Res. 18422-2021 Sala Constitucional · Sala Constitucional · 20/08/2021
OutcomeResultado
The contempt action is dismissed but a further six-month extension is granted for the authorities to comply with the original judgment, under warning to adopt alternative measures if the new well construction is not achieved.Se desestima la gestión de desobediencia pero se otorga una nueva prórroga de seis meses para que las autoridades cumplan con lo ordenado en la sentencia original, bajo apercibimiento de adoptar medidas alternativas si no se logra la construcción del nuevo pozo.
SummaryResumen
The Constitutional Chamber addressed a contempt action filed by a resident of Residencial El Molino in Cartago against the ASADA, AyA, Municipality, and other authorities, for non-compliance with Judgment 2019-013292 which ordered the supply of potable water from a new well within six months. Despite evidence that the existing well had chronic nitrate contamination since at least 2009 and that SENARA ordered its closure in 2016, the respondent authorities failed to drill the new well due to land transfer and permit procedures. The Chamber verified that the temporary water dilution measure has been maintained and that nitrate levels are within regulatory limits according to the Ministry of Health, thus finding no contempt. Nevertheless, given the insufficiency of previous deadlines, it grants a further six-month extension for a comprehensive and definitive solution, with a warning to adopt alternative measures if impossibility persists. The request for the Municipality to directly assume the service is again dismissed due to technical infeasibility already established in the original judgment.La Sala Constitucional conoció una gestión de desobediencia interpuesta por un vecino del Residencial El Molino de Cartago contra la ASADA, el AyA, la Municipalidad y otras autoridades, por el incumplimiento de la sentencia 2019-013292 que ordenó el suministro de agua potable de un nuevo pozo en un plazo de seis meses. A pesar de que se demostró que el pozo existente mantiene una contaminación crónica por nitratos desde al menos 2009, y que el SENARA dictaminó su cierre desde 2016, las autoridades recurridas no lograron perforar el nuevo pozo debido a trámites de traspaso de terrenos municipales y permisos. La Sala verificó que la medida temporal de dilución del agua se ha mantenido y que los niveles de nitratos están dentro de los límites reglamentarios según el Ministerio de Salud, por lo que no se configura desobediencia. Sin embargo, ante la insuficiencia de los plazos previos, otorga una nueva prórroga de seis meses para la solución integral y definitiva, con la advertencia de adoptar medidas alternativas si persiste la imposibilidad. Se reitera la improcedencia de que la Municipalidad asuma directamente el servicio, por inviabilidad técnica ya declarada en la sentencia original.
Key excerptExtracto clave
Now, from this overview, the Chamber finds that the respondent authorities have taken actions aimed at following up on the corresponding procedures for compliance with the Court’s order; however, the granted deadlines have been insufficient. Therefore, based on the arguments presented and considering the Ministry of Health’s response that the nitrate levels in the water supplied to the ASADA El Molino distribution network through the dilution process are within the alert level (25 mg/l) and maximum permissible level (50 mg/l), in compliance with Decree No. 38924-S, this Chamber deems it appropriate to dismiss the contempt action and instead grants the respondents an additional 6-month extension, counted from notification of this judgment, to comprehensively and definitively solve the nitrate contamination problem in the water supplied to the residents of Residencial El Molino. However, this extension is granted with the warning that if the construction of a new supply well is not possible within the granted period, the respondent authorities must adopt the corresponding measures to definitively solve the problem underlying this appeal.Ahora bien, desde este panorama, la Sala acredita que las autoridades accionadas han efectuado acciones tendientes a darle seguimiento a los trámites correspondientes para el cumplimiento de lo ordenado por este Tribunal; sin embargo, los plazos otorgados han sido insuficientes. Así las cosas, en mérito de los alegatos esgrimidos por los accionados, y tomando en consideración la respuesta del Ministerio de Salud en el sentido de que los resultados del parámetro de nitratos en el agua suministrada en la red de distribución del acueducto de la Asada El Molino mediante el proceso de dilución, se encuentran dentro del valor de alerta (25mg/l) y valor máximo admisible (50 mg/l) permitidos, cumpliendo con lo establecido en el decreto n.° 38924-S, es que esta Sala estima procedente desestimar la gestión de desobediencia y en su lugar se concede a los recurridos una prórroga de 6 meses más, contado a partir de la notificación de esta sentencia, para que se solucione de manera integral y definitiva, el problema de contaminación por nitratos en el agua suministrada a los vecinos del Residencial El Molino. No obstante, tal prórroga se otorga bajo la advertencia de que, si en el plazo concedido no resulta posible la construcción de un nuevo pozo de abastecimiento, las autoridades accionadas deberán adoptar las medidas correspondientes, a efectos de solucionar en definitiva el problema objeto de este recurso.
Pull quotesCitas destacadas
"se acredita que, mediante oficio PRE-LNA-2014- 1071 del 24 de noviembre de 2014, el Laboratorio de Aguas del AyA le informó a la ASADA recurrida sobre los niveles altos de nitrato en el agua de la ASADA y recomendó evaluar fuentes alternativas."
"it is proven that, by official communication PRE-LNA-2014-1071 of November 24, 2014, the AyA Water Laboratory informed the respondent ASADA of the high nitrate levels in the ASADA’s water and recommended evaluating alternative sources."
Considerando I — Antecedentes
"se acredita que, mediante oficio PRE-LNA-2014- 1071 del 24 de noviembre de 2014, el Laboratorio de Aguas del AyA le informó a la ASADA recurrida sobre los niveles altos de nitrato en el agua de la ASADA y recomendó evaluar fuentes alternativas."
Considerando I — Antecedentes
"el SENARA rindió un dictamen detallado sobre el pozo que abastece el Residencial El Molino y concluyó que este debía cerrarse y emplearse otra fuente de abastecimiento del líquido, toda vez que se había constatado un índice de contaminación por nitratos por encima de los valores máximos establecidos y con valores en ascenso desde el año 2009."
"SENARA issued a detailed opinion on the well supplying Residencial El Molino and concluded that it should be closed and another water source used, given a proven nitrate contamination index above the established maximum levels and with rising values since 2009."
Considerando I — Dictamen SENARA
"el SENARA rindió un dictamen detallado sobre el pozo que abastece el Residencial El Molino y concluyó que este debía cerrarse y emplearse otra fuente de abastecimiento del líquido, toda vez que se había constatado un índice de contaminación por nitratos por encima de los valores máximos establecidos y con valores en ascenso desde el año 2009."
Considerando I — Dictamen SENARA
"se impone declarar con lugar el recurso por la inercia o negligencia de las autoridades recurridas ante la añeja problemática por contaminación con nitratos del pozo del Residencial El Molino."
"the appeal must be granted due to the inertia or negligence of the respondent authorities in the face of the longstanding nitrate contamination problem in the Residencial El Molino well."
Considerando I — Sentencia original
"se impone declarar con lugar el recurso por la inercia o negligencia de las autoridades recurridas ante la añeja problemática por contaminación con nitratos del pozo del Residencial El Molino."
Considerando I — Sentencia original
Full documentDocumento completo
Constitutional Chamber Date of Resolution: 09:15 a.m. on August 20, 2021 Case File: 19-006036-0007-CO Type of Matter: Amparo appeal CONSTITUTIONAL CHAMBER OF THE SUPREME COURT OF JUSTICE. San José, at nine hours fifteen minutes on the twentieth of August of two thousand twenty-one.
Subsequent proceeding filed by ROYER ALEXANDER QUESADA ROJAS, in relation to judgment No. 2019-013292 of 9:20 a.m. on July 19, 2019.
Considering:
He claims that SENERA has carried out the following activities:
ACTIVITY RESPONSIBLE OBSERVATIONS 1. "For the case of the El Molino well and as it is considered a possible source of contamination of the groundwater, in the consecutive OFICIO No. UGH-248-16 of October 24, 2016, the Municipality of Cartago, AyA, Ministry of Health and ASADA El Molino and Mr. Alejandro Monge Ariño were informed that the well must be closed and sealed and another supply source must be used.
Municipality of Cartago, AyA, Ministry of Health and ASADA Residencial El Molino. The sealing of the well has not been carried out; the proposal is to carry out a new drilling and replace the existing one and tap the deeper aquifer. An activity that is in process. The proposal has not been submitted to SENARA The sealing of the well has not been carried out; the proposal is to carry out a new drilling and replace the existing one and tap the deeper aquifer. An activity that is in process. The proposal for the new subsoil drilling has not been submitted to SENARA, given that according to communication AREM-436- 2020, the drilling application was not admitted following the admissibility study under proceeding No. 202000378, indicating three aspects to be corrected.
2. In the closing and sealing process, it must be considered whether it requires any nearby area that needs to be left for protection.
Municipality of Cartago, AyA, Ministry of Health, SENARA and ASADA El Molino The closure of the well has not been defined. Through note SENARA-DIGH UI-INF- 100-2020, the Conceptual Hydrogeological Model of the Northern part of the Central Canton of Cartago is approved, which includes the protection zone of the well of the ASADA Residencial El Molino. However, the existence of said protection zone does not rule out carrying out the closure of the well, given the technical foundations indicated in communication UGH-248-2016 which justifies the threat to public health that said well represents, due to high nitrate levels, very shallow upper level, presence of houses with septic tanks within the protection zone and inadequate casing that promotes contamination of the two aquifers it taps by placing them in hydraulic communication.
The remedial plan must be presented by the ASADA and AyA ASADA El Molino and AyA In the most recent meetings related to the case at hand, it was defined that the remedial plan presented by the Asada and AyA had a timeframe of 10 months to a year; however, due to questions from the Ministry of Health and a recommendation from the attorney of the Municipality of Cartago, they had to adjust the remedial plan to the timeframe set by the Court, which was two months, or otherwise request the corresponding extension from the Court. In the last meeting, some procedures for the construction of the well had been advanced; however, they would submit the respective extension request and, once a response is received, they would be the ones to call a meeting.
It asserts that the criteria established in official letters UGH-248-16, DIGH-329-2016, SENARA-DIGH-121-2018, SENARA-DIGH-075-2019, SENARA-DIGH-001-2020 and follow-up, SENARA-DIGH-UGSA-137-2020, SENARA-DIGH-UGH-138-2020, are maintained regarding the closure and sealing of the ASADA Residencial El Molino well, as well as other aspects mentioned in the conclusions of each of these official letters in relation to the protection and proper management of the aquifers in the sector where said well is located.
Drafted by Magistrate Sánchez Navarro; and,
Considering:
In judgment No. 2019-013292 at 9:20 a.m. on July 19, 2019, it was ordered:
"IV.- On the specific case. The appellant alleges that he acquired a property in El Residencial El Molino and currently rents another in the same neighborhood. He accuses the respondent ASADA of denying him potable water service for his new property, on the grounds that new services and availabilities were suspended by virtue of AyA directive No. UEN-GAR-2017-00359. He alleges that said directive addresses the closure order that has weighed since 2016 on the well currently operated by the respondent ASADA, due to nitrate contamination in the water. He claims that, despite the passage of time, the well continues to operate, threatening the health of the subscribers. He requests that said well be closed immediately.
From the study of the case file, it is proven that, through official letter PRE-LNA-2014-1071 of November 24, 2014, the AyA Water Laboratory informed the respondent ASADA about the high nitrate levels in the ASADA's water and recommended evaluating alternative sources. A year later, through sanitary order No. CE-ARSC-OS-302-2015 of October 13, 2015, the Ministry of Health ordered the respondent ASADA to present a schedule to permanently solve said problem and to carry out a public awareness campaign in the community so that children under 1 year of age would not consume the liquid. Consequently, through bulletin AREM 151-15 of October 14, 2015, the respondent ASADA informed its subscribers that, based on official letter CE-ARSC-2400-2015 of the Ministry of Health, 'as a precautionary measure' given the nitrate levels detected, it was requested that children under one year of age not consume the water supplied by the ASADA. That same month, AyA prepared a hydrogeological study of the Residencial El Molino Well.
Subsequently, through official letter No. UGH-248-16 of October 24, 2016, SENARA issued a detailed report on the well that supplies Residencial El Molino and concluded that it must be closed and another source of liquid supply used, since a nitrate contamination index above the established maximum values had been verified, with values rising since 2009. Furthermore, an inadequate well construction was evidenced, causing hydraulic communication between the upper and lower aquifers (the contaminated upper waters filter into the lower aquifer). Likewise, the vulnerability of the well was confirmed, since 'the well's protection zone is invaded by houses with septic tanks, with an increase in dwellings since 2017, which generates a greater nitrate load.' By virtue of all this, SENARA requested the Ministry of Health and AyA for 'the closure of the well due to the high risk to public health' and ordered that the ASADA seal it with clay and cement and notify SENARA of the closure date so that an official from said state institution could be present. Additionally, SENARA recommended that AyA and the Municipality of Cartago analyze the aquifer and determine the scope of new regulatory and mitigation measures; the foregoing, due to the impact that accelerated urban development and the use of septic tanks has caused on the aquifers.
In merit of SENARA's report, through official letter AREM-2010-16 of December 15, 2016, the ASADA indicated to said institution that, in order to resolve the potable water supply problem in Residencial El Molino, steps would be initiated to drill a new well and the existing well would be sealed. Likewise, through directive UEN-GAR-2017-359 of February 2, 2017, the AyA Regional Office of Communal Systems notified the respondent ASADA that, by virtue of SENARA's request for well closure, it was recommended not to grant availability letters and new services until the Deputy Management of Communal Systems ruled on the matter. Also, based on SENARA's technical report No. UGH-248-2016, the Ministry of Health, through sanitary order No. CE-ARSC-OS-136-2017 of May 11, 2017, ordered the ASADA of El Molino to present a remedial plan to ensure the supply of potable water that met the regulated parameters.
Consequently, on May 25, 2017, the ASADA presented the corrective action plan and the schedule for the replacement of the potable water well in El Molino to the Ministry of Health. Subsequently, by official letter CE-URS-551-2017 of June 30, 2017, the Ministry of Health indicated that the nitrate contamination problems in the water of the ASADA El Molino date back to 2010, and it was concluded that the remedial plan presented by the ASADA had a reasonable execution period of 349 days for the new well to be put into operation; in addition, it was noted that this was scientifically and technically based on a technical study. However, later, through sanitary order No. CE-ARSC-OS-282-2017 of July 24, 2017, the Ministry of Health ordered the ASADA to expand the proposed remedial plan to include an immediate solution that would ensure water quality for subscribers, while the new well is built.
Consequently, by official letter AREM-238-2017 of August 10, 2017, the respondent ASADA presented the expansion of the remedial plan to the Ministry of Health and indicated that, as a temporary measure while the new well is drilled, a dilution process of the well water with nitrate-free water would be carried out – upon the recommendation of the AyA National Water Laboratory; the foregoing, in order to reduce the concentration of inorganic chemical compounds in the liquid.
Subsequently, through official letter CE-ARSC-R-1096-2017 of August 28, 2017, the Ministry of Health concluded that the ASADA had complied with sanitary order No. CE-ARSC-OS-282-2017 and recommended approving the dilution process proposed by the ASADA. However, on September 4, 2017, through sanitary order No. CE-ARSC-OS-323-2017, the Ministry of Health ordered the respondent ASADA to present a schedule for the remedial plan for the construction and commissioning of the new well, to perform monthly laboratory analyses on water quality, and to present quarterly progress reports on the well construction schedule.
In this context, through official letter AREM-248-17 received on September 19, 2017, the respondent ASADA informed the Cartago Health Governing Body that the public awareness campaign had already been launched, the exact drilling point had been defined, the new well had been designed, bidding companies had been invited, and quotes for drilling had been received. Additionally, it was indicated that the award and signing of the contract, processing of drilling permits, installation of equipment, drilling, water quality analysis, well development, pumping tests, installation of permanent equipment, commissioning of the new well, and sealing of the current well remained pending. Furthermore, it was noted that monthly water samplings had been arranged through the Instituto Tecnológico de Costa Rica. Finally, in the same official letter, the ASADA committed to presenting quarterly reports on the well construction schedule compliance.
Now then, regarding the dilution process, official letter AREM-361-2019 of April 2, 2019 is in the case file, through which the respondent ASADA informed the Cartago Health Governing Body that, as of January 31, 2019, the Municipality of Cartago had unilaterally suspended the water service for dilution, which is why on February 12, 2019, the municipality had been requested to resume the service until the drilling of the new well was completed. However, on the other hand, the Health Governing Body reports that the dilution process has been suspended since April 2019. Thus, regardless of the suspension date, the truth is that it is proven that currently, the water from the Residencial El Molino well is no longer being diluted with uncontaminated water from the Cartago aqueduct.
Finally, it is observed that, in compliance with sanitary order No. CEARSC-OS-323-2017, the respondent ASADA, through the Instituto Tecnológico de Costa Rica, has been sampling the water from the Residencial El Molino well and sending the results to the Cartago Health Governing Body. According to a sample taken on April 8, 2019, at a parameter of 50 as the maximum allowable value, the water from the residential area presented a nitrate value of 53±5, and according to a sample from May 13, 2019, the liquid presented a value of 54±4, so, as reported by the Ministry of Health, the maximum permitted levels were exceeded.
Thus, in light of the factual scenario set forth, it is demonstrated that although AyA (in its capacity as the governing body of the potable water and sanitation service) and the respondent ASADA have carried out different proceedings regarding the nitrate problem in the water of the Residencial El Molino well, the truth is that they have not acted efficiently, since the problem has not yet been resolved, despite the fact that it is recorded that, since 2014, the AyA Water Laboratory has been aware of the situation and informed the respondent ASADA about it.
On the other hand, it is also observed that the Ministry of Health has issued various sanitary orders and official letters in relation to the problem of nitrate concentration in the water of Residencial El Molino. However, it is verified that the situation has not been given efficient oversight and follow-up, since it is notably missing that the Health Governing Body has reacted effectively to the delay by the ASADA in relation to compliance with the remedial plan schedule. In this regard, it is noted that through official letter CE-URS-551-2017 of June 30, 2017, the Ministry of Health concluded that the remedial plan presented by the ASADA had a reasonable execution period of 349 days for the new well to be put into operation. However, more than two years later, the construction of the new well has not even started. Nor are concrete actions observed by the Ministry of Health in relation to the suspension of the dilution of the well water with liquid from the municipal aqueduct of Cartago, despite the fact that said measure addresses compliance with sanitary order No. CE-ARSC-OS-282-2017 of July 24, 2017, which demanded an immediate solution that would ensure water quality for the current subscribers of the ASADA, while the new well is built.
Furthermore, it is observed that SENARA, since 2016, issued a technical opinion that concluded that the Residencial El Molino well must be closed and another source of liquid supply used, by virtue of the nitrate contamination index with values rising since 2009. In addition, an inadequate well construction was evidenced that causes hydraulic communication between the upper and lower aquifers (the contaminated upper waters filter into the lower aquifer), well vulnerability, and invasion of the well protection zone by septic tanks from residential houses, which generates a greater nitrate load. By virtue of all this, SENARA requested the Ministry of Health and AyA for the closure of the well and ordered that the ASADA notify them of the closure date so that a SENARA official could be present. Additionally, in merit of the impact produced on the aquifers by the high urban development and the use of septic tanks, SENARA recommended that AyA and the Municipality of Cartago analyze the aquifer and determine the scope of new regulatory and mitigation measures.
It should be noted that by virtue of the provisions of Article 3, subsection h, of Law No. 6877 creating SENARA, said institution has among its functions 'to investigate, protect, and promote the use of the country's water resources, both surface and underground.' However, SENARA fails to inform this Court that it has properly followed up on the directives issued since 2016, despite the fact that contamination of an underground water body by human activity was verified, the need to close the current well was confirmed, and despite the fact that, as suggested by official letter No. DIGH-329-16 of November 1, 2016, it was suspected that the condition of the ASADA El Molino well could be repeating itself in other supply wells in the sector.
Moreover, regarding the Municipality of Cartago, it is observed that, through official letter No. UGH-248-16 of October 24, 2016, SENARA warned that 'the well's protection zone is invaded by houses with septic tanks, with an increase in dwellings since 2017, which generates a greater nitrate load.' By virtue of this, SENARA recommended that the municipality analyze the aquifer with emphasis on the supply wells and, due to the high impact that high urban development and the use of septic tanks have had in the area, determine the scope of new regulatory and mitigation measures.
However, in the report submitted to this Court, the municipality makes no mention whatsoever of having acted in accordance with what was indicated by SENARA, but quite the contrary, as it insists on emphasizing that it has no competence whatsoever in the case, despite the fact that it is the municipality that is responsible for regulating cantonal territorial planning and despite the fact that the accelerated urbanization of the area and the concomitant use of septic tanks has been shown to have a significant impact on the contamination of the area's underground water bodies.
Thus, the appeal must be granted due to the inertia or negligence of the respondent authorities in the face of the longstanding problem of nitrate contamination of the Residencial El Molino well.
V.In another vein, the appellant requests that the potable water service for the residents of Residencial El Molino be assumed by the aqueduct of the Municipality of Cartago. However, this petition must be dismissed, since the AyA authorities report under oath that this is not technically viable due to the water and hydraulic capacity of the area. Likewise, this Court considers reasonable the measure of not approving new potable water services to be provided by the current Residencial El Molino well, since a closure order weighs on it for the reasons extensively developed supra.
VI.Regarding specifically the denial of potable water service for the appellant's commercial premises, the amparo must be dismissed for the reasons set forth in Considering I, in the sense that this Court does not analyze said denials when they are for commercial establishments, as the satisfaction of people's basic needs is not at stake. (...)
Therefore:
The appeal is partially granted solely for the inertia or negligence of the respondent authorities in the face of the problem of nitrate contamination of the Residencial El Molino well in Cartago. It is ordered to José Rodolfo Ramírez Villalba, Vladimir Mesén Montenegro, and Carlos Eduardo Aguilar Quesada, in their order, Director of the UEN ASADA Management of the Instituto Costarricense de Acueductos y Alcantarillados, Head of the Central East Regional Office for ASADA Services of the Instituto Costarricense de Acueductos y Alcantarillados, and judicial and extrajudicial representative of the ASADA of Residencial El Molino, or whoever holds those positions in their stead, to carry out the necessary procedures and coordination, within the scope of their competencies, so that within a period of 6 months, counted from the notification of this pronouncement, potable water from a new well that meets the rational potability standards of the liquid begins to be supplied to the subscribers of the ASADA El Molino.
Likewise, immediately, they must take steps and coordinate what is necessary so that, within a maximum period of 15 days counted from the notification of this judgment, the dilution process of the water from the current Residencial El Molino well is resumed, as a temporary measure while the new well comes into operation. For its part, it is ordered to Roberto Ramírez Chavarría, in his capacity as Director of Water Management and Research of the Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento, or whoever holds the position, to properly follow up on the provisions set forth in the operative part of report No. UGH-248-16 of October 24, 2016. Furthermore, it is ordered to Andrea Morales Fiesler, in her capacity as Director of the Cartago Health Governing Body, or whoever holds the position, to properly follow up on and oversee compliance with the current sanitary orders issued; in addition, if necessary, to issue new sanitary orders.
Lastly, it is ordered to Rolando Rodríguez Brenes, in his capacity as Mayor of Cartago, or whoever holds the position, to issue the necessary directives within the scope of his competencies so that, within a period of 2 months counted from the notification of this judgment, the municipality submits a report on the current cantonal territorial planning regulations in relation to the aquifer protection zones and on the current compliance with said regulations in the Residencial El Molino sector and surrounding areas. Likewise, he must coordinate what is necessary to take the measures that are pertinent in light of the results of this report, which must be notified to the Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento, the ASADA El Molino, and the Instituto Costarricense de Acueductos y Alcantarillados. All of the above is ordered with the warning that, in accordance with Article 71 of the Ley de la Jurisdicción Constitucional, a prison sentence of three months to two years, or a fine of twenty to sixty days, shall be imposed on anyone who receives an order from this Court that they must comply with or enforce and disregards it, provided that the offense is not more severely punished.
The Instituto Costarricense de Acueductos y Alcantarillados, the Asociación Administradora del Acueducto y Alcantarillado Sanitario del Residencial El Molino, the Ministry of Health, the Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento, and the Municipality of Cartago are ordered to pay the costs, damages, and losses caused by the acts that serve as the basis for this declaration, which shall be settled in the enforcement of judgment of the contentious-administrative and civil proceedings, as applicable. In all other respects, the appeal is dismissed.
Let this ruling be notified to José Rodolfo Ramírez Villalba and Vladimir Mesén Montenegro, in their order Director UEN Gestión de ASADAS and Chief of the Oficina Regional Central del Este de Atención de ASADAS, both of the Instituto Costarricense de Acueductos y Alcantarillados; as well as to Carlos Eduardo Aguilar Quesada, Roberto Ramírez Chavarría, Rolando Rodríguez Brenes and Andrea Morales Fiesler, in their order judicial and extrajudicial representative of the ASADA of Residencial El Molino, Director of Gestión e Investigación Hídrica of the Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento, Mayor of Cartago and Director of the Área Rectora de Salud de Cartago, or to whomever holds those positions in their stead, personally.” That judgment was notified to the director UEN Gestión de ASADAS of the Instituto Costarricense de Acueductos y Alcantarillados on July 24, 2019, to the chief of the Oficina Regional del Este of the AyA and to the director of the Área Rectora de Salud de Cartago on July 29, 2019. Likewise, the judicial and extrajudicial representative of the ASADA of Residencial El Molino was notified on July 30, 2019, and the Mayor of Cartago received notification on July 31, 2019. Finally, on August 9, 2019, the resolution was notified to the director of Gestión e Investigación Hídrica of the Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento.
“III.- Regarding the petition of the Director UEN Gestión de ASADAS and the Chief of the Oficina Regional Central Este de Atención de ASADAS, both of the AyA. The petitioners Ramírez Villalba and Mesén Montenegro, in their order Director UEN Gestión de ASADAS of the AyA and Chief of the Oficina Regional Central Este de Atención de ASADAS of the AyA, request to supplement the operative part of the judgment on the merits of this amparo (No. 2019-13292 of 9:20 a.m. on July 19, 2019). In this line, they indicate that the Chamber ordered that, within a period of 6 months, the subscribers of the ASADA El Molino be supplied with water from a new well; however, they ask to add the caveat that this is conditional on it being technically feasible. In this context, they assert that there is still no certainty of the technical feasibility of the new well to supply Residencial El Molino, because it is in a pre-feasibility phase, where the hydrogeological study must be updated to establish the actual and effective depth required for drilling.
Additionally, the same petitioners request to supplement the judgment so that the municipality of Cartago is ordered to allow the AyA access to certain wells (IS-163 Lambert north coordinates E 544279 m, N 205053 m, IS-24 Lambert north coordinates E 544600 m, N 204800 m, IS-23 Lambert north coordinates E 544200 m, N 205055 m, IS-274 Lambert north coordinates E 544151 m, N 204348 m, IS-32 Lambert north coordinates E 543653 m, N 204675 m, and IS-495 Lambert north coordinates E 543790 m, N 204675 m), since access to these water bodies is fundamental for updating the hydrogeological study required prior to the drilling of the new well. Finally, they ask to supplement the judgment on the merits so that SENARA and MINAE are ordered to give priority and expeditious processing to the technical and administrative procedures required for the authorization of the drilling of the new well, its registration, and the corresponding allocation of water rights for the ASADA El Molino.
In this regard, it is necessary to emphasize that the supplementation of this Chamber’s judgments only proceeds when there is a need to complement an alleged point that was not analyzed in the ruling; however, this is not the case in the sub lite, since the arguments now raised in this subsequent petition were not put forward in a timely manner, that is, before the issuance of the judgment on the merits. In this sense, in the report rendered by the authorities of the AyA, it is noticeably absent that it was alleged that the drilling of the new well was conditioned on the results of an updated hydrogeological study to measure the actual depth required. On the contrary, from what was in the case file at the time of the issuance of the ruling on the merits, it was inferred that the well drilling process was very advanced and its technical feasibility was not questioned, to the point that, as indicated in the proven fact r) of judgment No. 2019-13292, since September 19, 2017, the respondent ASADA had already defined the exact drilling point and had even received quotes for the drilling.
Likewise, as reviewed in proven fact v), in April 2019, regarding the drilling, the ASADA was only awaiting the AyA's response to official letter AREM-273-2018 on the evaluation of the offers received. In the report rendered to this Chamber, it was also not alleged that, during all the years the problem of water contamination in the Residencial El Molino well has persisted, progress could not be made on the hydrogeological study because the Municipalidad de Cartago has not allowed the AyA access to certain wells in the area. Prior to the issuance of the judgment on the merits, this Chamber was also not asked, in the event that the appeal was granted, to order that SENARA and MINAE provide priority processing to the technical and administrative procedures required for the authorization of the drilling of the new well, its registration, and the corresponding allocation of water rights for the ASADA El Molino.
However, it is worth noting that, in the ordering part of judgment No. 2019-13292 of 9:20 a.m. on July 19, 2019, SENARA was ordered –specifically the Director of Gestión e Investigación Hídrica of the Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento– to give due follow-up to the provisions in the operative part of opinion No. UGH-248-16 of October 24, 2016, which established the need to close the current well at Residencial El Molino and determined the actions that institutions such as the AyA and the Municipalidad de Cartago should carry out in that regard. Furthermore, it is worth stating that in judgment No. 2019-13292, the Área Rectora de Salud de Cartago was also ordered to give due follow-up and oversee compliance with the current sanitary orders issued; moreover, should it be necessary, to issue new sanitary orders. In this context, in light of the orders given in the aforementioned judgment, the respondent authorities may coordinate among themselves –and, if necessary, with other competent authorities that were not procedural parties in this amparo– in order to comply with what was ordered by this Constitutional Court in the operative part of ruling No. 2019-13292 and thus resolve, in an integral and definitive manner, the problem of nitrate contamination in the water supplied to the residents of Residencial El Molino.
By virtue of the foregoing, it is improper to supplement the judgment on the merits regarding arguments that were not timely raised before this Court.
IV.Regarding the petitioner's petition. Royer Quesada Rojas, in his capacity as petitioner of the amparo processed in this file, asserts that the Municipalidad de Cartago has shown willingness to take over the operation, maintenance, and administration of the aqueduct currently operated by the ASADA of Residencial El Molino. By virtue of this, he considers that it is not necessary to drill a new well, nor to resume the dilution process for water extracted from the well that has been ordered closed, but rather to order that the Municipalidad de Cartago take over the operation, maintenance, and administration of the aqueduct of Residencial El Molino through interconnection with the municipal aqueduct.
In this regard, it is necessary to emphasize that, in considerando V of judgment No. 2019-13292 of 9:20 a.m. on July 19, 2019, the following was indicated:
‘V.- In another order of ideas, the petitioner requests that the drinking water service for the residents of Residencial El Molino be taken over by the aqueduct of the Municipalidad de Cartago. However, it is necessary to dismiss this request, since the authorities of the AyA report under oath that this is not technically feasible due to the water and hydraulic capacity of the area.’ Thus, it is inferred that what is now alleged by the petitioner is a disagreement with what was resolved by this Chamber. Ergo, the dismissal of this point is mandatory. (…)
Therefore:
The petitions are denied.” This resolution was notified to the respondent authorities on September 25, 2019.
“IV.- REGARDING THE PETITION OF DISOBEDIENCE. In this case, the petitioner states that, as of the date of filing the subsequent petition regarding judgment No. 2019-013292 of 9:20 a.m. on July 19, 2019, the respondent authorities have not complied with what was ordered by the Chamber, because the new well is still not operational; likewise, he requests that the Municipalidad de Cartago be ordered to supply the ASADA with drinking water service, and that the deadline not be extended. In this regard, it is noted that the Court ordered the authorities of the ICAA and the judicial and extrajudicial representative of the ASADA that ‘within a period of 6 months, counted from the notification of this ruling, the subscribers of the ASADA El Molino be supplied with drinking water from a new well that complies with the national potability standards for the liquid (…)’. (The highlighting is not from the original).
Now then, from the reading of the notification records added to the electronic file, it is extracted that the Director UEN Gestión de ASADAS and the Chief of the Oficina Regional Central del Este de Atención de ASADAS of the ICAA were notified on July 29, 2019, and that the judicial and extrajudicial representative of the ASADA of Residencial El Molino was notified on July 30, 2019, regarding judgment 2019-013292 of 9:20 a.m. on July 19, 2019. Thus, by virtue of the foregoing, as of the date the petitioner appeared before this Court, that is, November 15, 2019, the deadline to comply with what was ordered by the Chamber was still in effect. Therefore, the petition filed by the amparo beneficiary is premature for the date on which he filed it, and its rejection is mandated.
In the sub lite, it is noted that the authorities of the ICAA formulated a request for extension of the deadline granted by this Court; specifically, they request: ‘(…) to extend the deadline granted in judgment number 2019-013292 of nine hours twenty minutes on July nineteen, two thousand nineteen, by 12 months counted from the communication of the resolution rendered in this regard.’ Now then, from the records in the file, this Court notes that the request formulated by the respondent authorities was filed prior to the expiration of the deadline ordered by the Chamber.
Likewise, in this case, the Chamber verifies that, on August 21, 2019, geologist Cristina Castanedo Sotela of the Área Funcional de Hidrogeología of the UEN Gestión Ambiental del Recurso Hídrico of the Instituto Costarricense de Acueductos y Alcantarillados, conducted a ‘HYDROGEOLOGICAL STUDY WELL EL MOLINO, CARTAGO’, through which she concluded: ‘(…) 6. Based on the existing information, it is indicated that the problem of nitrates in the El Molino well is due to its structural conditions (…) and to the high nitrate content in the upper aquifer due to the presence of septic tanks. 7. From the hydrogeological point of view, the conditions of the deep aquifer and the results of the water quality analyses, it is recommended to carry out an exploration-production drilling of 150 m that captures the lower aquifer, provided that the isolation between the upper and lower aquifer is guaranteed during drilling. Additionally, the deep exploration-production drilling must guarantee the legal setbacks (…)’.
On the other hand, this Court holds as proven that the ASADA of Residencial El Molino and the ICAA held a meeting on October 3, 2019, in which they determined an action plan to follow in order to comply with the Chamber's order regarding the construction and drilling of the new well; however, they note that more time is required to fulfill it. It is indicated that 21 activities were established, of which 5 have already been resolved, namely: ‘i. Operating permit before the Ministry of Health: Follow-up for the granting of the operating permit for the ASADA El Residencial El Molino. AREM-383-2019; date October 1, 2019. ii. Delivery of the Hydrogeological Study to the ASADA: Official letter GSD-UEN-GAR-2019-04149. iii. Review of the recommendations of the Hydrogeological Study: Meeting minutes of October 3, 2019, between the ASADA, UEN Gestión de ASADA, and ORAC Central Este. iv. Analysis and Acceptance of the implementation of recommendations of the Hydrogeological Study: Meeting minutes of October 3, 2019, between the ASADA, UEN Gestión de ASADA, and ORAC Central Este. v. Determination of the route to follow regarding the protection zone: Official letter GSD-UEN-GAR-2020-00206’.
In addition to the foregoing, the Court verifies that the authorities of the ICAA, through memorandum GSD-UEN-GAR-2019-04376 of November 11, 2019, recorded that: ‘(…)d. This hydrogeological study prepared by the Hydrogeology unit of the UEN Gestión Ambiental determines the feasibility of drilling the new well for the definitive supply proposal for the Residencial El Molino aqueduct. e. As a result of the studies carried out, it was possible to determine that the well construction required works that do not allow communication between lithological strata and at a greater depth to ensure the water quality of the aquifer to be used; in other words, it generated the inputs to determine the characteristics of the well to be drilled.’ In relation to the actions carried out by the respondent authorities, SENARA, in the report rendered under oath, stated that on August 26, October 24, and November 21, all in 2019, several meetings were held, in which it was defined that the current well must be sealed and a new one drilled that does not capture the upper aquifer, and that, in addition, follow-up will be given to the drilling and water analysis processes.
For its part, it is verified that, on January 17, 2020, an engineer from the Oficina Regional Acueducto Comunales Central Este of the UEN Gestión de Acueductos Rurales sent official letter GSD-UEN-GAR-2020-00206 to the Coordinator of the Unidad Hidrogógica Caribe of the Dirección de Aguas of the Ministerio de Ambiente y Energía, in which he requested to schedule a visit to analyze the conditions and compliance with the minimum setbacks required for the drilling of a deep well that would allow the supply of the Residencial el Molino community.
In addition to the foregoing, the Court verifies that, in January 2019, the ASADA requested ‘HIDROAMBIENTE Consultores’ to carry out a ‘HYDROGEOLOGICAL INVESTIGATION REPORT-DESCRIPTION OF PIEZOMETER AND ANALYSIS OF NITRATE CONTENT, EL MOLINO DE CARTAGO’. In this study, a well construction proposal for a new well was made that seeks to mitigate the intake of nitrates. This report indicated that: ‘(…) the construction proposal for the definitive well is made, considering protection by means of a forewell and a concrete seal from 0 to 50 meters deep (…) and the extension of the well is proposed between 90 and 120 meters (…)’.
Based on the foregoing, this Court considers that the respondent authorities have proceeded to deploy the pertinent actions in order to comply with what was ordered by the Chamber through judgment No. 2019-013292 of 9:20 a.m. on July 19, 2019, in which it was ordered: ‘(…) It is ordered to José Rodolfo Ramírez Villalba, Vladimir Mesén Montenegro and Carlos Eduardo Aguilar Quesada, in their order Director UEN Gestión de ASADAS of the Instituto Costarricense de Acueductos y Alcantarillados, Chief of the Oficina Regional Central del Este de Atención de ASADAS of the Instituto Costarricense de Acueductos y Alcantarillados, and judicial and extrajudicial representative of the ASADA of Residencial El Molino, or to whomever holds those positions in their stead, to carry out the necessary procedures and coordination, within the scope of their powers, so that within a period of 6 months, counted from the notification of this ruling, the subscribers of the ASADA El Molino be supplied with drinking water from a new well that complies with the national potability standards for the liquid. (…)’.
In addition to the foregoing, although the Acting Director of the Área Rectora de Salud de Cartago indicated in report MS-DRRSCE-ARSC-0094-2020 that, in response to official letter DRRSCE-ARSC-IT-1148-2019 of September 23, 2019, it was determined that the ASADA El Molino was non-compliant with the nitrate parameter for the month of July 2019, it is no less true that she also reported that, as of July 19, 2019, the water dilution process began to be implemented through the installation of a pipe by the Municipalidad de Cartago. Thus, through technical reports No. DRRSCE-ARSC-IT-1149-2019, DRRSCE-ARSC-IT-1315-2019, MS-DRRSCE-ASRC-IT-0191-2020, MS-DRRSCE-ASRC-IT-0125-2020, MS-DRRSCE-ASRC-IT-0126-2020 and MS-DRRSCE-ASRC-IT-0192-2020, issued by the Centro de Investigación y de Servicios Químicos y Microbiológicos (CEQUIATEC) of the Instituto Tecnológico de Costa Rica, it was determined that the analyses of nitrate levels for August, September, October, November, and December, all of 2019, as well as January 2020, complied with the nitrate parameter.
On the other hand, the Minister of Health reports that it was determined that in the last four reports, the ASADA El Molino only provided three of the four samples required by sanitary order CE-ARSC-OS-0323-2017, by virtue of which sanitary order No. MS-DRRSCE-ARSC-OS-0020-2020 was issued, notified to the respondent ASADA on February 14, 2020, through which it was requested: ‘To carry out monthly laboratory analyses of the water quality in the supply system for the nitrate parameter, which include a measurement in the well, the diluted water storage tank, and 4 samples in the distribution network, taken in subscribers' homes starting from the month of February of this year; these analyses must be performed by a laboratory authorized by the Ministry of Health’.
Notwithstanding the foregoing, from the report rendered by the Minister of Health and the Director of the Área de Salud de Cartago, it was determined that: ‘As long as the dilution in the drinking water tank by the Municipalidad de Cartago is maintained and monthly samplings are carried out and reported to the Área Rectora de Salud de Cartago, there would be no impact on the users of Asada El Molino during the extension of the deadline for the construction of the new well’.
As indicated in judgment No. 2019-018328 of 9:30 a.m. on September 24, 2019; ‘from what was in the case file at the time of the issuance of the ruling on the merits, it was inferred that the well drilling process was very advanced and its technical feasibility was not questioned, to the point that, as indicated in proven fact r) of judgment No. 2019-13292, since September 19, 2017, the respondent ASADA had already defined the exact drilling point and had even received quotes for the drilling. Likewise, as reviewed in proven fact v), in April 2019, regarding the drilling, the ASADA was only awaiting the AyA's response to official letter AREM-273-2018 on the evaluation of the offers received.’ However, the respondent authorities now claim that a series of technical studies and the approval of prior permits by various state entities are needed in order to drill the new well at Residencial El Molino.
By virtue of the arguments put forward by the respondents, and taking into consideration the response from the Ministry of Health in the sense that an extension of the deadline would not affect the health of the residents if the dilution process continues, this Chamber deems it reasonable to grant the respondents a 6-month extension, counted from the notification of this judgment, so that the subscribers of the ASADA El Molino be supplied with drinking water from a new well that meets the national potability standards for the liquid. (…)
Therefore:
The deadline granted in judgment No. 2019-013292 of 9:20 a.m. on July 19, 2019, is extended, and José Rodolfo Ramírez Villalba, Vladimir Mesén Montenegro and Carlos Eduardo Aguilar Quesada, in their order Director UEN Gestión de ASADAS of the Instituto Costarricense de Acueductos y Alcantarillados, Chief of the Oficina Regional Central del Este de Atención de ASADAS of the Instituto Costarricense de Acueductos y Alcantarillados, and judicial and extrajudicial representative of the ASADA of Residencial El Molino, or whomever holds those positions in their stead, are granted an additional period of 6 months, counted from the notification of this judgment, to comply with what was ordered in judgment No. 2019-013292 of 9:20 a.m. on July 19, 2019, solely in relation to the commencement of the supply of drinking water from a new well that complies with the national potability standards for the liquid to the subscribers of the ASADA El Molino, under the same warnings.
In all other respects, the formulated petition is denied. Let this ruling be notified to José Rodolfo Ramírez Villalba and Vladimir Mesén Montenegro, in their order Director UEN Gestión de ASADAS and Chief of the Oficina Regional Central del Este de Atención de ASADAS, both of the Instituto Costarricense de Acueductos y Alcantarillados; to Carlos Eduardo Aguilar Quesada, judicial and extrajudicial representative of the ASADA of Residencial El Molino, and to Manuel Badilla Sánchez, in his capacity as Mayor of Cartago, or to whomever holds those positions, personally.” This ruling was notified to the respondent authorities on March 6, 2021.
In the sub lite, the petitioner raises a petition of disobedience in relation to judgment No. 2019-013292 of 9:20 a.m. on July 19, 2019. He states that in September 2020, the extended deadline that this Chamber granted to the respondents to comply with what was ordered expired. He maintains that he has provided the file with various documentation proving that the Municipalidad de Cartago has the capacity to provide the drinking water service to the residential community in a more economical and faster manner. He refers that the feasibility of such a circumstance is demonstrated because there is an interconnection through which water is diluted to reduce contaminants. He alludes that keeping the well open threatens the principle of a healthy and ecologically balanced environment. He requests that the immediate closure of the well be ordered and that the Municipalidad de Cartago be ordered to take over the service immediately and directly. He asks that what was ordered in judgment No. 2019-013292 of 9:20 a.m. on July 19, 2019, be complied with.
In this regard, it is worth mentioning that in the sub iudice, various orders were issued, namely: “It is ordered to José Rodolfo Ramírez Villalba, Vladimir Mesén Montenegro and Carlos Eduardo Aguilar Quesada, in their order Director UEN Gestión de ASADAS of the Instituto Costarricense de Acueductos y Alcantarillados, Chief of the Oficina Regional Central del Este de Atención de ASADAS of the Instituto Costarricense de Acueductos y Alcantarillados, and judicial and extrajudicial representative of the ASADA of Residencial El Molino, or to whomever holds those positions in their stead, to carry out the necessary procedures and coordination, within the scope of their powers, so that within a period of 6 months, counted from the notification of this ruling, the subscribers of the ASADA El Molino be supplied with drinking water from a new well that complies with the rational potability standards for the liquid.
Likewise, immediately, they must undertake and coordinate whatever is necessary so that, within a maximum period of 15 days counted from the notification of this judgment, the dilution process of the water from the current well at Residencial El Molino be resumed, as a temporary measure while the new well becomes operational. In turn, Roberto Ramírez Chavarría, in his capacity as Director of Gestión e Investigación Hídrica of the Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento, or whomever holds the position, is ordered to give due follow-up to the provisions in the operative part of opinion No. UGH-248-16 of October 24, 2016. On the other hand, Andrea Morales Fiesler, in her capacity as Director of the Área Rectora de Salud de Cartago, or whomever holds the position, is ordered to give due follow-up and oversee compliance with the current sanitary orders issued; moreover, should it be necessary, to issue new sanitary orders.
Finally, Rolando Rodríguez Brenes, in his capacity as Mayor of Cartago, or whomever holds the position, is ordered to issue the necessary directives within the scope of his powers so that, within a period of 2 months counted from the notification of this judgment, the municipality renders a report on the current cantonal territorial planning regulations in relation to the protection zones of the aquifers and on the current compliance with said regulations in the sector of Residencial El Molino and surrounding areas. Likewise, he must coordinate whatever is necessary so that the pertinent measures are taken in light of the results of this report, which must be notified to the Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento, the ASADA El Molino, and the Instituto Costarricense de Acueductos y Alcantarillados”.
Now then, given that what is alleged by the petitioner only concerns the supply of drinking water from the supply well, and such order was issued to the director UEN Gestión de ASADAS of the Instituto Costarricense de Acueductos y Alcantarillados, the chief of the Oficina Regional Central del Este de Atención de ASADAS of the Instituto Costarricense de Acueductos y Alcantarillados, and the judicial and extrajudicial representative of the ASADA of Residencial El Molino, only the situation pertaining to these respondent entities is analyzed.
Having clarified the foregoing, in the first place, it is inferred from the case file that the respondents have implemented what corresponds to the temporary measure of dilution of water from the current well at Residencial El Molino, and therefore, no disobedience is observed on this point.
Now then, from the respondents' own statements, it is extracted that, to date, what was ordered by the Chamber has not been complied with regarding that ‘within a period of 6 months, counted from the notification of this ruling, the subscribers of the ASADA El Molino be supplied with drinking water from a new well that complies with the rational potability standards for the liquid’. In this regard, the respondents report that, prior to the granting of the respective permit for the drilling of the new well, it is necessary for the Municipalidad de Cartago to transfer to the ASADA El Molino the lands on which it will be carried out, and that this legal process has prevented progress with what was ordered by this Chamber.
In this sense, it is observed that the authorities of the ICAA indicated that although the possibility of constructing a new well was considered discarded due to the situation described above and the possibility was analyzed that the ICAA itself take over the direct provision of the drinking water service to the community of Residencial El Molino, or that another operating entity do so, it is no less true that in the last report rendered on the occasion of the evidence for a better decision ordered by this Court, the respondents explained that significant progress has been made regarding the petition for the Municipality to transfer the properties to the ASADA El Molino. In this sense, they explain that for these purposes, bill No. 22.556 “DESAFECTACIÓN DEL USO PÚBLICO DE TERRENOS PROPIEDAD DE LA MUNICIPALIDAD DE CARTAGO PARA QUE LOS DONE A LA ASOCIACIÓN ADMINISTRADORA ACUEDUCTO Y ALCANTARILLADO EL MOLINO” was introduced before the Asamblea Legislativa, published in Gaceta No. 137 of July 16, 2021.
It was indicated: “THE LEGISLATIVE ASSEMBLY OF THE REPUBLIC OF COSTA RICA DECREES: DESAFECTACIÓN DEL USO PÚBLICO DE TERRENOS PROPIEDAD DE LA MUNICIPALIDAD DE CARTAGO PARA QUE LOS DONE A LA ASOCIACIÓN ADMINISTRADORA ACUEDUCTO Y ALCATARILLADO EL MOLINO ARTICLE 1- The following lands owned by the Municipalidad de Cartago, legal identification number three – zero fourteen – zero forty-two thousand eighty, registered in the Cartago district, are hereby removed (desaféctese) from public use: - Property 97469-000, NATURE: LOT 21 TO BUILD BLOCK J, BOUNDARIES: NORTH: LOT 22, SOUTH: LOT 20, EAST: STREET WITH 12 M 50 CM, WEST: STREET WITH 12 M 50 CM, MEASURES: TWO HUNDRED THIRTY-SIX METERS WITH SEVENTEEN SQUARE DECIMETERS, PLAN: NONE INDICATED, OWNER: GRUPO INVE SOCIEDAD ANONIMA (sic) LEGAL (sic) ID (sic) 3-101-039661. DOMAIN OWNER.
- Property: 97471-000, NATURE: GREEN AREA (sic) WITH WELL AND DRINKING WATER STORAGE TANK BLOCK J LOT TWENTY-TWO (sic), BOUNDARIES: NORTH: LOT 23, SOUTH: LOT 21, EAST: STREET WITH 20 M 86 CM, WEST: EL MOLINO SOCIEDAD CAFETALERA, MEASURES: TWO HUNDRED SEVENTY-EIGHT POINT NINETY-FIVE SQUARE METERS (sic) PLAN: NOT INDICATED. OWNER: GRUPO INVE SOCIEDAD (sic) ANONIMA (sic) LEGAL IDENTITY CARD (sic) 3-101-039661. DOMAIN OWNER. - Property: 97473-000, NATURE: LOT 23 FOR CONSTRUCTION BLOCK J, BOUNDARIES: NORTH: EL MOLINO SOCIEDAD CAFETALERA SOUTH: LOT 22 EAST: STREET WITH 29 M 50 CM WEST: EL MOLINO SOCIEDAD CAFETALERA. MEASURES: THREE HUNDRED SEVENTY-SIX POINT SEVENTY SQUARE METERS (sic). PLAN: NOT INDICATED. OWNER: GRUPO INVE SOCIEDAD ANONIMA (sic) LEGAL IDENTITY CARD (sic) 3-101-039661. DOMAIN OWNER. ARTICLE 2- The Municipality of Cartago is authorized to donate the lots removed from public use in the preceding article to the Asociación Administradora Acueducto y Alcantarillado El Molino, legal identity card 3-002-565237, to be used exclusively for the Water Supply System (Acueducto) of the El Molino urbanization.
In the event that the original use of the property is changed or the beneficiary legal entity is dissolved, ownership of the donated lands shall revert to the Municipality of Cartago. ARTICLE 3- The State Notary’s Office is authorized to proceed to formalize and register this donation in the Public Registry, with no estimated value, which includes the removal of the mortgage liens appearing in its registry entries under the citations: Property 97469-000 citations: mortgage 331-05005-01-0889, mortgage 331-05005-01-0890-001, mortgage 331-05005-01- 0890-001, mortgage 331-05005-01-0891-001, 331-05005-01- 0892-001. Property 97471, citations: mortgage 331-05005-01-0865-001, mortgage 331-05005-01-0866-001, mortgage 331-05005-01-867-001, mortgage 331-0505-01-868-001, filed citations: 575-50395-01-003-001, Juzgado Civil de Menor Cuantía de Cartago, case file 08-000485-0346-CI. Property 97473-000 citations: mortgage 331-05005-01-0852-001, mortgage 331-05005-01-0853-001, mortgage 331-05005-01-0919-001, mortgage 331-05005-01-0921-001. Its registration shall be exempt from the payment of fees and all types of duties and stamps. It takes effect upon its publication. (...)”.
Furthermore, in the technical report MS-DRRSCE-ARSC-IT-0913-2021 of August 10, 2021, signed by the Health Regulation official of the Governing Health Area (Área Rectora de Salud), it is noted that the ASADA has complied with the regulatory nitrate levels; additionally, it stated: “(…) regarding the current situation of the water supplied to the residents of Residencial El Molino, the Governing Area of Cartago (Área Rectora de Cartago), in its governing role of monitoring and oversight (Table 1) of administrative acts, remains vigilant with the monthly review of drinking water quality reports, evidencing that the results presented during the year 2021 comply with the values indicated in Chart 4. Water Quality Parameters Level Three (N3): Nitrate; Alert Value (25mg/l) and Maximum Allowable Value (50mg/l) of Decree No. 38924-s, Regulation for Drinking Water Quality (Reglamento para la Calidad de Agua Potable). (…) in this regard, the Ministry of Health granted approval for dilution as a temporary measure at the time, anticipating that the definitive solution to the nitrate problem would be partially resolved, pending the construction of the new well (…)”.
In addition, in the sub examine, it is also observed that the authorities of the ICAA request that this Court grant them a reasonable period to provide a comprehensive solution for the drinking water supply for the community.
Now then, from this perspective, the Chamber acknowledges that the respondent authorities have carried out actions aimed at following up on the corresponding procedures for compliance with what was ordered by this Court; however, the deadlines granted have been insufficient. Thus, in view of the arguments put forth by the respondents, and taking into consideration the Ministry of Health’s response to the effect that the results for the nitrate parameter in the water supplied in the distribution network of the Asada El Molino’s water supply system, through the dilution process, fall within the permitted alert value (25mg/l) and maximum allowable value (50 mg/l), complying with the provisions of Decree No. 38924-S, this Chamber deems it appropriate to dismiss the non-compliance proceeding and instead grant the respondents an extension of 6 more months, counted from the notification of this ruling, to resolve, in a comprehensive and definitive manner, the problem of nitrate contamination in the water supplied to the residents of Residencial El Molino.
However, this extension is granted under the warning that, if the construction of a new supply well is not possible within the granted period, the respondent authorities must adopt the corresponding measures to definitively resolve the problem subject to this appeal.
V.Finally, the appellant states that they have provided to the case file various documentation demonstrating that the Municipality of Cartago has the capacity to provide drinking water service to the residential area in a more economical and faster manner; furthermore, that the feasibility of such circumstance is demonstrated because there is an interconnection through which the water is diluted to reduce contaminants. Consequently, they request that the Municipality of Cartago be ordered to assume the service immediately and directly.
In this regard, it is necessary to highlight that this point was already resolved in Considerando V of ruling No. 2019-13292 of 9:20 a.m. on July 19, 2019, which stated the following: “V.- In another vein, the appellant requests that the drinking water service for the residents of Residencial El Molino be assumed by the water supply system of the Municipality of Cartago. However, this petition must be dismissed, since the authorities of the AyA report under oath that this is not technically viable due to the hydraulic and water capacity of the zone.” Thus, it is inferred that what the appellant is now alleging is a disagreement with what was resolved by this Chamber. Ergo, dismissal regarding this point is required. Ergo, it is appropriate to dismiss the action brought concerning this point.
The parties are warned that if they have provided any paper document, as well as objects or evidence contained in any additional electronic, computer, magnetic, optical, telematic device or one produced by new technologies, these must be retrieved from the office within a maximum period of 30 business days counted from the notification of this ruling. Otherwise, any material not retrieved within this period will be destroyed, as provided in the “Regulation on the Electronic Case File before the Judicial Branch” (Reglamento sobre Expediente Electrónico ante el Poder Judicial), approved by the Full Court in session No. 27-11 of August 22, 2011, article XXVI and published in Judicial Bulletin number 19 of January 26, 2012, as well as in the agreement approved by the Superior Council of the Judicial Branch, in session No. 43-12 held on May 3, 2012, article LXXXI.
Therefore:
The deadline granted in ruling No. 2019-013292 of 9:20 a.m. on July 19, 2019, is extended, and José Rodolfo Ramírez Villalba and Vladimir Mesén Montenegro, in their order as director UEN Gestión de ASADAS and head of the Oficina Regional Central del Este de Atención de ASADAS, both of the Instituto Costarricense de Acueductos y Alcantarillados; as well as Luis Paulino Méndez Badilla, in his capacity as president of the ASADA of Residencial El Molino, or whoever holds those positions, are granted a period of 6 more months, counted from the notification of this ruling, to comply with what was ordered in ruling No. 2019-013292 of 9:20 a.m. on July 19, 2019, solely regarding the commencement of supplying the subscribers of the ASADA El Molino with drinking water from a new well that meets the national standards for water potability, and under the warning that they must adopt the necessary measures to resolve, in a comprehensive and definitive manner, the water problem supplied to the residents of Residencial El Molino, should any impossibility to complete the aforementioned well within the aforementioned period be projected.
In all other respects, the action brought is dismissed. Let this pronouncement be notified personally to José Rodolfo Ramírez Villalba and Vladimir Mesén Montenegro, in their order as Director UEN Gestión de ASADAS and Head of the Oficina Regional Central del Este de Atención de ASADAS, both of the Instituto Costarricense de Acueductos y Alcantarillados; to Luis Paulino Méndez Badilla, president of the ASADA of Residencial El Molino, or to whoever holds those positions.
Paul Rueda L.
Acting President Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Marta Eugenia Esquivel R.
Ana María Picado B.
Ileana Sánchez N.
CASE FILE No. 19-006036-0007-CO Telephones: 2549-1500 / 800-SALA-4TA (800-7252-482). Fax: 2295-3712 / 2549-1633. Email address: www.poder-judicial.go.cr/salaconstitucional. Address: (Sabana Sur, Calle Morenos, 100 mts.Sur de la iglesia del Perpetuo Socorro). Reception of matters from vulnerable groups: Edificio Corte Suprema de Justicia, San José, Distrito Catedral, Barrio González Lahmann, calles 19 y 21, avenidas 8 y 6 It is a faithful copy of the original - Taken from Nexus.PJ on: 09-05-2026 09:46:20.
SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas quince minutos del veinte de agosto de dos mil veintiuno .
Gestión posterior planteada por ROYER ALEXANDER QUESADA ROJAS, en relación con la sentencia n.° 2019-013292 de las 9:20 horas del 19 de julio de 2019.
Resultando:
Alude que el SENERA ha realizado las siguientes actividades:
ACTIVIDAD RESPONSABLE OBSERVACIONES 1. “Para el caso del pozo El Molino y por considerarse como un posible foco de contaminación de las aguas subterráneas, en el consecutivo OFICIO No. UGH-248-16 del 24 de octubre de 2016 se le indicó a la Municipalidad de Cartago, AyA, Ministerio de Salud y ASADA El Molino y Señor Alejandro Monge Ariño, que debe procederse al cierre y sellado y emplear otra fuente de abastecimiento.
Municipalidad de Cartago, AyA, Ministerio de Salud y ASADA Residencial El Molino. No se ha realizado el sellado del pozo, la propuesta es realizar una perforación nueva y sustituir la existente y captar el acuífero más profundo. Actividad que está en proceso. A SENARA no se ha presentado la propuesta No se ha realizado el sellado del pozo, la propuesta es realizar una perforación nueva y sustituir la existente y captar el acuífero más profundo. Actividad que está en proceso. A SENARA no se ha presentado la propuesta de la nueva perforación del subsuelo, dado que según oficio AREM-436- 2020, la solicitud de perforación no fue admitida a partir del estudio de admisibilidad según gestión No. 202000378, indicando tres aspectos a subsanar.
2. En el proceso de cierre y sellado, debe de contemplarse si el mismo requiere de alguna zona cercana que requiere dejarse de protección.
Municipalidad de Cartago, AyA, Ministerio de Salud, SENARA y ASADA El Molino No se ha definido el cierre del pozo. Mediante nota oficio SENARA-DIGH UI-INF- 100-2020 se da por aprobado el Modelo Conceptual Hidrogeológico de la parte Norte del Cantón Central de Cartago, el cual contempla la zona de protección del pozo de la ASADA Residencial El Molino. No obstante, la existencia de dicha zona de protección no descarta la realización del cierre del pozo, dados los fundamentos técnicos indicados en el oficio UGH-248-2016 donde se justifica la amenaza a la salud pública que dicho pozo representa, por altos niveles de nitratos, nivel superior muy superficial, presencia de casas con tanques sépticos dentro de la zona de protección y un armado inadecuado que propicia la contaminación de los dos acuíferos que capta al ponerlos en comunicación hidráulica.
3. Plan remedial debe ser presentado por ASADA y A y A ASADA el Molino y A y A En las últimas reuniones relacionadas con el caso de marras, se definió que el plan remedial presentado por la Asada y el AyA tenía un plazo de 10 meses a un año, sin embargo por cuestionamientos del Ministerio de Salud y recomendación del abogado de la Municipalidad de Cartago, debían ajustar el plan remedial al plazo de la Sala, el cual correspondía a dos meses o bien solicitar la respectiva prorroga a la Sala, en la última reunión se tenía adelantado algunos trámites para la construcción del pozo, sin embargo, realizarían la solicitud de prórroga respectiva y en el momento que se tenga respuesta serían ellos quienes convocarían a reunión.
Asevera que se mantienen los criterios establecidos en los oficios UGH-248-16, DIGH-329-2016, SENARA-DIGH-121-2018, SENARA-DIGH-075-2019, SENARA-DIGH-001-2020 y seguimiento, SENARA-DIGH-UGSA- 137-2020, SENARA-DIGH-UGH-138-2020, en cuanto al cierre y sellado del pozo de la ASADA Residencial El Molino, así como otros aspectos que se mencionen en las conclusiones de cada uno de estos oficios en relación con la protección y manejo adecuado de los acuíferos en el sector donde se ubica tal pozo.
Redacta la Magistrada Sánchez Navarro; y,
Considerando:
En la sentencia n.° 2019-013292 de las 9:20 horas del 19 de julio de 2019, se dispuso:
“IV.- Sobre el caso concreto. El recurrente alega que adquirió un inmueble en El Residencial El Molino y actualmente alquila otro en el mismo barrio. Acusa que la ASADA recurrida le denegó el servicio de agua potable para su nueva propiedad, con el argumento de que los nuevos servicios y disponibilidades se encontraban suspendidos en virtud de la directriz del AyA n.° UEN-GAR-2017- 00359. Alega que dicha directriz atiende a la orden de cierre que pesa desde el año 2016 sobre el pozo que actualmente opera la ASADA recurrida, por la contaminación de nitratos en el agua. Reclama que, pese al trascurso del tiempo, el pozo continúa operando, atentando contra la salud de los abonados. Pide que se cierre inmediatamente dicho pozo.
Del estudio de los autos, se acredita que, mediante oficio PRE-LNA-2014- 1071 del 24 de noviembre de 2014, el Laboratorio de Aguas del AyA le informó a la ASADA recurrida sobre los niveles altos de nitrato en el agua de la ASADA y recomendó evaluar fuentes alternativas. Un año después, mediante orden sanitaria n.° CE-ARSC-OS-302-2015 del 13 de octubre de 2015, el Ministerio de Salud ordenó a la ASADA recurrida presentar un cronograma para solucionar permanentemente dicho problema y llevar a cabo una campaña de divulgación en la comunidad para que los niños menores de 1 año no consumieran el líquido. En consecuencia, mediante boletín AREM 151-15 del 14 de octubre de 2015, la ASADA accionada informó a sus abonados que, con base en el oficio CE-ARSC-2400-2015 del Ministerio de Salud, “como medida precautoria” ante los niveles de nitratos detectados, se solicitaba que los menores de un año de edad no consumieran el agua suministrada por la ASADA. Ese mismo mes, el AyA elaboró un estudio hidrogeológico del Pozo del Residencial El Molino.
Ulteriormente, mediante oficio n.° UGH-248-16 del 24 de octubre de 2016, el SENARA rindió un dictamen detallado sobre el pozo que abastece el Residencial El Molino y concluyó que este debía cerrarse y emplearse otra fuente de abastecimiento del líquido, toda vez que se había constatado un índice de contaminación por nitratos por encima de los valores máximos establecidos y con valores en ascenso desde el año 2009. Además, se evidenció un armado inadecuado del pozo, lo que causa comunicación hidráulica entre los acuíferos superior e inferior (las aguas contaminadas superiores se filtran hacia el acuífero inferior). Asimismo, se constató la vulnerabilidad del pozo, pues “la zona de protección del pozo se encuentra invadida por casas con tanques sépticos con un incremento de viviendas desde el año 2017 lo que genera una mayor carga de nitratos”. En virtud de todo ello, el SENARA solicitó al Ministerio de Salud y al AyA “el cierre del pozo por el alto riesgo a la salud pública” y se ordenó que la ASADA lo sellara con arcilla y cemento y notificara al SENARA la fecha de clausura con el fin de que se hiciera presente un funcionario de dicha institucional estatal.
Otrosí, el SENARA recomendó al AyA y a la Municipalidad de Cartago analizar el acuífero y determinar el alcance de nuevas medidas regulatorias y mitigación; lo anterior, debido al impacto que el acelerado desarrollo urbano y el uso de tanques sépticos ha causado en los acuíferos.
En mérito del dictamen del SENARA, mediante oficio AREM-2010-16 del 15 de diciembre de 2016, la ASADA le indicó a dicha institución que, a fin de resolver el problema de abastecimiento de agua potable en el Residencial El Molino, se iniciarían las gestiones para perforar un nuevo pozo y se sellaría el pozo existente. Asimismo, mediante directriz UEN-GAR-2017-359 del 2 de febrero de 2017, la Oficina Regional de Sistemas Comunales del AyA comunicó a la ASADA accionada que, en virtud de la solicitud de cierre del pozo por parte del SENARA, se recomendaba no otorgar cartas de disponibilidad y nuevos servicios hasta tanto la Subgerencia de Sistemas Comunales no se pronunciara al respecto. También con fundamento en el informe técnico n.° UGH-248-2016 del SENARA, el Ministerio de Salud, mediante orden sanitaria n.° CE-ARSC-OS-136-2017 del 11 de mayo de 2017, ordenó a la ASADA de El Molino que presentara un plan remedial para asegurar el abastecimiento de agua potable que cumpliera los parámetros establecidos reglamentariamente.
En consecuencia, el 25 de mayo de 2017, la ASADA presentó ante el Ministerio de Salud el plan de acciones correctivas y el cronograma para la sustitución del pozo de agua potable en El Molino. Posteriormente, por oficio CE-URS-551-2017 del 30 de junio de 2017, el Ministerio de Salud indicó que los problemas por contaminación con nitratos en el agua de la ASADA El Molino datan desde el año 2010 y se concluyó que el plan remedial presentado por la ASADA tenía un plazo de ejecución razonable de 349 días para la puesta en operación del nuevo pozo; además, se señaló que este estaba científica y técnicamente fundamentado en un estudio técnico. Sin embargo, luego, mediante orden sanitaria n.° CE-ARSC-OS-282-2017 del 24 de julio de 2017, el Ministerio de Salud ordenó a la ASADA ampliar el plan remedial propuesto a fin de incluir una solución inmediata que asegurara la calidad de agua para los abonados, mientras se construye el nuevo pozo.
En consecuencia, por oficio AREM-238-2017 del 10 de agosto de 2017, la ASADA recurrida presentó ante el Ministerio de Salud la ampliación del plan remedial e indicó que, como medida temporal mientras se perfora el nuevo pozo, se realizaría –por recomendación del Laboratorio Nacional de Aguas del AyA– un proceso de dilución del agua del pozo con agua libre de nitratos; lo anterior, a fin de disminuir la concentración de los compuestos químicos inorgánicos en el líquido.
Ulteriormente, mediante oficio CE-ARSC-R-1096-2017 del 28 de agosto de 2017, el Ministerio de Salud concluyó que la ASADA había cumplido con la orden sanitaria n.° CE-ARSC-OS-282-2017 y recomendó aprobar el proceso de dilución propuesto por la ASADA. No obstante, el 4 de setiembre de 2017, mediante orden sanitaria n.°CE-ARSC-OS-323-2017, el Ministerio de Salud ordenó a la ASADA recurrida presentar un cronograma del plan remedial de construcción y habilitación del nuevo pozo, realizar análisis mensuales de laboratorio sobre la calidad de agua y presentar avances trimestrales del cumplimiento del cronograma de la construcción del pozo.
En este contexto, mediante oficio AREM-248-17 recibido el 19 de setiembre de 2017, la ASADA recurrida informó al Área Rectora de Salud de Cartago que ya se había puesto en marcha la campaña de divulgación, se había definido el punto exacto de la perforación, diseñado el nuevo pozo, invitado a las empresas oferentes y recibido cotizaciones para la perforación. Otrosí, se indicó que quedaba pendiente la adjudicación y firma del contrato, tramitar los permisos para perforar, instalación de los equipos, perforación, análisis de la calidad de agua, desarrollo del pozo, pruebas de bombeo, instalación del equipo permanente, puesta en operación del nuevo pozo y sellado del pozo actual. Además, se señaló que se habían gestionado muestreos mensuales de agua a través del Instituto Tecnológico de Costa Rica. Finalmente, en el mismo oficio, la ASADA se comprometió a presentar informes trimestrales del cumplimiento del cronograma de construcción del pozo.
Ahora bien, sobre el proceso de dilución, consta en autos el oficio AREM-361-2019 del 2 de abril de 2019, mediante el que la ASADA recurrida informó al Área Rectora de Salud de Cartago que, desde el 31 de enero de 2019, la Municipalidad de Cartago había suspendido unilateralmente el servicio de agua para dilución, por lo que el 12 de febrero de 2019 se había solicitado al municipio reanudar el servicio hasta la que se concretara la perforación del nuevo pozo. Sin embargo, por otro lado, el Área Rectora de Salud informa que el proceso de dilución está suspendido desde abril de 2019. Así las cosas, independientemente de la fecha de suspensión, lo cierto es que se acredita que, actualmente, ya no se está diluyendo el agua del pozo del Residencial El Molino con agua no contaminada del acueducto de Cartago.
Finalmente, se aprecia que, en cumplimiento de la orden sanitaria n.°CEARSC-OS-323-2017, la ASADA recurrida, a través del Instituto Tecnológico de Costa Rica, ha estado realizando muestreos al agua del pozo del Residencial El Molino y remitiendo los resultados al Área Rectora de Salud de Cartago. Conforme muestreo tomado el 8 de abril de 2019, en un parámetro de 50 como valor máximo admisible, el agua del residencial presentaba un valor de 53±5 de nitratos y, según muestreo del 13 de mayo de 2019, el líquido presentaba un valor de 54±4, por lo que, conforme lo informado por el Ministerio de Salud, se superaban los niveles máximos permitidos.
Así las cosas, a la luz del cuadro fáctico esgrimido, se demuestra que si bien el AyA (en su condición de ente rector del servicio de agua potable y saneamiento) y la ASADA recurrida han llevado a cabo diferentes diligencias ante la problemática de los nitratos en el agua del pozo del Residencial El Molino, lo cierto es que no se ha actuado eficientemente, toda vez que el problema aún no se ha resuelto, pese a que consta que, desde el año 2014, el Laboratorio de Aguas del AyA conoce de la situación y le informó al respecto a la ASADA accionada.
Por otro lado, también se observa que el Ministerio de Salud ha emitido diversas órdenes sanitarias y oficios en relación con el problema de la concentración de nitratos en el agua del Residencial El Molino. Sin embargo, se verifica que a la situación no se le ha dado una fiscalización y seguimiento eficiente, toda vez que se echa de menos que el Área Rectora de Salud haya reaccionado eficazmente ante la demora por parte de la ASADA en relación con el cumplimiento del cronograma del plan remedial. En este sentido, consta que mediante oficio CE-URS-551-2017 del 30 de junio de 2017, el Ministerio de Salud concluyó que el plan remedial presentado por la ASADA tenía un plazo de ejecución razonable de 349 días para la puesta en operación del nuevo pozo. Empero, más de dos años después, la construcción del nuevo pozo ni siquiera se ha iniciado. Tampoco se observan acciones concretas por parte del Ministerio de Salud en relación con la suspensión de la dilución del agua del pozo con líquido proveniente del acueducto municipal de Cartago, pese a que dicha medida atiende al cumplimiento de la orden sanitaria n.° CE-ARSC-OS-282-2017 del 24 de julio de 2017, que exigió una solución inmediata que asegurara la calidad de agua para los abonados actuales de la ASADA, mientras se construye el nuevo pozo.
De otra parte, se aprecia que el SENARA, desde el año 2016, rindió un pronunciamiento técnico que concluyó que el pozo del Residencial El Molino debía cerrarse y emplearse otra fuente de abastecimiento del líquido en virtud del índice de contaminación por nitratos con valores en ascenso desde el año 2009. Además, se evidenció un armado inadecuado del pozo que causa comunicación hidráulica entre los acuíferos superior e inferior (las aguas contaminadas superiores se filtran hacia el acuífero inferior), vulnerabilidad del pozo e invasión de la zona de protección del pozo por parte de los tanques sépticos de las casas de habitación, lo que genera más carga de nitratos. En virtud de todo ello, el SENARA solicitó al Ministerio de Salud y al AyA el cierre del pozo y ordenó que la ASADA notificara sobre la fecha de clausura con el fin de que estuviera presente un funcionario del SENARA. Otrosí, en mérito del impacto producido a los acuíferos por el alto desarrollo urbano y el uso de tanques sépticos, el SENARA recomendó al AyA y a la Municipalidad de Cartago analizar el acuífero y determinar el alcance de nuevas medidas regulatorias y mitigación.
Adviértase que en mérito de lo dispuesto en el artículo 3, inciso h, de la ley n.° 6877 de Creación del SENARA, dicha institución tiene entre sus funciones “investigar, proteger y fomentar el uso de los recursos hídricos del país, tanto superficiales como subterráneos”. Sin embargo, el SENARA omite informar a esta Sala que haya dado el debido seguimiento a las directrices emitidas desde el año 2016, pese a que se verificó la contaminación de un cuerpo de agua subterráneo por actividad del ser humano, se constató la necesidad de cerrar el actual pozo, y a pesar de que, como lo deja entrever el oficio n.° DIGH-329-16 del 1° de noviembre de 2016, se sospechaba que la condición del pozo ASADA El Molino podía estarse repitiendo en otros pozos de abastecimiento del sector.
Por otro lado, respecto a la Municipalidad de Cartago, se aprecia que, mediante oficio n.° UGH-248-16 del 24 de octubre de 2016, el SENARA advirtió que “la zona de protección del pozo se encuentra invadida por casas con tanques sépticos con un incremento de viviendas desde el año 2017 lo que genera una mayor carga de nitratos”. En virtud de ello, el SENARA recomendó al municipio analizar el acuífero con énfasis en los pozos de abastecimiento y, debido al alto impacto que ha tenido el alto desarrollo urbano y el uso de tanques sépticos en la zona, determinar el alcance de nuevas medidas regulatorias y mitigación.
Empero, en el informe rendido a esta Sala, el municipio no hace alusión alguna a haber actuado conforme lo indicado por SENARA, sino todo lo contrario, pues se empeña en enfatizar que no tiene competencia alguna en el caso, pese a que es el municipio el encargado de regular el ordenamiento territorial cantonal y a pesar de que la acelerada urbanización de la zona y el concomitante uso de tanques de sépticos ha mostrado tener una importante incidencia en la contaminación de los cuerpos subterráneos de agua de la zona.
Así las cosas, se impone declarar con lugar el recurso por la inercia o negligencia de las autoridades recurridas ante la añeja problemática por contaminación con nitratos del pozo del Residencial El Molino.
V.En otro orden de ideas, el recurrente solicita que el servicio de agua potable para los vecinos del Residencial El Molino sea asumido por el acueducto de la Municipalidad de Cartago. Sin embargo, se impone desestimar esta petitoria, toda vez las autoridades del AyA informan bajo juramento que ello no es técnicamente viable por la capacidad hídrica e hidráulica de la zona. Asimismo, estima esta Sala que resulta razonable la medida de no aprobar nuevos servicios de agua potable para ser provistos por el pozo actual del Residencial El Molino, toda vez que sobre este pesa una orden de cierre por las razones ampliamente desarrolladas supra.
VI.En lo que respecta específicamente a la denegatoria del servicio de agua potable para el local comercial del recurrente, se impone desestimar el amparo por lo expuesto en el considerando I, en el sentido de que esta Sala no analiza dichas denegatorias cuando son para establecimientos comerciales, en cuanto no están en juego la satisfacción de las necesidades básicas de las personas. (…)
Por tanto:
Se declara parcialmente con lugar el recurso solo por la inercia o negligencia de las autoridades recurridas ante la problemática por contaminación con nitratos del pozo del Residencial El Molino en Cartago. Se le ordena a José Rodolfo Ramírez Villalba, Vladimir Mesén Montenegro y Carlos Eduardo Aguilar Quesada, por su orden Director UEN Gestión de ASADAS del Instituto Costarricense de Acueductos y Alcantarillados, Jefe de la Oficina Regional Central del Este de Atención de ASADAS del Instituto Costarricense de Acueductos y Alcantarillados, y representante judicial y extrajudicial de la ASADA de Residencial El Molino, o a quienes en su lugar ocupen esos cargos, que realicen las gestiones y coordinaciones necesarias, dentro del ámbito de sus competencias, a efectos de que dentro del plazo de 6 meses, contado a partir de la notificación de este pronunciamiento, se empiece a suministrar a los abonados de la ASADA El Molino agua potable proveniente de un nuevo pozo que cumpla con los estándares racionales de potabilidad del líquido.
Asimismo, en forma inmediata, deberán gestionar y coordinar lo necesario a efectos de que, en el plazo máximo de 15 días contado a partir de la notificación de esta sentencia, se reanude el proceso de dilución del agua del actual pozo del Residencial El Molino, como medida temporal mientras entra en funcionamiento el nuevo pozo. Por su parte, se le ordena a Roberto Ramírez Chavarría, en su condición de Director de Gestión e Investigación Hídrica del Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento, a quien ocupe el cargo, que le dé el debido seguimiento a lo dispuesto en la parte dispositiva del dictamen n.° UGH-248-16 del 24 de octubre de 2016. Por otro lado, se le ordena a Andrea Morales Fiesler, en su condición de Directora del Área Rectora de Salud de Cartago, o a quien ocupe el cargo, que dé el debido seguimiento y fiscalice el cumplimiento de las órdenes sanitarias vigentes emitidas; además, en caso de ser necesario, que emita nuevas órdenes sanitarias.
Por último, se le ordena a Rolando Rodríguez Brenes, en su condición de Alcalde de Cartago, o a quien ocupe el cargo, que gire las directrices necesarias en el ámbito de sus competencias a efectos de que, dentro del plazo de 2 meses contados a partir de la notificación de esta sentencia, la municipalidad rinda un informe sobre las actuales regulaciones cantonales de ordenamiento territorial en relación con las zonas de protección de los acuíferos y sobre el cumplimiento actual de dicha normativa en el sector del Residencial El Molino y zonas circunvecinas. Asimismo, deberá coordinar lo necesario para que se tomen las medidas que resulten pertinentes a la luz de los resultados de este informe, el cual deberá ser notificado al Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento, la ASADA El Molino y el Instituto Costarricense de Acueductos y Alcantarillados. Todo lo anterior se dicta con la advertencia que de conformidad con el artículo 71 de la Ley de la Jurisdicción Constitucional, se impondrá pena de prisión de tres meses a dos años o de veinte a sesenta día multa a quien reciba una orden de esta Sala que deba cumplir o hacer cumplir y la inobserve, siempre que el delito no esté más gravemente penado.
Se condena al Instituto Costarricense de Acueductos y Alcantarillados, Asociación Administradora del Acueducto y Alcantarillado Sanitario del Residencial El Molino, el Ministerio de Salud, el Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento y la Municipalidad de Cartago al pago de las costas, daños y perjuicios causados con los hechos que sirven de fundamento a esta declaratoria, los que se liquidarán en ejecución de sentencia de lo contencioso administrativo y civil, según corresponda. En lo demás, se declara sin lugar el recurso. Notifíquese este pronunciamiento a José Rodolfo Ramírez Villalba y Vladimir Mesén Montenegro, por su orden Director UEN Gestión de ASADAS y Jefe de la Oficina Regional Central del Este de Atención de ASADAS, ambos del Instituto Costarricense de Acueductos y Alcantarillados; así como a Carlos Eduardo Aguilar Quesada, Roberto Ramírez Chavarría, Rolando Rodríguez Brenes y Andrea Morales Fiesler, por su orden representante judicial y extrajudicial de la ASADA de Residencial El Molino, Director de Gestión e Investigación Hídrica del Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento, Alcalde de Cartago y Directora del Área Rectora de Salud de Cartago, o a quienes en su lugar ocupen esos cargos, en forma personal”.
Esa sentencia fue notificada al director UEN Gestión de ASADAS del Instituto Costarricense de Acueductos y Alcantarillados el 24 de julio de 2019, al jefe de la Oficina Regional del Este del AyA y a la directora del área Rectora de Salud de Cartago el 29 de julio de 2019. Asimismo, el representante judicial y extrajudicial de la ASADA de Residencial El Molino fue notificado el 30 de julio de 2019 y el alcalde de Cartago recibió la notificación el 31 de julio de 2019. Finalmente, el 9 de agosto de 2019 se le notificó la resolución al director de Gestión e Investigación Hídrica del Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento.
“III.- Sobre la gestión del Director UEN Gestión de ASADAS y el Jefe de la Oficina Regional Central Este de Atención de ASADAS, ambos del AyA. Los gestionantes Ramírez Villalba y Mesén Montenegro, por su orden Director UEN Gestión de ASADAS del AyA y Jefe de la Oficina Regional Central Este de Atención de ASADAS del AyA, solicitan adicionar la parte dispositiva de la sentencia de fondo de este amparo (n.° 2019-13292 de las 9:20 horas del 19 de julio de 2019). En esta línea, indican que la Sala ordenó que, dentro del plazo de 6 meses, se le empiece a suministrar agua proveniente de un nuevo pozo a los abonados de la ASADA El Molino; sin embargo, piden que se añada la salvedad de que ello está condicionado al hecho de que sea técnicamente viable. En este contexto, aducen que aún no hay certeza de la viabilidad técnica del nuevo pozo para abastecer el Residencial El Molino, pues se está en una fase de prefactibilidad, donde se debe actualizar el estudio hidrogeológico con la finalidad de establecer la profundidad real y efectiva que requiere la perforación.
Además, los mismos gestionantes piden que se adicione la sentencia a efectos de que se le ordene al ayuntamiento de Cartago que permita el ingreso del AyA a determinados pozos (IS-163 coordenadas Lambert norte E 544279 m, N 205053 m, IS-24 coordenadas Lambert norte E 544600 m, N 204800 m, IS-23 coordenadas Lambert norte E 544200 m, N 205055 m, IS-274 coordenadas Lambert norte E 544151 m, N 204348 m, IS-32 coordenadas Lambert norte E 543653 m, N 204675 m, e IS-495 coordenadas Lambert norte E 543790 m, N 204675 m), ya que el acceso a estos cuerpos de agua es fundamental para la actualización del estudio hidrogeológico requerido de previo a la perforación del nuevo pozo. Finalmente, piden que se adicione la sentencia de fondo a fin de que se le ordene al SENARA y al MINAE brindar trámite prioritario y expedito a las gestiones técnicas y administrativas requeridas para la autorización de la perforación del nuevo pozo, la inscripción de este y la correspondiente asignación de las aguas para la ASADA El Molino.
Al respecto, es menester destacar que la adición de sentencias de esta Sala solo procede cuando media la necesidad de complementar algún punto alegado que no fue analizado dentro del fallo; sin embargo, este no es el caso del sub lite, pues los alegatos ahora planteados en esta gestión posterior no fueron esgrimidos oportunamente, sea antes del dictado de la sentencia de fondo. En este sentido, en el informe rendido por las autoridades del AyA, se echa de menos que se haya aducido que la perforación del nuevo pozo estaba condicionada a los resultados de un estudio hidrogeológico actualizado para medir la profundidad real requerida. Por el contrario, de lo que constaba en autos al momento del dictado del fallo de fondo se colegía que el proceso de perforación del pozo estaba muy avanzado y su viabilidad técnica no estaba cuestionada, al punto que, como se indicó en el hecho probado r) de la sentencia n.° 2019-13292, desde el 19 de setiembre de 2017, la ASADA recurrida ya había definido el punto exacto de la perforación e incluso ya había recibido cotizaciones para la perforación.
Asimismo, como se reseñó en el hecho probado v), en abril de 2019, con respecto a la perforación, la ASADA solo estaba en espera de la respuesta del AyA al oficio AREM-273-2018 sobre la evaluación de las ofertas recibidas. En el informe rendido a esta Sala tampoco se alegó que, durante todos los años que se ha mantenido el problema de la contaminación del agua del pozo del Residencial El Molino, no se hubiera podido avanzar sobre el estudio hidrogeológico porque la Municipalidad de Cartago no ha permitido el ingreso del AyA a determinados pozos de la zona. Previo al dictado de la sentencia de fondo, tampoco se le solicitó a esta Sala que, en caso de una estimatoria del recurso, se ordenara que el SENARA y el MINAE brindaran trámite prioritario a las gestiones técnicas y administrativas requeridas para la autorización de la perforación del nuevo pozo, la inscripción de este y la correspondiente asignación de las aguas para la ASADA El Molino.
Sin embargo, no sobra reseñar que, en el por tanto de la sentencia n.° 2019-13292 de las 9:20 horas del 19 de julio de 2019, se le ordenó al SENARA –específicamente al Director de Gestión e Investigación Hídrica del Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento– que le dé el debido seguimiento a lo dispuesto en la parte dispositiva del dictamen n.° UGH-248-16 del 24 de octubre de 2016, en donde se estableció la necesidad del cierre del actual pozo del Residencial El Molino y se determinaron las actuaciones que al respecto debían llevar a cabo instituciones como el AyA y la Municipalidad de Cartago. Además, cabe indicar que en la sentencia n.° 2019-13292 también se ordenó al Área Rectora de Salud de Cartago que dé el debido seguimiento y fiscalice el cumplimiento de las órdenes sanitarias vigentes emitidas; además, en caso de ser necesario, que emita nuevas órdenes sanitarias.
En este contexto, a la luz de las órdenes dadas en la sentencia aludida, las autoridades recurridas podrán coordinar entre ellas –y si es necesario con otras autoridades competentes que no fueron parte procesal en este amparo– a fin de acatar lo dispuesto por este Tribunal Constitucional en la parte dispositiva del fallo n.° 2019-13292 y resolver así, de una forma integral y definitiva, el problema de contaminación por nitratos en el agua suministrada a los vecinos del Residencial El Molino.
En virtud de lo expuesto, resulta improcedente adicionar la sentencia de fondo sobre alegatos que no fueron planteados oportunamente ante este Tribunal
IV.Sobre la gestión del recurrente. Royer Quesada Rojas, en su condición de recurrente del amparo tramitado en este expediente, aduce que la Municipalidad de Cartago se mostró anuente a asumir la operación, mantenimiento y administración del acueducto que en la actualidad opera la ASADA del Residencial El Molino. En mérito de ello, estima que no resulta necesaria la perforación de un nuevo pozo, ni reanudar el proceso de dilución del agua extraída del pozo que se ha ordenado cerrar, sino ordenar que la Municipalidad de Cartago asuma la operación, mantenimiento y administración del acueducto del Residencial El Molino mediante la interconexión con el acueducto municipal.
Al respecto, es menester destacar que, en el considerando V de la sentencia n.° 2019-13292 de las 9:20 horas del 19 de julio de 2019, se indicó lo siguiente:
“V.- En otro orden de ideas, el recurrente solicita que el servicio de agua potable para los vecinos del Residencial El Molino sea asumido por el acueducto de la Municipalidad de Cartago. Sin embargo, se impone desestimar esta petitoria, toda vez las autoridades del AyA informan bajo juramento que ello no es técnicamente viable por la capacidad hídrica e hidráulica de la zona.” Así las cosas, se colige que lo ahora alegado por el recurrente es una disconformidad con lo resuelto por esta Sala. Ergo, se impone la desestimatoria respecto a este extremo. (…)
Por tanto:
No ha lugar a las gestiones”.
Tal resolución fue notificada a las autoridades recurridas el 25 de setiembre de 2019.
“IV.- SOBRE LA GESTIÓN DE DESOBEDIENCIA. En la especie, el recurrente manifiesta que a la fecha de interposición de la gestión posterior en relación con la sentencia n.° 2019-013292 de las 9:20 horas del 19 de julio de 2019, las autoridades recurridas no han cumplido lo ordenado por la Sala, por cuanto el nuevo pozo aún no se encuentra en funcionamiento; asimismo, solicita que se ordene a la Municipalidad de Cartago suministrarle a la ASADA el servicio de agua potable, y que no se le amplíes el plazo. Al respecto, se advierte que el Tribunal le ordenó a las autoridades del ICAA y al representante judicial y extrajudicial de la ASADA que “dentro del plazo de 6 meses, contado a partir de la notificación de este pronunciamiento, se empiece a suministrar a los abonados de la ASADA El Molino agua potable proveniente de un nuevo pozo que cumpla con los estándares nacionales de potabilidad del líquido (…)”. (El resaltado no es del original).
Ahora bien, de la lectura de las actas de notificación agregadas al expediente electrónico se extrae que el Director UEN Gestión de ASADAS y el Jefe de la Oficina Regional Central del Este de Atención de ASADAS del ICAA fueron notificados el 29 de julio de 2019 y que el representante judicial y extrajudicial de la ASADA de Residencial El Molino fue notificado el 30 de julio de 2019 sobre la sentencia 2019-013292 de las 9:20 horas del 19 de julio de 2019. Así, en virtud de lo anterior, a la fecha en que el recurrente acude a este Tribunal, sea, el 15 de noviembre de 2019, el plazo para cumplir lo ordenado por la Sala se encontraba vigente. Por ello, la gestión interpuesta por el amparado resulta prematura para la fecha en que la interpuso y se impone el rechazo.
En el sub lite se tiene que las autoridades del ICAA formularon una solicitud de prórroga del plazo otorgado por este Tribunal; en específico, solicitan: “(…) ampliar el plazo otorgado en la sentencia número 2019-013292 de las nueve horas veinte minutos del diecinueve de julio de dos mil diecinueve en 12 meses contados a partir de la comunicación de la resolución que se dicte al respecto”. Ahora bien, de los autos que constan en el expediente, este Tribunal advierte que la solicitud formulada por las autoridades recurridas se presentó previo al vencimiento del plazo ordenado por la Sala.
Asimismo, en la especie, la Sala constata que, el 21 de agosto de 2019, la geóloga Cristina Castanedo Sotela del Área Funcional de Hidrogeología de la UEN Gestión Ambiental del Recurso Hídrico del Instituto Costarricense de Acueductos y Alcantarillados, realizó un “ESTUDIO HIDROGEOLÓGICO POZO EL MOLINO, CARTAGO”, mediante el cual concluyó: “(…) 6. A partir de la información existente se indica que la problemática de los nitratos en el pozo de El Molino se debe a sus condiciones estructurales (…) y al alto contenido de nitratos en el acuífero superior por la presencia de tanque sépticos. 7. Desde el punto de vista hidrogeológico, las condiciones del acuífero profundo y los resultados de los análisis de la calidad de aguas, se recomienda realizar una perforación de exploración-perforación de 150 m que capte el acuífero inferior, siempre y cuando se garantice el aislamiento entre el acuífero superior y el inferior durante la perforación. Además, la perforación de exploración-producción profunda debe garantizar los retiros de ley (…)”.
De otro lado, este Tribunal tiene por acreditado que la ASADA del Residencial El Molino y el ICAA mantuvieron una reunión el 3 de octubre 2019, en la cual determinaron un plan de acción a seguir con la finalidad de acatar la orden de la Sala respecto a la construcción y perforación del nuevo pozo; sin embargo, advierten que para cumplir el mismo se requiere de mayor tiempo. Se indica que se establecieron 21 actividades, de las cuales 5 ya han sido solventadas, a saber: “i. Permiso de funcionamiento ante el Ministerio de Salud: Seguimiento para el otorgamiento del permiso de funcionamiento de la ASADA El Residencial El Molino.AREM-383-2019; fecha 01 de octubre del 2019. ii. Entrega del Estudio Hidrogeológico a la ASADA: Oficio GSD-UEN-GAR-2019-04149. iii. Revisión de las recomendaciones del Estudio Hidrogeológico: Minuta de reunión del 03 de octubre del 2019 entre la ASADA, UEN Gestión de ASADA y ORAC Central Este. iv. Análisis y Aceptación de implementación de recomendaciones del Est. Hidrogeológico: Minuta de reunión del 03 de octubre del 2910, entre la ASADA, UEN Gestión de ASADA y ORAC Central Este. v. Determinación de ruta a seguir respecto a la zona de protección: Oficio GSD-UEN-GAR-2020-00206”.
Aunado a lo anterior, el Tribunal verifica que las autoridades del ICAA, mediante el memorando GSD-UEN-GAR-2019-04376 del 11 de noviembre de 2019, consignaron que: “(…)d. Este estudio hidrogeológico elaborado por la unidad de Hidrogeología de la UEN Gestión Ambiental, determina la viabilidad de la perforación del nuevo pozo para la propuesta definitiva de abastecimiento del acueducto de Residencial El Molino. e. Producto de los estudios realizados se logró determinar que el armado del pozo requería obras que no permitan la comunicación entre estratos litológicos y a una profundidad mayor para asegurar la calidad del agua del acuífero a utilizar, dicho de otra forma, generó los insumos para determinar las características del pozo a perforar”.
En relación con las acciones realizadas por las autoridades recurridas, el SENARA, en el informe rendido bajo de juramento, manifestó que, el 26 de agosto, 24 de octubre y 21 de noviembre, todos de 2019, se mantuvieron distintas reuniones, en las cuales se definió que debe sellarse el pozo actual y perforarse uno nuevo que no capte el acuífero superior, y que, además, se le dará seguimiento a los procesos de perforación y análisis del agua.
Por su parte, se constata que, el 17 de enero de 2020, un ingeniero de la Oficina Regional Acueducto Comunales Central Este de la UEN Gestión de Acueductos Rurales remitió el oficio GSD-UEN-GAR-2020-00206 al Coordinador de la Unidad Hidrogógica Caribe de la Dirección de Aguas del Ministerio de Ambiente y Energía, en la cual le solicitó programar una visita para analizar las condiciones y el cumplimento de los retiros mínimos requeridos para la perforación de un pozo profundo que permita el abastecimiento de la comunidad del Residencial el Molino.
Sumado a lo anterior, el Tribunal verifica que, en enero de 2019, la ASADA le solicitó a “HIDROAMBIENTE Consultores” la realización de un “INFORME DE INVESTIGACIÓN HIDROGEOLÓGICA-DESCRIPCIÓN DE PIEZÓMETRO Y ANÁLISIS DE CONTENIDO DE NITRATOS, EL MOLINO DE CARTAGO”. En tal estudio se realizó una propuesta de armado para un nuevo pozo que procure mitigar la captación de nitratos. Este informe señaló que: “(…) se realiza la propuesta de armado del pozo definitivo, considerando una protección mediante un antepozo y un sello de concreto desde 0 hasta 50 metros de profundidad (…) y se propone la extensión del pozo entre 90 y 120 metros (…)”.
A partir de lo expuesto, este Tribunal considera que las autoridades recurridas han procedido a desplegar las acciones pertinentes a fin de cumplir lo ordenado por la Sala mediante la sentencia n.° 2019-013292 de las 9:20 horas del 19 de julio de 2019, en la que se dispuso: “(…) Se le ordena a José Rodolfo Ramírez Villalba, Vladimir Mesén Montenegro y Carlos Eduardo Aguilar Quesada, por su orden Director UEN Gestión de ASADAS del Instituto Costarricense de Acueductos y Alcantarillados, Jefe de la Oficina Regional Central del Este de Atención de ASADAS del Instituto Costarricense de Acueductos y Alcantarillados, y representante judicial y extrajudicial de la ASADA de Residencial El Molino, o a quienes en su lugar ocupen esos cargos, que realicen las gestiones y coordinaciones necesarias, dentro del ámbito de sus competencias, a efectos de que dentro del plazo de 6 meses, contado a partir de la notificación de este pronunciamiento, se empiece a suministrar a los abonados de la ASADA El Molino agua potable proveniente de un nuevo pozo que cumpla con los estándares nacionales de potabilidad del líquido. (…)”.
Aunado a lo anterior, si bien la Directora a.i del Área Rectora de Salud de Cartago señaló en el informe MS-DRRSCE-ARSC-0094-2020 que, en atención al oficio DRRSCE-ARSC-IT-1148-2019 del 23 de setiembre de 2019, se determinó que la ASADA El Molino incumplía con el parámetro de nitratos para el mes de julio de 2019, no menos cierto es que también informo que, a partir del 19 de julio de 2019, se empezó a implementar el proceso de dilución de agua mediante la instalación de una paja por parte de la Municipalidad de Cartago. Así, mediante los informes técnicos n.° DRRSCE-ARSC-IT-1149-2019, DRRSCE-ARSC-IT-1315-2019, MS-DRRSCE-ASRC-IT-0191-2020, MS-DRRSCE-ASRC-IT-0125-2020, MS-DRRSCE-ASRC-IT-0126-2020 y MS-DRRSCE-ASRC-IT-0192-2020, emitido por el Centro de Investigación y de Servicios Químicos y Microbiológicos (CEQUIATEC) del Instituto Tecnológico de Costa Rica, se determinó que los análisis de los niveles de nitrato de agosto, setiembre, octubre, noviembre y diciembre, todos de 2019, así como enero de 2020, cumplían con el parámetro de nitratos.
Por otra parte, informa el Ministro de Salud que se determinó que en los últimos cuatro reportes la ASADA El Molino únicamente aportó tres de las cuatro muestras requeridas por la orden sanitaria CE-ARSC-OS-0323-2017, en virtud de lo cual se giró la orden sanitaria n.° MS-DRRSCE-ARSC-OS-0020-2020, notificada a la ASADA recurrida el 14 de febrero de 2020, mediante la cual se le solicitó: “Realizar mensualmente análisis de laboratorio de la calidad del agua en el sistema de suministro para el parámetro de nitratos, que contemple una medición en el pozo, tanque de almacenamiento del agua diluida y 4 muestras en la red de distribución, tomadas en viviendas de los abonados a partir del mes de febrero del presente año, estos análisis deben ser realizados por un laboratorio autorizado por el Ministerio de Salud”.
No obstante lo anterior, del informe rendido por el Ministro de Salud y la Directora del Área de Salud de Cartago, se determinó que: “En tanto se mantenga la dilución en el tanque de agua potable por parte de la Municipalidad de Cartago y se realicen muestreos mensuales y se reporten al Área Rectora de Salud de Cartago, no se presentaría afectación a los usuarios de Asada El Molino, durante la ampliación del plazo para la construcción del nuevo pozo”.
Tal como se indicó en la sentencia n.° 2019-018328 de las 9:30 horas del 24 de setiembre de 2019; “lo que constaba en autos al momento del dictado del fallo de fondo se colegía que el proceso de perforación del pozo estaba muy avanzado y su viabilidad técnica no estaba cuestionada, al punto que, como se indicó en el hecho probado r) de la sentencia n.° 2019-13292, desde el 19 de setiembre de 2017, la ASADA recurrida ya había definido el punto exacto de la perforación e incluso ya había recibido cotizaciones para la perforación. Asimismo, como se reseñó en el hecho probado v), en abril de 2019, con respecto a la perforación, la ASADA solo estaba en espera de la respuesta del AyA al oficio AREM-273-2018 sobre la evaluación de las ofertas recibidas”. Sin embargo, ahora, las autoridades recurridas alegan que faltan una serie de estudios técnicos y la aprobación de permisos previos por parte de diversas entidades estatales, a fin de poder perforar el nuevo pozo en el Residencial El Molino.
En mérito de los alegatos esgrimidos por los accionados, y tomando en consideración la respuesta del Ministerio de Salud en el sentido de que una prórroga del plazo no afectaría la salud de los vecinos si se continúa el proceso de dilución, esta Sala estima razonable concederle a los recurridos una prórroga de 6 meses, contado a partir de la notificación de esta sentencia, para que se empiece a suministrar a los abonados de la ASADA El Molino agua potable proveniente de un nuevo pozo que satisfaga los estándares nacionales de potabilidad del líquido. (…)
Por tanto:
Se amplía el plazo conferido en la sentencia n.° 2019-013292 de las 9:20 horas del 19 de julio de 2019, y se confiere a José Rodolfo Ramírez Villalba, Vladimir Mesén Montenegro y Carlos Eduardo Aguilar Quesada, por su orden Director UEN Gestión de ASADAS del Instituto Costarricense de Acueductos y Alcantarillados, Jefe de la Oficina Regional Central del Este de Atención de ASADAS del Instituto Costarricense de Acueductos y Alcantarillados, y representante judicial y extrajudicial de la ASADA de Residencial El Molino, o a quienes en su lugar ocupen esos cargos, el plazo de 6 meses más, contado a partir de la notificación de esta sentencia, para cumplir lo ordenado en la sentencia n.° 2019-013292 de las 9:20 horas del 19 de julio de 2019, únicamente en relación con que se empiece a suministrar a los abonados de la ASADA El Molino agua potable proveniente de un nuevo pozo que cumpla con los estándares nacionales de potabilidad del líquido, bajo los mismos apercibimientos.
En lo demás, no ha lugar a la gestión formulada. Notifíquese este pronunciamiento a José Rodolfo Ramírez Villalba y Vladimir Mesén Montenegro, por su orden Director UEN Gestión de ASADAS y Jefe de la Oficina Regional Central del Este de Atención de ASADAS, ambos del Instituto Costarricense de Acueductos y Alcantarillados; a Carlos Eduardo Aguilar Quesada, representante judicial y extrajudicial de la ASADA de Residencial El Molino, y a Manuel Badilla Sánchez, en su condición de Alcalde de Cartago, o a quienes ocupen esos cargos, en forma personal.” Tal pronunciamiento fue notificado a las autoridades recurridas el 6 de marzo de 2021.
En el sub lite, el recurrente plantea gestión de desobediencia en relación con la sentencia n.° 2019-013292 de las 9:20 horas del 19 de julio de 2019. Manifiesta que en setiembre de 2020 venció el plazo ampliado que esta Sala le otorgó a los recurridos para cumplir lo ordenado. Sostiene que ha aportado al expediente diversa documentación que acredita que la Municipalidad de Cartago cuenta con la capacidad para brindar el servicio de agua potable al residencial de una forma más económica y rápida. Refiere que la factibilidad de tal circunstancia demuestra debido a que existe una interconexión mediante la que se diluye el agua para disminuir los contaminantes. Alude que mantener el pozo abierto atenta contra el principio de un ambiente sano y ecológicamente equilibrado. Solicita que se ordene el cierre inmediato del pozo y que se le ordene a la Municipalidad de Cartago asumir el servicio de manera inmediata y directa. Pide que se cumpla lo dispuesto en la sentencia n.° 2019-013292 de las 9:20 horas del 19 de julio de 2019.
Al respecto, conviene traer a colación que en el sub iudice se dictaron diversas órdenes, a saber: “Se le ordena a José Rodolfo Ramírez Villalba, Vladimir Mesén Montenegro y Carlos Eduardo Aguilar Quesada, por su orden Director UEN Gestión de ASADAS del Instituto Costarricense de Acueductos y Alcantarillados, Jefe de la Oficina Regional Central del Este de Atención de ASADAS del Instituto Costarricense de Acueductos y Alcantarillados, y representante judicial y extrajudicial de la ASADA de Residencial El Molino, o a quienes en su lugar ocupen esos cargos, que realicen las gestiones y coordinaciones necesarias, dentro del ámbito de sus competencias, a efectos de que dentro del plazo de 6 meses, contado a partir de la notificación de este pronunciamiento, se empiece a suministrar a los abonados de la ASADA El Molino agua potable proveniente de un nuevo pozo que cumpla con los estándares racionales de potabilidad del líquido.
Asimismo, en forma inmediata, deberán gestionar y coordinar lo necesario a efectos de que, en el plazo máximo de 15 días contado a partir de la notificación de esta sentencia, se reanude el proceso de dilución del agua del actual pozo del Residencial El Molino, como medida temporal mientras entra en funcionamiento el nuevo pozo. Por su parte, se le ordena a Roberto Ramírez Chavarría, en su condición de Director de Gestión e Investigación Hídrica del Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento, a quien ocupe el cargo, que le dé el debido seguimiento a lo dispuesto en la parte dispositiva del dictamen n.° UGH-248-16 del 24 de octubre de 2016. Por otro lado, se le ordena a Andrea Morales Fiesler, en su condición de Directora del Área Rectora de Salud de Cartago, o a quien ocupe el cargo, que dé el debido seguimiento y fiscalice el cumplimiento de las órdenes sanitarias vigentes emitidas; además, en caso de ser necesario, que emita nuevas órdenes sanitarias.
Por último, se le ordena a Rolando Rodríguez Brenes, en su condición de Alcalde de Cartago, o a quien ocupe el cargo, que gire las directrices necesarias en el ámbito de sus competencias a efectos de que, dentro del plazo de 2 meses contados a partir de la notificación de esta sentencia, la municipalidad rinda un informe sobre las actuales regulaciones cantonales de ordenamiento territorial en relación con las zonas de protección de los acuíferos y sobre el cumplimiento actual de dicha normativa en el sector del Residencial El Molino y zonas circunvecinas. Asimismo, deberá coordinar lo necesario para que se tomen las medidas que resulten pertinentes a la luz de los resultados de este informe, el cual deberá ser notificado al Servicio Nacional de Aguas Subterráneas, Riego y Avenamiento, la ASADA El Molino y el Instituto Costarricense de Acueductos y Alcantarillados”.
Ahora bien, visto que lo alegado por el recurrente solo versa en relación con el suministro del agua potable proveniente del pozo de abastecimiento, y tal orden se dictó al director UEN Gestión de ASADAS del Instituto Costarricense de Acueductos y Alcantarillados, al jefe de la Oficina Regional Central del Este de Atención de ASADAS del Instituto Costarricense de Acueductos y Alcantarillados, y representante judicial y extrajudicial de la ASADA de Residencial El Molino, se analiza únicamente la situación atinente a estas dependencias accionadas.
Aclarado lo anterior, en primer término, de los autos se colige que los recurridos han implementado lo correspondiente a la medida temporal de dilución del agua del actual pozo del Residencial El Molino, por lo que en este extremo no se observa desobediencia alguna.
Ahora bien, del propio dicho de los accionados, se extrae que a la fecha no se ha cumplido lo ordenado por la Sala en cuanto a que “dentro del plazo de 6 meses, contado a partir de la notificación de este pronunciamiento, se empiece a suministrar a los abonados de la ASADA El Molino agua potable proveniente de un nuevo pozo que cumpla con los estándares racionales de potabilidad del líquido”. Al respecto, los recurridos informan que, previo a que se conceda el permiso respectivo para la perforación del nuevo pozo, es necesario que la Municipalidad de Cartago le traspase a la ASADA El Molino los terrenos en los que este se realizará, y ese trámite legal ha generado que no se haya podido avanzar con lo ordenado por esta Sala.
En tal sentido, se aprecia que las autoridades del ICAA señalaron que si bien se consideró descartar la posibilidad de construir un nuevo pozo debido a la situación antes descrita y se analizó la posibilidad de que el mismo ICAA asumiera la prestación directa del servicio de agua potable a la comunidad del Residencial El Molino, o bien que lo hiciera otro ente operador, no menos cierto es que en el último informe rendido con ocasión a la prueba para mejor resolver ordenada por este Tribunal, los recurridos explicaron que se han dado avances significativos respecto a la gestión para que la Municipalidad traspase los inmuebles a la ASADA El Molino. En tal sentido, explican que para tales efectos se planteó ante la Asamblea Legislativa el proyecto de ley n.° 22.556 “DESAFECTACIÓN DEL USO PÚBLICO DE TERRENOS PROPIEDAD DE LA MUNICIPALIDAD DE CARTAGO PARA QUE LOS DONE A LA ASOCIACIÓN ADMINISTRADORA ACUEDUCTO Y ALCANTARILLADO EL MOLINO” publicado en la Gaceta n.° 137 del 16 de julio de 2021, se indicó: “LA ASAMBLEA LEGISLATIVA DE LA REPÚBLICA DE COSTA RICA DECRETA: DESAFECTACIÓN DEL USO PÚBLICO DE TERRENOS PROPIEDAD DE LA MUNICIPALIDAD DE CARTAGO PARA QUE LOS DONE A LA ASOCIACIÓN ADMINISTRADORA ACUEDUCTO Y ALCATARILLADO EL MOLINO ARTÍCULO 1- Desaféctese del uso público, los siguientes terrenos propiedad de la Municipalidad de Cartago, cédula jurídica número tres – cero catorce – cero cuarenta y dos mil ochenta, inscritos en el partido de Cartago: - Finca 97469-000, NATURALEZA: LOTE 21 PARA CONSTRUIR BLOQUE J, LINDEROS: NORTE: LOTE 22, SUR: LOTE 20, ESTE: CALLE CON 12 MTS 50 CM, OESTE: CALLE CON 12 MTS 50 CM, MIDE: DOSCIENTOS TREINTA Y SEIS METROS CON DIECISIETE DECIMETROS CUADRADOS, PLANO:NO SE INDICA, PROPIETARIO: GRUPO INVE SOCIEDAD ANONIMA (sic) CEDULA (sic) JURIDICA (sic) 3-101-039661.
DUEÑO DEL DOMINIO. - Finca: 97471-000, NATURALEZA: AREA (sic) VERDE CON POZO Y TANQUE DE ALMACENAMIENTO DE AGUA POTABLE BLOQUE J LOTE VEINTIDOS (sic), LINDEROS: NORTE: LOTE 23, SUR: LOTE 21, ESTE: CALLE CON 20 MTS 86 CM, OESTE: EL MOLINO SOCIEDAD CAFETALERA, MIDE: DOSCIENTOS SETENTA Y OCHO METROS CON NOVENTA Y CINCO DECIMETROS (sic) CUADRADOS PLANO:NO SE INDICA. PROPIETARIO: GRUPO INVE SOCIEDAD (sic) ANONIMA (sic) CEDULA (sic) JURIDICA (sic) 3-101-039661. DUEÑO DEL DOMINIO. - Finca: 97473-000, NATURALEZA: LOTE 23 PARA CONSTRUIR BLOQUE J, LINDEROS: NORTE: EL MOLINO SOCIEDAD CAFETALERA SUR: LOTE 22 ESTE: CALLE CON 29 MTS 50 CM OESTE: EL MOLINO SOCIEDAD CAFETALERA. MIDE: TRESCIENTOS SETENTA Y SEIS METROS CON SETENTA DECIMETROS (sic) CUADRADOS. PLANO:NO SE INDICA. PROPIETARIO: GRUPO INVE SOCIEDAD ANONIMA (sic) CEDULA (sic) JURIDICA (sic) 3-101-039661. DUEÑO DEL DOMINIO. ARTÍCULO 2- Se autoriza a la Municipalidad de Cartago a donar los lotes desafectados en el artículo anterior a la Asociación Administradora Acueducto y Alcantarillado El Molino, cédula jurídica 3-002-565237, para que sean destinados exclusivamente para el Acueducto de la urbanización El Molino.
En caso que se varíe el uso original del inmueble o se disuelva la persona jurídica beneficiaria, la propiedad de los terrenos donados volverá a ser propiedad de la Municipalidad de Cartago. ARTÍCULO 3- Se autoriza a la notaría del Estado, a que proceda a formalizar e inscribir en el Registro Público esta donación, sin valor estimado, lo que incluye la eliminación de los gravámenes hipotecarios que aparecen en sus asientos registrales bajo las citas: Finca 97469-000 citas: hipoteca 331-05005-01-0889, hipoteca 331-05005-01-0890-001, hipoteca 331-05005-01- 0890-001, hipoteca 331-05005-01-0891-001, 331-05005-01- 0892-001. Finca 97471, citas: hipoteca 331-05005-01-0865-001, hipoteca 331-05005-01-0866-001, hipoteca 331-05005-01-867-001, hipoteca 331-0505-01-868-001, practicado citas: 575-50395-01-003-001, Juzgado Civil de Menor Cuantía de Cartago, expediente 08-000485-0346-CI. Finca 97473-000 citas: hipoteca 331-05005-01-0852-001, hipoteca 331-05005-01-0853-001, hipoteca 331-05005-01-0919-001, hipoteca 331-05005-01-0921-001. Su inscripción estará exenta del pago de honorarios y de todo tipo de derechos y timbres. Rige a partir de su publicación. (…)”.
De otra parte, en el informe técnico MS-DRRSCE-ARSC-IT-0913-2021 del 10 de agosto de 2021, suscrito por el funcionario de Regulación de Salud del Área Rectora de Salud, se observa que la ASADA ha cumplido con los niveles de nitrato reglamentario, además, se indicó: “(…) acerca de la situación actual del agua que se suministra a los habitantes del Residencial El Molino, el Área Rectora de Cartago en su rol rector de seguimiento y fiscalización (Tabla 1) de los actos administrativos se mantiene vigilante con la revisión mensual de los reportes de calidad de agua potable, evidenciando que los resultados presentados durante el año 2021 cumplen con los valores indicados en el Cuadro 4. Parámetros de Calidad del Agua Nivel Tercero (N3): Nitrato; Valor de Alerta (25mg/l) y Valor Máximo Admisible (50mg/l) del Decreto N° 38924-s, Reglamento para la Calidad de Agua Potable. (…) en este sentido el Ministerio de Salud otorgó el visto bueno para la dilución como una medida temporal en su momento, previendo que la solución definitiva del problema por Nitratos se solventara parcialmente, a la espera de la construcción del nuevo pozo (…)”.
En adición, en el sub examine también se observa que las autoridades del ICAA le solicitan a este Tribunal que se les otorgue un plazo prudencial para brindar una solución integral al abastecimiento de agua potable para la comunidad.
Ahora bien, desde este panorama, la Sala acredita que las autoridades accionadas han efectuado acciones tendientes a darle seguimiento a los trámites correspondientes para el cumplimiento de lo ordenado por este Tribunal; sin embargo, los plazos otorgados han sido insuficientes. Así las cosas, en mérito de los alegatos esgrimidos por los accionados, y tomando en consideración la respuesta del Ministerio de Salud en el sentido de que los resultados del parámetro de nitratos en el agua suministrada en la red de distribución del acueducto de la Asada El Molino mediante el proceso de dilución, se encuentran dentro del valor de alerta (25mg/l) y valor máximo admisible (50 mg/l) permitidos, cumpliendo con lo establecido en el decreto n.° 38924-S, es que esta Sala estima procedente desestimar la gestión de desobediencia y en su lugar se concede a los recurridos una prórroga de 6 meses más, contado a partir de la notificación de esta sentencia, para que se solucione de manera integral y definitiva, el problema de contaminación por nitratos en el agua suministrada a los vecinos del Residencial El Molino.
No obstante, tal prórroga se otorga bajo la advertencia de que, si en el plazo concedido no resulta posible la construcción de un nuevo pozo de abastecimiento, las autoridades accionadas deberán adoptar las medidas correspondientes, a efectos de solucionar en definitiva el problema objeto de este recurso.
V.Finalmente, el recurrente sostiene que ha aportado al expediente diversa documentación que acredita que la Municipalidad de Cartago cuenta con la capacidad para brindar el servicio de agua potable al residencial de una forma más económica y rápida; además, que la factibilidad de tal circunstancia se demuestra debido a que existe una interconexión mediante la que se diluye el agua para disminuir los contaminantes. En consecuencia, solicita que se ordene a la Municipalidad de Cartago asumir el servicio de manera inmediata y directa.
Al respecto, es menester destacar que tal extremo ya fue resuelto en el considerando V de la sentencia n.° 2019-13292 de las 9:20 horas del 19 de julio de 2019, en el que se indicó lo siguiente: “V.- En otro orden de ideas, el recurrente solicita que el servicio de agua potable para los vecinos del Residencial El Molino sea asumido por el acueducto de la Municipalidad de Cartago. Sin embargo, se impone desestimar esta petitoria, toda vez las autoridades del AyA informan bajo juramento que ello no es técnicamente viable por la capacidad hídrica e hidráulica de la zona”. Así las cosas, se colige que lo ahora alegado por el recurrente es una disconformidad con lo resuelto por esta Sala. Ergo, se impone la desestimatoria respecto a este extremo. Ergo, lo procedente es desestimar la gestión planteada en lo que a tal extremo atañe.
Se previene a las partes que de haber aportado algún documento en papel, así como objetos o pruebas contenidas en algún dispositivo adicional de carácter electrónico, informático, magnético, óptico, telemático o producido por nuevas tecnologías, éstos deberán ser retirados del despacho en un plazo máximo de 30 días hábiles contados a partir de la notificación de esta sentencia. De lo contrario, será destruido todo aquel material que no sea retirado dentro de este plazo, según lo dispuesto en el "Reglamento sobre Expediente Electrónico ante el Poder Judicial", aprobado por la Corte Plena en sesión N° 27-11 del 22 de agosto del 2011, artículo XXVI y publicado en el Boletín Judicial número 19 del 26 de enero del 2012, así como en el acuerdo aprobado por el Consejo Superior del Poder Judicial, en la sesión N° 43-12 celebrada el 3 de mayo del 2012, artículo LXXXI.
Por tanto:
Se amplía el plazo conferido en la sentencia n.° 2019-013292 de las 9:20 horas del 19 de julio de 2019, y se confiere a José Rodolfo Ramírez Villalba y Vladimir Mesén Montenegro, por su orden director UEN Gestión de ASADAS y jefe de la Oficina Regional Central del Este de Atención de ASADAS, ambos del Instituto Costarricense de Acueductos y Alcantarillados; así como a Luis Paulino Méndez Badilla, en su condición de presidente de la ASADA de Residencial El Molino, o a quienes ocupen tales cargos, el plazo de 6 meses más, contado a partir de la notificación de esta sentencia, para cumplir lo ordenado en la sentencia n.° 2019-013292 de las 9:20 horas del 19 de julio de 2019, únicamente en relación con que se empiece a suministrar a los abonados de la ASADA El Molino agua potable proveniente de un nuevo pozo que cumpla con los estándares nacionales de potabilidad del líquido, y bajo la advertencia de que deberán adoptar las medidas necesarias para resolver de forma integral y definitiva el problema del agua que se le suministra a los vecinos del Residencial El Molino, en caso de que se proyecte alguna imposibilidad para finalizar el pozo aludido en el plazo antes citado.
En lo demás, no ha lugar a la gestión formulada. Notifíquese este pronunciamiento a José Rodolfo Ramírez Villalba y Vladimir Mesén Montenegro, por su orden Director UEN Gestión de ASADAS y Jefe de la Oficina Regional Central del Este de Atención de ASADAS, ambos del Instituto Costarricense de Acueductos y Alcantarillados; a Luis Paulino Méndez Badilla, presidente de la ASADA de Residencial El Molino, o a quienes ocupen esos cargos, en forma personal.
Paul Rueda L.
Presidente a.i Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Marta Eugenia Esquivel R.
Ana María Picado B.
Ileana Sánchez N.