← Environmental Law Center← Centro de Derecho Ambiental
Res. 12521-2021 Sala Constitucional · Sala Constitucional · 01/06/2021
OutcomeResultado
The Constitutional Chamber grants CONAVI an additional 36 months to build the wildlife crossings on Route 32, ordering biannual progress reports.La Sala Constitucional otorga 36 meses adicionales al CONAVI para construir los pasos de fauna en la Ruta 32, ordenando informes semestrales de avance.
SummaryResumen
The Constitutional Chamber resolves a request for an extension of time filed by CONAVI to comply with judgment 2021-001189, which ordered the construction and enabling of wildlife crossings on National Route 32. CONAVI argued that the original three-month deadline was insufficient due to technical, budgetary, and procurement reasons. The Chamber acknowledges that CONAVI has taken actions such as site studies, formation of a technical committee, and placement of 38 warning signs, but finds that the works remain incomplete. Considering the justifications regarding the project's complexity—including the need for financing of approximately $3.85 million, public bidding, and a 39-month timeline—the Chamber grants a 36-month extension, with biannual progress reports. The ruling highlights the tension between wildlife protection and the administrative realities of public works, establishing a monitoring mechanism to ensure future compliance.La Sala Constitucional resuelve una solicitud de ampliación de plazo presentada por el CONAVI para dar cumplimiento a la sentencia 2021-001189, que ordenó construir y habilitar pasos de fauna en la Ruta Nacional No. 32. El CONAVI argumentó que los tres meses originales eran insuficientes por razones técnicas, presupuestarias y de contratación. La Sala reconoce que el CONAVI ha realizado acciones como estudios de ubicación, conformación de un comité técnico y colocación de 38 rótulos de advertencia, pero constata que las obras no están completas. Considerando las justificaciones sobre la complejidad del proyecto —que incluye la necesidad de financiamiento de aproximadamente $3.85 millones, licitación pública y un cronograma de 39 meses—, la Sala otorga una prórroga de 36 meses, con informes semestrales de avance. El voto subraya la tensión entre la protección de la vida silvestre y las realidades administrativas de la obra pública, estableciendo un mecanismo de seguimiento para asegurar el cumplimiento futuro.
Key excerptExtracto clave
Despite the foregoing, and although it has been proven that the respondent authority has taken actions to comply with the order, the works carried out to date have not been sufficient to fully comply with what was ordered by this Chamber in the aforementioned judgment; however, this Tribunal understands the context surrounding the development and construction of the works in question, and therefore considers that the justifications for the delay incurred by CONAVI in complying with the order are acceptable to this Chamber. It should be clarified that, in this particular case, based on the technical report provided by the respondent authority, where a period of thirty-nine months is requested, this Tribunal considers that it is appropriate to extend the granted period by a maximum of thirty-six months, provided that during this period they must inform this Chamber semiannually of the actions they carry out in order to demonstrate full compliance with the order. In light of the foregoing, it is appropriate to extend the period for compliance with judgment No. 2021-001189 of 9:15 a.m. on January 22, 2021.A pesar de lo anterior, y si bien se tiene por acreditado que la autoridad recurrida ha llevado a cabo acciones en aras de dar cumplimiento a lo ordenado, lo cierto es que las obras ejecutadas, a la fecha, no han sido suficientes para dar cabal cumplimiento con lo ordenado por esta Sala en la sentencia supra indicada; no obstante, este Tribunal entiende el entorno que conlleva el desarrollo y construcción de las obras en cuestión, por lo que se estima que las justificaciones respecto de la demora en la que ha incurrido el CONAVI para cumplir lo ordenado son de recibo por esta Sala. Cabe aclarar que, en el caso particular, con base en el informe técnico aportado por la autoridad recurrida, donde se solicita una plazo de treinta y nueve meses, este Tribunal estima que lo procedente es ampliar el plazo otorgado por un plazo máximo de treinta y seis meses, siendo que durante dicho plazo deberán informar, de manera semestral, a esta Sala las acciones que vayan realizando durante dicho periodo a efectos de acreditar el pleno cumplimiento a lo ordenado. En virtud de lo anterior, lo procedente es ampliar el plazo, para el cumplimiento de lo ordenado en la sentencia No. 2021-001189 de las 09:15 horas del 22 de enero de 2021.
Pull quotesCitas destacadas
"este Tribunal entiende el entorno que conlleva el desarrollo y construcción de las obras en cuestión, por lo que se estima que las justificaciones respecto de la demora en la que ha incurrido el CONAVI para cumplir lo ordenado son de recibo por esta Sala."
"this Tribunal understands the context surrounding the development and construction of the works in question, and therefore considers that the justifications for the delay incurred by CONAVI in complying with the order are acceptable to this Chamber."
Considerando II
"este Tribunal entiende el entorno que conlleva el desarrollo y construcción de las obras en cuestión, por lo que se estima que las justificaciones respecto de la demora en la que ha incurrido el CONAVI para cumplir lo ordenado son de recibo por esta Sala."
Considerando II
"se realizaron los estudios pertinentes que generaron la ubicación, el número y las características de los puntos de pasos de fauna"
"the pertinent studies were carried out that generated the location, number, and characteristics of the wildlife crossing points"
Considerando II
"se realizaron los estudios pertinentes que generaron la ubicación, el número y las características de los puntos de pasos de fauna"
Considerando II
"se colocaron de rótulos de advertencia de la presencia de fauna a lo largo de la carretera, a distancias de 200 a 300 metros de las zonas de atropellos históricos un total de 38 señales."
"Warning signs about the presence of wildlife were placed along the road, at distances of 200 to 300 meters from historical roadkill zones, a total of 38 signs."
Considerando II
"se colocaron de rótulos de advertencia de la presencia de fauna a lo largo de la carretera, a distancias de 200 a 300 metros de las zonas de atropellos históricos un total de 38 señales."
Considerando II
Full documentDocumento completo
Constitutional Chamber Case File: 20-020651-0007-CO Relevance Indicators Relevant ruling Content of Interest:
Type of content: Majority vote Branch of Law: 4. MATTERS OF GUARANTEE Topic: NON-COMPLIANCE Subtopics:
DEADLINE IS EXTENDED.
012521-21. NON-COMPLIANCE. CONAVI IS GRANTED AN EXTENSION OF THE DEADLINE SET IN RULING 001189-21, FOR ITS DUE COMPLIANCE. ON THE ENABLING OF WILDLIFE CROSSINGS ON THE SECTIONS OF ROUTE 32.
“(…) Despite the foregoing, and while it is established that the appealed authority has carried out actions to comply with what was ordered, the truth is that the works executed, to date, have not been sufficient to fully comply with what was ordered by this Chamber in the aforementioned ruling; nevertheless, this Court understands the circumstances surrounding the development and construction of the works in question, and therefore considers that the justifications regarding the delay incurred by CONAVI in complying with the order are accepted by this Chamber.
It should be clarified that, in this particular case, based on the technical report provided by the appealed authority, which requests a thirty-nine month period, this Court deems it appropriate to extend the granted period by a maximum of thirty-six months, during which time they must inform this Chamber semi-annually of the actions taken during said period to demonstrate full compliance with the order.
By virtue of the foregoing, it is appropriate to extend the deadline for compliance with the order in ruling No. 2021-001189 of 09:15 on January 22, 2021. (…)” VCG07/2021 ... See more Content of Interest:
Type of content: Majority vote Branch of Law: 6. LAW OF THE CONSTITUTIONAL JURISDICTION ANNOTATED WITH JURISPRUDENCE Topic: 053- Compliance with an order issued by the Chamber. Disobedience Subtopics:
NOT APPLICABLE.
ARTICLE 53 OF THE LAW OF THE CONSTITUTIONAL JURISDICTION “(…) II.-Regarding the request for extension of the deadline. In this case, the Chamber notes that the authorities of the National Road Council request an extension of the three-month deadline granted in ruling No. 2021-001189 of 09:15 on January 22, 2021, due to budgetary reasons, since resources must be managed to finance the construction of the wildlife crossings, in addition, the contracting process for the company that will build said works must be carried out, and subsequently, the execution or construction stage of these must be undertaken.
First of all, it is important to note that ruling No. 2021-001189 of 09:15 on January 22, 2021 was notified to the appealed authority on January 25, 2021, in which a three-month deadline was granted for its compliance, which expired on April 25, 2021.
On this matter, it should be highlighted that, from the evidence provided in the case file and the report issued under oath, it is verified that the authority involved has carried out various actions to comply with what was ordered by this Chamber. In this regard, it is confirmed that the following actions have been carried out: a) the pertinent studies that generated the location, number, and characteristics of the wildlife crossing points were conducted; b) a search for updated scientific information support was carried out to locate or relocate the wildlife points; c) the formation of the Technical Committee for the study of wildlife points was finalized and formalized, which, based on the study “Verification of Environmental Measures to reduce the presence of wild fauna in the expansion of the National Highway Route 32 Limón, Costa Rica. 2016.”, located nine points for the possible placement of wildlife crossings; d) in March 2021, one of its study products was executed with the implementation of a mitigation measure, while the wildlife crossings are being built; e) wildlife presence warning signs were placed along the highway, at distances of 200 to 300 meters from historical wildlife-vehicle collision zones, a total of 38 signs.
Despite the foregoing, and while it is established that the appealed authority has carried out actions to comply with what was ordered, the truth is that the works executed, to date, have not been sufficient to fully comply with what was ordered by this Chamber in the aforementioned ruling; nevertheless, this Court understands the circumstances surrounding the development and construction of the works in question, and therefore considers that the justifications regarding the delay incurred by CONAVI in complying with the order are accepted by this Chamber. (…)” VCG07/2021 Case File: 20-020651-0007-CO CONSTITUTIONAL CHAMBER OF THE SUPREME COURT OF JUSTICE. San José, at nine forty-five on June first, two thousand twenty-one.
Request for deadline extension filed by Mario Rodríguez Vargas, in his capacity as executive director of the NATIONAL ROAD COUNCIL (CONAVI).
Whereas:
Drafted by Magistrate Araya García; and,
Considering:
I.Through ruling No. 2021-001189 of 09:15 on January 22, 2021, this Chamber resolved the following: “(…) The appeal is partially granted, solely against CONAVI. Mario Rodríguez Vargas, in his capacity as Executive Director of the National Road Council (CONAVI), or whoever holds that position, is ordered to take the corresponding measures so that within THREE MONTHS, counted from the notification of this ruling, the wildlife crossings are built and enabled on the sections of National Route No. 32 that have already been intervened in the rehabilitation and expansion project of that road. Likewise, he is to arrange what is necessary so that, within the same period, the construction of the other wildlife crossings on the sections of the same route that will be intervened soon is designed and planned, in the manner anticipated by SETENA, and that their proper construction is carried out in due course. (…)”
II.Regarding the request for extension of the deadline. In this case, the Chamber notes that the authorities of the National Road Council request an extension of the three-month deadline granted in ruling No. 2021-001189 of 09:15 on January 22, 2021, due to budgetary reasons, since resources must be managed to finance the construction of the wildlife crossings, in addition, the contracting process for the company that will build said works must be carried out, and subsequently, the execution or construction stage of these must be undertaken.
First of all, it is important to note that ruling No. 2021-001189 of 09:15 on January 22, 2021 was notified to the appealed authority on January 25, 2021, in which a three-month deadline was granted for its compliance, which expired on April 25, 2021.
On this matter, it should be highlighted that, from the evidence provided in the case file and the report issued under oath, it is verified that the authority involved has carried out various actions to comply with what was ordered by this Chamber. In this regard, it is confirmed that the following actions have been carried out: a) the pertinent studies that generated the location, number, and characteristics of the wildlife crossing points were conducted; b) a search for updated scientific information support was carried out to locate or relocate the wildlife points; c) the formation of the Technical Committee for the study of wildlife points was finalized and formalized, which, based on the study “Verification of Environmental Measures to reduce the presence of wild fauna in the expansion of the National Highway Route 32 Limón, Costa Rica. 2016.” 2016," nine points were located for the possible placement of wildlife crossings (pasos de fauna); d) in March 2021, one of its study products was implemented with the application of a mitigation measure, while the wildlife crossings (pasos de fauna) are built; e) a total of 38 signs warning of the presence of wildlife were placed along the highway, at distances of 200 to 300 meters from historical wildlife-vehicle collision zones.
Despite the foregoing, and although it is deemed accredited that the respondent authority has carried out actions in order to comply with what was ordered, the truth is that the works executed, to date, have not been sufficient to fully comply with what was ordered by this Chamber in the above-cited judgment; however, this Court understands the environment involved in the development and construction of the works in question, and therefore it is considered that the justifications regarding the delay incurred by CONAVI in complying with what was ordered are accepted by this Chamber.
It should be clarified that, in this particular case, based on the technical report provided by the respondent authority, which requests a period of thirty-nine months, this Court considers that the appropriate course is to extend the granted period for a maximum period of thirty-six months, it being understood that during said period they must report, semi-annually, to this Chamber on the actions they carry out during that period in order to accredit full compliance with what was ordered.
By virtue of the foregoing, it is appropriate to extend the period for compliance with what was ordered in judgment No. 2021-001189 of 09:15 hours on January 22, 2021.
III.Documentation provided to the case file. The parties are warned that if they have provided any paper document, as well as objects or evidence contained in any additional electronic, computer, magnetic, optical, telematic device or one produced by new technologies, these must be removed from the office within a maximum period of 30 business days counted from the notification of this judgment. Otherwise, all material not removed within this period will be destroyed, pursuant to the provisions of the "Reglamento sobre Expediente Electrónico ante el Poder Judicial," approved by the Corte Plena in session No. 27-11 of August 22, 2011, article XXVI and published in Boletín Judicial number 19 of January 26, 2012, as well as in the agreement approved by the Consejo Superior del Poder Judicial, in session No. 43-12 held on May 3, 2012, article LXXXI.
Por tanto:
Mario Rodríguez Vargas, in his capacity as executive director of the Consejo Nacional de Vialidad, or whoever occupies that position in his stead, is granted a non-extendable period of THIRTY-SIX MONTHS, counted from the notification of this resolution, to faithfully comply with the provisions of judgment No. 2021-001189 of 09:15 hours on January 22, 2021, under the warning that they must submit semi-annual compliance reports to this Court, which record the actions that accredit full compliance with what was ordered by this Chamber in the above-cited judgment. Furthermore, what was indicated in the cited judgment regarding article 71 of the Ley de la Jurisdicción Constitucional is reiterated. Notify.- Fernando Castillo V.
President Nancy Hernández L.
Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Marta Eugenia Esquivel R.
Ana María Picado B.
Clasificación elaborada por SALA CONSTITUCIONAL del Poder Judicial. Prohibida su reproducción y/o distribución en forma onerosa.
Indicadores de Relevancia Sentencia relevante Contenido de Interés:
Tipo de contenido: Voto de mayoría Rama del Derecho: 4. ASUNTOS DE GARANTÍA Tema: INCUMPLIMIENTO Subtemas:
SE AMPLIA PLAZO.
012521-21. INCUMPLIMIENTO. SE CONFIERE AL CONAVI LA AMPLIACIÓN DEL PLAZO DE LA SENTENCIA 001189-21, PARA SU DEBIDO CUMPLIMIENTO. SOBRE LA HABILITACIÓN DEL PASO DE FAUNA EN LOS TRAMOS DE LA RUTA 32.
“(…) A pesar de lo anterior, y si bien se tiene por acreditado que la autoridad recurrida ha llevado a cabo acciones en aras de dar cumplimiento a lo ordenado, lo cierto es que las obras ejecutadas, a la fecha, no han sido suficientes para dar cabal cumplimiento con lo ordenado por esta Sala en la sentencia supra indicada; no obstante, este Tribunal entiende el entorno que conlleva el desarrollo y construcción de las obras en cuestión, por lo que se estima que las justificaciones respecto de la demora en la que ha incurrido el CONAVI para cumplir lo ordenado son de recibo por esta Sala.
Cabe aclarar que, en el caso particular, con base en el informe técnico aportado por la autoridad recurrida, donde se solicita una plazo de treinta y nueve meses, este Tribunal estima que lo procedente es ampliar el plazo otorgado por un plazo máximo de treinta y seis meses, siendo que durante dicho plazo deberán informar, de manera semestral, a esta Sala las acciones que vayan realizando durante dicho periodo a efectos de acreditar el pleno cumplimiento a lo ordenado.
En virtud de lo anterior, lo procedente es ampliar el plazo, para el cumplimiento de lo ordenado en la sentencia No. 2021-001189 de las 09:15 horas del 22 de enero de 2021. (…)” VCG07/2021 ... Ver más Contenido de Interés:
Tipo de contenido: Voto de mayoría Rama del Derecho: 6. LEY DE LA JURISDICCIÓN CONSTITUCIONAL ANOTADA CON JURISPRUDENCIA Tema: 053- Cumplimiento de orden emitida por la Sala. Desobediencia Subtemas:
NO APLICA.
ARTÍCULO 53 DE LA LEY DE LA JURISDICCIÓN CONSTITUCIONAL “(…) II.-Sobre la solicitud de ampliación del plazo. En la especie, la Sala observa que las autoridades del Consejo Nacional de Vialidad solicitan una ampliación del plazo de tres meses concedido en la sentencia No. 2021-001189 de las 09:15 horas del 22 de enero de 2021, ello por motivos de presupuesto, ya que deben gestionarse los recursos para financiar la construcción de los pasos de fauna, además, debe realizarse el proceso de contratación de la empresa que construya dichas obras y, posteriormente, debe llevarse a cabo la etapa de ejecución o construcción de estas.
En primer lugar, es importante denotar que la sentencia No. 2021-001189 de las 09:15 horas del 22 de enero de 2021 fue notificada a la autoridad recurrida el 25 de enero de 2021, en la cual se concedió un plazo de tres meses para el cumplimiento de esta, el cual venció el 25 de abril de 2021.
Sobre el particular, cabe resaltar que, de las pruebas aportadas en autos, y el informe rendido bajo juramento, se constata que la autoridad involucrada ha llevado a cabo diversas actuaciones, en aras de acatar lo ordenado por esta Sala. En ese sentido consta que se han llevado a cabo las siguientes acciones: a) se realizaron los estudios pertinentes que generaron la ubicación, el número y las características de los puntos de pasos de fauna; b) se efectuó la búsqueda del apoyo de información científica actualizada para ubicar o reubicar los puntos de fauna; c) se concretó y formalizó la conformación del Comité Técnico para el estudio de los puntos de fauna, la cual, con base en el estudio “Verificación de Medidas Ambientales para disminuir la presencia de fauna silvestre en la ampliación de la Carretera Nacional Ruta 32 Limón, Costa Rica. 2016.”, se ubicaron nueve puntos para la posible ubicación de pasos de fauna; d) en marzo de 2021, se ejecutó uno de sus productos del estudio con la implementación de una medida de mitigación, en el tanto se construyen los pasos de fauna; e) se colocaron de rótulos de advertencia de la presencia de fauna a lo largo de la carretera, a distancias de 200 a 300 metros de las zonas de atropellos históricos un total de 38 señales.
A pesar de lo anterior, y si bien se tiene por acreditado que la autoridad recurrida ha llevado a cabo acciones en aras de dar cumplimiento a lo ordenado, lo cierto es que las obras ejecutadas, a la fecha, no han sido suficientes para dar cabal cumplimiento con lo ordenado por esta Sala en la sentencia supra indicada; no obstante, este Tribunal entiende el entorno que conlleva el desarrollo y construcción de las obras en cuestión, por lo que se estima que las justificaciones respecto de la demora en la que ha incurrido el CONAVI para cumplir lo ordenado son de recibo por esta Sala. (…)” VCG07/2021 ... Ver más SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas cuarenta y cinco minutos del uno de junio de dos mil veintiuno .
Solicitud de ampliación de plazo interpuesta por Mario Rodríguez Vargas, en su condición de director ejecutivo del CONSEJO NACIONAL DE VIALIDAD (CONAVI).
Resultando:
Redacta el Magistrado Araya García; y,
Considerando:
I.Mediante la sentencia No. 2021-001189 de las 09:15 horas del 22 de enero de 2021, esta Sala resolvió lo siguiente: “(…) Se declara parcialmente con lugar el recurso, únicamente contra el CONAVI. Se ordena a Mario Rodríguez Vargas, en condición de Director Ejecutivo del Consejo Nacional de Vialidad (CONAVI), o a quien ejerza tal cargo, tomar las medidas correspondientes para que en el plazo de TRES MESES, contado a partir de la notificación de esta sentencia, se construyan y habiliten los pasos de fauna en los tramos de la Ruta Nacional No. 32 que ya fueron intervenidos en el proyecto de rehabilitación y ampliación de esa vía. Asimismo, que disponga lo correspondiente para que, en el mismo plazo, se diseñe y planifique la construcción de los demás pasos de fauna en los tramos de la misma ruta que serán intervenidos próximamente, de la forma en que lo ha previsto SETENA, y, en su momento, se ejecute su debida construcción. (…)”
II.Sobre la solicitud de ampliación del plazo. En la especie, la Sala observa que las autoridades del Consejo Nacional de Vialidad solicitan una ampliación del plazo de tres meses concedido en la sentencia No. 2021-001189 de las 09:15 horas del 22 de enero de 2021, ello por motivos de presupuesto, ya que deben gestionarse los recursos para financiar la construcción de los pasos de fauna, además, debe realizarse el proceso de contratación de la empresa que construya dichas obras y, posteriormente, debe llevarse a cabo la etapa de ejecución o construcción de estas.
En primer lugar, es importante denotar que la sentencia No. 2021-001189 de las 09:15 horas del 22 de enero de 2021 fue notificada a la autoridad recurrida el 25 de enero de 2021, en la cual se concedió un plazo de tres meses para el cumplimiento de esta, el cual venció el 25 de abril de 2021.
Sobre el particular, cabe resaltar que, de las pruebas aportadas en autos, y el informe rendido bajo juramento, se constata que la autoridad involucrada ha llevado a cabo diversas actuaciones, en aras de acatar lo ordenado por esta Sala. En ese sentido consta que se han llevado a cabo las siguientes acciones: a) se realizaron los estudios pertinentes que generaron la ubicación, el número y las características de los puntos de pasos de fauna; b) se efectuó la búsqueda del apoyo de información científica actualizada para ubicar o reubicar los puntos de fauna; c) se concretó y formalizó la conformación del Comité Técnico para el estudio de los puntos de fauna, la cual, con base en el estudio “Verificación de Medidas Ambientales para disminuir la presencia de fauna silvestre en la ampliación de la Carretera Nacional Ruta 32 Limón, Costa Rica. 2016.”, se ubicaron nueve puntos para la posible ubicación de pasos de fauna; d) en marzo de 2021, se ejecutó uno de sus productos del estudio con la implementación de una medida de mitigación, en el tanto se construyen los pasos de fauna; e) se colocaron de rótulos de advertencia de la presencia de fauna a lo largo de la carretera, a distancias de 200 a 300 metros de las zonas de atropellos históricos un total de 38 señales.
A pesar de lo anterior, y si bien se tiene por acreditado que la autoridad recurrida ha llevado a cabo acciones en aras de dar cumplimiento a lo ordenado, lo cierto es que las obras ejecutadas, a la fecha, no han sido suficientes para dar cabal cumplimiento con lo ordenado por esta Sala en la sentencia supra indicada; no obstante, este Tribunal entiende el entorno que conlleva el desarrollo y construcción de las obras en cuestión, por lo que se estima que las justificaciones respecto de la demora en la que ha incurrido el CONAVI para cumplir lo ordenado son de recibo por esta Sala.
Cabe aclarar que, en el caso particular, con base en el informe técnico aportado por la autoridad recurrida, donde se solicita una plazo de treinta y nueve meses, este Tribunal estima que lo procedente es ampliar el plazo otorgado por un plazo máximo de treinta y seis meses, siendo que durante dicho plazo deberán informar, de manera semestral, a esta Sala las acciones que vayan realizando durante dicho periodo a efectos de acreditar el pleno cumplimiento a lo ordenado.
En virtud de lo anterior, lo procedente es ampliar el plazo, para el cumplimiento de lo ordenado en la sentencia No. 2021-001189 de las 09:15 horas del 22 de enero de 2021.
III.Documentación aportada al expediente. Se previene a las partes que de haber aportado algún documento en papel, así como objetos o pruebas contenidas en algún dispositivo adicional de carácter electrónico, informático, magnético, óptico, telemático o producido por nuevas tecnologías, éstos deberán ser retirados del despacho en un plazo máximo de 30 días hábiles contados a partir de la notificación de esta sentencia. De lo contrario, será destruido todo aquel material que no sea retirado dentro de este plazo, según lo dispuesto en el “Reglamento sobre Expediente Electrónico ante el Poder Judicial”, aprobado por la Corte Plena en sesión No. 27-11 de 22 de agosto de 2011, artículo XXVI y publicado en el Boletín Judicial número 19 de 26 de enero de 2012, así como en el acuerdo aprobado por el Consejo Superior del Poder Judicial, en la sesión No. 43-12 celebrada el 3 de mayo de 2012, artículo LXXXI.
Por tanto:
Se le confiere a Mario Rodríguez Vargas, en su condición de director ejecutivo del Consejo Nacional de Vialidad, o a quien en su lugar ocupe dicho cargo, un plazo improrrogable de TREINTA Y SEIS MESES, contado a partir de la notificación de la presente resolución, para dar fiel cumplimiento a lo dispuesto en la sentencia No. 2021-001189 de las 09:15 horas del 22 de enero de 2021, bajo el apercibimiento de que deberán remitir informes semestrales de cumplimiento a este Tribunal, en los que consten las acciones que acrediten el pleno cumplimiento a lo ordenado por esta Sala en la sentencia supra indicada. Se reitera, además, lo señalado en la sentencia de cita respecto del artículo 71 de la Ley de la Jurisdicción Constitucional. Notifíquese.- Fernando Castillo V.
Nancy Hernández L.
Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Marta Eugenia Esquivel R.
Ana María Picado B.
Clasificación elaborada por SALA CONSTITUCIONALdel Poder Judicial. Prohibida su reproducción y/o distribución en forma onerosa.
Document not found. Documento no encontrado.