Res. 03667-2021 Sala Constitucional · Sala Constitucional · 23/02/2021
OutcomeResultado
The Chamber denies the request to extend the deadlines for preparing and executing the remedial plan, finding that the first deadline was sufficiently extended already and the second has not yet expired.La Sala rechaza la solicitud de ampliar los plazos para elaborar y ejecutar el plan remedial, por considerar que el primer plazo ya fue prorrogado suficientemente y el segundo aún no ha vencido.
SummaryResumen
The Constitutional Chamber rejects, for the second time, the request by the Mayor of Poás to extend the deadlines set in ruling 2020-018374, which ordered the preparation of a remedial plan within two months and its execution within ten months to solve a landslide problem in San Juan District. The Chamber argues that the first deadline had already been extended, totaling four months, which it deems sufficient for preparing the plan. As for the second deadline, it has not yet expired and the Municipality still has time to carry out the works before winter, making an extension premature. The petitioners opposed the extension, citing the urgency of the works given the risk of further landslides threatening homes and human lives.La Sala Constitucional rechaza por segunda vez la solicitud del Alcalde de Poás para ampliar los plazos otorgados en la sentencia 2020-018374, que ordenó elaborar un plan remedial en dos meses y ejecutarlo en diez meses para solucionar un problema de deslizamiento en el Distrito San Juan. La Sala argumenta que el primer plazo ya fue prorrogado, sumando cuatro meses, lo que considera suficiente para la elaboración del plan. En cuanto al segundo plazo, aún no ha vencido y la Municipalidad tiene tiempo para ejecutar las obras antes de la llegada del invierno, por lo que resulta prematuro ampliarlo. Las recurrentes se opusieron a la prórroga, señalando la urgencia de las obras ante el riesgo de deslizamientos mayores que amenazan viviendas y vidas humanas.
Key excerptExtracto clave
The Chamber considers that such a claim is unacceptable. Regarding the first deadline, as indicated, it was already extended, totaling four months for the preparation of the remedial plan. A further extension is inappropriate. Moreover, the Mayor's submissions in both briefs refer more to the execution than the preparation of the plan that would solve the problem that has afflicted the petitioners for many years. (...) As for the second ten-month deadline, since the judgment was notified on September 28, 2020, it would expire on July 28, 2021, and thus it is appropriate to maintain it. First, it has not yet expired, so the Municipal Administration has time to continue executing the remedial plan. It would also be premature to seek an extension of something that has not yet concluded.Se considera que tal pretensión no es de recibo. En cuanto al primer plazo, como se indicó, ya fue prorrogado, sumando un total de cuatro meses para la elaboración del plan remedial. Siendo improcedente una nueva prórroga. Nótese, además, que lo expuesto por el Alcalde en ambos escritos, constituye más la ejecución y no la elaboración del plan que vendría a solucionar la problemática que desde hace muchos años aqueja a las recurrentes. (...) En cuanto al segundo plazo de diez meses, como la sentencia fue notificada el 28 de setiembre de 2020, vencería el 28 de julio de 2021, por lo que se estima procedente mantenerlo. Primero, no ha fenecido, por lo que la Administración Municipal tiene tiempo para seguir ejecutando el plan remedial. Así como sería prematuro pretender ampliar lo que no ha concluido.
Pull quotesCitas destacadas
"Se considera que tal pretensión no es de recibo."
"The Chamber considers that such a claim is unacceptable."
Considerando III
"Se considera que tal pretensión no es de recibo."
Considerando III
"En cuanto al primer plazo, como se indicó, ya fue prorrogado, sumando un total de cuatro meses para la elaboración del plan remedial. Siendo improcedente una nueva prórroga."
"As for the first deadline, as indicated, it was already extended, totaling four months for the preparation of the remedial plan. A further extension is inappropriate."
Considerando III
"En cuanto al primer plazo, como se indicó, ya fue prorrogado, sumando un total de cuatro meses para la elaboración del plan remedial. Siendo improcedente una nueva prórroga."
Considerando III
"En cuanto al segundo plazo de diez meses, como la sentencia fue notificada el 28 de setiembre de 2020, vencería el 28 de julio de 2021, por lo que se estima procedente mantenerlo. Primero, no ha fenecido, por lo que la Administración Municipal tiene tiempo para seguir ejecutando el plan remedial."
"As for the second ten-month deadline, since the judgment was notified on September 28, 2020, it would expire on July 28, 2021, and thus it is appropriate to maintain it. First, it has not yet expired, so the Municipal Administration has time to continue executing the remedial plan."
Considerando III
"En cuanto al segundo plazo de diez meses, como la sentencia fue notificada el 28 de setiembre de 2020, vencería el 28 de julio de 2021, por lo que se estima procedente mantenerlo. Primero, no ha fenecido, por lo que la Administración Municipal tiene tiempo para seguir ejecutando el plan remedial."
Considerando III
Full documentDocumento completo
Date of Resolution: February 23, 2021, at 09:40 Type of matter: Amparo action Judgment with protected data, in accordance with current regulations *200159560007CO* CONSTITUTIONAL CHAMBER OF THE SUPREME COURT OF JUSTICE. San José, at nine hours forty minutes on February twenty-third, two thousand twenty-one.
REQUEST FOR EXTENSION OF THE TIME LIMITS GIVEN IN JUDGMENT No. 2020-018374, at 9:15 a.m. on September 25, 2020, filed by the MAYOR OF POÁS in the AMPARO ACTION brought by [Name 001], of legal age, divorced, identity card No. [Value 001], resident of San Juan Norte de San Pedro de Poás, and [Name 002], of legal age, married, identity card No. [Value 002], resident of San Juan Norte de San Pedro de Poás, against the MUNICIPALITY OF POÁS.
WHEREAS:
| ID | Project Milestones | Duration (weeks) | Start Date | End Date |
|---|---|---|---|---|
| A | Start | 0 | February 22, 2021 | February 22, 2021 |
| B | Conducting studies | 16 | February 23, 2021 | June 4, 2021 |
| C | Design development | 11 | June 7, 2021 | August 20, 2021 |
| D | Budget preparation | 11 | August 23, 2021 | November 5, 2021 |
| E | Contracting of Works | 15 | November 8, 2021 | February 18, 2022 |
| F | Execution of works | 50 | February 21, 2022 | February 3, 2023 |
| G | End | 0 | February 3, 2023 | February 3, 2023 |
Project Start: February 22, 2021 Project End: February 3, 2023 Estimated Duration: 103 weeks (without estimating calendar exceptions).
It is clear that this first Remedial Plan of exclusive intervention on the critical point has enormous drawbacks since it requires a highly complex engineering intervention, in successive stages that imply successive public procurement processes. This entails a total delay of 103 weeks, a period that could be longer if there are appeals in the respective procurement processes. All of which results in an inefficiency of the solution itself because, firstly, the concrete solution for the petitioner residents and the territory is enormously delayed in time, and, secondly, with high probabilities of producing a technical alternative that does not give absolute certainty and, therefore, may become absolutely ineffective. It is for this technical reason that, according to the technical report of this Municipality issued by the Municipal Road Management Technical Unit, through official letter MPO-GVM-114-2021, dated February 4, 2021, the second solution and the respective Remedial Plan were developed and are reported in parallel, which, contrary to the previous one and based on a basic study that gives them an assessment of the problem of water flows (caudales), is the one that the Municipality of Poás prepares as technically and scientifically more suitable because it allows it to be in a position to develop an immediate intervention for the benefit of the residents and the territory, generating a definitive, real, and sustainable solution to the problem.
Said report determines the explanation and the estimated work execution schedule of the Comprehensive Remedial Plan for the execution of pipeline and sewer works upstream to divert them and prevent them from reaching the critical point of the discharge culvert and the gully, based on a hydrological study of the micro-watershed. The explanation and schedule of this second alternative are detailed below: For the second solution alternative, which we will call “Creation of a forced easement for rainwater” (Creación de servidumbre forzosa de aguas pluviales), which consists of opening a new rainwater easement on cantonal route number 2-08-020, known as Calle Cabuyal, through which a rainwater discharge would be built, discharging a significant percentage of water into the Prendas River. This alternative was also mentioned in previous official letters. For this solution, they have the following estimated deadlines.
| ID | Project Milestones | Duration (weeks) | Start Date | End Date |
|---|---|---|---|---|
| A | Start | 0 | February 22, 2021 | February 22, 2021 |
| B | Conducting Hydrological Study | 8 | February 23, 2021 | April 16, 2021 |
| C | Design development | 15 | April 19, 2021 | June 11, 2021 |
| D | Conformation of forced easement for rainwater | 15 | June 14, 2021 | September 24, 2021 |
| E | Budget preparation | 8 | September 27, 2021 | November 19, 2021 |
| F | Contracting of Works | 15 | November 22, 2021 | March 4, 2022 |
| G | Execution of works | 15 | March 7, 2022 | June 17, 2022 |
| H | End | 0 | June 17, 2022 | June 17, 2022 |
Project Start: February 22, 2021 Project End: June 17, 2022 Estimated Duration: 69 weeks (without estimating calendar exceptions) Consequently, the Municipality is analyzing the problem from an integral point of view, beyond the right-of-way, and technically considers that the waters can be diverted before they reach the critical point and thus prevent the sewer system and gully from continuing to deteriorate rapidly, this being the ideal technical solution to definitively, really, and sustainably resolve the landslide problem in the San Juan District of the Canton of Poás. For all the foregoing, and having stated the corresponding justification required by the resolution of the Constitutional Chamber, this Municipality respectfully requests: a) Both deadlines need to be extended. b) It indicates that four months are needed to prepare the hydrological study and designs. c) Twelve months are required for the implementation of the definitive solution, which includes: Forced easement for rainwater sewer, budget, procurement, and construction of the rainwater sewer works.
Drafted by Magistrate Garro Vargas; and,
CONSIDERING:
This Chamber, through judgment No. 2020-018374, at 9:15 a.m. on September 25, 2020, granted the appeal. Therefore, it ordered the following: “…Heibel Antonio Rodríguez Araya, in his capacity as Mayor of Poás, or whoever holds that position, is ordered to:
This Chamber, through Resolution No. 2020-022245, at 09:20 a.m. on November 18, 2020, ordered a period of two more months to be granted for full compliance with what was ordered in point a) of the operative part of judgment No. 2020-018374, at 9:15 a.m. on September 25, 2020, and rejected the request for extension of the deadline in point b) of said vote.
Heibel Antonio Rodríguez Araya, in his capacity as Mayor of Poás, appears before this Court on February 5, 2021, requesting, for the second time, an extension of the two and ten-month deadlines granted by the Chamber for the fulfillment of the remedial and definitive plans. As in the previous petition he submitted for the same purpose, which was partially accepted, he argues reasons ranging from logistical to budgetary. In that petition, he says that they are awaiting reports that will serve as definitive technical diagnoses to concretely determine the works to be carried out that will provide a final solution to the problem. That the contracted company has not quantified, in real and tangible terms, the total cost of the works to be executed. Also, that the economic circumstances he describes make it extremely difficult to comply with each and every one of the requirements within the proposed deadlines.
Although in a later petition, at a request from this Chamber, he reports that the Mayor's Office of Poás has been developing the scope, efficacy, and efficiency of two possible technical solutions in order to definitively resolve the landslide problem in the San Juan District, denounced in this amparo, preparing two remedial plans to solve the problem: 1. The Remedial Plan of exclusive intervention on the critical point. To start on February 22, 2021, and concluding on February 3, 2023, with an estimated duration of 103 weeks, not including calendar exceptions. 2. The Comprehensive Remedial Plan for the execution of pipeline and sewer works upstream to divert them and prevent them from reaching the critical point of the discharge culvert and the gully, based on a hydrological study of the micro-watershed. The start date is indicated as February 22, 2021, to conclude the project on June 17, 2022, with an estimated duration of 69 weeks, not counting calendar exceptions.
He points out that the latter is the one the Municipality of Poás prepares as technically and scientifically more suitable because it allows it to be in a position to develop an immediate intervention for the benefit of the residents and the territory, generating a definitive, real, and sustainable solution to the problem. Therefore, he requests the following: a) Both deadlines need to be extended. b) Four months are needed to prepare the hydrological study and designs. c) Twelve months are required for the implementation of the definitive solution, which includes: forced easement for rainwater sewer, budget, procurement, and construction of the rainwater sewer works.
The petitioners oppose the aforementioned request. They consider a lack of real commitment on the part of the municipality in requesting more time, understanding the magnitude of the existing emergency, the time they have been requesting help, without omitting the serious consequences that further postponing the physical works could bring this coming winter, since even though the hardware store was cleared, the existential danger has never corresponded to the weight of the buildings, but rather to the flow of water coming down through the culvert that causes the landslides, the same waters mostly coming from Cabuyal. Similarly, the situation on the land where the dwelling house is located, family patrimony, inhabited by 3 people belonging to Mrs. Castillo, would be unsustainable if the physical works are not carried out before next winter, as it is already quite eroded and with very steep slopes. They request that this Chamber maintain the deadlines given in the judgment, as well as the prompt execution of the works, since they cannot risk postponing the piping work that is extremely urgent due to the arrival of winter and be exposed to a greater danger where not only the lands would be more compromised but also the dwelling house of Mrs. Castillo, or worse yet, human lives.
This Chamber, through judgment No. 2020-018374, at 9:15 a.m. on September 25, 2020, granted the appeal and ordered the Mayor of Poás to prepare, within two months, a remedial plan to solve the landslide problem in the San Juan District, denounced in this amparo. Likewise, that within ten months, said plan be carried out and executed to provide a definitive solution to said problem. Finally, that he immediately adopt the necessary measures to mitigate the danger of a potential landslide. It is noted that the first two-month deadline was extended by Resolution No. 2020-022245, at 09:20 a.m. on November 18, 2020, for two more months. Now, the respondent Mayor again appears before this Court, requesting, for the second time, an extension of both deadlines. It is considered that such a claim is not acceptable. Regarding the first deadline, as indicated, it has already been extended, totaling four months for the preparation of the remedial plan.
A new extension is improper. Note, furthermore, that what the Mayor stated in both briefs constitutes more the execution and not the preparation of the plan that would solve the problem that has afflicted the petitioners for many years. To which it must be added that the time granted for such a task has been more than sufficient. Regarding the second ten-month deadline, since the judgment was notified on September 28, 2020, it would expire on July 28, 2021, so it is deemed appropriate to maintain it. First, it has not expired, so the Municipal Administration has time to continue executing the remedial plan. Furthermore, it would be premature to seek to extend what has not yet concluded.
By virtue of the foregoing, the request for extension of deadlines filed by the Mayor of Poás is rejected.
The parties are warned that, if they have provided any paper document, as well as objects or evidence contained in any additional electronic, computer, magnetic, optical, telematic device or one produced by new technologies, these must be withdrawn from the office within a maximum period of 30 business days counted from the notification of this judgment. Otherwise, all material not withdrawn within this period will be destroyed, in accordance with the provisions of the "Electronic Case File Regulations before the Judiciary" ("Reglamento sobre Expediente Electrónico ante el Poder Judicial"), approved by the Full Court in Session No. 27-11 of August 22, 2011, Article XXVI, and published in Judicial Bulletin No. 19 of January 26, 2012, as well as in the agreement approved by the Superior Council of the Judiciary, in Session No. 43-12 held on May 3, 2012, Article LXXXI.
THEREFORE:
The petition formulated by Heibel Antonio Rodríguez Araya, in his capacity as Mayor of Poás, is denied. Notify.
Fernando Castillo V. President Paul Rueda L. Luis Fdo. Salazar A.
Jorge Araya G. Anamari Garro V.
Hubert Fernández A. Ileana Sánchez N.
*UFI9TEKGQ8I61* EXPEDIENTE N° 20-015956-0007-CO Telephones: 2549-1500 / 800-SALA-4TA (800-7252-482). Fax: 2295-3712 / 2549-1633. Email address: www.poder-judicial.go.cr/salaconstitucional. Address: (Sabana Sur, Calle Morenos, 100 mts.Sur de la iglesia del Perpetuo Socorro).
Reception of cases involving vulnerable groups: Supreme Court of Justice Building, San José, Cathedral District (Distrito Catedral), González Lahmann neighborhood (Barrio González Lahmann), 19th and 21st Streets, 8th and 6th Avenues It is a faithful copy of the original – Taken from Nexus.PJ on: 09-05-2026 08:58:59.
Sentencia con datos protegidos, de conformidad con la normativa vigente *200159560007CO* SALA CONSTITUCIONAL DE LA CORTE SUPREMA DE JUSTICIA. San José, a las nueve horas cuarenta minutos del veintitres de febrero de dos mil veintiuno . SOLICITUD DE AMPLIACIÓN DE LOS PLAZOS DADOS EN LA SENTENCIA No. 2020-018374 , de las 9:15 horas del 25 de setiembre de 2020, planteada por el ALCALDE DE POÁS en el RECURSO DE AMPARO que interpusieron [Nombre 001], mayor, divorciada, cédula de identidad No. [Valor 001] , vecina de San Juan Norte de San Pedro de Poás y [Nombre 002], mayor, casada, cédula de identidad No. [Valor 002], vecina de San Juan Norte de San Pedro de Poás, contra la MUNICIPALIDAD DE POÁS. RESULTANDO: 1.- Por escrito recibido en la Secretaría de la Sala a las 10:59 horas del 20 de enero de 2021, Heibel Antonio Rodríguez Araya, en su condición de Alcalde de Poás, indica que se apersona en tiempo y forma a informar a la Sala Constitucional acerca de las acciones que esa Municipalidad ha ejecutado en aras de poder ejecutar y materializar el Plan Definitivo ordenado en la sentencia No. 2020-018374, de las 9:15 horas del 25 de setiembre de 2020, dictada en el presente asunto, y lo hace como sigue: HECHOS: 1.
Que, ante petición de la Administración Municipal, la Unidad Técnica de Gestión Vial Municipal, mediante oficio MPO-GVM-582-2020, de fecha 21 de diciembre de 2020, realizó un historial de las diversas acciones administrativas atendiendo al principio de coordinación interinstitucional pregonado en el ordinal 5 del Código Municipal, para mitigar la problemática suscitada en el desfogue de aguas pluviales que provienen de la calle pública de orden cantonal, código de camino cantonal número 2-08-020 y la ruta nacional, código 146, ubicado en la entrada de la urbanización Los Oviedo, en el distrito de San Juan de Poás, en las colindancias de los inmuebles de las señoras acá recurrentes. 2. Igualmente, la misma oficina de Gestión Vial Municipal, mediante el oficio No. MPO-GVM-067-2021, de fecha 19 de enero de 2021, hace una explicación de los avances y las nuevas acciones ejecutadas por ese Municipio para dar cumplimiento a las ordenanzas de la Sala Constitucional con el Plan Remedial solicitado.
Que ese Informe Técnico contiene el Plan Remedial y detalle de las actividades ejecutadas en el caso desfogue de las colindancias de las viviendas de las señoras [Nombre 003] y [Nombre 002] con las últimas actuaciones de acatamiento a los fallos dictados en el proceso sub judice con una copia del cronograma preliminar enviado a la Municipalidad desde esa área Técnica, para valoración de la Alcaldía Municipal. Que igualmente el citado Informe Técnico detalla las acciones administrativas ejecutadas desde inicio del año 2021, dando seguimiento a la ejecución de las actividades siguiendo lo establecido en el oficio MPO-GVM-582-2020, para ello se ha iniciado la cotización de las pruebas y de los ensayos con empresas que realicen este servicio técnico, se continúa con el monitoreo de la zona y se han realizado algunas visitas de campo. Destaca el informe de marras, que en la zona de carga del talud (donde se ubicaba la Ferretería Trejos) se retiró prácticamente toda la estructura e infraestructura que antes existió (únicamente queda una losa de concreto del contrapiso y una pared de la fachada principal), por lo que en este momento la reducción de carga del talud ha sido considerablemente disminuida en una de las fincas colindantes con el desfogue y ello minimiza en gran medida el desprendimiento de los taludes por no tener ya la carga de material constructivo que se almacenaba en el lote de relleno ubicado al costado norte del desfogue que nos ocupa.
El 14 de enero de 2021, se contó con la presencia del geólogo Blas Sánchez de la Comisión Nacional de Emergencias, quien realizó una nueva valoración de la zona y se está en espera de las resultas que ha de contener el informe de la visita con lo encontrado en sitio. Se recalca que la Municipalidad también ha materializado desde la Oficina de Gestión Vial Municipal trabajos de mantenimiento y limpieza en la boca del desfogue, para evitar almacenamiento de residuos, lastre u otros materiales que puedan causar algún tipo de represamiento para que el agua discurra con mayor facilidad de acuerdo a los niveles de escorrentía de aguas pluviales y servidas que ahí desfogan. Y por ello se aportan en el informe fotografías que detallan esos trabajos realizados en el sitio. En virtud de lo anterior y tomando en cuenta que están en espera de los informes que sirvan de diagnósticos técnicos definitivos para determinar en forma concreta los trabajos por ejecutar que den solución final al problema, asumen el compromiso de comunicarlos de forma inmediata a este Tribunal Constitucional en aras de mantenerles informados acerca de los avances administrativos y materiales de las obras que se vayan ejecutando en el sector aludido.
En igual sentido, de requerirse realizar ajustes presupuestarios, o de tener que presupuestar nuevas partidas dinerarias para inyectar más recursos de los ya destinados para financiar los estudios técnicos preliminares, también se harán saber en el momento mismo en que tengan cuantificado por la empresa contratada en términos reales y tangibles, el monto a que asciende en costo de las obras por ejecutar, una vez que así lo revelen los informes descritos pendientes de ser vertidos. Por todo lo anterior, instan a la Sala Constitucional a ampliar de ser posibles los plazos concedidos en el por tanto de la sentencia y la resolución posterior que motivó el presente emplazamiento para el cumplimiento de todos y cada uno de los extremos ahí ordenados, pues las circunstancias económicas descritas hacen sumamente difícil el cumplimiento de todas y cada una de las exigencias en los plazos propuestos, y adquieren el compromiso de realizar informes trimestrales o semestrales del cumplimiento y avances de trabajos atendiendo lo dispuesto en el fallo antes citado. 2.- Mediante resolución de las 17:17 horas del 20 de enero de 2021, la Magistrada Instructora dispuso poner en conocimiento de las recurrentes las manifestaciones que suscribe Heibel Antonio Rodríguez Araya, en su condición de Alcalde de Poás, en el escrito presentado a las 10:59 horas del 20 de enero de 2021.
Lo anterior para lo que a bien tuviesen en manifestar y de previo a resolver sobre la solicitud de ampliación de los plazos otorgados en la sentencia No. 2020-018374, de las 09:15 horas del 25 de setiembre de 2020, que formula en ese libelo. 3.- Por escrito recibido en la Secretaría de la Sala a las 11:50 horas del 28 de enero de 2021, las recurrentes indican que desde años atrás, cuando se produjo los primeros indicios de los deslaves y erosiones de los terrenos causados por la cantidad de agua que discurre por la alcantarilla, notificaron de manera inmediata a las instituciones competentes: Comisión de Emergencias, Defensoría de los habitantes y a la misma Municipalidad como responsable de velar por el buen funcionamiento de los alcantarillados (documentos probatorios que se encuentran en el expediente), sin embargo, el municipio nunca ejecutó obra alguna pese a su insistencia y tramitología durante tanto tiempo.
En la nota DCV (1-4)-145-2007, el Ing. Mauricio Rojas Quesada del CONAVI, en el punto b y c, da la recomendación idónea y pertinente que la Municipalidad debió ejecutar en ese entonces (2007) cuando se construyó la alcantarilla y que para el funcionamiento correcto y por ende evitar la erosión de los terrenos adjuntos, se debía continuar un canal o caño que evitaría la gran problemática de hoy en día. Información conocida por el municipio y que prueban con carta de recibido que adjuntan. Por lo tanto, consideran que la municipalidad ha tenido muchos años para planificar y presupuestar dicha obra y que, por no invertir en un trabajo menos costoso en el momento oportuno, se han visto afectadas en gran manera y ahora por su misma negligencia las obras son de mayor costo. Dado lo anterior, consideran una falta de compromiso real de parte del municipio al pedir más tiempo, entendiendo la magnitud de la emergencia existente, el tiempo que llevan solicitando ayuda, sin omitir las graves consecuencias que el seguir postergando las obras físicas pueda traer en este próximo invierno, ya que pese a que la ferretería fue evacuada, el peligro existencial nunca ha correspondido al peso de las edificaciones, sino al caudal que baja por la alcantarilla y provoca los deslizamientos, mismas aguas mayormente provenientes de Cabuyal.
De igual manera, sería insostenible la situación en el terreno donde se encuentra la casa de habitación, patrimonio familiar, habitada por 3 personas de la Sra. Castillo, de no ejecutarse las obras físicas antes del próximo invierno, el cual ya está bastante erosionado y con taludes muy pronunciados. Véanse las imágenes adjuntas. Aunado a esto quisieran mencionar que el mantenimiento a la alcantarilla de solo una única vez, hace año y ocho meses se ejecutó por petición de la Sra. Castillo. Adjuntan nota MPO-GVM-043-2019 donde conta como luce al día de hoy. 4.- Por escrito recibido en la Secretaría de la Sala a las 11:22 horas del 29 de enero de 2021, la recurrente [Nombre 001] indica que en este caso quiere hacer un adjunto a las manifestaciones enviadas el día 27-01-2021 a esta Sala. Adjunta nota AM-295-2007 del 07 de diciembre de 2007, emitida por el Ing. José Joaquín Brenes, Alcalde Municipal en ese entonces, donde manifiesta la mejor disposición de coordinar los trabajos necesarios una vez que el CONAVI terminara la alcantarilla, por lo tanto, desde entonces existe un compromiso por escrito de parte de la alcaldía que no se cumplió.
Misma nota que es respuesta al oficio DCV (1-4)-145-2007 que está adjunto en el manifiesto del 27 de enero de 2021. 5.- Mediante resolución de las 11:48 horas del 1° de febrero de 2021, como prueba para mejor resolver, la Magistrada Instructora previno a Heibel Antonio Rodríguez Araya, en su condición de Alcalde de Poás, o a quien ocupe ese cargo, que cumpla con lo siguiente:
Fernando Castillo V.
Paul Rueda L.
Luis Fdo. Salazar A.
Jorge Araya G.
Anamari Garro V.
Hubert Fernández A.
Ileana Sánchez N.
*UFI9TEKGQ8I61* EXPEDIENTE N° 20-015956-0007-CO
Document not found. Documento no encontrado.