analizando la viabilidad técnica y finaciera (sic) de la apliación (sic) de una estructura llamada un geocontendor estructural textil hidroblock prismático de alta resistencia a la interperie (sic) el cual es llenado mediante el material existente en el cauce, mediante medios mecánicos o hidráulicos con el suelo del sitio tipo grava, para obtener unidades de masa de gran volumen que se acomoden sobre el terreno de manera versátil.
Por su forma y tamaño se utilizan en la construcción de estructuras de gravedad, en la fachada de muros en suelos reforzados, en estructuras de control hidráulico, control de erosión en orillas, rehabilitación de orillas erosionadas, revestimiento de diques, terraplenes, taludes de cauces, realce de orillas, realce de corona en estructuras de control hidráulico, y protección de tuberías Esta solución es viable para fortalecer las secciones del cauce que presentan alta erosión de los taludes naturales que colindan con los patios, casas de habitación, que se han visto afectados por las crecidas del Río Nandayure, su costo es importante y se requiere de un presupuesto extraordinario, la ventaja que presenta esta estructura es que su costo como insumo, elemento, se ve compensado con el material se sitio, pues no tendríamos que comprar gran cantidad de material granular sobre tamaño que incrementaría exponencialmente los costos del proyecto. • Propuesta Técnica acompañamiento CNE- MOPT- MINAE- MUNICIPALIDAD Requerimos del acompañamiento interinstitucional con las siguientes competencias para poder impactar los puntos críticos mediante una programación a corto y mediano plazo según la disponibilidad de recursos de cada institución.
Requerimiento a solicitar la MOPT • Estudios Hidrológicos • Estudios Hidráulicos • Disponibilidad de Maquinaria y Equipo • Apoyo Técnico profesional Requerimiento a solicitar a la CNE: • Recursos financieros para compra geocontendor estructural textil hidroblock prismático. • Continuar con el estudio de vulnerabilidad valoración de riesgo en las márgenes del río Nandayure, del sector faltante entre el Puente Carmona hacia la comunidad de San Pablo. • Apoyo Técnico profesional • Disponibilidad de Maquinaria y Equipo (horas maquinaria). • Dar seguimiento a los compromisos que se generaron con el Decreto Nate, el mismo esta (sic) activo y se podría gestionar los recursos necesarios para contribuir con la solución planteada. Requerimiento a solicitar la MINAE: • Realizar los estudios para realizar obras en cauce de dominio público. • Apoyo Técnico profesional Requerimiento a la solicitar la Municipalidad Nandayure: • Recursos financieros para compra geocontendor estructural textil hidroblock prismático. • Disponibilidad de Maquinaria y Equipo • Apoyo Técnico profesional • Coordinación de enalce (sic) entre las instituciones indicadas.
De los plazos de ejecución periódo 2023 Como Municipalidad hemos iniciado con el estudio de anteproyecto de los puntos a intervenir para poder estimar los costos de cada sub proyecto, actualmente se presentará el presupuesto extraordinario para la compra de aproximadamente 3.393 bloques hidroblock prismático; para impactar los puntos más críticos donde el Río Nombre20770 presenta desbordamiento. Reiteramos que como Municipalidad no contamos con todos los recursos, por lo que insistimos que se debe de crear una comisión de trabajo para poder planear, y ejecutar las obras en un plazo adecuado para evitar mayores trajedias (sic) a los ciudadanos de Carmona y San Nombre41 y Puerto San Nombre41”.
Finalmente, ante una prueba para mejor resolver, el alcalde de Nombre20770 informó: “De conformidad con la resolución de las 14 horas 57 minutos del 18 de octubre del 2023, y como prueba para mejor resolver, me permito informar: 1. Desde cuanto (sic), se está trabajando en la solución para la problemática denunciada por la parte recurrente, que consiste en la aplicación de una estructura llamada: geo contenedor estructural textil hidroblock prismático. Las gestiones para el dragado del río Nombre20770 se vienen efectuando desde el año 2017, siendo que el río se dragó́ en el año 2017 y 2019, para paliar las afectaciones que produce, mientras se puede hacer un trabajo más integral, que se encuentra limitado por los altos costos de los estudios ambientales y de otro orden. Para efectuar un nuevo dragado se vienen haciendo gestiones desde el año 2022 por parte de la Municipalidad de Nombre20770 y otros entes, para la obtención de los permisos para la intervención del río, lamentablemente dichos permisos no han sido otorgados por motivos externos a nuestra institución, pero las gestiones si se han realizado en conjunto con la Comisión de Emergencias.
Con respecto a la aplicación del sistema denominado hydroblok, debe indicarse que cuando el señor Nombre11504 , esposo de la recurrente, se apersonó a la Municipalidad para preguntar sobre el estado para los trabajos del río, se le comento que se había ido a una capacitación para el conocimiento de un nuevo sistema constructivo llamado hydroblok, se le explico en qué consiste y cómo funciona, además se le externó que se estaba tratando de incluirlo dentro del presupuesto, para la compra de estas bolsas para iniciar pruebas en algunos de los puntos más problemáticos que teníamos en el cantón siempre y cuando se aprobara el presupuesto, pero en ningún momento se le dijo que eso iba a ser usado en la parte de su propiedad porque como se mencionó́ antes, se debían realizar pruebas para saber si eran funcionalmente aceptables para la solución del problema que tenemos no solo en el terreno del señor, si no en otros puntos a lo largo del rio, con un cauce problemático que tiene poco más de 13 kilómetros, al menos desde el Puente a la entrada a la ciudad de Carmona hasta su desembocadura en el Puerto de San Pablo.
En la figura adjunta, se puede observar que el río Nombre20770 presenta dos áreas de inundación potenciales y que afectan directamente a la Comunidad de Carmona, centro de población y a la comunidad de Puerto San Pablo, el río se desplaza de un punto alto hacia una zona muy plana situación que provoca el desbordamiento del cauce y por ende la afectación directa a las propiedades colindantes. El cauce del Río Nombre20770 en los últimos 10 años ha cambiado su morfología fluvial, por su movilidad las áreas colindantes no tienen estabilidad ni permanencia, se desplazan y modifican más de lo que suele imaginarse, dadas las características propias del mismo antes mencionadas (desplazamiento de un punto alto hacia una zona muy plana). Esta movilidad fluvial representa un peligro para las obras de ingeniería ubicadas sobre el lecho fluvial y en sus inmediaciones, las que por su propia naturaleza deben ser estables.
Es decir, la magnitud del problema no se soluciona únicamente con el dragado del cauce, debemos de ir más allá́, lo que se ha realizado en los últimos años se ha justificado en obras de encauzamiento formado por diques paralelos, y al ser caudales lo suficientemente grandes los mismos destruyen las obras generadas con los materiales del cauce, desbordan debido a su sinuosidad atacando frontalmente las defensas creadas por equipo especial. 2. Indicar si ya se solicitó́ el presupuesto, o si ya se aprobó́ el presupuesto. El presupuesto ya fue presentado ante el Concejo Municipal, lastimosamente dicho presupuesto fue improbado por parte de ellos. A lo anterior se suma la improbación de los últimos presupuestos por parte de la Contraloría General de la República. 3. Para cuándo se pretende iniciar las obras. Las obras se podrán realizar en cuanto exista el contenido presupuestario y se logren tramitar los permisos correspondientes ante la Dirección de Aguas del Ministerio del Ambiente y Energía (MINAE) para intención del río. 4.
Cuál es el estado actual del cauce de dicho río Nandayure. El estado actual del río es propenso a desbordarse en algunos sectores, como se indicó́ supra, pero en lo que respecta al terreno y vivienda de la señora [Nombre62 001] la vivienda se encuentra fuera de la zona de protección de este y hasta el momento no tiene peligro alguno de inundación. 5. Si se han comunicados con los vecinos para explicarles las obras a realizar y en qué plazo. Como decir que se haya efectuado una reunión masiva con los vecinos para explicarles las obras a realizar debo indicar que se no se ha efectuado, sin embargo, cuando se han hecho otros trabajos de intervención en algunos puntos del cauce, en coordinación entre la Municipalidad de Nandayure, el MOPT y la Comisión de Emergencias, si se ha informado los vecinos. Incluso, hace escasos unos 15 días más o menos, se visitó́ la zona donde se ubica la casa de la recurrente, reuniéndome con la misma y su esposo, a quien se les comunicó sobre los trabajos que se podrían efectuar a mediano plazo, así́ como sobre la problemática que presenta el río Nombre20770 en todo su cauce, principalmente desde el puente a la entrada a Ciudad Carmona hasta la desembocadura en Puerto San Pablo, que es precisamente la parte llana problemática por la fuerza que el mismo presenta.
También se les ha comunicado que actualmente no tenemos ningún permiso para intervención del rio, aunque actualmente nos encontramos tramitando un primer impacto sobre el rio, pero para ser intervenido en los puntos más críticos a lo largo del río”.
Aclarado ese panorama, nótese que a pesar de que han transcurrido casi 5 años, se aprecia que aún persiste la situación de las inundaciones, y que no se han ejecutado las obras necesarias para alcanzar una solución integral y definitiva.
En tal sentido, si bien las autoridades accionadas han realizado distintas obras paliativas como dragados y otros trabajos de limpieza y canalización, no menos cierto es que tales acciones han resultado insuficientes. Al respecto, la propia municipalidad accionada reconoce que es necesario ejecutar mayores esfuerzos para la implementación de obras duraderas que solventen el problema acusado. Así las cosas, pese a que desde al menos hace aproximadamente 5 años las autoridades conocen el problema de marras y han realizado determinados trabajos paliativos, no han gestionado lo pertinente para alcanzar una solución integral y definitiva garantice la seguridad de la comunidad de San Nombre41 de Nandayure.
De tal manera, lo procedente es declarar con lugar el recurso, a fin de garantizar una solución integral dentro de un plazo razonable.
VI.Nota del Magistrado Salazar Alvarado. En tesis de principio, considero que los casos relacionados con la inactividad de la Administración Pública en la reparación, construcción, modificación o demolición de cualquier obra de infraestructura deben ser desestimados, por constituir, esa omisión, un tema de legalidad, cuya discusión corresponde a la jurisdicción ordinaria, ante la cual la persona interesada puede debatir, con mayor amplitud, sus disconformidades. Sin embargo, cuando de aquella conducta administrativa omisiva se derive alguna violación a otros derechos fundamentales tutelados en esta jurisdicción constitucional, o se afecten grupos considerados vulnerables, sí entro a conocer el fondo del asunto, por constituir esta situación una excepción a mi posición en esta materia, tal y como sucede en este caso, en que la parte recurrente acusa que las autoridades recurridas realizaron trabajos de dragado en tal río; sin embargo, estos fueron efectuados defectuosamente, toda vez que cambiaron su curso normal, de modo que, ese mismo año, las lluvias destruyeron las obras. Aduce que el dragado redirigió el río a la parte trasera de su casa de habitación, por lo que teme que el caudal arrase con su vivienda.
Si bien coincido con la mayoría de la Sala en que el recurso se debe declarar con lugar, difiero sobre dónde residenciar la fase de ejecución del asunto, debido a la inexistencia de mecanismos adecuados previstos por la normativa que rige esta jurisdicción constitucional para dar seguimiento a una sentencia que reviste aspectos técnicos de gran complejidad, como es en este caso para que en el plazo de un año, contado a partir de la notificación de esta sentencia, se solucione el problema de inundaciones provocadas por el río Nombre20770 en la comunidad de San Nombre41 de Nandayure. En cambio, lo dispuesto por el Código Procesal Contencioso-Administrativo en materia de ejecución (artículo 155 y siguientes) tiene evidentes ventajas, como la posibilidad de pedir cronogramas, imponer multas, sentar responsabilidades, fiscalizar etapas de cumplimiento, etc. Por ello, de conformidad con lo dispuesto por el artículo 56 de la Ley de Jurisdicción Constitucional, estimo que la fase de ejecución debe realizarse ante el Área de Ejecución del Tribunal Contencioso Administrativo y Civil de Hacienda, bajo las reglas de ejecución de sentencia de dicho Código.
Se previene a las partes que de haber aportado algún documento en papel, así como objetos o pruebas contenidas en algún dispositivo adicional de carácter electrónico, informático, magnético, óptico, telemático o producido por nuevas tecnologías, éstos deberán ser retirados del despacho en un plazo máximo de 30 días hábiles contados a partir de la notificación de esta sentencia. De lo contrario, será destruido todo aquel material que no sea retirado dentro de este plazo, según lo dispuesto en el "Reglamento sobre Expediente Electrónico ante el Poder Judicial", aprobado por la Corte Plena en sesión N° 27-11 del 22 de agosto del 2011, artículo XXVI y publicado en el Boletín Judicial número 19 del 26 de enero del 2012, así como en el acuerdo aprobado por el Consejo Superior del Poder Judicial, en la sesión N° 43-12 celebrada el 3 de mayo del 2012, artículo LXXXI.
Por tanto:
Se declara con lugar el recurso. Se ordena a Giovanni Jiménez Gómez y Faride Beirute Cárdenas, por su orden, alcalde y jefe del Departamento de Ingeniería Municipal, ambos de la Municipalidad de Nandayure; a Luis Esteban Amador Jiménez y Óscar Salgado Portuguez, por su orden, ministro y director de Obras Fluviales, ambos del Ministerio de Obras Públicas y Transportes; así como a Alejandro José Picado Eduarte, en su condición de presidente de la Comisión Nacional de Prevención de Riesgos y Atención de Emergencias, o a quienes ocupen esos cargos, coordinar lo necesario y llevar a cabo todas las actuaciones que estén dentro del ámbito de sus respectivas competencias para que: i) en el plazo de DOS MESES, contado a partir de la notificación de este pronunciamiento, se diseñe un plan para atender el problema objeto de este recurso que deberá ser remitido a este Tribunal, y el cual deberá incluir un cronograma en el que se detallen las fechas de realización de las actividades, cuyos plazos deberán ser respetados, a los efectos de resolver tal problemática; y, 2) con esta programación, el problema objeto del presente amparo debe quedar definitivamente resuelto en el plazo de UN AÑO, a partir de la notificación de este pronunciamiento.
Se advierte a las autoridades recurrida que, de acuerdo con lo establecido en el artículo 71 de la Ley de la Jurisdicción Constitucional, se impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo, y no la cumpliere o hiciere cumplir, siempre que el delito no esté más gravemente penado. Se condena al Estado, a la Municipalidad de Nombre20770 y a la Comisión Nacional de Prevención de Riesgos y Atención de Emergencias al pago de las costas, daños y perjuicios causados con los hechos que sirvieron de base a la presente declaratoria, los que se liquidarán en ejecución de sentencia de la jurisdicción contencioso-administrativa. El Magistrado Salazar Alvarado pone nota. La Magistrada Garro Vargas salva el voto respecto a la ejecución de esta sentencia y, de conformidad con el artículo 56 de la Ley de la Jurisdicción Constitucional, dispone que debe realizarse ante el Área de Ejecución del Tribunal Contencioso Administrativo y Civil de Hacienda, bajo las reglas de ejecución, establecidos en los artículos 155 y siguientes del Código Procesal Contencioso Administrativo. Asimismo, ordena que se le remita copia de la sentencia para que se inicie los procedimientos de ejecución de este fallo.
Fernando Cruz C..
Presidente a.i.
Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Nombre5659 H.
Nombre5272 A.
Alexandra Alvarado A.