Res. 27316-2022 Sala Constitucional · Sala Constitucional · 18/11/2022
OutcomeResultado
The amparo is partially granted against the Municipality of Nandayure and the MOPT, ordering them to carry out the necessary works within 12 months to solve the Nandayure River flooding. It is denied against the CNE.Se declara parcialmente con lugar el recurso contra la Municipalidad de Nandayure y el MOPT, ordenándoles realizar las obras necesarias en 12 meses para solucionar las inundaciones del Río Nandayure. Se declara sin lugar contra la CNE.
SummaryResumen
The Constitutional Chamber heard an amparo filed by a resident of San Pablo de Nandayure, affected by recurrent flooding of the Nandayure River. Although in 2019 the Chamber had already ordered hydrological studies and a hydraulic model, three years later the flooding persisted and no comprehensive works had been carried out. The Chamber partially granted the amparo against the Municipality of Nandayure and the Ministry of Public Works and Transport (MOPT), ordering them to coordinate and carry out all necessary actions and works to comprehensively and definitively solve the flooding problem within a maximum of twelve months. Regarding the National Emergency Commission (CNE), the amparo was denied because it had responded to the Municipality's requests within its powers. The judgment includes a partial dissenting vote by Justice Garro Vargas, who considers that the enforcement phase should be handled by the Administrative Litigation Court, given the advantages of the Administrative Procedural Code for monitoring complex technical works.La Sala Constitucional conoció un recurso de amparo interpuesto por un vecino de San Pablo de Nandayure, afectado por las recurrentes inundaciones del Río Nandayure. A pesar de que en 2019 ya se había ordenado realizar estudios hidrológicos y una modelación hidráulica, tres años después las inundaciones persistían y no se habían ejecutado obras integrales. La Sala declaró parcialmente con lugar el recurso contra la Municipalidad de Nandayure y el Ministerio de Obras Públicas y Transportes (MOPT), ordenándoles coordinar y ejecutar todas las gestiones y obras necesarias para solucionar de manera integral y definitiva el problema de inundaciones, en un plazo máximo de doce meses. Respecto a la Comisión Nacional de Emergencias (CNE), el recurso se declaró sin lugar porque atendió las solicitudes de la Municipalidad dentro de sus competencias. La sentencia incluye un voto salvado parcial de la magistrada Garro Vargas, quien considera que la fase de ejecución debe tramitarse ante el Tribunal Contencioso Administrativo, dadas las ventajas del Código Procesal Contencioso-Administrativo para el seguimiento de obras técnicas complejas.
Key excerptExtracto clave
Thus, despite the fact that for at least three years the authorities of the Municipality of Nandayure and the MOPT's River Works Directorate have known about the problem and have carried out certain palliative works, they have not taken the necessary steps to achieve a comprehensive and definitive solution that guarantees the safety of the community of San Pablo de Nandayure. Therefore, it is appropriate to grant the amparo against these agencies, in order to ensure a comprehensive solution within a reasonable period. Jenaro Ruiz Chacón, acting director of the River Works Directorate of the Ministry of Public Works and Transport, and Giovanni Jiménez Gómez, mayor of Nandayure, or their respective successors, are ordered to coordinate accordingly, issue the relevant orders, and carry out all actions within their respective competencies so that, within a maximum period of TWELVE MONTHS from the notification of this judgment, all necessary steps and works are carried out to comprehensively and definitively solve the flooding problem of the Nandayure River affecting the community of San Pablo de Nandayure.Así las cosas, pese a que desde al menos hace 3 años las autoridades de la Municipalidad de Nandayure y de la Dirección de Obras Fluviales del MOPT conocen el problema de marras y han realizado determinados trabajos paliativos, no han ejecutado lo pertinente para alcanzar una solución integral y definitiva garantice la seguridad de la comunidad de San Pablo de Nandayure. De tal manera, lo procedente es declarar con lugar el recurso en cuanto a tales dependencias, a fin de garantizar una solución integral dentro de un plazo razonable. Se ordena a Jenaro Ruiz Chacón y a Giovanni Jiménez Gómez, por su orden, director a.i. de la Dirección de Obras Fluviales del Ministerio de Obras Públicas y Transportes y alcalde de Nandayure, o a quienes respectivamente ocupen tales cargos, que coordinen lo correspondiente, giren las órdenes pertinentes y lleven a cabo todas las actuaciones que estén dentro del ámbito de sus respectivas competencias para que, dentro del plazo máximo de DOCE MESES, contado a partir de la notificación de esta sentencia, se realicen todas las gestiones y obras pertinentes para solucionar de manera integral y definitiva el problema de inundaciones del Río Nandayure, que afecta a la comunidad de San Pablo de Nandayure.
Pull quotesCitas destacadas
"ante la duda, y dado que el año pasado se produjeron inundaciones que dañaron los trabajos ya realizados, se debe aplicar el 'principio de evitación prudente o precautorio', con respecto a la posible afectación que podría causar el desbordamiento del cauce del río, a la salud e integridad de las personas que habitan dicha comunidad así como a sus viviendas, la alteración de ecosistemas, erosión, la destrucción de caminos, cultivos, la afectación de la salud y el bienestar de la vida silvestre y el ganado, entre otros."
"given the doubt, and since last year floods damaged the already completed works, the 'principle of prudent avoidance or precaution' must be applied regarding the possible harm that the river overflowing could cause to the health and integrity of the people living in that community as well as their homes, the alteration of ecosystems, erosion, the destruction of roads, crops, the impact on the health and well-being of wildlife and livestock, among others."
Considerando III, quoting previous judgment 2019018960
"ante la duda, y dado que el año pasado se produjeron inundaciones que dañaron los trabajos ya realizados, se debe aplicar el 'principio de evitación prudente o precautorio', con respecto a la posible afectación que podría causar el desbordamiento del cauce del río, a la salud e integridad de las personas que habitan dicha comunidad así como a sus viviendas, la alteración de ecosistemas, erosión, la destrucción de caminos, cultivos, la afectación de la salud y el bienestar de la vida silvestre y el ganado, entre otros."
Considerando III, quoting previous judgment 2019018960
"Con el fin de proteger el medio ambiente, los Estados deberán aplicar ampliamente el criterio de precaución conforme a sus capacidades. Cuando haya peligro de daño grave o irreversible, la falta de certeza científica absoluta no deberá utilizarse como razón para postergar la adopción de medidas eficaces en función de los costos para impedir la degradación del medio ambiente."
"In order to protect the environment, the precautionary approach shall be widely applied by States according to their capabilities. Where there are threats of serious or irreversible damage, lack of full scientific certainty shall not be used as a reason for postponing cost-effective measures to prevent environmental degradation."
Considerando III, quoting Rio Declaration Principle 15
"Con el fin de proteger el medio ambiente, los Estados deberán aplicar ampliamente el criterio de precaución conforme a sus capacidades. Cuando haya peligro de daño grave o irreversible, la falta de certeza científica absoluta no deberá utilizarse como razón para postergar la adopción de medidas eficaces en función de los costos para impedir la degradación del medio ambiente."
Considerando III, quoting Rio Declaration Principle 15
"Restringir por parte de la Municipalidad de Nandayure el uso de suelo con fines habitacionales o de comercio en las zonas de protección del río Nandayure, según el artículo 33 de la ley forestal 7575, así como en las áreas identificadas con potencial afectación por inundaciones; según los mapas de amenazas naturales de la CNE."
"The Municipality of Nandayure must restrict land use for residential or commercial purposes in the protection zones of the Nandayure River, pursuant to Article 33 of Forestry Law 7575, as well as in areas identified as potentially affected by flooding, according to the CNE's natural hazard maps."
Considerando III, quoting CNE Technical Report recommendation C
"Restringir por parte de la Municipalidad de Nandayure el uso de suelo con fines habitacionales o de comercio en las zonas de protección del río Nandayure, según el artículo 33 de la ley forestal 7575, así como en las áreas identificadas con potencial afectación por inundaciones; según los mapas de amenazas naturales de la CNE."
Considerando III, quoting CNE Technical Report recommendation C
"Si bien coincido con la mayoría de la Sala en que el recurso se debe declarar con lugar, difiero sobre dónde residenciar la fase de ejecución del asunto, debido a la inexistencia de mecanismos adecuados previstos por la normativa que rige esta jurisdicción constitucional para dar seguimiento a una sentencia que reviste aspectos técnicos de gran complejidad."
"While I agree with the majority that the amparo should be granted, I differ on where to place the enforcement phase of the matter, due to the lack of adequate mechanisms provided by the rules governing this constitutional jurisdiction to follow up on a judgment involving highly complex technical aspects."
Considerando V, Dissenting vote of Justice Garro Vargas
"Si bien coincido con la mayoría de la Sala en que el recurso se debe declarar con lugar, difiero sobre dónde residenciar la fase de ejecución del asunto, debido a la inexistencia de mecanismos adecuados previstos por la normativa que rige esta jurisdicción constitucional para dar seguimiento a una sentencia que reviste aspectos técnicos de gran complejidad."
Considerando V, Dissenting vote of Justice Garro Vargas
Full documentDocumento completo
Date of Resolution: November 18, 2022, at 09:20 Case File: 22-019540-0007-CO Type of Matter: Amparo Appeal Judgment with Separate Note Relevance Indicators Relevant Judgment Related Judgments Content of Interest:
Strategic Themes: Economic, Social, Cultural, and Environmental Rights Type of Content: Majority Vote Branch of Law: 4. GUARANTEE MATTERS Topic: MUNICIPALITY Subtopics:
INFRASTRUCTURE AND CONDITIONS.
027316-22. MUNICIPALITY. ACCUSES FLOODING CAUSED BY THE NANDAYURE RIVER. THE APPEAL IS PARTIALLY GRANTED, SOLELY WITH RESPECT TO THE MUNICIPALITY OF NANDAYURE AND THE MINISTRY OF PUBLIC WORKS AND TRANSPORT. THE ACTING DIRECTOR OF THE FLUVIAL WORKS DIRECTORATE OF THE MINISTRY OF PUBLIC WORKS AND TRANSPORT AND THE MAYOR OF NANDAYURE ARE ORDERED TO COORDINATE ACCORDINGLY, ISSUE THE PERTINENT ORDERS, AND CARRY OUT ALL ACTIONS WITHIN THE SCOPE OF THEIR RESPECTIVE COMPETENCIES SO THAT, WITHIN A MAXIMUM PERIOD OF TWELVE MONTHS, ALL PERTINENT PROCEDURES AND WORKS ARE CARRIED OUT TO COMPREHENSIVELY AND DEFINITIVELY SOLVE THE PROBLEM OF FLOODING OF THE RÍO NANDAYURE, WHICH AFFECTS THE COMMUNITY OF SAN PABLO DE NANDAYURE. VCG05/2023 “(…) III.- ON THE SPECIFIC CASE. In the sub lite, the appellant states that he is a resident of San Pablo de Nandayure, an area affected by the flooding caused by the Río Nandayure. He claims that he has requested help from the respondent authorities to carry out the necessary works to solve the flooding problem; however, the situation remains the same. He adds that, in the current year, the aforementioned river destroyed trees, fences, posts, and crops.
From the study of the case file, it has been demonstrated that the respondent municipality reports that the Río Nandayure presents two flooding areas, affecting the communities of Carmona and San Pablo. In March 2020, the Dirección de Obras Fluviales of the MOPT carried out cleaning and channeling works on the Río Nandayure, as part of the measures to mitigate the effects of the rains. The president of the CNE reports: “this Commission, from 2018 to date, processed the following requests from the Municipalidad de Nandayure: 1) 2019PI-000008-0006500001 “Rental of Machinery to attend to the emergency in the community of San Pablo, río Nandayure, Nandayure 5th Occasion”, awarded on January 23, 2019, to the company Hermanos Herrera Barrantes Constructora, Sociedad Anónima, for 150 effective hours of an excavator and 150 effective hours of a Tractor, the purpose of which was the cleaning, re-excavation of the río Nandayure, and piling of material to the sides, like a dike, in order to avoid or mitigate overflows and greater affectation in the sector of the community of San Pablo, and 2) 2020PI-000374-0006500001 “Rental of Machinery to attend to affectations in San Pablo, desbordamiento río Nandayure”, where on December 11, 2020, it was awarded to Constructora Meco, Sociedad Anónima, for 150 effective hours of a tractor and 150 effective hours of an excavator, in order to attend to the undeclared emergency whose purpose was the cleaning and re-excavation of the riverbed of the río Nandayure in the community of San Pablo, Nandayure, in order to avoid new overflows of the river, that cause affectations to the communities and infrastructure.”.
In technical report no. CNE-UIAR-INF-1193-2021 of September 2022 from the Unidad de Investigación y Análisis de Riesgo of the CNE, it was recorded: “Risk assessment on the banks of the río Nandayure in the locality of San Pablo Viejo, due to problems of lateral erosion and flooding of the sector (…) Conclusions: A. According to the Mapa de Amenazas Naturales Potenciales of the CNE, the evaluated zones are within the area with direct affectation due to potential flooding when overflows of the flow of the río Nandayure and its tributaries occur in the plain zone, generally occurring when there are intense rains in the upper zone of the micro-watersheds influenced by extreme hydrometeorological phenomena. B. The sector evaluated in the locality of San Pablo Viejo is located within the micro-watershed of the río Nandayure, on the left bank. The evaluated zone is located within what corresponds to the area of the riverbed and alluvial plain, on the edges of the alluvial terraces built by the accretion of sediments deposited after extraordinary flood events.
C. The zone evaluated in the town of San Pablo Viejo de Nandayure presents a flat, undulating topography, is located at the point where the channel changes its encased condition in the river canyon and opens towards the alluvial plain, has varied cover with scattered trees and some housing infrastructure built within the zones that have been affected by flooding in the past, in addition, parallel to the channel runs a local road that is impacted when overflow events occur. D. In the sector evaluated running parallel to the riverbed of the río Nandayure, strong lateral erosion is observed on the banks, because the flow impacts the zones with great force. Throughout the lower section of the river, high sedimentation and clogging of materials that have completely filled it in are observed, generating a significant loss of hydraulic capacity and favoring overflow events when heavy rains occur.
E. Through the overflight carried out with an unmanned aerial vehicle (drone), evidence of overflow events, flooding, and deposit of debris on the banks in the plain, where several dwellings are located, is observed. Evidence is observed of the drag of the current and the debris it contained when it crosses the municipal road leading to San Pablo Viejo, and which continues towards adjacent lands. F. In the quebrada Pozas, which crosses the road leading to San Pablo Viejo, problems are observed at the crossing bridge, which becomes obstructed by debris drag and causes overflow of the flow. This problem interrupts passage, leaves the town isolated and without an option to leave because this is the only route to enter the community (…) Recommendations. A. The Municipalidad de Nandayure must coordinate with Obras Fluviales of the MOPT and the MINAE the possibility of carrying out adequate channeling on the riverbed of the río Nandayure at the evaluated sites presenting problems, to remove the amount of accumulated material that diminishes the hydraulic capacity of the sections, in addition, to carry out protection works to reduce lateral erosion on the banks and the protection dikes.
B. The Municipalidad de Nandayure must carry out the construction of adequate protection and containment works on the banks of the río Nandayure, with materials that are not eroded by extraordinary floods and that protect the sectors. C. Restrict, by the Municipalidad de Nandayure, the land use (uso de suelo) for residential or commercial purposes in the protection zones of the río Nandayure, according to Article 33 of the Ley Forestal 7575, as well as in the areas identified with potential affectation by flooding; according to the natural hazard maps of the CNE. D. The protection works that are implemented on the affected banks must be supervised by a professional affiliated with the Colegio Federado de Ingenieros y Arquitectos de Costa Rica, based on the standards established by the Código Sísmico, the Código de Cimentaciones, and the Reglamento de Construcciones, the Código Municipal, and other current legislation.
E. The Municipalidad de Nandayure must periodically carry out, according to the conditions of material accumulation in the channel of the río Nandayure and all those that drain the canton, adequate channeling that helps to recover the hydraulic capacity of the channel and reduces the flood hazard in each sector. F. The Municipalidad de Nandayure must remain vigilant over high-risk, flood, and landslide-susceptible zones, and not grant construction permits or development of informal housing settlements in them. G. Any anomaly regarding construction techniques or omission of the recommendations described herein, IS UNDER THE TOTAL RESPONSIBILITY of the institutions that grant the permits, the engineer or person responsible for the work, and the respective Municipality for not requesting the corresponding reports, inspections, and corrections.”. The mayor of the Municipalidad de Nandayure points out that dredging techniques and other works have been carried out to counteract flooding in the winter season; however, such actions are insufficient and a comprehensive, lasting solution has not been achieved.
On August 18, 2022, the Municipalidad de Nandayure and the CNE conducted a visit to each of the critical points in the community of San Pablo. The respondent municipality reports that it has begun the study of a preliminary project for the intervention of the river; however, it requires the participation of the other respondent agencies to plan and execute the respective works, in order to solve the problem denounced.
On this matter, it is important to highlight that, in judgment no. 2019018960 of 9:20 hours on October 4, 2019, this Court resolved an amparo appeal filed by the appellant, concerning the problematic situation of the Río Nandayure. In that resolution, it was stated:
“I.- Object of the appeal. The appellants claim that they have filed several procedures requesting the dredging of the río Nandayure, in the sector of San Pablo, and to date, they have not received a response nor have the corresponding actions been carried out (…)
IV.On the merits. The Administration, in light of Article 41 of the Constitución Política, has the obligation to guarantee citizens the fulfillment of prompt and complete justice, without denial, which implies, in the field of administrative justice, its obligation to decide with diligence and speed the claims raised by the administered parties, so that its resolution is consistent with the alleged points, as well as to communicate to the interested parties what has been ordered, all within a reasonable timeframe. In the case under study, the Chamber verifies an infringement of the provisions of Article 41 of the Constitución Política, given that the respondent party had not resolved the procedures filed by the appellants and other neighbors, since November 6, 2018, and reiterated on April 26 and June 13, both of 2019, which demonstrates a violation of the fundamental right to prompt and complete justice. Furthermore, it was upon notification of this amparo appeal that the respondent authority proceeded to resolve the procedure requested by the petitioners. Consequently, regarding this point, the appeal is granted.
V.On the other hand, although to date, it is not established that dredging of the río Nandayure is required in the sector requested by the appellants, as to be certain of this, technical studies must be carried out by the competent authorities; the truth is that, given the doubt, and considering that last year floods occurred that damaged the works already carried out, the 'precautionary principle or principle of prudent avoidance' (principio de evitación prudente o precautorio) must be applied, with respect to the possible affectation that the overflow of the river channel could cause to the health and integrity of the people living in said community as well as to their homes, the alteration of ecosystems, erosion, the destruction of roads, crops, the affectation of the health and well-being of wildlife and livestock, among others. Therefore, in application of said principle, and given the evidence that there could be a danger of serious or irreversible damage, the correct course of action is to act by minimizing, as much as possible, the risk situations that this situation could cause.
Furthermore, the appellants' claim is that a cleaning and deepening of the river in question, in the zone of San Pablo, be carried out, as well as the removal of rocks and sediments, to increase the depth, so translating said petition to constitutional grounds, the appropriate course is for the Chamber to grant the appeal and order the Municipal Mayor, in coordination with the competent entities of the Dirección de Obras Fluviales and the Region, of the Ministerio de Obras Públicas y Transportes, to carry out the technical studies indicated by said authorities, namely, a hydrological study and a two-dimensional hydraulic modeling to know with certainty the type of hydraulic work to be built and to identify if the existing infrastructure is within the river's protection zone for the solution of the problem. The foregoing is based on the provisions of Article 15 of the 'Declaración de Río', adopted by the Conferencia de las Naciones Unidas sobre el Medio Ambiente y el Desarrollo, in June 1992, which reads:
'In order to protect the environment, the precautionary approach shall be widely applied by States according to their capabilities. Where there are threats of serious or irreversible damage, lack of full scientific certainty shall not be used as a reason for postponing cost-effective measures to prevent environmental degradation'.
In accordance with the foregoing, it is necessary to insist that the observance of a principle can be rational or irrational, and the case of prudent avoidance is no exception. In fact, it is clear that the principle in question, as 'prudent avoidance', is only a recommendation, of transitory validity, for the application of specific preventive measures. Thus, by virtue of the foregoing, and in application of the precautionary principle, the appropriate course is to grant the appeal, solely with respect to this point.
Therefore:
The appeal is granted. Giovanni Jiménez Gómez, in his capacity as Mayor of the Municipalidad de Nandayure, or whoever holds said position, is ordered that, within a period of EIGHT MONTHS, from the notification of this judgment, must, in a coordinated manner with the authorities of the Dirección de Obras Fluviales and the Macro Región de Guanacaste, both of the Ministerio de Obras Públicas y Transportes, carry out and obtain the results of the hydrological study and the hydraulic modeling, as applicable, to know with certainty the type of hydraulic work to be built and to identify if the existing infrastructure is within the protection zone of the río Nadanyure, in order to solve the overflow problem occurring in the zone of San Pablo. The foregoing, under the warning of incurring the crime provided for in Article 71 of the Ley de la Jurisdicción Constitucional, in case of non-compliance.
The Municipalidad de Nandayure is ordered to pay the costs, damages, and losses caused by the facts serving as the basis for this declaration, which shall be settled in the sentence execution phase of the contentious-administrative jurisdiction. Notify this resolution to the respondent party, as well as to Jenaro Ruiz Chacón and Alonso Mora Arroyo, in their respective capacities as Acting Director of the Dirección de Obras Fluviales and Director of the Macro Región de Guanacaste, both of the Ministerio de Obras Públicas y Transportes, or whoever holds said positions, in person”.
Now then, as can be seen, in the precedent transcribed supra, the realization of certain studies that at that time were pending and that would serve to address the flooding problem in the river in question was ordered. However, approximately 3 years later, it is observed that the flooding situation still persists, and that the necessary works to achieve a comprehensive and definitive solution have not been executed.
In this sense, although the Municipalidad de Nandayure and the Dirección de Obras Fluviales of the MOPT have carried out various palliative works such as dredging and other cleaning and channeling works, it is no less true that such actions have been insufficient. In this regard, the respondent municipality itself acknowledges that it is necessary to execute greater efforts to carry out lasting works that resolve the denounced problem. Likewise, in technical report CNE-UIAR-INF-1193-2021 of September 2022 from the Unidad de Investigación y Análisis de Riesgo of the CNE, it was recorded that greater interventions and actions were necessary on the part of the respondent municipality.
Given the situation, despite the fact that for at least 3 years the authorities of the Municipalidad de Nandayure and the Dirección de Obras Fluviales of the MOPT have known about the problem in question and have carried out certain palliative works, they have not executed what is pertinent to achieve a comprehensive and definitive solution that guarantees the safety of the community of San Pablo de Nandayure.
Therefore, the appropriate course is to grant the appeal with respect to such agencies, in order to guarantee a comprehensive solution within a reasonable timeframe.
IV- On the other hand, in relation to the Comisión Nacional de Prevención de Riesgos y Atención de Emergencias, any omission meriting a declaration in this summary proceeding is ruled out a priori.
In this sense, it was reported under oath that the requests for assistance processed by the Municipalidad de Nandayure were duly attended to, and the contracts requested under procedures 2019PI-000008-0006500001 and 2020PI-000374-0006500001 were executed. Likewise, the respective inspection was carried out, and through report CNE-UIAR-INF-1193-2021 of September 2022, the recommendations pertaining to the works that the referred municipality must execute were detailed.
Consequently, the appropriate course is to dismiss the appeal with respect to this point. However, the president of the Comisión Nacional de Prevención del Riesgo y Atención de Emergencias must take note, so that, if required, within the framework of his competencies, he collaborates with the Municipalidad de Nandayure and the Dirección de Obras Fluviales of the MOPT in solving the problem subject to this appeal. (…)” ... See more Related Judgments Content of Interest:
Type of Content: Separate Note Branch of Law: 6. LEY DE LA JURISDICCIÓN CONSTITUCIONAL ANOTADA CON JURISPRUDENCIA Topic: 056- Ejecución de sentencias Subtopics:
NOT APPLICABLE.
While I concur with the majority of the Chamber that the appeal should be granted, I differ on where to place the enforcement phase of the matter, due to the lack of adequate mechanisms provided by the regulations governing this constitutional jurisdiction to follow up on a judgment that involves highly complex technical aspects, as is the case here of carrying out the necessary works to definitively solve the flooding problems suffered by the community of San Pablo caused by the río Nandayure. In contrast, the provisions of the Código Procesal Contencioso-Administrativo regarding enforcement (Article 155 and following) have evident advantages, such as the possibility of requesting schedules, imposing fines, establishing responsibilities, overseeing compliance phases, etc. Therefore, in accordance with the provisions of Article 56 of the Ley de Jurisdicción Constitucional, I believe that the enforcement phase should be carried out before the Área de Ejecución del Tribunal Contencioso Administrativo y Civil de Hacienda, under the sentence execution rules of said Code.
VCG05/2023 ... See more SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, at nine hours twenty minutes on the eighteenth of November two thousand twenty-two.
Amparo appeal processed in case file no. 22-019540-0007-CO, filed by RAMADIEL DE JESÚS SAENZ UGALDE, identity card number 0501230633, against COMISIÓN NACIONAL DE PREVENCIÓN DE RIESGOS Y ATENCIÓN DE EMERGENCIAS, MINISTERIO DE OBRAS PÚBLICAS Y TRANSPORTES, and MUNICIPALIDAD DE NANDAYURE.
Whereas:
And it is that lack of foresight, that is, not foreseeing that a certain situation may occur and not acting to avoid it, entails a risk to the life, health, and safety of persons and their property. It is understood that no Public Administration can prevent a public calamity from occurring, but it can be held responsible for not foreseeing the consequences that such a calamity may generate. This indicates that the legal system obligates every public body, but particularly the Commission, to act before the emergency arises and not only to act, but essentially to plan and take actions to prevent it, if it does arise, from causing harm to persons and property (Legal Opinion No. C-213-2014 of July 1, 2014). IV. POWERS AND RESPONSIBILITIES OF LOCAL GOVERNMENTS IN RISK PREVENTION THROUGH TERRITORIAL PLANNING: It is the duty of the municipal government to guarantee, through planning and the exercise of police power, that urban development addresses criteria of safety, health, and environmental sustainability.
The foregoing, in protection of citizens' rights. In this regard, the jurist Eduardo Ortiz Ortiz, cited in Legal Opinion C-032-98 of February 25, 1998, of the Office of the Attorney General of the Republic, has stated: \"The municipal competence to issue urban plans comes from the law, since it covers matters constitutionally reserved to it, but it also has constitutional foundation, since it is a local matter. This means that the law cannot delegate this except to the Municipality and that a law that did otherwise and empowered, for example, the Executive Branch, would be unconstitutional for violating municipal autonomy.\" Agreement No. 0443 of November 30, 2011, of the Board of Directors of the National Commission for Risk Prevention and Emergency Response, adopted in Extraordinary Session No. 10-11, held on Wednesday, November 9, 2011, and published in La Gaceta No. 230 of November 30, 2011, called: “Recommends to mayors to proceed immediately with the eviction of occupants of areas of recognized risk and imminent danger and to demolish the buildings located in them,” which textually concludes by stating: a. Recommend to all Mayors of the country: i. That in accordance with the duties and powers imposed upon them by the Political Constitution in its articles 50 and 169, the Municipal Code, the Urban Planning Law (Ley de Planificación Urbana), the Construction Law (Ley de Construcciones), the Organic Environmental Law (Ley Orgánica del Ambiente), article 33 of the Forestry Law (Ley Forestal), and related regulations, the General Health Law (Ley General de Salud), and the extensive case law on the subject, they proceed immediately with the eviction of occupants of areas of recognized risk and imminent danger, as well as to demolish the buildings located in them, and to monitor that they are not invaded again with human settlements, applying the procedural sequence cited in Considering IV, which is extracted from ruling No. 12485-2010 of the Constitutional Chamber. ii.
That due to the binding nature that the Constitutional Chamber confers upon them, they immediately implement the recommendations that the technicians of the CNE and academic institutions have repeatedly provided to them over many years and which are known to them, regarding concrete and timely actions to safeguard human life in areas of recognized risk and imminent danger. The studies and technical recommendations that have been historically issued in each case will be available to the municipalities at the CNE offices. The Internal Audit Offices and the Municipal Councils shall ensure compliance with these provisions. Disobedience will be considered a breach of duties, and must be brought by the Internal Audit Offices to the attention of the corresponding authority. (…) d. Formally communicate this Agreement to all Mayors, and to the Ombudsman's Office (Defensoría de los Habitantes). e. Publish this Agreement and the synthesis map of natural threats of the country (available on the website, www.cne.go.cr) in the official gazette and in a newspaper of national circulation.
The underlining is not from the original. At this point, it is necessary to recall that by constitutional mandate, the administration of the local interests and services of the canton is the competence of the Local Government, and for the specific case, the Municipality of Nandayure as a state legal entity, with its own assets and legal personality (article 2 of the Municipal Code No. 7794), has full legal capacity to execute all types of acts and contracts necessary to fulfill its purposes. V. THE BUDGET AND POWERS OF LOCAL GOVERNMENTS IN RISK PREVENTION 5.1. Article 46 bis of the National Law on Emergencies and Risk Prevention (Ley Nacional de Emergencias y Prevención del Riesgo): Through article 1 of Law No. 9907 of October twenty-seventh, two thousand twenty, article 46 bis was added to Law No. 8488, dedicated to the application of the three percent that was previously required to be transferred to the Commission by the municipal regime.
This article indicates that the municipalities and district municipal councils will calculate the three percent (3%) of the free budget surplus, set forth in article 46, based on the budget liquidation as of June 30 of the current year, having concluded the commitments effectively acquired from the prior period in accordance with what article 116 of Law 7794, Municipal Code, of April thirtieth, nineteen ninety-eight, allows. These resources will be executed by each municipal entity and will be allocated, exclusively, to the strengthening of technical capacity and municipal processes in risk management, to the prevention and response to emergencies, including those not covered under an emergency decree. The municipalities will create their own fund for these same purposes and the resources of this fund will be governed by the principles of multi-year budgeting and therefore what is not executed at the end of each fiscal year will not constitute a surplus.
VI. COMPETENCES AND RESPONSIBILITIES OF THE CNE: The National Commission for Risk Prevention and Emergency Response (Comisión Nacional de Prevención de Riesgos y Atención de Emergencias, CNE) is the governing public institution regarding the coordination of preventive efforts for situations of imminent risk, mitigation, and response to emergency situations. It is a body of maximum deconcentration attached to the Presidency of the Republic, with instrumental legal personality for the management and administration of its budget and for the investment of its resources, with its own assets and budget. Its domicile is in the capital of the Republic, where its main headquarters is located. The actions of the CNE must be guided in accordance with the principles established by Law No. 8488 in Article 3, among them state of necessity and urgency understood as the situation of danger to a legal right that can only be saved by violating another legal right, with the least possible harm to the second and subject to subsequently rendering the accounts demanded by the laws of economic, legal, and fiscal control; protection of life, considering that those who are in the national territory must be protected in their life, their physical integrity, their property, and the environment, against disasters or dangerous events that may occur; and finally prevention, as the anticipated action to seek to reduce vulnerability, as well as the measures taken to avoid or mitigate the impacts of dangerous events or disasters; by their very condition, these actions or measures are of public interest and mandatory compliance.
Ordinary and extraordinary actions have as a fundamental principle of their actions the protection of life, not only of Costa Ricans but of every inhabitant or resident in the country. Indeed, article 3 of the Law establishes that protection of life as a fundamental principle. However, the enunciation of the principle does not limit protection to the life and physical integrity of the person present in the national territory. On the contrary, the protection of life includes the protection of the environment and the property of resident persons, regardless of their nationality. Protection of life, physical integrity, property, and security that are at the basis of other principles established for the response to emergencies and risk situations, as occurs with the principle of solidarity. Within its ordinary competences, according to Law No. 8488, is the obligation to: Article 14- Ordinary prevention competences of the Commission.
The Commission shall be the governing entity regarding risk prevention and preparations to respond to emergency situations. It must fulfill the following competences: (…) c) Issue binding resolutions on situations of risk, disaster, and imminent danger, based on technical and scientific criteria, aimed at guiding regulation and control actions for their effective prevention and management, that regulate or provide for their effective compliance by State institutions, the private sector, and the general population. Officials of the organs and entities competent to execute or implement such binding resolutions may, in no case, disregard them. Natural or legal persons, public or private, who build on or improperly use areas restricted through these binding resolutions, shall be subject to the obligation to demolish or eliminate the work, pursuant to article 36 of this Law. (…) g) Promote and encourage the monitoring and management of risk situations, through the study or implementation of observation, monitoring, and alert measures, that allow for foreseeing, reducing, and avoiding the impact and damages of possible disaster events.
Furthermore, if necessary, coordinate the monitoring and management of such situations. (…) Likewise, it has its extraordinary competences defined in article 15, which textually states: “Once the state of emergency established in article 29 of this Law has been declared, the Commission shall be responsible for planning, coordinating, directing, and controlling the actions aimed at resolving urgent needs, executing protection, rescue, and rehabilitation programs and activities. To this end, it must execute, at a minimum, the following actions: a) The coordination, direction, and control of the response to emergencies declared as such by the Executive Branch shall be carried out according to the phases defined in article 30 of this Law; for this purpose, the Commission, through the Executive Directorate, must prepare the General Emergency Plan (Plan General de la Emergencia), according to the terms referred to in Chapter VI of this Law. b) It must coordinate the damage assessment, for which the institutions of the Central Administration, the Decentralized Public Administration of the State, the Local Governments, and state companies will be responsible for assessing the damages and coordinating their execution with the Commission. c) Plan, coordinate, organize, and supervise the execution of rescue actions by public and private, national and international organizations. d) Coordinate the scientific and technical investigations necessary for the Plan, as well as the physical and economic recovery programs, and provide the necessary follow-up. e) Appoint as executing units, the public institutions that have within their scope of competence, the execution of the works defined in the General Emergency Plan and supervise their execution. f) Hire the specialized personnel it requires for determined periods and in accordance with the emergency declaration.
Except as provided in the preceding subsections, the Commission shall attend, without an emergency declaration by the Executive Branch, local and minor emergencies that, due to the high frequency with which they occur and the serious impact they cause in communities, demand the provision of a first-impact humanitarian service, consisting of the delivery of blankets, food, sleeping mats, and if necessary, the acquisition of materials to rehabilitate basic services and enable shelters, as well as the contracting of a maximum of one hundred machine hours for cleaning the most affected area of the zone” (the underlining is not from the original) VII. UNDECLARED OR FIRST-IMPACT EMERGENCIES: Law No. 8488, as part of the extraordinary competences, empowers the CNE to attend local and minor emergencies through the figure of “First Impacts” (Primeros Impactos), given that article 15 in its final paragraph indicates: “(…) Except as provided in the preceding subsections, the Commission shall attend, without an emergency declaration by the Executive Branch, local and minor emergencies that, due to the high frequency with which they occur and the serious impact they cause in communities, demand the provision of a first-impact humanitarian service, consisting of the delivery of blankets, food, sleeping mats, and if necessary, the acquisition of materials to rehabilitate basic services and enable shelters, as well as the contracting of a maximum of one hundred machine hours for cleaning the most affected area of the zone.
(The underlining is not from the original) However, the final paragraph of article 15 refers to a first-impact humanitarian service. The Law uses the term “first impact” to refer to the first phase of response to a declared emergency. Indeed, article 30 of the Law, which divides said response into the response phase, rehabilitation phase, and finally reconstruction phase, establishes that the response phase is immediate to the occurrence of the event. A phase that includes urgent first-impact measures aimed at safeguarding life, vital public service infrastructure, property, and the environment. But also mitigation works directed at protecting the population, infrastructure, and the environment. Article 4 defines response as the actions immediate to the occurrence of an emergency; they seek to control a situation, to safeguard works and lives, avoid greater damages, and stabilize the area of the region directly impacted by the emergency.
In this sense, without an emergency declaration, the Commission may attend local and minor emergencies, for which the contracting of a maximum of 100 machine hours is permitted for cleaning the affected area. Likewise, article 30 subsection a) of the same law establishes that in the response phase, which is an operational phase immediate to the occurrence of the event, the urgent first-impact measures aimed at safeguarding life, vital public service infrastructure, the production of goods and services are included through actions of alert, alarm, evacuation, and relocation, among others. VIII. EMERGENCIES DECLARED UNDER EXECUTIVE DECREE: Regarding the Exceptional Regime, this arises from a Declaration of a State of Emergency, which is carried out by the Executive Branch, as provided in article 29 of Law No. 8488. The Emergency Declaration permits exceptional treatment in the face of budgetary rigidity, by virtue of article 180 of the Political Constitution, so that the Government can swiftly obtain sufficient economic, material, or other resources to attend to the persons, property, and services affected or in danger (art. 31 Law No. 8488); according to the need in the different stages of the emergency as established in article 30 of the cited law.
To use the exceptional regime, there must UNEQUIVOCALLY exist a causal link between the event that causes the state of necessity and urgency and the damages actually caused. In this sense, the Constitutional Chamber, in Vote No. 3410-92 reiterated in Vote No. 1369-2001 at fourteen hours thirty minutes of February fourteenth, two thousand one, indicated: “the existence of a causal link is required for the intervention of the CNE between the event that occurred and the investment being made, duly supported by an emergency decree issued by the Executive Branch and a General Emergency Plan, understood as a definition of functions and responsibilities and general procedures for reaction and institutional alerts (…)”. When the Executive Branch has issued the decree declaring the state of emergency, immediately the Commission, through its Executive Directorate and in consultation with its Presidency, shall convene the Institutions that have competence and any other it considers necessary because they are within the area of impact of the emergency, for the preparation of the General Emergency Plan, an instrument that will allow rational, efficient, and systematic planning and channeling of the actions that must be carried out, the necessary supervision, and the allocation of the resources required.
For this purpose, within a maximum period of two months, the convened institutions must deliver an official report of the damages suffered in their area of competence, with an estimate of the costs and needs that must be covered. A cause-and-effect relationship must unequivocally exist in this damage report. With the reports submitted and the other documentation the Commission accredits, the General Emergency Plan will be prepared. The General Emergency Plan is the planning instrument that establishes the effect of causality between the event that occurred, the actions, and the investment made to address the emergency. It consists of a description of the causal event, the damage assessment, and the estimate of the losses generated, broken down by canton and sector; likewise, it includes the delimitation of the actions that each institution must carry out, including those of the Commission itself; as well as a detail of the amount of investment required in each of the phases of emergency response, from the response phase to the reconstruction of the affected zone.
IX. REGARDING THE SPECIFIC CASE: In reference to the specific case, it must be clarified that the interventions carried out by the CNE, through “First Impact” (Primer Impacto) contracting, whether for declared or undeclared emergencies, respond to the on-site need to protect the population, infrastructure, and vital lines in the first instance, the purpose of these being to safeguard human life, agricultural activities, and protection of properties near the riverbank. These interventions carried out by the Commission, termed First Impacts (Primeros Impactos), consist of the contracting of machinery for a maximum of three hundred hours, for emergency intervention during the Response Phase of an extraordinary event or for the response to local emergencies, these works being urgent and necessary to eliminate landslides and restore passage, channel rivers, restore vital public services; that protect life and provide security to inhabitants and their property.
These contracts provide a palliative measure for an impact resulting from a local event. Upon consulting the Strategic Development Unit of the CNE, which is the unit responsible for advising and planning the development of the National Risk Management System and evaluating the results comprehensively and therefore for the preparation of Emergency Plans, [it was found] that the canton of Nandayure is included in the emergency declarations for Tropical Storm Nate (Executive Decree No. 40677-MP) and Hurricane Eta (Executive Decree No. 42705-MP); however, for neither of the two events is there an official damage and loss report for the General Emergency Plan regarding the river in question, on the part of the Municipality of Nandayure nor the Directorate of Fluvial Works (Dirección de Obras Fluviales) of the Ministry of Public Works and Transport within the time established by law. This being an indispensable requirement for the CNE to act within its extraordinary competences.
What it was able to verify is that this Commission, from the year 2018 to date, processed the following requests from the Municipality of Nandayure: 1) 2019PI-000008-0006500001 “Rental of Machinery to attend the emergency in the community of San Pablo, Nandayure River, Nandayure 5th Occasion,” where it was adjudicated on January 23, 2019, to the Company Hermanos Herrera Barrantes Constructora, Sociedad Anónima, 150 effective hours of an excavator and 150 effective hours of a Tractor, the purpose of which was cleaning, re-digging the Nandayure River, piling material on the sides, as a dike type with the aim of preventing or mitigating overflows and greater impact in the sector of the community of San Pablo and 2) 2020PI-000374-0006500001 “Rental of Machinery to attend impacts in San Pablo, Nandayure River overflow,” where on December 11, 2020, it was adjudicated to Constructora Meco, Sociedad Anónima, 150 effective hours of a tractor and 150 effective hours of an excavator, with the purpose of attending the undeclared emergency, the aim of which was cleaning and re-digging the Nandayure riverbed in the community of San Pablo, Nandayure, with the purpose of preventing new river overflows that cause impacts to the communities and infrastructure.
It is important to indicate that the processes noted in the preceding paragraph have been in response to requests made by the Municipality of Nandayure, which have been attended to in a timely and proper manner, under the figure of undeclared emergency contracting. As can be noted from the foregoing, the CNE has carried out proactive work within our legal framework, in terms of providing prompt and fulfilled response to the requests made by the Municipality of Nandayure. Mention must be made that the channel maintenance work as a preventive measure must be carried out either by the local government or by the Directorate of Fluvial Works of the Ministry of Public Works and Transport, since the construction of a rock retaining wall (requested by the petitioner), as an ordinary action, cannot and should not be provided by the CNE; since if that were the case, it would result in substituting the response through the ordinary channel with an exceptional regime, which is clearly improper in accordance with the rule cited throughout this report.”.
Due to their shape and size they are used in the construction of gravity structures, in the facing of walls in reinforced soils, in hydraulic control structures, bank erosion control, rehabilitation of eroded banks, lining of dikes, embankments, channel slopes, bank heightening, crest heightening in hydraulic control structures, and protection of pipelines (…) This solution is viable to strengthen the sections of the channel (cauce) that present high erosion of the natural slopes bordering yards and dwellings, which have been affected by the flooding of the Río Nandayure; its cost is significant and an extraordinary budget is required, but the advantage presented by this structure is that its cost as an input, an element, is offset by the on-site material, since we would not have to purchase large quantities of oversized granular material that would exponentially increase the project costs. • Current Condition of the Channel (Cauce) in the Community of San Pablo (…) The winter condition of the year 2022 can be observed, where the parallel dikes built have eroded, affecting the adjoining properties. • Technical Proposal for accompaniment CNE- MOPT- MINAE- MUNICIPALIDAD We require inter-institutional accompaniment with the following competencies in order to impact the critical points through short- and medium-term programming according to the availability of resources of each institution.
Requirement to request from MOPT: • Hydrological Studies • Hydraulic Studies • Availability of Machinery and Equipment • Professional Technical Support. Requirement to request from CNE: • Financial resources to purchase prismatic hydroblock structural textile geocontainer (geocontendor) (sic). • Continue with the vulnerability study and risk assessment on the banks of the Río Nandayure, in the remaining sector between Puente Carmona towards the community of San Pablo. • Professional Technical Support • Availability of Machinery and Equipment (machine hours). • Follow up on the commitments generated by the Nate Decree (Decreto Nate), which is (sic) active and under which the necessary resources could be managed to contribute to the proposed solution. Requirement to request from MINAE: • Carry out studies to perform works in a public-domain channel (cauce). • Professional Technical Support Requirement to request from the Municipalidad Nandayure: • Financial resources to purchase prismatic hydroblock structural textile geocontainer (geocontendor). • Availability of Machinery and Equipment • Professional Technical Support • Coordination of liaison (sic) between the indicated institutions.
Regarding execution timelines. As the Municipalidad, we have begun the preliminary project study of the points to intervene in order to estimate the costs of each sub-project, which will take us approximately three months given that the current conditions of the channel (cauce) present difficulties for carrying out in-situ inspections, which benefits later viewing the damages caused and thus quantifying and developing an intervention work plan where each of the involved institutions expresses its commitment or counterpart contribution to improve the hydraulic control of the channel (cauce). We reiterate that as the Municipalidad we do not have all the resources, therefore we insist that a working commission must be created to plan and execute the works within an adequate timeframe to avoid greater tragedies for the citizens of Carmona and San Pablo and Puerto San Pablo.”.
Drafted by Judge Rueda Leal; and,
Considering:
The appellant states that he is a resident of San Pablo de Nandayure, an area affected by the flooding caused by the Río Nandayure. He alleges that he has requested help from the respondent authorities to carry out the necessary works to solve the flooding problem; however, the situation remains the same. He adds that, in the current year, the aforementioned river destroyed trees, fences, posts, and crops.
Of importance for the decision in this matter, the following facts are deemed duly demonstrated, either because they have been accredited or because the respondent authority omitted to refer to them, as provided in the initial order:
C. The zone evaluated in the town of San Pablo Viejo de Nandayure presents an undulating flat topography; it is located at the point where the channel (cauce) changes from its boxed-in condition in the river canyon and opens toward the alluvial plain; it has varied cover with scattered trees and some housing infrastructure built within zones that have been affected by flooding in the past; furthermore, parallel to the channel (cauce) runs a local road that is impacted when overflow events occur. D. In the evaluated sector running parallel to the channel (cauce) of the Río Nandayure, strong lateral erosion is observed on the banks, because the flow impacts the zones with great force. Throughout the lower section of the river, high sedimentation and clogging of materials that have completely filled it are observed, generating a significant loss of hydraulic capacity and favoring overflow events when heavy rains occur.
E. Through the overflight carried out with an unmanned aerial vehicle (drone), evidence of overflow, flooding, and debris deposition events is observed on the banks in the plain, where several dwellings are located. Evidence of the drag from the current and the debris contained in the flow is observed when it crosses the municipal road leading to San Pablo Viejo, and which continues towards adjacent lands. F. In the Quebrada Pozas, which crosses the road leading to San Pablo Viejo, problems are observed in the crossing bridge, which is obstructed by debris drag and causes the flow to overflow. This problem interrupts passage, leaves the town incommunicado, and without an option to leave because there is only this route to enter the community (…) Recommendations. A. The Municipalidad de Nandayure must coordinate with Obras Fluviales of the MOPT and the MINAE the possibility of carrying out adequate channelization on the channel (cauce) of the Río Nandayure at the evaluated sites presenting problems, to remove the amount of accumulated material that reduces the hydraulic capacity of the sections, and also to carry out protection works to reduce lateral erosion on the banks and the protection dikes.
B. The Municipalidad de Nandayure must carry out the construction of adequate protection and containment works on the banks of the Río Nandayure, with materials that are not eroded by extraordinary floods and that protect the sectors. C. The Municipalidad de Nandayure must restrict land use (uso de suelo) for residential or commercial purposes in the protection zones of the Río Nandayure, according to Article 33 of the Ley Forestal 7575, as well as in areas identified as having potential flood impact, according to the natural hazard maps of the CNE. D. The protection works implemented on the affected banks must be supervised by a professional affiliated with the Colegio Federado de Ingenieros y Arquitectos de Costa Rica, based on the standards established by the Código Sísmico, Código de Cimentaciones, and Reglamento de Construcciones, Código Municipal, and other current legislation. E. The Municipalidad de Nandayure must periodically carry out, according to the conditions of material accumulation in the channel (cauce) of the Río Nandayure and all those that drain the canton, adequate channelization that helps recover the hydraulic capacity of the channel (cauce) and reduces the flood threat in each sector.
F. The Municipalidad de Nandayure must remain vigilant over high-risk, flood, and landslide-susceptible zones, and not grant construction permits or allow the development of informal housing settlements in them. G. Any anomaly regarding construction techniques or omission of the recommendations described herein IS UNDER THE TOTAL RESPONSIBILITY of the institutions granting the permits, the engineer or person responsible for the work, and the respective Municipalidad for failing to request the corresponding reports, inspections, and corrections.". (Documentary evidence).
In the case at hand (sub lite), the appellant states that he is a resident of San Pablo de Nandayure, an area affected by the flooding caused by the Río Nandayure. He alleges that he has requested help from the respondent authorities to carry out the necessary works to solve the flooding problem; however, the situation remains the same. He adds that, in the current year, the aforementioned river destroyed trees, fences, posts, and crops.
From the study of the case file, it has been demonstrated that the acting municipalidad reports that the Río Nandayure presents two flood areas, which affect the communities of Carmona and San Pablo. In March 2020, the Dirección de Obras Fluviales of the MOPT carried out cleaning and channelization works on the Río Nandayure, as part of the measures to mitigate the effects of the rains. The president of the CNE reports: "this Commission, from 2018 to date, processed the following requests from the Municipalidad de Nandayure: 1) 2019PI-000008-0006500001 'Alquiler de Maquinaria para atender la emergencia en la comunidad de San Pablo, río Nandayure, Nandayure 5ta Ocasión', which was awarded on January 23, 2019, to the company Hermanos Herrera Barrantes Constructora, Sociedad Anónima (Hermanos Herrera Barrantes Constructora, Sociedad Anónima), 150 effective hours of an excavator and 150 effective hours of a Tractor, the purpose of which was cleaning and re-excavation of the Río Nandayure, piling material on the sides, dike-type, in order to prevent or mitigate overflows and greater impact in the sector of the community of San Pablo, and 2) 2020PI-000374-0006500001 'Alquiler de Maquinaria para atender afectaciones en San Pablo, desbordamiento río Nandayure', where on December 11, 2020, Constructora Meco, Sociedad Anónima (Constructora Meco, Sociedad Anónima) was awarded 150 effective hours of a tractor and 150 effective hours of an excavator, for the purpose of attending to the undeclared emergency, the purpose of which was cleaning and re-excavating the channel (cauce) of the Río Nandayure in the community of San Pablo, Nandayure, in order to prevent new river overflows, which cause impacts to the communities and infrastructure.".
In the technical report no. CNE-UIAR-INF-1193-2021 of September 2022 from the Unidad de Investigación y Análisis de Riesgo of the CNE, it was recorded: "Risk assessment on the banks of the Río Nandayure in the locality of San Pablo Viejo, due to lateral erosion and flooding problems in the sector (…) Conclusions: A. According to the Mapa de Amenazas Naturales Potenciales of the CNE, the evaluated zones are within the area of direct impact from potential flooding when overflows of the Río Nandayure's flow and its tributaries occur in the flatland area, generally occurring when intense rains occur in the upper zone of the micro-watersheds due to the influence of extreme hydro-meteorological phenomena. B. The sector evaluated in the locality of San Pablo Viejo is located within the micro-watershed of the Río Nandayure, on the left bank. The evaluated zone is located within what corresponds to the river channel (cauce) area and alluvial plain, on the edges of the alluvial terraces built by the accretion of sediments deposited after extraordinary flood events.
C. The zone evaluated in the town of San Pablo Viejo de Nandayure presents an undulating flat topography; it is located at the point where the channel (cauce) changes from its boxed-in condition in the river canyon and opens toward the alluvial plain; it has varied cover with scattered trees and some housing infrastructure built within zones that have been affected by flooding in the past; furthermore, parallel to the channel (cauce) runs a local road that is impacted when overflow events occur. D. In the evaluated sector running parallel to the channel (cauce) of the Río Nandayure, strong lateral erosion is observed on the banks, because the flow impacts the zones with great force. Throughout the lower section of the river, high sedimentation and clogging of materials that have completely filled it are observed, generating a significant loss of hydraulic capacity and favoring overflow events when heavy rains occur.
E. Through the overflight carried out with an unmanned aerial vehicle (drone), evidence of overflow, flooding, and debris deposition events is observed on the banks in the plain, where several dwellings are located. Evidence of the drag from the current and the debris contained in the flow is observed when it crosses the municipal road leading to San Pablo Viejo, and which continues towards adjacent lands. F. In the Quebrada Pozas, which crosses the road leading to San Pablo Viejo, problems are observed in the crossing bridge, which is obstructed by debris drag and causes the flow to overflow. This problem interrupts passage, leaves the town incommunicado, and without an option to leave because there is only this route to enter the community (…) Recommendations. A. The Municipalidad de Nandayure must coordinate with Obras Fluviales of the MOPT and the MINAE the possibility of carrying out adequate channelization on the channel (cauce) of the Río Nandayure at the evaluated sites presenting problems, to remove the amount of accumulated material that reduces the hydraulic capacity of the sections, and also to carry out protection works to reduce lateral erosion on the banks and the protection dikes.
B. The Municipalidad de Nandayure must carry out the construction of adequate protection and containment works on the banks of the Río Nandayure, with materials that are not eroded by extraordinary floods and that protect the sectors. C. The Municipalidad de Nandayure must restrict land use (uso de suelo) for residential or commercial purposes in the protection zones of the Río Nandayure, according to Article 33 of the Ley Forestal 7575, as well as in areas identified as having potential flood impact, according to the natural hazard maps of the CNE. D. The protection works implemented on the affected banks must be supervised by a professional affiliated with the Colegio Federado de Ingenieros y Arquitectos de Costa Rica, based on the standards established by the Código Sísmico, Código de Cimentaciones, and Reglamento de Construcciones, Código Municipal, and other current legislation. E. The Municipalidad de Nandayure must periodically carry out, according to the conditions of material accumulation in the channel (cauce) of the Río Nandayure and all those that drain the canton, adequate channelization that helps recover the hydraulic capacity of the channel (cauce) and reduces the flood threat in each sector.
F. The Municipalidad de Nandayure must remain vigilant over high-risk, flood, and landslide-susceptible zones, and not grant construction permits or allow the development of informal housing settlements in them. G. Any anomaly regarding construction techniques or omission of the recommendations described herein IS UNDER THE TOTAL RESPONSIBILITY of the institutions granting the permits, the engineer or person responsible for the work, and the respective Municipalidad for failing to request the corresponding reports, inspections, and corrections.". The mayor of the Municipalidad de Nandayure points out that dredging (dragado) techniques and other works have been carried out to counteract flooding during the winter season; however, such actions are insufficient, and a durable, comprehensive solution has not been achieved. On August 18, 2022, the Municipalidad de Nandayure and the CNE conducted a visit to each of the critical points in the community of San Pablo.
The acting municipalidad reports that it has begun the study of a preliminary project for the intervention of the river; however, it requires the participation of the other acting agencies to plan and execute the respective works, in order to solve the alleged problem.
On this matter, it is of interest to highlight that, in judgment no. 2019018960 of 9:20 a.m. on October 4, 2019, this Court resolved an amparo appeal (recurso de amparo) filed by the appellant, concerning the problems with the Río Nandayure. In that resolution, it was stated:
"I.- Purpose of the appeal. The appellants allege that they have filed several petitions requesting the dredging (dragado) of the Río Nandayure, in the sector of San Pablo, and to date, they have not received a response nor have the corresponding actions been taken (…)
IV.On the merits. The Administration, in light of Article 41 of the Constitución Política, has the obligation to guarantee citizens the fulfillment of swift and complete justice, without denial, which implies, in the realm of administrative justice, its obligation to decide the claims raised by the administered parties with diligence and speed, in such a manner that its resolution is congruent with the alleged points, as well as to communicate what has been decided to the interested parties, all within a reasonable timeframe. In the case under study, the Chamber (Sala) confirms an infringement of the provisions of Article 41 of the Constitución Política, since the respondent party had not resolved the petitions filed by the appellants and other residents, since November 6, 2018, and reiterated on April 26 and June 13, both of 2019, which demonstrates a violation of the fundamental right to swift and complete justice. Moreover, it was upon notification of the present amparo appeal (recurso de amparo) that the respondent authority proceeded to resolve the petition requested by the petitioners. Consequently, regarding this point, the appeal is granted.
V.Furthermore, although to date, it is not established that dredging (dragado) of the Río Nandayure is required in the sector requested by the appellants, since to have certainty of this, technical studies must be carried out by the competent authorities; the truth is that, faced with doubt, and given that last year floods occurred that damaged the works already carried out, the 'principle of prudent avoidance or precautionary principle' must be applied, with respect to the possible impact that the overflow of the river channel (cauce) could cause to the health and integrity of the people inhabiting said community as well as to their homes, the alteration of ecosystems, erosion, the destruction of roads, crops, the impact on the health and well-being of wildlife and livestock, among others. Therefore, in application of said principle, and given the evidence that there could be a danger of serious or irreversible damage, the correct course of action is to act by minimizing as much as possible the risk situations that said situation may cause.
In addition, the appellants' claim is that a cleaning and deepening of the river in question be carried out, in the zone of San Pablo, as well as the removal of rocks and sediments, to increase the depth; therefore, translating said petition to the constitutional realm, the appropriate course is for the Chamber (Sala) to grant the appeal and order the Municipal Mayor in coordination with the competent entities of the Dirección de Obras Fluviales and of the Región, of the Ministerio de Obras Públicas y Transportes, that the technical studies indicated by said authorities be carried out, namely, a hydrological study and a two-dimensional hydraulic modeling to know with certainty the type of hydraulic work to be built and to identify whether the existing infrastructure is within the river's protection zone for the solution of the problem. The foregoing is based on the provisions of Article 15 of the 'Rio Declaration', adopted by the United Nations Conference on Environment and Development in June 1992, which reads:
'In order to protect the environment, the precautionary approach shall be widely applied by States according to their capabilities. Where there are threats of serious or irreversible damage, lack of full scientific certainty shall not be used as a reason for postponing cost-effective measures to prevent environmental degradation.' In accordance with the foregoing, it is necessary to insist that the observance of a principle can be rational or irrational, and the case of prudent avoidance is no exception. In fact, it is clear that the principle in question, as 'prudent avoidance,' is merely a recommendation, of temporary validity, for the application of certain preventive measures. Thus, by virtue of what has been stated, and in application of the precautionary principle, the appropriate course is to grant the appeal, solely regarding this point.
Therefore (Por tanto):
The appeal is granted. Giovanni Jiménez Gómez, in his capacity as Mayor of the Municipalidad de Nandayure, or whoever holds that office, is ordered that, within a period of EIGHT MONTHS, from the notification of this judgment, they must, in a coordinated manner with the authorities of the Dirección de Obras Fluviales and the Macro Región de Guanacaste, both of the Ministerio de Obras Públicas y Transportes, carry out and obtain the results of the hydrological study and the corresponding hydraulic modeling, to know with certainty the type of hydraulic work to be built and to identify whether the existing infrastructure is within the protection zone of the Río Nadanyure, in order to solve the overflow problem occurring in the San Pablo area. The foregoing, under the warning of incurring the crime provided for in Article 71 of the Ley de la Jurisdicción Constitucional, in case of non-compliance.
The Municipalidad de Nandayure is condemned to pay the costs, damages, and losses caused by the facts serving as the basis for this declaration, which shall be liquidated in the execution of the judgment of the contentious-administrative jurisdiction. Notify this resolution to the respondent party, as well as to Jenaro Ruiz Chacón and Alonso Mora Arroyo, in their respective order as Acting Director (Director a.i.) of the Dirección de Obras Fluviales and Director of the Macro Región de Guanacaste, both of the Ministerio de Obras Públicas y Transportes, or to whomever holds those offices, in person." Now, as can be seen, in the precedent transcribed above, the carrying out of certain studies that were pending at that time was ordered and that would serve to address the flooding problem in the river in question. However, approximately 3 years later, it is observed that the flooding situation still persists, and that the necessary works to achieve a comprehensive and definitive solution have not been executed.
In this regard, although the Municipalidad de Nandayure and the Dirección de Obras Fluviales of the MOPT have carried out various palliative works such as dredging (dragados) and other cleaning and channelization tasks, it is no less true that such actions have proven insufficient. In this respect, the acting municipalidad itself acknowledges that greater efforts are necessary to execute durable works that resolve the alleged problem. Likewise, in the technical report CNE-UIAR-INF-1193-2021 of September 2022 from the Unidad de Investigación y Análisis de Riesgo of the CNE, it was recorded that greater interventions and actions were necessary on the part of the acting municipalidad.
This being the case, despite the fact that for at least 3 years the authorities of the Municipalidad de Nandayure and the Dirección de Obras Fluviales of the MOPT have known about the problem in question and have carried out certain palliative works, they have not executed what is pertinent to achieve a comprehensive and definitive solution that guarantees the safety of the community of San Pablo de Nandayure.
Therefore, the appropriate course is to grant the appeal with respect to these agencies, in order to guarantee a comprehensive solution within a reasonable timeframe.
IV- Moreover, in relation to the Comisión Nacional de Prevención de Riesgos y Atención de Emergencias, any omission warranting being declared in this summary proceeding is ruled out a priori.
In this regard, it was reported under oath that the requests for help processed by the Municipalidad de Nandayure were duly attended to, and the procurements requested in dockets 2019PI-000008-0006500001 and 2020PI-000374-0006500001 were executed. Likewise, the respective inspection was carried out, and through report CNE-UIAR-INF-1193-2021 of September 2022, the recommendations concerning the works that the aforementioned municipalidad must execute were detailed.
Consequently, the appropriate course is to dismiss the appeal regarding this point, without prejudice. However, the president of the Comisión Nacional de Prevención del Riesgo y Atención de Emergencias must take note, so that, if required, within the framework of its competencies, it assists the Municipalidad de Nandayure and the Dirección de Obras Fluviales of the MOPT in solving the problem that is the subject of this appeal.
Although I agree with the majority of the Chamber (Sala) that the appeal should be granted, I differ on where to place the execution phase of the matter, due to the lack of adequate mechanisms provided for by the regulations governing this constitutional jurisdiction to follow up on a judgment that involves highly complex technical aspects, as is the case here in carrying out the necessary works to definitively solve the flooding problems suffered by the community of San Pablo from the Río Nandayure.
In contrast, the provisions of the Código Procesal Contencioso-Administrativo regarding enforcement (article 155 and following) have clear advantages, such as the possibility of requesting schedules, imposing fines, establishing liability, monitoring compliance stages, etc. Therefore, in accordance with the provisions of article 56 of the Ley de Jurisdicción Constitucional, I consider that the enforcement phase must be carried out before the Enforcement Division (Área de Ejecución) of the Tribunal Contencioso Administrativo y Civil de Hacienda, under the rules for judgment enforcement of said Code.
The parties are warned that, if they have submitted any paper document, as well as objects or evidence contained in any additional electronic, computer, magnetic, optical, telematic device or one produced by new technologies, these must be collected from the office within a maximum period of 30 business days counted from the notification of this judgment. Otherwise, all material not collected within this period will be destroyed, in accordance with the provisions of the "Reglamento sobre Expediente Electrónico ante el Poder Judicial", approved by the Corte Plena in session N°27-11 of August 22, 2011, article XXVI and published in Boletín Judicial number 19 of January 26, 2012, as well as the agreement approved by the Consejo Superior del Poder Judicial, in session N°43-12 held on May 3, 2012, article LXXXI.
Por tanto:
The appeal is partially granted, only with respect to the Municipalidad de Nandayure and the Ministerio de Obras Públicas y Transportes. Jenaro Ruiz Chacón and Giovanni Jiménez Gómez, respectively, acting director of the Dirección de Obras Fluviales of the Ministerio de Obras Públicas y Transportes and mayor of Nandayure, or whoever respectively holds those positions, are ordered to coordinate the corresponding actions, issue the pertinent orders, and carry out all actions within the scope of their respective competencies so that, within a maximum period of TWELVE MONTHS, counted from the notification of this judgment, all pertinent procedures and works are performed to comprehensively and definitively solve the flooding problem of the Río Nandayure, which affects the community of San Pablo de Nandayure. Notice is given that, in accordance with article 71 of the Ley de la Jurisdicción Constitucional, imprisonment from three months to two years, or a fine of twenty to sixty days, shall be imposed on anyone who receives an order that they must comply with or enforce, issued in an amparo appeal, and does not comply with it or have it complied with, provided the crime is not more severely punished.
The State and the Municipalidad de Nandayure are ordered to pay the costs, damages, and losses caused by the facts that served as the basis for this declaration, which shall be liquidated in the enforcement of judgment in the administrative litigation jurisdiction. In all other respects, the appeal is denied. The Comisión Nacional de Prevención de Riesgos y Atención de Emergencias shall take note of the recital at the end of considerando IV of this judgment. Judge Garro Vargas dissents with respect to the enforcement of this judgment and, in accordance with article 56 of the Ley de la Jurisdicción Constitucional, orders that it must be carried out before the Enforcement Division (Área de Ejecución) of the Tribunal Contencioso Administrativo y Civil de Hacienda, under the enforcement rules established in articles 155 and following of the Código Procesal Contencioso Administrativo. She further orders that a copy of the judgment be sent to initiate the enforcement proceedings for this ruling. Let it be notified.
Fernando Castillo V.
Fernando Cruz C.
Paul Rueda L.
Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Jose Roberto Garita N.
Clasificación elaborada por SALA CONSTITUCIONALdel Poder Judicial. Prohibida su reproducción y/o distribución en forma onerosa.
Sentencia con nota separada Indicadores de Relevancia Sentencia relevante Sentencias Relacionadas Contenido de Interés:
Temas Estrategicos: Der Económicos sociales culturales y ambientales Tipo de contenido: Voto de mayoría Rama del Derecho: 4. ASUNTOS DE GARANTÍA Tema: MUNICIPALIDAD Subtemas:
INFRAESTRUCTURA Y CONDICIONES.
027316-22. MUNICIPALIDAD. ACUSA INUNDACIONES PROVOCADAS POR EL RIO NANDAYURE. SE DECLARA PARCIALMENTE CON LUGAR EL RECURSO, ÚNICAMENTE EN CUANTO A LA MUNICIPALIDAD DE NANDAYURE Y AL MINISTERIO DE OBRAS PÚBLICAS Y TRANSPORTES. SE ORDENA AL DIRECTOR A.I. DE LA DIRECCIÓN DE OBRAS FLUVIALES DEL MINISTERIO DE OBRAS PÚBLICAS Y TRANSPORTES Y ALCALDE DE NANDAYURE, QUE COORDINEN LO CORRESPONDIENTE, GIREN LAS ÓRDENES PERTINENTES Y LLEVEN A CABO TODAS LAS ACTUACIONES QUE ESTÉN DENTRO DEL ÁMBITO DE SUS RESPECTIVAS COMPETENCIAS PARA QUE, DENTRO DEL PLAZO MÁXIMO DE DOCE MESES, SE REALICEN TODAS LAS GESTIONES Y OBRAS PERTINENTES PARA SOLUCIONAR DE MANERA INTEGRAL Y DEFINITIVA EL PROBLEMA DE INUNDACIONES DEL RÍO NANDAYURE, QUE AFECTA A LA COMUNIDAD DE SAN PABLO DE NANDAYURE. VCG05/2023 “(…) III.- SOBRE EL CASO CONCRETO. En el sub lite, el recurrente manifiesta que es vecino de San Pablo de Nandayure, zona afectada por las inundaciones que provoca el Río Nandayure. Alega que ha solicitado ayuda a las autoridades recurridas para que se realicen las obras necesarias para solucionar el problema de las inundaciones; empero, aún la situación es la misma. Añade que, en el año en curso, el río aludido destruyó árboles, cercas, postes y cosechas.
Del estudio de los autos se tiene demostrado, que la municipalidad accionada informa que el Río Nandayure presenta dos áreas de inundación, que afectan a las comunidades de Carmona y San Pablo. En marzo de 2020, la Dirección de Obras Fluviales del MOPT realizó trabajos de limpieza y canalización en el Río Nandayure, como parte de las medidas para mitigar los efectos de las lluvias. El presidente de la CNE informa: “esta Comisión desde el año 2018 a la fecha tramitó las siguientes solicitudes por parte de la Municipalidad de Nandayure: 1) 2019PI-000008-0006500001 “Alquiler de Maquinaria para atender la emergencia en la comunidad de San Pablo, río Nandayure, Nandayure 5ta Ocasión”, donde se adjudicó en fecha 23 de enero de 2019 a la Empresa Hermanos Herrera Barrantes Constructora, Sociedad Anónima, 150 horas efectivas de una excavadora y 150 horas efectivas de un Tractor, cuyo fin era la limpieza, recava del río Nandayure, apilación de material a los costados, tipo dique con el fin de evitar o mitigar desbordamientos y mayor afectación en el sector de la comunidad de San Pablo y 2) 2020PI-000374-0006500001 “Alquiler de Maquinaria para atender afectaciones en San Pablo, desbordamiento río Nandayure”, donde en fecha 11 de diciembre de 2020, se adjudicó a la Constructora Meco, Sociedad Anónima, 150 horas efectivas de un tractor y 150 horas efectivas de una excavadora, con el fin de atender la emergencia no declarada cuya finalidad era la limpieza y recavar el cauce del río Nandayure en la comunidad de San Pablo, Nandayure, con el fin de evitar nuevos desbordamientos del río, que ocasionen afectaciones a la comunidades e infraestructura.”.
En el informe técnico nro. CNE-UIAR-INF-1193-2021 de septiembre de 2022 de la Unidad de Investigación y Análisis de Riesgo de la CNE, se consignó: “Valoración de riesgo en las márgenes del río Nandayure en la localidad de San Pablo Viejo, por problemas erosión lateral y anegamiento del sector (…) Conclusiones: A. Según el Mapa de Amenazas Naturales Potenciales de la CNE, las zonas evaluadas se encuentran dentro del área con afectación directa por inundaciones potenciales cuando ocurren desbordamientos del caudal del río Nandayure y sus afluentes en la zona de planicie, generalmente ocurridos cuando se dan lluvias intensas en la zona alta de las microcuencas por influencia de fenómenos hidrometereológicos extremos. B. El sector evaluado en la localidad de San Pablo Viejo se localiza dentro de la microcuenca del río Nandayure, sobre la margen izquierda. La zona evaluada se ubica dentro de lo que corresponde con el área del cauce del río y planicie aluvial, en los bordes de las terrazas aluvionales construidas por la acreción de sedimentos depositados luego de eventos de crecidas extraordinarias.
C. La zona evaluada en el poblado de San Pablo Viejo de Nandayure presenta una topografía plana ondulada, se ubica en el punto donde el cauce cambia su condición encajonada en el cañón del río y se abre hacia la llanura aluvial, posee cobertura variada con árboles dispersos y algunas infraestructuras habitacionales construidas dentro de las zonas que se ha visto afectadas por anegamientos en el pasado, además, paralelo al cauce corre un camino vecinal que se ve impactado cuando ocurren los eventos de desbordamiento. D. En el sector evaluado que va paralelo al cauce del río Nandayure se observa una fuerte erosión lateral sobre las márgenes, debido a que el caudal impacta con gran fuerza las zonas. Se observa en toda la sección baja del río una alta sedimentación y colmatación de materiales que lo han rellenado por completo, generando una pérdida importante de la capacidad hidráulica y favoreciendo los eventos de desbordamiento cuando se dan lluvias fuertes.
E. Mediante el sobrevuelo realizado con un equipo aéreo no tripulado (drone), se observan evidencias de eventos de desbordamientos, anegamientos y depósito de escombros sobre las márgenes en la planicie, donde se ubican varias viviendas. Se observan evidencias del arrastre de la corriente y los escombros que contenía el flujo cuando atraviesa el camino municipal que lleva a San Pablo Viejo, y que continua hacia terrenos aledaños. F. En la quebrada Pozas, la cual atraviesa el camino que lleva a San Pablo Viejo, se observan problemas en el puente de paso, el cual se obstruye por arrastre de escombros y provoca el desbordamiento del caudal. Esta problemática interrumpe el paso, deja incomunicado al poblado y sin opción de salir debido a que solo existe esta vía para ingresar a la comunidad (…) Recomendaciones. A. La Municipalidad de Nandayure deberá coordinar con Obras Fluviales del MOPT y el MINAE la posibilidad de realizar una adecuada canalización sobre el cauce del río Nandayure en los sitios evaluados que presentan problemas, para remover la cantidad de material acumulado que disminuye la capacidad hidráulica de las secciones, además, realizar obras de protección para disminuir la erosión lateral sobre las márgenes y los diques de protección.
B. La Municipalidad de Nandayure deberá realizar la construcción de adecuadas obras de protección y contención en las márgenes del río Nandayure, con materiales que no sean erosionados por las crecidas extraordinarias y protejan los sectores. C. Restringir por parte de la Municipalidad de Nandayure el uso de suelo con fines habitacionales o de comercio en las zonas de protección del río Nandayure, según el artículo 33 de la ley forestal 7575, así como en las áreas identificadas con potencial afectación por inundaciones; según los mapas de amenazas naturales de la CNE. D. Las obras de protección que se implementen sobre las márgenes afectadas deben ser supervisadas por un profesional agremiado al Colegio Federado de Ingenieros y Arquitectos de Costa Rica, con base en las normas establecidas por el Código Sísmico, Código de Cimentaciones y Reglamento de Construcciones, Código Municipal y otra legislación vigente.
E. La Municipalidad de Nandayure deberá realizar periódicamente, según las condiciones de acumulación de materiales en el cauce del río Nandayure y todos aquellos que drenan el cantón, una adecuada canalización que ayude a recuperar la capacidad hidráulica del cauce y disminuya la amenaza de inundación en cada sector. F. La Municipalidad de Nandayure deberá permanecer vigilante de las zonas de alto riesgo, inundación y susceptibles al deslizamiento, no otorgar permisos constructivos o desarrollo de asentamientos informales de viviendas en ellos. G. Cualquier anomalía en cuanto a técnicas de construcción u omisión a las recomendaciones aquí descritas, QUEDA BAJO TOTAL RESPONSABILIDAD de las instituciones que otorgan los permisos, del ingeniero o responsable de la obra y de la Municipalidad respectiva de no solicitar los informes, inspecciones y correcciones correspondientes.”. El alcalde de la Municipalidad de Nandayure señala que se han realizado técnicas de dragado y otros trabajos para contrarrestar las inundaciones en época de invierno; empero, tales acciones resultan insuficientes y no se ha podido alcanzar una solución integral duradera.
El 18 de agosto de 2022, la Municipalidad de Nandayure y la CNE efectuaron una visita a cada uno de los puntos críticos en la comunidad de San Pablo. La municipalidad accionada informa que ha iniciado con el estudio de un anteproyecto para la intervención del río; empero, requiere la participación de las demás dependencias accionadas para planear y ejecutar las obras respectivas, a fin de solucionar el problema acusado.
Sobre el particular, interesa resaltar que, en la sentencia nro. 2019018960 de las 9:20 horas de 4 de octubre de 2019, este Tribunal resolvió un recurso de amparo interpuesto por el recurrente, atinente a la problemática del Río Nandayure. En esa resolución, se indicó:
“I.- Objeto del recurso. Los recurrentes alegan, que han presentado varias gestiones solicitando el dragado del río Nandayure, en el sector de San Pablo, y a la fecha, no han recibido respuesta ni se han realizado los actos correspondientes (…)
IV.Sobre el fondo. La Administración, a la luz del artículo 41, de la Constitución Política, tiene la obligación de garantizarle a la ciudadanía el cumplimiento de la justicia pronta y cumplida, sin denegación, lo que implica, en el ámbito de la justicia administrativa, su obligación de decidir con diligencia y celeridad los reclamos planteados por los administrados, de tal manera que su resolución sea congruente con los extremos alegados, así como de comunicarles a los interesados lo dispuesto, todo ello dentro de un plazo razonable. En el caso bajo estudio, la Sala acredita una infracción a lo dispuesto en el artículo 41, de la Constitución Política, toda vez que la parte recurrida no había resuelto las gestiones interpuestas por los recurrentes y demás vecinos, desde el 6 de noviembre de 2018, y reiteradas, el 26 de abril y el 13 de junio, ambos del 2019, lo que evidencia una lesión al derecho fundamental a la justicia pronta y cumplida. Además, fue con la notificación del presente recurso de amparo, que la autoridad recurrida procedió a resolver la gestión a lo solicitado por los gestionantes. En consecuencia, en cuanto este extremo se declara con lugar el recurso.
V.Por otra parte, si bien a la fecha, no consta que se requiera hacer el dragado del río Nandayure en el sector solicitado por los recurrentes, pues para tener certeza de ello, se requiere realizar los estudios técnicos, por parte de la autoridades competentes; lo cierto es que, ante la duda, y dado que el año pasado se produjeron inundaciones que dañaron los trabajos ya realizados, se debe aplicar el "principio de evitación prudente o precautorio", con respecto a la posible afectación que podría causar el desbordamiento del cauce del río, a la salud e integridad de las personas que habitan dicha comunidad así como a sus viviendas, la alteración de ecosistemas, erosión, la destrucción de caminos, cultivos, la afectación de la salud y el bienestar de la vida silvestre y el ganado, entre otros. De manera, que en aplicación a dicho principio, y dada la evidencia de que se podría estar en presencia de un peligro de daño grave o irreversible, lo correcto es actuar minimizando en lo posible las situaciones de riesgo que pueda provocar dicha situación.
Además, la pretensión de los recurrentes es que se realice una limpieza y ahondamiento del río en cuestión, en la zona de San Pablo, así como la remoción de rocas y sedimentos, para aumentar la profundidad, por lo que traduciendo dicha petición al terreno de lo constitucional, lo procedente es que la Sala acoja el recurso y ordene al Alcalde Municipal en coordinación con los entes competentes de la Dirección de Obras Fluviales y de la Región, del Ministerio de Obras Públicas y Transportes, que se realicen los estudios técnicos, señalados por dichas autoridades, a saber, un estudio hidrológico y una modelación hidráulica en dos dimensiones para saber con certeza el tipo de obra hidráulica a construir e identificar, si la infraestructura existente, se encuentra dentro de la zona de protección del río para la solución del problema. Lo anterior se fundamenta en lo dispuesto en el artículo 15, de la "Declaración de Río", adoptada por la Conferencia de las Naciones Unidas sobre el Medio Ambiente y el Desarrollo, en junio de 1992, que reza:
"Con el fin de proteger el medio ambiente, los Estados deberán aplicar ampliamente el criterio de precaución conforme a sus capacidades. Cuando haya peligro de daño grave o irreversible, la falta de certeza científica absoluta no deberá utilizarse como razón para postergar la adopción de medidas eficaces en función de los costos para impedir la degradación del medio ambiente" .
Acorde con lo anterior, es necesario insistir en que la observancia de un principio puede ser racional o irracional, y el caso de la evitación prudente no es excepción. De hecho, está claro que el principio en cuestión, como "evitación prudente" es únicamente una recomendación, de vigencia transitoria, para que se apliquen determinadas medidas preventivas. Así, en virtud de lo expuesto, y en aplicación del principio precautorio, lo procedente es acoger el recurso, únicamente en cuanto a este extremo.
Por tanto:
Se declara con lugar el recurso. Se ordena a Giovanni Jiménez Gómez, en su condición de Alcalde de la Municipalidad de Nandayure, o a quien ocupe dicho cargo, que en el plazo de OCHO MESES, a partir de la notificación de esta sentencia, deberá, de manera coordinada con las autoridades de la Dirección de Obras Fluviales y de la Macro Región de Guanacaste, ambos del Ministerio de Obras Públicas y Transportes, deberán realizar y obtener los resultados del estudio hidrológico y de la modelación hidráulica, que corresponda, para saber con certeza el tipo de obra hidráulica a construir e identificar, si la infraestructura existente se encuentra dentro de la zona de protección del río Nadanyure, con el fin de solucionar el problema de desbordamiento que se presenta en la zona de San Pablo. Lo anterior, bajo la advertencia de incurrir en el delito previsto por el artículo 71, de la Ley de la Jurisdicción Constitucional, en caso de no hacerlo.
Se condena a la Municipalidad de Nandayure, al pago de las costas, daños y perjuicios causados con los hechos que sirven de base a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso administrativo. Notifíquese esta resolución a la parte recurrida, así como a Jenaro Ruiz Chacón y a Alonso Mora Arroyo, por su orden Director a.i. de la Dirección de Obras Fluviales y Director Macro Región de Guanacaste, ambos del Ministerio de Obras Públicas y Transportes, o a quienes ocupen dichos cargos, en forma personal”.
Ahora bien, como se aprecia, en el precedente transcrito supra se ordenó la realización de determinados estudios que en ese momento estaban pendientes y que servirían para atender el problema de las inundaciones en el río de marras. No obstante, aproximadamente 3 años después, se aprecia que aún persiste la situación de las inundaciones, y que no se han ejecutado las obras necesarias para alcanzar una solución integral y definitiva.
En tal sentido, si bien la Municipalidad de Nandayure y la Dirección de Obras Fluviales del MOPT han realizado distintas obras paliativas como dragados y otros trabajos de limpieza y canalización, no menos cierto es que tales acciones han resultado insuficientes. Al respecto, la propia municipalidad accionada reconoce que es necesario ejecutar mayores esfuerzos para ejecutar obras duraderas que solventen el problema acusado. Asimismo, en el informe técnico CNE-UIAR-INF-1193-2021 de septiembre de 2022 de la Unidad de Investigación y Análisis de Riesgo de la CNE se consignó que mayores intervenciones y acciones eran necesarias por parte de la municipalidad accionada.
Así las cosas, pese a que desde al menos hace 3 años las autoridades de la Municipalidad de Nandayure y de la Dirección de Obras Fluviales del MOPT conocen el problema de marras y han realizado determinados trabajos paliativos, no han ejecutado lo pertinente para alcanzar una solución integral y definitiva garantice la seguridad de la comunidad de San Pablo de Nandayure.
De tal manera, lo procedente es declarar con lugar el recurso en cuanto a tales dependencias, a fin de garantizar una solución integral dentro de un plazo razonable.
IV- Por otra parte, en relación con la Comisión Nacional de Prevención de Riesgos y Atención de Emergencias, a priori se descarta alguna omisión que amerite ser declarada en esta vía sumaria.
En tal sentido, se informó bajo juramento que las solicitudes de ayuda tramitadas por la Municipalidad de Nandayure fueron debidamente atendidas, y se ejecutaron las contrataciones solicitadas en las gestiones 2019PI-000008-0006500001 y 2020PI-000374-0006500001. Asimismo, se efectuó la respectiva inspección y mediante el informe CNE-UIAR-INF-1193-2021 de septiembre de 2022 se detallaron las recomendaciones atinentes a las obras que la referida municipalidad debe ejecutar.
En consecuencia, lo procedente es declarar sin lugar el recurso en cuanto a este extremo. Sin embargo, deberá tomar nota el presidente de la Comisión Nacional de Prevención del Riesgo y Atención de Emergencias, a fin de que, en caso de ser requerido, dentro del marco de sus competencias se coadyuve con la Municipalidad de Nandayure y con la Dirección de Obras Fluviales del MOPT en la solución del problema objeto de este recurso. (…)” ... Ver más Sentencias Relacionadas Contenido de Interés:
Tipo de contenido: Nota separada Rama del Derecho: 6. LEY DE LA JURISDICCIÓN CONSTITUCIONAL ANOTADA CON JURISPRUDENCIA Tema: 056- Ejecución de sentencias Subtemas:
NO APLICA.
Si bien coincido con la mayoría de la Sala en que el recurso se debe declarar con lugar, difiero sobre dónde residenciar la fase de ejecución del asunto, debido a la inexistencia de mecanismos adecuados previstos por la normativa que rige esta jurisdicción constitucional para dar seguimiento a una sentencia que reviste aspectos técnicos de gran complejidad, como es en este caso llevar a cabo las obras necesarias para solucionar en definitiva la problemática de inundaciones que sufre la comunidad de San Pablo por parte del río Nandayure. En cambio, lo dispuesto por el Código Procesal Contencioso-Administrativo en materia de ejecución (artículo 155 y siguientes) tiene evidentes ventajas, como la posibilidad de pedir cronogramas, imponer multas, sentar responsabilidades, fiscalizar etapas de cumplimiento, etc. Por ello, de conformidad con lo dispuesto por el artículo 56 de la Ley de Jurisdicción Constitucional, estimo que la fase de ejecución debe realizarse ante el Área de Ejecución del Tribunal Contencioso Administrativo y Civil de Hacienda, bajo las reglas de ejecución de sentencia de dicho Código.
VCG05/2023 ... Ver más SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas veinte minutos del dieciocho de noviembre de dos mil veintidos .
Recurso de amparo que se tramita en el expediente n.° 22-019540-0007-CO, interpuesto por RAMADIEL DE JESÚS SAENZ UGALDE, cédula de identidad 0501230633, contra LA COMISIÓN NACIONAL DE PREVENCIÓN DE RIESGOS Y ATENCIÓN DE EMERGENCIAS, EL MINISTERIO DE OBRAS PÚBLICAS Y TRANSPORTES Y LA MUNICIPALIDAD DE NANDAYURE.
Resultando:
Redacta el Magistrado Rueda Leal; y,
Considerando:
El recurrente manifiesta que es vecino de San Pablo de Nandayure, zona afectada por las inundaciones que provoca el Río Nandayure. Alega que ha solicitado ayuda a las autoridades recurridas para que se realicen las obras necesarias para solucionar el problema de las inundaciones; empero, aún la situación es la misma. Añade que, en el año en curso, el río aludido destruyó árboles, cercas, postes y cosechas.
De importancia para la decisión de este asunto, se estiman como debidamente demostrados los siguientes hechos, sea porque así han sido acreditados o bien porque la autoridad recurrida haya omitido referirse a ellos, según lo prevenido en el auto inicial:
C. La zona evaluada en el poblado de San Pablo Viejo de Nandayure presenta una topografía plana ondulada, se ubica en el punto donde el cauce cambia su condición encajonada en el cañón del río y se abre hacia la llanura aluvial, posee cobertura variada con árboles dispersos y algunas infraestructuras habitacionales construidas dentro de las zonas que se ha visto afectadas por anegamientos en el pasado, además, paralelo al cauce corre un camino vecinal que se ve impactado cuando ocurren los eventos de desbordamiento. D. En el sector evaluado que va paralelo al cauce del río Nandayure se observa una fuerte erosión lateral sobre las márgenes, debido a que el caudal impacta con gran fuerza las zonas. Se observa en toda la sección baja del río una alta sedimentación y colmatación de materiales que lo han rellenado por completo, generando una pérdida importante de la capacidad hidráulica y favoreciendo los eventos de desbordamiento cuando se dan lluvias fuertes.
E. Mediante el sobrevuelo realizado con un equipo aéreo no tripulado (drone), se observan evidencias de eventos de desbordamientos, anegamientos y depósito de escombros sobre las márgenes en la planicie, donde se ubican varias viviendas. Se observan evidencias del arrastre de la corriente y los escombros que contenía el flujo cuando atraviesa el camino municipal que lleva a San Pablo Viejo, y que continua hacia terrenos aledaños. F. En la quebrada Pozas, la cual atraviesa el camino que lleva a San Pablo Viejo, se observan problemas en el puente de paso, el cual se obstruye por arrastre de escombros y provoca el desbordamiento del caudal. Esta problemática interrumpe el paso, deja incomunicado al poblado y sin opción de salir debido a que solo existe esta vía para ingresar a la comunidad (…) Recomendaciones. A. La Municipalidad de Nandayure deberá coordinar con Obras Fluviales del MOPT y el MINAE la posibilidad de realizar una adecuada canalización sobre el cauce del río Nandayure en los sitios evaluados que presentan problemas, para remover la cantidad de material acumulado que disminuye la capacidad hidráulica de las secciones, además, realizar obras de protección para disminuir la erosión lateral sobre las márgenes y los diques de protección.
B. La Municipalidad de Nandayure deberá realizar la construcción de adecuadas obras de protección y contención en las márgenes del río Nandayure, con materiales que no sean erosionados por las crecidas extraordinarias y protejan los sectores. C. Restringir por parte de la Municipalidad de Nandayure el uso de suelo con fines habitacionales o de comercio en las zonas de protección del río Nandayure, según el artículo 33 de la ley forestal 7575, así como en las áreas identificadas con potencial afectación por inundaciones; según los mapas de amenazas naturales de la CNE. D. Las obras de protección que se implementen sobre las márgenes afectadas deben ser supervisadas por un profesional agremiado al Colegio Federado de Ingenieros y Arquitectos de Costa Rica, con base en las normas establecidas por el Código Sísmico, Código de Cimentaciones y Reglamento de Construcciones, Código Municipal y otra legislación vigente.
E. La Municipalidad de Nandayure deberá realizar periódicamente, según las condiciones de acumulación de materiales en el cauce del río Nandayure y todos aquellos que drenan el cantón, una adecuada canalización que ayude a recuperar la capacidad hidráulica del cauce y disminuya la amenaza de inundación en cada sector. F. La Municipalidad de Nandayure deberá permanecer vigilante de las zonas de alto riesgo, inundación y susceptibles al deslizamiento, no otorgar permisos constructivos o desarrollo de asentamientos informales de viviendas en ellos. G. Cualquier anomalía en cuanto a técnicas de construcción u omisión a las recomendaciones aquí descritas, QUEDA BAJO TOTAL RESPONSABILIDAD de las instituciones que otorgan los permisos, del ingeniero o responsable de la obra y de la Municipalidad respectiva de no solicitar los informes, inspecciones y correcciones correspondientes.”. (Prueba documental).
En el sub lite, el recurrente manifiesta que es vecino de San Pablo de Nandayure, zona afectada por las inundaciones que provoca el Río Nandayure. Alega que ha solicitado ayuda a las autoridades recurridas para que se realicen las obras necesarias para solucionar el problema de las inundaciones; empero, aún la situación es la misma. Añade que, en el año en curso, el río aludido destruyó árboles, cercas, postes y cosechas.
Del estudio de los autos se tiene demostrado, que la municipalidad accionada informa que el Río Nandayure presenta dos áreas de inundación, que afectan a las comunidades de Carmona y San Pablo. En marzo de 2020, la Dirección de Obras Fluviales del MOPT realizó trabajos de limpieza y canalización en el Río Nandayure, como parte de las medidas para mitigar los efectos de las lluvias. El presidente de la CNE informa: “esta Comisión desde el año 2018 a la fecha tramitó las siguientes solicitudes por parte de la Municipalidad de Nandayure: 1) 2019PI-000008-0006500001 “Alquiler de Maquinaria para atender la emergencia en la comunidad de San Pablo, río Nandayure, Nandayure 5ta Ocasión”, donde se adjudicó en fecha 23 de enero de 2019 a la Empresa Hermanos Herrera Barrantes Constructora, Sociedad Anónima, 150 horas efectivas de una excavadora y 150 horas efectivas de un Tractor, cuyo fin era la limpieza, recava del río Nandayure, apilación de material a los costados, tipo dique con el fin de evitar o mitigar desbordamientos y mayor afectación en el sector de la comunidad de San Pablo y 2) 2020PI-000374-0006500001 “Alquiler de Maquinaria para atender afectaciones en San Pablo, desbordamiento río Nandayure”, donde en fecha 11 de diciembre de 2020, se adjudicó a la Constructora Meco, Sociedad Anónima, 150 horas efectivas de un tractor y 150 horas efectivas de una excavadora, con el fin de atender la emergencia no declarada cuya finalidad era la limpieza y recavar el cauce del río Nandayure en la comunidad de San Pablo, Nandayure, con el fin de evitar nuevos desbordamientos del río, que ocasionen afectaciones a la comunidades e infraestructura.”.
En el informe técnico nro. CNE-UIAR-INF-1193-2021 de septiembre de 2022 de la Unidad de Investigación y Análisis de Riesgo de la CNE, se consignó: “Valoración de riesgo en las márgenes del río Nandayure en la localidad de San Pablo Viejo, por problemas erosión lateral y anegamiento del sector (…) Conclusiones: A. Según el Mapa de Amenazas Naturales Potenciales de la CNE, las zonas evaluadas se encuentran dentro del área con afectación directa por inundaciones potenciales cuando ocurren desbordamientos del caudal del río Nandayure y sus afluentes en la zona de planicie, generalmente ocurridos cuando se dan lluvias intensas en la zona alta de las microcuencas por influencia de fenómenos hidrometereológicos extremos. B. El sector evaluado en la localidad de San Pablo Viejo se localiza dentro de la microcuenca del río Nandayure, sobre la margen izquierda. La zona evaluada se ubica dentro de lo que corresponde con el área del cauce del río y planicie aluvial, en los bordes de las terrazas aluvionales construidas por la acreción de sedimentos depositados luego de eventos de crecidas extraordinarias.
C. La zona evaluada en el poblado de San Pablo Viejo de Nandayure presenta una topografía plana ondulada, se ubica en el punto donde el cauce cambia su condición encajonada en el cañón del río y se abre hacia la llanura aluvial, posee cobertura variada con árboles dispersos y algunas infraestructuras habitacionales construidas dentro de las zonas que se ha visto afectadas por anegamientos en el pasado, además, paralelo al cauce corre un camino vecinal que se ve impactado cuando ocurren los eventos de desbordamiento. D. En el sector evaluado que va paralelo al cauce del río Nandayure se observa una fuerte erosión lateral sobre las márgenes, debido a que el caudal impacta con gran fuerza las zonas. Se observa en toda la sección baja del río una alta sedimentación y colmatación de materiales que lo han rellenado por completo, generando una pérdida importante de la capacidad hidráulica y favoreciendo los eventos de desbordamiento cuando se dan lluvias fuertes.
E. Mediante el sobrevuelo realizado con un equipo aéreo no tripulado (drone), se observan evidencias de eventos de desbordamientos, anegamientos y depósito de escombros sobre las márgenes en la planicie, donde se ubican varias viviendas. Se observan evidencias del arrastre de la corriente y los escombros que contenía el flujo cuando atraviesa el camino municipal que lleva a San Pablo Viejo, y que continua hacia terrenos aledaños. F. En la quebrada Pozas, la cual atraviesa el camino que lleva a San Pablo Viejo, se observan problemas en el puente de paso, el cual se obstruye por arrastre de escombros y provoca el desbordamiento del caudal. Esta problemática interrumpe el paso, deja incomunicado al poblado y sin opción de salir debido a que solo existe esta vía para ingresar a la comunidad (…) Recomendaciones. A. La Municipalidad de Nandayure deberá coordinar con Obras Fluviales del MOPT y el MINAE la posibilidad de realizar una adecuada canalización sobre el cauce del río Nandayure en los sitios evaluados que presentan problemas, para remover la cantidad de material acumulado que disminuye la capacidad hidráulica de las secciones, además, realizar obras de protección para disminuir la erosión lateral sobre las márgenes y los diques de protección.
B. La Municipalidad de Nandayure deberá realizar la construcción de adecuadas obras de protección y contención en las márgenes del río Nandayure, con materiales que no sean erosionados por las crecidas extraordinarias y protejan los sectores. C. Restringir por parte de la Municipalidad de Nandayure el uso de suelo con fines habitacionales o de comercio en las zonas de protección del río Nandayure, según el artículo 33 de la ley forestal 7575, así como en las áreas identificadas con potencial afectación por inundaciones; según los mapas de amenazas naturales de la CNE. D. Las obras de protección que se implementen sobre las márgenes afectadas deben ser supervisadas por un profesional agremiado al Colegio Federado de Ingenieros y Arquitectos de Costa Rica, con base en las normas establecidas por el Código Sísmico, Código de Cimentaciones y Reglamento de Construcciones, Código Municipal y otra legislación vigente.
E. La Municipalidad de Nandayure deberá realizar periódicamente, según las condiciones de acumulación de materiales en el cauce del río Nandayure y todos aquellos que drenan el cantón, una adecuada canalización que ayude a recuperar la capacidad hidráulica del cauce y disminuya la amenaza de inundación en cada sector. F. La Municipalidad de Nandayure deberá permanecer vigilante de las zonas de alto riesgo, inundación y susceptibles al deslizamiento, no otorgar permisos constructivos o desarrollo de asentamientos informales de viviendas en ellos. G. Cualquier anomalía en cuanto a técnicas de construcción u omisión a las recomendaciones aquí descritas, QUEDA BAJO TOTAL RESPONSABILIDAD de las instituciones que otorgan los permisos, del ingeniero o responsable de la obra y de la Municipalidad respectiva de no solicitar los informes, inspecciones y correcciones correspondientes.”. El alcalde de la Municipalidad de Nandayure señala que se han realizado técnicas de dragado y otros trabajos para contrarrestar las inundaciones en época de invierno; empero, tales acciones resultan insuficientes y no se ha podido alcanzar una solución integral duradera.
El 18 de agosto de 2022, la Municipalidad de Nandayure y la CNE efectuaron una visita a cada uno de los puntos críticos en la comunidad de San Pablo. La municipalidad accionada informa que ha iniciado con el estudio de un anteproyecto para la intervención del río; empero, requiere la participación de las demás dependencias accionadas para planear y ejecutar las obras respectivas, a fin de solucionar el problema acusado.
Sobre el particular, interesa resaltar que, en la sentencia nro. 2019018960 de las 9:20 horas de 4 de octubre de 2019, este Tribunal resolvió un recurso de amparo interpuesto por el recurrente, atinente a la problemática del Río Nandayure. En esa resolución, se indicó:
“I.- Objeto del recurso. Los recurrentes alegan, que han presentado varias gestiones solicitando el dragado del río Nandayure, en el sector de San Pablo, y a la fecha, no han recibido respuesta ni se han realizado los actos correspondientes (…)
IV.Sobre el fondo. La Administración, a la luz del artículo 41, de la Constitución Política, tiene la obligación de garantizarle a la ciudadanía el cumplimiento de la justicia pronta y cumplida, sin denegación, lo que implica, en el ámbito de la justicia administrativa, su obligación de decidir con diligencia y celeridad los reclamos planteados por los administrados, de tal manera que su resolución sea congruente con los extremos alegados, así como de comunicarles a los interesados lo dispuesto, todo ello dentro de un plazo razonable. En el caso bajo estudio, la Sala acredita una infracción a lo dispuesto en el artículo 41, de la Constitución Política, toda vez que la parte recurrida no había resuelto las gestiones interpuestas por los recurrentes y demás vecinos, desde el 6 de noviembre de 2018, y reiteradas, el 26 de abril y el 13 de junio, ambos del 2019, lo que evidencia una lesión al derecho fundamental a la justicia pronta y cumplida. Además, fue con la notificación del presente recurso de amparo, que la autoridad recurrida procedió a resolver la gestión a lo solicitado por los gestionantes. En consecuencia, en cuanto este extremo se declara con lugar el recurso.
V.Por otra parte, si bien a la fecha, no consta que se requiera hacer el dragado del río Nandayure en el sector solicitado por los recurrentes, pues para tener certeza de ello, se requiere realizar los estudios técnicos, por parte de la autoridades competentes; lo cierto es que, ante la duda, y dado que el año pasado se produjeron inundaciones que dañaron los trabajos ya realizados, se debe aplicar el "principio de evitación prudente o precautorio", con respecto a la posible afectación que podría causar el desbordamiento del cauce del río, a la salud e integridad de las personas que habitan dicha comunidad así como a sus viviendas, la alteración de ecosistemas, erosión, la destrucción de caminos, cultivos, la afectación de la salud y el bienestar de la vida silvestre y el ganado, entre otros. De manera, que en aplicación a dicho principio, y dada la evidencia de que se podría estar en presencia de un peligro de daño grave o irreversible, lo correcto es actuar minimizando en lo posible las situaciones de riesgo que pueda provocar dicha situación.
Además, la pretensión de los recurrentes es que se realice una limpieza y ahondamiento del río en cuestión, en la zona de San Pablo, así como la remoción de rocas y sedimentos, para aumentar la profundidad, por lo que traduciendo dicha petición al terreno de lo constitucional, lo procedente es que la Sala acoja el recurso y ordene al Alcalde Municipal en coordinación con los entes competentes de la Dirección de Obras Fluviales y de la Región, del Ministerio de Obras Públicas y Transportes, que se realicen los estudios técnicos, señalados por dichas autoridades, a saber, un estudio hidrológico y una modelación hidráulica en dos dimensiones para saber con certeza el tipo de obra hidráulica a construir e identificar, si la infraestructura existente, se encuentra dentro de la zona de protección del río para la solución del problema. Lo anterior se fundamenta en lo dispuesto en el artículo 15, de la "Declaración de Río", adoptada por la Conferencia de las Naciones Unidas sobre el Medio Ambiente y el Desarrollo, en junio de 1992, que reza:
"Con el fin de proteger el medio ambiente, los Estados deberán aplicar ampliamente el criterio de precaución conforme a sus capacidades. Cuando haya peligro de daño grave o irreversible, la falta de certeza científica absoluta no deberá utilizarse como razón para postergar la adopción de medidas eficaces en función de los costos para impedir la degradación del medio ambiente" .
Acorde con lo anterior, es necesario insistir en que la observancia de un principio puede ser racional o irracional, y el caso de la evitación prudente no es excepción. De hecho, está claro que el principio en cuestión, como "evitación prudente" es únicamente una recomendación, de vigencia transitoria, para que se apliquen determinadas medidas preventivas. Así, en virtud de lo expuesto, y en aplicación del principio precautorio, lo procedente es acoger el recurso, únicamente en cuanto a este extremo.
Por tanto:
Se declara con lugar el recurso. Se ordena a Giovanni Jiménez Gómez, en su condición de Alcalde de la Municipalidad de Nandayure, o a quien ocupe dicho cargo, que en el plazo de OCHO MESES, a partir de la notificación de esta sentencia, deberá, de manera coordinada con las autoridades de la Dirección de Obras Fluviales y de la Macro Región de Guanacaste, ambos del Ministerio de Obras Públicas y Transportes, deberán realizar y obtener los resultados del estudio hidrológico y de la modelación hidráulica, que corresponda, para saber con certeza el tipo de obra hidráulica a construir e identificar, si la infraestructura existente se encuentra dentro de la zona de protección del río Nadanyure, con el fin de solucionar el problema de desbordamiento que se presenta en la zona de San Pablo. Lo anterior, bajo la advertencia de incurrir en el delito previsto por el artículo 71, de la Ley de la Jurisdicción Constitucional, en caso de no hacerlo.
Se condena a la Municipalidad de Nandayure, al pago de las costas, daños y perjuicios causados con los hechos que sirven de base a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso administrativo. Notifíquese esta resolución a la parte recurrida, así como a Jenaro Ruiz Chacón y a Alonso Mora Arroyo, por su orden Director a.i. de la Dirección de Obras Fluviales y Director Macro Región de Guanacaste, ambos del Ministerio de Obras Públicas y Transportes, o a quienes ocupen dichos cargos, en forma personal”.
Ahora bien, como se aprecia, en el precedente transcrito supra se ordenó la realización de determinados estudios que en ese momento estaban pendientes y que servirían para atender el problema de las inundaciones en el río de marras. No obstante, aproximadamente 3 años después, se aprecia que aún persiste la situación de las inundaciones, y que no se han ejecutado las obras necesarias para alcanzar una solución integral y definitiva.
En tal sentido, si bien la Municipalidad de Nandayure y la Dirección de Obras Fluviales del MOPT han realizado distintas obras paliativas como dragados y otros trabajos de limpieza y canalización, no menos cierto es que tales acciones han resultado insuficientes. Al respecto, la propia municipalidad accionada reconoce que es necesario ejecutar mayores esfuerzos para ejecutar obras duraderas que solventen el problema acusado. Asimismo, en el informe técnico CNE-UIAR-INF-1193-2021 de septiembre de 2022 de la Unidad de Investigación y Análisis de Riesgo de la CNE se consignó que mayores intervenciones y acciones eran necesarias por parte de la municipalidad accionada.
Así las cosas, pese a que desde al menos hace 3 años las autoridades de la Municipalidad de Nandayure y de la Dirección de Obras Fluviales del MOPT conocen el problema de marras y han realizado determinados trabajos paliativos, no han ejecutado lo pertinente para alcanzar una solución integral y definitiva garantice la seguridad de la comunidad de San Pablo de Nandayure.
De tal manera, lo procedente es declarar con lugar el recurso en cuanto a tales dependencias, a fin de garantizar una solución integral dentro de un plazo razonable.
IV- Por otra parte, en relación con la Comisión Nacional de Prevención de Riesgos y Atención de Emergencias, a priori se descarta alguna omisión que amerite ser declarada en esta vía sumaria.
En tal sentido, se informó bajo juramento que las solicitudes de ayuda tramitadas por la Municipalidad de Nandayure fueron debidamente atendidas, y se ejecutaron las contrataciones solicitadas en las gestiones 2019PI-000008-0006500001 y 2020PI-000374-0006500001. Asimismo, se efectuó la respectiva inspección y mediante el informe CNE-UIAR-INF-1193-2021 de septiembre de 2022 se detallaron las recomendaciones atinentes a las obras que la referida municipalidad debe ejecutar.
En consecuencia, lo procedente es declarar sin lugar el recurso en cuanto a este extremo. Sin embargo, deberá tomar nota el presidente de la Comisión Nacional de Prevención del Riesgo y Atención de Emergencias, a fin de que, en caso de ser requerido, dentro del marco de sus competencias se coadyuve con la Municipalidad de Nandayure y con la Dirección de Obras Fluviales del MOPT en la solución del problema objeto de este recurso.
Si bien coincido con la mayoría de la Sala en que el recurso se debe declarar con lugar, difiero sobre dónde residenciar la fase de ejecución del asunto, debido a la inexistencia de mecanismos adecuados previstos por la normativa que rige esta jurisdicción constitucional para dar seguimiento a una sentencia que reviste aspectos técnicos de gran complejidad, como es en este caso llevar a cabo las obras necesarias para solucionar en definitiva la problemática de inundaciones que sufre la comunidad de San Pablo por parte del río Nandayure. En cambio, lo dispuesto por el Código Procesal Contencioso-Administrativo en materia de ejecución (artículo 155 y siguientes) tiene evidentes ventajas, como la posibilidad de pedir cronogramas, imponer multas, sentar responsabilidades, fiscalizar etapas de cumplimiento, etc. Por ello, de conformidad con lo dispuesto por el artículo 56 de la Ley de Jurisdicción Constitucional, estimo que la fase de ejecución debe realizarse ante el Área de Ejecución del Tribunal Contencioso Administrativo y Civil de Hacienda, bajo las reglas de ejecución de sentencia de dicho Código.
Se previene a las partes que, de haber aportado algún documento en papel, así como objetos o pruebas contenidas en algún dispositivo adicional de carácter electrónico, informático, magnético, óptico, telemático o producido por nuevas tecnologías, éstos deberán ser retirados del despacho en un plazo máximo de 30 días hábiles contados a partir de la notificación de esta sentencia. De lo contrario, será destruido todo aquel material que no sea retirado dentro de este plazo, según lo dispuesto en el "Reglamento sobre Expediente Electrónico ante el Poder Judicial", aprobado por la Corte Plena en sesión N°27-11 del 22 de agosto del 2011, artículo XXVI y publicado en el Boletín Judicial número 19 del 26 de enero del 2012, así como en el acuerdo aprobado por el Consejo Superior del Poder Judicial, en la sesión N°43-12 celebrada el 3 de mayo del 2012, artículo LXXXI.
Por tanto:
Se declara parcialmente con lugar el recurso, únicamente en cuanto a la Municipalidad de Nandayure y al Ministerio de Obras Públicas y Transportes. Se ordena a Jenaro Ruiz Chacón y a Giovanni Jiménez Gómez, por su orden, director a.i. de la Dirección de Obras Fluviales del Ministerio de Obras Públicas y Transportes y alcalde de Nandayure, o a quienes respectivamente ocupen tales cargos, que coordinen lo correspondiente, giren las órdenes pertinentes y lleven a cabo todas las actuaciones que estén dentro del ámbito de sus respectivas competencias para que, dentro del plazo máximo de DOCE MESES, contado a partir de la notificación de esta sentencia, se realicen todas las gestiones y obras pertinentes para solucionar de manera integral y definitiva el problema de inundaciones del Río Nandayure, que afecta a la comunidad de San Pablo de Nandayure. Se advierte que, de conformidad con lo establecido en el artículo 71, de la Ley de la Jurisdicción Constitucional, se impondrá prisión de tres meses a dos años, o de veinte a sesenta días multa, a quien recibiere una orden que deba cumplir o hacer cumplir, dictada en un recurso de amparo, y no la cumpliere o hiciere cumplir, siempre que el delito no esté más gravemente penado.
Se condena al Estado y a la Municipalidad de Nandayure al pago de las costas, daños y perjuicios causados con los hechos que sirvieron de base a la presente declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso-administrativo. En lo demás, se declara sin lugar el recurso. Tome nota la Comisión Nacional de Prevención de Riesgos y Atención de Emergencias de lo consignado in fine del considerando IV de esta sentencia. La magistrada Garro Vargas salva el voto respecto a la ejecución de esta sentencia y, de conformidad con el artículo 56 de la Ley de la Jurisdicción Constitucional, dispone que debe realizarse ante el Área de Ejecución del Tribunal Contencioso Administrativo y Civil de Hacienda, bajo las reglas de ejecución, establecidos en los artículos 155 y siguientes del Código Procesal Contencioso Administrativo. Asimismo, ordena que se le remita copia de la sentencia para que se inicie los procedimientos de ejecución de este fallo. Notifíquese.
Fernando Castillo V.
Fernando Cruz C.
Paul Rueda L.
Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Jose Roberto Garita N.
Clasificación elaborada por SALA CONSTITUCIONALdel Poder Judicial. Prohibida su reproducción y/o distribución en forma onerosa.