Res. 33874-2026 Sala Constitucional · Sala Constitucional · 03/09/2026

Municipal Enforcement of Orders Against Illegal ConstructionEjecución municipal de órdenes por construcción ilegal

View document ↓ Ver documento ↓ View original source ↗ Ver fuente original ↗

Loading…Cargando…

OutcomeResultado

GrantedCon lugar

The amparo was granted because the Municipality had not notified or enforced its orders concerning illegal construction; it was ordered to resolve and notify the complaint and, if appropriate, carry out the demolition within three months.Se declaró con lugar el amparo por la falta de notificación y ejecución de las órdenes municipales relativas a construcciones ilegales; se ordenó resolver y notificar la denuncia y, si procede, ejecutar la demolición en tres meses.

SummaryResumen

The Constitutional Chamber (Sala Constitucional) found a violation of the right to prompt and effective justice because, although the Municipality of Alajuelita had ordered the suspension and demolition of illegal construction reported in 2022, it had neither notified the applicant of that decision nor carried out the demolition. The applicant alleged leaks, wastewater, and risks to health, property, and the environment. The Chamber granted the amparo and ordered the Municipality to resolve and notify the complaint and, if appropriate, carry out the demolition within three months.La Sala Constitucional tuvo por lesionado el derecho a una justicia pronta y cumplida porque, aunque la Municipalidad de Alajuelita había ordenado suspender y demoler unas construcciones ilegales denunciadas desde 2022, no notificó esa decisión a la recurrente ni ejecutó la demolición. La recurrente alegó filtraciones, aguas residuales y riesgos para la salud, la propiedad y el ambiente. La Sala declaró con lugar el amparo y ordenó a la Municipalidad resolver y notificar la denuncia y, si corresponde, ejecutar la demolición dentro de tres meses.

Key excerptExtracto clave

Because it was not established that the applicant knew the outcome of the matter she had raised or the dates on which the illegal constructions would ultimately be demolished, her right to prompt and effective justice is deemed to have been violated. Accordingly, the amparo is to be granted.Al no tener por acreditado que la recurrente tenga conocimiento del resultado de la gestión planteada ni las fechas en las que finalmente se demolerán las construcciones ilegales, se estima lesionado su derecho a una justicia pronta y cumplida. Por lo anterior, lo procedente es declarar con lugar el recurso.

Pull quotesCitas destacadas

  • "Al no tener por acreditado que la recurrente tenga conocimiento del resultado de la gestión planteada ni las fechas en las que finalmente se demolerán las construcciones ilegales, se estima lesionado su derecho a una justicia pronta y cumplida."

    "Because it was not established that the applicant knew the outcome of the matter she had raised or the dates on which the illegal constructions would ultimately be demolished, her right to prompt and effective justice is deemed to have been violated."

    Considerando VI

  • "Al no tener por acreditado que la recurrente tenga conocimiento del resultado de la gestión planteada ni las fechas en las que finalmente se demolerán las construcciones ilegales, se estima lesionado su derecho a una justicia pronta y cumplida."

    Considerando VI

Full documentDocumento completo

033874-26. INFORMATION. MUNICIPALITY. IT IS ALLEGED THAT THE MUNICIPALITY OF ALAJUELITA DID NOT FINALLY RESOLVE A COMPLAINT FILED IN 2022 ABOUT THE ILLEGAL CONSTRUCTION OF APARTMENTS THAT CAUSES LEAKS AND WASTEWATER AND POSES RISKS TO PROPERTY, HEALTH, AND THE ENVIRONMENT. ALTHOUGH CLOSURE AND DEMOLITION OF THE STRUCTURES WERE ORDERED, THE DECISION WAS NOT NOTIFIED TO THE INTERESTED PARTY OR CARRIED OUT FOR MORE THAN FOUR YEARS, IN VIOLATION OF ARTICLE 41 OF THE CONSTITUTION. THE AMPARO APPLICATION IS GRANTED, AND THE MUNICIPALITY IS ORDERED TO RESOLVE AND NOTIFY THE COMPLAINT AND, IF APPROPRIATE, CARRY OUT THE DEMOLITION WITHIN THREE MONTHS. VCG09/2026 “(…) VI.—THE SPECIFIC CASE. In the case at hand, the applicant states that the construction of several apartments adjoining her home affects the foundations of her house and causes problems related to wastewater, leaks, and waste disposal, posing risks to health and the environment. She indicates that since 2022 she has submitted various requests to the Municipality of Alajuelita, seeking municipal intervention, a halt to and closure of the works, their eventual demolition, and the closure of windows that overlook her property. However, she alleges that her requests have not been definitively answered and that no measures have been taken regarding the complaint, so the situation persists.

Now, although it is true that the authorities of the Municipality of Alajuelita, within the scope of their powers, have taken some steps to address the reported situation and issued decisions ordering suspension and subsequent demolition of the structures, there is no evidence that the decision was notified to the amparo applicant, nor is there evidence that the order to demolish the illegal constructions was ultimately carried out, even though the complaints date back to 2022. Since it has not been established that the applicant knows the outcome of the request she submitted or the dates on which the illegal constructions will ultimately be demolished, her right to prompt and effective justice is deemed to have been violated. Accordingly, the amparo application must be granted. (…)”

033874-26. INFORMACIÓN. MUNICIPALIDAD. SE DENUNCIA QUE LA MUNICIPALIDAD DE ALAJUELITA NO RESOLVIÓ DEFINITIVAMENTE UNA DENUNCIA PRESENTADA EN 2022 CONTRA LA CONSTRUCCIÓN ILEGAL DE APARTAMENTOS QUE GENERA FILTRACIONES, AGUAS RESIDUALES Y RIESGOS PARA LA PROPIEDAD, LA SALUD Y EL AMBIENTE. AUNQUE SE ORDENARON LA CLAUSURA Y DEMOLICIÓN DE LAS ESTRUCTURAS, LA DECISIÓN NO FUE NOTIFICADA A LA INTERESADA NI EJECUTADA DURANTE MÁS DE CUATRO AÑOS, EN VIOLACIÓN DEL ARTÍCULO 41 CONSTITUCIONAL. SE DECLARA CON LUGAR Y SE ORDENA RESOLVER Y NOTIFICAR LA DENUNCIA Y, SI PROCEDE, EJECUTAR LA DEMOLICIÓN EN TRES MESES. VCG09/2026 “(…) VI.- SOBRE EL CASO CONCRETO. En el sub lite, la recurrente manifiesta que una construcción de varios apartamentos colindante con su vivienda afecta las bases de su casa y genera problemas relacionados con aguas residuales, filtraciones y disposición de residuos, con riesgos para la salud y el ambiente. Señala que desde el año 2022 ha presentado diversas gestiones ante la Municipalidad de Alajuelita solicitando la intervención municipal, la paralización y clausura de las obras, su eventual demolición y el cierre de ventanas que tienen vista hacia su propiedad. No obstante, acusa que sus gestiones no han sido respondidas en forma definitiva y que tampoco se han adoptado medidas respecto de la denuncia, por lo que la situación persiste.

Ahora bien, a pesar de que es cierto que las autoridades de la Municipalidad de Alajuelita, dentro del ámbito de sus competencias, han realizado algunas actuaciones dirigidas a atender la situación denunciada y emitieron resoluciones ordenando la suspensión y posterior demolición de las estructuras, no consta que ésta haya sido notificada a la parte amparada, ni tampoco consta que finalmente se haya ejecutado la orden de demoler las construcciones ilegales, pese a que las denuncias se remontan al 2022. Al no tener por acreditado que la recurrente tenga conocimiento del resultado de la gestión planteada ni las fechas en las que finalmente se demolerán las construcciones ilegales, se estima lesionado su derecho a una justicia pronta y cumplida. Por lo anterior, lo procedente es declarar con lugar el recurso. (…)”

Document not found. Documento no encontrado.

Implementing decreesDecretos que afectan

    TopicsTemas

      Concept anchorsAnclajes conceptuales

        Spanish key termsTérminos clave en español

        News & Updates Noticias y Actualizaciones

        All articles → Todos los artículos →

        Weekly Dispatch Boletín Semanal

        Field reporting and policy analysis from Costa Rica's forests. Reportajes y análisis de política desde los bosques de Costa Rica.

        ✓ Subscribed. ✓ Suscrito.

        One email per week. No spam. Unsubscribe in one click. Un correo por semana. Sin spam. Cancela en un clic.

        Or WhatsApp channelO canal de WhatsApp →
        Coalición Floresta © 2026 · All rights reserved © 2026 · Todos los derechos reservados

        Stay Informed Mantente Informado

        Conservation news and action alerts, straight from the field Noticias de conservación y alertas de acción, directo desde el campo

        Email Updates Actualizaciones por Correo

        Weekly updates, no spam Actualizaciones semanales, sin spam

        Successfully subscribed! ¡Suscripción exitosa!

        WhatsApp Channel Canal de WhatsApp

        Join to get instant updates on your phone Únete para recibir actualizaciones instantáneas en tu teléfono

        Join Channel Unirse al Canal
        Coalición Floresta Coalición Floresta © 2026 Coalición Floresta. All rights reserved. © 2026 Coalición Floresta. Todos los derechos reservados.
        🙏